43047421 project pavement condition survey at parit jelutong batu pahat johor

Upload: syura-raman

Post on 02-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    1/74

    CHAPTER 1

    PROBLEM STATEMENT

    As Malaysia's roads become more congested, the Works Ministry has the daunting task of ensuring they are constantly in good condition and safe for motorists. Roadinfrastructure development is generally synonymous with the overall growth of a

    nation. Malaysia has had a tremendous increase in road mileage since the last 40 years, expedited by her independence. With the convenience of road developmentcomes issues that cause specific inconvenience to the people, namely poor roadcondition during rainy seasons, traffic congestion and road accidents. During the rainy seasons, many areas will have potholes and other types of problems, creating a dangerous condition and causing accidents as drivers react to avoid them.

    1

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    2/74

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    3/74

    In order to complete our project for BFC 3042, we are required to conduct a survey on pavement condition to identify the damage which occurred and propose a suitable pavement method work to local authority.

    1.1

    SCOPE

    For this task we are required to conduct a survey on the pavement condition in the certain road, along 1kilometer. We have to do a few methods to complete thissurvey. We had picked up the main road from Parit Jelutong. At the site survey,we have to determine some categories of pavement distress and damage. From the data obtained, we have to discuss and analyze the suitable method to regarding the condition.

    1.2

    AIM

    We had survey a few roads in the radius of UTHM. We found that Parit Jelutong ismost suitable site that we chose to continue the project as it is nearby to UTHM. The respective road had a few sort of damaged that easily can found on theirpavement due to transportation of oil palm material in and out from the particular place.

    1.3

    METHOD

    For the method of analyzation, we collect the data by filling the damage found into the condition survey data sheet. We also did the sand patch method in orderto covers the determination of the average texture depth of paved surface sand t

    o give the volume of voids. For the treatment, we use chip seal to assure that the damage occurred has been treat and the road will be use safe and smoothly.

    3

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    4/74

    CHAPTER 2

    LITERATURE REVIEW

    The movement of people and goods throughout the world is primarily dependent upon a transportation network consisting of roadways. Most, if not all, business economies, personal economies, and public economies are the result of this transpo

    rtation system. Considering the high initial and annual cost of roadways and since each roadway serves many users, the only prudent owner of roadways is the public sector. Thus it is the discipline of civil engineering that manages the vastnetwork of roadways. The surface of these roadways, the pavement, must have sufficient smoothness to allow a reasonable speed of travel, as well as ensure thesafety of people and cargo. Additionally, once the pavement is in service, the economies that depend upon it will be financially burdened if the pavement is taken out of service for repair or maintenance. Thus, pavements should be designedto be long lasting with few maintenance needs.

    The accomplishment of a successful pavement design depends upon several variables. The practice of pavement design is based on both engineering principles and e

    xperience. Pavements were built long before computers, calculators, and even slide rules. Prior to more modern times, pavements were designed by trial-and-errorand commonsense methods, rather

    4

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    5/74

    than the more complicated methods being used currently. Even more modern methodsrequire a certain amount of experience and common sense. The most widely used methods today are based on experiments with full-scale, in-service pavements thatwere built and monitored to failure. Empirical information derived from these road tests is the most common basis for current pavement design methods. More recently, with the ever-expanding power of personal computers, more mathematicallybased pavement design methods such as finite element analysis and refined elasti

    c layer theory have been introduced. These methods require extensive training touse and are not developed for the inexperienced. Types of pavements can be broadly categorized as rigid, flexible, or composite. The characteristics of these types are reviewed in the following articles.

    RIGID PAVEMENT FLEXIBLE PAVEMENT COMPOSITE PAVEMENT (OVERLAYS)

    In this literature review, we need to spend and focus over the aspect that involving in pavement design criteria. It is centralized as three of analytical important prospect in this part of literature review for the Project gaining information as listed below; PAVEMENT STRESS DESIGN OF CHIP SEAL TYPES OF PAVEMENT DISTRESS

    Rigid pavement can be constructed with contraction joints, expansion joints, dowelled joints, no joints, temperature steel, continuous reinforcing steel, or nosteel. Most generally, the construction requirements concerning these options are carefully chosen by the owner or the public entity that will be responsible for future maintenance of the pavement. The types of joints and the amount of steel used are chosen in concert as a strategy to control cracking in the concrete pavement. Often, the owner specifies the construction requirements but requires the designer to take care of other details such as intersection jointing detailsand the like. It is

    5

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    6/74

    imperative that a designer understand all of these design options and the role each of these plays in concrete pavement performance.

    Load transfer is the critical element at joints and cracks. In undo welled, unreinforced pavements, any load transfer must be provided by aggregate interlock.

    Source: Highway Engineering Handbook, 2nd edition

    Aggregate interlock is lost when slabs contract and the joints or cracks open up. Also, interlock is slowly destroyed by the movement of the concrete as trafficpasses over. Given large temperature variations and heavy trucks, aggregate interlock is ineffectual, and faulting is the primary result.

    Where a long joint spacing is used and intermediate cracks are expected, steel reinforcement is added to hold the cracks tightly closed (JRCP). This allows theload transfer to be accomplished through aggregate interlock without the associated problems described above. Contraction joints do not provide for expansion ofthe pavement unless the same amount of contraction has already taken place. This contraction will initially be from shrinkage due to concrete curing. Later cha

    nges in the pavement length are due to temperature changes. Where

    6

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    7/74

    fixed objects such as structures are placed in the pavement, the use of an expansion joint is warranted. Expansion joints should be used sparingly. The pavementwill be allowed to creep toward the expansion joint, thus opening the adjacentcontraction joints. This can cause movement in the adjacent contraction joints in excess of their design capabilities and result in premature failures.

    This is showed, how the good implementation and idea given to review the overall

    literature of Project Making Process with high intention of other fundamental idea in highway engineering.

    2.1

    PAVEMENT STRESS

    Pavement Stress is considered to be under the flexible pavement. The basic ideaof pavement stress starting from the loading area and impact on the pavement. Rutting in asphalt pavement includes densification and shear flow of hot-mix asphalt, but the majority of severe instable rutting results from shear flow within the asphalt mixtures. In recent years, another type of surface distress called To

    p-Down Cracking (TDC), which is usually found in longitudinal path, has become more common in asphalt pavement, this is also considered as a shear-related failure. As a result, shear stress is believed to be one of the critical factors affecting pavements performance, and it is necessary to well understand shear stressin asphalt pavements. To gain an accurate understanding of the effect of shearstress on pavement performance, a laboratory method of applying tirepavement contact pressure is employed in this paper. The results are compared for differingloading conditions. The effects of tire pressure and stress components in termsof vertical and horizontal stress on shear stress are comprehensively investigated by three-dimensional finite element method. In addition, the effects of asphalt layer thickness and interface conditions are also discussed.

    7

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    8/74

    Car loading is the most important aspect in order to effect the load distribution on pavement surface to the base. Rutting influenced by the load of car, and regularly happened on the mid of section in single road. We need to predict and understand stress - strain distribution within the pavement structure as they relate to failure cracking and rutting.

    In Flexible Pavement Stress Analysis, there are two (2) types of prediction stre

    ss in pavement that occur. 1. Numerical Models 2. Ideal Models

    Numerical Models Need model to compute deflections (d) an

    strains (e). Num

    rous mo

    ls availabl

    with

    iff

    r

    nt: Capabiliti

    s Un

    rlying assumptions Compl

    xity Mat

    rial information r

    quir

    m

    nts I

    al Mo

    ls Pr

    icts an

    Input Param

    t

    rs Str

    ss

    s Strains Static &

    ynamic loa

    s Mat

    rial prop

    rti

    s Traffic Environm

    nt

    8

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    9/74

    Availabl

    Mo

    ls in th

    s

    fi

    l

    s of highway analysis that us

    wi

    ly in r

    al sit

    as b

    low list

    ; o Multilay

    r Elastic Th

    ory o Finit

    El

    m

    nt M

    tho

    s o o o Visco

    lastic Th

    ory (tim

    an

    t

    mp.-

    p

    n

    nt b

    havior) Dynamic Analysis (in

    rtial

    ff

    cts) Th

    rmal Mo

    ls (t

    mp

    ratur

    chang

    )

    But most wi

    ly us

    is; o R

    asonabl

    R

    sults o Prop

    rti

    s R

    lativ

    ly Simpl

    toObtain

    Falling W

    ight D

    fl

    ctom

    t

    r

    Us

    lastic th

    ory to pr

    ict th

    fl

    ction basin for th

    giv

    n loa

    . Th

    n it

    rat

    with

    iff

    r

    nt mo

    ul

    configurations until th

    calculat

    fl

    ction basin match

    s th

    m

    asur

    . This Proc

    ss using th

    tools; Small trail

    r Dropping W

    ight G

    ophon

    s D

    fl

    ction Basin

    9

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    10/74

    This Pav

    m

    nt Str

    ss g

    n

    rat

    by th

    th

    ory of Multilay

    r Elastic Th

    ory. An

    af

    w assumptions w

    r

    taking part of th

    analysis to mak

    sur

    that will b

    r

    asonabl

    an

    practic

    to b

    on

    . As r

    sult, a graph g

    n

    rat

    by th

    fin

    ings in th

    analysis as th

    ory assumption ha

    ma

    b

    for

    th

    analysis. Th

    figur

    of fin

    ing as show

    b

    low.

    Figur

    G

    n

    rating Fin

    ing from Analysis Th

    ory Sourc

    : Dr. Christos Drakos, Univ rsity of Flori a

    10

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    11/74

    Graph: On

    -lay

    r Solutions (Fost

    r & Ahlvin 1954) Sh

    ar str

    ss

    s

    u

    to circularloa

    ing. Sourc

    : Dr. Christos Drakos, Univ

    rsity of Flori

    a

    Asphalt concr

    t

    pav

    m

    nt, also r

    f

    rr

    to as fl

    xibl

    pav

    m

    nt, is a mixtur

    of san

    , aggr

    gat

    , a fill

    r mat

    rial, an

    asphalt c

    m

    nt combin

    in a controll

    proc

    ss, plac

    , an

    compact

    . Th

    fill

    r mat

    rial can rang

    from quarry crushing

    ust an

    asphalt-plant bag hous

    fin

    s to woo

    fib

    rs (c

    llulos

    ). Th

    r

    ar many a itiv s that can b us in asphalt concr t mix s to ncourag thick rc

    m

    nt coatings, mor

    lastic mix

    s, stiff

    r mix

    s, an

    l

    ss t

    mp

    ratur

    -s

    nsitiv

    mix

    s. Fl

    xibl

    pav

    m

    nts can b

    of a typ

    construct

    on a pr

    par

    sub gra

    , which is call

    full-

    pth asphalt concr

    t

    pav

    m

    nt (FDACP), or of a typ

    built on an untr

    at

    granular bas

    , which is not as car

    fully i

    ntifi

    by th

    in

    ustry but is r

    f

    rr

    to h

    r

    in as

    p-str

    ngth asphalt concr

    t

    pav

    m

    nt (DSACP).

    11

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    12/74

    2.2

    DESIGN OF CHIP SEAL

    Th

    r

    ar

    a f

    w qu

    stions about th

    Chip S

    al that play aroun

    th

    fi

    l

    s of construction

    sp

    cially among th

    p

    opl

    who liv

    ly involv

    in th

    in

    ustry of roa

    maint

    nanc

    . To clarify th

    qu

    stions issu

    that

    m

    rg

    in t

    rms of right kno

    wl g an fun am ntal of Chip S al, th Maint nanc T chnical A visory Gui (MTAG) US, w

    r

    using to k

    p maintain an

    bri

    fly

    xplain th

    Chip S

    al D

    sign.

    2.3

    MAINTENANCE TECHNICAL ADVISORY GUIDE (MTAG)

    2.3.1 Chip S

    al from MTAG R

    vi

    w.

    Application of asphalt bin

    r on

    xisting pav

    m

    nt follow

    by a lay

    r of aggr

    gat

    chips. Th

    tr

    atm

    nt is th

    n roll

    to

    mb

    th

    aggr

    gat

    into th

    bin

    r.

    o P

    rformanc

    Typical tr

    atm

    nt lif

    : 5 to 10 y

    ars Function of climat

    ,

    xistingpav

    m

    nt con

    ition, traffic, typ

    of chip s

    al o Av

    rag

    cost $2.50 to $5.00/y

    2(

    p

    n

    ing on oil pric

    )

    12

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    13/74

    Th

    chip s

    al practic

    w

    r

    oing an

    apply bas

    on wh

    r

    an

    wh

    n th

    n

    c

    ssarywork w

    r

    impl

    m

    nting to solv

    th

    roa

    maint

    nanc

    probl

    m bas

    on th

    crit

    ria that list

    b

    low to mak

    sur

    th

    capability an

    workability of work in highint

    nsity of

    n

    uring quality of pav

    m

    nt for th

    liv

    y

    ars. o Surfac

    for light to m

    ium traffic (ADT < 30,000) o Wat

    rproof lay

    r o Ski

    r

    sistant surfac

    o S

    al th

    surfac

    o A

    r

    ss bl

    ing o T

    mporary bas

    cours

    cov

    r o D

    fin

    shoul

    rs

    Pictur

    : Chip S

    al Proc

    ss

    13

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    14/74

    Aft

    r w

    fin

    th

    n

    c

    ssarily wh

    n an

    wh

    r

    , w

    hav

    to know that th

    chip s

    al also hav

    som

    con

    ition that not r

    lat

    to th

    main asp

    ct. So, w

    hav

    toconsi

    r th

    right tim

    wh

    n w

    ar

    not going to us

    th

    Chip S

    al as con

    itionpr

    f

    r b

    low; o Structurally

    fici

    nt pav

    m

    nts o Cracks >1/4 in wi

    th unl

    sss

    al

    o Larg

    numb

    r of pothol

    s o Rutting >1/2 in o Ri

    quality n

    s significant improv

    m

    nt

    In or r to th st p of succ ss in chip s al sign, th right k y of chip s al

    sign w

    hav

    to consi

    r so that th

    work going to b

    succ

    ss an

    on

    prop

    rly. o Prop

    r surfac

    pr

    paration o Us

    th

    right bin

    r an

    cl

    an aggr

    gat

    s o Follow th

    construction sp

    cs, inclu

    ing th

    n

    for traffic control o Chip s

    alin goo

    w

    ath

    r con

    itions

    Pictur

    : Crit

    ria D

    sign St

    p an

    Proc

    ss

    14

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    15/74

    2.3.2 Chip S

    al Variations o Applications o Singl

    chip s

    als o Doubl

    or tripl

    chip s

    als o Cap

    s

    als o Fabric an

    chip s

    als o Scrub s

    als o Asphalt Bin

    rTyp

    s o PME o PMA o AR

    (Singl

    Chip S

    als)

    (Doubl

    Chip S

    als)

    15

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    16/74

    (Cap

    S

    als)

    (Fabric an

    Chip S

    als)

    16

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    17/74

    (Fabric an

    Chip S

    als)

    2.3.3 D

    sign, Mat

    rials & Sp

    cifications

    D

    t

    rmin

    Quantity o R

    si

    ual asphalt cont

    nt o Asphalt c

    m

    nt factor = 1.0 o Emulsion factors rang

    = 0.65 to 0.70 o Aggr

    gat

    application rat

    o Singl

    chip lay

    r o No mor

    than 10%

    xc

    ss chips o 70%

    mb

    m

    nt r

    comm

    n

    17

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    18/74

    Chip S

    al D

    sign M

    tho

    s

    McL

    o

    proc

    ur

    Asphalt Institut

    m

    tho

    1. D

    t

    rmin

    aggr

    gat

    siz

    an

    sp

    cific gravity 2. Aggr

    gat

    an

    bin

    r quantiti

    s from tabl

    3. A

    just aggr

    gat

    (if n

    c

    ssary) 4. A

    just asphalt cont

    nt bas

    on con

    ition of roa

    (if n

    c

    ssary) Mat

    rial S

    l

    ction Bin

    r -

    Mat

    rial S

    l

    ction-Emulsion Ingr

    i

    nts Asphalt Wat

    r Emulsifying ag

    nt (surfactant)

    Polym

    r-mo

    ifi

    mulsions Polym

    r-mo

    ifi

    bin

    r Polym

    r-mo

    ifi

    r

    juv

    nating

    mulsions (PMRE) Asphalt Rubb

    r

    2.3.4 Asphalt Rubb

    r Chip S

    als Bin

    r Mat

    rial Fi

    l

    Bl

    n

    (min. 45 minut

    s an

    viscosity 1,500 cps-4,000) hot asphalt,

    xt

    n

    r oil, crumb rubb

    r, an

    highnatural.AR bin

    r application is usually .60 gal / squar

    yar

    through an agitat

    istributor truck attach

    with a vapor r

    cov

    ry syst

    m. Aggr

    gat

    Chips ar

    always hot pr

    -coat

    , an

    appli

    at 35-40 lbs. p

    r squar

    yar

    .

    18

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    19/74

    Sourc

    : Maint

    nanc

    T

    chnical A

    visory Gui

    (MTAG)-U.S

    19

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    20/74

    2.4

    TYPES OF FLEXIBLE PAVEMENT DISTRESS

    In

    x of Pav

    m

    nt Distr

    ss

    s Shown on this Pag

    Fatigu

    (alligator) cracking Bl

    ing Block cracking Corrugation an

    shoving D

    p

    r ssion Joint r fl ction cracking Lan /shoul r rop-off Longitu inal cracking Patching

    Polish

    aggr

    gat

    Pothol

    s Rav

    ling Rutting Slippag

    cracking Stripping Transv

    rs

    (th

    rmal) cracking Wat

    r bl

    ing an

    pumping

    2.4.1

    Fatigu

    (Alligator) Cracking This s

    ction is a summary of th

    major fl

    xibl

    pav

    m

    nt

    istr

    ss

    s. Each

    istr

    ss

    iscussion inclu

    s (1) pictur

    s if availabl

    , (2) a

    scription of th

    istr

    ss, (3) why th

    istr

    ss is a probl

    m an

    (4) typical caus

    s of th

    istr

    ss.

    20

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    21/74

    D

    scription S

    ri

    s of int

    rconn

    ct

    cracks caus

    by fatigu

    failur

    of th

    HMAsurfac

    (or stabiliz

    bas

    ) un

    r r

    p

    at

    traffic loa

    ing. In thin pav

    m

    nts,cracking initiat

    s at th

    bottom of th

    HMA lay

    r wh

    r

    th

    t

    nsil

    str

    ss is th

    high

    st th

    n propagat

    s to th

    surfac

    as on

    or mor

    longitu

    inal cracks. This is commonly r

    f

    rr

    to as "bottom-up" or "classical" fatigu

    cracking. In thick pav

    m

    nts, th

    cracks most lik

    ly initiat

    from th

    top in ar

    as of high localiz

    t

    nsil

    str

    ss

    s r

    sulting from tir

    -pav

    m

    nt int

    raction an

    asphalt bin r aging (top- own cracking). Aft r r p at loa ing, th longitu inal cracks conn

    ct forming many-si

    sharp-angl

    pi

    c

    s that

    v

    lop into a patt

    rn r

    s

    mbling th

    back of an alligator or croco

    il

    . Probl

    m In

    icator of structural failur

    , cracks allow moistur

    infiltration, roughn

    ss, may furth

    r

    t

    riorat

    to apothol

    Possibl

    Caus

    s Ina

    quat

    structural support, which can b

    caus

    by amyria

    of things. A f

    w of th

    mor

    common on

    s ar

    list

    h

    r

    :o

    D

    cr

    as

    in pav

    m

    nt loa

    supporting charact

    ristics Loss of bas

    , sub bas

    or sub gra

    support (

    .g., poor

    rainag

    or spring thaw r

    sulting in a l

    ss stiff bas

    ).o

    Stripping on th

    bottom of th

    HMA lay

    r (th

    stripp

    portion contribut

    s littl

    to pav

    m

    nt str

    ngth so th

    ff

    ctiv

    HMA thickn

    ss

    cr

    as

    s)

    o o

    Incr

    as

    in loa

    ing (

    .g., mor

    or h

    avi

    r loa

    s than anticipat

    in

    sign) Ina

    quat

    structural

    sign

    21

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    22/74

    o

    Poor construction (

    .g., ina

    quat

    compaction)

    R

    pair A fatigu

    crack

    pav

    m

    nt shoul

    b

    inv

    stigat

    to

    t

    rmin

    th

    root caus

    of failur

    . Any inv

    stigation shoul

    involv

    igging a pit or coring th

    pav

    m

    nt to

    t

    rmin

    th

    pav

    m

    nt's structural mak

    up as w

    ll as

    t

    rmining wh

    t

    h r or not subsurfac moistur is a contributing factor. Onc th charact risticalligator patt

    rn is appar

    nt, r

    pair by crack s

    aling is g

    n

    rally in

    ff

    ctiv

    . Fatigu

    crack r

    pair g

    n

    rally falls into on

    of two cat

    gori

    s:o

    Small, localiz

    fatigu

    cracking in

    icativ

    of a loss of subgra

    support. R

    mov

    th

    crack

    pav

    m

    nt ar

    a th

    n

    ig out an

    r

    plac

    th

    ar

    a of poor subgra

    an

    improv

    th

    rainag

    of that ar

    a if n

    c

    ssary. Patch ov

    r th

    r

    pair

    subgra

    .

    o

    Larg

    fatigu

    crack

    ar

    as in

    icativ

    of g

    n

    ral structural failur

    . Plac

    an HMA ov

    rlay ov

    r th

    ntir

    pav

    m

    nt surfac

    . This ov

    rlay must b

    strong

    noughstructurally to carry th

    anticipat

    loa

    ing b

    caus

    th

    un

    rlying fatigu

    crack

    pav

    m

    nt most lik

    ly contribut

    s littl

    or no str

    ngth (Rob

    rts

    t. al., 1996).

    2.4.2

    Bl

    ing

    D

    scription A film of asphalt bin

    r on th

    pav

    m

    nt surfac

    . It usually cr

    at

    sa shiny, glass-lik

    r

    fl

    cting surfac

    (as in th

    thir

    photo) that can b

    com

    quit

    sticky. Probl

    m Loss of ski

    r

    sistanc

    wh

    n w

    t

    22

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    23/74

    Possibl

    Caus

    s Bl

    ing occurs wh

    n asphalt bin

    r fills th

    aggr

    gat

    voi

    s

    uring hot w

    ath

    r an

    th

    n

    xpan

    s onto th

    pav

    m

    nt surfac

    . Sinc

    bl

    ing is not r

    v

    rsibl

    uring col

    w

    ath

    r, asphalt bin

    r will accumulat

    on th

    pav

    m

    nt surfac

    ov

    r tim

    . This can b

    caus

    by on

    or a combination of th

    following:

    Exc ssiv asphalt bin r in th HMA ( ith r u to mix sign or manufacturing)

    Exc

    ssiv

    application of asphalt bin

    r

    uring BST application (as in th

    abov

    figur

    s)

    Low HMA air voi

    cont

    nt (

    .g., not

    nough room for th

    asphalt to

    xpan

    into

    uring hot w

    ath

    r)

    R

    pair Th

    following r

    pair m

    asur

    s may

    liminat

    or r

    uc

    th

    asphalt bin

    rfilm on th

    pav

    m

    nt's surfac

    but may not corr

    ct th

    un

    rlying probl

    m that caus

    th

    bl

    ing:

    Minor bl

    ing can oft

    n b

    corr

    ct

    by applying coars

    san

    to blot up th

    xc

    ss asphalt bin

    r.

    Major bl

    ing can b

    corr

    ct

    by cutting off

    xc

    ss asphalt with a motor gra

    r or r

    moving it with a h

    at

    r plan

    r. If th

    r

    sulting surfac

    is

    xc

    ssiv

    ly rough, r

    surfacing may b

    n

    c

    ssary (APAI, no

    at

    giv

    n).

    23

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    24/74

    2.4.3

    Block Cracking

    D

    scription Int

    rconn

    ct

    cracks that

    ivi

    th

    pav

    m

    nt up into r

    ctangular pi

    c

    s. Blocks rang

    in siz

    from approximat

    ly 0.1 m2 (1 ft2) to 9 m2 (100 ft2).Larg

    r blocks ar

    g

    n

    rally classifi

    as longitu

    inal an

    transv

    rs

    cracking.

    Block cracking normally occurs ov r a larg portion of pav m nt ar a but som tim

    s will occur only in non-traffic ar

    as. Probl

    m Allows moistur

    infiltration,roughn

    ss Possibl

    Caus

    s HMA shrinkag

    an

    aily t

    mp

    ratur

    cycling. Typicallycaus

    by an inability of asphalt bin

    r to

    xpan

    an

    contract with t

    mp

    ratur

    cycl

    s b

    caus

    of:

    Asphalt bin

    r aging Poor choic

    of asphalt bin

    r in th

    mix

    sign

    R

    pair Strat

    gi

    s

    p

    n

    upon th

    s

    v

    rity an

    xt

    nt of th

    block cracking:

    Low s

    v

    rity cracks (< 1/2 inch wi

    ). Crack s

    al to pr

    v

    nt (1)

    ntry of moistu

    r

    into th

    sub gra

    through th

    cracks an

    (2) furth

    r rav

    ling of th

    crack

    g

    s. HMA can provi

    y

    ars of satisfactory s

    rvic

    aft

    r

    v

    loping small cracks if th

    y ar

    k

    pt s

    al

    (Rob

    rts

    t. al., 1996).

    24

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    25/74

    High s

    v

    rity cracks (> 1/2 inch wi

    an

    cracks with rav

    l

    g

    s). R

    mov

    an

    r

    plac

    th

    crack

    pav

    m

    nt lay

    r with an ov

    rlay

    2.4.4

    Corrugation an Shoving

    D

    scription A form of plastic mov

    m

    nt typifi

    by rippl

    s (corrugation) or an abrupt wav

    (shoving) across th

    pav

    m

    nt surfac

    . Th

    istortion is p

    rp

    n

    icular to th

    traffic

    ir

    ction. Usually occurs at points wh

    r

    traffic starts an

    stops (corrugation) or ar

    as wh

    r

    HMA abuts a rigi

    obj

    ct (shoving). Probl

    m Roughn

    ss Possibl

    Caus

    s Usually caus

    by traffic action (starting an

    stopping)combin

    with:

    An unstabl

    (i.

    . low stiffn

    ss) HMA lay

    r (caus

    by mix contamination, poor mix

    sign, poor HMA manufacturing, or lack of a

    ration of liqui

    asphalt

    mulsion

    s)

    Exc

    ssiv

    moistur

    in th

    sub gra

    R

    pair A h

    avily corrugat

    or shov

    pav

    m

    nt shoul

    b

    inv

    stigat

    to

    t

    rmin

    th

    root caus

    of failur

    . R

    pair strat

    gi

    s g

    n

    rally fall into on

    of two cat

    gori

    s:

    25

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    26/74

    Small, localiz

    ar

    as of corrugation or shoving. R

    mov

    th

    istort

    pav

    m

    ntan

    patch.

    Larg corrugat or shov ar as in icativ of g n ral HMA failur . R mov th amag

    pav

    m

    nt an

    ov

    rlay.

    2.4.5

    D

    pr

    ssion

    D

    scription Localiz

    pav

    m

    nt surfac

    ar

    as with slightly low

    r

    l

    vations thanth

    surroun

    ing pav

    m

    nt. D

    pr

    ssions ar

    v

    ry notic

    abl

    aft

    r a rain wh

    n th

    y fill with wat

    r. Probl

    m Roughn

    ss,

    pr

    ssions fill

    with substantial wat

    rcan caus

    v

    hicl

    hy

    roplaning Possibl

    Caus

    s Frost h

    av

    or sub gra

    s

    ttl

    m

    nt r

    sulting from ina

    quat

    compaction

    uring construction. R

    pair By

    finitio

    n,

    pr

    ssions ar

    small localiz

    ar

    as. A pav

    m

    nt

    pr

    ssion shoul

    b

    inv

    stigat

    to

    t

    rmin

    th

    root caus

    of failur

    (i.

    ., sub gra

    s

    ttl

    m

    nt or frost h

    av

    ). D

    pr

    ssions shoul

    b

    r

    pair

    by r

    moving th

    aff

    ct

    pav

    m

    nt th

    n

    igging out an

    r

    placing th

    ar

    a of poor sub gra

    . Patch ov

    r th

    r

    pair

    sub gra

    .

    26

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    27/74

    2.4.6

    Joint R

    fl

    ction Cracking

    D

    scription Cracks in a fl

    xibl

    ov

    rlay of a rigi

    pav

    m

    nt. Th

    cracks occur

    ir

    ctly ov

    r th

    un

    rlying rigi

    pav

    m

    nt joints. Joint r

    fl

    ction cracking

    o

    s not inclu

    r

    fl

    ction cracks that occur away from an un

    rlying joint or from

    any oth r typ of bas ( .g., c m nt or lim stabiliz ). Probl m Allows moistur

    infiltration, roughn

    ss Possibl

    Caus

    s Mov

    m

    nt of th

    PCC slab b

    n

    ath th

    HMA surfac

    b

    caus

    of th

    rmal an

    moistur

    chang

    s. G

    n

    rally not loa

    initiat

    , how

    v

    r loa

    ing can hast

    n

    t

    rioration. R

    pair Strat

    gi

    s

    p

    n

    upon th

    s

    v

    rity an

    xt

    nt of th

    cracking:

    Low s

    v

    rity cracks (< 1/2 inch wi

    an

    infr

    qu

    nt cracks). Crack s

    al to pr

    v

    nt (1)

    ntry of moistur

    into th

    sub gra

    through th

    cracks an

    (2) furth

    r rav

    ling of th

    crack

    g

    s. In g

    n

    ral, rigi

    pav

    m

    nt joints will

    v

    ntually r

    fl

    ct through an HMA ov

    rlay without prop

    r surfac

    pr

    paration.

    High s

    v

    rity cracks (> 1/2 inch wi

    an

    num

    rous cracks). R

    mov

    an

    r

    plac

    th

    crack

    pav

    m

    nt lay

    r with an ov

    rlay.

    27

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    28/74

    2.4.7

    Rav

    ling

    D

    scription Th

    progr

    ssiv

    isint

    gration of an HMA lay

    r from th

    surfac

    ownwar

    as a r

    sult of th

    islo

    g

    m

    nt of aggr

    gat

    particl

    s. Probl

    m Loos

    bris on th

    pav

    m

    nt, roughn

    ss, wat

    r coll

    cting in th

    rav

    l

    locations r

    sultin

    g in v hicl hy roplaning, loss of ski r sistanc .

    28

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    29/74

    Possibl

    Caus

    s S

    v

    ral inclu

    ing:

    Loss of bon

    b

    tw

    n aggr

    gat

    particl

    s an

    th

    asphalt bin

    r as a r

    sult of:-

    o

    A ust coating on th aggr gat particl s that forc s th asphalt bin r to bonwith th

    ust rath

    r than th

    aggr

    gat

    o

    Aggr

    gat

    S

    gr

    gation. If fin

    particl

    s ar

    missing from th

    aggr

    gat

    matrix,th

    n th

    asphalt bin

    r is only abl

    to bin

    th

    r

    maining coars

    particl

    s at th

    ir r

    lativ

    ly f

    w contact points.

    o

    Ina

    quat

    compaction

    uring construction. High

    nsity is r

    quir

    to

    v

    lop s

    uffici

    nt coh

    sion within th

    HMA. Th

    thir

    figur

    abov

    shows a roa

    suff

    ringfrom rav

    ling

    u

    to ina

    quat

    compaction caus

    by col

    w

    ath

    r paving.

    M

    chanical

    islo

    ging by c

    rtain typ

    s of traffic (stu

    tir

    s, snowplow bla

    s or track

    v

    hicl

    s). Th

    first an

    fourth figur

    s abov

    show rav

    ling most lik

    ly caus

    by snow plows.

    R

    pair A rav

    l

    pav

    m

    nt shoul

    b

    inv

    stigat

    to

    t

    rmin

    th

    root caus

    offailur

    . R

    pair strat

    gi

    s g

    n

    rally fall into on

    of two cat

    gori

    s:

    Small, localiz ar as of rav ling. R mov th rav l pav m nt an patch.

    Larg

    rav

    l

    ar

    as in

    icativ

    of g

    n

    ral HMA failur

    . R

    mov

    th

    amag

    pav

    m

    nt an

    ov

    rlay.

    29

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    30/74

    CHAPTER 3

    METHODOLOGY

    3.1

    FORMING GROUP

    In w

    k 1, l

    ctur

    r tol

    us th

    r

    is a proj

    ct for Highway Engin

    ring subj

    ct an

    sh

    ask

    us to form in a group. Each group consists of 5 p

    opl

    but sp

    cialp

    rmission to our group wh

    r

    w

    contain of 6 stu

    nts.

    30

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    31/74

    3.2

    PROBLEM AND SCOPE OF PROJECT

    In w

    k 3, l

    ctur

    r gav

    us th

    probl

    m an

    th

    scop

    of proj

    ct. Sh

    bri

    fly

    xplain

    th

    probl

    m. Th

    probl

    m was about th

    roa

    s that hav

    b

    n built ar

    oft

    n

    amag

    u

    to v

    hicl

    loa

    an

    nvironm

    nt. This situation r

    quir

    s th

    mai

    nt nanc work to b on so that it can provi comfortabl ri ing to roa us rs. Each of th

    group has to con

    uct a surv

    y of pav

    m

    nt con

    itions to

    t

    rmin

    amag

    s an

    r

    comm

    n

    appropriat

    pav

    m

    nt pr

    s

    rvation work to local authoriti

    s. Th

    local authority woul

    lik

    to us

    chip s

    al m

    tho

    to r

    pair th

    amag

    roa

    surfac

    . Subs

    qu

    ntly, stu

    nts hav

    to

    sign an appropriat

    chip s

    al tr

    atm

    nt. Th

    factors of th

    amag

    to th

    roa

    s also n

    to b

    r

    vi

    w

    , stu

    i

    an

    r

    lat

    sign asp

    cts of th

    xisting

    rainag

    syst

    m.

    3.3

    BRIEFING OR BRAINSTORMING SESSION

    Our l

    ctur

    r gav

    us a brainstorming on how to solv

    th

    r

    lat

    probl

    m. In this s

    ssion, l

    ctur

    r ha

    giv

    n us som

    opinions such as th

    proc

    ur

    s an

    th

    r

    quir

    m

    nts of th

    proj

    ct an

    th

    quipm

    nts that ar

    n

    for this proj

    ct

    31

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    32/74

    3.4

    DISCUSSION / INVESTIGATING PROBLEM

    Aft

    r th

    l

    ctur

    r bri

    f

    us th

    proj

    ct probl

    m an

    th

    group

    iscussion on 26July 2010, w

    ha

    sugg

    st

    f

    w sit

    s for our proj

    ct which ar

    Parit J

    lutong,Jalan R

    ngit, Taman M

    l

    war roa

    an

    Parit Haji Rais. To

    t

    rmin

    th

    sit

    for

    our proj ct, w hav to con uct a surv y on th sit so that th sit that w choos

    is fulfill

    th

    r

    quir

    m

    nts of this proj

    ct such as minimum four crackswithin 1km of th

    roa

    . W

    ci

    to choos

    Parit J

    lutong as our proj

    ct sit

    aft

    r w

    con

    uct

    surv

    ys on th

    s

    f

    w sit

    s on 30 July 2010. B

    for

    w

    start th

    onsit

    laboratory works, w

    w

    r

    ivi

    into s

    v

    ral small groups. Each of th

    group m

    mb

    r has to i

    ntify th

    probl

    ms an

    o r

    s

    arch on th

    probl

    ms inth

    int

    rn

    t, books an

    journal. Aft

    r that, th

    i

    ntifi

    probl

    ms will b

    solv

    in FILA tabl

    by using brainstorming m

    tho

    . Th

    m

    tho

    of FILA tabl

    is asfollowings:

    FACTS - th

    roa

    s that hav

    b

    n built ar

    oft

    n

    amag

    u

    to v

    hicl

    loa

    an

    nvironm

    nt

    IDEAS -Singl

    chip s

    al -Doubl

    chip s

    al -Str

    ss absorbing M

    mbran

    (SAM) -M

    mbran

    Int

    rlay

    r (SAMI)

    LEARNING ISSUES -Typ

    s of chip s

    al -D

    sign of chip s

    al -Aggr

    gat

    for chip s

    als

    ACTION PLANS - I

    ntifi

    th

    cracks - Bas

    on

    ata analysis, r

    comm

    n

    a

    sign of chip s

    al to r

    pair th

    cracks

    32

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    33/74

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    34/74

    3.7

    RESULT ANALYSIS AND RECOMMENDATION

    Bas

    on th

    ata that got from on-sit

    laboratory works an

    laboratory works, firstly w

    hav

    to g

    t th

    Pav

    m

    nt Con

    ition In

    x (PCI) valu

    . To obtain PCI valu

    , th

    r

    ar

    st

    ps which ar

    Distr

    ss D

    nsity, Corr

    ct

    D

    uct Valu

    an

    PCI

    Rating scal . Th PCI valu for s ction 1, 2, 3 an 4 ar 54 (LOS D, POOR), 83 (LOS B, SATISFACTORY), 81 (LOS B, SATISFACTORY) an

    82 (LOS B, SATISFACTORY) r

    sp

    ctiv

    ly. Th

    total PCI valu

    for 1km roa

    is 75 (LOS B, SATISFACTORY) which m

    ans s

    ction pav

    m

    nt is in satisfactory con

    ition, L

    v

    l of S

    rvic

    is B an

    n

    to pr

    v

    ntiv

    maint

    nanc

    . Bas

    on th

    total PCI valu

    for 1 km l

    ngth of th

    roa

    , w

    sign th

    chip s

    al

    sign. Accor

    ing to our chip s

    al

    sign, w

    r

    comm

    n

    that th

    roa

    shall b

    using Doubl

    Chip S

    al, th

    siz

    for first lay

    ris 14mm an

    th

    siz

    for s

    con

    lay

    r is 6mm.

    3.8

    FINAL REPORT AND PRESENTATION

    W

    submitt

    our final r

    port an

    pr

    s

    nt

    our proj

    ct on w

    k 12. On Satur

    ay16th Octob

    r th

    r

    will b

    a post

    r pr

    s

    ntation will b

    carri

    out as part ofour

    valuation.

    3.9

    FINAL EVALUATION

    Final

    valuation on our group will b

    giv

    n aft

    r w

    submitt

    our final r

    portan

    i

    our pr

    s

    ntation bas

    on quality of our r

    port an

    pr

    s

    ntation an

    th

    way that w

    pr

    s

    nt

    .

    34

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    35/74

    CHAPTER 4

    DATA ANALYSIS AND DISCUSSION

    35

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    36/74

    BRANCH : TRAFFIC LABORATORY UTHM SURVEYED BY: MOGANRAJ

    DATE : 9 AUGUST 2010 SAMPLE UNIT : SAMPLE AREA : 4.8m x 250m

    SECTION : 4 (1 km)

    11. Patching & 01. Aligator Cracking (m2) 06. D

    pr

    ssion (m2) 07. E

    g

    Cracking

    02. Bl ing (m2) (m) 12. Polish 08. Joint R fl ction 03. Block Cracking (m2)Cracking (m) 13. Pothol

    s(no) 04. Bumps an

    Sags (m) 14. Railroa

    Crossing 05. Corrugation (m2) 09. Lan

    /shoul

    r Drop (m) 15. Rutting (m2) (m) Aggr

    gat

    (m2) Utility Cut Patching (m2)

    17. Slippag

    Cracking (m2)

    18. Sw

    ll (m2)

    19. W

    ath

    ring/

    Rav

    lling (m2)

    10. Longitu

    inal & Transv

    rs

    Cracking (m)

    16. Shoving (m2)

    36

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    37/74

    Sampl

    1 (for s

    ction 0 250m) D

    t

    rmin

    th

    Distr

    ss D

    nsity an

    D

    uct Valu

    DISTRESS SURVEY DEDUCT VALUE

    QUANTITY

    TOTAL

    DENSITY (%)

    100*(3.7/1200) 01M 3.7 3.7 = 0.31 100*(5.6/1200) 10M 5.6 5.6 = 0.47 100*(0.4/1200) 13L 0.4 0.4 = 0.03 42 6 14

    Maximum allowabl

    numb

    r of

    ucts, m High

    st

    uct valu

    , HDV = 42 m = 1 + (9/98)(100 HDV) = 1 + (9/98)(100 42) = 6.33

    D

    ucts valu

    s in

    sc

    n

    ing or

    r = 42, 14, 6 Numb

    r of

    uct valu

    = 3

    Maximum Corr

    ct

    D

    uct Valu

    , CDV Numb

    r of

    uct valu

    gr

    at

    r than 2, q = 3Total

    uct valu

    = 42 + 14 + 6 = 62 From Figur

    B 45, CDV = 40

    37

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    38/74

    NO 1 2 3 42 42 42 14 14 2

    DEDUCT VALUES 6 2 2

    TOTAL 62 58 46

    q 3 2 1

    CDV 40 43 46

    Maximum CDV = 46

    D

    t

    rmin

    th

    Pav

    m

    nt Con

    ition In

    x, PCI

    PCI

    = 100 - CDVmax = 100 - 46 = 54 (LOS D, POOR)

    Th

    PCI is 54. Bas

    on th

    rating for PCI valu

    of 54, this s

    ction pav

    m

    nt is

    in poor con

    ition, L

    v

    l of S

    rvic

    is D an

    n

    to major r

    habilitation or

    f

    rr

    action.

    38

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    39/74

    Sampl

    2 (for s

    ction 250 500m) D

    t

    rmin

    th

    Distr

    ss D

    nsity an

    D

    uct Valu

    DISTRESS SURVEY DEDUCT VALUE

    QUANTITY

    TOTAL

    DENSITY (%)

    100*(11.3/1200) 10M 11.3 11.3 = 0.94 100*(0.3/1200) 13M 0.3 0.3 = 0.03 15 9

    Maximum allowabl

    numb

    r of

    ucts, m

    High

    st

    uct valu

    , HDV = 15 m = 1 + (9/98)(100 HDV) = 1 + (9/98)(100 15) = 8.82

    D

    ucts valu

    s in

    sc

    n

    ing or

    r = 15, 9 Numb

    r of

    uct valu

    = 2

    Maximum Corr

    ct

    D

    uct Valu

    , CDV Numb

    r of

    uct valu

    gr

    at

    r than 2, q = 2

    Total

    uct valu

    = 15 + 9 = 24 From Figur

    B 45, CDV = 17

    39

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    40/74

    NO 1 2 15 15 9 2

    DEDUCT VALUES

    TOTAL 24 17

    q 2 1

    CDV 17 17

    Maximum CDV = 17

    D

    t

    rmin

    th

    Pav

    m

    nt Con

    ition In

    x, PCI

    PCI

    = 100 - CDVmax = 100 - 17 = 83 (LOS B, SATISFACTORY)

    Th

    PCI is 83. Bas

    on th

    rating for PCI valu

    of 83, this s

    ction pav

    m

    nt is

    in satisfactory con

    ition, L

    v

    l of S

    rvic

    is B an

    n

    to pr

    v

    ntiv

    maint

    nanc

    40

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    41/74

    Sampl

    3 (for s

    ction 500 750m) D

    t

    rmin

    th

    Distr

    ss D

    nsity an

    D

    uct Valu

    DISTRESS SURVEY

    QUANTITY

    TOTAL

    DENSITY (%)

    DEDUCT VALUE

    100*(3.6/1200) 10M 3.6 3.6 = 0.30 100*(0.4/1200) 13L 0.4 0.4 = 0.03 100*(0.3/1200) 13M 0.3 0.3 = 0.03 15 9 3

    Maximum allowabl

    numb

    r of

    ucts, m High

    st

    uct valu

    , HDV = 15 m = 1 + (9/98)(100 HDV) = 1 + (9/98)(100 15) = 8.82

    D

    ucts valu

    s in

    sc

    n

    ing or

    r = 15, 9, 3 Numb

    r of

    uct valu

    = 3

    Maximum Corr

    ct

    D

    uct Valu

    , CDV Numb

    r of

    uct valu

    gr

    at

    r than 2, q = 3Total

    uct valu

    = 15 + 9 + 3 = 27 From Figur

    B 45, CDV = 15

    41

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    42/74

    NO 1 2 3 15 15 15 9 9 2

    DEDUCT VALUES 3 2 2

    TOTAL 27 26 19

    q 3 2 1

    CDV 15 19 19

    Maximum CDV = 19

    D

    t

    rmin

    th

    Pav

    m

    nt Con

    ition In

    x, PCI

    PCI

    = 100 - CDVmax = 100 - 19 = 81 (LOS B, SATISFACTORY)

    Th

    PCI is 81. Bas

    on th

    rating for PCI valu

    of 81, this s

    ction pav

    m

    nt is

    in satisfactory con

    ition, L

    v

    l of S

    rvic

    is B an

    n

    to pr

    v

    ntiv

    maint

    nanc

    .

    42

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    43/74

    Sampl

    4 (for s

    ction 750 1000m) D

    t

    rmin

    th

    Distr

    ss D

    nsity an

    D

    uct Valu

    DISTRESS SURVEY DEDUCT VALUE

    QUANTITY

    TOTAL

    DENSITY (%)

    100*(1.3/1200) 01M 0.2 1.1 1.3 = 0.11 100*(0/3/1200) 13M 0.3 0.3 = 0.03 15 8

    Maximum allowabl

    numb

    r of

    ucts, m

    High

    st

    uct valu

    , HDV = 15 m = 1 + (9/98)(100 HDV) = 1 + (9/98)(100 15) = 8.82

    D

    ucts valu

    s in

    sc

    n

    ing or

    r = 15, 8 Numb

    r of

    uct valu

    = 2

    Maximum Corr

    ct

    D

    uct Valu

    , CDV Numb

    r of

    uct valu

    gr

    at

    r than 2, q = 2

    Total

    uct valu

    = 15 + 8 = 23 From Figur

    B 45, CDV = 16

    43

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    44/74

    NO 1 2 15 15 8 2

    DEDUCT VALUES

    TOTAL 23 17

    q 2 1

    CDV 16 18

    Maximum CDV = 18

    D

    t

    rmin

    th

    Pav

    m

    nt Con

    ition In

    x, PCI

    PCI

    = 100 - CDVmax = 100 - 18 = 82 (LOS B, SATISFACTORY)

    Th

    PCI is 82. Bas

    on th

    rating for PCI valu

    of 82, this s

    ction pav

    m

    nt is

    in satisfactory con

    ition, L

    v

    l of S

    rvic

    is B an

    n

    to pr

    v

    ntiv

    maint

    nanc

    .

    44

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    45/74

    Calculation of th

    PCI s

    ction Jalan Parit J

    lutong PCIri x Ari Ari Wh

    r

    , PCIS Ari = = PCI of pav

    m

    nt s

    ction. Ar

    a of th

    ran

    om sampl

    unit i.

    PCIS

    =

    PCIS

    = (54 + 83 + 81 + 82)(1200) 4800

    =

    75 (LOS B, SATISFACTORY)

    Th

    PCI is 75. Bas

    on th

    rating for PCI valu

    of 75, this s

    ction pav

    m

    nt isin satisfactory con

    ition, L

    v

    l of S

    rvic

    is B an

    n

    to pr

    v

    ntiv

    maint

    nanc

    .

    45

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    46/74

    4.2

    CHIP SEAL

    Crit

    ria of chip s

    al

    Existing Surfac

    an

    traffic Soft surfac

    , such as P

    n

    tration Maca

    am with < 10

    00 v hicl p r ay Soft surfac with > 1000 v hicl p r ay M ium surfac , suchas roll

    asphalt with < 1000 v

    hicl

    p

    r

    ay Har

    surfac

    , such as Portlan

    C

    m

    nt Concr

    t

    or Asphalt Concr

    t

    > 1000 v

    hicl

    p

    r

    ay Tabl

    Singl

    Chip S

    l

    ction Crit

    ria

    Nominal siz

    (mm) 20mm

    14mm 10mm 6mm

    Existing Surfac

    an

    traffic

    Nominal siz

    1st + 2n

    s

    al (mm)

    Soft to m

    ium surfac

    with < 1000 v

    hicl

    p

    r

    ay Har

    surfac

    with > 1000 v

    hicl

    p

    r

    ay Tabl

    Doubl

    Chip S

    l

    ction Crit

    ria

    20 + 10 14 + 6

    Data gain

    from obs

    rvation of total v

    hicl

    s us

    th

    roa

    , it is

    fin

    thattotal v

    hicl

    s us

    th

    roa

    in a

    ay ar

    :

    Traffic in lan

    volum

    p

    r hour Traffic in lan

    (vp

    /lan

    )

    = =

    62 vph/hour/lan 1488 vp / ay/lan

    46

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    47/74

    D

    sign of Chip S

    al For Jalan Parit J

    lutong

    Propos

    of Doubl

    chip s

    al for pr

    v

    ntiv

    maint

    nanc

    at Jalan Parit J

    lutong,Parit Raja, Batu Pahat Johor.

    DETERMINATION OF SIZE, SHAPE AND GRADING OF SEALING CHIPS

    Class No. Thickn ss Tally (a) Rang Ston s In mm Class (b) 1 2 3 4 5 6 7 8 9 1011 12 13 14

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    48/74

    15 16 17 18 19 20 21 22 23 24 25

    14 - 15 15 - 16 16 - 17 17 - 18 18 - 19 19 - 20 20 - 21 21 - 22 22 - 23 23 - 2424 - 25 (c) =

    14.5 15.5 16.5 17.5 18.5 19.5 20.5 21.5 22.5 23.5 24.5 100 (f) = 793

    For 6mm: Aggr gat Av rag L ast Dim nsion, ALD: [ (f) / (c) 0.5 ] [ 793 / 100 0.5] 7.97 mm

    ALD6mm

    = = =

    For 14mm:

    48

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    49/74

    Class No. Thickn

    ss Tally (a) Rang

    Ston

    s In mm Class (b) 1 2 3 4 5 6 7 8 9 1011 12 13 14 15 16 17 18 19 20 21

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    50/74

    22 23 24 25

    21 - 22 22 - 23 23 - 24 24 - 25 (c) =

    21.5 22.5 23.5 24.5 100 (f) = 1221

    Aggr

    gat

    Av

    rag

    L

    ast Dim

    nsion, ALD: [ (f) / (c) 0.5 ] [ 1221 / 100 0.5 ] 12.27

    mm

    ALD14mm

    = = =

    Bin

    r Rat

    of Application, R

    R

    = ( 0.138 x ALD +

    ) x Tf

    Wh

    r

    : ALD : Av

    rag

    L

    ast Dim

    nsion (mm)

    Tf : Bitum

    n n

    to fill roa

    surfac

    : Factor to allow an incr

    as

    application rat

    for low traffic volum

    to

    lay Durability failur

    For 6 mm: R = [ ( 0.138 x 7.97 ) + 0.004 ] x 1.0021 = 1.106 l/m2

    50

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    51/74

    For 14 mm: R = [ ( 0.138 x 12.27 ) + 0.004 ] x 1.0021 = 1.701 l/m2

    Aggr

    gat

    , C

    C

    = 1.364 x ALD

    Wh

    r

    : C = Cov

    r Aggr

    gat

    (kg/m2) Aggr

    gat

    Av

    rag

    L

    ast Dim

    nsion (mm)

    ALD =

    For 6 mm: C = 1.364 x ALD = 1.364 x 7.97 = 10.87 kg/m2

    For 14 mm: C = 1.364 x ALD = 1.364 x 12.27 = 16.74 kg/m2

    51

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    52/74

    4.3 SAND PATCH DATA

    Volum

    = 45 ml = 2.5 cm h H

    ight = 9.30 cm

    Point

    Diam

    t

    r 1

    Diam

    t

    r 2

    Diam

    t

    r 3

    Diam

    t

    r 4

    Diam

    t

    r 5

    Diam

    t

    r 6

    Av

    rag

    (mm)

    1 510 2 490 3 450 4 510 540 510 540 530 530 526.67 450 450 460 450 440 450.00 450 470 480 460 470 470.00 510 480 500 510 480 498.33

    Av

    rag

    Diam

    t

    r

    =

    498.33 + 470 + 450 + 526.67 4

    =

    486.25 mm

    52

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    53/74

    Th

    t

    xtur

    pth, T

    T

    =

    4V D2

    Wh

    r

    : V = Volum

    (ml) D = Diam

    t

    r (mm)

    T

    =

    4V D2

    =

    4(45) (486.25)2 2.42 x 10-4 mm

    =

    4.4

    COST RATE ESTIMATION

    -

    Propos

    of Doubl

    lay

    r chip S

    al for pr

    v

    ntiv

    maint

    nanc

    at Jalan Parit J

    lutong, Parit Raja, Batu Pahat, Johor Darul Ta'zim. For 4800 m2 area of chip seal will bring two (2) days work.

    -

    First layer Supply and Lay Modified Bitumen or Equivalent for the Chip Seal Layer o For bitumen application rate of 1.10 litres /sq .m to 1.30 litres/sq.

    53

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    54/74

    Machinery Descriptions Rate per day (RM) 570 TOTAL Quantity 1 Days 2 Total (RM)1140 1140

    20Tonne Dump Truck

    Manpower Descriptions General Labour Driver Rate per day (RM) 50 65 TOTAL Quantity 2 2 Days 2 2 Total (RM) 200 260 460

    Raw Materials (Bitumen) 1.10 litres /sq .m to 1.30 litres/sq (Average 1.2 litres/sq.m)

    Description

    Rate per barrel (RM) RM 500 TOTAL

    Quantit y 29

    Total

    Bitumen

    14500 14500

    NOTE : 1 Barrel = 200 litres 4800 m2 x 1.2litres/m2 = 5760 litres (5760 litres /200 litres) = 28.8 29 barrels 4800 m2 need 29 barrels bitumen for first layer.

    54

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    55/74

    COST for 4800m2 ITEM Machinery Manpower Materials Cost Profit 40% Total for 4800m COST (RM) 1 140 460 14 500 16 100 16 100 x 0.4 = 6 440 22 540.00

    22540.00 Rate for 1 m = 4800

    = RM 4.70/ m2 to be transfer in Bill of Quantity

    55

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    56/74

    Supply, Lay and Compact uniformly 16 mm pre coated cover aggregates as Chip SealLayer

    a)

    Machinery Description Rate per day (RM) 577 420 Quantity 1 1 Days 2 2 Total (RM)1154 840

    Asphalt Paver 7 Tonne Tandem Roller Sweeper

    495 TOTAL

    1

    2

    990 2 984

    b)

    Manpower Rate per day (RM) 50 85 TOTAL Quantity Days Total (RM)

    Description

    Bitumen Worker Operator

    7 4

    2 2

    700 680 1 380

    56

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    57/74

    c)

    Raw Materials (Aggregate) Descriptions Rate per tan(RM) 14 mm Aggregate 38 Quantity Total (RM) 178.886 6797.67

    TOTAL NOTE : -

    6797.67

    Quantity = Area x Thickness of Aggregate x Density of Aggregate Quantity = 4800m2 x 0.014 m x 2.662 Mg/m3 = 178.886 tonne

    d)

    Cost for 4800 m ITEM Machinery Manpower Materials Cost Profit 40% Total for 4 800m COST (RM) 2 984 1 380 6 797.67 11 161.67 11 161.67 x 0.4 = 4 464.67 15 626.34

    Rate for 1 m =

    15626.34 4800

    = RM 3.26/ m2 to be transfer in Bill of Quantity

    57

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    58/74

    SECOND LAYER Supply and lay second layer modified bitumen or equivalent for thechip seal layer: For bitumen application rate of 0.8 litres/sq.m to 1.0 litres/sq.

    a)

    Machinery Descriptions 20 Tonne Dump Truck Rate per day (RM) 570 Quantity Days T

    otal (RM)

    1

    2

    1140

    TOTAL

    1140

    b)

    Manpower Descriptions Rate per day (RM) General Labor Driver 50 Quantity Days Total (RM)

    2

    2

    200

    65 TOTAL

    2

    2

    260 460

    58

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    59/74

    c)

    Raw Materials (Bitumen) 1.10 litres /sq .m to 1.30 litres/sq (Average 1.2 litres/sq.m) Description Bitumen Rate per barrel (RM) RM 500 TOTAL Quantity 22 Total 11 500 11 500

    NOTE:o 1 Barrel = 200 litres o 4800 m2 x 0.9litres/m2 = 4 320 litres o (4 320 li

    tres / 200 litres) = 21.6 22 barrels o 4800 m2 need 22 barrels bitumen for firstlayer.

    d)

    COST for 4800m2 ITEM Machinery Manpower Materials Cost Profit 40% Total for 4800m COST (RM) 1 140 460 11 500 13 100 13 100 x 0.4 = 5 240 18 340.00

    59

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    60/74

    18340 Rate for 1 m = 4800

    = RM 3.82/ m2 to be transfer in Bill of Quantity

    Supply, lay second layer modified bitumen or equivalent for the chip seal layer:For bitumen application of 0.8 litres/sq.m to 1.0 litres/sq.

    a)

    Machinery Rate per day (RM) 577 Quantity Days 1 2 Total (RM) 1154

    Description Asphalt Paver 7 Tonne Tandem Roller Sweeper

    420

    1

    2

    840

    495 TOTAL

    1

    2

    990 2 984

    60

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    61/74

    b)

    Manpower Description Bitumen Worker Operator Rate per day (RM) 50 Quantity DaysTotal (RM)

    7

    2

    700

    85 TOTAL

    4

    2

    680 1 380

    c)

    Raw Materials (Aggregate) Descriptions 6 mm Aggregate Rate per tan (RM) 40 Quantity Total (RM)

    76.666

    3 066.64

    TOTAL

    3 066.64

    NOTE: Quantity = Area x Thickness of Aggregate x Density of Aggregate Quantity =4800 m2 x 0.006 m x 2.662 Mg/m3 = 76.666 tonne

    61

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    62/74

    d)

    Cost for 4 800 m ITEM Machinery Manpower Materials Cost Profit 40% Total for 4 800 m COST (RM) 2 984 1 380 3 066.64 7 430.64 7 430.64 x 0.4 = 2 972.26 10 402.90

    Rate for 1 m =

    10402.90 4800

    = RM 2.17/ m2 to be transfer in Bill of Quantity

    62

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    63/74

    4.4.1

    BILL OF QUANTITY.

    PROPOSED OF DOUBLE LAYER CHIP SEAL PREVENTIVE MAINTENANANCE AT JALAN PARIT JELUTONG

    ITEM

    DESCRIPTION

    UNIT

    RATE (RM)

    QUANTITY

    AMOUNT (RM)

    1.

    Supply and lay modified bitumen of equivalent for the chip seal layer :I. For bitumen application rate of 1.10 litres per square meter to 1.30 liters per squaremeter.

    m2

    4.70

    4800

    22 560.00

    Supply, lay and compact uniformly 14 mm precoated cover aggregates as chip seal.2. Supply and lay second layer modified bitumen or equivalent for chip seal layer: 3. II. For bitumen application rate of 0.8 litres/sq.m to 1.10/sq.m m2 3.264800 15 648.00

    63

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    64/74

    Supply, lay and and compact 6mm precoated cover aggregate as chip seal layer.

    m2

    3.82

    4800

    18 336.00

    4

    m2

    2.17

    4800

    10 416.00

    TOTAL COST

    66 960.00

    Unquestionably, all of the design methods can effectively guide inexperienced personnel through the process of chip seal design. The following best practices can be drawn from a comparison of the chip seal design methodologies. To begin, the selection of the binder is a very important decision and should be made afterconsidering all the factors under which the chip seal is expected to perform. After all, the primary purpose of a chip seal is to prevent water intrusion into the underlying pavement structure, and the asphalt layer formed by the binder isthe mechanism that performs this vital function. The previously explained design

    methods are all based on the assumption that single-course chip seal design required the use of uniformly manner. The application rates of all methods appear to be based on residual binder and each method has a procedure for dealing with adjustments owing to factoring the loss of binder to absorption by the underlyingpavement surface and the aggregate being used. Contemporary design practices need to determine binder application rated based on surface characterization,

    64

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    65/74

    absorption factors, traffic condition, climate consideration, aggregate selection, and the type of chip seal being constructed. Another important discovery is that all methods have a design objective for embedment to be between 50% and 70%of that seal's depth. Best practices for chip seal design are difficult to isolate, because there appears to be such a large variation in practices from agency toagency. However, the following can be identified as meeting this project's definition for best practices:

    Chip seal perform best only on roads with low underlying surface distress that will benefit from this technology. The international practice is to characterizethe underlying road's texture and surface hardness and use that as a basis for developing the subsequent formal chip seal design. Where the local council responses indicated a routine use of qualitative characterization in the design process.Thus, the next logical enhancement would be to incorporate international methods to quantitatively characterize the underlying surface in the chip seal designprocess. One of those enhancements would be to try using the racked-in seal as the corrective measure for bleeding instead of spreading fine aggregate and sandon the bleeding surface.

    65

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    66/74

    CHAPTER 5

    CONCLUSION

    5.2

    CONCLUSION

    The conclusion in this area is quite evident. First, the selection of chip sealmaterials is project dependent, and the engineer in charge of design must fullyunderstand not only the pavement and traffic conditions in which the chip seal will operate but also the climatic condition under which the chip seal will be applied. It appears that the widespread use of emulsion binder chip seal results from the nation that emulsion are less sensitive to environmental conditions during construction. Additionally, as emulsions are installed at a lower binder temperature they are probably less hazardous to the construction crew. Binder performance can be improved through the use of modifiers such as polymers and crumb rubber.

    66

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    67/74

    Next, the selection of the binder is dependent on the type of aggregate that iseconomically available for the chip seal project. In other way, we could to bearadditional aggregate costs to ensure the quality of their chip seals are something that should be seriously considered in this area.

    The aggregate should be checked to ensure that electrostatic compatibility is met with the type of binder specified. Also pre-coating of the aggregate appears t

    o be required for use with hot asphalt cement binders to ensure good adhesion after application. Finally, it appears that the use of geotextile-reinforced chipseal is promising and should be considered for those roads that have more than normal surface distress and for which an overlay is not warranted. Therefore, several next practices can be extracted from the foregoing discussion: Conduct electrostatic testing of chip seal aggregate source before chip design to ensure that the binder selected for the project is compatible with the potential sources of aggregate. Specify a uniformly graded high-quality aggregate. Consider using lightweight synthetic aggregate in areas where postconstruction vehicle damage isa major concern. Use life-cycle cost analysis to determine the benefit of importing either synthetic aggregate or high-quality natural aggregate to areas whereavailability of high-quality aggregate is limited. Use polymer-modified binders

    to enhance chip seal performance

    67

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    68/74

    5.1

    SUGGESTION

    Since the failed pavement been identified and the sand patch method carried out,the design using chip seal method have been analyzed. So the best ways to solvethose pavement failures are through the chip seal method, this is because of fe

    w concrete reasons which are:More durable and long lasting Protect and preservethe pavement from heavy climate weather Extend pavement life

    Basically chip sealing is a common pavement preservation tactic that prevents water from seeping into an asphalt pavement

    s base course and sub-grade, while improving skid resistance and rehabilitating weathered asphalt surfaces. This assessment has found that chip seal practices can be instituted that will improve thereliability of maintenance chip seals. Many of the best practices identified fell in the areas of construction procedures and equipment management practice. This is not surprising, in that construction is the most critical portion of the chip seal project life cycle.

    The area that apparently been surveyed which is Parit Jelutong has the greatestpotential for enhancement is chip seal design. This is also the area in which advancements in technical understanding will have the greatest potential to dispelthe view that the use of chip seals is merely an art. The major issue in chip seal design lies in accurately characterizing the surface on which the seal willbe applied, through using engineering measurements of macro-texture and hardness.

    68

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    69/74

    APPENDIX

    Measuring Distance

    Length of 1km taken

    Cone Been Placed

    Sand Patch Circle

    Patching To a Circullar Shape

    Sand Patch Diameter Taken

    Collecting Back The Sand

    69

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    70/74

    Shoving

    Edge Drop-off

    Pothole Crocodile Crack

    Longitunal Crack

    Cracking

    70

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    71/74

    Length of Crack Measured

    Transverse Crack

    Pothole

    Longitunal Crack

    Aligator Crack

    Tranverse Crack

    71

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    72/74

    Edge Crack

    Pothole Depth Measured

    Block Crack

    Crack Length Measured

    72

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    73/74

    REFERENCES

    Garber N.J. and Hoel L.A. Traffic & Highway Engineering (3rd Edition). US: Brooks/Cole Norman Edwards, Peter Keys (1996), Singapore - A Guide to Buildings, Streets, Places, Times Books International, Victor R Savage, Brenda S A Yeoh (2003),Toponymics - A Study of Singapore Street Names, Eastern Universities Jones, KenD., Arthur F. McClure and Alfred E. Twomey. The Types Road Failures. New York:

    Castle Books, 1970. Small, Kenneth A.; Jos A. Gomez-Ibaez (1998). Road Pricing forCongestion Management: The Transition from Theory to Policy. The University ofCalifornia Transportation Center, University of California at Berkeley. pp. 213.John Shadely, Acoustical analysis of the New Jersey Turnpike widening project between Raritan and East Brunswick, Bolt Beranek and Newman, 1973 Michael Hogan,Highway Noise, 3rd Environmental Pollution Symposium

    73

  • 8/10/2019 43047421 Project Pavement Condition Survey at Parit Jelutong Batu Pahat Johor

    74/74