8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 1 of 28
MAHARASHTRA POLLUTION CONTROL BOARD
Minutes of 8th Consent Appraisal Committee Meeting of 2017-2018 held on 09.02.2018 at 3.00 p.m. at MHADA Office, Grihanirman Bhavan,
Kalanagar, Bandra (East), Mumbai, Maharashtra 400051.
……….
The Consent Appraisal Committee meeting of the Board was held on 09.02.2018. Following members of the Consent Appraisal Committee were
present:
1. Shri Milind Mhaiskar, Chairman
Vice President & CEO, MHADA and
Chairperson, MPCB, Mumbai.
2. Shri. P. Anbalagan Member
Member Secretary, MPC Board, Mumbai
3. Shri. Padmakar Nandusekar Member
Technical Advisor (Environment), MIDC, Mumbai
4. Shri. P. K. Mirashe Member Convener
Assistant Secretary (Technical), MPC Board, Mumbai
Additional Chief Secretary, Home (Transport) Dept., Mumbai could not attend the meeting. Leave of absence was granted to them.
Following Officer of MPCB were present for the meeting:
Following Officer of MPCB were present for the meeting:
1. Shri. V. M. Motghare, JD(APC), MPCB, Special Invitee
2. Shri. Y. B. Sontakke, JD(WPC), MPCB, Special Invitee
3. Shri A. R. Supate, PSO, Mumbai, Special Invitee
4. Shri. N. N. Gurav, Regional Officer (HQ), Mumbai, Special Invitee
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 2 of 28
The meeting thereafter deliberated on the fresh agenda of Consent to Establish [Book-let no. 14] is placed before the committee and following
decisions were taken.
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
Booklet No 14 Consent to Establish
1 MPCB-
CONSENT-
0000016949
Mumbai International
Airport Pvt. Ltd,1st floor,
Terminal 1B, Santacruz
East Chhatrapati Shivaji
Intenational Airport,
Andheri
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that as per the EIA notification, there is
separate entity for Airports which falls under 7 (A)
whereas building construction project falls under 8(a) &
(b).
In view of above, it was decided to grant consent to
establish for expansion for up-gradation of Air Port on
total plot area 12,44,355 Sq. Mtrs and total BUA-
10,00,000 Sq. Mtrs. And by imposing Environmental
Clearance and standard condition.
1. PP shall not take any effective steps without obtaining
prior Environmental Clearance and submit BG of Rs
10 lakh towards compliance of the same
2 MPCB-
CONSENT-
0000019288
Indospace Industrial Park
Pune Pvt. Ltd. Plot No. D-
223/1, D-223/2, D-223/3 ,
D-223/4, Village-
Bhamboli, Chakan MIDC
Industrial Area, Phase-II
Khed
APPROVED
Consent to
Establish
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that PP has applied for proposed logistic
park on Total Plot Area 1,44,065.50 sq. mtrs and
Construction BUA 1,05,000 sq. Mtrs. Also noted that
there will not be generation of industrial effluent however,
STP based on MBBR Technology is proposed for the
treatment of sewage including OWC for wet garbage.
In view of above, it was decided to grant consent to
establish for proposed logistic park on Total Plot Area
1,44,065.50 sq. mtrs and Construction BUA 1,05,000 sq.
Mtrs. by imposing following conditions:
1. PP shall not take any effective steps without obtaining
prior Environmental Clearance and submit BG of Rs 10
lakh towards compliance of the same.
2. Logistics park shall mainly avail logistics facilitates to
Light & Heavy Engineering industries, Automobile and
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 3 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
automobile ancillary manufacturing industries,
Electronics and Consumable durables, IT Hardware,
Fibre Glass manufacturing industries.
3. Industrial Storage, Industrial logistics industrial
assembling etc. Individual industry in the logistic park
will be responsible for obtaining their Consent to
Establish and Operate separately from MPCB.
4. Applicant shall provide and operate common pollution
control infrastructure facility such as STP, Bio-gas
plant/OWC and ensure that the individual
industries/units shall enter into MOU with Industrial
park to ensure operation and maintenance of the
common facility and other assets.
5. PP shall not allot the plot to the trade effluent
generating industry.
6. PP shall achieve the treated domestic effluent standard
for the parameter BOD- 10 mg/lit.
7. The treated domestic effluent shall be 60% recycled for
secondary purposes such as toilet flushing, air
conditioning, cooling tower make up, firefighting etc.
and remaining shall be used on own land for gardening/
irrigation purpose within premises. In no case, effluent
shall find its way to any water body directly/indirectly
at any time. The firm shall affix the separate meter for
ensurance of 60% recycling of treated sewage and keep
the records of the same.
8. PP shall install online monitoring system for BOD, TSS
and flow at the outlet of STP.
9. PP shall submit BG of Rs. 25 Lakhs towards
compliance of Consent to Establish condition.
Consent shall be granted after receipt of map showing
proposed pollution control system i.e. ETP, STP, MSW
disposal arrangements etc.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 4 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
3 MPCB-
CONSENT-
0000026473
Resort Health and Farm,
930 -934P 935, 936, 940-
959, 961, 972 -977, 1023,
1024, 1032P, 1033, 1034P
village - Shilimb -
chawsar, [ Gut No:Cha
223, 226, 232, 234-236
243], [Sh.905-908, 910,
920, 921-928 ] Maval,
Dist. Pune
APPROVED
Consent to
Establish for
Expansion.
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that Show Cause Notice for refusal of
Consent was issued on 03.01.2018 and also noted the
reply submitted by PP on 05.01.2018 wherein, PP has
submitted desired details.
Considering the reply of the PP, it was decided to grant
Consent to Establish for Expansion for Hotel activity for
total plot area- 13,24,930 Sq. mtrs. and Construction BUA
(Expansion) of 7076.21 sq. mtrs out of 35,821.11 Sq. Mtrs
as per EC dated 09.12.2016 by imposing following
conditions;-
1. PP shall submit an affidavit in prescribed format
regarding compliance of conditions of EC and
Consent to Establish condition.
2. PP shall submit an affidavit regarding the area for
which expansion of C to E application is made is
included in Environment Clearance.
3. PP shall achieve the treated domestic effluent standard
for the parameter BOD- 10 mg/lit.
4. The treated effluent shall be 60% recycled for
secondary purposes such as toilet flushing, air
conditioning, cooling tower make up, firefighting etc.
and remaining shall be utilized on land for gardening.
5. PP shall install online monitoring system for BOD,
TSS and flow at the outlet of STP.
6. PP shall submit BG of Rs. 25 Lakhs towards
compliance of EC and Consent to Establish condition.
7. PP shall re-validate the EC if project is not completed
before the expiry of the same.
8. 1st consent to operate for expansion will be considered
only after submission of NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
Consent shall be issued after receipt of additional fees, if
required.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 5 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
4 MPCB-
CONSENT-
0000013136
Persipina Developers Pvt.
Ltd. Bhokarpada &
Talegaon Panshil, S. No.
65/1A, 65/1B, 66/0, 67/0,
65/2, 74/6, 74/4B, 74/2,
69/0, 68/0, 62/0, 59/0,
57/1, 57/2, 57/3B, Panvel
& Khalapur, Dist. Raigad
APPROVED
Revalidation of
Consent to
Establish
(Part-I)
5 years/ validity
of EC
whichever is
earlier
It was decided to grant revalidation of consent to establish
(Phase-I) for Construction of IT SEZ and Residential
township on Total Plot area of 13,51,193.65 sq.m and
Construction BUA (FSI+Non-FSI) for Phase-I of
8,15,471sq.m. out of Total Construction BUA (FSI+Non-
FSI) of 44,82,711 sq.m. of entire project as per revalidated
EC dated 16.03.2015, by imposing following conditions:
1. PP shall submit BG of Rs. 25 lakh towards
compliance of EC and Consent to Establish condition.
2. PP shall submit an affidavit in prescribed format
regarding compliance of conditions of EC and
Consent to Establish condition.
3. PP shall achieve the treated domestic effluent standard
for the parameter BOD- 10 mg/lit.
4. The treated effluent shall be minimum 60% recycled
for secondary purposes such as toilet flushing, air
conditioning, cooling tower make up, firefighting etc.
and remaining shall be used on land for gardening and
connected to the sewerage system provided by local
body.
5. PP shall submit Board Resolution from company
Board, towards starting of construction work without
obtaining valid consent to establish from the MPC
Board thus violated the provisions of Environmental
Laws and in future, they will not do such violations
and BG of Rs. 2 lakh towards submission of Board
resolution within one month of issue of consent.
6. PP shall amend the EC dated 16.03.2015 for name
change from M/s. Sunnyvista Realtors Pvt. Ltd to M/s.
Persipina Developers Pvt. Ltd
7. 1st consent to operate for expansion will be considered
only after submission of NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 6 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
5 MPCB-
CONSENT-
0000026450
JBM MA Automotive
Private Limited, Chakan
Talegaon Road C-1/2,
MIDC Chakan, Khed,
Dist. Pune.
APPROVED
1st Consent to
Operate for
expansion and
amalgamation
with existing
consent
30.04.2018 Committee noted the reply submitted by the industry
dated 23.10.2017 in respect of SCN issued by the Board
that the industry has wrongly selected option of consent to
establish instead of 1st consent to operate.
Considering the reply of the industry, it was decided to
grant 1st consent to operate for expansion to manufacture
Sheet Metal component- 1000 MT/M (without
electroplating, pickling and painting activity) with die
washing activity and amalgamation with existing consent.
Consent shall be issued after receipt of verification report
regarding submission of Board resolution and BG as per
consent condition.
6 MPCB-
CONSENT-
0000027366
Ichalkaranji Powerloom
Mega Cluster Ltd. (Signal
Stake Holder Company -
Kallappanna Awade Co -
op. Phase II, Sector B,
Plot No. 1 to 7 Shri
Laxmi Co - oprative
Industrial Estate Ltd,
Hatkanangle, Dist.
Kolhapur
APPROVED
Consent to
Establish
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that industry has obtained consent to
establish to manufacture Sized & Warped Yarn- 23
MT/Day, Dyed Yarn-2 MT/Day and Processed Fabric-
1,00,000 Mtrs/Day vide consent dated 10.02.2017.
Now industry has applied for consent to establish for
expansion to manufacture Sized & Warped Yarn- 2
MT/Day, Dyed Yarn-2 MT/Day and Processed Fabric-
25,000 Mtrs/Day.
In view of above, it was decided to grant consent to
establish by overriding with earlier consent to establish
granted by the Board by imposing following conditions
1. Industry shall submit the BG of Rs. 10 lakh towards
compliance of consent to establish conditions.
2. Industry shall provide full-flagged ETP followed by
RO & MEE to reuse/recycle 100% treated trade
effluent in process so as to achieve zero liquid
discharge.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 7 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
7 MPCB-
CONSENT-
0000012122
Tata Housing
Development Company
Ltd, S.NO.-32(pt), 34(pt),
35(pt), 36/A(pt), 36/B,
36/1, 36/2, 37/1(pt), 37/B,
37/C(pt), 37/ Amantra
Project, Ecocity, Ranjoli ,
Tal- Bhivandi, Dist-
Thane
APPROVED
Re-validation
of consent to
establish
project with
expansion in
construction
BUA.
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that PP has obtained Environmental
Clearance vide letter dated 06.11.2017 for total BUA
5,35,592.40 Sq. Mtrs and consent to establish vide letter
dated 19.10.2011 for total BUA 3,64,751.24 Sq. Mtrs
which was expired on 18.10.2016.
Now, PP has applied for re-validation of consent to
establish granted by the Board dated 19.10.2011 with
increase in BUA for the total BUA- 5,35,592 Sq. Mtrs.
In view of above, it was decided to grant re-validation of
Consent to Establish with increase in BUA for
construction of Proposed Residential project on Total Plot
area of 82,263.36 sq. Mtr. and Construction BUA of
5,35,592.40 Sq Mtr. as per EC by imposing following
conditions:
1. PP shall submit BG of Rs. 25 lakh towards
compliance of EC and Consent to Establish
conditions.
2. PP shall submit an affidavit in prescribed format
regarding compliance of conditions of EC and
Consent to Establish condition.
3. PP shall achieve the treated domestic effluent standard
for the parameter BOD - 10 mg/lit.
4. The treated effluent shall be 60 % recycled for
secondary purposes such as toilet flushing, air
conditioning, cooling tower make up, firefighting etc.
and remaining shall be used on land for gardening and
connected to the sewerage system provided by local
body.
5. PP shall install online monitoring system for
parameters BOD, TSS and flow at outlet of STP.
Consent shall be issued after obtaining –
i. Revised information regarding water consumption,
domestic effluent generation treatment provided and
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 8 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
verification of the same from SRO, Bhivandi.
ii. After verification of CRZ Clearance from competent
authority as the total BUA is increased.
iii. After receipt of year-wise C.A. Certificate /
Undertaking regarding investment done after receipt
of consent to establish dated 19.10.2011.
8 MPCB-
CONSENT-
0000030452
Sahakar Maharshi
Shivajirao Narayanrao
Nagawade SSK Ltd 51/1
Shrigonda Factory
Shrigonda, Dist.
Ahmednagar
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant consent to establish for expansion
of Sugar unit for 1300 TCD (from 4800 TCD to 6100
TCD) by imposing Environmental Clearance and
following conditions:
1. Industry shall not take any effective steps prior
obtaining EC and submit Bank Guarantee of Rs. 5
lakh towards compliance of consent conditions.
2. Industry shall install CPU and submit Bank Guarantee
of Rs. 3 lakh towards compliance of same.
3. 1st consent to operate for expansion will be considered
only after submission of NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
9 MPCB-
CONSENT-
0000030896
Gangamai Industries &
Constructions Ltd.,
6,222/3,223,224,225/1,22
5/2,225/3,232,233 At-
Najik Babulgaon
Shevgaon, Ahmednagar
APPROVED
Consent to
Establish
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant consent to establish for expansion
for Sugar unit- 2000 TCD (from 5500 TCD to 7500 TCD)
& Co-Gen plant 5 MW (from 32 MW to 37 MW) by
imposing Environmental Clearance and following
conditions:
1. Industry shall not take any effective steps prior to
obtaining Environment Clearance and submit Bank
Guarantee of Rs. 5 lakh towards compliance of same
and consent conditions.
2. 1st consent to operate for expansion will be considered
only after submission of NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 9 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
10 MPCB-
CONSENT-
0000033035
Indiabulls Infraestate Ltd,
C.S. No. 131, 132 & 1/132
Lower Parel, Near Worli
Naka. Mumbai
APPROVED
Revalidation
of Consent to
Establish
Commissioning
of the unit or
upto
05.09.2022
whichever is
earlier
Committee noted that PP has amended the EC vide letter
dated 09.08.2017 total plot area 43,603.27 Sq. Mtrs and
total BUA 2,02,712 Sq. Mtrs. PP has obtained consent to
establish vide consent dated 06.09.2012 for total plot area
43,603.27 Sq. Mtrs and total BUA 2,14,419 Sq. Mtrs
In view of above, it was decided to grant revalidation of
Consent to Establish for construction of residential
development project for Total Plot Area of 43,603 sq.
mtrs. and total Construction BUA 2,02,712 sq. mtrs (as
per EC dated 09.08.2017) by imposing following
conditions:
1. 1.PP shall comply conditions stipulated in EC dated
09.08.2017
2. PP shall submit an affidavit in prescribed format
regarding compliance of conditions of Environment
Clearance and Consent to Establish conditions.
3. PP shall achieve the treated domestic effluent standard
for the parameter BOD - 10 mg/lit.
4. The treated effluent shall be 60% recycled for
secondary purposes such as toilet flushing, air
conditioning, cooling tower, make up, firefighting etc.
and remaining shall be utilized on land for gardening.
5. PP shall install online monitoring system for BOD,
TSS and flow at the outlet of Sewage Treatment Plant
(STP).
6. PP shall extend/Top up Bank Guarantee of Rs.25 Lakh
towards compliance of Environment Clearance and
Consent to Establish condition.
11 MPCB-
CONSENT-
0000033121
Transworld Furtichem
Pvt. Ltd. Plot No. 39/1 &
39/2 Dhatav, Tal. Roha,
Dist. Raigad
NOT
APPROVED
Consent to
Establish for
expansion
---- It was decided to issue Show Cause Notice for refusal of
Consent to Establish as unit is located in MIDC Dhatav
which falls under Eco Sensitive Area, Draft Notification
of Western Ghat and also CETP is not meeting outlet
norms.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 10 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
12 MPCB-
CONSENT-
0000031699
Pioneer Distilleries
Limited, 286/1, 2,
285/1/A, B, 285/2 286/1,
2, 285/1/A, B, 285/2, Vill.
Balapur, Tq. Dharmabad,
Dist. Nanded
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
In view of above, it was decided to grant consent to
establish for expansion of Ethanol plant- 70 KLPD and
Malt Spirit - 12 KLPD, by imposing Environment
Clearance and following conditions:
1. Industry shall not take any effective steps prior to
obtaining Environment Clearance for expansion
activity and submit Bank Guarantee of Rs. 5 lakh
towards compliance of the same.
2. Industry shall provide adequate facility so as to
achieve Zero Liquid Discharge of spent wash.
3. 1st consent to operate for expansion will be considered
only after submission of NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
13 MPCB-
CONSENT-
0000031945
Eurotas Infrastucture
Limited, (Cement
Grinding Unit)
Plot No. DTA 1B
Additional Sinnar
Industrial area, Village
Musalgaon, Tal. Sinnar,
Dist. Nashik
APPROVED
Re-validation
of Consent to
Establish
5 years/ upto
30.06.2019 as
per EC validity
whichever is
earlier
Committee noted that industry has obtained
Environmental Clearance vide letter dated 30.06.2012
which is valid upto 30.06.2019 (i.e. 7 years). Industry has
also obtained consent to establish to manufacture
Pozzolana Portland Cement- 4,12,500 T/M vide consent
dated 18.07.2012 which was valid upto 17.07.2017.
Now industry has applied for revalidation of consent to
establish to manufacture Pozzolana Portland Cement-
4,12,500 T/M by imposing following condition;
1. Industry shall submit Bank Guarantee of Rs. 10 Lakhs
for compliance of Consent to Establish &
Environment Clearance conditions.
2. Industry shall comply the revised standards as per new
Notification for Cement Manufacturing sector.
3. PP shall make provision of 3 CAAQMS at location as
per condition stipulated in Consent to Establish.
4. PP shall implement mechanical close type
transportation system for coal / Metal Mineral
transporting trucks.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 11 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
14 MPCB-
CONSENT-
0000012108
Noble Hospital,
153/A/1,2,4/1 Magarpatta
City Haveli, Dist. Pune
APPROVED
Combined
Consent &
BMW
Authorization ,
Consent to
Establish
30.06.2019 Committee noted that PP has submitted the requisite
consent fee, Bombay Nursing Home registration
certificate for 250 beds which is valid up to 31.03.2018.
In view of above, it was decided to grant combined
consent and biomedical waste authorization for 250
Bedded Hospital by imposing HCE BG regime and
standard conditions.
Consent shall be issued only after obtaining requisite bank
Guarantee Rs. 3 Lakhs.
15 MPCB-
CONSENT-
0000034084
Jindal PolyFilms Limited,
339,381, 28 Km Stone,
NH-3, Nashik Igatpuri
High Road,Village
Mundhegaon, Igatpuri,
Dist. Nasik
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that industry has consent to operate
which is valid upto 30.09.2020 to manufacture Polyester
Films/Polypropylene/PVDC film, Polyester Chips and
Coated films.
In view of above, it was decided to grant consent to
establish for expansion for manufacture of Pet Chips =
12,000 MT/M by imposing following conditions.
1. Industry shall provide adequate treatment facility for the
effluent generated from proposed expansion project so
as to achieve zero liquid discharge.
2. 1st consent to operate for expansion will be considered
only after submission of NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
16 MPCB-
CONSENT-
0000034171
Parag Milk Foods Ltd.,
43/1A/1 & 43/1A/2 At
Awasari Phata, Post.
Manchar. Tal. Ambegaon,
Dist. Pune
NOT
APPROVED
Consent to
Establish for
expansion
--- Committee noted that industry has consent to operate
which is valid upto 30.04.2020 to manufacture Milk
products. However, industry has not submitted any
documentary proof viz, NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 12 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
In view of above, it was decided to issue SCN for consent
to establish for expansion to manufacture Milk products
due to above non-compliance.
17 MPCB-
CONSENT-
0000034517
Innovassynth
Technologies (India)
Limited, Revene survey
no -9-24 Wasarang -34-36
Chinchwali Khopoli
Khalapur, Dist. Raigad
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant consent to establish for expansion
with deletion of 25 existing products, reduction in
production quantity of 21 existing products and increase
in production quantity of 21 existing products and
addition of 45 new products by imposing following
conditions.
1. Industry shall not take any effective steps without
obtaining environmental clearance and shall submit
the BG of Rs. 10 lakh towards compliance of the
same.
2. Industry shall 100% reuse/recycle the treated effluent
by providing RO & MEE so as to achieve zero liquid
discharge.
18 MPCB-
CONSENT-
0000032976
Shivneri Sugars Ltd, A/p-
Ganeshtekadi, Nhavi (Bk),
Tal- Koregaon , Dist-
Satara.
APPROVED
Consent to
Establish
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that industry has purchased the existing
Sugar unit from M/s. Jijamata Sugar and Power Industries
Limited of capacity - 800 TCD, however, the said unit is
not in operation since long time.
In view of above, it was decided to grant consent to
establish for Sugar unit-4200 TCD & Co-Generation
plant- 8 MW by imposing following conditions;
1. Industry shall provide adequate capacity of effluent
treatment plant so as to achieve consented standards
along with scientific disposal arrangements for the
treated effluent.
2. Industry shall provide ESP/Bag Filters/Scrubbers to
coal/bagasse fired boiler so as to achieve the emission
standards.
3. Industry shall install CPU and submit Bank Guarantee
of Rs. 3 lakh towards compliance of same.
4. 1st consent to operate for expansion will be considered
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 13 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
only after submission of NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
5. Industry shall submit Bank Guarantee of Rs. 5 lakh
towards compliance of consent to establish conditions.
19 MPCB-
CONSENT-
0000034871
Shri Bhogawati Sahakari
Sakhar Karkhana Ltd.
1195 to 1221 Shahunagar ,
Parite Karveer, Dist.
Kolhapur
NOT
APPROVED
Consent to
Establish for
expansion
--- Committee noted that existing Sugar unit is having
capacity- 3500 TCD and now industry applied for
expansion of Sugar unit from 3500 TCD to 4900 TCD i.e.
1400 TCD.
Committee also noted that industry has carried out excess
crushing more than consented quantity and all the JVS
results are exceeding the consented standards. Industry
has also discharged substandard effluent into the river due
to which fish kill incidence took place on 19.11.2017.
In view of above, it was decided to issue SCN for refusal
of consent to establish for expansion due to above non-
compliances by forfeiting the BG of Rs. 10 lakh as JVS
results are exceeding the consented standards.
20 MPCB-
CONSENT-
0000034578
Everest Industries
Limited, 152 & 153
Village -Lakhamapur
Dindori, Dist. Nasik
NOT
APPROVED
Consent to
Establish for
expansion
--- Committee noted that industry has consent to operate
which is valid upto 31.03.2021 to manufacture Asbestos
Cement Corrugated Sheets. However, industry has not
submitted any documentary proof viz, NOC from
CGWB/Irrigation department for consumption of ground
water/Surface water.
In view of above, it was decided to issue SCN for consent
to establish for expansion due to above non-compliance.
21 MPCB-
CONSENT-
0000035038
Finolex Industries
Limited157, 193, 95, 202,
203, 195, 196 Ranpar-
Golap, Pawas Road Dist.
Ratnagiri
NOT
APPROVED
Consent to
Establish for
--- Committee noted that industry has not submitted any
documentary proof viz, NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 14 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
expansion In view of above, it was decided to issue SCN for consent
to establish for expansion due to above non-compliance.
22 MPCB-
CONSENT-
0000035299
Deepak Novochem
Technologies Ltd, Plot
No. D-27/3/1 & D-27/2,
Lote- Parshuram MIDC
Khed
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that industry has existing consent to
operate which is valid upto 30.10.2019 on plot no D-
27/3/1. Consent to Establish obtained for Plot No- D-27/2
dtd. 15 May 2015 for storage of Bio mass briquette.
Now, Industry has applied for consent to establish for
expansion for plot no D-27/3/1 and D-27/3/1. They have
applied for EC. Industry has proposed to provide ETP of
200 CMD and STP of 25 CMD. Industry is in MIDC Lote
and Lote CETP is non-complying. However industry has
proposed to achieve zero liquid discharge by installing RO
& MEE. They have proposed to recycle the treated
effluent in cooling towers and for gardening. However, in
zero liquid discharge, on land for gardening is not
allowed.
In the view of above, it was decided to grant consent to
establish for expansion by imposing following conditions
1. Industry shall not take any effective steps prior to
obtaining Environment Clarence from the competent
authority and submit Bank Guarantee of Rs. 5 lakh
towards compliance of same.
2. Industry shall provide adequate treatment system
followed RO & MEE so as to achieve Zero Liquid
Discharge. Industry shall not discharge treated and
untreated effluent on land for gardening
23 MPCB-
CONSENT-
0000032083
Tata Consultancy Services
Ltd, Plot C, Patlipada
Village Thane
NOT
APPROVED
Consent to
Establish and
Operate
---- Committee noted the following non-compliances viz.
1. The area mentioned in Environment Clearance,
Consent to Establish and application of Consent to
Operate do not match.
2. PP failed to re-validate Consent to Establish and
Environment Clearance.
3. The area in Occupation Certificate is different as
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 15 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
compared with Consent to Establish and Environment
Clearance.
4. PP failed to submit the documentary proof regarding
change in name.
In view of above, it was decided to issue Show Cause
Notice for consent to establish and operate due to above
non compliances with stop work direction.
24 MPCB-
CONSENT-
0000035483
Hotel and Beach Resort
Project, Sagartirth: 2,
HISSA no. 3 B 4, HISSA
no. 1 & 3 , Tank: 16,
HISSA no. 1/1 & 1/4 27-
1/2, Temb 15 Village
Sagartirth, Tank and
Temb, Taluka Vengurla,
Dist. Sindhudrugh,
APPROVED
Revalidation of
Consent to
Establish
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that PP has obtained Environmental
Clearance vide letter dated 05.04.2017 for total plot area
2,19,084 Sq. mtrs and total BUA 61,926.22 Sq. mtrs in the
name of Hotel and Beach Resort Project. Whereas, PP has
also obtained consent to establish vide consent dated
13.02.2013 for total plot area 2,19,084 Sq. mtrs and total
BUA 61,926.22 Sq. mtrs on the name of Elite Township
Pvt. Ltd. (Beach Resort)
Now PP has applied for re-validation of consent to
establish for construction of hotel on the name of named
Hotel and Beach Resort Project on Total Plot area of
2,19,084 sq.m. and total Construction BUA of 61,926.22
sq.m. by imposing following conditions;
1. PP shall submit an affidavit in prescribed format
regarding compliance of conditions of EC and
Consent to Establish condition.
2. PP shall achieve the treated domestic effluent standard
for the parameter BOD- 10 mg/lit.
3. The treated effluent shall be 60% recycled for
secondary purposes such as toilet flushing, air
conditioning, cooling tower make up, firefighting etc.
and remaining shall be utilized on land for gardening.
4. PP shall install online monitoring system for BOD,
TSS and flow at the outlet of STP.
5. PP shall submit BG of Rs. 25 lakh towards
compliance of EC and Consent to Establish condition.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 16 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
6. PP shall re-validate the EC if project is not completed
before the expiry of the same.
7. 1st consent to operate for expansion will be considered
only after submission of NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
Consent shall be issued after submission of documentary
proof regarding name change from M/s. Elite Township
Pvt. Ltd. (Beach Resort) to M/s. Hotel and Beach Resort
Project and after receipt of additional fees, if required.
25 MPCB-
CONSENT-
0000031725
Indoco Remedies Ltd. A-
26, A-27, A-28/1, A-28/2
Patalganaga MIDC,
Khalapur, Dist Raigad
APPROVED
Consent to
Establish for
Expansion
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that industry has existing consent to
operate which is valid upto 31.01.2021. Industry has also
obtained Environmental Clearance for expansion activity
vide letter dated 18.07.2016.
In view of above, it is decided to grant consent to establish
for expansion to manufacture 7 new products viz.
Dorzolamide Hydrochloride (0.274 Tones/M), Allopurinol
(34.17 Tones/M), Quetiapine Furmate (9.83 Tones/M),
Pregabalin (9.27 Tones/M), Febuxostat (5.083 Tones/M),
Lacosamide (0.666 Tones/M), Merabegron (1.5
Tones/M), Dapagliflozin (0.666 Tones/M), Cangliflozin
(5.0 Tones/M), Apixaban (0.583 Tones/M), Aloglitin
Benzoate (4.0 Tones/M) & Rufinamide (0.258 Tones/M),
by imposing following conditions;
1. Industry shall submit Bank Guarantee of Rs. 5 lakh
towards compliance of consent to establish and
conditions stipulated in Environment Clearance.
2. Industry shall install RO, MEE, ATFD and recycle
100 % treated effluent so as to achieve ZLD. There
shall not be any discharge on land for gardening.
3. Industry shall submit Board Resolution in prescribed
format within one month as industry took effective
steps prior to obtaining C to E and submit the BG of
Rs. 2 lakh towards compliance of the same.
4. Industry shall not to violate the conditions stipulated
in EC and consent in future and submit the BG of Rs.
25 lakh towards compliance of the same.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 17 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
26 MPCB-
CONSENT-
0000035827
ADM Agro Industries
Latur and Vizag Pvt. Ltd.
G 75-86 Latur, Dist. Latur
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that industry has existing consent in Red
category for the manufacturing of Edible Oil which is
valid upto 30.04.2018. Now, industry has applied for
consent to establish for Dal Mill & Flour Mill.
In view of above, it was decided to grant consent to
establish for Dal Mill & Flour Mill in Red category by
imposing following conditions;
1. Industry shall submit Bank Guarantee of Rs. 5 lakh
towards compliance of consent conditions.
27 MPCB-
CONSENT-
0000035293
Umicore Autocat India
Pvt Ltd, Plot 03, survey
No, 1295, 1296,
1122B,1129B,1140
Shirwal, Tal. Khandala,
Dist. Satara
APPROVED
Consent to
Establish for
installation of
additional
machinery
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant consent to establish for addition of
one no of Electric Heating Furnace by imposing following
conditions;
1. There shall be any increase in existing production
quantity as well as existing pollution load due to
addition of one no of Electric Heating Furnace.
28 MPCB-
CONSENT-
0000035904
Tata Autocomp GY
Batteries Pvt Ltd Plot No.
C-2, MIDC Ranjangaon,
Tal - Shirur, Dist - Pune
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant consent to establish for expansion
to manufacture Two Wheeler Lead Acid VRLA Battery-
7,50,000 No/M by imposing following conditions;
1. Industry shall upgrade the existing STP with adequate
capacity before obtaining the 1st consent to operate.
2. Industry shall 100% recycle/reuse the metal bearing
effluent into the process and non metal bearing
effluent shall be sent to CETP for further treatment
and disposal and shall not use for gardening. Industry
shall install online flow meter to ETP outlet and
recycle system to monitor the total quantity of effluent
recycled and sent to CETP within 02 months and
submit the BG of Rs. 2 lakh towards compliance of
the same.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 18 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
29 MPCB-
CONSENT-
0000034208
Nxtra Data Ltd. Plot No -
13/10A, 28 Hinjewadi
Mulshi, Dist. Pune
APPROVED
Consent to
establish
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant Consent to Establish for
construction of commercial project for Data Center
activity for Total Plot area 18,981 Sq. M. & Construction
BUA of 29,722.97 Sq. Mtrs. by imposing following
conditions;
1. Industry shall not take effective steps before obtaining
EC from Competent authority.
2. PP shall achieve the treated domestic effluent standard
for the parameter BOD- 10 mg/lit.
3. The treated effluent shall be 60% recycled for
secondary purposes such as toilet flushing, air
conditioning, cooling tower make up, firefighting etc.
and remaining shall be used on land for gardening and
connected to the sewerage system provided by local
body.
4. PP shall install online monitoring system for parameters
BOD, TSS and flow at outlet of STP.
30 MPCB-
CONSENT-
0000034450
AAK Kamani Pvt. Ltd.,
Sr. No. 21,21,23,24,24,25
& 26, Village Honad, Post
: Sajgaon Village Honad,
Takai Adoshi Road
Khalapur, Dist. Raigad
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that industry has provided RO & MEE
to the existing unit.
In view of above, it was decided to grant consent to
establish for expansion to manufacture Refined Oil and
Vanaspati Oil
31 MPCB-
CONSENT-
0000036524
Indiabulls Real Estate
Company Pvt Ltd C.S No
613 & 612 Lower parel
Division, Elphinstone Mill
Mumbai
APPROVED
Revalidation of
Consent to
Establish
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that PP has obtained amended
Environmental Clearance vide letter dated 03.07.2017 for
Total Plot Area 34,383 Sq. Mtrs and Total Construction
BUA of 3,60,099 Sq. Mtrs. PP has also obtained consent
to establish vide consent dated 23.10.2012 for Total Plot
Area 34,384.93 Sq. Mtrs. and Total Construction BUA of
3,74,700 Sq. Mtrs
Now industry has applied for Re-validation of Consent to
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 19 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
Establish with amendment for Total Plot Area 34,383
Sq.Mtrs mtrs. and Total Construction BUA of 3,60,099
Sq.Mtrs (ie for Office(wing A,B,C)-1,68,909 Sq.Mtrs,
Wing D-99,995 Sq.Mtrs, MCGM car parking-91,195
Sq.Mtrs.) as per amended EC dated 03.7.2017 by
imposing following conditions:
1. PP shall comply conditions stipulated in amended EC
granted by Board dated 3.7.2017.
2. PP shall submit an affidavit in prescribed format
regarding compliance of conditions of Environment
Clearance and Consent to Establish condition.
3. PP shall achieve the treated domestic effluent standard
for the parameter BOD - 10 mg/lit.
4. The treated effluent shall be 60% recycled for
secondary purposes such as toilet flushing, air
conditioning, cooling tower, make up, firefighting etc.
and remaining shall be utilized on land for gardening.
5. PP shall install online monitoring system for BOD,
TSS and flow at the outlet of STP.
6. PP shall extend/ top up the BG to form total sum of
Rs. 25 lakh towards O&M of pollution control system.
32 MPCB-
CONSENT-
0000036764
Gangamai Industries and
Constructions
Ltd.(GIACL) 224
Harinagar, Najik
Babhulgaon Post-Rakshi
Shevgaon, Dist.
Ahmednagar
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant consent to establish for expansion
for Ethanol production- 100 KLPD by imposing EC
conditions and following conditions;
1. Industry shall not take any effective steps prior to
obtaining Environment Clarence from the competent
authority and submit Bank Guarantee of Rs. 5 lakh
towards compliance of same.
2. Industry shall submit Bank Guarantee of Rs. 5 lakh
towards compliance of consent to establish conditions.
3. 1st consent to operate for expansion will be considered
only after submission of NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 20 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
33 MPCB-
CONSENT-
0000037044
Datwyler Pharma
Packaging India Pvt Ltd
Plot No-3,4 & 5 Khandala
SEZ(Phase-I) Khandala,
Dist. Satara
APPROVED
Consent to
Establish for
Expansion
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that industry has consent to operate to
manufacture Rubber Clousers- 9000 MT/A which is valid
upto 30.09.2021.
In view of above, it was decided to grant consent to
establish for expansion to manufacture Rubber Clousers-
9000 MT/A and Omniflex Coated Rubber Clousers in
Orange category by imposing following conditions
1. Industry shall provide adequate treatment system so as
to achieve Zero Liquid Discharge (ZLD).
2. 1st consent to operate for expansion will be considered
only after submission of NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
34 MPCB-
CONSENT-
0000035310
Nagpur Metro Rail
Corporation Limited, 4/2
& other MIHAN, Dist.
Nagpur
APPROVED
Consent to
Establish
Commissioning
of the unit or 5
years
whichever is
earlier
It is observed that PP has applied for Metro Rail Depot at
MIHAN which include washing line, O&M line,
Workshop & Offices activities for Metro Rrail. for
domestic effluent propose to provide STP and for trade
effluent propose to provide ETP. Also, Built Up Area is
less than 20,000 sq. mtrs.
In view of above, it was decided to grant consent to
establish by imposing following condition –
1. PP shall submit bank guarantee of Rs. 10 Lakhs for
compliance of Consent to establish condition.
2. PP shall install online monitoring system for the
parameters BOD, TSS and flow at outlet of ETP.
3. PP shall obtain permission from Central Ground
Water Authority in case source of water is
groundwater.
4. Industry shall provide adequate treatment system
followed by RO & MEE so as to achieve Zero Liquid
Discharge.
5. 1st consent to operate will be considered only after
amendment in EC obtained by MIHAN.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 21 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
35 MPCB-
CONSENT-
0000037170
Elpro International
Limited C.T.S. No. - 4270
Chinchwadgaon, Haveli,
Dist. Pune
APPROVED
Revalidation of
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that PP has obtained Environmental
Clearance vide letter dated 04.09.2017 for Total Plot area
1,72,560 Sq. M. & Total Construction BUA of
1,39,482.94 Sq. M. PP has also obtained consent to
establish vide consent dated 13.11.2009 for Total Plot area
1,68,100 Sq. Mtrs. & Total Construction BUA of 231350
Sq. Mtrs.
In view of above, it was decided to grant re-validation of
Consent to Establish for construction of commercial and
residential project for Total Plot area 1,72,560 Sq. Mtrs.
and Total Construction BUA of 1,39,482.94 Sq. Mtrs. as
per Environmental Clearance granted vide letter dated
4.9.2017 by imposing following conditions;
1. PP shall submit an affidavit in prescribed format
regarding compliance of conditions of Environment
Clearance and Consent to Establish conditions.
2. PP shall achieve the treated domestic effluent standard
for the parameter BOD - 10 mg/lit.
3. The treated effluent shall be 60% recycled for
secondary purposes such as toilet flushing, air
conditioning, cooling tower, make up, firefighting etc
and remaining shall be utilized on land for gardening.
4. PP shall install online monitoring system for BOD,
TSS and flow at the outlet of Sewage Treatment Plant
(STP).
5. PP shall submit fresh/top up Bank Guarantee of Rs. 25
Lakh towards compliance of Environment Clearance
and Consent to Establish condition.
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 22 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
Consent shall be issued after submission of additional
consent fee.
36 MPCB-
CONSENT-
0000036993
Endurance Technologies
Limited K-226/1, K-227
MIDC Industrial Area,
Waluj, Dist. Aurangabad
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant Consent to establish for expansion
to manufacture Clutch Assembly- 2,50,000 Nos./M,
Friction Plate- 10,00,000 Nos./M, CVT- 15,000 Nos./M
and Aluminum Pressure Die Casting- 700 Ton/M by
imposing following conditions;
1. Industry shall upgrade the existing ETP to the
adequate capacity prior to obtain 1st consent to
operate from the Board.
37 MPCB-
CONSENT-
0000037502
LEMON TREE
PREMIER HOTEL at
Sahar Road, CSI Airport,
Andheri Mumbai Plot No.
NS C-04, GVK Sky City,
CTS No. 145A,Village
Sahar, Sahar Road, CSI
Airport, Mumbai, SAHAR
ROAD Kurla
NOT
APPROVED
Consent to
Establish
--- Committee noted that PP has applied for consent to
establish on 12.12.2017 which is after Hon’ble High Court
order dated 26 and 29 February, 2016 in the case of Civil
Application No. 221 Of 2013 in Public Interest Litigation
No. 217 of 2009.
Hence it was decided to issue SCN for refusal of consent
to establish, as the Hon’ble High Court has restricted the
process of granting permissions for construction of new
residential and commercial buildings, including malls,
hotels and restaurants The restrictions had become
applicable from 1st March 2016.
38 MPCB-
CONSENT-
0000037896
Endurance Technologies
Limited K-228/229 MIDC
area Waluj Gangapur,
Dist. Aurangabd
APPROVED
Consent to
Establish for
expansion
Commissioning
of the unit or 5
years
whichever is
earlier
Committee noted that industry has existing consent to
operate to manufacture Aluminum Die Casting- 5000
Ton/A which is valid upto 30.04.2022.
In view of above, it was decided to grant consent to
establish for expansion to manufacture Aluminium Die
Castings- 5000 Ton/A
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 23 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
39 MPCB-
CONSENT-
0000037798
Jubilant Life Sciences Ltd.
Gut No 25, 26, 27, 28, 32,
45 Nira Baramati, Dist.
Pune
APPROVED
Consent to
Establish for
new ETP
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant consent to establish for
construction of new Effluent Treatment Plant (ETP) of
capacity 500 CMD followed by RO system.
40 MPCB-
CONSENT-
0000038722
Harman Finochem
Limited, Plot No. A-100,
A-100/1, A-100/2, A-120
& D-1, Five star MIDC
Shendra, Aurangabad.
APPROVED
Consent to
Establish for
Expansion in
pharmaceutical
formulations
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant consent to establish for expansion
of pharmaceutical formation of Tablets - 130 Crs./Y &
Capsules - 10 Crs./Y by imposing following conditions:
1. Industry shall submit Bank Guarantee of Rs. 5 lakh
towards Compliance of consent to establish
conditions.
2. Industry shall 100% reuse/recycle the treated trade
effluent by providing RO & MEE so as to achieve
zero liquid discharge.
3. Industry shall amend Environment Clearance within
three months.
41 MPCB-
CONSENT-
0000038772
Wadhwa Construction and
Infrastructure Pvt. Ltd.,
S.No. 40 /1 and others
Village Vardoli, Panvel
Taluka Panvel, Dist.
Raigad
APPROVED
Consent to
Establish
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant Consent to Establish for
construction of residential township project for
Total Plot area 8,46,129.3 Sq. Mtrs and Total construction
BUA of 4,25,117.93 Sq. Mtrs by imposing following
conditions;
1. PP shall obtained EC from competent authority and
PP shall not take effective steps before obtaining EC
from Competent authority.
2. PP shall achieve the treated domestic effluent standard
for the parameter BOD- 10 mg/lit.
3. The treated effluent shall be 60% recycled for
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 24 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
secondary purposes such as toilet flushing, air
conditioning, cooling tower make up, firefighting etc.
and remaining shall be used on land for gardening and
connected to the sewerage system provided by local
body.
4. PP shall install online monitoring system for
parameters BOD, TSS and flow at outlet of STP.
5. 1st consent to operate for expansion will be considered
only after submission of NOC from CGWB/Irrigation
department for consumption of ground water/Surface
water.
42 MPCB-
CONSENT-
0000038761
EVERSHINE
DEVELOPERS; New
survey no. 5, 5B, 5F, 5G,
5D New survey no. 5, 5B,
5F, 5G, 5D at Village
Dongare, Virar (West),
Taluka - Vasai, Dist -
Thane. Vasai
NOT
APPROVED
Revalidation of
Consent to
Establish for
Expansion
--- It was decided to defer the case and revert back to next
CAC along with clarity on EC revalidation, OC status and
provision of pollution control system.
43 MPCB-
CONSENT-
0000041397
Gondegaon Extension OC
Coal Mine Expansion
Project, Plot No 622
Gondegaon, Parseoni,
Dist. Nagpur
APPROVED
Consent to
Establish for
Expansion
from 2.5 to 3.5
MTPA
capacity
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant Consent to establish for expansion
for Coal Mining activity- 1.0 MTPA by imposing standard
Opencast Coal Mining conditions including bank
Guarantee as per BG regime.
Consent to Establish shall be issued-
i. After obtaining Environment Clearance copy from PP.
ii. After obtaining details regarding domestic effluent
quantity & treatment provided for domestic effluent.
44 MPCB-
CONSENT-
0000039698
Ajmera Developers,
S No. 69, 71, 72, 73, 74,
75, 76, 77, 78, S. No 119,
121, 122 ,124 ,125, 126,
127, 128,129 - Vasai
APPROVED
Consent to
Establish
Commissioning
of the unit or 5
years
whichever is
earlier
It was decided to grant of Consent to Establish for
proposed residential cum commercial project & Rajhans
Kshitij for Total plot area 1,37,012.20 sq. mtrs and total
construction BUA area 2,97,236.97 sq. mtrs. as per
Environment Clearance dtd. 31.07.2017 by imposing
following conditions;
1. PP shall submit an affidavit in prescribed format
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 25 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
regarding compliance of conditions of Environment
Clearance and Consent to Establish condition.
2. PP shall achieve the treated domestic effluent standard
for the parameter BOD -10 mg/lit.
3. The treated effluent shall be 60% recycled for
secondary purposes such as toilet flushing, air
conditioning, cooling tower, make up, firefighting etc.
and remaining shall be utilized on land for gardening.
4. PP shall install online monitoring system for BOD,
TSS and flow at the outlet of STP.
5. PP shall submit Bank Guarantee of Rs.25 Lakhs
towards compliance of Environment Clearance and
Consent to Establish conditions.
1 Policy Guideline for Use of Pet Coke as a
fuel in Cement Kiln
It was decided to use Pet Coke as a substitute fuel in integrated cement
plants subject to the terms and conditions notified in the MoEF notification
dated 10.05.2016 & 23.11.2016.
1. They should abide by the conditions mentioned in proceeding in Writ
petition 13029/1985 in Hon’ble Supreme Court in the matter of Mr. M.
C. Mehta Vs Union of India.
2. The height of stack shall be as per the standard formula of stack height
calculation. They shall install all requisite pollution control measures as
per guidelines.
3. All the cement plants shall conduct ambient air quality monitoring on
regular interval of 15 days.
4. For pet coke storage where grinding and storage of pet coke carried out,
a barrier walls of adequate height along the periphery of premises shall
be provided.
5. Pet coke using cement industries shall submit detail of analysis of pet
coke before its use.
6. Pet coke shall be transported by providing scientific cover so as to
control fugitive emissions.
7. They shall comply with the Hazardous Waste (M & TM) 2016.
8. To comply the order issued by Hon’ble N.G.T. in the matter of
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 26 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
471/2016 in the matter of People for Education Research Scholarship &
Outward Nutrition Vs union of India & Central Pollution Control Board.
9. Board will issue trial permission for use of pet coke initially for 6-
month period and for the compliance of same to obtain Bank Guarantee
of Rs. 10 lakhs.
10. Cement plants using pet coke shall strictly follow MoEF notification
dated 29.01.2018 regarding sale and use of pet coke in cement plants.
2 Policy Guidelines for utilization of
Pond/Bottom Ash generating from
Thermal Power Plants for backfiling in
Abandoned mines/Stone quarry
It was decided to approve only bottom ash generating from Coal based
Thermal Power Plants for backfilling in abandoned mine / stone quarries
subject to land approval from district authorities.
On the basis of compliance of fly ash notification issued by MoEFCC, GoI
we may grant NOC for utilization bottom ash for landfill to reclaim low
lying areas including back filling in abandoned mines/ stone quarry, with
following BG Regime.
Bank Guarantee Regime for utilization of Bottom ash generated form
Thermal Power Plant for back filling in abandoned mines/stone quarry.
1. Dispose available bottom ash at designated sites (earth quarry) and soil
borrow area shall be filled up with proper compaction and reclamation
and shall ensure that such reclamation and compaction to be done in
accordance with the specifications and guidelines laid down by
authorities & fly ash notifications.
2. The compaction shall be done on a scientific way so as to give strength of
natural soil strata
3. The boundary of the reclaimed site shall have fencing and entire
reclaimed site shall be bordered by scientific garland drain so as to
prevent the runoff before commencement of activity.
4. Tree plantation shall be done on the reclaimed land @ 2500 plants /
hectare and shall be maintained. The proposed program and its
implementation schedule shall be submitted within one month of
commencement of the work.
5. Declare bottom ash generation details on monthly basis prior to its
disposal. A separate register about disposal of bottom ash shall be
maintained where officials shall make entry of utilization of bottom ash
regularly and industry shall regularly submit manifests of bottom ash
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 27 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
monthly to Board
6. There shall not be any fugitive emissions, leakage/ spillage during
transportation [Loading /Unloading] and Bottom ash transportation trucks
shall be closed from all four sides and shall be fully covered with
tarpaulins to avoid the leakage/ spillages and shall not cause any nuisance
in the surrounding during the transportation
7. The fly ash shall be utilized as per the MOEF Notification about Fly Ash
Utilization no. S.O. 763(E), dated 14/09/1999, S.O.2804 (E), dated:
03/11/2009 and S.O.254(E), dated 25.01.2016.
8. Pre monsoon & Post monsoon water quality monitoring shall carry out
every year and submit report to SPCB
9. Carrying out leachability study from reputed institute where the bottom
ash is being dumped.
10. Construction of metallic roads for transportation of ash from plant to
designated backfilling site before commencement of activity & in any
case it shall not be transported through the village.
3 Policy decision in respect of grant of
consent to Establish Expansion of
Industrial Units in the area of non-
performing CETPs
The committee noted that scheme of zero liquid discharge. Industries had
filed Writ Petitions before Hon’ble High Court Mumbai to consider their
application along with ZLD plan in a time bound manner and to grant
requisite permission.
The Hon’ble High Court Mumbai in one of the Write Petition vide order
dated 11.04.2017 directed to MPCB to process the application of the
petitioner and it is come to the conclusion that the petitioner satisfies
requirements and guideline of CPCB, then NOC may be granted to the
Petitioner.
Considering the NGT and High Court orders in the matter of non-complying
CETP’s, the issue was discussed at length and decided to consider to grant
consent to establish / expansion of industrial units with effluent treatment
plant in non-performing CETP areas, where in industry shall achieve the
zero liquid discharge (ZLD) and no pollution potential, subject to
compliance of the following directions dated 31.03.2016 issued by CPCB.
1. Not resulting in increase in pollution load such as industries generating
Nil industrial effluent, 100% industrial effluent recycling, industries
8th CAC meeting of 2017-2018 (Book-let no. 14 Consent to Establish) dated 09.02.2018 Page 28 of 28
Sr
No
Application
Unique
Number
Industry Name &
Address
Decision on
grant of
consent
Consent
granted upto Remarks/Discussion
generating only concentrated stream disposed at common hazardous
waste treatment and disposal facility.
2. CETP has un-utilised hydraulic capacity and effluent of the new industry/
expansion will help in improving the performance of CETP.