Merancas Classroom Building
Weekly Update June 07, 2019
Merancas Campus
Meetings & Milestones
• This Week:
• Poured Area C Slab on Grade
• Area C Forms Stripped
• Installed Crane Road
• Backfilled Plan West Area
• Steel Trade Mobilization
• Subcontractor Meeting
• 06/04/19 at 10:00AM
• OACG Meeting
• 06/04/19 at 1:30PM
Meetings & Milestones
• Next Week:
• Begin Sequence 1 Steel Erection
• Begin Sequence 2 Steel Erection
• Begin Sequence 3 Steel Erection
• Subcontractor Meeting
• 06/11/19 at 10:00AM
• State Construction Meeting
• 06/11/19 at 1:30PM
Progress Photos
Placed Area C Slab
on Grade
Progress Photos
Placed Area C Slab
on Grade
Progress Photos
Saw Cut Area C
Slab on Grade
Progress Photos
Stripped Area C Slab
on Grade Forms
Progress Photos
Stripped Area C Slab
on Grade Forms
Progress Photos
Area C Slab on
Grade Wet Cure
Progress Photos
Staged Sequence 1
Steel Columns
Progress Photos
Staged Sequence 1
Steel Beams
Progress Photos
Prepared Crane for
Steel Erection
Progress Photos
Prepared Crane for
Steel Erection
Conclusion of Weekly Update 06/07/2019