justo a tiempo y kanbam

Upload: juankmedina

Post on 14-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Justo a Tiempo y KANBAM

    1/31

    The M cGraw -H i l l Companies, Inc., 2004

    1

    Just-in-Time and Lean Systems

  • 7/29/2019 Justo a Tiempo y KANBAM

    2/31

    The M cGraw -H i l l Companies, Inc., 2004

    2

    JIT Defined

    The Toyota Production System

    JIT Implementation Requirements

    JIT in Services

    OBJECTIVES

  • 7/29/2019 Justo a Tiempo y KANBAM

    3/31

    The M cGraw -H i l l Companies, Inc., 2004

    3

    Just-In-Time (JIT)

    Defined

    JIT can be defined as an integrated set of

    activities designed to achieve high-volumeproduction using minimal inventories (rawmaterials, work in process, and finished

    goods) JIT also involves the elimination of waste in

    production effort

    JIT also involves the timing of productionresources (i.e., parts arrive at the next

    workstation just in time)

  • 7/29/2019 Justo a Tiempo y KANBAM

    4/31The M cGraw -H i l l Companies, Inc., 2004

    4

    JIT and Lean Management

    JIT can be divided into two terms: Big JIT andLittle JIT

    Big JIT (also called Lean Management) is aphilosophy of operations management that seeksto eliminate waste in all aspects of a firmsproduction activities: human relations, vendorrelations, technology, and the management ofmaterials and inventory

    Little JIT focuses more narrowly on schedulinggoods inventory and providing service resourceswhere and when needed

  • 7/29/2019 Justo a Tiempo y KANBAM

    5/31The M cGraw -H i l l Companies, Inc., 2004

    5

    JIT Demand-Pull Logic

    Customers

    Sub

    Sub

    Fab

    Fab

    Fab

    Fab

    Vendor

    Vendor

    Vendor

    Vendor

    Final

    Assembly

    Here the customer starts

    the process, pulling an

    inventory item from

    Final Assembly

    Here the customer starts

    the process, pulling an

    inventory item fromFinal Assembly

    Then sub-assembly work is

    pulled forward by

    that demand

    Then sub-

    assembly work is

    pulled forward by

    that demand

    The process continues

    throughout the entire

    production process andsupply chain

    The process continues

    throughout the entire

    production process and

    supply chain

    6

  • 7/29/2019 Justo a Tiempo y KANBAM

    6/31The M cGraw -H i l l Companies, Inc., 2004

    6

    The Toyota Production System

    Based on two philosophies: 1. Elimination of waste

    2. Respect for people

    7

  • 7/29/2019 Justo a Tiempo y KANBAM

    7/31The M cGraw -H i l l Companies, Inc., 2004

    7

    Waste in Operations

    1. Waste from overproduction

    2. Waste of waiting time

    3. Transportation waste

    4. Inventory waste

    5. Processing waste

    6. Waste of motion

    7. Waste from product defects

    8

  • 7/29/2019 Justo a Tiempo y KANBAM

    8/31The M cGraw -H i l l Companies, Inc., 2004

    8

    Minimizing Waste:

    Focused FactoryNetworks

    CoordinationSystem Integration

    These are small specialized

    plants that limit the range

    of products produced

    (sometimes only one type of

    product for an entire

    facility)

    These are small specialized

    plants that limit the range

    of products produced

    (sometimes only one type of

    product for an entire

    facility)

    Some plants inJapan have as

    few as 30 and

    as many as

    1000 employees

    Some plants in

    Japan have as

    few as 30 and

    as many as

    1000 employees

    9

  • 7/29/2019 Justo a Tiempo y KANBAM

    9/31The M cGraw -H i l l Companies, Inc., 2004

    9

    Minimizing Waste: Group Technology (Part 1)

    UsingDepartmental Specialization for plant layout can cause a lot of

    unnecessary material movement

    UsingDepartmental Specialization for plant layout can cause a lot of

    unnecessary material movement

    Saw Saw

    Lathe PressPress

    Grinder

    LatheLathe

    Saw

    Press

    Heat Treat

    Grinder

    Note how the flow lines are going back and forthNote how the flow lines are going back and forth

    10

  • 7/29/2019 Justo a Tiempo y KANBAM

    10/31

    The M cGraw -H i l l Companies, Inc., 2004

    10

    Minimizing Waste:

    Group Technology (Part 2) Revising by using Group Technology Cells can reduce movement and

    improve product flow

    Revising by using Group Technology Cells can reduce movement andimprove product flow

    Press

    Lathe

    Grinder

    Grinder

    A

    2

    BSaw

    Heat Treat

    LatheSaw Lathe

    PressLathe

    1

    11

  • 7/29/2019 Justo a Tiempo y KANBAM

    11/31

    The M cGraw -H i l l Companies, Inc., 2004

    11

    Minimizing Waste:

    Uniform Plant Loading (heijunka)

    Not uniform Jan. Units Feb. Units Mar. Units Total

    1,200 3,500 4,300 9,000

    Uniform Jan. Units Feb. Units Mar. Units Total

    3,000 3,000 3,000 9,000

    Suppose we operate a production plant that produces a single

    product. The schedule of production for this product could be

    accomplished using either of the two plant loading schedules

    below.

    Suppose we operate a production plant that produces a single

    product. The schedule of production for this product could be

    accomplished using either of the two plant loading schedules

    below.

    How does the uniform loading help save labor costs?How does the uniform loading help save labor costs?

    or

    12

  • 7/29/2019 Justo a Tiempo y KANBAM

    12/31

    The M cGraw -H i l l Companies, Inc., 2004

    12

    Minimizing Waste: Just-In-Time

    Production

    Management philosophy

    Pull system though the plant

    WHAT IT IS

    Employee participation Industrial engineering/basics

    Continuing improvement

    Total quality control Small lot sizes

    WHAT IT REQUIRES

    Attacks waste Exposes problems and bottlenecks

    Achieves streamlined production

    WHAT IT DOES

    Stable environment

    WHAT IT ASSUMES

    13

  • 7/29/2019 Justo a Tiempo y KANBAM

    13/31

    The M cGraw -H i l l Companies, Inc., 2004

    Minimizing Waste: Inventory

    Hides Problems

    Work in

    processqueues

    (banks)

    Change

    orders

    Engineering design

    redundancies

    Vendor

    delinquencies

    Scrap

    Design

    backlogs

    Machine

    downtime

    Decision

    backlogs

    Inspection

    backlogs

    Paperwork

    backlog

    Example: By

    identifying defective

    items from a vendorearly in the

    production process

    the downstream work

    is saved

    Example: Byidentifying defective

    work by employees

    upstream, the

    downstream work issaved

    14

  • 7/29/2019 Justo a Tiempo y KANBAM

    14/31

    The M cGraw -H i l l Companies, Inc., 2004

    Minimizing Waste: Kanban Production

    Control Systems

    Storage

    Part A

    Storage

    Part AMachine

    CenterAssembly

    Line

    Material Flow

    Card (signal) Flow

    Withdrawal

    kanban

    Once the Production kanban is

    received, the Machine Center

    produces a unit to replace the

    one taken by the Assembly Line

    people in the first place

    This puts thesystem back

    were it was

    before the item

    was pulled

    The process begins by the Assembly Line

    people pulling Part A from Storage

    Production kanban

    15

  • 7/29/2019 Justo a Tiempo y KANBAM

    15/31

    The M cGraw -H i l l Companies, Inc., 2004

    Determining the Number of Kanbans

    Needed Setting up a kanban system requires

    determining the number of kanbans cards (orcontainers) needed

    Each container represents the minimumproduction lot size

    An accurate estimate of the lead time requiredto produce a container is key to determining

    how many kanbans are required

    16

  • 7/29/2019 Justo a Tiempo y KANBAM

    16/31

    The M cGraw -H i l l Companies, Inc., 2004

    The Number of Kanban Card Sets

    C

    SDL

    k

    )(1

    containertheofSizestockSafetytimeleadduringdemandExpected

    +=

    +=

    k = Number of kanban card sets (a set is a card)

    D = Average number of units demanded over some time

    period

    L = lead time to replenish an order (same units of time asdemand)

    S = Safety stock expressed as a percentage of demand

    during leadtime

    C = Container size

    17

  • 7/29/2019 Justo a Tiempo y KANBAM

    17/31

    The M cGraw -H i l l Companies, Inc., 2004

    Example of Kanban Card Determination:

    Problem Data A switch assembly is assembled in batches of 4 units

    from an upstream assembly area and delivered in

    a special container to a downstream control-panel

    assembly operation

    The control-panel assembly area requires 5 switchassemblies per hour

    The switch assembly area can produce a container ofswitch assemblies in 2 hours

    Safety stock has been set at 10% of needed inventory

    18

  • 7/29/2019 Justo a Tiempo y KANBAM

    18/31

    The M cGraw -H i l l Companies, Inc., 2004

    Example of Kanban Card

    Determination: Calculations

    3or,75.2

    4

    5(2)(1.1))(1

    containertheofSize

    stockSafetytimeleadduringdemandExpected

    ==+

    =

    +

    =

    C

    SDL

    k

    Always round up!

    19

  • 7/29/2019 Justo a Tiempo y KANBAM

    19/31

    The M cGraw -H i l l Companies, Inc., 2004

    Respect for People

    Level payrolls

    Cooperative employee unions

    Subcontractor networks

    Bottom-round management style

    Quality circles (Small Group InvolvementActivities or SGIAs)

    20

  • 7/29/2019 Justo a Tiempo y KANBAM

    20/31

    The M cGraw -H i l l Companies, Inc., 2004

    Toyota Production Systems Four Rules

    1. All work shall be highly specified as to content,sequence, timing, and outcome

    2. Every customer-supplier connection must be direct, andthere must be an unambiguous yes-or-no way to send

    requests and receive responses

    3. The pathway for every product and service must be

    simple and direct

    4. Any improvement must be made in accordance with the

    scientific method, under the guidance of a teacher, at the

    lowest possible level in the organization

    21

  • 7/29/2019 Justo a Tiempo y KANBAM

    21/31

    The M cGraw -H i l l Companies, Inc., 2004

    JIT Implementation Requirements:

    Design Flow Process

    Link operations

    Balance workstation capacities

    Redesign layout for flow

    Emphasize preventive maintenance

    Reduce lot sizes

    Reduce setup/changeover time

    22

  • 7/29/2019 Justo a Tiempo y KANBAM

    22/31

    The M cGraw -H i l l Companies, Inc., 2004

    JIT Implementation Requirements: Total

    Quality Control

    Worker responsibility

    Measure SQC

    Enforce compliance

    Fail-safe methods

    Automatic inspection

    23

  • 7/29/2019 Justo a Tiempo y KANBAM

    23/31

    The M cGraw -H i l l Companies, Inc., 2004

    JIT Implementation Requirements:

    Stabilize Schedule

    Level schedule

    Underutilize capacity

    Establish freeze windows

    24

  • 7/29/2019 Justo a Tiempo y KANBAM

    24/31

    The M cGraw -H i l l Companies, Inc., 2004

    JIT Implementation Requirements:

    Kanban-Pull

    Demand pull

    Backflush

    Reduce lot sizes

    25

  • 7/29/2019 Justo a Tiempo y KANBAM

    25/31

    The M cGraw -H i l l Companies, Inc., 2004

    JIT Implementation Requirements: Work

    with Vendors

    Reduce lead times

    Frequent deliveries

    Project usage requirements

    Quality expectations

    26

  • 7/29/2019 Justo a Tiempo y KANBAM

    26/31

    The M cGraw -H i l l Companies, Inc., 2004

    JIT Implementation Requirements:

    Reduce Inventory More

    Look for other areas

    Stores

    Transit

    Carousels

    Conveyors

    27

  • 7/29/2019 Justo a Tiempo y KANBAM

    27/31

    The M cGraw -H i l l Companies, Inc., 2004

    JIT Implementation Requirements:

    Improve Product Design

    Standard product configuration

    Standardize and reduce number of parts

    Process design with product design

    Quality expectations

    28

  • 7/29/2019 Justo a Tiempo y KANBAM

    28/31

    The M cGraw -H i l l Companies, Inc., 2004

    JIT Implementation Requirements:

    Concurrently Solve Problems

    Root cause

    Solve permanently

    Team approach

    Line and specialist responsibility

    Continual education

    29

  • 7/29/2019 Justo a Tiempo y KANBAM

    29/31

    The M cGraw -H i l l Companies, Inc., 2004

    JIT Implementation Requirements:

    Measure Performance

    Emphasize improvement

    Track trends

    30

  • 7/29/2019 Justo a Tiempo y KANBAM

    30/31

    The M cGraw -H i l l Companies, Inc., 2004

    JIT in Services (Examples)

    Organize Problem-Solving Groups

    Upgrade Housekeeping

    Upgrade Quality

    Clarify Process Flows

    Revise Equipment and Process Technologies

    31

  • 7/29/2019 Justo a Tiempo y KANBAM

    31/31

    The M cGraw -H i l l Companies, Inc., 2004

    JIT in Services (Examples)

    Level the Facility Load

    Eliminate Unnecessary Activities

    Reorganize Physical Configuration

    Introduce Demand-Pull Scheduling

    Develop Supplier Networks