joe polidoro, sr. engineer pjm interconnection, llc 610-666-4693 grid of the future: integrating...

16
Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Upload: steven-sutton

Post on 01-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Joe Polidoro, Sr. EngineerPJM Interconnection, LLC

610-666-4693

 

Grid of the Future:Integrating Load Response

into the Markets

                                                               

Page 2: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

PJM Mission

• Maintain the safety, adequacy, reliability and security of the power system

• Create and operate a robust, competitive, and non-discriminatory wholesale electric power market

Page 3: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Ensure that customers receive the value of competitively priced generation

Utilize Advanced Information Technologies to: Simplify the life of the customer Solve the problems Integrate Load Response into the Markets

Keep the Focus

Page 4: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Future Footprint

PJM PJM Western Region Duquesne - Jan ‘05 AEP – Oct ’04 Dayton Power & Light

- Oct ‘04 ComEd – May ‘04 Dominion Power –

Spring 2005

Page 5: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

“Load response is a highly useful and beneficial tool to reduce costs and maintain reliability during peak periods when generation supplies may be scarce.”

According to the April 30,2002 FERC Order

Why Is Load Response Important?

Page 6: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Participation in the Energy Markets

Program Name Economic-Real-Time

Frequency

I want a 100% voluntary program with no risk and no penalties where I can determine the start and stop times of my curtailment any day of the year.

I want to decide when to reduce load 

     

RiskI want a 100% voluntary program

with no risk and no penalties

     

Implementation

I want to reduce load or use my emergency generators and I have the proper permits.

I will only reduce load if I'm paid a minimum of $0.50/kW or higher

(Defined by the end user)

Page 7: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Industrial and Commercial End User Registrations (June 2002 thru December

2004) in the PJM Load Response Programs

Emergency Program New Sites

Economic Program

New Sites

2002 61 2002116

2003 107 2003129

2004 4,144 2004 1,784

Page 8: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Previous rules developed when large generators were the only resource

With the right tools, load can be as reliable and robust as generation

New rules explicitly allows for load to provide contingency reserve

New technology allows load to be responsive in real-time

Removing Barriers to the Ancillary Markets

Page 9: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Timeline

Introduction of Implementation Approach Nov 2004

Whitepaper Revisions / Business Rule Development

Dec 2004 Reliability Council Changes

March 2005 Committee votes

June 2005 Implementation

September 2005

Page 10: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Spinning Reserve: No less than one minute scan rate

surrounding spin event Can be sent to PJM at end of day in

one upload

Regulation 6 second scan rate minimum Transmission to PJM in real time

Telemetry Requirements

Page 11: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Turn Data into Information with free web based tools (eData)

Page 12: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Turn Data into Information with free web based tools (eData)

Page 13: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Turn Data into Information with free web based tools (eData)

Page 14: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

Register with a Curtailment Service Provider

Working group participation in 2005 will likely fix your options for the next few years

There are many protocols issues that will be addressed by the working group this year that will affect whether your load is suitable for other opportunities and assist efforts to remove barriers for participation

You can participate in person, via phone or via web (free)

Why Is Your Participation Important?

Page 15: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

PJM is responsible for: the reliability of the electric system, the operation of competitive

wholesale electric markets, and ensuring that no member has undue

influence. An Independent Board governs PJM’s

business. The Members Committee advises the Board on changes to meet members’ needs.

A series of Internet Tools are available at www.pjm.com to assist customers with business functions.

Summary of PJM

Page 16: Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693 Grid of the Future: Integrating Load Response into the Markets

For any additional information, please do not hesitate to contact PJM or a PJM Curtailment Service Provider at PJM’s Web site: www.pjm.com > Services > Demand Response Program

Joe PolidoroPJMPhone: [email protected]

www.PJM.com

Contact the organizers