Module Loading Site Qualification G. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 Module Loading TF - Genova Site G. Darbo - INFN / Genova G. Darbo - INFN / Genova November 25, 2004 November 25, 2004 Copy of this talk on the CDS Agenda: Copy of this talk on the CDS Agenda: http://www. ge . infn .it/ATLAS/SQTF/Minutes/Minutes_04-11-25_aux/

Upload: clara-booker

Post on 04-Jan-2016

219 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Module Loading Site Qualification G. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 Module Loading TF - Genova Site G. Darbo - INFN / Genova November 25, 2004

Module Loading Site QualificationG. Darbo - INFN / Genova SQTF, 25 / 11 / 2004

Module Loading TF - Genova Site

Module Loading TF - Genova Site

G. Darbo - INFN / GenovaG. Darbo - INFN / GenovaNovember 25, 2004November 25, 2004

Copy of this talk on the CDS Agenda:Copy of this talk on the CDS Agenda:http://www.ge.infn.it/ATLAS/SQTF/Minutes/Minutes_04-11-25_aux/

Page 2: Module Loading Site Qualification G. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 Module Loading TF - Genova Site G. Darbo - INFN / Genova November 25, 2004

Module Loading Site QualificationG. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 2

Cooling & Thermal CyclesCooling & Thermal Cycles Cooling circuit modified:

Lauda RK20-KS with Ethylene Glycol (75%) + H2O (25%) running at -30ºC to cool the box at ~ -3º

Lauda RP855C with C8F18 to cool or thermal cycle the stave. Problems encountered with Lauda chillers:

Lauda RP845 break down, under repair -> Given a new and more powerful version in evaluation: RP855 -> faulty behaviour from time to time of the refrigerator…

Lauda RP855 has a pressure/suction pump (see next slide) for fluid circulation in the application. We suspect that the suction generates cavitations in the C8F18 (bubbling) -> fluid lost.

The system is now capable to run thermal cycles between ±30º on the power off modules (see slide)

Page 3: Module Loading Site Qualification G. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 Module Loading TF - Genova Site G. Darbo - INFN / Genova November 25, 2004

Module Loading Site QualificationG. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 3

Lauda RP855 Pressure/Suction Pump

Lauda RP855 Pressure/Suction Pump

Page 4: Module Loading Site Qualification G. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 Module Loading TF - Genova Site G. Darbo - INFN / Genova November 25, 2004

Module Loading Site QualificationG. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 4

Thermal CyclesThermal Cycles

QuickTime™ and aTIFF (LZW) decompressor

are needed to see this picture.

Page 5: Module Loading Site Qualification G. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 Module Loading TF - Genova Site G. Darbo - INFN / Genova November 25, 2004

Module Loading Site QualificationG. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 5

Stave S4028 - Electrical TestStave S4028 - Electrical Test LOAD test completed:

Some dead pixel on the first row of several chip (see last week presentation) are not really bad - they respond to source.

Thermal cycles done STAVE test underway

Total Bad Pixels (Digital + Analog)

0

50

100

150

200

250

300

350

M6C M5C M4C M3C M2C M1C M0 M1A M2A M3A M4A M5A M6A

Module on Stave

No. of bad pixels

BURN

LOAD

Page 6: Module Loading Site Qualification G. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 Module Loading TF - Genova Site G. Darbo - INFN / Genova November 25, 2004

Module Loading Site QualificationG. Darbo - INFN / Genova SQTF, 25 / 11 / 2004 6

S4024 - Robot UpgradeS4024 - Robot Upgrade Third production stave under loading

11 modules loaded -> completed tomorrow.

A Heidenhain Linear Encoder will be added to verify/correct the Z movement of the robot