india: accelerating infrastructure investment …...this environmental and social due diligence...

76
Environmental and Social Due Diligence Report Project Number: 47083-004 December 2019 INDIA: Accelerating Infrastructure Investment Facility in India Tranche 3 Freedom Point Expressways Private Limited (Part 5 of 5) Prepared by India Infrastructure Finance Company Limited for the India Infrastructure Finance Company Limited and the Asian Development Bank.

Upload: others

Post on 13-Mar-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

Environmental and Social Due Diligence Report

Project Number: 47083-004 December 2019

INDIA: Accelerating Infrastructure Investment

Facility in India – Tranche 3 Freedom Point Expressways Private Limited (Part 5 of 5)

Prepared by India Infrastructure Finance Company Limited for the India Infrastructure Finance

Company Limited and the Asian Development Bank.

Page 2: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

Annexure -

Page 4: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 5: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 6: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 7: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 8: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

From To Obstruction Length

1 08+800 08+900 100 7

2 08+900 09+000 Bus Bay

3 09+000 09+460 460 31

4 09+460 12+400 NA

5 12+400 12+650 250 17

6 12+650 12+920 Cut

7 12+920 13+790 870 58

8 13+790 14+050 Cut

9 14+050 14+421 371 25

10 14+421 14+800 379 26

11 14+800 17+580 2780 186

12 17+580 17+910 Cut

13 17+910 18+020 110 8

14 18+020 18+300 Cut

15 18+300 18+640 340 23

16 18+640 18+900 Cut

17 18+900 20+560 1660 111

18 20+560 20+900 Cut

19 20+900 21+180 Cut

20 21+180 21+220 40 3

21 21+220 21+770 550 37

22 21+770 23+300 1530 102

23 23+300 23+650 Cut

24 23+650 23+750 100 7

25 23+750 23+960 Bus Bay

26 23+960 26+380 2420 162

27 26+380 27+000 PUP

28 27+000 27+350 350 24

29 27+350 28+850 VUP

30 28+850 30+150 1300 87

31 30+150 30+890 PUP

32 30+890 34+367 3477 232

33 39+300 40+000 NA

34 40+000 40+420 420 28

35 40+420 40+920 Cut

36 40+920 40+945 25 2

37 40+945 41+180 Cut

38 41+180 41+580 400 27

39 41+580 41+640 MNB

40 41+640 42+170 530 36

41 42+170 42+440 Cut

42 42+440 42+890 450 30

NH-24

LHS

Sr. no.Chainage Availability Nos. of

trees

Annexure -13

Page 9: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

From To Obstruction Length

LHS

Sr. no.Chainage Availability Nos. of

trees

43 42+890 43+020 130 9

44 43+020 43+200 180 12

45 43+200 44+150 NA

46 44+150 44+550 400 27

47 44+550 44+850 Cut

48 44+850 45+500 650 44

49 45+500 45+650 MJB

50 45+650 45+920 270 18

51 45+920 46+200 280 19

52 46+200 46+520 320 22

53 46+520 46+610 90 6

54 46+610 46+660 50 4

55 46+660 47+600 940 63

56 47+600 48+200 Toll

57 48+200 48+310 Cut & Truck Bay

58 48+310 48+380 70 5

59 48+380 48+650 Cut

60 48+650 49+100 450 30

61 49+100 49+370 Cut

62 49+370 49+700 330 22

63 49+700 50+500 Vup & Cut

64 50+500 51+100 600 40

65 51+100 52+320 VUP & MNB

66 52+320 52+520 200 14

67 52+520 53+140 PUP

68 53+140 53+220 80 6

69 53+220 53+550 Cut

70 53+550 54+030 480 32

71 54+030 55+190 1160 78

72 55+190 55+380 VUP

73 55+380 56+750 1370 92

74 56+750 56+820 MNB

75 56+820 56+890 70 5

76 56+890 57+330 Cut

77 57+330 58+200 NA

78 58+200 58+480 280 19

79 58+480 58+600 NA

80 58+600 58+920 Might be

81 58+920 61+600 NA

82 61+600 62+500 900 60

83 62+500 63+600 NA

84 63+600 64+000 400 27

85 64+000 64+300 NA

Page 10: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

From To Obstruction Length

LHS

Sr. no.Chainage Availability Nos. of

trees

86 64+300 65+550 1250 84

87 65+550 65+670 MNB

88 65+670 66+770 1100 74

89 66+770 67+050 Cut

90 67+050 67+550 500 34

91 67+550 67+730 Cut

92 67+730 67+820 90 6

93 67+820 67+930 MNB

94 67+930 68+600 NA

95 68+600 68+860 260 18

96 68+860 69+120 Cut

97 69+120 69+210 90 6

98 69+210 69+500 Cut

99 69+500 70+800 1300 87

100 70+800 71+000 Bus Bay

101 71+000 71+360 360 24

102 71+360 71+610 Cut

103 71+610 72+960 1350 90

104 72+960 73+240 280 19

35192 2365Total

Page 11: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

Annexure- 14

Page 12: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 13: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 14: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 15: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

Annexure-15

Page 16: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 17: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 18: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 19: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 20: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 21: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 22: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily
Page 23: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

1

4 Laning of Meerut – Bulandshahar section of NH-235 from Km 8.800 (design

Chainage Km 8.800) to Km 66.482 (design Chainage Km 73.512) in the state of

Uttar Pradesh on Hybrid Annuity Mode

NATIONAL HIGHWAYS AUTHORITY OF INDIA

Safety & Health Management Plan

FREEDOMPOINTEXPRESSWAY (Pvt.) Limited(An SPV for Development of Meerut - Bulandshahar Section of NH – 235; NEW NH – 334)

CIN: U45400UP2016PTC076383

EPC Contractor Checked By: (Concessionaire)

Reviewed By: (Concessionaire)

Approved By: (Client/IE)

Name

Designation

Signature

Date

Annexure -16

Page 24: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

2

Table of Content

Sl.No Description Page No.

1 Introduction & Statement of Purpose 3

2 Scope 4

3 Description of Project 5

4 Management Commitment 7

5 Organization & Responsibility 9

6 Communication with Employees 11

7 Training & Briefing 12

8 Hazard identification & Risk Management 13

9 Safe system of Work Procedures 14

10 Medical health Programme 16

11 Checking ,monitoring and improvement actions 18

12 Safety & Health review 19

13 Organizational Structure and H&S Management implementation 20

14 Control Measures 21

15 Appendix 1.-Training Matrix 28

16 Appendix-2 Statutory inspection programme 29

17 Appendix-3 Type & frequency of S& H training 30

18 Appendix-4 List of Checklist & Formats 31

19 Appendix-5 References 32

Page 25: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

3

1.0 INTRODUCTION AND STATEMENT OF PURPOSE

The purpose of the Safety & Health (S&H) Management Plan is to provide guidance for the

implementation of Safety and Health Management in the 4-laning of Meerut-Bulandshahr section of

NH-235 (New NH-334) Project. The S&H Plan is to assist FEPL in establishing, implementing and

integrating S&H control, monitoring and mitigation measures for the project.

FEPL shall carry out the work within the scope of the contract, directly with own employed labour and plant or with appointed sub-contractors. All sub-contractors are required to fully support the principles of the Safety & Health Management Plan and to cooperate with FEPL to ensure that the overall S&H objectives are maintained throughout the project. The S&H Plan applies to all personnel working on or visiting the site.

Page 26: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

4

2.0 SCOPE

The Safety & Health Plan reflect the high priority that FEPL Senior Management place upon the Safety

& Health at work. It also demonstrates FEPL’S commitment to ensure that all reasonably practicable

measures are taken to:

Comply with the relevant statutory and Contractual Safety and Health requirements.

Ensure the Safety & Health of all persons is not affected by the work.

Provide and maintain plant, places and systems of work that are safe and without risk to health

and the environment.

Ensure that all construction – planning takes into account the Safety and Health of all persons

that may be affected by the work.

Establish effective communication on Health & Safety matters with all relevant parties involved

in the Project works.

Effective control, Co-ordinate and monitor the activities of all personnel on the Project,

including contractors, in respect of Health, Safety, Environment and Security

Establish effective communication on Health & Safety matters with all relevant parties involved in the Project works.

Provide all personnel with adequate information, instruction, training and supervision.

Protect the Health & Safety of all persons engaged at work site.

Page 27: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

5

3.0 DESCRIPTION OF PROJECT 3.1 The scope of work involves:

Four Laning of Meerut-Bulandshahr Section of NH-235 (New NH-334) in the State of Uttar Pradesh

under NHDP Phase-IV on Hybrid Annuity Mode.

3.2 Details of Highways as per CA:

Four Lane Carriageway – Reconstruction : 61.19 Km

(Rigid Pavement – 59.962 Km. & Flexible Pavement – 1.228 Km.)

Service Road/Slip Road: 4.22 Km (At 3 Locations)

Design Chainage Proposed

Length* (m)

Carriageway

Side From To Width in m

27+770 28+530 2 x 760 7.0m Both

51+340 51+940 2 x 600 7.0m Both

54+350 55+100 2 x 750 7.0m Both

Bypass: 29.450 Km (04 Nos.)

Sl.

No.

Design Chainage

Length in km Type of Pavement

From To

LHS RHS

1 8+800 23+400 14.600 Rigid Rigid

2 23+400 34+600 11.200 Rigid Rigid

3 34+600 35+456 0.856 Flexible Flexible

4 35+456 38+978 3.522 Out of Scope

5 38+978 39+350 0.372 Flexible Flexible

6 39+350 73+512 34.162 Rigid Rigid

Sl. No. Bypass

Location

Design Chainage (km) Length

From To (Km)

1 Phapunda

Bypass

12+100 14+800 2.70

2 Kharkhuda

Bypass

17+700 20+900 3.20

3 Hapur Bypass

23+400 34+600 11.20

34+600 35+456 0.86

35+456 38+978 3.52

38+978 39+350 0.37

4 Gulaothi

Bypass

49+700 57+300 7.60

Total Length 29.45

Page 28: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

6

3.3. Details of structures as per CA: List of structures are given below.

Type of Culvert New Re-

Construct Repair/

Widening Total

Culverts 25 19 15 59

Minor Bridges 05 04 02 11

Major Bridges 01 01 01

Vehicular Underpass

(VUP) 03 - 01 04

Pedestrian Underpasses

(PUP) 04 - - 04

Subway 01 - - 01

ROB 01 - - 01

3.4 Details of Project Facilities as per CA: Toll Plaza: One Toll Plaza is proposed at Design Ch. 47+900 of Project.

Truck Lay-byes: One Truck Lay-Byes is proposed at Design Ch. 46+400 in Village Padao.

Bus Bays: There are 04 (Four) Bus Bays are proposed at following locations:

Sl. No. Existing

Chainage (km)

Design Chainage

(km)

Location/ Village

1 8+900 8+900 Meerut

2 22+900 23+600 Hapur

3 44+380 49+425 Gulaothi

4 64+000 71+000 Bulandshahr

Bus Shelters: There are 11 (Eleven) Bus Shelters are proposed at following locations

At Grade Intersections: There are 11 (Eleven) at Grade Intersections (Major Junctions) are proposed

in the project stretches.

Sl. No.

Existing Chainage(Km)

Design Chainage(Km)

Location

1 11+600 11+600 Alipur

2 13+900 13+900 Phaphunda

3 17+800 17+800 Kharkhoda

4 20+500 20+500 Lalpur

5 22+800 22+800 Kaili

6 On Proposed Hapur Bypass

26+900 Jogipura

7 28+400 Dastoi

8 36+200 41+200 Hadikpur

9 38+100 43+100 Padao

10 50+540 57+400 Mithipur

11 61+600 68+600 Jainpur

Page 29: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

7

4.0 MANAGEMENT COMMITMENT

4.1 Health, safety & Environment Policy

We, the management of FEPL are committed to the safe and efficient operation of our facilities. The

highest standards of equipment integrity and reliability are maintained to avoid risk to people and the

environment.

We are committed to:

The elimination of accidents and work-related ill health and the protection of the environment.

The management of Health, Safety and Environment (HSE) in the same way as any other critical business activity.

The efficient and responsible use of energy and materials.

The promotion of HSE management in all our sites.

The development of a culture -supported by publicity, training and education -which will result in sharing this commitment at all levels within the FEPL

We will pursue this commitment with a policy based upon

A well-structured HSE organisation in which competencies and responsibilities are clearly

defined to provide instruction to all employees in compliance with all applicable laws,

regulations and ethical standards.

The principles of prevention where measures will be taken to avoid, prevent, control and

restrict HSE related risks.

The development of action plans and the setting of targets which will be monitored measured

and reported to achieve continuous improvement.

A requirement that all contractors manage HSE consistent with this policy.

The recognition of employees' contributions to HSE management in their performance

appraisal when appropriate.

The management will visibly and rigorously support the implementation of this policy. We

expect the support of all employees and contractors in order to make FEPL HSE performance

one which will earn us the continuing confidence of our customers and the community at large.

We, the management of FEPL are committed to the safe and efficient operation of our facilities.

The highest standards of equipment integrity and reliability are maintained to avoid risk to

people and the environment.

Page 30: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

8

4.2 S&H OBJECTIVES

4.3 S& H TARGETS

Safety: Zero recordable first aid, medical aid or lost time cases of all labor on site.

Zero on site damage accidents and incidents.

Zero off site traffic incidents involving transport of personnel, materials and equipment to and from site.

Health: Optimization of the onsite working conditions, leading to a minimum of occupational sickness leave of all labor.

Safety: Prevention of all on site accidents and incidents potentially leading to injury of labor and third parties or damage to materials and equipment.

Minimization of offsite traffic incident potentially leading to injury of labor, third parties or damage to materials and equipment

Health: Protection of occupational health of all labor, in relation to the work and the working conditions

Page 31: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

9

5.0 ORGANISATION & RESPONSIBILITIES The organization for implementing the S&H requirements is shown under APPENDIX 1. The general responsibilities of project staff are described as below:

5.1 Project Manager The Project Manager has the ultimate responsibility for safety & health. He will:

Ensure that the S&H Policy is implemented and promoted

Assigned specific responsibilities to individual within the organization for its implementation.

Ensure that sufficient resources are allocated to meet the requirements of the Policies

Ensure that the applicable laws, regulations, ordinances, statutes, rules, codes and approvals

governing S&H requirements are complied with.

Regularly review the Policy and the S&H plan for their effectiveness.

5.2 HSE Manager/Officer

The HSE Manager/officer has a responsibility to the Project Manager for policy, coordination, audit

and act as a advisor on all matters concerning safety and health. The HSE Manager/Officer advises

and coordinates with other managers and employees / sub-contractors on matters relating to health &

safety. He will:

Have the authority and over all control on all Safety & health related matters and decision

making pertaining to safety & health

Coordinate all activities relating to the development ,distribution and implementation of the

policies.

Implement procedures for the collation, analysis and dissemination of information relating to

safety & health

Initiate the preparations of project specific safety & health

Coordinate safety & health auditing on a routine basis, and prepare program of inspections,

compilation of reports and follow-up on actions resulting from the inspections as properly

implemented

Carry out where appropriate accident and incident investigations.

Collect, analyse and maintain statistics on any incident at the place of work.

Organise Safety Committee meeting.

Conduct toolbox briefings, induction to new employees etc.

Record & distribute the minutes of safety & health meeting held.

Prepare monthly safety report, summarising the safety activities and programme carried out.

Prepare safe work procedures and Risk Assessment Summary

Monitor & manage the issuance of PPE and safety equipment.

Liaise with authorities on safety & health matters.

Recommend to Project Manager for STOP WORK ORDER

5.3 Managers, Engineers, Supervisors, General Foremen and Foremen

All Managers, Engineers, Supervisors, General Foremen and Foremen are responsible for ensuring that all employees/sub-contractors within the scope of his/her responsibility adhere at all times to the Policies and all supporting standards and procedures. He /she will:

Report any accident, incident or dangerous occurrence involving personnel or plant &

equipment to his/her immediate Manager and the HSE Manager / Officer

Cooperate and assist in the investigation of accident and incident

Page 32: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

10

Identify employees / sub-contractors safety & health training requirements.

Carry out regular assessment of their areas of responsibilities to identify safety and health

hazards

Prepare recommendation for improving safety & health performance

Conduct the pre-defined safety & health program and ensure that all workers are involved and

understand the purpose and objective of this program in achieving the defined safety & health

objectives. This will include safety induction, tool box talk, specific safety training, etc.

Ensure that notices and posters are displayed at strategic locations e.g., offices, canteen,

workshops, workers quarters, rest areas, etc.

Ensure that Safety is a line responsibility and that everyone on this job-site understands the

safety concept and show commitment and encourage workers to participate

Arrange for continuous training to cultivate a good and efficient safety culture for all workers.

5.4 Stores In-charge

To maintain high housekeeping standards and ensure that the personnel under him are

properly trained in housekeeping and safe storage of materials.

Possess licenses under Explosive Act, The petroleum Act & Rules, Gas Cylinder Rules and

other legal requirements.

To maintain Material Safety Data sheets and Inventory of chemicals for pilferage to ensure

security in accordance with S & H Management System.

To ensure that the material procured comply with the relevant standards.

Ensuring adequate stock of Personal Protective Equipment and other safety equipments.

5.5 Employees

It is the responsibilities of all employees to take reasonable care of the safety and health of

themselves and of other persons who may be affected by their acts or omission at work. It is the

responsibilities of all employees to have regard for the environment in which they live and work. All

employees are therefore required to:

Familiarize themselves with the provisions of the S&H Policy, and any specific procedures

relating to health & safety at their place of work

Act and work in safe manner to avoid harm to self or others

Report any accident and incidents to their immediate superiors and S&H Officer

Report any unsafe working conditions to immediate superior and S&H Officer

Cooperate with Management at all times on matter relating to health & safety

Ensure that equipment issued to them is correctly used and properly maintained so that it

presents no threat to health or safety.

Wear protective clothing/equipment whenever instructed or when circumstances required its

use

Maintain a good standard of housekeeping in the areas in which they work

Carry out their duties in such a manner as to ensure compliance with all legislation relating to

individual job responsibilities, Policies and supporting procedures

Comply with all Safety requirements when working on the job-site

Page 33: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

11

6.0 COMMUNICATION WITH EMPLOYEES

Information is relayed to personnel through training program, safety meetings, safety notice boards, etc. Copies of all pertinent document, procedures, etc. relating to health and safety will be freely available to individuals. Nominated/appointed HSE representatives will be communicated on measures designed to ensure health and safety at work. Consultations will include matters such as S&H objectives, changes and modifications, implementation of control measures, introduction of Personal Protective Equipment, and any other S&H matters which will directly affect the employees. Appropriate facilities and assistance will be provided as may be required for the employees to carry out their job function. In addition to the HSE representatives, other employees shall be directly consulted on matters and changes which directly affect that group. Communication is also established through the pre-defined training program and briefing with the Supervisors, Foremen and Management personnel. The Project Manager will chair the HSE Committee Meeting. This meeting is devoted to the communication of and discussion on S&H matters. The S&H meeting will be held once per month. Attendance is compulsory for all HSE representatives. The HSE officer. The meeting shall include discussion and interaction by all attendees. The following issues, among others will be discussed in the Meeting.

Policy changes

Safety & Health performance statistics

Audit & Inspection results

Unsafe acts, infringement and non-compliance to safety & health requirements

Corrective & preventive actions

Training & safety promotion activities.

Page 34: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

12

7.0 TRAINING & BRIEFING

All employees and sub-contractors are required to attend the in-house S&H Induction Program before

the commencement of work. The program will provide the basic training on requirement for safe work

practices on site, safety rules & regulations to comply. The S&H Policy & Objectives will be made

aware in this Induction. Suppliers and vendors who are required to be frequently on the site shall have

to attend the in-house S&H Induction Program also.

Each manager is required to identify the training needs of the people in his respective work group and

to plan and allocate time and other resources to ensure their fulfilment. Experienced internal staff such

as the Safety Officer will facilitate the in-house training.

On-site toolbox briefings will be conducted on a regular basis. This will be a part of the pre-task

briefing for employees to communicate the hazards, risks, and impacts associated with the specific

work, prior to the start of that work activity. Topic of training covered takes into consideration the latest

activities at the work place and shall also include topics such as Accidents. Incidents, Near Misses,

Vehicle Accident, Property Damage, Fire, First Aid Cases, Reportable Cases, Electrical safety, LTA

and Fatalities. This is to enhance the awareness of workers on Safety.

All Drivers, including Light and Heavy Vehicles (Truck), shall have valid driving license before they are

permitted to enter the construction area and on the existing roads. The performance of drivers will be

tracked and any non-compliance to company’s rule & regulations or any regulatory laws or project

requirements will be dealt with in accordance to company procedures.

Records of Induction, Trainings, driving license evidence, toolbox meeting shall be maintained.

Page 35: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

13

8.0 HAZARD IDENTIFICATION & RISK MANAGEMENT

The process for hazard identification and risk assessment will be utilized to determine areas where the

project site is classified as hazardous. Once the potential for accident has been identified and

assessed, the appropriate control measures will be implemented.

Work place hazards will be identified through:

Inspections

Specific review (e.g. noise, air quality, equipment guarding, etc.)

Review of incident/accidents reports

Issues identified and raised by personnel

All identified potential hazards, unsafe conditions or unsafe acts must be reported promptly to the

appropriate Manager and S&H Officer who takes or ensure that the appropriate actions are taken for

their elimination or mitigation. Where necessary the advice of the S&H Officer can be obtained to

ensure that the appropriate measures for health and safety of personnel are implemented

Regular inspections are carried out to identify potential hazards, unsafe conditions or unsafe acts and

appropriate remedial actions are taken.

Hazard control measures will be implemented to ensure that the risk is eliminated or reduced to an

acceptable level.

Page 36: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

14

9.0 SAFE SYSTEM OF WORK & PROCEDURES

In all area of work, the responsible Manager ensures that a safe system of work is operated. Where potentially hazardous situations exist, The Permit to work procedure is used. The S&H Plan has provided the general guidelines in the implementation of a safe & healthy work procedure for the site. The safety procedures shall be developed from the available information, manuals, relevant project standards and complying with the guidelines from the specified statutory & regulatory requirements The content of the safety procedure shall comply with the following points-

Description of health & safety tasks for specific work

Skills of employed workforce

Instruction & training of workforce before execution.

Needs for safety coordination with other workers

Prevention of accidents and incidents

Health and safety measures taken in advance for the execution.

Technical equipment and safety facilities

Personal protection equipment

Special safety equipment for the job

Safety distance & barring of the work area

The details of Risk Assessment to be included in the method statement as per following.

Activity Hazard Risks Control Measures Monitoring &

compliance Responsibility

9.1 Protective Clothing & equipment

Where it is accessed that the hazards relating to the employees’ job require it, personal protective clothing and equipment is provided by the Site Management. All equipment will conform to a relevant Indian standards or standard set by the authority. 9.2 Site Facilities & Equipment

The Project Manager shall ensure that facilities and equipment are designed, operated and maintained in accordance with standard and applicable legislation and comply with approved work practices Managers will cooperate with the Project Manager to ensure as far as practicable that the facilities and equipment are safe and without risk to health, safety or the environment.

Page 37: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

15

9.3 Sub-Contractors Management All companies contracted to carry out work for the Project are obliged in their work to comply with all applicable health, safety and environmental laws and meet the industry standards. An integral part of the contract selection process is a review of a contractor’s working practices and safety performance Sub-contractors shall cooperate with Management on all matters relating to the implementation of safety, health and protection of the environment 9.4 Plant & Equipment

Before the introduction of new plant and equipment, a full technical appraisal is carried out. This is to ensure that when in normal use, the plant and machineries are within the limit of risks to health, safety and the environment required by legislation and to comply with company standards. Management will ensure that the required permits and approval for the plant and equipment is available and valid. The plant and equipment which requires competency certificate includes (but not limited to):

All earth moving equipment

All lifting equipment

All mobile elevated work platform equipment

All other work equipment deemed to require additional training Management will ensure that the only operators of plant and equipment who are competent and qualified are employed to operate the equipment they are assigned to. Operators will be selected based on their experience, and evidence of competencies (license) All Plant and Equipment shall have the periodic inspections / checks performed using the relevant checklist. Site Vehicles, machineries and Work Equipment’s where applicable, shall be fitted with Audible Reverse Alarm. Other safety features which are peculiar to specific machinery must be maintained in good working condition. 9.5 Emergency Preparedness & Response Emergency response plan shall be developed to manage effectively a wide range of incidents that may occur at the project site. This includes emergency plans for fire, soil collapse and road accident, and other emergency as identified which may affect the project. Personnel are required to familiarize themselves with the procedures. Such procedures shall be displaced at notice boards where appropriate, and made available to all. Teams of employees will be selected and trained to be involved in handling emergency situation. These teams will be called into action in times of emergency, and will be given other authorities beside their usual work responsibilities. In the event of road traffic accident, the appropriate channel of information shall be established where the line managers, S&H Officer, Project Manager, and Employer shall be informed, in addition to the relevant authorities associated with the accidents, such as the police, hospital, fire brigade, etc.

Page 38: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

16

10.0 MEDICAL & HEALTH PROGRAMME The site Management must ensure that only medically fit personnel are employed for the specific work. A surveillance program will be implemented where applicable by regulations, to assess employee’s suitability, health condition and the health protection required for the specific work. Health education will be a part of the toolbox briefings. 10.1 First Aid First aid facilities shall be provided at the camp area or within close distance of construction area for medical treatment of employees and sub-contractors in the performance of the works. The name and telephone numbers of first aid facilities are to be listed and posted for awareness. 10.2 Site Sanitation & Housekeeping Management will provide and maintain facilities for waste disposal, sanitary and washing, and drinking water for the use of employees. Such facilities will be maintained and regulated according to applicable laws and standards, so as to provide a healthy environment for the employees. Being neat, tidy and organized at the site is very important, as this carry a lot of weight in the successful operation of work. Managers, engineers, supervisors and employees are instructed to maintain proper housekeeping standards:

Clean all tools, equipment and work areas at the end of each work days

Dispose all waste in proper places for efficient and safe removal

Keep floors, stairways, and aisles free of any obstruction.

Properly stack, store and put away materials, tools, and equipment 10.3 Substance Abuse

If an employee who unlawfully possess or misuses or whose performance is impaired by the abuse of controlled drugs or alcohol whilst on company business or premises, he/she will be subjected to Management disciplinary procedures up to and including dismissal. 10.4 Welfare Facilities

The welfare of the workers will be given priority in this project to ensure that their physical and social

needs are being fulfilled: The following will be provided:

Proper accommodation.

Kitchen, Dining Hall facilities

Toilet facilities,

Garbage and Waste Disposal facilities

Adequate fire fighting equipment (i.e. Fire extinguishers, fire hose reels etc)..

First Aid facilities

Page 39: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

17

Water supply and sanitary requirements

Regular Maintenance of Buildings, Accessories and Cleanliness

Adequate lighting around Buildings and Workers Camp

Appropriate Personal Protective Equipment such as Safety Helmet, High visible Vest, Foot

Protection.

Page 40: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

18

11.0 CHECKING, MONITORING & IMPROVEMENT ACTIONS

11.1 Inspection, And Walk-About The HSE Manger will initiate safety & health inspections and audit program in conjunction with other HSE representatives & site representative Their frequency is governed by the level of activity on the site. Any serious hazards identified during an inspection which represents an immediate risk to safety or health will be remedied immediately.

As soon as practical, an inspection report will be prepared detailing any specific safety, health or the

environment hazards identified, and actions taken or recommendations made to mitigate them

Further inspections of any reported hazards must be undertaken, after appropriate action has been taken, to confirm the hazard has been mitigated The HSE Manager/officer will initiate a “safety walk-about” on an agreed schedule. In this program, managers and supervisors will join the HSE Manger/officer on a “walk-about” to observe the implementation of the safety & health program, and behaviour demonstrated by the employees. Unsafe behaviours will be corrected with immediate effects, whenever and where they are seen. 11.2 Accident Reporting and Investigation

All accidents, incidents and dangerous occurrences, no matter how minor it may be, must be reported to the Manager responsible and the HSE Manager/Officer. An initial investigation will be carried out by the line management The responsible manager will ensure that the accident/incidents are recorded, thoroughly investigated and preventive measure identified. He/she is assisted by the HSE Manager/ Officer in the investigation, identification of root cause and corrective & preventive action implementation. A standard format for the investigation report shall be developed which include all the required information, such as full description, the time and location, source, witness statement, photo, police/medical report of the accident/incident. The accident/incident report will include the immediate, corrective and preventive actions which will be implemented. Such improvement actions will be discussed in S&H meetings and communicated to employees via written instruction, toolbox briefings, notice boards or other forms of assimilating information.

Page 41: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

19

12.0 SAFETY & HEALTH REVIEW

The Project Manager will chair the review of the HSE Management System. Review of the S&H System will be initiated by the HSE Manager/Officer. The scope of the review will include

Result of S&H inspections

Client audit/inspection findings

Extent of compliance with respect to project requirements

Number and nature of S&H incidents

Corrective and preventive action implemented as a result of any incidents. The review of the S&H system will be the base for continuous improvement to the S&H system implemented for the project.

Page 42: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

20

13.0 ORGANISATION STRUCTURE FOR SAFETY & HEALTH MANAGEMENT IMPLEMENTATION

PROJECT

HEAD

HSE HEAD MGR/OFCR

MANAGEMENT REPRESENTATIVE

CONTRACTOR REPRESENTATIVE

EMPLOYEE REPRESENTATIVE

HEAD P&M

HEAD HIGHWAY

HEAD STRUCTURES

ADMIN OFFICER

ENGINEER/ SUPERVISOR HIGHWAY

ENGINEER/ SUPERVISOR STRUCTURE

HEAD QUALITY

ENGINEER/ SUPERVISOR P&M

Page 43: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

21

14.0 CONTROL MEASURES 14.1 Excavations Prior to excavation presence of any underground utility services shall be have been identified, located and if necessary, isolated.

Dependent on the nature of the soil condition excavations 1.50 meters or deeper should be shored or battened/stepped back in order to prevent collapse.

All excavations will be provided with suitable perimeter protection e.g. scaffold barriers.

Suitable means of access/egress shall be provided to excavations e.g. ramps, ladders, scaffold access. The location of the presence of any overhead lines and other obstructions must be identified.

Personnel will be kept clear of machinery whilst it is in operation, minimum distance of 5 meters.

Barriers and signs will be erected to keep unauthorized personnel clear.

Trucks used for the removal of spoil will be controlled and sited by a banks man.

The on-going provision of side supports shall be programmed into the work to maintain the integrity of the excavation.

Excavated soil will be stacked a minimum distance of one meter from the edge of the excavation edge.

Ground and Environmental conditions must be continuously monitored for change.

14.2 Working at heights: The primary means of achieving safe working conditions when working at heights is to provide adequate and sufficient access and egress arrangements and suitable working platforms at the place of work.

A toolbox Talk will be given to each person carrying out work at height. Following an assessment of the risks, supervisors will instruct personnel on the instructions and precautions to be followed when working at height.

Approved full body safety harnesses should only be used as a last resort where conditions make it impracticable to provide a safe working platform Fall Protection Equipment All personnel working above ground level will be provided with, and will use, appropriate fall protection equipment and PPE. Appropriate regulatory standards must be observed when using fall arrest equipment.

A competent person must regularly inspect fall protection equipment. It should also be maintained so that it remains satisfactory for use during the construction period. Effective actions must be taken to rectify any defects observed as a result of these inspections.

Fall protection equipment that has been deployed in a fall must be examined by a competent person and repaired or destroyed, as necessary.

Fall protection devices and systems will not be used for any other purpose than those for which they are designed.

Page 44: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

22

Safety Harnesses

Fall protection in the form of full body safety harnesses and lifelines must be used in situations where it is impracticable to provide primary systems. Whenever full body safety harnesses are used they must be secured to a secure anchorage point, running line or arrestor device.

Safety harnesses and lifelines will be used for working at elevations in excess of 1.5 metres or where a fall of this distance is possible. A proper anchor, mounted preferably overhead

Full body harness using double latch self-locking snap hooks at each connection.

Synthetic fibre lanyards Shock absorbers must be provided with the harness system in order to reduce the shock loading in the event of a fall.

A visual inspection of the fall arrest equipment and system is completed and any equipment that is damaged or has been activated is taken out of service.

Person(s) are competent to perform the work.

A fixed platform is used with guard or hand rails, verified by a competent person, or the safety harness which restricts to fall must be used. Ladders

Ladders should be used primarily as a means of access, NOT as a working platform. If work is required to be carried out from ladders, personnel shall use and wear approved safety harnesses as a means of fall protection. Ladders should be suited for the purpose for which it is to be used and free from defects. Ladders shall be set on a firm level base. Makeshift props should not be used to gain extra height or to level up stiles. Ladders should not cause a hazard by placing them where they may be struck or dislodged. Barriers should be placed around the foot of the ladder where necessary. Ladders should, wherever possible, be secured at the top and bottom by lashing, irrespective of whether metal clips or clamps are used. In cases where the ladder is unable to be secured, a person must steady the ladder by standing at the bottom and holding the ladder in place with one foot on the bottom rung. (Permitted only if the ladder is shorter than 5 meters). Ladders should not rest against any fragile surface or fitting. Ladders must extend at least 1.00 meters above the landing place unless some other suitable handhold is available. Scaffolds & Working Platform Erection, modification and dismantling activities of scaffolding work platforms shall be done only under the supervision of competent foreman and scaffolders. All scaffolding components used to connect the various members of a scaffold shall be of an approved type and shall be erected as per standard procedures.

Page 45: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

23

Scaffold shall be erected on a rigid base. All scaffolding components shall be used where it is

appropriate and secured well using appropriate tools. Before erecting any further lifts, a minimum of

three secured scaffold boards are to be used for erection and dismantling purposes Access is to be by

ladder. All scaffold erectors shall wear full body harness with double lanyard and will be anchored on

rigid part of the scaffold structure under erection/dismantling/modification on above shoulder level as

practicably possible.

Scaffold structures shall be inspected by competent person on weekly basis and tagged red or green

as per the condition of the structure.

14.3 Hazardous Materials

Information on the hazards of the materials is obtained from the manufacturer or supplier and

communicated to the users. Employees shall be trained in the safe use of the materials, including

personal protective equipment and emergency procedures.

Paints, thinners and solvents

Cleaning agents

Insulating materials such as fibre glass and ceramics

Cleaning agents, and sandblasting materials

Compressed gasses such as oxygen, nitrogen, argon, helium

Greases, oils, and other lubricants

Fuel gases such as acetylene & Propane

Epoxy resins

Sealants

Fuels

Asbestos products such as gaskets and sheeting materials

MSDS (Material Safety Data Sheet) of any material that can be hazardous to human life will be used to train related workforce & all MSDSs will be recorded in file as hardcopy.

14.4 Fire Protection

Adequate fire fighting equipment shall be provided and regularly checked and maintained.

Temporary fire protection equipment for the Worksite will be provided and may include but is not restricted to:

Quantities of flammable materials on site and particularly in work areas shall be kept to an absolute minimum and shall be properly handled and stored. Only approved containers, cans or portable tanks will be used for the storage and handling of flammable liquids. Manufacturer storage instruction shall be followed.

Storage areas are to be freely ventilated to eliminate any possible build-up of flammable vapour or gas and tanks and containers are to be located in bunded areas capable of containing any spillage or leak.

Static, portable and mobile plant and equipment is not to be refuelled with the engine running.

Fires and open type heating devices are prohibited on all sites and work areas.

All hot works and welding operations will be carried out under a permit to work system. The following controls will be put in place:

Page 46: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

24

All work activity will be coordinated with other activities in the area. Work areas are to be cleared of all combustible and flammable materials Fire blanket/fire retardant material will be used to cover any combustible materials that cannot be cleared

Appropriate fire extinguishers must be at the work area at all times and shall be regularly inspected (at

least once in a month) for proper functioning & record shall be maintained

14.5 Working with Electricity All permanent and temporary electrical installations are to be designed, installed, modified, maintained

and repaired by competent electrical persons

Any electrical systems, circuits, installations, equipment is to be safe for its intended purpose and

suitable inspected and tested before it is put into service and thereafter every months by a competent

electrical person.

All electrical circuits that shall be created to be protected by Earth Leakage Circuit Breakers /Residual

Current Circuit Breakers (ELCB/RCCB)

Electrical circuits and equipment is to be suitably earthed when operational. Temporary electrical equipment such as generators, welding units lighting towers must have earth protection.

Work on electrical equipment shall be carried out by competent electricians only & the isolation of

energy shall be strictly followed.

14.6 Cranes & lifting

Crane operators and riggers must be trained, tested, and certified before they can operate a crane or rig a load.

Rigging of the load is carried out by a competent person(s).

All crane outriggers must be deployed while making the lift. Any exception must be approved by the Work Responsible Person.

Cribbing may be necessary so that the load and the weight of the crane is properly distributed on the outriggers.

No outrigger or boom extension shall extend beyond the maximum distance recommended by the crane manufacturer.

The accessible area within the swing radius of the rear of the rotating superstructure of the crane shall be barricaded to prevent personnel access.

No rotating part of a crane shall come within one (1) meter of any building, structure, pipeline, or other load.

When lifting near an excavation, special care must be taken to prevent a cave-in, or to prevent the crane from falling into the excavation. A crane shall not be operated on an earth bank or where an incline exceeds certified crane specifications.

Special precautions must be observed when working near electrical hazards

The hook shall be brought over the load in such a manner as to prevent swinging.

The cables must not be kinked or twisted around each other.

The load must be checked for balance immediately upon placing a strain on the cables. When lifting a load that approaches the rated load of the crane, it should be raised a few inches and the brakes applied before making the lift.

The lift must be made slowly to avoid shock and damage to the load and the rigging equipment.

Page 47: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

25

Before a load is lifted, check to see that it is not fixed, jammed, or frozen to the ground or to another object.

Hand signals must be used for all lifts. Only one Rigger Signal-man) shall be designated to give signals to the Crane Operator.

A tag line must be used to steady the load during the lift. Loads must not be steadied by hand.

The Crane Operator should never move loads over personnel, live power lines, pressurized pipe work or running machinery.

Personnel must stand well away from all suspended loads and cables that are under strain. They must not stay in the cab or bed of a truck that is being loaded or unloaded when the load is more than 6 inches/150 mm off the bed.

The crane mechanisms must never be activated when personnel are on the crane (unless they are inspecting or adjusting mechanisms or electrical equipment).

A load must not be left suspended longer than necessary.

When a load is moved horizontally, it must be kept at least 0.5 meters above the objects that it passes over.

Cranes must not be "walked" while carrying a load. The load should be transported and then picked up again as necessary. Cranes should not be used to "slide" loads horizontally. Exceptions must be approved by the Work Responsible Person. A sling must not be pulled from under a load while the load is resting on it.

When wind velocities are above 32 km/h (20 mph), the rated load and boom lengths shall be reduced according to manufactures specifications. Wind forces are greater at height by as much as 35% or more. All lifts above ground level, must account for wind force i.e., side loads, down drafts, etc., as applied to the load and the boom.

The crane operator must always keep the load in sight. If this cannot be achieved, a Rigger (Signal-man) must be positioned where he can see both the load and the crane operator during the lift.

Lifting devices and equipment have been certified for use within last 12 months,

Any safety devices installed on lifting equipment are operational at all time.

14.7 Work Permits

Before conducting work that involves confined space entry, work on energy systems, ground

disturbance in locations where buried hazards may exist, or hot work in potentially explosive

environments or for any hazard that can arise in any kind of work, a permit must be obtained that:

Defines the scope of work

Identifies hazards and assesses risk

Establishes control measures to eliminate or mitigate hazards

Links the work to other associated work permits or simultaneous operations

Is authorized by the responsible person(s)

Communicates above information to all involved in the work

Ensures adequate control over the return to normal operations. Procedures will be implemented for controlling the work via a permit to work system in recognition of the following guidelines:

Page 48: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

26

Agreement and implementation of proformas and types of permits, including: Hot work

High Voltage Electrical Work Permit

Confined Space Entry

Radiography

14.8 Driving Safety All categories of vehicle, including mobile plants & equipment’s, must not be operated unless: Vehicle is fit for purpose, inspected and confirmed to be in safe working order.

Loads are secure and do not exceed manufacturer’s design specifications or legal limits for the vehicle.

Drivers must not be authorized to operate the vehicle unless:

They are trained, certified and medically fit to operate the class of vehicle

They are not under the influence of alcohol or drugs, and are not suffering from fatigue.

They do not use hand-held /hand free cell phones while driving. (Best way is to switch of all phones or

keep it in silent mode)

14.9 Traffic Management & Work Near Existing Highway (Public safety)

All traffic diversions shall be planned, approved, installed, operated and maintained in accordance with the Work Zone Traffic Management plan (Reference-IRC SP 55 & IRC SP-67)

Road works and traffic diversions/management must be under the direct supervision of a competent supervisor who has the necessary training and experience in the type of works being undertaken.

Workers must be given specific training and instruction on the dangers of working on or adjacent to live traffic.

Adequate signs are to be displayed giving road users advance warning of roadwork’s, the numbers and size and the distance in advance of the works for the signs are dictated by the type and of road and speed limit. Signs and guarding equipment must be secured to prevent being blown over or out of position by the wind or passing traffic.

Barriers, signs are to be installed to prevent personnel and members of the public falling into excavations. Barriers are also required to protect the workforce from passing traffic and passing traffic from the dangers of plant and equipment encroaching into traffic lanes.

Two lanes traffic shall opened to traffic throughout the construction phase.

If Work is needed to be carried out at night under floodlights; care shall be taken for floodlights must not dazzle or blind oncoming traffic.

Where properties are located adjacent to the right of way adequate & appropriate signage, & local access shall be provided. Work zone shall be isolated from public by the use of concrete or water filled plastic barriers as per engineer’s approval.

Page 49: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

27

14.10 Housekeeping & Waste management

Sites are to be kept clean and tidy and free from slip, trip and fall hazards

Workplace are to be left clean and tidy at the end of each shift and where there is an accumulation of materials throughout the shift, at regular intervals as required to maintain a clean and safe site

Materials are to be stored so as they do not pose a risk to personnel stacking, removing or walking by. Wastes viz. arising from construction activities and also from food will be disposed off from site in suitable manner. Cables/hoses/other trailing leads are to be protected, buried or secured above head height to avoid a slip trip, fall hazard

Waste is to be placed in designated containers and covered to protect against high winds, pests or risk of fire. Waste containers are to be emptied on a regular basis to prevent a build-up of material.

Page 50: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

28

Appendix 1 TRAINING MATRIX

Training JOB TITLE H

SE

In

du

ction

Em

erg

en

cy

Pre

pa

redn

ess &

R

esp

onse

Wa

ste

man

age

men

t

Fir

e S

afe

ty

Wo

rk z

one

Tra

ffic

m

an

ag

em

en

t

Wo

rk P

erm

it

Syste

m

Sca

ffold

ing

Wo

rk a

t H

eig

ht

Ha

nd

& P

ow

er

To

ol

sa

fety

Co

nfin

ed

Sp

ace

Sa

fe e

xcava

tio

n &

tr

en

ch

ing

Sa

fe o

pe

ratio

n o

f P

lan

t &

eq

uip

me

nt

Ho

t W

ork

Ho

use

Ke

epin

g

Sa

fe L

oa

d liftin

g

pro

ced

ure

CO

SH

H

PP

E

Project Director Project Manager Managers

Site Engineer Foreman/ Supervisor

Surveyors Store Keeper Scaffolder

Equipment Operator

Worker

Page 51: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

29

Appendix -2 Schedule of Statutory Inspections/Programmes

Plant/Equipment

Da

ily a

nd

Be

fore

u

se b

y u

se

r

We

ekly

(eve

ry 7

d

ays)

Re

cord

ed

Mo

nth

ly

3 M

onth

ly

6 M

onth

ly

12 M

onth

ly

General Access Scaffolds x x

Fall Protection Equipment (including lifelines, anchors, safety harnesses)

x

x

Ladders x

x

Excavations (including trenches, shafts and tunnels)

x x

Cranes (mobile, tower, lorry mounted etc)

x

x (if used for lifting persons)

x

Lifting Accessories (chains, slings, shackles, jacks etc)

x

x

Plant, Equipment and Machinery

x

x

Vehicles x

x

x

Fire Protection Equipment

x

Electrical Equipment x

x

Hand Tools & Power Tools X

X

Page 52: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

30

Appendix-3 Type and Frequency of Health and Safety Training

Activity Frequency Attendees Record

Induction training Daily New Comers to the Site/Project Attendance

Toll Box talks Weekly Workers ,HSE officers supervisors, staffs

Topics+

Attendance

Topics on Work

Related Safety

Awareness

Monthly Once Engineers/Supervisors Workers Attendance

Page 53: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

31

Appendix-4 List of checklist/Formats as per the Project Specific Plan

Sl.No Description Format No 1 Safety Risk Assessment F-01 2 Scaffolding Checklist F-02 3 PPE F-03 4 Ladder Checklist F-04 5 Fire protection F-05 6 Electrical Safety F-06

7 Hand & Power Tools F-07 8 Excavation & shoring F-08 9 Toolbox Meeting Record F-09 10 Accident/Incident Report Form F-10

Note: For monitoring purpose if required additional project specific checklist/format shall be developed and implemented.

Page 54: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

32

Appendix-5 References 1. Concessionaire Agreement 2. NHAI Safety Manuals 3. MOST Specifications 4. The BOCW Acts & Rules 5. The Motor Vehicle Acts & Rules. 6. The Petroleum Act & Rules 7. The Indian Electricity Rules

Page 55: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

1

4 Laning of Meerut – Bulandshahar section of NH-235 from Km 8.800 (design

Chainage Km 8.800) to Km 66.482 (design Chainage Km 73.512) in the state of

Uttar Pradesh on Hybrid Annuity Mode

NATIONAL HIGHWAYS AUTHORITY OF INDIA

Traffic Management Plan

FREEDOMPOINTEXPRESSWAY (Pvt.) Limited (An SPV for Development of Meerut - Bulandshahar Section of NH – 235; NEW NH – 334)

CIN: U45400UP2016PTC076383

EPC Contractor Checked By:

(Concessionaire)

Reviewed By:

(Concessionaire)

Approved By:

(Client/IE)

Name

Designation

Signature

Date

Page 56: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

2

Table of Content

Sl.No Description Page No.

1 Introduction & Statement of Purpose 3

2 Scope 4

3 Traffic Management for work zone 5

4 Traffic Control Devices 9

5 Safety Management during Construction 15

6 Typical Lay out 17

7 Weekly work zone traffic management assessment checklist 20

Page 57: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

3

1.0 INTRODUCTION AND STATEMENT OF PURPOSE

The purpose of the Traffic Management Plan is to provide guidance for the implementation of traffic

management during development, operation & maintenance of 4-laning of Meerut-Bulandshahar

section of NH-235 (New NH-334) Project. The Traffic Management Plan is to assist FEPL in

establishing, implementing and integrating traffic control, monitoring and mitigation measures for the

project.

FEPL shall carry out the work within the scope of the contract, directly with own employed labour and plant or with appointed sub-contractors. All sub-contractors are required to fully support the principles of the traffic Management Plan and to cooperate with FEPL to ensure that the overall objectives are maintained throughout the project. The Traffic Management Plan applies to all personnel working on or visiting the site.

Page 58: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

4

2.0 SCOPE

The Traffic Management Plan reflect the high priority that FEPL Management place upon the traffic

management at construction zone. It also demonstrates FEPL’s commitment to ensure that all

reasonably practicable measures are taken to:

Comply with the relevant statutory and Contractual traffic management requirements.

Ensure that existing road users are not affected by the construction work.

Provide and maintain plant, places and systems of work that are safe and without risk to health

and the environment.

Ensure that all construction – planning takes into account the smooth movements of all existing

road users that may be affected by the work.

Establish effective communication on Traffic diversion or detour with all relevant parties

involved in the Project works.

Effective control, Co-ordinate and monitor the activities of all traffic detours from existing

highway on the Project during construction phase.

Provide all personnel with adequate information, as needed.

Page 59: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

5

3.0 TRAFFIC MANAGEMENT FOR WORK ZONES

Guiding Principles & Safety Standards:

Traffic safety and temporary traffic control shall be an integral and high-priority element of the project

from planning through design, construction, and maintenance. It shall comply with IRC SP 55. IRC 67.

2012, IRC 79, MORTH and IRC 62.

The purpose of work zone traffic control is to provide a safe work area for workers within the roadway,

while facilitating the safe and orderly flow of motorists, bicyclists and pedestrians through the work

zone. In order to avoid or mitigate road work zone safety problems, the following main safety

objectives can be defined:

– Assist road users by relevant, reliable, correctly-timed and updated information, warning and

guidance, to ensure proper adaptation of their behaviour:

Inform them about traffic disruptions, restrictions and alternative routes.

Warn them about the work zone and unusual conditions or hazards.

Guide them to the path that must be followed.

– Apply traffic regulations at the work zone to achieve appropriate driver behaviour - and ensure

the enforcement of regulations.

– Provide adequate protection for road workers (safe working environment) - as well as for road

users, especially the more vulnerable ones (avoidance of hazardous elements and conditions,

vulnerable road users.

– Inspect traffic control elements routinely and modify when necessary.

– Train all persons that select, place and maintain temporary traffic control devices.

In order to achieve the above objectives Traffic Management will be carried out both during scheduled

construction work operations. The basic objective of the following guidelines is to lay down procedures

to be adopted by Contractor and Subcontractors to ensure the safe and efficient movement of traffic

and also to ensure the safety of workmen at construction sites.

The guiding principles to be adopted for safety in construction zone are to

i) Warn the road user clearly and sufficiently in advance.

ii) Provide safe and clearly marked lanes for guiding road users.

iii) Provide safe and clearly marked buffer and work zones.

iv) Provide adequate measures that control driver behaviour through construction zones.

Such traffic management plans shall include provision for traffic diversion and selection of alternative

routes for transport of equipment.

The objective of TMP is to provide a safe & smooth drive to road users plying on the Project Highway all the time of the day throughout the year and provide protection to the project workers when they are on the work. Obviously, it involves different situations on the highway including construction zone, lane closure, traffic diversions, etc.

Page 60: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

6

Construction Zone and Its Components:

This zone prepares the driver for an alert behaviour and is an essential part of any traffic control

system. The warning system shall prepare the driver well in advance by providing information

regarding distance, extent and type of hazard ahead so that he can gradually reduce the speed of his

vehicle. The information in this zone is conveyed mostly through a series of traffic signs along its

Construction Zone, or as some prefer to call Traffic Control Zone, is defined as an area of the highway

which involves the conflict of the right of use between the road users and authority responsible for the

maintenance/ improvement of the highway.

The Traffic Control Zone can be divided into various sub-zones:-

Advance Warning Zone

Approach Transition Zone

Working Zone, and

Terminal Transition Zone.

Below Figure illustrates the various components of a temporary work zone.

Page 61: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

7

Advance Warning Zone:

This zone prepares the driver for an alert behaviour and is an essential part of any traffic control

system. The warning system shall prepare the driver well in advance by providing information

regarding distance, extent and type of hazard ahead so that he can gradually reduce the speed of his

vehicle. The information in this zone is conveyed mostly through a series of traffic signs along its

length.

Diversion:

It is a component of the work zone of the road section, where the traffic movement in one or both

directions are organised through a temporary road or /new carriage way constructed alongside the

work zone, while construction is going on the existing carriage way .The diversion road is reconnect

with the existing carriage way after the end of work zone at a safer distance.

Approach Transition Zone:

The transition in this sub-zone is the area in which the traffic is steered and guided into and out of the

diverted path around the work sub-zone. This is the most critical sub-zone from safety point of view

since most of the movements are turning movements. The traffic in this sub-zone is mostly taken

across with the help of barricades and channelisers.

Working Zone:

This is the actual area where construction or maintenance is taking place and the main concern,

therefore, is the safety of the workers at the site from the plying traffic. The path of the traffic must,

therefore, be very clearly delineated to avoid intrusion of vehicles moving into the work area.

Buffer Zone:

There should be a suitable lateral buffer area between the working zone and the main highway. An

adequate buffer zone between the traffic control zone and the work zone has to be constructed as part

of the plan. A buffer zone needs to be of sufficient width, with strong barriers placed between traffic

and workers. Deflecting barriers should be placed where traffic will be running closely parallel to the

work zone. Neither work activity nor the storage of equipment or material shall occur in this area.

Length of Various Components of Construction Zone:

Depending upon the area availability the length of the work sub-zone will vary. The length of the

warning and transition zones shall be governed by the speed of the approaching vehicles. Table III.1

provides the lengths of such components as recommended by IRC.

Page 62: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

8

Recommended length of Traffic Control as extracted from IRC

Note: Adjustment to be made at site level as per the area availability, work activities, site conditioned.

Page 63: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

9

4.0 TRAFFIC CONTROL DEVICES

The primary traffic control devices used in work zones shall include signs, delineators, barricades, cones, pavement markings and flashing lights. Road Signs

The road construction and maintenance signs which fall into the same three major categories as do other traffic signs that are Regulatory Signs, Warning Signs and Direction (or guidelines) Signs shall only be used. The IRC: 67 (Code of Practice for Road Signs) provide a list of traffic signs. The size, colours and placement of sign shall confirm to IRC: 67. 2012 these signs shall be placed on left hand side of the road.

Regulatory signs Regulatory signs impose legal restriction on all traffic. It is essential, therefore, that they are used only

after consulting the local police and traffic authorities. The most common types for the use in

construction zones are “Do not enter”, “Road Closed”, “Give Way to Pedestrian”, “Speed Limit” etc.

Warning signs

Warning signs in the traffic control zone shall be utilised to warn the drivers of specific hazards that

may be encountered.

Guide Signs

Guide signs in construction zones shall have different background colour than the normal information

signs of IRC-67. These signs shall have black messages and arrows on yellow background). These

commonly used guide signs are “Diversion”, “Road Ahead Closed” and “Sharp Deviation of Route” etc.

Some Examples of Signs to be used for work zone TMP

Stop

Overtaking Prohibited

Compulsory keep left

Road Closed

Page 64: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

10

Informatory Diversion

Ahead

No Entry

Two way

movement

Men at Work

Right lane closure out of two lanes

Traffic lane tapper Left & Right

Dual carriage way

begins

Roads suddenly

Narrow due to

Construction

Traffic shifting to

other carriage

way.

Narrow bridge ahead

Adequate and Well-Designed Signage

The three types of signs viz., regulatory, warning, and Guide / Information, shall follow standard

conventions as laid by IRC and others to aid recognition and credibility. Careful planning, installation

and maintenance of road signs can contribute to the safe and efficient operation of the road network.

They shall be designed to convey clear and unambiguous messages to road users so that they can be

understood quickly and easily.

Miscellaneous

Detour signage shall be placed at strategic locations along with installation of appropriate warning

signs.

In order to minimize disruption of access to residences and business, the at least one entrance to a

property shall be maintained where multiple entrances exist.

Page 65: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

11

A warning sign shall be installed on a secondary road which merges with the primary road and where

the construction work is in progress; at a sufficient distance before it merges with the primary road so

as to alert the road users regarding the “Work in Progress”.

Materials hanging over / protruded from the chassis / body of any vehicle especially during material

handling shall be indicated by red indicator (red light/flag) to indicate the caution to the road users

Some Examples of Protective Equipment’s To be Used by construction team at work zone

Fluorescent Vest

Foot

Protection (depending upon the

nature of job)

Traffic Cones with reflectors for temporary Traffic Control/Channelization.

Delineators

with Reflectors for Night Visibility

Light batons for Traffic Control During darkness

Hard hat

Road Markings

Traffic flow and safety are almost invariably improved if traffic streams are separated into clearly

marked lanes by the use of road markings. Lane lines allow drivers to locate the vehicle laterally on

the roadway, and thus assist in avoiding collisions with both roadside objects or straying on to the

roadside. These are particularly helpful in conditions of poor visibility such as at night or under adverse

weather conditions such as in fog or rain. It has now been well established that delineation of the

outside edge of the travel lane is highly desirable, especially for roads wider than 6 m. Therefore,

steps be taken to provide proper road markings and maintain those well always. Provide markings on

each category of roads whether it is existing road waiting to be upgraded, an upgraded road section

being used as a diversion or a temporary diversion as a part of the traffic management for the work

zone.

It is necessary to provide adequate visual information to the driver to control and navigate the vehicle,

and also to enable the pedestrian to safely walk to the intended destination. All the median kerbs

should, therefore, be properly painted as per IRC guidelines and should always be maintained well.

The over grown shrubs spreading onto the carriageway should be trimmed to provide good

delineation.

Page 66: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

12

DELINEATORS The delineators are the elements of a total system of traffic control and have two distinct purposes:

i) To delineate and guide the driver to and along a safe path

ii) As a taper to move traffic from one lane to another.

These channelizing devices such as cones, traffic cylinders, tapes and drums shall be placed in or

adjacent to the roadway to control the flow of traffic. These should normally be retro-reflectors

complying with relevant standards

TRAFFIC CONES

Traffic cones of 500mm, 750mm and 1000mm high and 300mm to 500mm in diameter or in square

shape at base and are often made of plastic or rubber and normally have retro-reflective red and white

sleeve shall be used, wherever warranted.

Traffic Cones shall have suitable anchoring so that they are not easily blown over or displaced. It

might be preferable to use double cone i.e. one above the other. The cones shall be placed close

enough together to create an impression of continuity. Larger cone can be used where speeds are

high or where a more conspicuous guidance is required.

DRUMS

Drums about 800mm to 1000mm high and 300mm in diameter can be used either as channelizing or

warning devices. These are highly visible, give the appearance of being formidable objects and,

therefore, command the respect of drivers.

Empty bitumen drums (made of metal) cut to the required height can be used for channelizing devices

since they are highly visible, give the appearance of being a formidable objects, thereby commanding

the respect of the drivers. These drums can also be of plastic which are lighter, easy to transport and

store. As delineators, these drums shall be about 0.80 to 1 m high and 0.30 m in diameter. They shall

be painted in circumferential strips 0.10 m t0 0.15 m wide, alternatively in black and white colours.

BARRICADES Traffic barriers protect workers and reduce the need for many other traffic control devices and police

presence. The cost of furnishing and removing temporary traffic barriers on long-duration projects can

often be less than the cost of periodically relocating other traffic control devices and providing a higher

level of police presence. Traffic barriers may also provide greater night time visibility of work areas or

traffic shifts.

Full height fence, barriers, barricades etc. shall be erected around the site (s) in order to prevent the

working area from the risk of accidents due to speedy vehicular movement as well as to protect the

road users from the danger due to construction equipment and other temporary structures.

Page 67: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

13

In order to provide protected areas, segregated from road traffic, all work areas shall be barricaded

with portable or permanent barricades of suitable material according to IS Code. The barricades shall

be heavy and strong enough to withstand strong winds

The barricades shall be paint marked with alternate yellow/black stripes sloping at 450 towards the

direction of traffic.

A gate or movable section should be provided to allow the movement of personnel and machinery.

The movements of personnel and machinery from the work area to the road where traffic is joining

shall be properly controlled.

The work area shall be demarcated by blinker lights placement during dark hours and inclement

weather. All barricades shall be conspicuously seen in the dark/night time by the road users so that no

vehicle hits the barricade. Visibility shall be ensured by affixing retro reflective stripes of required size

and shape at appropriate angle at the bottom and middle portion of the barricade at a minimum gap of

1000mm. In addition minimum one red light or red light blinker or reflectors should be placed on the

top of barricades at regular intervals.

Where it is authorised by the relevant authority for vehicles ferrying materials to the worksite to be

parked outside the barricaded work zone, suitable safety measures should be taken. Such measures

should include cordoning off such parking areas and suitable warning signs, lights and flagman should

be provided.

Where it is absolutely necessary for construction machinery to carry out work from outside the

hoarded area, the operating area of the machine outside the area should be cordoned off and suitable

warning signs and lights and flagman should be provided.

Barriers to prevent pedestrians from entering construction zones should be continuous and

constructed of rigid materials in order to be discerned by pedestrians with vision impairments. The use

of “caution” tape or other measures is not acceptable for defining a pedestrian route since these

materials are easily broken and do not adequately direct pedestrians into the temporary pathway.

Scaffolding and other construction fencing should not have objects that protrude into the clear head

space for pedestrians. Temporary work on sidewalks also needs to be barricaded.

FLAGMEN

A flagger may be necessary to alert traffic, or to stop traffic intermittently, as required by the progress

of work in a work zone. In large construction sites, flagmen with flags and sign paddles shall be

effectively used to guide the safe movements. No employees shall be utilized as a flagger until the

employee has shown conclusively to their Supervisor that they realize fully the importance of the job,

and understands the duties and responsibilities associated with it. The flagger’s only job is work zone protection and traffic control. The flagger must never assist the crew with work activities, or engage in

any distraction, and must remain on duty until properly relieved.

Flaggers shall be placed where approaching drivers can easily see them and never placed in shadows

or where other workers may be close to them. Their station must have an escape route.

Page 68: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

14

Flaggers shall be trained to gain and maintain eye contact with motorists and to be courteous but firm

when communicating with drivers by both word and gesture. They must be dressed in bright warning

vests.

Flaggers will be used in the following situations: One lane is alternately used for both directions of traffic.

The roadway is closed for a brief period of time.

Traffic speeds need to be substantially reduced.

Inadequate sight distance hinders advance warning.

Information, such as changing conditions, needs to be conveyed to motorists.

Opposing traffic needs to be controlled at an intersection.

Installing and removing other traffic control devices.

Where conditions require unusual precautions.

During some work situations, the TCP supervisor may have to place flaggers at the beginning of, or in the activity zone. Alternatives to flaggers should always be used when hazardous conditions such as limited visibility or high-speed traffic are present. If flaggers must be used, they must be adequately trained before assuming their duties. In more complex situations it may be necessary to place a Spotter at some locations. A Spotter is a person with the same qualifications of the flagger. A spotter may be required to warn workers of errant vehicles, danger from traffic, or to assist drivers of work vehicles in entering or leaving work sites or in performing U-turns.

The flags for signalling shall be 600mm x 600mmm size, made of a good red cloth and securely fastened to a staff of approximately 1m in length. Wherever practicable sign paddles shall be used.

MISCELLANEOUS

It shall be ensured that all construction vehicles plying on public roads (like dump trucks, trailers, etc.) have proper permit/registration to ply on public roads from the State Transport Authority. Drivers holding proper valid license as per the requirements of Motor Vehicles Act shall only drive these vehicles.

FEPL/its sub-contractor shall not undertake loading and unloading at carriageways obstructing the free flow of vehicular traffic and encroachment of existing roads applying the excuse of work execution. All construction workers should be provided with high visibility jackets with reflective tapes. The conspicuity of workmen at all times shall be increased so as to protect from speeding vehicular traffic. In all cases, FEPL shall employ proper precautions. Wherever operations undertaken are likely to interfere with public traffic, specific traffic management plans shall be drawn up and implemented by FEPL in consultation with the approval of local police authorities and/or the concerned metropolitan/civil authorities as the case may be.

Page 69: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

15

5.0 SAFETY MANAGEMENT DURING CONSTRUCTION PERIOD Measures for providing safe movement of traffic in some of the most commonly occurring work zones

on highways shall be as described in the following sub-sections:

Access to Sites Temporary Diversion:

Depending on the work space at site pedestrian and vehicular access shall be separated.

Adequate and appropriate signs shall be posted on all routes.

Routes shall be free of obstructions/ tripping hazards.

Ladders used, as access to heights shall be placed away from vehicle/equipment and secured at top.

Detour on Temporary Diversion: In the case of major repairs or works on a highway section, traffic may have to pass on a diversion, moving parallel to the highway. A temporary diversion road should basically satisfy the following requirements:

i) It shall have smooth horizontal and vertical profile with smooth vertical and horizontal curves.

ii) It shall not get overtopped by flood or drainage discharge under any conditions. iii) It shall have adequate capacity to cater for the diverted traffic. iv) It shall be dust free and shall ensure clear visibility at all times of day and night. v) It shall be provided with the required safety standards, and vi) It shall be provided with suitable barricades to prevent intrusion affecting the movement

and safety of the traffic. The warning signs for the construction ahead shall be provided by the sign “Men at Work” about 1km earlier to the start of the work zone. In addition a supplementary plate indicating “Diversion Ahead” (With distance)and a sign “Road Closed Ahead” shall be placed. It should be followed by compulsory “Turn Right/Left Sign”. The “Diversion” and “Sharp Deviation” sign shall be used to guide the traffic into the diversion. Hazard markers will be placed just where railings for cross drainage structures on the diversion starts. In a construction zone that carries considerable traffic, it is often preferable to provide a route which will take the traffic around the construction zone. If the Contractor is proposing a detour, as part of his traffic control, the complete design of the detour would be the Contractor’s responsibility. It is usually necessary to obtain local government approval when city streets are used for detours. It is desirable that both ends of the detour are visible to approaching motorists. Transitions should not be in close proximity to horizontal or vertical curves, structures, or any obstruction which would interfere with the motorist's view of the transition. One ideal situation is to locate entering transitions on far sides of sag vertical curves so that the complete detour is visible (like a huge map) to the motorists. Detour plans call for a great deal of thought, planning, and on-the-ground investigation. Carriageway Repairs When the work is of small magnitude, to be done in the middle of the carriageway, such as minor repairs of potholes, cracks and patches, then the traffic control measures shall mainly consist of providing cautionary signs of “Men at Work”, well ahead work zone for the approaching vehicle. Other cautionary sign of “Road Narrows” shall be placed at 100 m ahead of the work area. Regulatory sign

Page 70: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

16

of “Keep Left/Right” shall be placed at the commencement point of work zone and next to barriers for approaching vehicles Moveable type of barriers shall also be placed on both sides of the work area. Cones or drums shall be placed at suitable interval to demarcate the work area.

Page 71: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

17

6.0 TYPICAL LAYOUTS

W

O

R

K

Z

O

N

E

TYPICAL LAYOUT: WIDENING FOR DUAL HIGHWAY CONSTRUCTION.

Page 72: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

18

TYPICAL LAYOUT: MEDIAN CROSS OVER DURING TWO LANE DUAL HIGHWAY CONSTRUCTION.

Page 73: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

19

:

W

O

R

K

Z

O

N

E

TYPICAL LAYOUT: TRAFFIC MAANGEMENT FOR WORK NEAR JUNCTION.

Page 74: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

20

7.0 WEEKLY WORK ZONE TRAFFIC MANAGEMENT ASSESSMENT CHECKLIST WORK PLACE DETAIL

Date of Assessment

Work Place Location & Area

Persons Conducting Assessment Name : Sign

ROAD CONDITION Yes No Comments/Action Required

1, Surface smooth, free of damage (Potholes, cracks, surface irregularities ,edge breaks etc,)

2.Road marking visible

3.Any changes to the existing path

4. Item No.3 if Yes, TMP developed & available.

WORK ZONE WARNING SIGNAGE

5.Work zone demarcated with suitable means (like sand filled sacks with reflective strips/delineator posts

6.Road work signs and devices installed, adequately distributed across the work area

7. Appropriate signs are posted to warn the road users.

8. Signage suitably placed especially for approaching vehicle at high speed.

9. Have any contradictory, distracting sign present and need the authority’s interference.

10. Are the signs free from damage and defect?

11.Are signs mounting secure ,stable and not a hazard to road users

12. Persons engaged in traffic management work are wearing high visibility clothing.

Page 75: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

Compliance to ADB Observations on Environment & Social Due Diligence Report

(ESDDR) of

Freedom Point Expressways Pvt Ltd. (FPEPL)

Page 1 of 2

S.No. ADB Comment IIFCL response/clarifications

1. Confirm that the sub-project

complies with ADB’s SPS 2009. Yes

2. Please provide a copy of the EIA

report prepared for the sub-project

as a part of the ESDDR;

EIA for FPEPL is not required, as the sub-

project length is below 100 kms (~61.19

Kms), this is exempted from obtaining

environmental clearance (EC) and conducting

EIA.

Concessioning Authority - NHAI was

accorded environmental clearance by

MOEF&CC on 2nd

January 2013 for NH-235.

The EIA Notification’s Amendment regarding

exemption of expansion of highways upto 100

Km involving additional right of way or land

acquisition upto 40 mts on existing

alignments and 60 mts on realignments or by

passes, had come on 22nd

August 2013.

3. The diversion of 92.6 ha of forest

land is noted from the ESDDR.

Please correct Para 48 accordingly;

Corrections have been done and

inconsistencies removed from the ESDDR.

4. The ESDDR has mentioned that the

working permissions for working in

forest areas were obtained in

September 2015, however, final

forest clearance (stage II) is still

awaited. Please confirm that the

works in the forest areas have been

undertaken during the validity of

these working permissions. Please

provide the rationale for delay in

obtaining final forest clearance for

the sub-project;

Developer has confirmed that the works in

forest area have been done during the validity

of working permission only.

Developer has informed that all the

documentation is already completed and

Stage II Forest Clearance is awaited.

5. Please provide copies of consents

to operate and authorization

obtained as part of ESDDR;

Developer has confirmed during site visit that

Consent to operate has been obtained. Copies

yet to be shared by the developer.

6. Please confirm that the construction

material has been procured from

the sources compliant with

environmental regulations of India;

FPEPL has obtained permissions for borrow

areas and the borrow area locations were

approved in compliance with MoEF&CC

letter D.O. No. 22-346/2026-1A-111 dated

28th

October, 2016 to NHAI followed by

letters from UP Government dated 23rd

May

2017 and NHAI’s letter to District Magistrates (Meerut, Hapur and Bulandshahr)

dated 26th

May 2017 and district magistrate

orders (Meerut, Hapur and Bulandshahr)

dated 18th

November 2017 granting

permission to allow borrow area activity

Page 76: INDIA: Accelerating Infrastructure Investment …...This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily

Compliance to ADB Observations on Environment & Social Due Diligence Report

(ESDDR) of

Freedom Point Expressways Pvt Ltd. (FPEPL)

Page 2 of 2

while classifying this activity coming under

public good (Janhit). The sample copies of

these permissions are given in Annexure 6 of

the ESDDR. LIE report (September 2019)

mentioned that crushers will not be operated

or installed by concessionaire. Hence,

permissions from state government for

extraction of boulders from quarry are not

required. This was further confirmed from the

concessionaire during site visit on 31st

October 2019. The concessionaire is sourcing

stone dust from the third party based in

Yamuna Nagar, Haryana.

The sample of permission received by the

third part based in Yamuna Nagar, Haryana

from Haryana Pollution Control Board is

already shared with the ESDDR.

7. Please provide copies of the

permission obtained for the

ordinary earth for borrowing under

the relevant environmental

regulations of India (attached letters

are issued under the mining acts of

the state);

Clarifications provided as per point no. 6.

8. The number of trees cut stated in

table 2 are 4780 and in table 3 are

7322. Please check and provide the

corrected number;

Number of trees cut for the sub project are

7322. This is consistently mentioned at Table

2 -page 13, para 30, Table 3 (page 16), para

39, para 46 (bullet 4) of the revised ESDDR.

9. Please provide the quantity of fly

ash used so far during

implementation of the sub-project;

Developer has informed that total 40436 MT

flyash has been used for the project.

10. Confirmation that requisite

permission has been obtained for

temporary change in land use for

the land being used for construction

camp site if it was originally an

agricultural land.

Developer has informed that lease agreement

has been executed for the land for camp site.