lean - coursework 3

Upload: syed-shah-areeb-hussain

Post on 04-Nov-2015

222 views

Category:

Documents


0 download

TRANSCRIPT

  • M14 EKM FUTURE STATE MAP

    Syed Shah Areeb Hussain - 5401198

  • SUMMARY

    In the previous report, the current state map of RAC was produced and the problems within the

    system were highlighted. In this report we have suggested the improvements to the RAC

    manufacturing plant in the future state map. The suggested improvements can greatly reduce

    the lead time of the operation by introducing flow between the processes. This will enable RAC

    to meet the customer demand much faster through an efficient and lean process. The total lead

    time was reduced by almost 10 times in our analysis. Moreover, it also helped reduce the space

    and workload on operators.

  • TABLE OF CONTENTS

    1. ..................................................................................................................................................... 4

    2. INTRODUCTION ....................................................................................................................... 5

    3. LITERATURE REVIEW ............................................................................................................... 6

    3.1. VALUE STREAM MAPPING ................................................................................................ 6

    3.1.1. Current State Map .................................................................................................... 6

    3.1.2. Future State Map ...................................................................................................... 7

    3.2. TOOLS AND TECHNIQUES FOR THE FUTURE STATE ......................................................... 7

    3.2.1. Pareto Analysis .......................................................................................................... 7

    3.2.2. Spaghetti Diagram..................................................................................................... 8

    3.2.3. Heijunka Box ............................................................................................................. 8

    3.2.4. Kanban ...................................................................................................................... 9

    3.2.5. Pacemaker Process ................................................................................................. 10

    3.2.6. Supermarkets .......................................................................................................... 10

    3.2.7. FIFO Lanes ............................................................................................................... 10

    4. REVIEW OF CURRENT STATE MAP ........................................................................................ 12

    4.1. WIP IN DAYS ................................................................................................................... 12

    4.2. PARETO ANALYSIS .......................................................................................................... 13

    4.3. PERCENTAGE UTILIZATION ............................................................................................. 14

    4.4. CURRENT STATE MAP (WITH KAIZEN BURST SUGGESTIONS) ........................................ 14

    5. FUTURE STATE MAP .............................................................................................................. 16

    6. DISCUSSION ........................................................................................................................... 17

    6.1. SUPPLIER LOOP............................................................................................................... 17

    6.2. PACEMAKER/CUSTOMER LOOP ..................................................................................... 17

    6.3. PROCESS LOOP ............................................................................................................... 19

    6.4. AZ LOOP .......................................................................................................................... 19

    6.4.1. Press Blank .............................................................................................................. 20

    SMED ................................................................................................................................. 20

  • 6.4.2. Press Form .............................................................................................................. 21

    SMED ................................................................................................................................. 21

    6.4.3. Machining Cell ......................................................................................................... 21

    Calculations ....................................................................................................................... 22

    Yamazumi Board ............................................................................................................... 23

    Standard Ops Sheet .......................................................................................................... 24

    6.4.4. Automatic Paint ...................................................................................................... 24

    6.5. BZ LOOP .......................................................................................................................... 25

    6.5.1. Saw .......................................................................................................................... 25

    6.5.2. BZ Cell ...................................................................................................................... 26

    Calculations ....................................................................................................................... 26

    Cell Layout ......................................................................................................................... 27

    Walk Diagrams .................................................................................................................. 27

    6.5.3. Heat Treatment ....................................................................................................... 28

    6.6. ASSEMBLY LOOP ............................................................................................................. 28

    6.6.1. Assembly 1 .............................................................................................................. 29

    6.6.2. Assembly Cell .......................................................................................................... 29

    Yamazumi board ............................................................................................................... 30

    Standard Operations Sheet ............................................................................................... 30

    6.7. FACTORY LAYOUT ........................................................................................................... 31

    7. IMPLEMENTATION PLAN ...................................................................................................... 32

    8. BENEFITS ............................................................................................................................... 34

    9. REFERENCES .......................................................................................................................... 35

  • List of Figures

    Figure 2-1 - Types of kanban signals - Source: (Nash & Poling, 2011) ............................................ 9

    Figure 3-1: WIP in days after each process ................................................................................... 12

    Table 3-1: Pareto Analysis of WIP in days ..................................................................................... 13

    Figure 3-2: Percentage utilization with respect to the takt time ................................................. 14

    (Note: Takt time for processes press blank to automatic paint is 150 sec whereas takt time of

    process saw to assembly 3 is 300 sec) .......................................................................................... 14

    Figure 5-1: Suppliers loop ............................................................................................................. 17

    Figure 5-2: Pacemaker loop .......................................................................................................... 18

    Table 5-1: Heijunka Box ................................................................................................................ 19

    Figure 5-3: AZ Loop ....................................................................................................................... 19

    Figure 5-4: Current state yamazumi board ................................................................................... 23

    Figure 5-5: Yamazumi board Adjusted ....................................................................................... 23

    Figure 5-6: Standard Operations Sheet (Manufacturing cell)....................................................... 24

    Figure 5-7: BZ Loop ....................................................................................................................... 25

    Figure 5-8: Cell Layout - BZ Cell .................................................................................................... 27

    Figure 5-9: Walk Diagram ............................................................................................................. 27

    Figure 5-10: Assembly loop ........................................................................................................... 29

    Figure 5-11: Yamazumi Board - Assembly cell .............................................................................. 30

    Figure 5-12: Spaghetti Diagram .................................................................................................... 31

  • 1. INTRODUCTION

    The roots of the lean manufacturing principles can be traced back to the Ford production

    system developed by Henry Ford himself. It was the first instance in which the complete

    production process was integrated into a single flow using the concept of moving assembly

    lines. Special-purpose machines and go/no-go gauges were used to fabricate and assemble

    different components within a few minutes. The problem with this system was that it greatly

    reduced the worker span of control and was unable to provide any variety in the product.

    After World War II, the Japanese analyzed Fords Original thinking and introduced simple

    innovations to provide both continuity and variability in the process flow. These innovations

    were implemented within the Toyota Production System and were later named as the lean

    production methodology.

    The Lean production system, as introduced by Toyota, was composed of five basic principles

    (Womack & Jones, 1996)

    To identify the value that the customer desires

    To identify the processes that add value to the product and eliminate all wastes (muda)

    within the process

    To make a continuous flow of product through the value-added processes

    To introduce pull systems in place of push between steps where continuous flow is not

    possible

    Continuously improve to reduce the steps, time and information needed to meet the

    customer demand

    This philosophy helped Toyota become the largest automaker in terms of the overall sales and

    poised it as the exemplar in efficient production systems (OICA, 2012). Today, lean has becomes

    an industrial norm and more and more organizations are attempting to implement lean in both

    the manufacturing and the service industry.

    Over the years a number of different technologies and tools have progressed lean even further

    and has ushered a new age in the lean production systems. However, switching from a mass

    production to a lean manufacturing system is not an easy feat and hence several companies are

    still hesitant in introducing lean technologies. One of the key problems faced is the difficulty in

    identifying the wastes within the system and the changes to be made (Ludvig, 2011). To

    facilitate a smooth transition from a mass production philosophy to lean manufacturing Mike

    Rother and John Shook introduced the concept of value stream mapping in their book Learning

    to See (Rother & Shook, 1999). The value stream map is a method of mapping the process flow

    and the communications within the processes of an organization. Such a map enables almost

  • anyone to differentiate the value from the wastes and can be used to develop a picture of how

    the process flow should be in the future.

    The current report is a continuation of the previous report in which a current state map was

    developed for the Reads Automotive Components. Upon analyses of the current state map,

    several areas of improvement were identified. These will be introduced and implemented in the

    future state map and presented in this report.

    2. LITERATURE REVIEW

    2.1. VALUE STREAM MAPPING

    Value Stream Mapping is a tool used in the industry to understand the flow of material and

    information as a product makes its way through the value stream (Rother & Shook, 1999).

    There are several benefits to value stream mapping.

    1) Firstly, it enables us to visualize the complete flow rather than a single process.

    2) It also makes the wastes in the process more visible and easy to recognize.

    3) Value Stream Mapping promotes a common language that can be used by everyone to

    communicate about the manufacturing processes

    4) It brings to light the different decisions within the flow enabling discussions over them

    5) It makes the implementation easier by providing the basis for an implementation plan

    6) It helps link the flow of information with the flow of material within the process.

    7) Lastly, it provides a qualitative overview as opposed to a quantitative one and hence

    describes in detail what is needed to create flow.

    Value stream maps can be used throughout the implementation process to identify the areas

    for improvement and then to develop the implementation plan. It involves the development of

    a current state map and a future state map.

    2.1.1. Current State Map

    The current state map is a picture in time of the current processes involved in the production. It

    provides a detailed view of the flow of information from the customer through the production

    control and to the supplier as well as the flow of materials from the supplier through the

    various processes and then to the customer.

    The current state map brings to light the different wastes within the processes and hence

    provides a starting point for the implementation of lean techniques. Combining the current

    state map with other lean analysis tools such as the Yamazumi board, spaghetti charts and

    pareto analysis can prove to be very powerful in determining the areas for improvement.

  • The current state map and the various analysis tools were described in detail and utilized in

    coursework 1, wherein a current state map for Reads Automotive Components was produced.

    2.1.2. Future State Map

    The future state map is developed using the current state map such that its implementation

    results in the elimination of the wastes discovered in the current state map. It provides the

    goals to achieve so as to make the process completely efficient. This map provides the basis for

    all the actions needed to create a continuous flow.

    Though the future state map provides the goal that must be achieved, it is not always that the

    value stream is modified exactly as the future state map. This is because while each of the

    outcomes of the future state map are implemented, new problems and opportunities arise,

    thereby greatly changing the value stream. Oft times some changes take too long or may be too

    expensive to implement. Hence while the eventual outcome could be close to the map, it may

    not be exactly the same. In this way the future state map provides the blueprint for the change

    (Nash & Poling, 2011).

    To create the future state map, the first step is to brainstorm on the current state map and

    identify the areas of improvement and the possible solutions. These can be illustrated directly

    on the current state map in the form of Kaizen bursts. Once all the potential solutions are

    recorded, the most applicable and suitable solutions are selected and used to develop the

    future state.

    The future state map generally makes use of several lean tools such as the supermarket, FIFO

    lanes, kanbans and the Heijunka box. These tools and techniques are discussed and described

    in the subsequent sections.

    2.2. TOOLS AND TECHNIQUES FOR THE FUTURE STATE

    The value stream maps illustrate the bigger picture of the current processes and the future

    changes. This big picture is then comprehended by several tools and techniques which provide

    insight of how the processes work. Some of the key tools and techniques used to find the

    wastes in a current state map have been described and used in coursework 1. In this report, the

    tools and techniques for identifying the areas of improvement and implementing those

    improvements will be used. These tools are

    2.2.1. Pareto Analysis

    The Pareto Principle was first used by Vilfredo Pareto, an Italian economist in the nineteenth

    century, who determined that about 80% of the wealth in the state was in the hands of only

    20% of the people. The Pareto Principle was found to be true in several other situations in the

  • industry and government. To put in general terms, the Pareto principle states that 80% of the

    effects are caused by 20% of the causes (Fryman, 2002).

    The strength of the Pareto principle lies in the fact that it can be used to identify the largest

    contributors of process variations or other areas which provides valuable insight on where to

    spend resources (Fryman, 2002).

    The Pareto analysis is performed by arranging the different categories in a descending order

    and finding the cumulative values at each level. Upon calculation of the percentages of the

    cumulative values, the largest contributors can be identified easily.

    2.2.2. Spaghetti Diagram

    A spaghetti diagram is a visual layout of the flow of the process as it would appear as one walks

    through it from the beginning to the end (Nash & Poling, 2011). The spaghetti diagram enables

    the viewer to observe the movement of the operator. This brings to light the wastes of motion

    and transportation and can be used to determine the optimal layout of the different

    departments such that the distances travelled between processes is minimal. Reducing the

    complexity of routes can be extremely advantageous as it reduces the wastes of motion and

    transportation while also creates order within the factory floor (Kaplan, 2008).

    2.2.3. Heijunka Box

    Heijunka is the Japanese term for load leveling or balancing. The Heijunka box is a load

    leveling system that enables the factory to make what is needed, when it is needed and in the

    exact quantity that it is needed (Luyster & Tapping, 2006).

    There are several advantages to such a system. Firstly, it accomplishes a standardized process

    that makes any problem within the flow easily visible, allowing immediate corrective action.

    Secondly, load leveling also creates a base for other effective kaizen to be implemented. Lastly,

    the load leveling system enables quick response to variation in production planning and

    scheduling (Luyster & Tapping, 2006).

    The Heijunka is responsible for setting the pace of the flow for the product withdrawal and

    hence the production process. The heijunka box simply implies that product is withdrawn from

    the production line at established increments of time known as the pitch. It is preferable to

    keep the pitch as low as possible (Luyster & Tapping, 2006). The pitch (pace of withdrawal) can

    be calculated by multiplying the takt time with the no. of products that can fit in a single

    container. For example if the takt time is 60 seconds and one container can be filled with 20

    products, the pitch of the process will be 20 minutes ((60/60) min * 20). This means that every

    20 minutes, a container containing 20 products is withdrawn from the production line. This

  • helps the production line to constantly measure their performance versus the standard

    required.

    One of the simplest heijunka systems is the SLMS heijunka developed by Standard Lean

    Manufacturing Systems Inc. for the Toyota Production System (Luyster & Tapping, 2006). In this

    system a heijunka box is used which has several sections based on the pitch intervals. The

    production control places the orders in these boxes and they are withdrawn by the process at

    selected intervals i.e. the pitch.

    Andon signaling systems can be used if the production line is behind schedule. This notifies the

    management that some problem exists within the flow and enables them to react in a timely

    manner. To maintain the production while behind schedule, wait boxes can also be used

    (Luyster & Tapping, 2006).

    2.2.4. Kanban

    Kanban in Japanese refers to a visual signal. Kanban is described as a material flow control

    mechanism and determines the proper quantity and the proper time for the production of the

    required products (Graves, et al., 1995). A Kanban system was initially developed to fulfill the

    specific needs of the Toyota Production System and was later adopted into the general lean

    manufacturing principles (Junior & Filho, 2010).

    Within the setting of a lean manufacturing plant, several Kanban signals are used for relaying

    information. Kanbans sent to the purchasing department are collected at the Kanban post

    (Junior & Filho, 2010). Within a supermarket, two types of Kanbans are used the withdrawal

    Kanban and the production Kanban. The withdrawal Kanban visually informs the workers when

    replenishment is required. This informs the workers when raw materials, the work in process or

    finished goods need to be withdrawn from the supermarket. On the other hand, the production

    kanbans are replenishment signals from a super market to an upstream process and signals the

    process to produce additional parts and products (Nash & Poling, 2011). The representation of

    the different kanbans in the value stream maps is provided below:

    Figure 2-1 - Types of kanban signals - Source: (Nash & Poling, 2011)

  • 2.2.5. Pacemaker Process

    While in a push system schedules are sent to each and every process, in a pull system the

    schedule is provided to only one process known as the pacemaker process. The way the

    production at this process is controlled determines the pace for all the upstream processes. The

    pacemaker also determines the processes in the value stream that become part of the time

    required to meet the customer demand. For this reason it is mostly preferable to set the most

    downstream continuous flow process as the pacemaker (Rother & Shook, 1999).

    2.2.6. Supermarkets

    A supermarket is a controlled inventory system where kanbans are used to signal the need for

    replenishment. These kanbans are generally in the form of visual aids, such as cards, bins, lights

    or racks that inform the employees in the value stream that additional inventory or WIP is

    required. Supermarkets are used in order to control the inventory in places where continuous

    flow is not possible.

    Supermarkets are used to control and manage several products in the value stream. The

    upstream process connected to the supermarket sends a withdrawal Kanban signal to the

    supermarket and receives the required amount of items. Based upon the amount withdrawn,

    the supermarket then sends a production Kanban to the upstream process to which it is

    connected. This signals the process to start production and supply the required amount of parts

    to the supermarket. Supermarkets are represented in a value stream map as:

    2.2.7. FIFO Lanes

    A FIFO lane (first in, first out) is an inventory management system that ensures that the oldest

    WIP that enters the area is the first to receive the value added activity. The amount of WIP that

    stays at the FIFO lane is generally limited to a specific amount. When the limit of the WIP is

    reached, the preceding process stops production.

    The FIFO lanes are very easy to manage as they do not need much Kanban signaling (only the

    first process needs to know when to produce). However, in certain situations it is unfavorable

    to use a FIFO lane such as

    When the two processes have very different cycle times

  • When lot sizes of each product is different

    When parallel processes merge or a single flow splits

    When high flexibility and reaction time is required

    A general value stream contains a mix of FIFO lanes and supermarkets. Generally all the

    processes upstream of the pacemaker process are connected by a FIFO lane. The FIFO lane is

    represented on the future state map as

  • 3. REVIEW OF CURRENT STATE MAP

    The current state map for RAC was developed in coursework 1 and was analyzed with respect

    to the lean manufacturing principles. The current state map along with the tools used to

    analyze the map in coursework 1 are presented in Appendix A. Based on the analysis it was

    found that at least 6 of the 7 deadly wastes of lean was present in the process stream. These

    were the wastes of inventory, transportation, motion, waiting, overproduction and defects.

    Before building the future state map, it is essential to identify the areas for improvement in the

    current process and analyze which of these will be most applicable.

    3.1. WIP IN DAYS

    Based on the current state map, the WIP after each process is presented in Figure 3.1.

    Figure 3-1: WIP in days after each process

    Figure 3.1 provides a clear view of the WIP in days after each process and its impact on the

    system. This can be used to perform the Pareto analysis and identify the greatest contributors

    to the inventory in the process.

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    WIP

    (d

    ays)

    Process

  • 3.2. PARETO ANALYSIS

    The Pareto analysis for the WIP in days is illustrated in Table 3.1. The major contributors to the

    WIP in days have been highlighted in blue.

    Table 3-1: Pareto Analysis of WIP in days

    Process WIP (days) Cumulative WIP Cumulative WIP (%) Cumulative Range (%)

    Press Blank 16.9 16.9 19.31 6.67

    Dispatch 16 32.9 37.60 13.33

    Grind 7.7 40.6 46.39 20.00

    Heat Treatment 7.1 47.7 54.51 26.67

    Raw Materials Store 5 52.7 60.22 33.33

    Raw Materials Store (BZ111) 5 57.7 65.94 40.00

    Press Form 4.8 62.5 71.42 46.67

    Insert 4.7 67.2 76.79 53.33

    Drill 3.9 71.1 81.25 60.00

    Assembly 2 3.8 74.9 85.59 66.67

    Automatic paint 3.6 78.5 89.70 73.33

    Assembly 1 3.2 81.7 93.36 80.00

    Saw 2.4 84.1 96.10 86.67

    Assembly 3 2.3 86.4 98.73 93.33

    CNC Turn 1.11 87.51 100.00 100.00

    TOTAL 87.51

    As evident from the analysis, 60% of the processes contribute to 81.25% of the WIP. This shows

    that the 20/80 rule is not completely applicable and hence to produce a sizeable impact,

    changes must be introduced in several processes. Inventory at Press blank, grind, press form,

    insert and drill can be eliminated by introducing cells. Where continuous flow is not possible,

    supermarkets and FIFO lanes can be used. Similarly inventory at the Dispatch and the two raw

    material stores is reduced by the use of supermarkets and FIFO lanes. However, since the heat

    treatment process is sub-contracted, it is not possible to reduce the turnaround time. In this

    case we can only connect the preceding and the succeeding processes with a FIFO lane or

    supermarket.

    Often all the changes suggested in the Future State Map may not be implemented due to lack

    of resources or long time for implementation. In such cases a Pareto analysis becomes

    extremely useful in order to identify optimization of which processes will produce the greatest

    impact. The Pareto analysis performed here shows that to effectively reduce the inventory, the

    excess WIP at 6 of the processes have to be eliminated.

  • 3.3. PERCENTAGE UTILIZATION

    Another common area of improvement is the utilization of the machines. Often the workload

    distributed between the workers is uneven. This results in greater stress at some process while

    wastage due to waiting at other processes. Figure 3.2 provides a visual representation of the

    utilization of the machines and their comparison to the takt time.

    Figure 3-2: Percentage utilization with respect to the takt time (Note: Takt time for processes press blank to automatic paint is 150 sec whereas takt time of process saw to assembly 3 is 300 sec)

    We can see from Figure 3.2 that there is great variability in the percentage utilization. While

    some operators contribute to only 5% of the takt time, others contribute to almost 200% of the

    takt time. This variability results in bottleneck and stress, which in turn reduces efficiency and

    quality of products. Therefore, work balancing must be introduced to the value stream.

    3.4. CURRENT STATE MAP (WITH KAIZEN BURST SUGGESTIONS)

    In the preceding sections several areas for improvement were recognized in the current value

    stream. Based on the literature review, all the suggestions are then noted on the current state

    value stream map inside Kaizen bursts. These makes it easier to develop the future state map

    based on the suggested changes. The current state map with the suggested changes is

    illustrated in Figure 3.3.

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    200

    Pe

    rce

    nta

    ge U

    tiliz

    atio

    n

    Processes

  • Introduce

    Cell

  • 4. FUTURE STATE MAP

  • Figure 5-1: Suppliers loop

    5. DISCUSSION

    5.1. SUPPLIER LOOP

    A closer look at the supplier loop in the future state map is provided

    in Figure 5.1. As seen in the future state map, the inventory raw

    materials store at the start of the AZ process stream and the BZ

    process stream has been replaced by supermarkets. This ensures that

    the inventory at the raw materials store is controlled.

    In the current state map the inventory at the raw goods store

    accounts for five days in the lead time. The need for a high amount of

    inventory is due to the fact that raw materials from lanchester steel

    are received only once a week. Hence the raw goods store must

    contain raw materials for the whole week, equivalent to 5 days. To

    eliminate this, it is suggested to instead place a daily order to

    Lanchester steel and therefore receive raw materials for each of the

    process streams daily. Therefore, it would be only necessary to hold a

    single days inventory at the raw goods store. In order to account for

    delays or other risks, a safety stock of 0.5 days may be added,

    therefore making the total inventory at the raw goods supermarket to

    be 1.5 days.

    When materials are withdrawn from the raw materials supermarkets,

    a withdrawal Kanban post is issued which sends a signal to the

    production control to place a daily order to Lanchester Steel. This

    ensures that the order is placed based on the actual usage and not

    based on the MRPs estimate of the future usage of the raw materials.

    Though MRP may still be used to provide capacity-planning forecasts

    for the supplier, the day to day orders must be based on pull. This

    type of daily receipt of raw materials is called milk runs.

    5.2. PACEMAKER/CUSTOMER LOOP

    The pacemaker loop displays the material and information flow between the production

    control, the customer and the pacemaker process of the value stream. Figure 5.2 presents a

    closer look at the pacemaker loop of the future state map of RAC.

    The customer demand is 2520 car sets per month, where each car set consists of the parts

    AZ123, AZ124, AZ223 and AZ224. This equates to a daily demand of 504 units of each part per

  • day. The daily demand for BZ111 components that assemble to AZ123 and AZ124 will be 252

    units per day.

    3 shipments per day are carried out to the customer. Returnable carriers hold 15 assemblies

    each.

    The production control sets the pitch for the process stream. The pitch for RAC can be

    calculated using the takt time and the packout quantity. The takt time for the assembly flow is

    150 seconds as calculated in the current state map (Appendix ).

    =

    = 15 150

    = 2,250 = .

    Therefore, the daily order is divided based on the pitch and every 37.5 minutes production

    control provides instructions for withdrawal of 15 assemblies from the supermarket, through

    Kanban posts in the load levelling box. These assemblies are then transferred to the dispatch

    for shipment. The withdrawal of parts from the supermarkets triggers signal Kanban that

    notifies the preceding process for replenishment. The Heijunka box for the future state map of

    RAC Automotive is displayed in table 5.1

    Figure 5-2: Pacemaker loop

  • Table 5-1: Heijunka Box

    8:00 8:37 9:15 9:30 10:08 10:46 11:24 11:54 12:32 13:09 13:47 14:02 14:40 15:18 15:56

    AZ 123

    Bre

    ak 1

    Lun

    ch

    Bre

    ak 2

    AZ 124

    AZ 223

    AZ 224

    BZ 111

    5.3. PROCESS LOOP

    The process or the manufacturing loop represents the flow of information and materials

    through the process stream. The process stream can be divided into three further loops,

    namely the AZ Loop, The BZ Loop and the Assembly loop.

    5.4. AZ LOOP

    The AZ Loop contains the processes press blank, press form, machining cell and automatic

    paint. A closer view of these processes is provided in figure 5.3.

    Figure 5-3: AZ Loop

    AZ 123

  • The processes press blank, press form, machining cell and auto paint are connected by a FIFO

    lane. Upon withdrawal of items from the supermarket after Auto Paint, a batch signal is sent to

    the very first process i.e. the press blank. The need of a batch signal arises from the fact that

    press blank is a low cycle time shared resource, due to which it must be done in batches. There

    are several reasons for using FIFO lanes in between the four processes. Firstly, FIFO lanes add

    simplicity to the system as compared to supermarkets, which require much organization and

    control. This simplicity ensures smooth flow within the process stream. Secondly, FIFO lanes

    can often prove advantageous in batch processes, and since the first two processes in the AZ

    loop are batch, it becomes ideal. After the process Auto Paint it is necessary to have a

    supermarket. This is because after this process the stream splits into two, with 2 parts going to

    assembly 2 and 2 parts going to assembly 1. In base of splitting or joining of process stream,

    FIFO lanes become difficult to manage and hence supermarkets are preferable. Moreover, they

    also provide a flow of information from the pacemaker process to the first process.

    5.4.1. Press Blank

    Press blank are high volume high value equipment and is consequently a shared resource at

    RAC. Due to this it cannot be placed in a cell and must remain as a separate process. However,

    the main issues with the press blank that has been highlighted in the current state map is the

    extremely large batch size. Currently a batch size of 2500 is used which results in almost every

    product every month. The reason for such high batch times is that even through the process

    takes only 3 seconds, the changeover time takes 320 minute. Such high changeover times and

    low cycle times result in the need for high batch sizes. In order to prevent accumulation of

    inventory due to high batch size, it is necessary to therefore reduce the batch size.

    SMED

    The concept of SMED (Single Minute Exchange of Dyes) can be used to attain a production rate

    of every product every shift for the Press Blank process. Currently the changeover takes 320

    minutes, while carrying out the operation on a batch size of 2500 would take (2500 x 3) or 125

    minutes. This would add up to be 445 minutes. However, the available time per shift is only 420

    minutes. Therefore, the work will have to be carried over to the next shift. This does not

    account for the other processes that need to be carried out on the press blank as it is a shared

    resource.

    One way the changeover time can be reduced is by changing the layout. As shown in the

    spaghetti chart, the tool storage and the tooling area are separated from the main factory floor

    by three other rooms. Hence a majority of the time is taken in walking between the two areas

    and unnecessary motion. To eliminate this waste, the tools required for Press blank must be

    available next to the machine. Using 5S principles to create a clean and organized workplace

  • can further reduce the changeover time. Finally, it would require an analysis of the external and

    the internal work elements to appropriately distribute the work while the machine is operating

    and when it is stopped. It is assumed that upon performing the aforementioned techniques, the

    changeover time has been reduced to less than 10 minutes.

    Once the change over time has been reduced, we can create continuous flow by sizing the

    batch such that it is completed within the takt time. From the current state map, we know that

    the takt time for the process is 150 seconds and the cycle time is 3 seconds. Therefore the

    appropriate batch size would be 50. Using this method we can now produce every product

    every shift.

    5.4.2. Press Form

    Similar changes can be introduced to the press form process. As with the press blank process,

    this is a high change over low cycle time process that operates in batches of 2500 units.

    SMED

    The cycle time of press form is 5 seconds while its changeover time is 290 seconds. As with the

    press blank, the major causes of high changeover times are the wasteful motion. By eliminating

    long walks, applying 5S techniques and appropriately converting internal work elements to

    external, we can assume that the changeover time has been reduced to less than 10 minutes. In

    order to match the total time with the takt time, we can use a batch of 30 units which would be

    produced in 150 seconds.

    Note: It may seem that the press blank and the press form processes are producing much faster

    than needed, since they produce in batches of 50 and 30 every takt instead of just one product

    every takt. However, in practical the machines are not operated continuously as they are a

    shared resource and will be used for other processes as well. Therefore, whenever needed they

    produce in batches and transfer it to the FIFO lanes. The maximum capacity of the FIFO lane

    can be calculated by adding the batch sizes of the two processes and the safety stock.

    Max. no. of units (FIFO1) = 50 + 30 + 20 = 100

    Where 20 is assumed the safety stock.

    5.4.3. Machining Cell

    The machining cell consists of the processes insert and drill. Since the cell does not contain any

    automatic process, it is a standard cell.

  • Calculations

    Firstly it is necessary to decide the number of operators for the cell. This can be calculated using

    the formula:

    . =

    =38 + 60

    150

    = 0.65 = 1 operator

    Next, we need to calculate the target takt time and verify is the operation time is less than the

    target takt time. To do these we need to calculate the overall equipment efficiency. Assuming

    an equipment efficiency 95% we have

    =

    () = 0.95 0.99

    () = 94.05%

    () = 0.95 0.95

    () = 90.25%

    () = 92.15

    =

    = 150 0.9215

    = .

    The Total operation time is 98 seconds which is well below the target takt time.

  • Yamazumi Board

    Figure 5-4: Current state yamazumi board

    Figure 5.4. shows the current work distribution of the two processes and its relation to the takt

    time. It is clear from the yamazumi board that the two operators are underutilized and work for

    less than half the takt time. Therefore, in the future state machining cell, the two operations

    are clubbed together and performed by a single operator.

    Figure 5-5: Yamazumi board Adjusted

    Figure 5.5 shows the yamazumi board that has been adjusted for the machining cell. A single

    operator performs both the two operations. The total cycle time for the cell is 98 seconds which

    is still well below the takt time of 150 seconds. However, it is not possible to combine either the

    preceding or the succeeding process with the cell and hence the subsequent FIFO lane size is

    adjusted to prevent overproduction from the machining cell.

    0

    50

    100

    150

    200

    Operator 1 Operator 2Insert Drill Takt

    0

    50

    100

    150

    Operator 1

    Chart Title

    Insert Drill

    Takt Time

    Takt Time

  • Standard Ops Sheet

    The standard Operations sheet provides the general layout of the cell. As seen in the standard

    operations sheet, a general L shaped plan will be used wherein the operator retrieves raw

    materials from the raw goods store, performs Insert operation, switches to Drill operation and

    then places the units in the finished goods store.

    5.4.4. Automatic Paint

    The cycle time for the automatic paint is 280 seconds. This is well above the takt time of 159

    seconds. Moreover, it is not possible to accommodate the automatic paint in the

    manufacturing cell as the complete walks, manual operation times, and load unload times

    would exceed the target takt time.

    Though the cycle time of the automatic paint is 280 seconds, it produces 2 units in that time as

    it can hold two parts at a time. Moreover, the twin pallet system allows for efficiently loading

    Insert Drill

    Gan

    gway

    Figure 5-6: Standard Operations Sheet (Manufacturing cell)

    1

    2

    Raw Materials

    Store

    Finished

    Goods

    Store

    2 1 2

    Operator route Standard WIP

    Safety alert Operator Quality check

  • and unloading while the operation is continuing, i.e. loading and unloading becomes and

    external process. Due to this even though the cycle time of the machine is higher, it will be able

    to meet the demand within the pitch and does not require a purchase of an extra machine.

    However, to ensure that there is no waiting, the inventory before and after the automatic paint

    must be appropriately managed.

    The automatic paint is connected to the preceding process by a FIFO lane. The FIFO lane has a

    maximum size of 100 units and it ensures that enough WIP is always available to the automatic

    paint.

    The succeeding process is connected by a supermarket. Therefore, we must ensure that the

    supermarket has enough WIP to meet the needs of the succeeding processes. For this reason, a

    WIP of 50 units for each product is selected. Moreover, the reorder point is set to 20 units. This

    ensures that there is no shortage of parts to the processes after the automatic paint.

    5.5. BZ LOOP

    The BZ loop contains the saw, BZ cell and the heat treatment. It is responsible for producing the

    BZ 111 parts which then attach to the AZ 223 and AZ 224 parts in Assembly 1. A summary of all

    the operations and cells within the BZ loop are presented below.

    Figure 5-7: BZ Loop

    5.5.1. Saw

    The first operation in the BZ loop is saw. However, this is a shared resource and hence cannot

    be introduced in a flow. Therefore it has to be kept as a separate process. To introduce smooth

    flow, a supermarket is used after the Saw operation.

    Raw materials are withdrawn from the raw materials supermarket and then undergo the saw

    operation which has a cycle time of 15 seconds. To meet with the takt time of the flow it is

    suggested to carry out the saw operation in matches of 20 units. Therefore the total time of the

  • operation will be 300 seconds which corresponds to the takt time. Moreover, there is no

    changeover time and hence no modifications are needed.

    The saw operation is followed by a supermarket with a maximum capacity of 50 units. The

    reorder point of the supermarket is 10 units since the replenishment time of the previous

    operation is small.

    5.5.2. BZ Cell

    The BZ Cell contains the operations CNC Turn and Grind. Since it contains both automatic and

    manual times, the cell is a nagare cell. Based on the high cycle time, a new CNC turn machine

    will be needed to complete a single walk within the takt time.

    Calculations

    The first step is to calculate the number of operators for the nagare cell. For this it is necassry

    to present a clear view of the manual and the automatic operations.

    Operation Manual Time Automatic Time

    CNC 10s 535s

    Grind 250s -

    Therefore the total manual time for the operation is 260 seconds.

    Calculating the no. of operators = 260/300

    = 0.8667 = 1 operator

    Therefore only a single operator is required.

    Next we need to calculate the target takt time of the cell. We assume the performance of the

    equipment to be 95%

    OEE (CNC) = 0.95 x 0.9 = 85.5%

    OEE (Grind) = 0.95 x 0.92 = 87.45%

    OEE (Avg) = 86.48%

    Target takt time = 0.8648 x 300 = 259.43 seconds

  • Cell Layout

    A standard U shape layout is selected for the BZ cell. It is assumed that walks between the

    machines takes 3 seconds.

    Walk Diagrams

    Figure 5-9: Walk Diagram

    The operator first takes raw materials from the raw materials store and loads them in CNC 1.

    Then he moves on to the Grind and performs manual work for 250 seconds. After completing

    his work he places the units in the finished goods store and starts the second cycle. In the

    seconds cycle the operator uses the CNC 2 machine while the automatic process in CNC 1 still

    RMS CNC

    Grind FGS

    Figure 5-8: Cell Layout - BZ Cell

  • continues. By the end of the second cycle the CNC 1 has completed the automatic work and is

    used in the third cycle.

    The total time for the operator assuming 3 second walks will be

    3 + 10 + 3 + 250 + 3 + 3 = 272 seconds

    Therefore the operator has a lag time of 18 seconds. However, this is higher than the target

    takt time of 259 seconds. Therefore, steps must be taken to improve the performance and

    quality pass rate of the machine so that the target takt time is higher. This would require better

    maintenance or replacement with a new machine in the long term.

    It is to be noted that the CNC Turn machine has a very high changeover time of 120 minutes.

    However, since the BZ loop is dedicated to only a single type of product, changeovers within

    the loop will not be required and hence there is no need to apply SMED principles to the CNC

    Turn. However, 5S principles may still be applied to promote a more well organized layout.

    5.5.3. Heat Treatment

    The final process in the BZ Loop is the Heat treatment. The heat treatment is a subcontracted

    process and hence it cannot be optimized to reduce cycle times or inventory. Currently the heat

    treatment takes 120 minutes and has a turnaround time of 3 days. This turnaround time is non

    value added but cannot be changed as the process is subcontracted.

    It is not possible to connect subcontracted systems with a supermarkets as the subcontractors

    may not agree to use the Kanban signals for providing replenishment. Moreover, due to a high

    turnaround time it is also needed to have some amount of WIP as a safety stock. Hence the

    best option to connect subcontracted processes is through a FIFO lane. This ensures that there

    is always enough WIP to meet the demands of the processes further down the stream.

    5.6. ASSEMBLY LOOP

    The assembly loop consists of Assembly 1 and the Assembly cell.

  • Figure 5-10: Assembly loop

    5.6.1. Assembly 1

    Assembly 1 is responsible for the assembling of AZ 123 and AZ 123 parts with the BZ 111 parts.

    This process cannot be introduced in a cell. This is due to the splitting of the process streams

    before and after the cell, which would make it extremely difficult to manage if put in a cell.

    The takt time for Assembly 1 is 300 seconds, while is cycle time is 290 seconds. Therefore the

    operation is within the takt time and has 10 seconds of lag time. This is ideal and hence does

    not require any optimization.

    Assembly 1 receives AZ 123 and AZ 124 units from the automatic paint through a supermarket

    and received BZ 11 parts from the heat treatment subcontractor through a FIFO lane. Since

    there a split in the process stream before the process and convergence after the process, it is

    necessary to keep Assembly 1 separate from the other assemblies. This is done also due to the

    fact that its takt time is different than the takt time of Assembly 2 and Assembly 3.

    5.6.2. Assembly Cell

    Assembly 2 and Assembly 3 have been grouped together to form and assembly cell. This is

    because the two processes have a very low cycle time and hence are well below the takt time

    even after grouping the two together. This is the pacemaker process as the supermarket

    succeeding the cell receives the order every pitch from the production control.

    The Assembly cell withdraws AZ 123 and AZ 124 parts from the supermarket after assembly 1,

    and withdraws AZ 223 and AZ 224 parts from the supermarket after Automatic paint.

    Therefore, the use of supermarkets in the previous processes helps create a smooth continuous

    flow. A FIFO lane in place of the supermarkets would have been possible but would be

  • extremely difficult to manage. The Assembly cell is followed by a supermarket. When units are

    withdrawn from the supermarket for dispatch, a signal is sent to the Assembly cell for

    replenishment. The reorder point of the super market is selected to be 10 units.

    Yamazumi board

    Figure 5-11: Yamazumi Board - Assembly cell

    Figure 5.10 shows the comparison of the workloads before and after. Initially, the two

    operators have a very low work load which results in much waste. When both the operations

    are clubbed together to be performed by a single operator, the work load is still below the takt

    time with 5 seconds of lag time.

    Standard Operations Sheet

    Since the cell consists of only a single operator performing both assembly 2 and assembly 3, the

    layout of the cell is extremely simple with a single desk with raw materials and finished goods

    store on either side.

    0

    20

    40

    60

    80

    100

    120

    140

    160

    Operator 1 Operator 2

    Assembly 2 Assembly 3 Takt

    0

    20

    40

    60

    80

    100

    120

    140

    160

    Operator 1

    Assembly 1 Assembly 2

    Takt Time

  • 5.7. FACTORY LAYOUT

    In order to accommodate the cells and implement the different parts discussed above, the

    factory layout must be changed to be better suited for cellular manufacturing.

    The spaghetti diagram shows the flow of products through the layout of the factory floor. Based

    on the future state map, a change in the factory floor layout has been proposed. The suggested

    layout ensures a smooth flow of units through the factory floor. The use of 5S principles and

    well organized work space with tooling present right at the point of use has eliminated the

    need for a separate tool room, tool store and a guage room. Moreover, the use of a

    supermarket at the start has also eliminated the need of a raw materials store. Due to this the

    overall space taken has been greatly reduced. The flow of products through the factory flow is

    in a single line and is therefore ideal. Assembly 1 has been placed at one end of the factory

    floor which enables it to be efficiently connected to another part where the BZ 111 units will be

    produced.

    Press Shop Machining Cell Automatic Paint

    Assembly 1 Assembly Cell Dispatch

    NDT X-Ray

    Go

    od

    s

    Go

    od

    s

    Ou

    t

    I

    n

    Inspection

    Figure 5-12: Spaghetti Diagram

  • 6. IMPLEMENTATION PLAN

    VSM Loop Objectives Measures and targets Person Implementation Schedule () Completed

    On 1 2 3 4 5 6 7 8 9 10 11 12

    Pacemaker loop Minimize inventory at dispatch Use Supermarket before dispatch

    Supplier loop Minimize inventory at raw materials store

    Establish milk runs, Use supermakret in place of raw materials store

    Assembly loop Create continuous flow Place Assembly 1 and Assembly 2 in Assembly cell

    Assembly loop Establish pull system Use a supermarket before and after assembly cell

    AZ loop Create continuous flow Establish cellular manufacturing. Place Insert and drill in a cell

    AZ loop Reduce batch size Perform SMED optimizations for press blank and press form

    AZ loop Establish pull system Connect Press blank, form, machining cell and automatic paint through FIFO.

    BZ loop Create continuous flow Place CNC and Grind in BZ Cell

    BZ loop Establish pull system Uses supermarkets to connect saw and BZ sell. Use FIFO to connect to subcontrated heat treatment

    Process loop Manage parallel flow Establish supermarkets between AZ loop, BZ loop and Assembly loop

    Pacemaker loop Production levelling Introduce Heijunka box with a pitch of 37.5 minutes.

    Implementation Plan Review Scheduled Date Person in Charge

  • 7. BENEFITS

    The Future state map shows several benefits as compared to the current process. These

    benefits are described below:

    Lead Time Reduction Initially the total lead time of the process was 64.2 days. This was

    extremely high and was the cause for the need of large inventories. However, the lead time in

    the future state map is only 6.6 days which shows that the lead time has been greatly reduced.

    Low inventory The future state map has eliminated the need for separate areas for inventory.

    This therefore greatly reduces the costs, as a dedicated area for inventory is not required.

    Change over Times The changeover times for 3 equipment have also been greatly reduced by

    using 5S and SMED principles. This therefore has enabled the production rate of every product

    every shift and has greatly reduced the time to meet customer demand.

    Bottlenecks By making sure that every product is produced to takt time, the bottlenecks in

    the process have been eliminated and hence has this has reduced the stress on workers as well

    as waiting times. This can result in better quality of the products and lesser reworks as the

    operator is not too stressed.

  • 8. REFERENCES

    Fryman, M. A., 2002. Quality and Process Improvement. 1 ed. s.l.:Cengage Learning.

    Graves, R., Konopka, J. M. & Milne, R. J., 1995. Literature review of material flow control

    mechanisms. Production planning and control, 6(5), pp. 395-403.

    Junior, M. L. & Filho, M. G., 2010. Variations of the kanban system: Literature review and

    classification. International Journal of Production Economics, 125(1), pp. 13-21.

    Kaplan, G. S., 2008. Advanced Lean Thinking: Proven Methods to Reduce Waste and Improve

    Quality in Health Care. 1 ed. s.l.:Joint Commission Resources.

    Ludvig, A., 2011. Challenges of implementing lean principles in product development - the case

    of Visual planning. Cambridge, 18th EurOMA Conference.

    Luyster, T. & Tapping, D., 2006. Creating You Lean Future State: How to move from Seeing to

    Doing. 1 ed. s.l.:Productivity Press.

    Nash, M. A. & Poling, S. R., 2011. Mapping the Total Value Stream. s.l.:CRC Press.

    OICA, 2012. World motor vehicle production: OICA correspondents survey, World Ranking of

    Manufacturers. [Online]

    Available at: http://www.oica.net/wp-content/uploads/2013/03/ranking-2012.pdf

    [Accessed 22 Dec 2014].

    Rother, M. & Shook, J., 1999. Learning to See. 1.2 ed. Massachusetts: Lean Enterprise Insitute.

    Womack, J. P. & Jones, D. T., 1996. Lean Thinking. Michigan: Simon & Schuster.