2011 annual audit report for iloilo city

37
1 PART II DETAILED FINDINGS AND RECOMMENDATIONS Financial and Compliance Audit 1. Property, Plant and Equipment of P820,848,827.34 is disclosed in subsidiary ledgers as unreconciled due to the absence of supporting PPE records, thus 35% of the total PPE of P2,339,113,086.34 is of doubtful accuracy and existence. This is a reiteration of our audit finding embodied in the Annual Audit Reports for CYs 2008, 2009 and 2010. The financial records for Property, Plant and Equipment (PPE) as of December 31, 2011 totaled P2,339,113,086.34, broken down by funds as presented below (Please see Annex III.a for the detailed breakdown) : Fund Total PPE Unreconciled % Unreconciled to: PPE Total Per Fund General P1,797,722,380.88 649,616,106.94 27.78 36.13 Spec. Educ 338,316,451.94 90,177,819.78 3.85 26.65 Trust Fund 203,074,253.52 81,054,900.62 3.46 39.91 - - - Total P 2,339,113,086.34 820,848,827.34 35.09 or 35% Our review of the PPE subsidiary ledgers disclosed the following: a. Of the total General Ledger balance of PPE of P2,339,113,086.34, 35.09% is disclosed in their subsidiary ledgers as unreconciled with 27.77% from the General Fund, 3.85% from the Special Education Fund and 3.40% from the Trust Fund. b. Of this total General Ledger balance, the percentage of unreconciled per fund is 36.13%, 26.65%, and 39.91% of the general, special education and trust fund, respectively. As to PPE classification 31.96% pertains to Land, 85.08% to Land Improvements, 76.62% to Office Buildings, 39.70% to School Buildings, 74.69% to Furniture & Fixtures, 49.20% to Other Machineries and Equipment and 48.79% to Technical and Scientific Equipment.

Upload: manuel-mejorada

Post on 27-Oct-2014

3.033 views

Category:

Documents


0 download

DESCRIPTION

This document exposes how Jed Patrick E. Mabilog overpriced the items of work for the New Iloilo City Hall building project.

TRANSCRIPT

Page 1: 2011 Annual Audit Report for Iloilo City

1

PART II – DETAILED FINDINGS AND RECOMMENDATIONS

Financial and Compliance Audit

1. Property, Plant and Equipment of P820,848,827.34 is disclosed in subsidiary

ledgers as unreconciled due to the absence of supporting PPE records, thus

35% of the total PPE of P2,339,113,086.34 is of doubtful accuracy and

existence.

This is a reiteration of our audit finding embodied in the Annual Audit

Reports for CYs 2008, 2009 and 2010.

The financial records for Property, Plant and Equipment (PPE) as of

December 31, 2011 totaled P2,339,113,086.34, broken down by funds as

presented below (Please see Annex III.a for the detailed breakdown) :

Fund Total PPE Unreconciled % Unreconciled to:

PPE Total Per Fund

General P1,797,722,380.88 649,616,106.94 27.78 36.13

Spec. Educ 338,316,451.94 90,177,819.78 3.85 26.65

Trust Fund 203,074,253.52 81,054,900.62 3.46 39.91

- - -

Total P 2,339,113,086.34 820,848,827.34 35.09 or 35%

Our review of the PPE subsidiary ledgers disclosed the following:

a. Of the total General Ledger balance of PPE of P2,339,113,086.34,

35.09% is disclosed in their subsidiary ledgers as unreconciled with

27.77% from the General Fund, 3.85% from the Special Education

Fund and 3.40% from the Trust Fund.

b. Of this total General Ledger balance, the percentage of

unreconciled per fund is 36.13%, 26.65%, and 39.91% of the

general, special education and trust fund, respectively. As to PPE

classification 31.96% pertains to Land, 85.08% to Land

Improvements, 76.62% to Office Buildings, 39.70% to School

Buildings, 74.69% to Furniture & Fixtures, 49.20% to Other

Machineries and Equipment and 48.79% to Technical and Scientific

Equipment.

Page 2: 2011 Annual Audit Report for Iloilo City

2

c. Construction in Progress – Flood Controls under the General Fund

indicated an abnormal balance (P667,761.54). PPE, being an asset

account, normally should have a positive debit balance.

The unreconciled PPE, represented account balances without identified

supporting records, was determined after the City computerized its accounting

system using the electronic New Government Accounting System (e NGAS) in

July 2006.

This year’s unreconciled balance of PPE of P820,848,827.34 decreased

by P126,516.49 compared to last year’s balance of P820,975,343.83.

The problem of unreconciled balances was brought about by inadequacy

of property records and the non-reconciliation with accounting records.

We appreciate the efforts of the GSO in the conduct of physical

inventory. While we consider this as an initial step to address the problem,

documentation and maintenance of complete property records should be equally

given importance to lessen the unreconciled difference.

Recommendation

We recommend that the General Services Office complete and enhance

their property records and coordinate with the Accounting Office in reducing

if not totally eliminating the unreconciled difference between their records.

2. The contract for the Supplemental Works on the Construction of the

Updated Plans of the New Iloilo City Hall Building amounting to

P224,171,752.59 is wanting of essential information necessary for its proper

review and evaluation, thus resulting in the delay of auditorial review of

the contract.

We have reviewed Supplemental Agreement No. 1 Re: Construction of

the Updated Plans of the New Iloilo City Hall in the amount of P224,171,752.59,

as itemized below and observed the following:

Items proposed in the Supplemental

Contract

Amount Remarks

(1) Ground Floor:

Relocate City Health, Library and Office of

6,544,698.87

Page 3: 2011 Annual Audit Report for Iloilo City

3

Senior Citizen to Second Floor

Reserve the area as bank space

Second Floor:

Space for ramp area will be

Converted to City Health, Library and

OSCA Offices

Additional billeting room and shower room

at Crisis Management Division

Electrical works

Sanitary Works

Mechanical Works

(2) Third Floor:

Provide toilet and future areas to the

occupants

Provide space for connecting pedestrian

bridge way from parking building

Architectural Works

Sanitary Works

4,087,613.17

(3) Provide additional fire exit stairs from the

ground floor to third floor

1,398,911.49

(4) Use modular system furniture with seating

system instead of plywood low partition

Low partition and worktop

38,184,003.72

(5) Install power cables, distribution

transformers and generator set to

accommodate additional load

-power cables

-distribution transformers

-generator set

20,979,607.55

(6) Provide pump, motors and pressure tanks

for water distribution system

9,664,347.00

(7) Provide additional passenger elevator, 2

new units and upgrade 2 units

13,814,077.33

(8) Install inverter type air conditioning system

(11,400sqm.)

- Inverter units of air conditioning

- Centralized air con monitoring

system

55,945,324.54

(9) Provide space for cafeteria with counter 15,597,376.01

Page 4: 2011 Annual Audit Report for Iloilo City

4

and seating system

- Provide additional areas for

executive use.

- Complete with folding wall partition

at the roof deck

(10) Provide roll-up curtain blinds for all

windows

11,156,861.62

(11) Use of homogenous ceramic tiles for all

executive offices instead of vinyl tiles.

Use of carpet tiles for Mayor’s Office.

19,427,113.05

(12) Sanitary/Plumbing works

-(2) waterline system- potable and non-

potable

-separate water system for potable and non-

potable

5,935,536.37

(13) Use T5 lighting fixtures instead of ordinary

fluorescent tube lights

1,988,494.74

(14) Provide vault for Legal and Mayor’s Office 197,656.25

(15) Install solar assisted air conditioning units

on the 7th

floor Mayor’s Office and

Cafeteria area

9,446,640.50

(16) Provide drainage outfall from STP to river 2,891,940.29

(17) Provide insulation on all gypsum dry wall 618,017.40

(18) Other electrical works 5,867,500.54

(19) Additional partitions at the 7th

floor 426,032.16

Total Amount 224,171,752.60

1. The Contract - Supplemental Agreement No. 1 covering the construction of

the Updated Plans of the New Iloilo City Hall Building did not mention the

mode of procurement that was opted to by the Iloilo City Government.

2. No document was submitted to show that a public bidding was conducted on

the supplemental works, considering the materiality of the project cost,

neither was there a BAC Resolution had any of the alternative modes of

procurement was resorted to by the City Government.

3. There was no proof that the Notice of Award for the Supplemental Works was

posted in the PHILGEPS website.

Page 5: 2011 Annual Audit Report for Iloilo City

5

4. The provision on the payment to the same contractor of the 15%

mobilization expenses for the supplemental works was contrary to COA

Cir. 82-177 dated March 04, 1982, since mobilization had already been paid

to the same contractor. The stated Circular provides that the advance

payment covers the cost of mobilizing equipment to the job site. Considering

that this is a supplemental agreement and the scope of works do not require

heavy equipment, the payment of the additional 15% for mobilization is no

longer necessary.

5. The submission of the subject Contract to this Office was not compliant to

COA Cir. 2009-001 dated February 12, 2009. Audited agencies should

furnish the auditor with copies of perfected contracts within 5 working days

upon approval together with the supporting documents for review. While the

contract was perfected on July 22,2011, the same was submitted to COA

only on August 22,2011.

The noted observations were brought to the attention of LGU

management on October 05, 2011 thru a Memorandum dated October 03,

2011. However , no reply or management comment was received. We have issued

Audit Observation Memorandum (AOM) No. 11-010 dated December 12, 2011

on this audit finding, however no management comment was advanced in

this regard.

Recommendation

We recommend that the LGU management cause the submission of the

necessary information/ documents to facilitate the auditorial review and

evaluation of the contract covering the Supplemental Works on the

Construction of the Updated Plans of the New Iloilo City Hall Building so that the

necessary audit action can be rendered on time.

3. Completed infrastructure projects totaling to P204,546,952.04 had no

warranty security against Structural Defects and Failures after the one (1)

year defects liability period as stipulated in the conditions of the contract

contrary to Sec. 62.2.3.3 of the Revised Implementing Rules and Regulations

of Republic Act No. 9184.

We have observed that the LGU did not impose warranty security

against Structural Defects and Failures to contractors of completed infrastructure

projects totaling P204,546,952.04, after the one (1) year defects liability period as

stipulated in the conditions of the contract contrary to Sec. 62.2.3.3 of the Revised

Page 6: 2011 Annual Audit Report for Iloilo City

6

Implementing Rules and Regulations of Republic Act No. 9184, thus

responsibilities of the contractors during the applicable warranty periods are not

guaranteed.

Sec. 62.2.3.3 of the Revised IRR of R.A. No. 9184 provides:

“To guarantee that the contractor shall perform his

responsibilities as prescribed in Sec. 62.2.3.1 (a) of this IRR, it

shall be required to post a warranty security in accordance with

the following schedule:

Form of Warranty Security

Amount of Warranty Security

(Equal to Percentage of the

Total Contract Price)

a) Cash or Letter of Credit issued by

a Universal or Commercial Bank:

Provided, however, that the LC

shall be confirmed or

authenticated by a Universal or

Commercial Bank, if issued by a

foreign bank.

Five percent (5%)

b) Bank guarantee confirmed by a

Universal or Commercial Bank

Ten percent (10%)

c) Surety bond callable upon demand

issued by GSIS or a surety or

insurance company duly certified

by the Insurance commission as

authorized to issue such security

Thirty percent (30%)

For biddings conducted by LGUs, the contractor may also submit

warranty securities in the form of bank guarantee or letter of credit

from other banks certified by the BSP as authorized to issue such

financial instrument.”

Sec. 62.2.3.1(a) reads as follows:

“The following shall be held responsible for Structural Defects”,

i.e., major faults/flaws/deficiencies in one or more key structural

elements of the project which may lead to structural failure of the

completed elements or structure, or “Structural Failures”, i.e.,

Page 7: 2011 Annual Audit Report for Iloilo City

7

where one or more key structural elements in an infrastructure

facility fails or collapses, thereby rendering the facility or part

thereof incapable of withstanding the design loads, and/or

endangering the safety of the users or the general public:

a) Contractor – Where Structural Defects/Failures arise due to faults

attributable to improper construction, use of inferior

quality/substandard materials, an any violation of the contract

plans and specifications, the contractor shall be held liable;”

Infrastructure projects under the General Fund, Special Education Fund

and Trust Fund totaling P204,546,952.04 were reported by the LGU as completed

and paid as of December 31, 2010 (Annex III.b). However, the LGU had not

finally accepted the projects in 2011 after the defects liability period of one (1)

year from project completion in 2010. The projects should have been finally

accepted already provided there were no repair works to be undertaken thereon so

that the stipulated warranty in the conditions of the contract against structural

defects and failures as provided under Sec. 62.2.3.3 of the Revised IRR of R.A.

No. 9184 could be imposed to the contractors starting from the date of final

acceptance. The contractors should post warranty securities for two (2), five (5) or

fifteen (15) years from final acceptance depending on the type of the projects,

except those occasioned by force majeure and those caused by other parties.

Had the projects been finally accepted, the following warranty securities

should have been required to be posted by the contractors in 2011:

Form of Warranty Security Amount

a) In case of cash or Letter of Credit issued by a

Universal or Commercial Bank: Provided,

however, that the LC shall be confirmed or

authenticated by a Universal or Commercial

Bank, if issued by a foreign bank.

P10,227,347.62

b) In case of bank guarantee confirmed by a

Universal or Commercial Bank

P20,454,695.20

c) In case of Surety bond callable upon demand

issued by GSIS or a surety or insurance

company duly certified by the Insurance

commission as authorized to issue such

security

P61,364,085.61

Page 8: 2011 Annual Audit Report for Iloilo City

8

Since above mentioned warranty securities were not posted by the

contractors, their responsibilities during the applicable warranty periods are not

guaranteed. They should be held liable for structural defects and failures which

may arise due to faults attributable to improper construction, use of inferior

quality/substandard materials, and any violation of the contract plans and

specifications.

An Audit Observation Memorandum No. 12-002 dated March 7, 2012

was issued in order to bring the matter to the attention of the City of Iloilo. In

response, the OIC City Engineer agreed with the COA finding and showed

willingness to adhere with the imposition of such in notable projects such as the

New Iloilo City Hall Building and the like. However, projects costing Two

Million and below were somehow given consideration regarding the imposition

of warranty security so that the City Government would be able to eliminate any

deterrent factors in the expeditious delivery of public services and benefits to the

people. The OIC City Engineer also assured the COA that they are closely

monitoring the implementation of the programs of the City Government to be able

to give quality and excellent projects to its constituents.

Recommendation

We recommend that the applicable warranty security against structural

defects and failures be imposed from the contractors after final acceptance of the

infrastructure projects. The types of the projects should be classified by the Office

of the City Engineer as permanent structures, semi-permanent structures or other

structures in order to determine the applicable warranty period of fifteen (15)

years, five (5) years or two (2) years, respectively. The Office of the City

Accountant should ensure that the contractors post the warranty security covering

the full amount in the first year and renew the same every year thereafter, subject

to reduction every year by the amount of depreciation on a straight line basis. The

warranty security should be returned only after the lapse of the applicable

warranty period.

The City Mayor should create a committee to conduct inspection of the

infrastructure projects after the 1 year defects liability period. In the event that any

of the infrastructure projects will be damaged due to faults attributable to the

contractors, they should be obliged to undertake the necessary repair works at

their own expense before they are issued Certificates of Acceptance by the LGU.

Page 9: 2011 Annual Audit Report for Iloilo City

9

The Bids and Awards Committee should require contractors to support

the Statement of Completed Government and Private Contracts with Certificates

of Acceptance, if applicable.

4. As of December 31, 2011, audit disallowances summed up to P60,715,912.27

of which P495,497.75 have already been refunded while P258,134.57 of the

total audit suspensions of P939,054.77, have been settled.

The Auditor’s responsibility in the issuance of the Notices of

Suspensions, Disallowances & Charges is in line with the Commission’s

constitutional mandate under the Philippine Constitution which is to examine,

audit and settle all accounts pertaining to the revenues and receipts of and the

expenditures and uses of funds and property, owned or held in trust by, or

pertaining to, the Government, or any of its subdivisions, agencies or

instrumentalities, including government-owned and controlled corporations.

Total disallowances and suspensions issued as a result of post audit on

the accounts of the City Government totaled P60,715,912.27 and P939,054.77,

respectively.(Annex III.c)

Of the total disallowances, P59,541,716.35 pertain to CY 2010

transactions; P384,041.50 for CY 2009; P38,885.46 for CY 2008; P26,968.96

for CY 2007, and the rest date back prior to CY 2005. The disallowances issued

for CY 2010 are still under appeal and no Notice of Finality of Decision had been

issued hence the same are not recorded in the agency books as Receivables-

Disallowances/Charges.

The disallowances of P59,541,716.35 for CY 2010 consist of Personnel

Enhancement Incentive of P46,424,328.24 granted to officials and employees of

the City of Iloilo, Financial Assistance of P5,270,000 given to different barangays

of Iloilo City and Cash Allowance of P7,847,388.11 of National Government

officials and employees assigned to the City of Iloilo.

Of the total suspensions of P939,054.77, P258,134.57 has already been

settled, leaving a balance of P680,920.20.

Recommendation

We recommend that the LGU Management faithfully adhere to the

prescribed government laws rules and regulations, ensure economy, efficiency

and effectiveness in their operations and require adequate documentation of its

Page 10: 2011 Annual Audit Report for Iloilo City

10

financial transactions to avoid disallowances and suspensions in the post audit of

their accounts by the COA Auditor.

5. The City of Iloilo paid Cash allowances to officials and personnel of DILG,

DepEd-Division of Iloilo City, Internal Affairs Service and City and Regional

Prosecutor’s Office totaling to P3,406,723.66 out of the unexpended balance

of the FY 2010 Calamity Fund contrary to item b.4 of the IRR of R.A. No.

8185, thus depriving the constituents of the use of the fund in case of

calamity.

We have audited the FY 2010 4th

Quarter City Cash Allowance released

by the City of Iloilo on January, 2011 to officials and personnel of DILG, DepEd-

Division of Iloilo City, Internal Affairs Service and City and Regional

Prosecutor’s Offices totaling P3,406,723.66, covered by the following reference

documents and particulars:

Check No.

Date

Amount of

Check

Amount

Disallowed

--------------- ---------- ------------------ -------------------

0034260557 1/3/11 P 3,600.00 P 3,600.00

0034260569 1/4/11 3,542,874.46 2,668,548.14

0034260579 1/6/11 1,009,125.00 280,606.42

0034260588 1/7/11 1,174,162.37 411,832.24

0034260604 1/10/11 806,670.82 22,936.86

0034260620 1/12/11 452,096.48 3,600.00

0034260654 1/17/11 126,187.78 3,600.00

0034260720 1/27/11 721,847.11 12,000.00

Total P3,406,723.66

==========

The LGU provided funds for the City Cash Allowance of national

government officials and personnel concerned from the unexpended balance of

the FY 2010 Calamity Fund through Appropriations Ordinance No. 2010-108

(Supplemental Budget No. 8) which was enacted by the Honorable Members of

the Sangguniang Panlungsod on December 20, 2010 and later approved by the

Honorable City Mayor on December 21, 2010 (Annex III.d). In the review dated

January 10, 2011 (Annex III.e) of such budget, the Department of Budget and

Management (DBM) Region VI, Iloilo City, declared the expenditure items in the

appropriations ordinance, including the City Cash Allowance, inoperative

effective immediately in view of item b.4 of the IRR of R.A. No. 8185 which

states:

Page 11: 2011 Annual Audit Report for Iloilo City

11

“Any unexpended balance of the Calamity Fund at the end of

the Current Year shall revert to the Unappropriated Surplus for

re-appropriation during the succeeding budget year.”

Under Section 353 of the Local Government Code of 1991, the official

fiscal year of local government units shall be the period beginning with the first

(1st) day of January and ending with the thirty-first (31

st) day of December of the

same year.

The total amount of P3,406,723.66 was disallowed in audit because the

use of FY 2010 Calamity Fund for the City Cash Allowance was contrary to item

b.4 of the IRR of R.A. No. 8185, as pointed out by the DBM Region VI in the

aforementioned budget review. We have issued ND No. 12-001-100-(11) dated

February 1, 2012, in this regard.

Recommendation

We recommend that the Iloilo City Government observe strictly the

laws rules and regulations on the use of calamity fund to ensure that the

desired services and benefits can be delivered to its constituents in times

of calamities.

We also recommend that the Local Chief Executive direct the persons

liable to settle the said disallowance.

6. The rate of project implementation of 48.60% funded from the 20%

Development Fund could have been increased to a higher level had there

been proper coordination among the project beneficiaries and the officials

involved in planning, execution and monitoring.

We have evaluated the status of implementation of the projects

funded out of the CY 2011 - 20% Development Fund and noted the following

observation:

The 2011 Annual Development Plan and Investment Program (ADPIP)

embodies the list of sectoral programs, projects and activities with their

corresponding budgets designed to help address Iloilo City’s development needs

and concerns for CY 2011. These developmental concerns are among the

priorities of the LGU in pursuing its vision of becoming a Premier City by

2015.

Page 12: 2011 Annual Audit Report for Iloilo City

12

Local plans and programs were classified into three categories,

namely: General Public Services, Social Services and Economic Services

with a corresponding share of the budget of 12.76%, 63.37% and 23.87%,

respectively.

As the City’s concern for development was impressively presented

in the ADPIP, actual project implementation did not speak so well of the

desired output. The percentage of project implementation was only 48.60%

by the end of 2011. (Annex III.f) For CY 2011, the agency appropriated a

sum of P 122,311,761.00 for development projects to be funded from the 20%

Development Fund. Evaluation of project implementation showed the relative

accomplishments per category, viz: General Public Services - 9.87%; Social

Services 51.21% and Economic Services 62.36%. At the end of the year

only P59,438,451.00 of the appropriated amount of P122,311,761.00 or

48.60% was expended for implemented projects. We also noted that

numerous projects from the CY 2010 Development Fund were only

implemented in CY 2011.

While budget consideration is not a deterrent factor in project

implementation, the desired services/benefits could have been delivered to

the City’s constituents on time and to the optimum level had there been

proper coordination among the project beneficiaries and the officials

involved in planning, execution and monitoring of such projects. Moreover,

the rate of project implementation could have been increased had monitoring

mechanisms been put in place in gauging the efficiency of implementation in

real time so that whatever deficiencies/ shortfall which may have been noted

along the way, the same could have been rectified within the time frame of

implementation. It is thru feed-back that inputs for efficiency and further

improvement are drawn.

We issued AOM No. 2012-003 dated March 8, 2012 for this finding. In

response, the City Budget Officer replied that the delay in implementation was

due to a change in administration during the first semester of CY 2010 that

necessitated the observance of a transition period so that the new administration

may appraise the existing programs and projects of the City, it being subject to the

approval and clearance of the City Mayor. In addition, the ADPIP is being

prepared by the City Development Council with the City Engineer’s Office as the

primary implementing office. Monitoring of implementation thereof rests with

them. Meanwhile, the City Budget Office releases allotments based on request of

the end-user and approved by the Local Chief Executive. Nevertheless, the City

Budget Office gave an assurance to take note of the audit recommendations and

Page 13: 2011 Annual Audit Report for Iloilo City

13

shall undertake to give sound advice to the concerned offices/departments with

regard to these matters, particularly the Local Chief Executive.

The OIC City Engineer also justified that numerous projects from CY

2010 Development Fund were only implemented in 2011 due to the domino

effect of sixty (60) days (before and after) banning period of the Commission on

Election on construction projects in line with the 2010 National Election and

forty five (45) days (before and after) on Local Election. It took the City until

September 2011 to start implementing the 2011 projects. Nevertheless, the OIC

City Engineer made assurance that the projects for CY 2012 will be implemented

as scheduled.

Recommendation

We recommend that the rate of implementation of projects funded

from the 20% Development be enhanced so that the desired services and

benefits which go with these projects be delivered to the constituents of the

City without unnecessary delay.

We further recommend that regular monitoring mechanisms be

employed in assessing the rate of progress of project implementation and

that a closer coordination among the officials involved in planning,

execution and monitoring be enhanced to achieve the desired level of

efficiency.

7. Due to the absence of proper monitoring controls, payments for garbage

collection and transport services totaling to P46,708,593.75 were not

supported with official trip tickets contrary to the contract’s term of

reference; thus, the propriety of disbursements were not ensured.

We have audited the payments to JS Layson & Co., Inc. for garbage

collection and transport services totaling P46,708,593.75 for the period December

1, 2010 to March 31, 2011 and found out that official trip tickets were not made to

support the claims for payment contrary to the contract’s terms of reference, thus

proper monitoring controls were not put in place to ensure the propriety of

disbursements.

The terms of reference of the Contract for Garbage Collection and

Transport Services dated March 24, 2010 stipulates:

Page 14: 2011 Annual Audit Report for Iloilo City

14

“xxx, the Office of Public Services shall provide official trip

ticket forms to be filled up by driver/collection crew, signed by the

Contractor’s foreman and approved by the LGU designated

inspector and by the LGU Officer in charge of garbage collection.

Xxx

The Office of Public Services shall keep all records of collection

trips and complete the same for the required monthly

accomplishment report, which shall form part of the documents for

its billing purposes. ”

Details of billings and corresponding payments are as follows:

Date Check No. Gross Taxes Net Period Days Trips Rate

1/6/11 0034260582 P4,231,500.00 P264,468.75 P3,967,031.25 12/1-31/10

31 78 P1,750

2/04/11 0034260784 4,231,500.00 264,468.75 3,967,031.25 1/1-31/11 31 78 1,750

3/03/11 0034261034 3,822,000.00 238,875.00 3,583,125.00 2/1-28/11 28 78 1,750 4/13/11 0035906335 4,231,500.00 264,468.75 3,967,031.25 3/1-31/11 31 78 1,750

5/10/11 0035906567 4,095,000.00 255,937.50 3,839,062.50 4/1-30/11 30 78 1,750 6/08/11 0035906877 4,231,500.00 264,468.75 3,967,031.25 5/1-31/11 31 78 1,750

7/07/11 0035907149 4,095,000.00 255,937.50 3,839,062.50 6/1-30/11 30 78 1,750

8/04/11 0035907466 4,231,500.00 264,468.75 3,967,031.25 7/1-31/11 31 78 1750 9/05/11 0035907715 4,231,500.00 264,468.75 3,967,031.25 8/1-31/11 31 78 1,750

10/7/11 0037605667 4,095,000.00 255,937.50 3,839,062.50 9/1-30/11 30 78 1,750

11/8/11 0037605882 4,231,500.00 264,468.75 3,967,031.25 10/1-31/11

31 78 1,750

12/5/11 0037606179 4,095,000.00 255,937.50 3,839,062.50 11/1-

30/11

30 78 1,750

------------------ ----------------- -------------------

Total P49,822,500.00 P3,113,906.25 P46,708,593.75

------------------ ----------------- -------------------

The use of aforementioned official trip tickets was not observed because

the Office of the City General Services has not yet come up with and provided

forms to be accomplished by contractor’s personnel for approval by the

designated LGU personnel.

The contractor consistently billed the LGU for 78 trips per day at P1,750

per trip based on the contract’s scope of work. The apparent disregard of the

pertinent terms of reference of the contract on the use of official trip tickets shows

that monitoring controls are not in place to ensure that the desired services have

been rendered and payments of claims are sufficiently supported with complete

documentation.

We have issued AOM No. 11-009 dated December 7, 2011 on this

observation. In reply to the audit memorandum, the LGU management claimed

Page 15: 2011 Annual Audit Report for Iloilo City

15

that they have been consistently monitoring the daily number of trips rendered by

the contractor through their Garbage Monitoring report at the Calajunan Disposal

Facility. The reports are part of the attachments in every claim/payment to the

service contractor. In compliance to the auditor’s recommendation, the LGU

management would be implementing the use of monitoring reports/official trip

tickets at the dispatch area in every district after giving due information to the

personnel involved and the service contractor as soon as possible.

Recommendation

We recommend that the Office of the City General Services (GSO)

implement the use of official trip tickets to facilitate the monitoring of daily

number of trips rendered by the contractor and to verify the accuracy of its billing

statements. The concerned employees of the GSO should be made aware of their

responsibilities as specified in the contract on garbage collection and transport

services to ensure that the LGU derives the desired services and value for money

being expended for the purpose.

We commend management for implementing this recommendation

effective January 2012.

8. In the procurement of materials for the improvement /installation of

street lighting of the different barangays of Iloilo City and instructional

materials charged against Special Education Fund aggregating to

P12,921,529.00, the Agency failed to adhere to Rule II, Section7 of the

Revised Implementing Rules and Regulations; thus, causing piecemeal

purchases and splitting of Requisitions and Purchase Orders contrary to

COA Circular 76-41 dated July 30, 1976.

Rule II, Section 7 of the Revised Implementing Rules and Regulations

of Republic Act 9184 sets forth the initial steps of the procurement process

wherein the end-users are required to prepare their respective Program

Project Management Plan (PPMP) for consolidation into the proposed Annual

Procurement Plan (APP) of the Agency. This APP serves as a vital tool to

the agency in the management and phasing of their procurement needs.

Commission on Audit Circular No. 76-41 dated July 30, 1976 deals on

the prohibition against splitting of requisitions, purchase orders, vouchers and

others. Within the sphere of Government procurement, splitting is associated

with requisitions, purchase orders, deliveries and payments in the form of:

Page 16: 2011 Annual Audit Report for Iloilo City

16

a. Non-consolidation of requisitions for one or more items needed

at or about the same time by the requisitioner (splitting of

requisitions);

b. Issuance of two or more purchase orders based on two or more

requisitions for the same or at about the same time by different

requisitioners (splitting of P.O.); and

c. Making two or more payments for one or more items involving

one purchase order (splitting of payments).

In the review of Purchase Orders, we noted numerous deviations

from the given criteria summarized in the tables presented below:

Table A. Procurement of Electrical Supplies from Topmost Dev. Corp.

P.O. No. Date Supplier Amount Items Purchased 11-08-0540 08/24/2011 Topmost Dev. Corp. 199,243.00

Electrical Supplies

11-08-0561 08/10/2011 Topmost Dev. Corp. 49,783.00 Electrical Supplies

11-08-0562 08/10/2011 Topmost Dev. Corp. 49,799.00 Electrical Supplies

11-08-0563 08/10/2011 Topmost Dev. Corp. 50,704.00

Electrical Supplies

11-08-0564 08/10/2011 Topmost Dev. Corp. 50,717.00 Electrical Supplies

11-04-0193 04/20/2011 Topmost Dev. Corp. 749,514.00 Electrical Supplies

11-04-0244 04/27/2011 Topmost Dev. Corp. 74,076.00 Electrical Supplies

Total 1,223,836.00

Page 17: 2011 Annual Audit Report for Iloilo City

17

Table B. Procurement of Instructional Materials from St. Augustine Publishing

The given data show that similar goods needed at about the same

time are procured from the same supplier in several transactions instead of

consolidating the same in one single procurement

Evidently, (2) two among the (3) three conditions of splitting are

manifested in these transactions. The circular further states that in whatever

form splitting has been resorted to, the idea is to do away with and circumvent

control measures promulgated by the government. As evidently noted in the given

transactions, the pertinent provisions of R.A. 9184 were not observed at the very

onset of the procurement process. The needs of the different departments as

reflected in their respective Project Procurement Management Plan (PPMP)

were not consolidated and contained in an Annual Procurement Plan.

Procurement needs are still being catered on a per purchase request basis

making the process more tedious and inefficient.

P.O. No. Date Supplier Amount Items

Purchased

11-05-0321 06/28/2011 St. Augustine

Publications

999,845.00

Textbooks

11-05-0323 06/28/2011 St. Augustine Publications

499,895.00 Textbooks

11-05-0328 05/25/2011 St. Augustine

Publications

499,920.00 Instructional

Materials

11-08-0536 09/02/2011 St. Augustine

Publications

499,848.00 Various textbooks

11-08-0538 09/02/2011 St. Augustine

Publications

699,975.00 Various textbooks

11-08-0537 09/02/2011 Various textbooks 699,865.00 Various textbooks

11090633 11/03/2011 St. Augustine

Publications

799,784.00 Instructional

Materials

11100696 11/03/2011 St. Augustine

Publications

1,499,685.00 Instructional

Materials

11100698 11/03/2011 St. Augustine

Publications

1,499,370.00 Instructional

Materials

11100700 11/03/2011 St. Augustine

Publications

1,999,656.00 Instructional

Materials

11-10-0701

11/03/2011

St. Augustine

Publications

999,880.00 Instructional

Materials

11100702 11/03/2011 St. Augustine

Publications

499,985.00 NAT Reviewer

11090664 11/03/2011 St. Augustine

Publications

499,985.00 NAT Reviewer

Total P11,697,693.00

Page 18: 2011 Annual Audit Report for Iloilo City

18

The existing practice had resulted in: (a) increased consumption of

office supplies as the same set of documents are being attached to several

vouchers covering the purchase of similar goods from the same supplier at

about the same time; (b) added man-hours in processing the same claims

from the same suppliers being split into several P.O.s and disbursement

vouchers and (c) non-availment of volume discounts for bulk purchase.

While this deficiency deals more on procedural flaws and not

intended to circumvent control measures, this could be a pre -disposing

factor to splitting which is not acceptable under procurement laws. This

finding was previously brought to the attention of management. It is sad to

note however that the same remain unaddressed.

An Audit Observation Memorandum No. 12-004 dated March 2, 2012

was issued to call on the attention of the LGU management.

Recommendation

We recommend that management consider the strict observance of

Rule II, section 7 RA 9184 and Commission on Audit Circular No. 76-41 as

well as the imposition of control measures to ensure that procurement is

effected in an efficient, economical and effective manner that is most

advantageous to the government and to prevent possible disallowances for

such violation.

9. Proper liquidations of financial assistance granted to government and non-

government organizations totaling to P11,843,500.00 were not complied with

contrary to prescribed accounting and monitoring controls, thereby resulting

in untimely verification of financial records and reports and evaluation of

project implementation.

We have audited the financial assistance granted to government and

non-government organizations totaling P11,843,500.00, and observed that proper

liquidation of funds were not complied with contrary to prescribed accounting and

monitoring controls, thereby resulting in untimely verification of financial records

and reports and evaluation of project implementation.

1. Iloilo Dinagyang Foundation, Inc. (IDFI) - P7,673,500.00

The LGU released the following financial assistance totaling

P7,673,500.00 to the IDFI:

Page 19: 2011 Annual Audit Report for Iloilo City

19

Date

Check No.

Purpose

Amount

Submission of

liquidation

No. of days

Liquidated

No. of

days Delayed

--------- --------------- ---------------------------------- ----------------- ----------------- -------------- ------------

1/7/11 003687391 2011 Iloilo Dinagyang Festival,

January 14-23, 2011

P1,000,000.00 11/8/11 289 229

1/14/11 0034260646 2011 Iloilo Dinagyang

Festival,

January 14-23, 2011

4,313,500.00 11/8/11 289 229

1/18/11 0034260664 Iloilo-Panay Badminton

Club,

1st Mayor Jed Patrick E. Mabilog Dinagyang

Badminton Cup,

January 20-21, 2011

160,000.00 11/14/11 297 237

1/18/11 0034260663 Panay Anglers Association Inc.,

Mayor’s Cup Dinagyang

Tournament, January 22-23, 2011

100,000.00 11/14/11 295 235

1/20/11 003687394 2011 Iloilo Dinagyang

Festival, January 14-23,

2011

1,000,000.00 11/8/11 289 229

1/25/11 003260708 Practical Shooting

Association, Inc.,

1st Mayor Jed Patrick E. Mabilog Dinagyang

Shooting Competition,

January 21-23, 2011

30,000.00 12/23/11- 334 274

4/15/11 0035906360 Aliwan Festival, April 14-

17, 2011

1,070,000.00 12/13/11 240 180

----------------- Total P7,673,500.00

==========

As shown in the records, liquidation documents and reports of financial

assistance were submitted by the IDFI to the LGU after 289 to 334 days from

completion of each activity. Item 5.4 of COA Circular No. 2007-001 dated

October 25, 2007 states:

“Within sixty (60) days after completion of the project, the

NGO/PO shall submit the final Fund Utilization Report certified

by its Accountant and approved by its President/Chairman to the

GO, together with the inspection report and certificate of project

completion rendered/issued by the GO authorized representative,

list of beneficiaries with their acceptance/acknowledgment of the

project/funds/goods/services received. The validity of these

documents shall be verified by the internal auditor or equivalent

official of the GO and shall be the basis of the GO in recording

Page 20: 2011 Annual Audit Report for Iloilo City

20

the fund utilization in its books of accounts. These documents

shall support the liquidation of funds granted to the NGO/PO.”

The IDFI was delayed by 180 to 274 days in submitting the liquidation

documents and reports. As a consequence of its failure to submit the required

reports, it was precluded from receiving funds to support its promotional

marketing of the Dinagyang Festival at the Independence Day Celebrations in

New York and Washington D.C., U.S.A. last June, 2011. Despite the City

Accountant’s reminder to the Foundation to liquidate the previous financial

assistance as embodied in a letter dated October 24, 2011, the same was not

complied with before the delegation left for the U.S.

Timely submission was not facilitated because the Memorandum of

Agreement (MOA) dated October 19, 2010 entered into by and among the LGU,

IDFI and San Jose Parish Placer did not specifically stipulate the 60-day

reglementary period nor did it require liquidation of prior financial assistance

before the release of a new one. The delayed submission of utilization reports

from November to December 2011 has deterred the LGU from promptly verifying

actual expenditures before the forthcoming 2012 Iloilo Dinagyang Celebration

scheduled on January 20 to 22, 2012. To date, such utilizations are not yet

credited to the account of the IDFI and recorded in the books of the LGU because

verification has not been completed.

While we recognize that some controls are in place, there is still a need

to impose tighter controls particularly in the setting up of the terms and conditions

of the MOA and the reglementary period for liquidations so that future events

needing financial assistance will not be adversely affected.

It was also noted that the 1st Mayor Jed Patrick E. Mabilog Dinagyang

Badminton Cup of the Iloilo Badminton Club, Mayor’s Cup Dinagyang

Tournament of the Panay Anglers Association, Inc. and 1st Mayor Jed Patrick E.

Mabilog Dinagyang Shooting Competition of the Practical Shooting Association,

Inc. were not included in the 2011 Iloilo Dinagyang Festival Factsheet, Budget

and in the Schedule of Activities. However, financial assistance totaling

P290,000.00 were extended to the IDFI for such purposes for the use of the

respective sports associations. This scheme circumvented COA Circular No.

2007-001 which requires the submission of eligibility documents by the

concerned sports associations to qualify for financial assistance.

2. Brgy. Mohon – P170,000.00

Page 21: 2011 Annual Audit Report for Iloilo City

21

The LGU granted financial assistance totaling P170,000.00 to Brgy.

Mohon, Iloilo City for the Arevalo District Fireworks Contest held on January 16,

2011, to wit:

Date Check No. Amount

---------- --------------- ----------------

1/12/11 0034260625 P120,000.00

1/13/11 0034260637 50,000.00

---------------

Total P 170,00.00

=========

However, liquidation of the aforesaid financial assistance was not

required contrary to item 4.6 of COA Circular No. 94-013 dated December 13,

1994 which provides:

“Within ten (10) days after the end of each month/end of the

agreed period for the project, the IA shall submit the Report of

Checks Issued (RCI) and the Report of Disbursement (RD) to

report the utilization of funds. Only actual project expenses shall

be reported. The reports shall be approved by the Head of the

IA.”

The City Accountant explained that submission of liquidation report was

relinquished because verification of actual expenditures out of the financial

assistance was all done at the barangay level. This practice, however, did not

facilitate monitoring and recording of related actual expenditures in the books of

the LGU.

An Audit Observation Memorandum No.12-001 dated January 2, 2012

was issued to call the attention of the City Government. Consequently, the City

Accountant endorsed the said memorandum to the concerned personnel in charge

of these activities. In a letter from the President of the Iloilo Dinagyang

Foundation, Inc. dated February 8, 2012, he promised timely submission of

liquidation on subsequent activities and that they have already fully liquidated and

complied with to their best efforts the documentary requirements that COA is

requesting on the subject audit observation memorandum. A justification was also

received from the Sports Development Officer stating that the three sports

activities namely, the 1st Mayor Jed Patrick E. Mabilog Dinagyang Badminton

Cup, Mayor’s cup Dinagyang Fishing Tournament and 1st Mayor Jed Patrick E.

Page 22: 2011 Annual Audit Report for Iloilo City

22

Mabilog Shooting Competition were included in the official calendar of activities

as part of the 2011 Dinagyang Celebration. These were excluded from the 2011

Dinagyang Factsheet and budget because as agreed with the City Tourism and

IDFI, the sports division of the City Mayor’s Office will shoulder the expenses of

the different sports activities that will request inclusion in the celebration’s special

events due to lack of budget on the part of the City Tourism and IDFI.

As to delayed submission of liquidation reports, the Sports Development

Officer assured that additional controls were already made by his office to correct

the matter in the 2012 Dinagyang Celebration and that disciplinary actions will be

instilled to those who will fail to follow the guidelines on proper liquidation.

Recommendation

We recommend that the LGU consider incorporating in the MOA the

requisites in granting additional financial assistance, the liquidation terms and

required monitoring and project accomplishment reports.

We further recommend that a Memorandum of Agreement requiring

submission of a liquidation report be executed prior to the release of funds. It

should be the responsibility of the barangay to return unused balance to the LGU

upon completion of the purpose and refund audit disallowance, if any.

10. Collection of light fees from six (6) public markets for the period

December 2010 to September 2011 fall short by P6,305,496.17 or 34.14%

compared to the actual cost of electric consumption paid by Iloilo City

amounting to P18,473,638.66, indicating that the Local Economic Enterprise

has not fully attained the desired economic viability.

We have reviewed the monthly electric bills of the six (6) public markets

from December 2010 to September 2011 and observed that the collected light fees

were lesser by P6,305,496.17 compared with the actual cost of the electric

consumption paid by Iloilo City which runs counter to the principle of economic

viability of local economic enterprises.

The public markets were established as local economic enterprises under

Regulation Ordinance No. 2009-316 of the City of Iloilo. As an economic

enterprise, each public market should exist on its own funds, satisfy both the

economic and social objectives of the local government concerned and generate

income while improving the delivery of basic goods or services to the people.

Page 23: 2011 Annual Audit Report for Iloilo City

23

For the duration of the 10-month period, the public markets consumed

2,123,207 kwh of electricity costing P18,473,638.66 (Annex III.g). However, the

collection of light fees from market lessors in the same period amounted to

P12,168,142.49 only, a shortfall in collection of P6,305,496.17 or 34.13% which

had been subsidized by the funds of the Office of the Local Economic Enterprise

(LEE) coming from other sources.

The payments of light fees by market lessors were stipulated in the lease

contracts but the rate of light fees was not categorically stated therein. In the

absence of a prescribed rate, the Office of the LEE billed light fees to market

lessors based on their actual consumption at the prevailing monthly rate of PECO

per kwh. The electric consumption of the communal areas, facilities,

administrative offices of the public markets and any related overhead costs were

not considered in the billing of the light fees. In addition, the electric consumption

of the public markets included that of the legislative offices located at the Iloilo

Terminal Market. As a result, actual expenses for electricity exceeded the actual

collection for the same period.

An Audit Observation Memorandum No. 12-006 dated March 28, 2012

was issued to call the attention of the management on this deficiency. A reply

received from the City Treasurer stated that they are considering the COA

recommendations to address the issue at hand.

Recommendation

We recommend that the existing policy on the rate of the light fees being

collected at the public markets be reviewed and control measures be set to ensure

sustainability of operations. The entire funding requirements for the electric

consumption may be sourced from the collection of light fees in order that

electricity expenses would be self-liquidating. The LGU may consider imposing

fixed or variable electric charges to market lessors for the electric consumption of

communal areas, facilities, administrative offices of the public markets and any

related overhead costs in addition to their actual usage. The rate of light fees

should be specified and expressly authorized by an ordinance pursuant to Sec.

305(c) of R.A. 7160.

We further recommend that the electric consumption of the regular

offices of the LGU located at the Iloilo Terminal Market should be segregated

from the electric bill of the public markets to be paid by the General Fund in view

of the “matching principle” of accounting.

Page 24: 2011 Annual Audit Report for Iloilo City

24

11. Payments for conference and membership fees made to Regional Association

of Treasurers and Assessors in Region VI (REGATA VI), Inc. and Philippine

Association of Assessing Officers (PAAO) amounting to P84,100.00 and

P4,500.00 were inconsistent with the guidelines embodied in the Bureau of

Local Government Finance (BLGF) Regional Circular No. 01-2001 dated

January 13, 2011 and National Budget Circular (NBC) No. 442 dated

November 29, 1995.

We have audited the payment to the Regional Association of Treasurers

and Assessors in Region VI (REGATA VI), Inc. and Philippine Association of

Assessing Officers (PAAO) totaling P84,100.00 and P4,500.00, respectively, and

observed the following deficiencies/errors:

1. The payment by the LGU of conference fees totaling P75,600.00 to REGATA

VI during the Annual Performance Conference-Workshop and General

Assembly of Provincial, City, Municipal Assessors & Treasurers and Ranking

Personnel of Treasury & Assessment Offices held at Iloilo Grand Hotel, Iloilo

City on January 25 to 27, 2011 were not consistent with the Bureau of Local

Government Finance (BLGF) Regional Circular No. 01-2001 dated January

13, 2011. (Annex III.h)

While said conference was called for by BLGF Region VI, Iloilo

City through Regional Circular No. 01-2001 dated January 13, 2011, payment

of conference fees were made in favor of REGATA VI, a private organization.

The circular and the nature of its purpose implied that the Bureau, which is

tasked to supervise and coordinate the conduct of local treasury and

assessment operations of the provinces, cities and municipalities within the

region for proper implementation of laws, decrees, rules and regulations and

administrative issuances of the Department of Finance, has the responsibility

for the conduct of such conference, in which case it is deemed proper that the

payments should have been made to and receipted by BLGF Region VI.

Considering that the conference is an annual undertaking by the

BLGF Region VI, as observed, substantial amount of government funds are

being expended for the purpose without the benefit of COA audit in the

context of treating the collections as public funds.

2. Checks issued for the payment of conference fees were dated January 27,

2011 while the covering official receipts were dated January 25, 2011.

Page 25: 2011 Annual Audit Report for Iloilo City

25

3. The LGU paid REGATA VI and Association of Assessing Officers (PAAO) a

total of P13,000.00 to settle membership fees and CY 2011 annual dues of

personnel, contrary to National Budget Circular (NBC) No. 442 dated

November 29, 1995. (Annex III.h)

Department of Budget and Management NBC No. 442 dated March

29, 1995 re: Cost of Participation of Government Officials and Employees in

Conventions, Seminars, Conferences, Symposia and Similar Gatherings states:

“Membership and similar fees paid for personal or individual

membership in private organizations shall be for the account of

the member concerned and shall not be charged to government

funds. However, institutional membership fees, i.e., agency

membership may be charged to government funds.”

The payments were authorized by BLGF Region VI through the

same Regional Circular No. 01-2011 as chargeable against the appropriation

of the LGU subject to accounting and auditing requirements. However, such

authorization appeared inconsistent with NBC No. 442. The LGU could have

saved the amount for the payment of fees and dues had NBC No. 442 been

observed.

We issued AOM No. 11-008 dated November 28, 2011 on these

deficiencies. In reply, City Treasurer and the City Assessor commented:

1. The conference was authorized by BLGF, Region VI in view of the request

for authority dated January 11, 2011 by the President of REGATA VI to

conduct the same and that the letter of the REGATA VI President also

requested for the inclusion of BLGF personnel to act only as secretariat and at

the same time facilitate the circularization of a regional memorandum to

ensure more attendance of the REGATA VI members. The Bureau is

responsible only in providing technical guidance in the conduct of said

training pursuant to the Bureau’s existing mandate while the

conference/assembly itself is being run/conducted by REGATA VI in which

members’ registration fees were made to and receipted by the association.

Expenses for supplies and materials, snacks and lunch, honorarium of

lecturers and speakers and other necessary expenses were shouldered by

REGATA VI.

2. It is a common practice in the organization that Official Receipt is issued on

the first day of the conference/seminar to persons who registered. Trust and

Page 26: 2011 Annual Audit Report for Iloilo City

26

confidence is reposed by REGATA VI upon all its members and it is always

presumed that those who registered are paying participants. However, it so

happened that the processing of voucher was delayed, hence, the issuance of

check for the purpose was also delayed and was dated only January 27, 2011,

just in time before the seminar ends.

3. The City Treasurer and City Assessor are fervently requesting for a re-

consideration for the payment of membership fees and promise that the same

will not be committed again.

Recommendation

We recommend that the conference fees be paid to Bureau of Local

Government Finance Region VI.

We recommend that the LGU refrain from paying the membership fees

and annual dues of personnel concerned to REGATA VI and PAAO.

12. Non-consolidation of procurement needs and the non-observance of

procurement procedures in violation of Rule II, Section 7.3.4 of the revised

IRR of RA 9184 and Sec. 22 of the Manual on the New Government

Accounting System for Local Government Units had resulted in piece-meal

purchases of jetmatic pumps in varying prices at almost the same time

aggregating to P1,428,718.60.

In the post-audit of disbursements on procurement, particularly the

acquisition of jetmatic pumps, we noted the following observations:

1. The City paid a total of P 1,428,718.60 for the procurement of

422 units jetmatic pumps in five separate transactions,

P1,140,218.60 of which were not supported with actual

distribution lists duly signed by the respective recipients.

(Annex III.i)

2. A perusal of the pertinent documents showed that the same items

procured at about the same time were differently priced since the

pricing was closely pegged against the individual cost estimates

of each end-user. To cite a concrete example, Purchase Orders

numbered 110-60385 dated June 09, 2011 and 110-60394 dated June

22, 2011, showed a relative price difference of P1,400.00 and

Page 27: 2011 Annual Audit Report for Iloilo City

27

P1,199.80 per unit, respectively as compared to our canvassed

price of P 2,400.00 (Annex III.j). Comparative analysis between

the prices set by end-users in the Purchase Requests and the

actual purchase prices per Purchase Orders showed that the cost

estimates set by end-users were made as the bases of the

Approved Budget for the Contract.

Consequently, it follows that the higher the cost estimates, the

higher are the actual purchase prices. The absence of review

mechanisms to serve as control measures for establishing the

price reasonableness of the items procured, coupled with the

non-consolidation of quarterly procurement needs had resulted to

the aforementioned conditions.

3. A comparative evaluation of Purchase Orders Numbered 107-

0325 and 107-0365 further revealed a downward trend in pricing

from P3,398.00 in December 16, 2010 to P2,885.00 in February 07,

2011, or a drop in price of P513.00 per unit, considering that the

estimated price set by the requesting office was P2,900.00. As shown

in Annex B, the latter has the lowest price difference of P485.00

against the canvass price of P2,400.00, among the five transactions.

We analyzed the root cause of variable pricing as earlier cited in the

sample transactions and noted that the condition emanated from the different

cost estimates set by different end-users in their purchase requests which

were not subjected to review and consolidation prior to procurement. Instead,

each Purchase Request was catered on a piece-meal basis.

Section 122 of the Manual on the New Government Accounting System

for Local Government Units require that the Office of the General Services

Office (GSO) is responsible for the preparation of the Purchase Request for

supplies and materials needed for the quarter based on the approved Annual

Procurement Program (APP). This is based on the premise that the Project

Procurement Management Plans (PPMPs) of the respective end-users had

been reviewed and consolidated by the BAC Secretariat pursuant to Rule II,

Sec.7.3.4 of the revised Implementing Rules and Regulations (IRR) of Republic

Act. (RA) No. 9184.

Page 28: 2011 Annual Audit Report for Iloilo City

28

We brought this matter to the attention of management, through Audit

Observation Memorandum No. 12-007 dated March 30, 2012. No management

response was given on this finding.

Recommendation

We recommend strict compliance to Rule II, Section 7.3.4 of the

revised IRR of RA 9184 and Section 122 of the Manual on the New

Government Accounting System for Local Government Units and a valid

justification for the material unit price variances found in audit. Review

mechanisms over purchases particularly on cost estimates and actual purchase

cost should be installed so as to ensure that financial resources can be maximally

utilized.

We further recommend that a distribution list duly signed and dated

by the identified beneficiaries be submitted as one of the supporting

documents of the paid vouchers covering payments for the purchase of

jetmatic pumps.

13. The management of rentals on the use of public plazas is lodged with

the Association of Barangay Captains (ABC) which is not in accord with

City Ordinance No. 40, Series of 1972, thus depriving the City of a

potential source of income.

A perusal of City Ordinance No. 40, Series of 1972, entitled “ An

Ordinance Imposing Fees for the Use of Public Places Owned or Administered

by the City of Iloilo revealed the following observations:

1. The said Ordinance was enacted on February 24, 1972, 40 years ago

and has not been subjected to any updating;

2. The rates fixed in the ordinance is no longer suited to the current

economy;

3. The provisions of the Ordinance have not been strictly enforced,

and;

4. The City Treasure’s Office has not been collecting the rental rates

pursuant to the Ordinance.

Page 29: 2011 Annual Audit Report for Iloilo City

29

It was learned through interviews and queries that it is the

Association of Barangay Captains (ABC), a private organization registered

with the Securities and Exchange Commission (SEC) that manages the stall

rentals of public plazas including the collection, disbursement and

accounting of income derived from such rentals which are not being

subjected to audit. This policy is not provided in the existing ordinance.

While Executive Orders of the City Mayor numbered 49-A and 77-A,

both series of 2011, dated September 5 and December 13, respectively,

authorized and designated the ABC Jaro District headed by its President

Rammy J. Guintibano to manage and maintain the 2012 Jaro Agro-Industrial Fair

at Jaro Plaza, Iloilo City, the said Order did not spell out in particular the

financial aspect detailing the proper use and accounting of income derived

therefrom.

In the absence of an updated City Ordinance relative to Ordinance No.

40, control measures in managing and accounting for income derived from

the use of public plazas and other public places are not put in place to the

advantage of the LGU. Rental rates should likewise be amended to suit the

current economy. There should be an appropriate sharing scheme of income

derived from stall rentals between the association being authorized to

manage and the City Government considering that the use of public plazas

is one potential source of income to the City.

We have issued Audit Observation Memorandum No. 12-005 dated

March 20, 2012 for this deficiency.

According to the City Mayor during the exit conference, public

plazas will no longer be rented out to private entrepreneurs during fiestas

and trade fairs as there is a plan to develop and beautify the same.

Recommendation

We recommend that City Ordinance No. 40, series of 1972 be

amended/revised to suit the current economic conditions. Pending such

amendment/revision, the Ordinance shall remain enforceable.

We further recommend that there shall be a sharing scheme of

income between the City and the concerned Association of Barangay

Captains to ensure that what should accrue to the LGU must be earned.

Page 30: 2011 Annual Audit Report for Iloilo City

30

14. Assets donated by other government and private entities to the City of Iloilo

were not covered with Deeds of Donation and Acceptance of Donations

pursuant to the pertinent provisions in the Handbook on Property and

Supply Management hence these were not recorded in the books of accounts

as donated assets in accordance with the financial statement assertion on

completeness, thus understating the Property, Plant and Equipment

accounts.

The financial statement assertion of completeness requires that all

transactions that should be recorded have been recorded. On the other hand, the

pertinent provision in the Handbook on Property and Supply Management System

requires a Deed of Donation and an Acceptance of Donation as attachment papers

of the donated assets.

Moreover, Section 23 of the Local Government Code of 1991 states:

“Local chief executives may, upon authority of the sanggunian,

negotiate and secure financial grants or donations in kind, in

support of the basic services or facilities enumerated under

Section 17 hereof, from local and foreign assistance agencies

without necessity of securing clearance or approval thereof from

any department, agency, or office of the National Government or

from any higher local government unit; Provided, that projects

financed by such grants or assistance with national security

implications shall be approved by the national government

agency concerned: Provided, further, that when such national

agency fails to act on the request for approval within thirty (30)

days from receipt thereof, the same shall be deemed approved.

The local chief executive shall, within thirty (30) days upon

signing of such grant agreement or deed of donation, report the

nature, amount, and terms and of such assistance to both Houses

of Congress and the President.”

Donated assets were obtained by the LGU from various donors. These

assets remain unrecorded in the books of accounts as of December 31, 2011 due

to lack of documentation.

Donations are usually received by the City Mayor’s Office. However,

the corresponding donation papers were not obtained/prepared.

Page 31: 2011 Annual Audit Report for Iloilo City

31

Ideally, all donations should be covered by Deeds of Donation. After

execution of the Deeds of Donation, the City General Services Office should be

furnished with a copy thereof for recording in the property records and thereafter,

the City Accountant for booking-up the same in the books of accounts.

In the absence of the deeds of donation, the assets remain unrecorded in

the property records and in the accounting books, thus understating the Property,

Plant and Equipment accounts.

We have issued AOM No. 12-011 dated May 16, 2012 on this

deficiency.

Recommendation

We recommend that the City Mayor’s Office document every donated

asset by executing a deed of donation duly signed by the donor and donee,

reflecting thereon the type of asset being donated, the related cost/s, the intent for

the use of the said donation and to furnish the City General Services Office and

the City Accountant with copies thereof for recording purposes.

The City General Services Office and the City Accountant shall record

all donated assets in the property and accounting records, respectively, based on

the deeds of donations being furnished by the City Mayor’s Office. These Offices

should coordinate to ensure compliance with regulations on donated assets.

For donations without value, the City Mayor may create a committee to

appraise the value of the donated asset for proper recording in the books of

accounts.

15. Collection of parking fees on public areas pursuant to Sec. 133 of Tax

Ordinance No. 2007-016, which could have increased the revenue collections

of the City, has not been imposed.

Sec. 133 of Tax Ordinance No. 2007-016 provides:

“(a) Night Parking. – for using street, sidewalk or public place in

front of their houses or in places of business as their garage or

parking space during night time:

1) For cars and jeepneys per quarter or fraction thereof.....P350.00

2) For buses and trucks per quarter……………………….. 500.00

Page 32: 2011 Annual Audit Report for Iloilo City

32

3) For container vans/travel per night or fraction thereof….. 50.00

Stickers shall be issued by the City Treasurer to vehicle upon

payment of the above mentioned Night Parking Fees.

Vehicle found night parking without stickers shall be

impounded and kept in the City Motor Pool at the expense of the

owner.

b) Day Parking Fee – For all owners/drivers of private motor vehicle

using designated parking area of the PNP as parking places between

the hour of 7:00 o’clock in the morning to 5:00 o’clock in the

afternoon shall pay the following fees:

1) For cars and jeepneys per hour or fraction thereof ..……..P5.00

2) For all container vans/trailers per hour or fraction thereof.. 5.00

3) For buses and trucks per hour or fraction thereof..……….. 5.00

The Office of the City Treasurer shall assign collectors for

the purpose of collecting day private motor vehicle and shall be

responsible for the issuance of official receipts or cash ticket for such

payment.”

The City of Iloilo has not been collecting the night and day parking fees

since the effectivity of Tax Ordinance No. 2007-016 on January 1, 2008 due to

non-implementation of the parking regulation which is still wanting of

implementing guidelines as there is no particular office directed under the

ordinance to undertake the same.

We sent an audit query to solicit management comments on the

observation. While we recognize the constraints given by management for the

non-implementation, the same may be addressed by setting strategies,

mechanisms and well defined implementing guidelines to that effect.

An Audit Observation Memorandum No. 12-009 dated was issued on

this deficiency.

In a letter reply from the City Treasurer, she informed that a conference

was called by the Honorable City Mayor on April 30, 2012 and discussed

issuance of the following directives:

Page 33: 2011 Annual Audit Report for Iloilo City

33

1. City Police Director Marito Valerio- To coordinate with Iloilo City’s

Transportation Management and Traffic Regulation Office

(TMTRO) in identifying areas in the city as parking spaces for

submission to the Sangguniang Panlungsod for designation.

2. OIC-City Engineer Karl Quimsing- To prepare the signage for

parking spaces identified by PNP-TMTRO and designated by the

Sangguniang Panlungsodthrough an ordinance.

3. City Treasurer Katherine T. Tingson – To prepare the assignment of

treasury personnel/collectors of Parking Fees upon approval by the

Sangguniang Panlungsod of the parking spaces.

The City Government is currently considering the option to submit in a

competitive bidding the towage requirement of Night Parking Fee to companies in

Iloilo City with towage trucks and/or similar vehicles.

Recommendation

We recommend that parking fees on public places be imposed by

implementing the night and day parking regulations. Necessary amendments

should be made on Sec. 133 of Tax Ordinance No. 2007-016 to operationalize the

collection of the parking fees. Specific office should be mandated to come up with

the implementing rules and regulations, setting forth the apprehension of parking

violators that includes the impounding and towing of vehicles.

16. Payroll preparation and processing of the different departments , offices

and sections was not in accordance with the prescribed guidelines set forth

under Section 261 of the Government Accounting and Auditing Manual,

Volume I, thereby resulting in duplication of the workload and incurrence of

additional man-hours and cost of supplies.

We have reviewed the procedures in the preparation and payment of

payrolls by the City of Iloilo for the year ended December 31, 2011 and observed

the following:

1. The different departments, offices and sections of the LGU

prepared and processed payrolls of regular personnel for the 1st

and 2nd

quincena of the month separately contrary to the

prescribed guidelines under Sec. 261 of the Government

Accounting and Auditing Manual (GAAM) Vol. I, thereby

Page 34: 2011 Annual Audit Report for Iloilo City

34

resulting in duplication of the workload, added man-hours and

incurrence of additional supplies costs.

Under Sec. 261 of the GAAM Vol. I, government

offices may make payment of salaries and allowances to

government officials and employees twice a month, first on the

15th

and the second on the last day of the month. The following

guidelines shall be observed in the preparation of the General

Payroll:

a. For each month, the payroll shall be prepared in two (2) sets

– one (1) for the first half and one for the second half.

b. The payroll for the first half of the month shall reflect the

basic monthly salary, all allowances and itemized monthly

deductions.

c. Net pay for the first half and second half shall be computed

as follows: Basic salary plus all allowances less total

deductions divided by two (2).

The different departments, offices and sections of the LGU prepared and

processed their respective payrolls for the payment of salaries and allowances of

1,689 regular personnel. Separate payrolls were prepared and processed for the 1st

and 2nd

quincena of the month. The net pays of personnel for the two (2) pay days

during the month were not of equal amounts because different sets of deductions

were made on each pay period. More than 50% of the salaries of personnel were

accrued on the 1st half of the month in order to accommodate bigger salary

deductions during this pay period. Moreover, payment of the Personnel Economic

Relief Allowance (PERA) was deferred to the end of the month.

Based on Sec. 261 of the GAAM Vol. I, there should only be one (1)

payroll every month for each of the different departments, offices and sections of

the LGU. The payroll should reflect the basic salary plus allowances less

deductions divided by two in order to arrive at the equal net pay for the 1st and 2

nd

quincena of the month. The monthly payroll should be prepared in two (2) sets to

support the payments made for each quincena.

It has been the practice of the LGU to prepare and process payrolls twice

a month instead of once a month. Such practice duplicated the monthly workload,

man-hours and office supplies in accomplishing the task. The total number of paid

Page 35: 2011 Annual Audit Report for Iloilo City

35

payrolls of about 2,859 for the year ended December 31, 2011 could have been

reduced by 1,429 had the monthly scheme been observed.

Moreover, monthly salaries and allowances of about 170 LGU

employees chargeable to the Special Education Fund (SEF), semi-monthly wages

of 2,638 job order hires, 289 Transportation Management and Traffic Regulation

Services (TMTRO), 85 Barangay Peacekeeper Acting Team (BPAT), 268

Coordinated Executive Sangguniang Panlungsod Efforts for Development of

Iloilo City (CESPEDIC) and 124 Legislative Support Program (LSP) personnel

and quarterly honorarium of 2,379 Department of Education (DEpEd), 643

Philippine National Police (PNP), 85 Bureau of Jail Management and Penology

(BJMP) and 95 Bureau of Fire Protection (BFP) employees were paid through

cash advances drawn by disbursing officers for the purpose. This practice

involved additional man-hours to disbursing officers and long queuing of

personnel concerned at the Office of the City Treasurer in claiming their

emoluments as compared to payments through ATM accounts. The time spent

could have been used more productively in the actual performance of the

personnel’s respective functions.

We have issued AOM No. 12-008 dated April 3, 2012 on this

deficiency. The recommendation earned the appreciation of the City

Accountant. She assured that the payroll makers, payroll clerks and other

employees concerned will undergo orientation on proper preparation and

processing of payrolls of permanent employees on a monthly basis which take

effect on May 2012. As for the salaries of non-regular employees, the City Mayor

has already taken into consideration the payment scheme recommended and will

implement it in the succeeding month. As to our recommendation on

centralization and computerization of payroll system, this is one project that is

being considered for the year after the implementation of the biometrics system

for time keeping.

Recommendation

We recommend that the payrolls of regular personnel be prepared and

processed on a monthly basis. These payrolls should be prepared in two (2) sets,

reflecting both the 1st and 2

nd quincena of the month. The net pay should be

arrived at by adding the basic salary and all allowances less total deductions

divided by two (2). The payroll proof list showing the semi-monthly net pay

credited to the personal bank accounts of the personnel should form part of the

supporting documents of the Auto Debit Advice (ADA) issued to the bank by the

LGU.

Page 36: 2011 Annual Audit Report for Iloilo City

36

The payroll preparation should include the monthly payslips to be

distributed to every employee at least one (1) day before the 15th

of the month. It

should be indicated in the payslip that the employee’s net pay has been credited to

his/her bank account.

We further recommend that the payrolls of SEF, job order, TMTRO,

BPAT, CESPEDIC, LSP, DepEd, PNP, BJMP and BFP personnel totaling 6,776

be paid through Automated Teller Machines (ATM) to save on man-hours, avoid

queuing of personnel during paydays, promote ease and convenience of personnel

in claiming their emoluments and optimize personnel productivity.

Likewise, the LGU may consider adopting a centralized and

computerized payroll system to promote effectiveness and efficiency in the

payment of salaries, allowances, wages and other benefits to personnel.

17. The minimum net monthly take home pay of P3,000.00 as mandated

under Section 43 of the General Provisions of the General Appropriations

Act of 2011 were not implemented and complied with by 352 employees

of the City as of December 31, 2011.

Sec. 43 of the General Provisions of the General Appropriations Act of

2011 provides:

“Deductions from salaries, emoluments or other benefits

accruing to any government employee chargeable against the

appropriations for Personal Services may be allowed for the payment

of individual employee’s contributions or obligations due the

following:

(a) The BIR, GSIS, HDMF and PHILHEALTH;

(b) Mutual benefits associations, thrift banks and non-stock

savings and loan associations duly operating under existing

laws which are managed by and /or for the benefit of

government employees;

(c) Associations/cooperatives/provident funds organized and

managed by government employees for their benefit and

welfare;

(d) Duly licensed insurance companies accredited by national

government agencies; and

Page 37: 2011 Annual Audit Report for Iloilo City

37

(e) Organizations and companies such as banks, non-bank

financial institutions, financing companies and other similar

entities that have authority to engage in lending and mutual

benefits or mutual aid system as stated in their respective

constitutions and by-laws approved by government regulating

bodies such as the Securities and Exchange Commission

(SEC), Insurance Commission (IC), Banko Sentral ng Pilipinas

(BSP) and Cooperative Development authority (CDA).

PROVIDED, That such deductions shall not reduce the

employee’s monthly net take home pay to an amount lower than

Three Thousand Pesos (P3,000.00), after all authorized deduction:

PROVIDED, FURTHER, That in the event total authorized

deductions shall reduce net take home pay to less than Three

Thousand Pesos (P3,000.00), authorized deductions under item (a)

shall enjoy first preference, those under item (b) shall enjoy second

preference, and so forth.”

There were 352 employees receiving a monthly net take home pay of

less than P3,000.00 as of December 31, 2011. The LGU allowed these employees

to contract loans with the government and private lending institutions to the extent

of reducing their net take home pay below P3,000.00 in violation of the aforecited

criteria. Furthermore, preference of authorized deductions should have been

applied.

An AOM No. 12-010 dated May 9, 2012 was issued to call the attention

of the management regarding this violation for which a positive response was

given. Considering that most of the City Government Employees have existing

loans payable for more than a year, an appeal was made to give them time until

these accounts are settled, then the implementation.

Recommendation

We recommend that the prescribed minimum employee’s monthly net

take home pay under the GAA be observed. Effective January 1, 2012, the

P3,000.00 minimum limit was increased to P5,000.00 pursuant to Sec. 37 of the

General Provisions of the current GAA of 2012.