equipment at hps

Upload: sam

Post on 05-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Equipment at HPS

    1/60

    Electro-mechanical Equipment

    in Hydro Power Station

  • 7/31/2019 Equipment at HPS

    2/60

    Main Electro-Mechanical Equipments

    Turbine MIV (Spherical Valve)/Butterfly Valve Governing System

    Mechanical Auxiliaries like Cooling water system, drainage

    dewatering system, Fire fighting system HVAC etc. Generator Electrical Auxiliaries like Bus Duct, LT/HT switchgears, DC

    battery system, earthing, cabling, Station/Auxiliary Transformer etc. Generator Transformers

    Switchyard and Pot head yard XLPE Cables/Tie line Control and Instrumentation Systems( SCADA)

  • 7/31/2019 Equipment at HPS

    3/60

    Hydraulic Turbines

    Hydraulic Turbines

    Impulse Turbine Reaction Turbine

    Pelton Turbine Francis Turbine

    Propeller Turbine

    Kaplan Turbine

    Bulb Turbine

    Deriaz Turbine

  • 7/31/2019 Equipment at HPS

    4/60

    Types of Hydraulic Turbines

    Reaction Turbines Derive power from pressure drop across turbine

    Totally immersed in water

    Angular & linear motion converted to shaft power Propeller, Francis, and Kaplan turbines

    Impulse Turbines Convert kinetic energy of water jet hitting buckets

    No pressure drop across turbines

    Pelton, Turgo, and crossflow turbines

  • 7/31/2019 Equipment at HPS

    5/60

    Pelton Turbine

  • 7/31/2019 Equipment at HPS

    6/60

    PELTON ARRANGEMENT

  • 7/31/2019 Equipment at HPS

    7/60

    Francis Turbine

    Runner

    Spiral CasingSectional View

  • 7/31/2019 Equipment at HPS

    8/60

    Kaplan Turbine

  • 7/31/2019 Equipment at HPS

    9/60

    Deriaz Turbine

  • 7/31/2019 Equipment at HPS

    10/60

    Spiral case and wicket gates/Nozzles- to direct and control the

    water entering the turbine runner. The spiral case is a steel-linedconduit connected to the penstock or intake conduit, and itdistributes flow uniformly into the turbine. Wicket gates areadjustable vanes that surround the turbine runner entrances andthey control the area available for water to enter the turbine.

  • 7/31/2019 Equipment at HPS

    11/60

    SELECTION CRITERIA FOR TYPE OF HYDROTURBINE

    Depends mainly on:

    Head availableSpecific Speed

    Impulse Turbine :- Pelton Wheel turbine for Head>300m

    Reaction Turbine:- Francis Turbine for Head 30m to 400mKaplan Turbine for Head 10m to 60m

    Bulb/Tubular Turbine Head 3 to 30m

    In the overlapping zone of head more detailed analysis is required fromtechno-economic considerations.

  • 7/31/2019 Equipment at HPS

    12/60

    Overlapping Regionbetween Francis

    and Pelton Turbine

    TapovanVishnugad,Head-494,

    Francis Sp.Speed-78

    LoharinagPala. Head-438, FrancisSp. Speed-

    85.3

    LoharinagPala. Head-438, PeltonSp. Speed-

    56

    TapovanVishnugad,Head-494,Pelton Sp.Speed-54.6

    Figure 1: Selection of

    turbines; Head vs

    Specific Speed (Ns)

    (Source:IS:12837:1989)

  • 7/31/2019 Equipment at HPS

    13/60

    Turbines of NTPC Projects

    PROJECT TYPE OF TURBINE

    Koldam(4X200 MW) Francis

    Loharinag Pala(4X150 MW) Pelton

    Tapovan Vishnugad(4X130 MW) Pelton

    Lata-Tapovan(3X57 MW) Francis

    Rammam Pelton

  • 7/31/2019 Equipment at HPS

    14/60

    Main Inlet Valve

    Main inlet valves at the inlet of the turbine areinstalled to isolate the flow in case ofmaintenance and emergency .

    Spherical ValveGenerally used as Main Inlet Valve for high headinstallation in case of the Pelton type of turbine (In LNP&TVN)

    Butterfly valveGenerally used as Main Inlet Valve for medium headinstallation in case of the Francis type of turbine (InKoldam) and as Penstock valve (e.g. LNP& TVN)

  • 7/31/2019 Equipment at HPS

    15/60

    Cross-section of Power house -LNP

  • 7/31/2019 Equipment at HPS

    16/60

    L-section of Power house -LNP

  • 7/31/2019 Equipment at HPS

    17/60

    MIV floor drawing -LNP

  • 7/31/2019 Equipment at HPS

    18/60

    Governing System

    It regulates the speed and the output of the Turbine-Generatorunits by controlling the position of the wicket gates (in Francis)and Nozzles (in Pelton) to adjust the water flow through theturbine.

    The hydraulic turbine governor is equipment to control the guidevanes/ nozzles by detecting the turbine speed and the opening ofthe guide vane/nozzles in order to keep the turbine speed stableor to regulate its output.

    Accordingly the controllability of the power station and the quality

    of the electric power depends upon the performance of thegovernor.

    It operates the Deflector (in Pelton) in case of sudden loadrejection to divert the water jet.

  • 7/31/2019 Equipment at HPS

    19/60

    Contd

    Main components of the Governor systemOil Pressure UnitPressure accumulatorElectro-Hydro actuatorPressurizing system

    Air Pressure (40-70Kg/cm2) Nitrogen pressure (100 Kg/cm2 and above)

    High pressure systems are compact as compared to the Lowpressure system.

    Due to space constraints in case of underground Power house,generally high pressure system is used .KoldamAir pressure systemLNP&TVN- Nitrogen/Air High Pressure System

  • 7/31/2019 Equipment at HPS

    20/60

    Schematic diagram of Governor

  • 7/31/2019 Equipment at HPS

    21/60

    DEFLECTOR SERVOMOTOR

  • 7/31/2019 Equipment at HPS

    22/60

    LINKAGE ARRANGEMENT OF

    DEFLECTOR SERVOMOTOR

  • 7/31/2019 Equipment at HPS

    23/60

    NOZZLE SERVOMOTOR

  • 7/31/2019 Equipment at HPS

    24/60

    OIL PRESSURE UNIT

  • 7/31/2019 Equipment at HPS

    25/60

    Mechanical Auxiliaries

    Cranes

    Cooling Water System & General water system

    Fire Fighting system

    Air conditioning and Ventilation System Drainage and dewatering system

  • 7/31/2019 Equipment at HPS

    26/60

    Cranes

    Cranes used in the hydro-power house Power house crane

    Transformer house crane (in case of underground PH)

    Butterfly valve house crane

    Capacity of the PH crane is decided by heaviest

    equipment (Generally Generator Rotor) to be lifted bythe crane.

    When the weight of the heaviest equipment is veryhigh then 2 PH cranes are used in the tandem

    PH Crane is one of the most important equipmentbecause it plays a major role in the erection of theequipments.

  • 7/31/2019 Equipment at HPS

    27/60

    TF and BF valve House crane

    TF hall crane is used for the erection andmaintenance of the GIS equipments.

    BF valve house crane is used for the

    erection and maintenance of the Butterflyvalve.

  • 7/31/2019 Equipment at HPS

    28/60

    Cooling Water System

    Water is used to cool the various equipments like Generator air cooler

    Thrust bearing

    Guide bearing/Shaft seal

    Generator transformer

    Due to heavy silt content in river water closed loopcooling system is adopted and circulating water is

    cooled in Plate heat exchanger (PHE).

    Koldam, LNP &TVN- closed loop cooling system.

  • 7/31/2019 Equipment at HPS

    29/60

    Schematic diagram of CWS-LNP

  • 7/31/2019 Equipment at HPS

    30/60

    COOLING WATER SYSTEM

  • 7/31/2019 Equipment at HPS

    31/60

    COOLING WATER PUMPS

  • 7/31/2019 Equipment at HPS

    32/60

    COOLING WATER FILTERS

  • 7/31/2019 Equipment at HPS

    33/60

    Air conditioning and ventilation

    system Air conditioning units (For control room , Shift

    engineer room and conference room )

    Ventilation Supply and Exhaust air fans Supply and return air ducts

    Air Handling Units

  • 7/31/2019 Equipment at HPS

    34/60

    Air conditioning and ventilation system- LNP

  • 7/31/2019 Equipment at HPS

    35/60

    Fire Protection system

    Fire alarm and Detection system Bymeans of Smoke detector, heat detector

    Protection system

    Water based Hydrant system

    Medium velocity spray system

    High velocity spray system

    Inert gas clean agent system

    Portable fire extinguisher

  • 7/31/2019 Equipment at HPS

    36/60

    Generator

    Convert the mechanical power produced by theturbine into the electrical power.

    Major Components- Shaft : coupled with turbine shaft and rotates synchronously.

    Rotor :series of large electromagnets that spins inside Stator.

    Stator : a tightly-wound coil of copper wire around rotor.

    Excitation system: sends an DC current to the rotor.

    As the turbine blades turn, so do a series of magnetsinside the generator, Giant magnets (i.e. rotor) rotatepast copper coils (i.e. Stator), producing alternatingcurrent (AC).

  • 7/31/2019 Equipment at HPS

    37/60

    A cross- sectional view of Hydroturbine-Generator Unit

  • 7/31/2019 Equipment at HPS

    38/60

    Generator parameters Output capacity in KVA Rated speed

    Rated Voltage Power factor Insulation system Reactive power capability Short Circuit Ratio (SCR) Inertia constant/Fly Wheel Effect Generator efficiency

    Bearing arrangement Cooling system Excitation system

    Bearing arrangement Umbrella type- Thrust bearing is placed below the rotor, a guide bearing

    surrounds it . Mostly used for higher diameter and lower speed.

    Semi-Umbrella type - Thrust bearing is placed below the rotor and guidebearing is installed above the rotor.

    Suspended type - combined thrust bearing and guide bearing on topbracket above the rotor

  • 7/31/2019 Equipment at HPS

    39/60

    Cooling system of Generator

    Air cooling is used for large hydro generators

    Cooling of the machine should be as uniformas possible.

    Cooling is achieved by forced air cooling bynatural fan action of the rotor or withsupplementary motor operated cooling fans

    In our design, cooling is achieved by axial fanfitted on rotor.

  • 7/31/2019 Equipment at HPS

    40/60

    EXCITATION SYSTEM

    STATIC EXCITATION SYSTEMStatic, potential source rectifier exciters are generally used for medium to large generators.They are also used for smaller generating sets, partly owing to the free choice of locationand the reduced length of the set and because of the fast-acting response to networktransients. Static potential source rectifier exciters derive the necessary electrical powerdirectly from the terminals of the generator. They consist of a power transformer, thethyristor control element, the electronic regulator and the de-excitation unit.

    BRUSHLESS EXCITATION SYSTEMThe essential components of a brushless exciter system are the ac exciter machine withits rectifier bridge and the electronic regulator. Power for the voltage regulator can beprovided by a permanent magnet generator or via a transformer from the generatorterminals. The brushless exciter consists of a salient-pole synchronous generator with athree-phase winding in the rotor and a dc exciter winding in the stator. It is mounted on thegenerator shaft. At the non-driving end of the rotor is the diode carrier ring with six silicondiodes in a bridge connection.

  • 7/31/2019 Equipment at HPS

    41/60

    Transformers

    A transformer is an electrical device that takeselectricity of one voltage and changes it into another

    voltage.

    Type of TF used in hydro power plant Generator Transformer- It takes the low voltage Supply from the

    Generator and converts it into High voltage to be transmitted to the Grid.

    Unit auxiliary Transformer- It takes the supply from the generatoroutput and converts it to low voltage for the auxiliary consumption of the unit.

    Station Transformer - Used to feed the equipments which are common

    for the station.

  • 7/31/2019 Equipment at HPS

    42/60

    Electrical Single Line Diagram

  • 7/31/2019 Equipment at HPS

    43/60

    Classification based on Cooling arrangementof TF Air cooled

    Water cooled

    Koldam LNP

    TVN

  • 7/31/2019 Equipment at HPS

    44/60

    Switchyard

    It is an interface between generating Unit andGrid.Used to evacuate the generated power to grid.

    Elements of Switchyard: Bus bar Insulators

    Circuit Breakers (SF6, Vacuum, Air, Gas etc.) Isolators Current Transformer (CT) Capacitive Voltage Transformer (CVT) Surge Arrestor Lightning Protection System Wave Trap

  • 7/31/2019 Equipment at HPS

    45/60

    Types of Switchyard

    SURFACE

    low cost, Large space requirement, In case of steepslope Stepping of the area Under ground Due to space constrain GIS (Gas insulated

    switchyard ), Small area requirement.

    Factor affecting selection of type of AIS and

    GIS Space Terrain Cost

    Koldam Over ground

    LNP - GIS TVN - GIS

  • 7/31/2019 Equipment at HPS

    46/60

    GIS Insulating Medium SF6 Low space requirement due to reduction in clearances Unaffected by climatic conditions such as rains etc. No corona losses SF6 has excellent properties to be used as an insulating medium,

    very high dielectric strength, chemically inert, non-inflammable, non

    poisonous Costly equipments Online monitoring of pressure of SF6 gas is required Main features: pressure of SF6 gas selected from 5-40 bar

    depending upon the requirements Bare conductors run inside metallic enclosures surrounded by

    pressurized sf6 gas All CTs, circuit breakers, PTs etc are inside the metal clad

    enclosures GIS will be used first time in NTPC in Loharinag pala and Tapovan

    Vishnugad HEPP

    GAS INSULATED

  • 7/31/2019 Equipment at HPS

    47/60

    SWITCHGEAR

  • 7/31/2019 Equipment at HPS

    48/60

    XLPE Cable

    XLPE STANDS FOR Cross linked polyethyleneinsulated power cable (XLPE cable)

    XLPE cable is used as interconnecting circuitbetween GIS and transmission lines through

    overhead pothead yard.

    XLPE cables are generally used because thedistance between GIS and pothead yard is moreand through a Cable ventilation tunnel.

    400 KV XLPE cables are used for first time in NTPCin Loharinag Pala and Tapovan Vishnugad HEPP

  • 7/31/2019 Equipment at HPS

    49/60

    XLPE CABLES..

  • 7/31/2019 Equipment at HPS

    50/60

    Electrical Auxiliaries

    BUSDUCT

    DC supply system

    Grounding system

    Illumination

  • 7/31/2019 Equipment at HPS

    51/60

    BUS DUCTS AND UCBs

  • 7/31/2019 Equipment at HPS

    52/60

    BUS DUCT

    Bus ducts

  • 7/31/2019 Equipment at HPS

    53/60

    Bus ducts

  • 7/31/2019 Equipment at HPS

    54/60

    DC supply system

    D.C. Supply distribution systems typicallycontains:-

    Batteries

    Battery Chargers

    Distribution Boards

  • 7/31/2019 Equipment at HPS

    55/60

    D.C. Batteries Batteries are required at most of the hydro-electric stations for control alarm

    annunciation, protection, communication, emergency lighting and solenoidoperated valves and field flashing requirements of generating units. Ingeneral, lead acid batteries are widely used. The standard voltage rating forthe batteries used are 110 V or 220 V depending on the DC load of thepower station.

    Batteries are generally designed with 10% design margin and 25% of agingfactor. Small and medium hydro plant one battery set (110 V) with twobattery chargers and for large hydro stations, two battery sets (220 V each)and one 48 V battery set with two (2) chargers for each battery are generally

    recommended. Minimum load requirement on D.C. system is generator fieldflash load for one unit and emergency lighting.

    Battery Chargers The battery charger having rectifiers with thyristors are usually used for

    charging the battery system. The charging is generally in float charging i.e.the batteries are kept in float charging condition in the normal operation. In

    case of commissioning of the batteries and otherwise the boost charger isused to charge the boost batteries.

    G di S

  • 7/31/2019 Equipment at HPS

    56/60

    Grounding System

    Separate groundmat, if feasible, be provided for power house, switchyard,remote structures such as control buildings, communication buildings,

    spillway gate structures, storage buildings, etc.

    Power House Grounding System be designed to provide a maximum 1.0ohm resistance to ground.

    If the control, computer and communication rooms are located in electrically

    noisy areas (e.g. VFC drives(in case pumped staorage), high voltage GISequipment etc), a "High-frequency signal reference ground grid beneath afalse floor shall be considered, to provide a noise-free, low impedenceground to the equipment.

    Switchyard grounding electrode systems should be designed to provide amaximum of 1.0 ohm resistance to ground. The switchyard mat shouldextend 1.5 - 2.0 mts. outside the switchyard fencing.

    Touch and Step potentials limit be maintained to an acceptable value.

    Ill i i

  • 7/31/2019 Equipment at HPS

    57/60

    Illumination

    General indoor and outdoor lighting and receptacle are served by 3-, 4 wire

    A.C. system. Transformers and panels are located so as to optimize wiring andto limit voltage drops to acceptable values.

    Fluorescent lamps are most used in interior spaces

    High-density Discharge (HD)

    Sodium vapour lighting fixtures are preferred for outdoor lighting such as

    switchyards, spillways and dams, parking areas etc. Automatic switching viaphoto electric cells can be adopted for outdoor lighting to optimize powerconsumption.

    Metal-halide fixtures are used for certain indoor areas such as erection bay,generator hall, machine shop, turbine pit and other "high-bay" areas whereproper color redention is needed and long-life is essential.

    Emergency lighting is deployed in the event that normal A.C. power distribution

    system fails. The emergency requirement are at first met from the dieselgenerator sets and when all alternatives of A.C. supply fail, battery poweredemergency fixtures provide the minimum requirement of lighting. The batteryshould have sufficient capacity to provide 4 hours uninterrupted illuminationindependently.

  • 7/31/2019 Equipment at HPS

    58/60

    C&I COMPONENTS IN A TYPICAL

    HYDRO STATION

    1. MAIN PLANT CONTROL & INSTRUMENTATION SYSTEM

    TURBINE, GENERATOR & AUXILIARIES

    COOLING WATER SYSTEM

    DRAINAGE & DEWATERING SYSTEM

    FLOOD DETECTION SYSTEM

    2. SWITCHYARD SCADA AND SUBSTATION AUTOMATION SYSTEM

    3. DAM /RESERVOIR INSTRUMENTATION4. SPILLWAY INSTRUMENTATION

    C S S C

  • 7/31/2019 Equipment at HPS

    59/60

    CONTROL SYSTEM AUTOMATION HIERARCHY

    1. LOCAL

    2. UCB

    - DRIVE

    - SUB GROUP

    - GROUP

    3. Station

    - SUB GROUP

    - GROUP

    - STATION

    4. REMOTE (FUTURE)

    - GROUP

    - STATION

  • 7/31/2019 Equipment at HPS

    60/60

    THANK YOU