justo a tiempo y kanbam
TRANSCRIPT
-
7/29/2019 Justo a Tiempo y KANBAM
1/31
The M cGraw -H i l l Companies, Inc., 2004
1
Just-in-Time and Lean Systems
-
7/29/2019 Justo a Tiempo y KANBAM
2/31
The M cGraw -H i l l Companies, Inc., 2004
2
JIT Defined
The Toyota Production System
JIT Implementation Requirements
JIT in Services
OBJECTIVES
-
7/29/2019 Justo a Tiempo y KANBAM
3/31
The M cGraw -H i l l Companies, Inc., 2004
3
Just-In-Time (JIT)
Defined
JIT can be defined as an integrated set of
activities designed to achieve high-volumeproduction using minimal inventories (rawmaterials, work in process, and finished
goods) JIT also involves the elimination of waste in
production effort
JIT also involves the timing of productionresources (i.e., parts arrive at the next
workstation just in time)
-
7/29/2019 Justo a Tiempo y KANBAM
4/31The M cGraw -H i l l Companies, Inc., 2004
4
JIT and Lean Management
JIT can be divided into two terms: Big JIT andLittle JIT
Big JIT (also called Lean Management) is aphilosophy of operations management that seeksto eliminate waste in all aspects of a firmsproduction activities: human relations, vendorrelations, technology, and the management ofmaterials and inventory
Little JIT focuses more narrowly on schedulinggoods inventory and providing service resourceswhere and when needed
-
7/29/2019 Justo a Tiempo y KANBAM
5/31The M cGraw -H i l l Companies, Inc., 2004
5
JIT Demand-Pull Logic
Customers
Sub
Sub
Fab
Fab
Fab
Fab
Vendor
Vendor
Vendor
Vendor
Final
Assembly
Here the customer starts
the process, pulling an
inventory item from
Final Assembly
Here the customer starts
the process, pulling an
inventory item fromFinal Assembly
Then sub-assembly work is
pulled forward by
that demand
Then sub-
assembly work is
pulled forward by
that demand
The process continues
throughout the entire
production process andsupply chain
The process continues
throughout the entire
production process and
supply chain
6
-
7/29/2019 Justo a Tiempo y KANBAM
6/31The M cGraw -H i l l Companies, Inc., 2004
6
The Toyota Production System
Based on two philosophies: 1. Elimination of waste
2. Respect for people
7
-
7/29/2019 Justo a Tiempo y KANBAM
7/31The M cGraw -H i l l Companies, Inc., 2004
7
Waste in Operations
1. Waste from overproduction
2. Waste of waiting time
3. Transportation waste
4. Inventory waste
5. Processing waste
6. Waste of motion
7. Waste from product defects
8
-
7/29/2019 Justo a Tiempo y KANBAM
8/31The M cGraw -H i l l Companies, Inc., 2004
8
Minimizing Waste:
Focused FactoryNetworks
CoordinationSystem Integration
These are small specialized
plants that limit the range
of products produced
(sometimes only one type of
product for an entire
facility)
These are small specialized
plants that limit the range
of products produced
(sometimes only one type of
product for an entire
facility)
Some plants inJapan have as
few as 30 and
as many as
1000 employees
Some plants in
Japan have as
few as 30 and
as many as
1000 employees
9
-
7/29/2019 Justo a Tiempo y KANBAM
9/31The M cGraw -H i l l Companies, Inc., 2004
9
Minimizing Waste: Group Technology (Part 1)
UsingDepartmental Specialization for plant layout can cause a lot of
unnecessary material movement
UsingDepartmental Specialization for plant layout can cause a lot of
unnecessary material movement
Saw Saw
Lathe PressPress
Grinder
LatheLathe
Saw
Press
Heat Treat
Grinder
Note how the flow lines are going back and forthNote how the flow lines are going back and forth
10
-
7/29/2019 Justo a Tiempo y KANBAM
10/31
The M cGraw -H i l l Companies, Inc., 2004
10
Minimizing Waste:
Group Technology (Part 2) Revising by using Group Technology Cells can reduce movement and
improve product flow
Revising by using Group Technology Cells can reduce movement andimprove product flow
Press
Lathe
Grinder
Grinder
A
2
BSaw
Heat Treat
LatheSaw Lathe
PressLathe
1
11
-
7/29/2019 Justo a Tiempo y KANBAM
11/31
The M cGraw -H i l l Companies, Inc., 2004
11
Minimizing Waste:
Uniform Plant Loading (heijunka)
Not uniform Jan. Units Feb. Units Mar. Units Total
1,200 3,500 4,300 9,000
Uniform Jan. Units Feb. Units Mar. Units Total
3,000 3,000 3,000 9,000
Suppose we operate a production plant that produces a single
product. The schedule of production for this product could be
accomplished using either of the two plant loading schedules
below.
Suppose we operate a production plant that produces a single
product. The schedule of production for this product could be
accomplished using either of the two plant loading schedules
below.
How does the uniform loading help save labor costs?How does the uniform loading help save labor costs?
or
12
-
7/29/2019 Justo a Tiempo y KANBAM
12/31
The M cGraw -H i l l Companies, Inc., 2004
12
Minimizing Waste: Just-In-Time
Production
Management philosophy
Pull system though the plant
WHAT IT IS
Employee participation Industrial engineering/basics
Continuing improvement
Total quality control Small lot sizes
WHAT IT REQUIRES
Attacks waste Exposes problems and bottlenecks
Achieves streamlined production
WHAT IT DOES
Stable environment
WHAT IT ASSUMES
13
-
7/29/2019 Justo a Tiempo y KANBAM
13/31
The M cGraw -H i l l Companies, Inc., 2004
Minimizing Waste: Inventory
Hides Problems
Work in
processqueues
(banks)
Change
orders
Engineering design
redundancies
Vendor
delinquencies
Scrap
Design
backlogs
Machine
downtime
Decision
backlogs
Inspection
backlogs
Paperwork
backlog
Example: By
identifying defective
items from a vendorearly in the
production process
the downstream work
is saved
Example: Byidentifying defective
work by employees
upstream, the
downstream work issaved
14
-
7/29/2019 Justo a Tiempo y KANBAM
14/31
The M cGraw -H i l l Companies, Inc., 2004
Minimizing Waste: Kanban Production
Control Systems
Storage
Part A
Storage
Part AMachine
CenterAssembly
Line
Material Flow
Card (signal) Flow
Withdrawal
kanban
Once the Production kanban is
received, the Machine Center
produces a unit to replace the
one taken by the Assembly Line
people in the first place
This puts thesystem back
were it was
before the item
was pulled
The process begins by the Assembly Line
people pulling Part A from Storage
Production kanban
15
-
7/29/2019 Justo a Tiempo y KANBAM
15/31
The M cGraw -H i l l Companies, Inc., 2004
Determining the Number of Kanbans
Needed Setting up a kanban system requires
determining the number of kanbans cards (orcontainers) needed
Each container represents the minimumproduction lot size
An accurate estimate of the lead time requiredto produce a container is key to determining
how many kanbans are required
16
-
7/29/2019 Justo a Tiempo y KANBAM
16/31
The M cGraw -H i l l Companies, Inc., 2004
The Number of Kanban Card Sets
C
SDL
k
)(1
containertheofSizestockSafetytimeleadduringdemandExpected
+=
+=
k = Number of kanban card sets (a set is a card)
D = Average number of units demanded over some time
period
L = lead time to replenish an order (same units of time asdemand)
S = Safety stock expressed as a percentage of demand
during leadtime
C = Container size
17
-
7/29/2019 Justo a Tiempo y KANBAM
17/31
The M cGraw -H i l l Companies, Inc., 2004
Example of Kanban Card Determination:
Problem Data A switch assembly is assembled in batches of 4 units
from an upstream assembly area and delivered in
a special container to a downstream control-panel
assembly operation
The control-panel assembly area requires 5 switchassemblies per hour
The switch assembly area can produce a container ofswitch assemblies in 2 hours
Safety stock has been set at 10% of needed inventory
18
-
7/29/2019 Justo a Tiempo y KANBAM
18/31
The M cGraw -H i l l Companies, Inc., 2004
Example of Kanban Card
Determination: Calculations
3or,75.2
4
5(2)(1.1))(1
containertheofSize
stockSafetytimeleadduringdemandExpected
==+
=
+
=
C
SDL
k
Always round up!
19
-
7/29/2019 Justo a Tiempo y KANBAM
19/31
The M cGraw -H i l l Companies, Inc., 2004
Respect for People
Level payrolls
Cooperative employee unions
Subcontractor networks
Bottom-round management style
Quality circles (Small Group InvolvementActivities or SGIAs)
20
-
7/29/2019 Justo a Tiempo y KANBAM
20/31
The M cGraw -H i l l Companies, Inc., 2004
Toyota Production Systems Four Rules
1. All work shall be highly specified as to content,sequence, timing, and outcome
2. Every customer-supplier connection must be direct, andthere must be an unambiguous yes-or-no way to send
requests and receive responses
3. The pathway for every product and service must be
simple and direct
4. Any improvement must be made in accordance with the
scientific method, under the guidance of a teacher, at the
lowest possible level in the organization
21
-
7/29/2019 Justo a Tiempo y KANBAM
21/31
The M cGraw -H i l l Companies, Inc., 2004
JIT Implementation Requirements:
Design Flow Process
Link operations
Balance workstation capacities
Redesign layout for flow
Emphasize preventive maintenance
Reduce lot sizes
Reduce setup/changeover time
22
-
7/29/2019 Justo a Tiempo y KANBAM
22/31
The M cGraw -H i l l Companies, Inc., 2004
JIT Implementation Requirements: Total
Quality Control
Worker responsibility
Measure SQC
Enforce compliance
Fail-safe methods
Automatic inspection
23
-
7/29/2019 Justo a Tiempo y KANBAM
23/31
The M cGraw -H i l l Companies, Inc., 2004
JIT Implementation Requirements:
Stabilize Schedule
Level schedule
Underutilize capacity
Establish freeze windows
24
-
7/29/2019 Justo a Tiempo y KANBAM
24/31
The M cGraw -H i l l Companies, Inc., 2004
JIT Implementation Requirements:
Kanban-Pull
Demand pull
Backflush
Reduce lot sizes
25
-
7/29/2019 Justo a Tiempo y KANBAM
25/31
The M cGraw -H i l l Companies, Inc., 2004
JIT Implementation Requirements: Work
with Vendors
Reduce lead times
Frequent deliveries
Project usage requirements
Quality expectations
26
-
7/29/2019 Justo a Tiempo y KANBAM
26/31
The M cGraw -H i l l Companies, Inc., 2004
JIT Implementation Requirements:
Reduce Inventory More
Look for other areas
Stores
Transit
Carousels
Conveyors
27
-
7/29/2019 Justo a Tiempo y KANBAM
27/31
The M cGraw -H i l l Companies, Inc., 2004
JIT Implementation Requirements:
Improve Product Design
Standard product configuration
Standardize and reduce number of parts
Process design with product design
Quality expectations
28
-
7/29/2019 Justo a Tiempo y KANBAM
28/31
The M cGraw -H i l l Companies, Inc., 2004
JIT Implementation Requirements:
Concurrently Solve Problems
Root cause
Solve permanently
Team approach
Line and specialist responsibility
Continual education
29
-
7/29/2019 Justo a Tiempo y KANBAM
29/31
The M cGraw -H i l l Companies, Inc., 2004
JIT Implementation Requirements:
Measure Performance
Emphasize improvement
Track trends
30
-
7/29/2019 Justo a Tiempo y KANBAM
30/31
The M cGraw -H i l l Companies, Inc., 2004
JIT in Services (Examples)
Organize Problem-Solving Groups
Upgrade Housekeeping
Upgrade Quality
Clarify Process Flows
Revise Equipment and Process Technologies
31
-
7/29/2019 Justo a Tiempo y KANBAM
31/31
The M cGraw -H i l l Companies, Inc., 2004
JIT in Services (Examples)
Level the Facility Load
Eliminate Unnecessary Activities
Reorganize Physical Configuration
Introduce Demand-Pull Scheduling
Develop Supplier Networks