environmental management programme (empr) for the … · environmental management programme (empr)...
TRANSCRIPT
Environmental Management Programme
(EMPr) for the proposed construction of the new 88kV Kashan Substation with associated power line and access road to the existing Hekpoort Substation.
Report Prepared for
Eskom Holdings SOC Ltd
Report Number 465044
Report Prepared by
January 2015
SRK Consulting: 465044 EMPr Kashan Page i
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Environmental Management Programme
(EMPr) for the proposed construction of the new Eskom 88kV Kashan Substation with associated power line and access road to the existing Hekpoort Substation.
Eskom Holdings SOC Ltd
SRK Consulting (South Africa) Pty Ltd. Block A, Menlyn Woods Office Park
291 Sprite Avenue
Faerie Glen
Pretoria 0081
South Africa e-mail: [email protected] website: www.srk.co.za
Tel: +27 (0) 12 361 9821 Fax: +27 (0) 12 361 9912
SRK Project Number 465044
February 2015
Compiled by: Peer Reviewed by:
Fiona Evans Environmental Scientist
Andy Smithen Partner
Email: [email protected]
Authors:
Fiona Evans; Linda Poll-Jonker; Manda Hinsch
SRK Consulting: 465044 EMPr Kashan Page ii
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Executive Summary The purpose of the Environmental Management Programme (EMPr) is to provide the mitigation and
management measures required to ensure that social and environmental impacts, risks and liabilities
identified during the Environmental Impact Assessment (EIA) process are effectively managed
during the construction and operations of the proposed Kashan substation and associated power line
connection to the existing Hekpoort substation. The construction of the substations will minimise the
voltage and performance constraints and allow for future connections and development in the area.
Summary of principal objectives
The key objectives of this EMPr are to:
Determine environmental and social impact mitigation and management measures to minimise
the impact of the proposed substations and associated power lines;
Formalise and disclose the programme for the environmental and social management of impacts
of the proposed substations and associated power lines;
Ensure compliance to environmental legislation and guidelines which may be local, provincial
and / or national;
Ensure sufficient resources are allocated on the project budget so that the scale of the EMPr
related activities are consistent with the significance of the identified environmental and social
impacts of the substations and associated power lines;
Provide feedback for continual improvement in environmental performance; and
Provide a framework for the implementation of environmental and social management initiatives.
Key Definitions and Abbreviations Used in this EMPr
Key definitions used in this EMPr are listed in Table 1-1.
Table 1-1: Key Definitions and Abbreviations Used in this EMPr
Term Definition
C Construction phase (in mitigation table).
Contractor Any provider of services, goods or people to Eskom for the purpose of the proposed development. These may directly or indirectly include contractors, sub-contractors, hired labour agencies and consultants. All contracted are required to draft and abide by a contractor specific EMP in line with the EMPr.
DEA Department of Environmental Affairs.
DWS Department of Water and Sanitation
Environmental Consultant An independent environmental consultant with experience in the assessment of environmental impacts associated with the proposed project, identification of appropriate and reasonable mitigation and management measures, and able to draft the EMPr applicable to the management of construction, operation and decommissioning and closure activities.
ECO Environmental Control Officer: The ECO is appointed by Eskom to ensure compliance to the EMPr and conditions of the EA during construction and provides proof of compliance documentation to the Project Management Team, and authorities, where required.
EIA Environmental Impact Assessment: The assessment of changes in the environment, whether adverse or beneficial, wholly or partly, resulting from the proposed activities associated with a project.
EA Environmental Authorisation: allows for the organisation to commence/continue with activities applied for in the EIA process as authorised in terms of Section 24 of NEMA.
SRK Consulting: 465044 EMPr Kashan Page iii
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Term Definition
Environmental management Eskom employees that deal with environmental considerations in the management cycle of the Project, i.e. policy, planning and design, implementation (preconstruction, construction and operation), monitoring and corrective action and review.
EMPr Environmental Management Programme.
ERP Emergency response plan
Eskom Eskom Holdings SOC Ltd
GDARD Gauteng Department of Agricultural and Rural Development.
IFC International finance corporation.
Incident An undesired event that may result in an environmental, although can be managed through internal response and procedures.
I&APs Interested and affected parties: Any person who is directly or indirectly affected by the proposed project.
NWREAD North West Department of Rural, Environment and Agriculture Development.
NWPHRA North West Provincial Heritage Resources Authority
O Operational phase (in mitigation table).
PC Pre-Construction phase (in mitigation table)
Project Management Team The responsibility of the EMPr implementation resides on this team. This team may include a Project Manager and Section Leader and appointed contractors and consultants, including the ECO.
Programme Identifies a series of interrelated measures (often contained in detailed plans) for managing the environmental effects of the proposed project. A programme provides broad direction and covers more than one project phase.
PPP Public Participation Programme.
SAHRA South African Heritage Resources Agency.
SHE Safety, Health and Environment.
SHE officer A representative from each contractor, appointed as a Safety Health and Environmental Officer, assisting the construction manager on Safety, Health and Environmental aspects of the project on the construction site.
SRK SRK Consulting SA (Pty) Ltd.
TOPS Threatened or Protected Species specified by the NEM: Biodiversity act (2004).
SRK Consulting: 465044 EMPr Kashan Page iv
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Table of Contents Executive Summary ..................................................................................................................................... ii
1 Introduction .................................................................................................................. 1
1.1 Background ......................................................................................................................................... 1
1.2 Objectives of the Management Programme for the Substations and Power lines ............................. 2
1.3 Expertise of Authors of the EMPr ........................................................................................................ 3
1.4 Approach to Environmental Impact Management ............................................................................... 3
2 Organizational Structure and Responsibilities .......................................................... 4
2.1 The Project Management Team ......................................................................................................... 4
2.1.1 Project Manager ...................................................................................................................... 4
2.1.2 The Contractor (Including Sub-Contractors) ........................................................................... 4
2.1.3 The Environmental Control Officer .......................................................................................... 5
2.1.4 The Safety, Health and Environmental Officer of Eskom ........................................................ 5
3 The Proposed Substations and Associated Power Lines ......................................... 6
3.1 Planning and Design ........................................................................................................................... 6
3.2 Pre-construction and Construction ...................................................................................................... 6
3.3 Operation ............................................................................................................................................ 7
3.4 Closure ................................................................................................................................................ 7
4 Auditing and Corrective Action ................................................................................... 7
5 Site Documentation and Reporting ............................................................................. 8
6 Monitoring ..................................................................................................................... 8
7 Environmental Awareness Plan .................................................................................. 9
8 General Requirements ................................................................................................. 9
9 Management Review .................................................................................................... 9
Appendix A: Team CVs ................................................................................................... 21
Appendix B: Eskom Management Standards ................................................................ 22
List of Tables and Figures Table 1-1: Key Definitions and Abbreviations Used in this EMPr ................................................................. ii
Table 1-2: Approach to Impact Management ................................................................................................ 3
Table 9-1: Environmental Management Programme for the proposed Substations and associated Power line route. ................................................................................................................................... 10
Figure 1-1: The locality of the proposed Kashan substation and associated Powerline alternatives ................ 1
SRK Consulting: 465044 EMPr Kashan Page 1
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
1 Introduction
1.1 Background
Eskom is in the process of expanding their power supply grid by supplying additional substations to
areas in need of additional capacity and supplying electricity to areas with increasing electricity
demand in the North West and Gauteng Province.
The proposed project includes the construction of a new substation in Kashan and a power line of
approximately 13 km to the existing Hekpoort Substation. The proposed Kashan Substation falls
within the Gauteng Province, north-west of Krugersdorp and it is intended to alleviate the power
supply demands experienced by Eskom in the area and to provide electrical infrastructure for future
development.
The proposed Kashan Substation will occupy a footprint of approximately 1.2 ha and will be
connected to the existing Hekpoort Substation via an 88 kV power line which runs approximately 13
km in a north easterly direction from Kashan (Gauteng Province) into the North West Province.
There are two proposed alternative routes for the power line which are indicated in Figure 1 below.
It is for this reason that Eskom propose to construct the following infrastructure the detail can be
seen in Figure 1-1:
Figure 1-1: The locality of the proposed Kashan substation and associated Powerline alternatives
SRK Consulting: 465044 EMPr Kashan Page 2
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
The purpose of the EMPr is to provide the mitigation and management measures to ensure that
social and environmental impacts, risks and liabilities identified during the Environmental Impact
Assessment (EIA) process are effectively managed during the construction, operations and closure
of the proposed Kashan substation and associated power line. The construction of the substations
will minimise the voltage and performance constraints and allow for future connections and
development in the area.
The EMPr specifies the mitigation and management measures to which Eskom is committed, should
the Environmental Authorisation (EA) be granted, and shows how Eskom will mobilise organisational
capacity and resources to implement these measures. The EMPr also shows how management
measures aimed at mitigation and enhancement will be scheduled.
1.2 Objectives of the Management Programme for the Substations and Power lines
The key objectives of the EMPr are to:
Formalise and disclose the programme for environmental and social management;
Ensure compliance to national and provincial environmental legislation and guidelines.
Ensure sufficient resources are allocated on the project budget so that the scale of the EMPr related activities are consistent with the significance of project impacts;
Provide feedback for continual improvement in environmental performance; and
Provide a framework for the implementation of environmental and social management initiatives.
Good practice , guided by the principals set out in the NEMA (Act 107 of 1998) section 2, require that
every reasonable effort be made to reduce and preferably to prevent negative impacts, while
enhancing positive benefits, especially within the communities most directly affected by the proposed
development. These principles have been guided the EIA process.
The EMPr has been compiled on the basis of the outcome of work undertaken during the EIA
process and represents legally binding management commitments of Eskom, should the
Environmental Authorisation (EA) be issued by the competent Authorities. The EIA process has
involved concurrent and on-going data collection and public consultation activities to date.
Work underpinning the EMPr, which has been compiled in adherence to the EIA regulatory
requirements, as prescribed by GN R. 543 dated June 2010, includes the following:
Public participation programme (PPP) as stipulated in Regulation 54 – 57 of GN R. 543; and
Preparation of a draft BAR in accordance with Regulation 22 and this EMPr in accordance with Regulation 33 of GN R. 543, for review and comment by Interested and Affected Parties (I&APs).
The EMPr covers information on the management and/or mitigation measures that will be taken into
consideration to address identified biophysical, social, and cultural impacts in respect of:
Pre-construction and Construction activities; and
Operation; and
Closure and rehabilitation, where relevant.
It should be noted that the EMPr is a dynamic document that will be periodically reviewed and
updated. It will also be necessary to update the version presented in the final BAR during the
detailed design phase, prior to the commencement of construction. As part of on-going
implementation, this EMPr will also be publicly disclosed during the PPP. An opportunity will be
offered to participating stakeholders to comment on it.
SRK Consulting: 465044 EMPr Kashan Page 3
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
1.3 Expertise of Authors of the EMPr
This EMPr was prepared by Fiona Evans and Linda Poll-Jonker under technical guidance of Manda
Hinsch, and reviewed by Andy Smithen.
Fiona Evans is an Environmental Consultant with SRK Consulting (Pty) Ltd (SRK). She has an
Honours degree in Ecology, Environment and Conservation obtained from the University of the
Witwatersrand, and has one years of project experience in environmental management. Fiona has
both personally prepared and given input to various EMPrs.
Linda Poll-Jonker is a Senior Environmental Consultant at SRK with over 7 years’ experience. Linda
has been involved with management and compilation of documentation required for the application
processes for Environmental Authorisation under NEMA. She has compiled EIAs and EMPrs in
terms of the MPRDA and compiled a number of integrated water use licences applications and
integrated water and waste management plans in terms of the NWA.
Manda Hinsch is an Associate Partner and Principal Environmental Scientist with SRK and has 31
years of experience in water quality management, waste management, project management and
water and environmental legislation. Manda is a member of the Professional Natural Scientists South
Africa and FWISA.
Andy Smithen is a Partner Andy Smithen has been involved in the field of environmental engineering
for the past 26 years. His expertise includes: compilation of EIAs and Environmental Management
Plans for numerous mines, closure planning and costing, assessment of environmental risk for
operating mines and redundant operations, environmental due diligence and liability assessments
and environmental auditing. Andy has also been involved in the development of risk based decision-
making methodologies and has assisted in the development of water management plans.
The project team collectively possesses the core competence required to prepare the EMPr for the
proposed project. For more information pertaining to the qualifications and expertise of the project
team, refer to Appendix A.
1.4 Approach to Environmental Impact Management
The responsibility for the implementation of the EMPr will ultimately reside in the Eskom project
management team for the proposed substations and associated power lines as representatives of
the holder of the Environmental Authorisation (EA). There will be links with other fundamental units
such as Safety, Health and Environmental (SHE) officers of Eskom, operational and maintenance
services.
The sections that follow outline the management cycle and responsibilities of the Project
Management Team. Table 1-1: illustrates the range of approaches to be undertaken to
appropriately mitigate and manage potential environmental impacts that have been identified during
the EIA Phase of the project, for the construction, operation and decommissioning and closure
phases of the proposed substations and associated power lines.
Table 1-1: Approach to Impact Management
Avoidance Avoiding activities that could result in adverse impacts and/or resources or areas considered sensitive.
Prevention Preventing the occurrence of negative environmental impacts and/or preventing such an occurrence having negative impacts.
Preservation The process of working to protect something valuable so that it is not damaged or destroyed i.e. environmental resources)
Minimization Limiting or reducing the degree, extent, magnitude or duration of adverse impacts through scaling down, relocating, redesigning and/or realigning elements of the project.
SRK Consulting: 465044 EMPr Kashan Page 4
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Mitigation Measures taken to minimise adverse impacts on the environmental and social aspects.
Enhancement Magnifying and/or improving the positive effects or benefits of a project.
Rehabilitation Repairing affected resources to their original state.
Restoration Restoring affected resources to an earlier (possibly more stable and productive) state, typically ‘background’ condition, where identified to be appropriate and reasonable. These resources may include soils and biodiversity.
2 Organizational Structure and Responsibilities
2.1 The Project Management Team
The project management team consists of the project manager, the contractor, the environmental
control officer (ECO) and the SHE officer of Eskom. The roles of these team members are discussed
under separate sub headings below.
2.1.1 Project Manager
The project manager, assisted by the ECO, will be responsible for the co-ordination of the project
management team. With the assistance of the ECO he/she will be required to:
Familiarise themselves with the EMPr for the substations and associated power lines, and the
conditions set out in the EA, and relevant environmental legislation as identified in the Final
Basic Assessment Report (BAR). Information packs will be distributed to the Project
Management Team by the ECO and transmittal notes will be kept on file.
Ensure that the contractors are aware of the specifications, legal constraints and Eskom
standards and procedures pertaining to activities taking place regarding the proposed
substations and associated power lines, by reference to the conditions of the EMPr and EA that
have been inserted into their service contract by Eskom;
Ensure that all commitments/conditions in the EMPr are communicated and adhered to by
relevant Eskom employees and contractors involved with the proposed development, by making
the documents available to relevant employees and contractors and including the requirements
into the induction programme for the proposed substations and associated power lines.
2.1.2 The Contractor (Including Sub-Contractors)
The contractor and sub –consultants will be responsible for the implementation of the contractor
specific EMP the Safety Health and Environment (SHE) Plan and Eskom’s Emergency Response
Plan (ERP) attached in Appendix B. The contractor specific EMP should be guided by a Risk
Register informed by Risk Assessments of hazards identified by the contractor to be associated with
the day to day tasks during the construction programme.. The contractor specific EMP must be
guided by a Risk Register informed by Risk Assessments of hazards identified by the contractor to
be associated with the day to day tasks during the construction programme. The SHE Plan and the
ERP must be associated with the day to day tasks by the project team and the ECO. The ERP must
be appropriate for any potential emergency.
The contractor and all sub-contractors will be responsible for:
Complying with the EMPr commitments and any other legislative requirements as applicable to
the contractors appointment for the proposed substations and associated power lines;
Drafting a method statement (contractor specific EMP) appropriate to the day to day activities
under his direct control. The method statement must abide by the EMPr. The Contractor specific
EMP must be agreed upon, by the Project Team representatives and the ECO, for the activities
to be undertaken by the contractor;
SRK Consulting: 465044 EMPr Kashan Page 5
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
the Risk Assessments are agreed to be appropriate for the tasks by the Project Team
representatives and the ECO, as appropriate;
Adhering to any instructions issued by the Project Manager, and/or other designated lead agent
administering the contract, on advice of the Eskom environmental specialist and ECO;
Submitting an environmental report at identified site meetings on the environmental incidents
that have occurred within the period between site meetings, and reporting on action to address
any incidents previously identified by the contractor or the Project Team, the ECO or Eskom
representatives;
Ensuring that all employees of the contractors, and Eskom employees as may be involved in the
construction programme, receive appropriate training prior to the commencement of
construction, taking cognisance of this EMPr and the conditions of the EA.
2.1.3 The Environmental Control Officer
An ECO will be appointed to provide ECO inputs during the construction phase of the proposed
substations and associated power lines. During the operational phase these functions will be taken
over by the SHE Department of Eskom. The ECO will be appointed by Eskom and not the
contractor and will report directly to Eskom.
The ECO will:
Fully understand the commitments in the EMPr and EA for the proposed substations and
associated power lines.
Familiarise him / herself and ensure compliance with the relevant legislation applicable to the
project ESKOM SHE Policy and procedures;
Communicate the contents of the EMPr to the contractor and sub-contractor staff members;
Monitor the implementation of the EMPr throughout the project, by means of site inspections,
reporting to Eskom and the Project Team at progress meetings;
Undertake site inspections, on a weekly basis, to assess compliance with the EMPr and
conditions in the EA and to advise on appropriate action to rectify non – compliances;
Recommend to Eskom the removal of personnel and / or equipment should they contravene the
specifications of the EMPr;
Liaise with environmental statutory bodies, including Gauteng Department of Agricultural and
Rural Development (GDARD), North West Department of Rural, Environment and Agricultural
Development (NWREAD), Department of Environmental Affairs (DEA), and Department of Water
and Sanitation (DWS), where this is deemed necessary in association with the Project Team
and/or Eskom personnel;
Compile monthly progress reports for submission to the Project Manager; and
Advise the Project Management Team on environmental issues and recommendations for the
proposed substations and power lines construction activities.
2.1.4 The Safety, Health and Environmental Officer of Eskom
The SHE Officer will:
Monitor to ensure that all aspects of the construction and operation of the proposed substations
and power lines comply with the requirements of the SHE plan of Eskom;
Be responsible for ECO duties during the operation;
Ensure corrective actions required to address identified impacts are followed up and closed out.
SRK Consulting: 465044 EMPr Kashan Page 6
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
3 The Proposed Substations and Associated Power Lines
3.1 Planning and Design
No impacts have been identified during this phase therefore no management and mitigation
measures have been considered for this phase of the proposed development.
3.2 Pre-construction and Construction
The EMPr provides for mitigation and management measures to avoid or minimise negative impacts
and optimise the benefits arising from the positive impacts during construction activities. The
primary focus on project management for the construction phase will include:
Communicating the construction programme and activities to Stakeholders prior to activities
commencing, particularly community members as they may be affected by the construction
activities.
Delineation of servitudes for the power line route.
Establishment of contractor camps for site offices, change-rooms, local workshops, vehicle
parking, ablutions, materials storage, waste storage, and communications etc.
Establishment of security measures for the construction activities and the substations and power
line routes, including, but not limited to, the construction of palisade fencing for the substations,
and fencing and lighting of contractor’s operational areas (camp/s and materials storage areas
etc.).
Transportation of equipment and machinery to the construction site locations.
Stripping and removal of surface vegetation from the substation sites and the designated route
of the power line.
Stripping and stockpiling of topsoil and sub soil from the substation sites and the designated
route of the power line to a stockpile/s for later use for rehabilitation and landscaping.
Grading and earthworks that will be conducted at the substation sites and along the power line
construction footprint.
Sourcing of construction material.
Construction and commissioning of the substations and power lines according to the agreed
programme.
Development of construction environmental management procedures.
Transportation of equipment, material, and people.
Construction of watercourse crossings.
Erosion control and pollution control.
Site rehabilitation following the construction phase, of areas that have been disturbed and are
not part of the on-going operational phase of the proposed substations and associated power
lines.
Stripping and stockpiling of topsoil and sub soil from the substation sites and the designated
route of the power line to a stockpile/s for later use for rehabilitation and landscaping.
Monitoring and maintenance of rehabilitated areas.
Some potential impacts are difficult to monitor quantitatively, such as soil erosion and waste
management. However this on–going, but pragmatic, inspection regime must be developed, and will
be updated once the detailed project programme is confirmed. The finalised version must allow for
potential environmental transgressions to be identified proactively so that mitigation can be quickly
and effectively implemented to an appropriate level.
SRK Consulting: 465044 EMPr Kashan Page 7
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
3.3 Operation
The primary operation of the proposed substations and associated power lines will be to supply and
distribute electricity to the Hekpoort area. The primary focus on project management for the
operational phase will include:
Development of operational phase environmental management procedures.
Operation of the substations and power lines for 24 hours a day under normal circumstances,
adjusted according to the operation and maintenance programme for Eskom, and maintenance
programme for the substations and power lines.
Fortnightly inspections of the substations and power lines for anomalies, spillage, vandalisms,
copper wire theft etc. as these may affect the operation of the substations and power lines.
Maintenance and repair of the substations, power lines and associated infrastructure will be
undertaken throughout the operational phase according to a designated maintenance
programme, as informed by the specifications of the electrical technology supplier, as well as
Eskom’s existing maintenance and servicing regimes.
3.4 Closure
Due to the permanent nature of the proposed development, a closure and rehabilitation phase is not
envisaged. In the event where closure and decommissioning is necessary, rehabilitation must be
done in accordance with the relevant guidelines and legislation.
4 Auditing and Corrective Action Auditing and implementing corrective action, should it be required, forms an important component of
the EMPr management cycle. These ensure that:
The required EMPr management conditions are being implemented, and reported appropriately;
The desired outcomes are being achieved;
On–going inspections of operational controls and general state of operation are undertaken and
reported appropriately;
Two internal audits must be undertaken during construction to assess the compliance to the
EMPr or to focus on particular performance issues in relation to the conditions of the EA.
One external audit by an independent practitioner must be undertaken four months after the
commencement the construction phase to assess the compliance to the EMPr or to focus on
particular performance issues in relation to the conditions of the EA.
Annual internal audits during the operational phase must be conducted internally in order to
assess the compliance to the conditions in the EMPr and the EA.
As noted above, some potential impacts are difficult to monitor quantitatively, such as soil erosion
and waste management. However an on–going, but pragmatic, inspection regime has been
developed, and will be updated once the detailed project programme is confirmed, that must allow
for potential environmental transgressions to be identified proactively so that mitigation can be
quickly and effectively implemented to an appropriate level.
There are several mechanisms for implementing corrective action both during construction and
operational phases. The main instruments used to address non-compliances are the following:
Verbal instructions – Minor transgressions to the EA and EMPr by the ECO and Project
Management Team;
Written instructions – To support and formalise verbal instructions by the ECO and Project
Management Team;
SRK Consulting: 465044 EMPr Kashan Page 8
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Contract Notice – Following a material breach in contract issued by the Project Management
Team;
Directive from Regulating Authority – Following a material non-compliance with the conditions of
the EA and the EMPr
5 Site Documentation and Reporting All non-conformances will be recorded by the ECO and reported to the Project Manager on a
monthly basis during the construction phase. Monthly inspections will be undertaken under taken by
the Environmental Advisor from SHEQS and the Technical Operator of the infrastructure.
The following documentation will be required to be kept at Eskom:
Project EA;
Project EMPr;
Project Programme;
Project Risk Register;
Project SHE Plan;
Complaints register;
Environmental Incident Register;
Audit reports of compliance and non – compliance to EMPr and EA conditions;
Written corrective action instructions;
Proof that incidents and non – compliances have been closed out appropriately.
The findings of all inspections and internal audits will be structured into instructive reporting provided
to the Project Manager. Corrective actions must be clearly defined as appropriate and reasonable,
where required.
Emergency procedures for the management of the proposed development during all phases of
operation must be in line with Eskom’s relevant ERP.
Within the reporting function a structured review component will be required from the Project
Management Team. This review function will assist in prescribing appropriate and reasonable
corrective actions, and ensuring their timeous implementation.
6 Monitoring During the construction phase, the ECO will be responsible for monitoring and inspecting
contractors’ written records to illustrate compliance with the EMPr. This falls under the inspection
role of the ECO.
The aim of the compliance monitoring is to verify that the responsible parties are adhering to the
procedures, management conditions, and specifications contained in this EMPr and the conditions
set out in the EA. A monthly inspection report will be submitted to the project manager during the
construction phase.
The ECO will regularly monitor their programme implementation for the proposed development. This
will include the regular monitoring of:
Control of alien vegetation associated with the cleared power line routes by the contractor;
The contractors waste management programmes used to manage the generation of waste
requiring disposal; and
Rehabilitation of the construction sites, post construction.
SRK Consulting: 465044 EMPr Kashan Page 9
EVAF/POLL//HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
7 Environmental Awareness Plan On-site training must be provided for all contractors and personnel working on site during
Construction and operation. No personnel may be allowed onto site without having been instructed
on the requirements of the approved EMPr.
The training must deal specifically with triggers that would require the implementation of mitigation
measures contained in the EMPr. These include, but are not limited to:
Identification of TOPS listed species, both fauna and flora
Identification of potential heritage resources
Identification and avoidance of demarcated no-go areas
Substation site access and security.
8 General Requirements Monthly meetings to be held to ensure proper and continuous liaison between Eskom and the
contractors to make certain everyone is informed at all times;
Eskom will compile and implement a physical access plan and the contractor shall adhere to this
plan at all times, unless agreed with the Project Manager;
The contractor must adhere to all conditions of the EMPr that are applicable to the construction
phase activities that are the express responsibility of the contractor;
Eskom must adhere to all conditions of the EMPr that are applicable to the construction phase
activities that are the express responsibility of Eskom;
The contractor will implement Eskom’s existing ERP focusing on environmental emergencies
including: major hydrocarbon spills, watercourse pollution, extensive erosion, flooding and
rehabilitation of no – go areas disturbed as a result of construction phase activities of the
proposed substations and associated power lines;
Implementation of good housekeeping principles;
Documentation and record keeping of all complaints / incidents and actions taken in line with
EMPr requirements;
Fortnightly site inspections throughout the construction period; and
The contractor shall not be released from site until the Project Manager in consultation with the
ECO has signed off the release documentation and is satisfied with the contractor’s adherence
to the EMPr.
The general environmental management requirements, with responsibilities and time frames, are
provided in Table 9-1.
9 Management Review The purpose of the management review is for the Project Manager and the Project Management
Team to review the EMPr, and to propose measures for improving the performance in the spirit of
continuous improvement, and as issues and aspects are identified during the operational phase.
SRK Consulting: 465044 EMPr Kashan Page 10
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Table 9-1: Environmental Management Programme for the proposed Substations and associated Power line route.
Ref no Measure, criteria or principles Monitoring
Partner
Time frame Phase
General
1. An ECO will be appointed who will have responsibility for ensuring compliance with the EMPr
throughout the life of the operations.
Eskom Project
Manager
Prior to the start
of the project
PC
2. Annual audits will be conducted to ascertain compliance with the EMPr and Environmental
Authorisation should it be granted.
ECO Annually All
3. Existing management practices for Eskom’s operations must be applied to each proposed substation
and associated power line.
ECO On-going All
4. Informal fires by construction or Eskom personnel during any phase of the project will be prohibited. ECO On-going All
5. Emergency firefighting equipment must be made available at the proposed substations. ECO On-going C/O
Soil and Land Use
6. Soil must only be stripped from areas to be disturbed during construction or maintenance. Eskom/contractors When
applicable
C/O
7. It will be ensured that erosion controls are included in the designs of linear infrastructure. Eskom During design PC
8. Vehicles must be restricted to travelling only on designated roadways, as far away from the wetland
areas as possible to limit the ecological footprint of the proposed development activities.
ECO On-going C/O
9. All disturbed areas must be rehabilitated, using stockpiled soil as required. A final rehabilitation plan
must be compiled towards the end of the construction period.
SRK Consulting: 465044 EMPr Kashan Page 11
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Ref no Measure, criteria or principles Monitoring
Partner
Time frame Phase
Biodiversity
10. Compliance in accordance with Eskom's existing Land and Biodiversity Standard (Appendix C) as well
as Eskoms Vegetation Management Standard (Appendix C) shall be maintained and monitored on an
annual basis.
ECO Monthly
monitoring
during
construction
All
11. The extent of the construction site must be demarcated and no vegetation is to be removed outside of
this zone.
ECO Before and
during
construction
C
12. Should any of the threatened or protected species (TOPS), identified in the Biodiversity impact
assessment, be found during construction; protection must be carried out in accordance to NEMBA
(Act 10 of 2004) Chapter 4, Part 2. This will include any amendments or changes to regulations and
guidelines pertaining to the protection of TOPS.
ECO On-going PC
13. An alien eradication and management program must be developed. Eradication and monitoring must
be undertaken monthly during the construction phase and yearly during the operational phase.
ECO Fortnightly
Or Monthly
C/O
14. If herbicides need to be used to control the spread of invasive plants, only herbicides approved by the
National Department of Agriculture should be used.
Eskom When
applicable
PC/C
15. No trapping or hunting of fauna must be allowed by construction- or Eskom personnel during any
phase of the project.
ECO On-going All
16. Install bird flaps and diverters on the erected power lines to help mitigate the bird collisions with the
power lines.
Eskom During power
line alignment
C
17. River banks and other ecologically sensitive areas must be rehabilitated, in consultation with a
specialist, where they have been damaged once construction in that particular area is complete.
ECO Upon
completion of
construction or
maintenance in
an area.
All
Visual
SRK Consulting: 465044 EMPr Kashan Page 12
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Ref no Measure, criteria or principles Monitoring
Partner
Time frame Phase
18. All topsoil removed from the site, prior to construction activities, must be stored for rehabilitation
purposes at the site.
ECO When
applicable
PC
19. The natural vegetation (trees and shrubs) around the site must be retained to provide screening for the
construction equipment/vehicles, except where their removal is unavoidable for construction to
proceed.
ECO On-going C/O
20. If vegetation is to be cleared on site, erosion control measures must be kept in place to ensure that
excessive scarring of the landscape is reduced.
ECO When
applicable
C
21. Construction activities must be restricted between the hours of 7:30 – 18:00. Eskom – Project
Manager
When
applicable
C
22. Investigation into the establishment of vegetation and/or the construction of man-made barriers
between the sensitive viewers and the proposed development (i.e. the proposed substation sites) must
be undertaken during the construction and operational phases.
ECO On-going C/O
23. During construction, litter control measures must be kept in place to ensure that the site is maintained
in a neat and tidy condition.
ECO On-going C/O
24. During construction, dust control measures must be implemented to ensure that undue interest is not
drawn to the site.
ECO On-going C
25. External signage must be kept to a minimum, and where possible must be attached to existing
structures, to avoid free-standing signage.
ECO When
applicable
C/O
26. Low foot level lighting must be used where it is deemed safe. Contractor On-going C
27. Where possible, lighting must be faced / shielded inward away from the viewers. ECO/Contractor On-going O
Heritage
28. If any new artefacts of archaeological or cultural interest are found, including graves, then the area will
be marked and all activities in that vicinity will cease with immediate effect. SAHRA and the North
West Provincial Heritage Resources Authority (NWPHRA) will be notified of the finding and operations
at that specific site will only continue after the relevant permissions have been granted to do so.
ECO On-going All
SRK Consulting: 465044 EMPr Kashan Page 13
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Ref no Measure, criteria or principles Monitoring
Partner
Time frame Phase
29. The identified graveyard sites (as documented in the Basic Assessment report) must be noted along the proposed power line route must be fenced off with access gates installed.
ECO Before
construction
PC
30. The location of the identified historical sites (as documented in the Basic Assessment report) must be noted prior to the start of the construction phase and pylons must be positioned so that any impact on the identified historical sites is avoided.
ECO Before
construction
PC
Surface and ground water
31. Construction may not commence without a Water Use License being issued by the Department of Water and Sanitation. Any conditions attached to such
32. Adequate storm water management must be incorporated into the design of the power line route and the sub-station site in order to prevent erosion. In this regard special mention is made of the installation of drift fences to capture silt
Eskom On-going PC
33. Provision of appropriate sewage facilities during the construction phase (one toilet for 15 staff members). These must be located within the footprint construction area.
ECO When
Applicable
C
34. Toilets provided for staff members must be cleaned twice a week. ECO Biweekly C/O
35. Reinforce banks and drainage features where necessary with gabions, reno mattresses and geotextiles
Contractor At the start of
construction in
an active water
course.
C
36. Stripping and clearing of vegetation must ideally be planned to be done during the dry season (March -
August).
ECO During
construction
C
37. Ensure that erosion control measures are included in the method statement for construction of the
substations and associated power lines, particularly if stripping and clearing of vegetation is likely to
occur during the wet season (September - April)
ECO Stripping and
clearing during
the Wet season
C
38. Spillage or leakage of materials and wastes should be reported to the project manager and cleaned up
within 24 hours.
ECO Within 24 hours
of the spillage
C/O
39. Incidents relating to the contamination of surface water will be communicated to Eskom Management,
and then reported to DWA, depending on significance and risk rating.
ECO Within 2 weeks
of the incident
occurring
C
SRK Consulting: 465044 EMPr Kashan Page 14
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Ref no Measure, criteria or principles Monitoring
Partner
Time frame Phase
40. Should any construction activities occur within a 1 in 100 year flood line or within 500 m of a wetland,
relevant authorisation should be obtained according to the National Environmental Management Act
(NEMA) 107 of 1998 and Section 21 c and i of the National Water Act 36 of 1998.
ECO When
applicable
PC/C
41. No support structures should be constructed within the riparian areas or within the active stream
channel. If at all possible all support structures should be developed above the 1:100 year, or, if that is
not possible, above the 1:50 year flood line.
ECO/Eskom Planning and
Design
PC
42. Wetland areas in the vicinity of construction works must be fenced for the duration of the construction
phase and designated a ‘no-go’ area.
ECO When
applicable
C
43. During the construction and operational phases of the proposed development, erosion berms should
be installed to prevent gully formation and siltation of the riparian resources. The following points
should serve to guide the placement of erosion berms:
Where the track has slope of less than 2%, berms every 50m should be installed.
Where the track slopes between 2% and 10%, berms every 25m should be installed.
Where the track slopes between 10%-15%, berms every 20m should be installed.
Where the track has slope greater than 15%, berms every 10m should be installed.
If appropriate, these specifications can be replaced by Eskom guidelines.
Eskom If applicable C
44. No maintenance or servicing of vehicles will take place on site. ECO On-going C/O
45. Rehabilitation of disturbed areas must be carried out concurrently with construction as far as possible
and disturbed footprint areas must be kept to the minimum necessary
C/O
46. All construction and maintenance vehicles must be inspected regularly for oil leaks and such leaks
repaired before further use of the vehicle. Drip trays must be used to collect spilt oil from vehicles prior
to repairs being completed.
Waste Management
47. Existing waste management practices for Eskom’s operations must be applied to each proposed
substation and associated power line.
ECO On-going All
SRK Consulting: 465044 EMPr Kashan Page 15
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Ref no Measure, criteria or principles Monitoring
Partner
Time frame Phase
48. Domestic waste generated on the proposed site must be collected by the municipality and disposed at
the nearest licensed municipal landfill site.
ECO Monthly C/O
49. No dumping of waste material must be allowed. Litter bins must be provided and must be emptied
when full, and then transported to at the nearest licensed Municipal landfill site.
ECO On-going C/O
50. All waste building material must be removed from the site on completion of construction ECO/Contractor Upon
completion of
construction
C/O
51. Contaminated construction and maintenance waste and clean construction waste must be dealt with
separately, and then removed to an appropriately registered waste disposal site.
ECO Monthly C/O
52. Oils, greases etc. must be collected and segregated in temporary storage facilities prior to disposal at
a licenced Hazardous Waste Landfill site or collected by oil recyclers. Hazardous storage containers
and storage areas must comply with relevant SABS standards.
ECO Monthly C/O
SRK Consulting: 465044 EMPr Kashan Page 16
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Ref no Measure, criteria or principles Monitoring
Partner
Time frame Phase
Traffic
53. Warning signs must be erected indicating the presence of construction vehicles along the envisaged
routes.
ECO/Contractor On-going during
construction on
public roads
C
54. Vehicles must be restricted to travelling only on designated roadways, as far away from the wetland
areas as possible to limit the ecological footprint of the proposed development activities.
ECO/Contractor On-going C
55. Speed limits must be enforced at 30 km/h on the access roads to substations and temporary access
routes along the power line servitude.
ECO/Contractor On-going C/O
56. Parking on public roads used for access will be restricted to the extent that this is possible ECO/Contactor When
applicable
C/O
Noise
57. Construction and maintenance equipment to comply with the standards for construction vehicles as
stipulated in the IFC's Environmental, Health and Safety Regulations.
ECO On-going C/O
Air quality
58. Dust suppression during construction for Eskom’s operations must be applied to each proposed
substation and associated power line.
Eskom Project
Manager
On-going PC/C
Socio-Economic
59. Ensure effective communication with the land owners during construction and during site maintenance. ECO On-going All
60. Ensure transparency over the labour process to ensure that there is no conflict in the community
ECO When
applicable
All
61. Track all complaints made during the construction period and address them in accordance with the
relevant specialist studies. Respond to all complaints.
ECO On-going C/O
62. Speak to all landowners regarding the anticipated use of the land and plan the power line route to ECO When PC
SRK Consulting: 465044 EMPr Kashan Page 17
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Ref no Measure, criteria or principles Monitoring
Partner
Time frame Phase
minimise the impact of the project on current and future land use and production applicable
63. Where the area cannot be rehabilitated to its original condition within two months of the completion of
construction, Eskom or its appointed contractor(s) should provide alternative income/food to the farmer
for the time period required for production.
Eskom When
applicable
64. Available formal and informal employment opportunities must be made available to local residents
and/or service providers.
Eskom When
applicable
C/O
65. Compensation should be paid by the utility for the right of use over the servitude. This value should be
set via negotiation with affected landowners and take into account current norms and practice with
regards compensation.
Eskom When
applicable
PC
66. Compensation for loss of stock or any other damages where negligence by Eskom can be proved
must be paid.
Eskom When
applicable
PC
SRK Consulting: 465044 Kashan
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Prepared by
Fiona Evans
Environmental Scientist
Reviewed by
Andy Smithen
Partner
All data used as source material plus the text, tables, figures, and attachments of this document
have been reviewed and prepared in accordance with generally accepted professional engineering
and environmental practices.
SRK Consulting: 465044 Kashan
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
SRK Report Distribution Record
Report No. 465044
Copy No.
Name/Title Company Copy Date Authorised by
The Director IEA Department of Environmental Affairs
1-2 04 March 2015
Department of Water and Sanitation (DWS) - NW
3 04 March 2015
Department of Water and Sanitation (DWS) - Gauteng
4 04 March 2015
Gauteng Department of Agriculture and Rural Development (GDARD)
5 04 March 2015
Rural, Environmental and Agricultural Development (READ)
6 04 March 2015
Regional Land Claims Commission: North West Province
7 04 March 2015
Regional Land Claims Commission: Gauteng
8 04 March 2015
Department of Public Works and Roads - North West Regional Office
9 04 March 2015
Department of Public Works and Roads – Gauteng
10 04 March 2015
Mogale City Local Municipality
11 04 March 2015
Madibeng Local Municipality
12 04 March 2015
West Rand District Municipality
13 04 March 2015
Bojanala District Municipality
14 04 March 2015
Hekpoort Library 15 04 March 2015
Hekpoort Mokoya Lodge 16 04 March 2015
Neo Masemola Eskom Holdings SOC Ltd 17 04 March 2015
- SRK Consulting – Library 18 04 March 2015
- SRK Consulting – File 19 04 March 2015
This report is protected by copyright vested in SRK (SA) Pty Ltd. It may not be reproduced or transmitted in
any form or by any means whatsoever to any person without the written permission of the copyright holder,
SRK.
SRK Consulting: 465044 Kashan
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
SRK Consulting: 465044 Kashan
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Appendix A: Team CVs
Resume
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Specialisation Environmental management, mine closure planning, environmental auditing, rehabilitation planning, due diligence, environmental risk assessment, environmental impact assessment
Expertise Andy Smithen has been involved in the field of environmental engineering for the past 26 years. His expertise includes: • compilation of Environmental Impact Assessments and Environmental
Management Plans for numerous mines; • closure planning and costing; • assessment of environmental risk for operating mines and redundant operations; • environmental due diligence and liability assessments and environmental
auditing. Andy has also been involved in the development of risk based decision-making methodologies and has assisted in the development of water management plans.
Employment 2003 – present 2001 – 2003 1998 – 2001 1995 – 1998 1992 – 1995 1986 – 1992 1977 – 1986
SRK Consulting (Pty) Ltd, Environmental Department, Partner, Durban SRK Consulting (Pty) Ltd, Environmental Department, Director, Johannesburg SRK Consulting (Pty) Ltd, Water and Environmental Technology Department, Director, Johannesburg SRK Consulting (Pty) Ltd, Environmental Department, Principal Engineer, Johannesburg Gengold, Manager, Environmental Management Trans Natal Coal Corporation, Manager, Environmental Management Department of Agriculture, Engineer
Publications Numerous papers published relating to environmental management.
Languages English – read, write, speak Afrikaans – read, write, speak
Profession Environmental Engineer
Education MBL, UNISA, Johannesburg, 1994
MSc, Eng, Agric, University of Natal, 1981
BSc, Eng, Civil, University of Natal, 1976
Registrations/ Affiliations
Pr Eng (South Africa), 120/83
MSAICE, MSAIAE, MSAIMM
SRK Consulting Page 2
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Publications 1. Various papers on soil erosion research, agricultural engineering principles applied to rehabilitation,
environmental management in the mining environment, and environmental impact assessment in southern Africa.
SRK Consulting Page 3
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Due diligence Location: Zimbabwe Project duration & year: 2013 Client: Confidential Name of Project: Confidential Project Description: Environmental and social due diligence an underground mine. Job Title and Duties: Environmental and social specialist Value of Project: n/a Location: Mpumalanga Province. South Africa Project duration & year: 2013 Client: Confidential Name of Project: Confidential Project Description: Environmental gap analysis for a mining feasibility study Job Title and Duties: Environmental specialist Value of Project: n/a Location: Namibia Project duration & year: 2012 – 2013 Client: Confidential Name of Project: Confidential Project Description: Due diligence for a mining operation Job Title and Duties: Environmental reviewer Value of Project: n/a Location: Zambia and the DRC Project duration & year: 2012 – 2013 Client: Confidential Name of Project: Confidential Project Description: Environmental and social due diligence for open pit and underground copper
mines. Job Title and Duties: Environmental and social specialist Value of Project: n/a Location: Gauteng Project duration & year: 2012 – 2013 Client: Confidential Name of Project: Confidential Project Description: Environmental and social due diligence for underground gold mines Job Title and Duties: Environmental and social specialist Value of Project: n/a Location: Kwa Zulu Natal Project duration & year: 2012 Client: Confidential Name of Project: Confidential Project Description: Environmental risk assessment and closure cost review for a smelter Job Title and Duties: Environmental specialist Value of Project: n/a
SRK Consulting Page 4
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Due diligence Location: South Africa, Limpopo Province Project duration & year: 2012 Client: Vergenoeg Flourspar Mine Name of Project: Vergenoeg Risk Assessment Project Description: Compilation of a risk matrix and report for all aspects of the mining operation Job Title and Duties: Project manager Value of Project: ZAR 300 000 Location: South Africa, Gauteng Province Project duration & year: 2012 Client: n/a Name of Project: Confidential Project Description: High level environmental due diligence for two building material manufacturing
sites Job Title and Duties: Project manager Value of Project: ZAR 100 000 Location: South Africa, Free State Province Project duration & year: 2011 – 2012 Client: n/a Name of Project: Confidential Project Description: Environmental and Social component of a due diligence for the transfer of a
coal mine to a BEE Company Job Title and Duties: Environmental and social specialist Value of Project: Part of a bigger project Location: South Africa Project duration & year: 2011 Client: n/a Name of Project: Confidential Project Description: Directors Liability assessment for a number of Iron Ore and Manganese mines Job Title and Duties: Environmental and social specialist Value of Project: ZAR500 000 Location: South Africa Project duration & year: 2011 Client: n/a Name of Project: Confidential Project Description: Directors Liability assessment for a manganese mine in the Northern Cape Job Title and Duties: Environmental and social specialist Value of Project: ZAR200 000 Location: South Africa Project duration & year: 2011 Client: n/a Name of Project: Confidential Project Description: Environmental and social due diligence for a number of coal mines Job Title and Duties: Environmental and social specialist Value of Project: Part of a bigger project
SRK Consulting Page 5
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experienc e: Due diligence Location: South Africa Project duration & year: 2011 Client: n/a Name of Project: Confidential Project Description: Due diligence for a Greenfields platinum project Job Title and Duties: Environmental and social specialist Value of Project: Part of a bigger project Location: Zimbabwe Project duration & year: 2010 Client: n/a Name of Project: Confidential Project Description: Environmental Due Diligence for a gold mine Job Title and Duties: Environmental and social specialist Value of Project: Part of a bigger project Location: Democratic Republic of the Congo Project duration & year: 2008 Client: Confidential Name of Project: Confidential Project Description: Environmental Due Diligence Job Title and Duties: Environmental and social specialist Value of Project: Part of a bigger project Location: North West Province, South Africa Project duration & year: 2007-2008 Client: Uranium One Name of Project: Due Diligence Project Description: Environmental due diligence for operational uranium mine. Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project Location: Copperbelt and Southern Province, Zambia Project duration & year: 2007-2008 Client: Confidential Name of Project: Confidential Project Description: Environmental and social due diligence for three gemstone mines. Job Title and Duties: Environmental and social specialist Value of Project: Part of a bigger project Location: Democratic Republic of the Congo Project duration & year: 2005 Client: Confidential Name of Project: Confidential Project Description: Environmental input for feasibility studies for proposed copper mines Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project
SRK Consulting Page 6
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Due diligence Location: Republic of Macedonia Project duration & year: 2005 Client: Confidential Name of Project: Confidential Project Description: Environmental input for a mining and smelting operation Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project Location: Free State Province, South Africa Project duration & year: 2005 Client: Buffelsfontein Name of Project: Due diligence Project Description: Environmental due diligence for Buffelsfontein Chrome Mine Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project Location: Lesotho Project duration & year: 2005 Client: Confidential Name of Project: Confidential Project Description: Environmental due diligence for a diamond mine Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project Location: Lesotho Project duration & year: 2003-Present Client: Kao Name of Project: Due diligence Project Description: Environmental due diligence for Kao Diamond Mine and subsequent follow up
work Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project Location: India Project duration & year: 2003 Client: Sterlight in Rajasthan. Name of Project: Due diligence Project Description: Environmental due diligence for the Lead Zinc mining operations of Sterlight in
Rajasthan. Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project Location: Mpumalanga, South Africa Project duration & year: 2003 Client: Middleburg Consolidated Coal Mines Name of Project: Middleburg due diligence Project Description: Environmental due diligence for Middleburg Consolidated Coal Mines Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project
SRK Consulting Page 7
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Due diligence Location: Zambia Project duration & year: 2002 Client: Konkola Mines Zambia Name of Project: Due diligence Project Description: Environmental due diligence for Konkola Mines Zambia Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project Location: Western Cape Project duration & year: 2002 Client: n/a Name of Project: Marine diamonds Project Description: Environmental due diligence for off shore diamond mining. Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project Location: South Africa Project duration & year: 2002 Client: Spoornet Name of Project: Environmental due diligence Project Description: Environmental due diligence audit of the operations of Spoornet for the
proposed privatisation of Spoornet Job Title and Duties: Environmental team leader Value of Project: ZAR 500 000 Location: Free State Province, South Africa Project duration & year: 2001 Client: Freegold Name of Project: Environmental due diligence Project Description: Environmental due diligence for Freegold Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project Location: North West Province, South Africa Project duration & year: 2001 Client: Afrikaner Leases Name of Project: Environmental due diligence Project Description: Environmental due diligence for Afrikaner Leases Job Title and Duties: Environmental Specialist Value of Project: Part of a bigger project Location: Swaziland Project duration & year: 2001 Client: Maloma Colliery Name of Project: Exit environmental due diligence Project Description: Exit environmental due diligence for dis-investment at Maloma Colliery Job Title and Duties: Team leader Value of Project: ZAR 100 000
SRK Consulting Page 8
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Due diligence Location: North West Province and Free State. Project duration & year: 2001 Client: African Rainbow Minerals Name of Project: ARM due diligence Project Description: Environmental due diligence for African Rainbow Minerals Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project Location: South Africa Project duration & year: 2001 Client: Spoornet Name of Project: Spoornet due diligence: coal mines Project Description: Environmental due diligence of coal mining operations using the Coallink
railway of Spoornet Job Title and Duties: Environmental team leader Value of Project: Part of a bigger project Location: Gauteng and Free State, South Africa Project duration & year: 2001 Client: Harmony Gold Mining Operations Name of Project: Harmony due diligence Project Description: Environmental due diligence for Harmony Gold Mining Operations Job Title and Duties: Environmental specialist. Value of Project: Part of a bigger project Location: Mpumalanga, South Africa Project duration & year: 2000-2002 Client: Eastern Transvaal Consolidated Gold Mines and Target Gold Mine Name of Project: Eastern Transvaal Consolidated Project Description: Environmental due diligence for Avgold, including Eastern Transvaal
Consolidated Gold Mines and Target Gold Mine This work extended from 2000 to 2002 and included due diligence audits for the raising of capital by Avgold to the acquisition of ETC by Metorex
Job Title and Duties: Environmental Specialist Value of Project: Part of a bigger project Location: Namibia Project duration & year: 2000 Client: Gobabis Sepeolite Name of Project: Environmental due diligence Project Description: Environmental due diligence for a sepeolite mine in Gobabis Job Title and Duties: Environmental team leader Value of Project: Part of a bigger project Location: Zimbabwe Project duration & year: 2000 Client: Ngezi Platinum Mine Name of Project: Ngezi platinum Project Description: Environmental due diligence for Ngezi Platinum Mine Job Title and Duties: Environmental specialist Value of Project: Part of a bigger project
SRK Consulting Page 9
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Due diligence Location: South Africa Project duration & year: 1998 Client: Goldfields gold assets and Gengold Name of Project: Due Diligence Project Description: Due Diligence for the merger between Goldfields gold assets and Gengold Job Title and Duties: Team leader Value of Project: Part of a bigger project Location: South Africa Project duration & year: 1997 Client: Anglogold Name of Project: Due Diligence Project Description: Due Diligence for formation of Anglogold Job Title and Duties: Team leader Value of Project: Part of a bigger project Key Experience: Environmental impact assessment and environmental
management planning Location: Limpopo Province, South Africa Project duration & year: 2012 – On Going Client: Sasol Mining Name of Project: Environmental Impact Assessments / Environmental Management Plan Project Description: EIA / EMP for a proposed coal mine. Waterberg Coal Field Job Title and Duties: Project Reviewer Value of Project: n/a Location: KwaZulu Natal, South Africa Project duration & year: 2012 – On Going Client: Richards Bay Minerals Name of Project: Environmental Impact Assessments / Environmental Management Plan Project Description: EIA / EMP for a proposed new mining area Job Title and Duties: Project Reviewer Value of Project: n/a Location: KwaZulu Natal, South Africa Project duration & year: 2012 – On Going Client: Richards Bay Minerals Name of Project: Environmental Impact Assessments / Environmental Management Plan Project Description: EIA / EMP for a services corridor for proposed new mining area. Job Title and Duties: Project Reviewer Value of Project: n/a Location: Limpopo Province, South Africa Project duration & year: 2011-2012 Client: Anglo Platinum Mogalakwena Mine Name of Project: Environmental Impact Assessments for Environmental Management Plan
Amendments Project Description: Several EIAs and Basic Assessments for proposed developments at the mine Job Title and Duties: Project Reviewer Value of Project: n/a
SRK Consulting Page 10
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Environmental impact assessment and environmental management planning
Location: Limpopo Province, South Africa Project duration & year: 2011-2012 Client: China Minmetals Name of Project: Naboom Social and Labour Plan Project Description: Social and Labour plan for a proposed chrome mine Job Title and Duties: Project Reviewer Value of Project: Value of project ZAR 3 million Location: Mpumalanga Province, South Africa Project duration & year: 2010-2011 Client: Samancor Name of Project: Samancor Energy Recovery Plant EIAs Project Description: EIA for energy co-generation projects for several smelters Job Title and Duties: Project Reviewer Value of Project: Value of project ZAR 3 million Location: Limpopo Province, South Africa Project duration & year: 2010 – 2011 Client: China Minmetals Name of Project: Naboom Chrome mining project EIA Project Description: EIA for the Naboom greenfields chrome mining project Job Title and Duties: Project Reviewer Value of Project: Value of project ZAR 3 million Location: Limpopo Province, South Africa Project duration & year: 2009 – 2011 Client: Central Energy Fund Name of Project: Vlakfontein Coal mine EIA Project Description: EIA for a greenfields coal mining project Job Title and Duties: Project Reviewer Value of Project: Value of project ZAR 5 million Location: Maun area, Botswana Project duration & year: 2009 – 2010 Client: Discovery Metals Limited Name of Project: Boseto Copper Mine Project Description: EIA for a greenfields copper mining project Job Title and Duties: Project Reviewer Value of Project: Value of project ZAR 3 million Location: From Komatipoort to Kendal in Mpumalanga, South Africa Project duration & year: 2007 – 2009 Client: Petroline Pipeline Name of Project: Petroline Pipeline Project Description: Route Selection and Environmental Impact Assessment Job Title and Duties: Project Reviewer Value of Project: Capital value of project – estimated at ZAR 4 billion
SRK Consulting Page 11
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Environmental impact assessment and environmental management planning
Location: North West Province South Africa Project duration & year: 2008 – ongoing Client: Aquarius Platinum Marikana Mine Name of Project: Aquarius Platinum Marikana Mine Project Description: Environmental Impact Assessment and Environmental Management Plan for
new shaft and associated infrastructure Job Title and Duties: Project Reviewer Value of Project: ZAR 1 200 000 Location: Botswana and Namibia Project duration & year: 2008 – ongoing Client: Confidential Name of Project: Confidential Project Description: High level environment screening project for proposed project Job Title and Duties: Project Reviewer Value of Project: ZAR 1 500 000 Location: Botswana and Namibia Project duration & year: 2008 Client: Trans Kalahari Railway line Name of Project: Trans Kalahari Railway line Project Description: Route Selection and Environmental Aspects of Pre-feasibility study for a
railway line from Mmamabula in Botswana to the Namibian Coast. The project involved port and route selection and pre-feasibility environmental studies
Job Title and Duties: Project Reviewer Value of Project: Not yet available Location: Ngamiland – Botswana Project duration & year: 2007 – ongoing Client: Discovery Metals North West Botswana Copper Mine ESIA Name of Project: Discovery Metals North West Botswana Copper Mine ESIA Project Description: Environmental and Social Impact Assessment and Environmental Management
Plan for new mining infrastructure to IFC standards Job Title and Duties: Project Reviewer and co-ordinator for related studies Value of Project: ZAR 3 500 000 Location: Katanga Province. Democratic Republic of the Congo. Project duration & year: 2007 – ongoing Client: Barytex International Name of Project: Barytex International. Shituru Mine ESIA Project Description: Environmental and Social Impact Assessment and Environmental Management
Plan for new mining infrastructure to IFC standards Job Title and Duties: Project Reviewer Value of Project: ZAR 3 000 000
SRK Consulting Page 12
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Environmental impact assessment and environmental management planning
Location: Katanga Province, Democratic Republic of the Congo Project duration & year: 2007 – ongoing Client: Gem Diamonds. Mbelenge Mine ESIA Name of Project: Gem Diamonds. Mbelenge Mine ESIA Project Description: Environmental Impact Assessment and Environmental Management Plan for
proposed alluvial diamond mine to IFC standards Job Title and Duties: Project Reviewer Value of Project: ZAR 1 200 000 Location: North West Province, South Africa Project duration & year: 2007 – ongoing Client: Rustenburg Platinum and Aquarius Platinum Name of Project: Rustenburg Platinum and Aquarius Platinum Pooling and Sharing Agreement.
K6 EMP Project Description: Environmental Impact Assessment and Environmental Management Plan for
new shaft and associated infrastructure Job Title and Duties: Project Reviewer Value of Project: ZAR 1 200 000 Location: North West Province, South Africa Project duration & year: 2007 – 2008 Client: Rustenburg Platinum Mines Name of Project: Rustenburg Platinum Mines – Rustenburg Section Merensky Deeps EIA Project Description: Environmental Impact Assessment and Environmental Management Plan for
new shaft and associated infrastructure Job Title and Duties: Project Reviewer Value of Project: ZAR 2 000 000 Location: Gauteng Province, South Africa Project duration & year: 2007 Client: Harmony Gold Mine Name of Project: Harmony Gold Mine Project Description: Environmental Impact Assessment for proposed disposal of tailings in open
cast pits. Initial assessment. Job Title and Duties: Project Reviewer Value of Project: ZAR 500 000 Location: North West Province, South Africa Project duration & year: 2007 Client: Rustenburg Platinum and Aquarius Platinum Pooling and Sharing Agreement.
K2 EMP Name of Project: Rustenburg Platinum and Aquarius Platinum Pooling and Sharing Agreement.
K2 EMP Project Description: Environmental Impact Assessment and Environmental Management Plan for
new ore bunker and load out facility Job Title and Duties: Project Reviewer Value of Project: ZAR 700 000
SRK Consulting Page 13
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Environmental impact assessment and environmental management planning
Location: Mpumalanga, South Africa Project duration & year: 2005 Client: Doornbosch Name of Project: Doornbosch Project Description: Environmental Management Programme report for expansions at Eastern
Chrome Mine Job Title and Duties: Team leader Value of Project: ZAR 300 000 Location: Democratic Republic of the Congo Project duration & year: 2005 Client: Confidential Name of Project: Confidential Project Description: Environmental Impact Assessment for a copper project Job Title and Duties: Team leader Value of Project: n/a Location: Gauteng and Free State, South Africa Project duration & year: 2004 Client: Petronet Name of Project: Petronet Project Description: Environmental impact assessment and Environmental Management Plan for a
petrol Pipeline for Petronet Job Title and Duties: Team Leader Value of Project: ZAR 200 000 Location: Mpumalanga, South Africa Project duration & year: 2004 Client: Der Brochen Name of Project: Der Brochen Project Description: Environmental Management Plan for Addendams to Der Brochen Platinum
Mine Job Title and Duties: Project reviewer Value of Project: ZAR 1000 000 Location: North West Province, South Africa Project duration & year: 2003 Client: Kroondal Name of Project: Kroondal EMPR Project Description: Environmental Management Plan, as an addendum to the EMPR for Kroondal
Platinum Mine Job Title and Duties: Project reviewer Value of Project: ZAR 300 000 Location: Northern Province, South Africa Project duration & year: 2003 Client: Lebowa Name of Project: Lebowa EMPR Project Description: Environmental Management Plan for expansions to Lebowa Platinum Mine Job Title and Duties: Project reviewer Value of Project: ZAR 300 000
SRK Consulting Page 14
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Environmental impact assessment and environmental management planning
Location: Mpumalanga, South Africa Project duration & year: 2003 Client: Der Brochen Name of Project: Der Brochen EMPR Project Description: Environmental management plan for proposed Der Brochen Platinum Mine for
Anglo Platinum Job Title and Duties: Project reviewer Value of Project: ZAR 400 000 Location: Burkina Faso Project duration & year: 2002 Client: Taparko Name of Project: Taparko scoping Project Description: Environmental scoping for a proposed gold mining operation Job Title and Duties: Project reviewer Value of Project: ZAR 200 000 Location: Swaziland Project duration & year: 2000 to present Client: Maguga Name of Project: Maguga EIA Project Description: Komati Basin Authority: Environmental Impact Assessment, Environmental
Management Plans and Environmental Management Audits for Maguga dam Job Title and Duties: Environmental auditor Value of Project: Part of a bigger project Location: Rustenburg Project duration & year: 2000 to present Client: Kroondal Name of Project: Kroondal EMP Project Description: Environmental management for Kroondal Platinum Mine Job Title and Duties: Review of work of outsourced (SRK) environmental control officer Value of Project: ZAR 400 000 Location: Limpopo Province, South Africa Project duration & year: 2000 Client: Potgietersrust EMPR Name of Project: Potgietersrust EMPR Project Description: Environmental Management Plan for Potgietersrust Platinum Mine Job Title and Duties: Project reviewer Value of Project: n/a
SRK Consulting Page 15
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Closure planning, closure costing and environmental liability assessment
Location: Mpumalanga Province, South Africa Project duration & year: 2013 – on going Client: Anglo Coal Name of Project: Kriel Colliery – expansion project Project Description: Preliminary Closure Plan Job Title and Duties: Project Reviewer Value of Project: n/a Location: Zambia Project duration & year: 2013 Client: Lubambe Copper Mine Name of Project: Closure Cost Estimate. Lubambe Copper Mine Project Description: Mine closure cost estimate Job Title and Duties: Project Reviewer Value of Project: n/a Location: Mpumalanga Province, South Africa Project duration & year: 2012 Client: Anglo Coal Name of Project: Elders Colliery Project Description: Preliminary Closure Plan Job Title and Duties: Project Reviewer Value of Project: n/a Location: Zambia Project duration & year: 2010-2011 Client: Equinox Mining Name of Project: Closure Cost Estimate. Lumwana Copper Mine Project Description: Mine closure cost estimate Job Title and Duties: Project Manager Value of Project: ZAR 200 000 Location: Mpumalanga Province, South Africa Project duration & year: 2007 – 2012 Client: Nkomati Mine Name of Project: Closure Cost Estimate. Nkomati Mine Project Description: Update of mine closure cost estimate Job Title and Duties: Project Reviewer Value of Project: ZAR 80 000 per annum Location: Tanzania Project duration & year: 2007-2008 Client: Bulyanhulu Gold Mine Name of Project: Closure Cost Estimate Project Description: Mine closure cost estimate Job Title and Duties: Project Reviewer Value of Project: ZAR 200 000
SRK Consulting Page 16
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Closure planning, closure costing and environmental liability assessment
Location: Mpumalanga Province, South Africa Project duration & year: 2007 Client: Nkomati Mine Name of Project: ZAR 80 000 Project Description: Update of mine closure cost estimate Job Title and Duties: Project Reviewer Value of Project: ZAR 80 000 Location: North West Province, South Africa Project duration & year: 2007 Client: Rustenburg Platinum Mines – Union Section Name of Project: Closure Cost Estimate Project Description: Update of mine closure cost estimate Job Title and Duties: Project Reviewer Value of Project: ZAR 80 000 Location: Limpopo Province, South Africa Project duration & year: 2007 Client: Lebowa Platinum Mines Name of Project: Closure Cost Estimate Project Description: Update of mine closure cost estimate Job Title and Duties: Project Reviewer Value of Project: ZAR 80 000 Location: Mpumalanga Province, South Africa Project duration & year: 2006 Client: Nkomati Mine Name of Project: Closure Cost Estimate Project Description: Update of mine closure cost estimate Job Title and Duties: Project Reviewer Value of Project: ZAR 70 000 Location: North West Province, South Africa Project duration & year: 2006 Client: Rustenburg Platinum Mines – Union Section Name of Project: Closure Cost Estimate Project Description: Update of mine closure cost estimate Job Title and Duties: Project Reviewer Value of Project: ZAR 70 000 Location: Limpopo Province, South Africa Project duration & year: 2006 Client: Lebowa Platinum Mines Name of Project: Closure Cost Estimate Project Description: Update of mine closure cost estimate Job Title and Duties: Project Reviewer Value of Project: ZAR 70 000
SRK Consulting Page 17
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Closure planning, closure costing and environmental liability assessment
Location: Richards Bay, South Africa Project duration & year: 2005 Client: Richards Bay Minerals Name of Project: Closure planning for Richards Bay Minerals Project Description: Compilation of a closure plan for the sand mining operations and processing
works. Job Title and Duties: Project Reviewer Value of Project: ZAR 800 000 Location: North West Province, South Africa Project duration & year: 2004 Client: Pandora Joint Venture Name of Project: Liability assessment Project Description: Liability assessment for Lonmin and Rustenburg Platinum Mines prior to the
commencement of their joint venture agreement for the Pandora project Job Title and Duties: Environmental specialist Value of Project: ZAR 50 000 Location: Zambia Project duration & year: 2003 Client: Konkola Copper Mines Name of Project: Closure planning Project Description: Provision of input for closure planning for Konkola Copper Mines Job Title and Duties: Closure planning specialist Value of Project: Part of the overall project Location: Mozambique Project duration & year: 2003 Client: Monarch Gold Mine Name of Project: Decommissioning and Closure Plan Project Description: Decontamination and closure plan for and abandoned gold mine Job Title and Duties: Project leader Value of Project: ZAR 400 000 Location: North West Province, South Africa Project duration & year: 2003 Client: Between Kroondal Platinum Mine and Rustenburg Platinum Mines Name of Project: Liability assessment for the pooling and sharing agreement Project Description: Assessment of the individual and joint liabilities for the two mines prior to
commencement of the pooling and sharing agreement for the joint project Job Title and Duties: Environmental specialist Value of Project: ZAR 50 000 Location: North West Province Project duration & year: 2003 Client: Kroondal Platinum Mine Name of Project: Rehabilitation plan Project Description: Planning for the rehabilitation of open cast mine workings Job Title and Duties: Project reviewer Value of Project: ZAR 100 000
SRK Consulting Page 18
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Closure planning, closure costing and environmental liability assessment
Location: North West Province Project duration & year: 2002 Client: Platinum mine Name of Project: Paste Backfill project Project Description: Evaluation of the environmental aspects of tailings backfilling using paste
technology for a large Platinum mine Job Title and Duties: Closure specialist Value of Project: Part of a bigger project Location: Kwa-Zulu Natal. South Africa Project duration & year: 2002 Client: Welgedacht Colliery Name of Project: Welgedacht liability assessment Project Description: Mine closure liability assessment Welgedacht Colliery, for the Department of
Minerals and Energy Job Title and Duties: Team leader Value of Project: ZAR 100 000 Location: Kwa-Zulu Natal, South Africa Project duration & year: 2002 Client: Capital Coal Name of Project: Capital coal liability assessment Project Description: Mine closure liability assessment for Capital Coal. Job Title and Duties: Team Leader Value of Project: ZAR 50 000 Location: Northern Cape, South Africa Project duration & year: 2001 Client: Bishop Manganese Name of Project: Bishop closure plan Project Description: Closure plan for the defunct Bishop Manganese for Assmang Job Title and Duties: Team Leader Value of Project: ZAR 300 000 Location: Potgietersrust Project duration & year: 2001 Client: Potgietersrust Platinum Name of Project: Potgietersrust closure cost assessment Project Description: Closure cost estimate for Potgietersrust Platinum 2001 Job Title and Duties: Team Leader Value of Project: ZAR 200 000 Location: South Africa Project duration & year: 2000 Client: ISCOR Name of Project: Environmental Risk Assessment Project Description: Environmental closure liability assessment for the coal and iron ore mining
operations of Iscor Job Title and Duties: Team member Value of Project: Part of a bigger project
SRK Consulting Page 19
Andy Smithen Principal Engineer
Smtn/Omar SRK ZA_DBN_SmithenA_Sept_2013.docx_QR Sept 2013
Key Experience: Closure planning, closure costing and environmental liability assessment
Location: South Africa Project duration & year: 2000 Client: Anglogold Name of Project: Closure Cost Audit Project Description: Desk top audit of the closure cost estimate for the operations of Anglogold Job Title and Duties: Team Leader Value of Project: ZAR 50 000 Location: South Africa Project duration & year: 2000 Client: Avgold and Avmin Name of Project: Avmin audit Project Description: Environmental audits and environmental liability assessments for Avgold and
Avmin Job Title and Duties: Team Leader Value of Project: ZAR 500 000 Location: North West Province, South Africa Project duration & year: 2000 Client: Impala Name of Project: Closure Cost Project Description: Closure costing for Impala Platinum Job Title and Duties: Team Leader Value of Project: ZAR 200 000 Location: North West Province, South Africa Project duration & year: 1997-2011 Client: Kroondal Platinum Mine Name of Project: Kroondal Closure Costs Project Description: Annual closure cost estimates for Kroondal Platinum Mine Job Title and Duties: Project reviewer Value of Project: ZAR 400 000 Location: Free State Province, South Africa Project duration & year: 1996 Client: Coalbrook Name of Project: Closure Plan Project Description: Closure plan for Coalbrook Job Title and Duties: Team leader responsible for closure planning Value of Project: ZAR100 000
SRK Consulting: 465044 Kashan
EVAF/POLL/HINM 465044_20150108_Kashan BAR_EMPr(draft)_FINAL.docx February 2015
Appendix B: Eskom Management Standards 1. Emergency response plan
2. Biodiversity standard
3. Vegetation standard
EMERGENCY PREPAREDNESS PLAN 2013 - 2014
NORTH WEST OPERATING UNIT
In terms of EPC 32-95, it is the responsibility of the Senior Supervisor or next in charge to report an environmental incident to the Environmental Manager (EM) of the Operating Unit. This must be done by sending an SMS to the EM on 083 9666 104 within 24 hours of the incident and then after submit a flash report detailing the nature of the incident.
Environmental Resources to be contacted:
Name Work area Contact Details 1. Lusanda Ngesi
Environmental Manager North West Operating Unit
083 966 6104/ 043 703 5358 [email protected]
2. Blondie Moukangwe Senior Environmental
Advisor
Matlosana Zone 0060 491 7310/ 018 464 6691 [email protected]
3. Katlego Motlhabane Senior Supervisor EM
Platinum Zone 073 138 5668/014 565 1137 [email protected]
4. Sonwabiso Ndaki Environmental Advisor
Platinum Zone 074 940 2753/014 597 4530 [email protected]
5. Bonginkosi Sifunda Environmental Advisor
Matlosana Zone 018 464 6834/ 079017 6658 [email protected]
6. Amy Harington Environmental Officer
Matlosana Zone 018 464 6834 /074 190 7902 [email protected]
Oil spills - the following oil spill clean-up companies can be contacted for a quotation. This quotation must be approved by the Senior Supervisor before approval can be given to the contractor. Major oil spills under emergency conditions may be authorised directly by the relevant Sector Manager.
COMPANY CONTACT PERSON TELEPHONE NUMBER
FAX NUMBER
24 HOUR SPILL
RESPONSE RAPID RESPONSE
CHRIS BADENHORST (011) 740 7820 011 740 7148 082 458 4838
ENZA JACO VAN DEVENTER (011) 477 3892 086 642 8349 0834988798
DRIZIT ENVIRONMENTAL MARTINUS STANDER (011) 312 0218 0862180015 0795272534
Bee Removals – In the event that Bees are posing a safety issue on site, these bees must be removed by contacting Grant Arrand (Southerns Beekeepers Association) 083 652 0760.
PCM Refere
SCOT Stud
Title: VEGANESAN
Compiled
Inba Pillay
Senior EnAdvisor
Date:
ence: <xxxx
y Committee
GETATIOND MAINTEKOM LANDD RIGHTS
by:
y
vironment
xxx>
e Number/Na
N MANAGENANCE WI
D, SERVITUOF WAY
al
ame: <Numb
EMENT ITHIN UDES
Approved
Rudi Krug
VegetationConvenor
Date:
ber or name
Standard
Unique Ide
AlternativeNumber:
Area of Ap
Revision:
Total Page
Next Revi
DisclosureClassificat
by:
ger
n Care Gro
>
entifier:
e Reference
pplicability:
es:
ew Date:
e tion:
oup
T
240-70
e 32-247
Engine
1
17
Januar
Contro
Supported
Sebastian
MaintenanSteering C
Date:
Authorised
Prince Mo
Power DelGM
Date:
Technology
0172585
7
eering
ry 2019
olled Disclo
d by: SCOT
Pasquallie
nce ManageCommittee
d by:
oyo
livery Engi
y
osure
T SC
e
ement Chair
neering
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 2 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Content
Page
1. Introduction ............................................................................................................................................... 3
2. Supporting clauses ................................................................................................................................... 3 2.1 Scope .............................................................................................................................................. 3
2.1.1 Purpose ............................................................................................................................... 3 2.1.2 Applicability .......................................................................................................................... 3
2.2 Normative/informative references .................................................................................................... 3 2.2.1 Normative ............................................................................................................................ 3 2.2.2 Informative ........................................................................................................................... 4
2.3 Definitions ........................................................................................................................................ 4 2.3.1 General ................................................................................................................................ 4 2.3.2 Disclosure classification ....................................................................................................... 6
2.4 Abbreviations ................................................................................................................................... 6 2.5 Roles and responsibilities ................................................................................................................ 6 2.6 Process for monitoring ..................................................................................................................... 7 2.7 Related/supporting documents ........................................................................................................ 7
3. Standard ................................................................................................................................................... 7
4. Authorisation ........................................................................................................................................... 10
5. Revisions ................................................................................................................................................ 10
6. Development team .................................................................................................................................. 10
7. Acknowledgements ................................................................................................................................. 10
8. Annexures .............................................................................................................................................. 11
Annex A – Impact assessment....................................................................................................................... 12
Annex B - Implementation timeframe ............................................................................................................. 13
Annex C - Training or communication ............................................................................................................ 15
Annex D - Special tools, equipment, software ................................................................................................ 16
Annex E : Biomes and Vegetation types ........................................................................................................ 17
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 3 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
1. Introduction
This standard specifically deals with vegetation management in Eskom land including servitudes and rights of way, specifying general requirements and servitude widths to assist in the development of Scope of Work for servitude maintenance. It sets out the manner in which all initial servitude route clearing, and any subsequent vegetation maintenance is to be performed on Eskom servitudes. It sets the minimum standards for vegetation clearing and maintenance of Eskom land.
It is notable that all vegetation management within commercial forestry areas shall be done in terms of the Timber Growers Agreement (the maintenance and management agreement in forest plantation areas and servitude areas (where applicable)). This particular document has however not been accepted by all foresters, but can be used as a guideline for future agreements.
2. Supporting clauses
2.1 Scope
2.1.1 Purpose
The purpose of this standard is to set requirements for initial servitude route clearing and any subsequent vegetation management performed within Eskom land.
The objective of vegetation management within Eskom land is to ensure the safe mechanical and/or electrical operation of infrastructure to meet Eskom’s legal, business, social and environmental obligations.
2.1.2 Applicability
This standard shall apply throughout Eskom Holdings SOC Limited and its Divisions, subsidiaries, and entities in which Eskom has a controlling interest, including identified contractors, suppliers and service providers of Eskom where significant vegetation management impacts and risks may occur.
Where Eskom has influence in entities and/or operations, including instances where Eskom may have contractors, this standard will be applied in those areas directly under the control of Eskom, and due process will be followed to influence the entity or operation to comply with the requirements of this standard.
2.2 Normative/informative references
Parties using this document shall apply the most recent edition of the documents listed in the following paragraphs.
2.2.1 Normative
[1] Conservation of Agricultural Resource Act, 1989 (Act No. 43 of 1989)
[2] Eskom Land and Biodiversity Policy (32-736)
[3] Eskom Land and Biodiversity Standard (32-815)
[4] Eskom Contract Specification For Vegetation Management Services On Eskom Networks (240-52456757)
[5] National Environmental Management Act, 1998 (Act No. 107 of 1998)
[6] National Environmental Management: Biodiversity Act (NEMBA), 2004 (Act No. 10 of 2004)
[7] National Environmental Management: Protected Areas Act (NEMPA), 2003 (Act No. 57 of 2003)
[8] National Environmental Management: Waste Act (NEMWA), 2008 (Act No. 59 of 2008)
[9] National Forests Act, 1998 (Act No. 84 of 1998) (List of protected Tree species)
[10] National Parks Act, 1976 (Act No. 57 of 1976)
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 4 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
[11] National Veld & Forest Fire, 1998 (Act 1998 (Act 101 of 1998)
[12] Occupational Health and Safety Act, 1993 (Act No. 85 of 1993)
2.2.2 Informative
[1] Business and Biodiversity Offset Programme (BBOP) – Biodiversity Offset Design Handbook
[2] Commercial Timber Growers Guideline for: Maintenance and management agreement in forest plantation areas and servitude areas
[3] ISO 14001:2004 Environmental Management System Standard
[4] ISO 9001 Quality Management System Standard
[5] National Biodiversity Framework (NBF), January 2008
[6] National Protected Area Expansion Strategy (NPAES)
[7] National Spatial Biodiversity Assessment (NSBA) 2011
[8] Provincial Guideline on Biodiversity Offsets, Western Cape, Revised Draft – March 2007
[9] South Africa’s National Biodiversity Strategy and Action Plan (2005)
[10] The Electrical Machinery Regulations, 2011 under Section 43 of the Occupational Health and Safety Act, 1993 (Act No. 85 of 1993).
2.3 Definitions
2.3.1 General
Definition Description
Alien species (a) a species that is not an indigenous species; or
(b) an indigenous species translocated or intended to be translocated to a place outside its natural distribution range in nature, but not an indigenous species that has extended its natural distribution range by natural means of migration or dispersal without human intervention (National Environmental Management: Biodiversity Act, 2004 (Act No. 10 of 2004).
Commercial timber growers
Timber growers, both individually or as represented by the Forest Owners Association, South African Wattle Growers Union or the South African Timber Growers Association and their staff (Commercial Timber Growers' Guideline).
Critically endangered Ecosystems that have undergone severe degradation of their ecological structure, function or composition as a result of human intervention and are subject to an extremely high risk of irreversible transformation (National Environmental Management: Biodiversity Act (Act No. 10 of 2004)
Ecosystem A dynamic system of plant, animal and micro-organism communities and their non-living environment interacting as a functional unit (National Environmental Management Act, 1998 (Act No. 107 of 1998).
Eskom land Any land and/or servitude and/or any real right registered in the Deeds Office in Eskom’s name or favour. It also includes rights of way granted to Eskom.
Habitat A place where a species or ecological community naturally occurs (National Environmental Management: Biodiversity Act, 2004 (Act No. 10 of 2004)
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 5 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Definition Description
Indigenous species In relation to a specific protected area, means a species that occurred, naturally in a free state in nature within that specific protected area, but excludes a species introduced in that protected area as a result of human activity.1
Land user Refers to the Eskom Business Unit (BU) or function accountable for the Eskom land, at the time, and its associated infrastructure (for example a power station and a field service centre).
National Park (a) an area which was a park in terms of the National Parks Act, 1976 (Act No. 57 of 1976), immediately before the repeal of that Act by section 90(1) of this Act, and includes a park established in terms of an agreement between a local community and the Minister which has been ratified by Parliament; or
(b) an area declared or regarded as having been declared in terms of section 20 as a national park, and includes an area declared in terms of section 20 as part of an area referred to in paragraph (a) or (b) of the National Environmental Management: Protected Areas Act 57 Of 2003.
Plantation Any trees planted and managed by commercial timber growers for commercial purposes (see Commercial Timber Growers' Guideline).
Servitude A servitude is a real right (i.e. registered in the Deeds Office against the title deed of an erf), the content of which is to allow limited access to an erf for a specific purpose. It does not entail ownership and must be exercised in a reasonable way, within the boundaries of the specific purpose. In this standard, the reference is specifically to servitudes which allow Eskom only to build, operate and maintain infrastructure for the generation and conveyance of electricity, and ancillary purposes.
Special nature reserve (a) an area which was a special nature reserve in terms of the Environment Conservation Act, 1989 (Act No. 73 of 1989), immediately before the repeal of section 18 of that Act by section 90 of the National Environmental Management: Protected Areas Act, 2003 (Act No. 57 of 2003); or
(b) an area declared, or regarded as having been declared, in terms of section 18 of the National Environmental Management: Protected Areas Act, 2003 (Act No. 57 of 2003) as a special nature reserve;
(c) and includes an area declared in terms of section 18 of the National Environmental Management: Protected Areas Act, 2003 (Act No. 57 of 2003) as part of an area referred to in paragraph (a) or (b) above.
Species A kind of animal, plant or other organism that does not normally interbreed with individuals of another kind, and includes any subspecies, cultivar, variety, geographic race, strain, hybrid or geographically separate population (National Environmental Management: Biodiversity Act, 2004 (Act No. 10 of 2004).
Way leave Permission to cross or a right of way across land.
1 NEMPA, 2003 (Act No 57 of 2003)
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 6 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Definition Description
Weed Any kind of plant which has under section 2 (3) been declared a weed, and includes the seed of such plant and any vegetative part of such plant which reproduces itself asexually (Conservation of Agricultural Resources Act, 1983 (Act No. 43 of 1983).
2.3.2 Disclosure classification
Controlled disclosure: controlled disclosure to external parties (either enforced by law, or discretionary).
2.4 Abbreviations
Abbreviation Description
A & F Assurance and Forensics
BSC Board Sustainability Committee
CARA Conservation of Agricultural Resources Act
EIA Environmental Impact Assessment
ELC Environmental Liaison Committee
EMPr Environmental Management Programme
Exco Executive Management Committee
kV kilovolt
MVCD Minimum Vegetation Clearance Distance
NEMA National Environmental Management Act
ORHVS Operating regulations for high-voltage systems
PCO Pest Control Officer
2.5 Roles and responsibilities
a) The Chief Executive has the responsibility for ensuring that this standard is implemented.
b) Divisional Executives shall be responsible and accountable for the development, implementation and performance of the appropriate biodiversity management systems in their respective divisions.
c) The Environmental Manager: Sustainability Division shall establish mechanisms to ensure an Eskom co-ordinated and aligned approach to biodiversity management and shall ensure that issues relating to biodiversity performance are monitored and recorded. All areas of the organisation shall report on biodiversity issues, and the Environmental Manager of Sustainability Division shall complement the assurance function provided by A&F to the Exco, and the BSC.
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 7 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
2.6 Process for monitoring
A monitoring process to determine the effectiveness of this standard will be developed through existing internal audits (ISO 14001) and in collaboration with the A&F department.
2.7 Related/supporting documents
Eskom Contract Specification For Vegetation Management Services On Eskom Networks (240-52456757)
Land and Biodiversity Policy 32-736
Land and Biodiversity Standard 32-815
3. Standard
This section sets the minimum standards for vegetation clearing and maintenance of all Eskom land in accordance with four key aspects. Should one or more of the four aspects be applicable, problematic vegetation must be managed in terms of Section 3.5 and in accordance to the Eskom Contract Specification for Vegetation Management Services on Eskom Networks (240-52456757):
Where the vegetation poses a safety clearance risk,
When access to the Eskom land is hindered,
When the vegetation poses a fire risk,
To comply with legal imperatives.
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 8 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
The following process must be followed when assessing vegetation should one of the above aspects hold true:
1. Does the vegetation impact on safe clearances?2. Does the vegetation prevent access to the servitude? 3. Will the vegetation pose a fire risk? 4. Is there a legal imperative?
Leave it alone Protected species?
Yes No
Yes No
Obtain permit to cut protected vegetation
Choose vegetation group (refer to Specification 240-
52456757)
Use specification as per the Eskom Contract Specification for Vegetation Management
Services on Eskom Networks (240-52456757)
ISO Process
(Continuous monitoring and reviewing of specifications)
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 9 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
3.1 Where the Vegetation Poses a Safety Clearance Risk
Vegetation should be controlled where it intrudes on the minimum vegetation clearance distance, (MVCD) or will intrude on this distance before the next scheduled clearance as per Item 3.5 and The Eskom Contract Specification for Vegetation Management Services on Eskom Networks (240-52456757).
Trees and any other vegetation, that could, if they fall over or negatively impact the safe operation of the line or damage the infrastructure, must be identified and managed.
3.2 When Access to the Eskom Land is Hindered
Vegetation should be cleared to allow vehicles access below power lines and related infrastructure as per Item 3.5 and The Eskom Contract Specification for Vegetation Management Services on Eskom Networks (240-52456757).
3.3 When the Vegetation Poses a Fire Risk
Where vegetation poses a potential fire risk to Eskom’s infrastructure or to the operation of power lines, there must be a specific fire management programme to reduce this risk and vegetation must be controlled as per Item 3.5 and The Eskom Contract Specification for Vegetation Management Services on Eskom Networks (240-52456757).
3.4 Legal Compliance
Eskom must clear vegetation if required by any national or provincial legislation as per Item 3.5 and The Eskom Contract Specification for Vegetation Management Services on Eskom Networks (240-52456757) to.
3.5 Standard for Maximum Vegetation Clearances
The following table (from 240-52456757) shall be used as a standard for Vegetation Clearance for new and existing powerlines for access purposes (inspection, repair and maintenance), safety clearance, and prevention of fires in Servitudes and Wayleaves.
NOTE: Where there is a specific risk to operations as a result of equipment design or environmental condition - the Operating Unit will manage vegetation on merit. The justification for this shall only be in exceptional circumstances and shall be open to scrutiny and review.
Nominal voltage
Servitude building restriction widths
(measured from the centre line of the
power line) *
Maximum Vegetation Clearance
11 kV 9 m 4m on either side of the centre line will be cleared. Grass and scrubs will be managed in accordance with Annex B (refer to 240-52456757) which is biome and land use dependant
22 kV 11 m 4m on either side of the centre line will be cleared. Grass and scrubs will be managed in accordance with Annex B (refer to 240-52456757) which is biome and land use dependant
88 kV 11 m 5 m on either side of the centre line will be cleared. Grass and scrubs will be managed in accordance with Annex B (refer to 240-52456757) which is biome and land use dependant
132 kV 15,5 m 8 m on either side of the centre line will be cleared. Grass and scrubs will be managed in accordance with Annex B (refer to 240-52456757)
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 10 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
which is biome and land use dependant
220 to 765 kV
22 m to 40 m Clear from the centre of the power line up to the outer conductor, plus an additional 10 meters on either side. Grass and scrubs will be managed in accordance with Annex B (refer to 240-52456757) which is biome and land use dependant.
533 kV DC 15 m 8 m either side of the centre line will be cleared. Grass and scrubs will be managed to a width of 15 meter either side of the centre of the line
4. Authorisation
This document has been seen and accepted by the Vegetation Care Group.
Name and surname Designation
Richard Chinzvende Senior Manager Transmission Division
Hein Vosloo Senior Manager Transmission Division
Louis Maleka Senior General Manager Distribution Division
Deidre Herbst Eskom Environmental Manager Sustainability Division
5. Revisions
Date Rev. Compiler Remarks
Jan 2014 1 I Pillay Scheduled review of document and number changed to 240-70172585
Sept 2007 0 D Lucas Document changed to standard
6. Development team
The following people were involved in the development of this document:
Vegetation Care Group
R Kruger
I Pillay
H Vosloo
K Kraft
M Michael
C Pelser
R Chinzvende
N Ockhuis
7. Acknowledgements
Vegetation Care Group
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 11 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
8. Annexures
A. Impact Assessment
B. Implementation Timeframe
C. Training or Communication
D. Special tools, equipment or software
E. Biomes and Vegetation Types
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 12 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Annex A – Impact assessment (Normative – for Eskom internal use only)
Impact assessment form to be completed for all documents.
A.1 Guidelines
All comments must be completed.
Motivate why items are not applicable (n/a).
Indicate actions to be taken, persons or organizations responsible for actions and deadline for action.
Change control committees to discuss the impact assessment and, if necessary, give feedback to the compiler regarding any omissions or errors.
A.2 Critical points
A.2.1 This standard prescribes the minimum requirements for vegetation management in Eskom.
A.3 Impact on stock holding and depletion of existing stock prior to switch over.
Comment: None
A.4 When will new stock be available?
Comment: Not applicable
A.5 Has the interchangeability of the product or item been verified - i.e. when it fails is a straight swop possible with a competitor's product?
Comment: Not applicable
A.6 Identify and provide details of other critical (items required for the successful implementation of this document) points to be considered in the implementation of this document.
Comment: Not applicable
A.7 Provide details of any comments made by the Regions regarding the implementation of this document.
Comment: (N/A during commenting phase)
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 13 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Annex B - Implementation timeframe
B.1 Time period for implementation of requirements.
Comment: Vegetation contracting in the 2013 financial year
B.2 Deadline for changeover to new item and personnel to be informed of DX wide change-over.
Comment: 2015
B.3 Buyers Guide and Power Office
B.3.1 Does the Buyers Guide or Buyers List need updating?
Comment: No
B.3.2 What Buyer’s Guides or items have been created?
Comment: None
B.3.3 List all assembly drawing changes that have been revised in conjunction with this document.
Comment: None
B.3.4 If the implementation of this document requires assessment by CAP, provide details under 5
B.3.5 Which Power Office packages have been created, modified or removed?
Comment: Not applicableCAP / LAP Pre-Qualification Process related impacts
B.4 Is an ad-hoc re-evaluation of all currently accepted suppliers required as a result of implementation of this document?
Comment: Not applicable
B.5 If NO, provide motivation for issuing this specification before Acceptance Cycle Expiry date.
Comment: This process is a Strategic Sourcing by Commercial and Procurement.
B.6 Are ALL suppliers (currently accepted per LAP), aware of the nature of changes contained in this document?
Comment: Not applicable
B.7 Is implementation of the provisions of this document required during the current supplier qualification period?
Comment: No
B.8 If Yes to B.7, what date has been set for all currently accepted suppliers to comply fully?
Comment: Not applicable
B.9 If Yes to B.7, have all currently accepted suppliers been sent a prior formal notification informing them of Eskom’s expectations, including the implementation date deadline?
Comment: Not applicable
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 14 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
B.10 Can the changes made, potentially impact upon the purchase price of the material/equipment?
Comment: Not applicable
B.11 Material group(s) affected by specification: (Refer to Pre-Qualification invitation schedule for list of material groups)
Comment: Not applicable
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 15 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Annex C - Training or communication
C.1 Is training required?
Comment: No
C.2 State the level of training required to implement this document. (E.g. awareness training, practical / on job, module, etc.)
Comment: Not applicable
C.3 State designations of personnel that will require training.
Comment: Not applicable
C.4 Is the training material available? Identify person responsible for the development of training material.
Comment: Not applicable
C.5 If applicable, provide details of training that will take place. (E.G. sponsor, costs, trainer, schedule of training, course material availability, training in erection / use of new equipment, maintenance training, etc).
Comment: Not applicable
C.6 Was Technical Training Section consulted w.r.t module development process?
Comment: Not applicable
C.7 State communications channels to be used to inform target audience.
Comment: Not applicable
Document Classification: Controlled Disclosure
VEGETATION MANAGEMENT AND MAINTENANCE WITHIN ESKOM LAND, SERVITUDES AND RIGHTS OF WAY
Unique Identifier: 240-70172585
Revision: 1
Page: 16 of 17
ESKOM COPYRIGHT PROTECTED
When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Annex D - Special tools, equipment, software
D.1 What special tools, equipment, software, etc will need to be purchased by the Region to effectively implement?
Comment: None
D.2 Are there stock numbers available for the new equipment?
Comment: Not applicable
D.3 What will be the costs of these special tools, equipment, software? N/A
D.4 What total costs would the Regions be required to incur in implementing this document? Identify all cost activities associated with implementation, e.g. labour, training, tooling, stock, obsolescence
Comment:
Budgets provided for in the Strategic Sourcing for vegetation management at national level Allocation to Operating Units will arise from the National Contract establishment
Impact assessment completed by:
Name: Rudi Kruger
Designation: Corporate Specialist
Document
VEGETATWITHIN ESOF WAY
W
Different veContract Svegetation m
(Source: Na
Classificati
TION MANASKOM LAN
When download
egetation spSpecification managemen
ational Protec
on: Control
AGEMENT AND, SERVIT
ded from the W
to ensu
Annex
pecies pose for Vegeta
t within spec
cted Areas E
led Disclosu
AND MAINTUDES AN
ESKOM C
WEB, this docu
re it is in line w
x E: Biom(Info
different thation Managcific biomes.
Expansion St
ure
TENANCE D RIGHTS
COPYRIGHT P
ment is uncont
with the authoriz
mes and Vrmative)
reats and regement Serv
trategy, Depa
Uniqu
Revis
Page
PROTECTED
trolled and the
zed version on
Vegetatio
equire differvices on Es
artment of E
ue Identifier:
sion:
e:
responsibility r
n the WEB.
n types
rent treatmeskom Netwo
nvironmenta
240-701725
1
17 of 17
rests with the u
nts. Refer torks (240-5
al Affairs, Ma
585
user
to the Esko52456757) fo
y 2010)
m or