  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    1/61

    www.huawei.com

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved.

    OptiX RTN 600 Equipment

    Commissioning

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    2/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 2

    Learning Guide

    Before studying this course, you are supposed to complete the

    study on

    Basics of digital microwave communications or related

    knowledge

    OptiX RTN 600 Product Introduction

    OptiX RTN 600 Networking and Protection Mechanism

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    3/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 3

    References

    Digital Microwave Communications Basics

    OptiX RTN 600 Radio Transmission System Configuration

    Guide

    OptiX RTN 600 Radio Transmission System Commissioning

    Guide

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    4/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 4

    Objectives

    Upon completion of this course, you will be able to:

    Finish proper preparations before the commissioning

    Performing NE commissioning of the OptiX RTN 600

    Performing hop commissioning of the OptiX RTN 600

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    5/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 5

    Contents

    1. Preparations for the OptiX RTN 600 Commissioning

    2. NE Commissioning of the OptiX RTN 600

    3. Hop Commissioning of the OptiX RTN 600

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    6/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 6

    Contents

    1. Preparations for the OptiX RTN 600 Commissioning

    1.1 Determining Commissioning Items

    1.2 Preparing Related Documents

    1.3 Preparing Related Tools

    1.4 Checking Commissioning Conditions

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    7/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 7

    Determining Commissioning Items

    1. NE Commissioning Items

    Commissioning Item Optional/Require

    d

    Remarks

    Powering on the

    equipment Required

    Check fan status after power on if fan is

    available.

    Testing indicators RequiredCheck whether all indicators work

    normally or not.

    Accessing the Web LCT Required -

    Configuring the data Required -

    Performing the service

    loopback testOptional

    Recommend to test if instrument

    available on site.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    8/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 8

    Determining Commissioning Items (cont.)

    1. NE Commissioning Items (cont.)

    Commissioning Item Optional/Require

    d

    Remarks

    Testing E1 cablesconnections

    Optional It applies to the station where the E1service is accessed.

    Checking the receive

    and transmit power of

    the optical interface

    Optional

    It applies to the station where the SDH

    optical interface service is accessed.

    Testing the RF transmitpower

    Required Use the Web LCT to query the RFtransmit power.

    Testing the

    active/standby cross-

    connect board switching

    Required

    It only applies to the equipment

    configured with the active and standby

    cross-connect boards.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    9/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 9

    2. Hop Commissioning Items

    Commissioning Item Optional/

    Required

    Remarks

    Aligning the antenna Required -

    Testing the ECC Required -

    Testing the

    orderwire phone

    Optional

    It is applicable when there is the

    order wire phone available between

    stations.

    Testing all services Required

    Test all service types turned up at

    the station like the E1, STM-1, and

    WS.

    Determining Commissioning Items (cont.)

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    10/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 10

    Commissioning

    Item

    Optional/Require

    dRemarks

    Testing the clocktracing

    Required Check and ensure that the clocksource can be traced normally.

    Testing the IF

    switching modesRequired

    It is applicable when the 1+1

    HSB/FD/SD protection is configured.

    Testing the SNCPswitching

    Required It is applicable when the SNCP isconfigured.

    Testing the long-

    term BERRequired

    Generally perform the test for 24

    hours according to the actual

    conditions

    2. Hop Commissioning Items (cont.)

    Determining Commissioning Items (cont.)

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    11/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 11

    Preparing Related Documents

    Engineering design documents like

    OptiX RTN 600 Radio Transmission System Network Planning

    Document

    OptiX RTN 600 Radio Transmission System Engineering

    Design Document

    Commissioning guide documents like:

    OptiX RTN 600 Radio Transmission System Commissioning

    Guide

    OptiX RTN 600 Radio Transmission System Quick Installation

    and Commissioning Guide

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    12/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 12

    Preparing Tools

    The tools that are required include the common tools, special tools

    and instruments. The recommended list is as follows:

    Type Description

    Common

    tool

    Adjustable wrench, percussion drill, sharp-nose pliers, and

    electric knife

    Special

    tool

    Anti-static glove, ESD-preventive wrist strap, telescope,

    and intercom

    InstrumentMulti-meter, BER tester, and laptop computer (installed

    with the Web LCT)

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    13/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 13

    Checking NE Commissioning Conditions

    The hardware installation complete.

    The power supply is normal.

    The cable / fiber installation.

    Web LCT is available.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    14/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 14

    Checking Hop Commissioning Conditions

    The NE commissioning is complete.

    The weather condition.

    Safety of the operation at a high altitude.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    15/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 15

    Summary

    This chapter describes the following contents:

    NE commissioning items and hop commissioning items

    Documents and tools prepared before the commissioning

    Commissioning conditions

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    16/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 16

    Contents

    1. Preparations for the OptiX RTN 600 Commissioning

    2. NE Commissioning of the OptiX RTN 600

    3. Hop Commissioning of the OptiX RTN 600

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    17/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 17

    Contents

    2. NE Commissioning of the OptiX RTN 600

    2.1 Powering On the Equipment

    2.2 Testing Indicators

    2.3 Accessing the Web LCT

    2.4 Configuring the Data

    2.5 Performing the Service Loopback test

    2.6 Testing the Connections of the E1 Cables

    2.7 Testing the Transmit and Receive Optical Power

    2.8 Testing the RF Transmit Power

    2.9 Testing the Active/Standby Cross-Connect Board Switching

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    18/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 18

    Powering On the Equipment

    Prerequisites

    Hardware installation complete and power is available.

    The power supply must be available, and the fuse capacity of

    the power supply must meet the requirements.

    Tools and Instruments

    Multi-meter

    Procedure Turn off all power switches on equipment.

    Turn on the input power switch of the cabinet.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    19/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 19

    Powering On the Equipment (cont.)

    Test power volt and polarity.

    Turn on the switch on PXC board.

    Monitor fan and indicators.

    Turn on the power of ODU.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    20/61

    Copyright 2009 Huawei Technologies Co., Ltd. All rights reserved. Page 20

    Testing Indicators

    Prerequisites

    After 5 minutes power on

    Tools and Instruments

    None.

    Procedure

    Press or release the button on SCC.

    LAMP

    TEST

    button

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    21/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 21

    Accessing the Web LCT

    Prerequisites

    After power on.

    Tools and Instruments

    Laptop computer installed with Web LCT

    Cross cable

    Procedure

    Connect cable.

    Start Web LCT on laptop computer.

    Set IP of computer.

    Set the options of the Internet Explorer (IE).

    NM interface

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    22/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 22

    Accessing the Web LCT(con.)

    On desktop, double-click the Start Web

    LCT icon. The system displays the

    USER LOGIN window of the Web LCT

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    23/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 23

    Accessing the Web LCT (con.)

    Enter User Name and Password, and then click Login. The

    user name of the Web LCT is admin by default, and the

    corresponding password is T2000 by default.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    24/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 24

    Configuring the Data

    Prerequisites

    After Web LCT access.

    Tools and Instruments

    Web LCT

    Procedure

    Set the new ID and IP as the planning document request.

    Configure all the existing boards in equipment.

    Monitor board indicators again.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    25/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 25

    Checking alarm

    Prerequisites

    The equipment must be connected to the Web LCT.

    Data configuration must be complete.

    Tools, Instruments, and Materials

    Web LCT

    Procedure

    Select an NE from the Object Tree in the NE Explorer, and then click in the

    toolbar.

    Select Auto Refresh.

    Check the displayed alarm information.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    26/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 26

    Testing Transmit and Receive Optical

    Power

    Prerequisites

    Fiber connection is available.

    Boards are configured

    Tools and Instruments

    Web LCT or optical power meter

    Procedure

    Disable automatic laser shutdown (ALS) function.

    Check the transmit and receive optical power by Web LCT or optical

    power meter.

    Judge the power value is normal or not.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    27/61

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    28/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 28

    Testing E1 Cable Connections

    Prerequisites

    Service and cable connection available.

    Tools and Instruments

    Web LCT and BER tester

    Procedure

    Connect tester and set the outloop.

    Release outloop, AIS alarm should occur. All the ports can be test together.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    29/61

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    30/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 30

    Testing Active/Standby Cross-

    connect Switching

    Prerequisites

    Service be configured.

    The active and standby cross-connect boards be configured.

    Tools and Instruments

    Web LCT and BER tester

    Procedure

    Current status of two PXC should be normal.

    Switch PXC board by Web LCT and monitor their status and alarms.

    Restore back PXC board.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    31/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 31

    Questions

    What is the procedure to access Web LCT?

    How should the E1 port be set and connected for testing the connections

    of E1 cables? How to adopt the testing it quickly?

    Why shall we disable the ATPC function when test RF transmit power?

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    32/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 32

    Summary

    Powering on the equipment

    Testing indicators

    Accessing the Web LCT

    Checking Alarm

    Configuring the data

    Testing the transmit and receive optical power

    Performing the service loopback test

    Testing the connections of E1 cables

    Testing the RF transmit power

    Testing the active/standby cross-connect board switching

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    33/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 33

    Contents

    1. Preparations for the OptiX RTN 600 Commissioning

    2. NE Commissioning of the OptiX RTN 600

    3. Hop Commissioning of the OptiX RTN 600

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    34/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 34

    Contents

    3. Hop Commissioning of the OptiX RTN 600

    3.1 Aligning the Single-PolarizedAntenna

    3.2 Aligning the Dual-Polarized Antennas

    3.3 Testing the ECC

    3.3 Testing the E1 Service

    3.3 Testing the Ethernet Service

    3.4 Testing the WS Service

    3.5 Testing the order wire

    3.6 Testing the Clock Tracing

    3.7 Testing the IF 1+1 Switching

    3.8 Testing the SNCP Switching

    3.9 Testing the 24-Hour BER

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    35/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 35

    Aligning the Single-PolarizedAntenna

    Prerequisites

    The NE commissioning is complete.

    Weather is suitable for commissioning.

    The on-site conditions and personnel fit for high altitude operation.

    ATPC disabled.

    Tools and Instruments

    Wrench, multi-meter and intercom.

    Procedure

    1. Rotate antenna approximately.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    36/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 36

    RS

    SI

    Aligning the Single-PolarizedAntenna(cont.)

    Procedure (cont.) 2. Test VBNC value:

    VBNC

    RSL

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    37/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 37

    Aligning the Single-PolarizedAntenna(cont.)

    Procedure (cont.)

    3. Rotate antenna in horizontal manner widely to search the

    highest VBNC.

    4. Adjust the elevation angle to search the highest VBNC.

    5. Aligning the remote antenna.

    6. Repeat step 2 to step 5 for 2 to 4 times until get the highest

    VBNC at both sides.

    7. Tighten all the screws to fix antenna and make a mark.

    8. Read the current RSL for both sides.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    38/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 38

    Aligning the Single-PolarizedAntenna(cont.)

    Precautions

    Align the antennas respectively in case of two antennas

    configured at both sides.

    1+1 SD.

    1+1 FD + SD.

    The antenna adjustment device is screw bolt.

    Make the test line with BNC interface for multimeter in advance.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    39/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 39

    Aligning the Dual-PolarizedAntenna

    Prerequisites

    The NE commissioning of the radio equipment at both ends of the

    radio link must be complete.

    The weather must be suitable for outdoor work. There should be

    no rain, snow or fog between stations.

    The on-site conditions must meet the requirement for performing

    operations at high altitudes and the personnel in charge of

    commissioning the antenna must be trained to work at high

    altitudes.

    The ATPC function must be disabled.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    40/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 40

    Aligning the Dual-PolarizedAntenna(cont.)

    Tools, Instruments, and Materials

    Ejector lever

    Multi-meter

    Procedure

    1.Power off the vertically polarized ODUs at both ends of the

    radio link, power on the horizontally polarized ODUs at both ends

    of the radio link, and thus ensure that the antennas transmit

    horizontally polarized signals.

    2.Adjust the azimuth angle and elevation angle of the antennas at

    both ends and ensure that the main lobe of the horizontally

    polarized signals is aligned with the antenna.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    41/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 41

    Aligning the Dual-PolarizedAntenna(cont.)

    3.Measure the RSL (P1) of the horizontally polarized signals at

    the local end.

    4.Adjust the feed boom at the local end, and ensure that the RSL

    of the vertically polarized signals reaches the lower threshold (P2).

    5.Record the angle (D1) of the current feed boom.

    6.Power off the horizontally polarized ODUs at both ends

    of the radio link, power on the vertically polarized ODUs at

    both ends of the radio link, and thus ensure that the

    antennas transmit vertically polarized signals.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    42/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 42

    Aligning the Dual-PolarizedAntenna(cont.)

    7.Measure the RSL (P3) of the vertically polarized signals

    at the local end by referring to 3.

    8.Power on the horizontally polarized ODU at the local end,

    and calculate the level (P4) of the horizontally polarized

    signals received at the local end by referring to 4. The

    calculated XPD2 (XPD2 = P3 P4) should not be less than

    30 dB.

    9.Record the angle (D2) of the current feed boom.

    http://localhost/var/www/apps/Local%20Settings/Temp/Rar$EX25.4922/web/01-04%20HOP%20Commissioning%20Guide.htmhttp://localhost/var/www/apps/Local%20Settings/Temp/Rar$EX25.4922/web/01-04%20HOP%20Commissioning%20Guide.htmhttp://localhost/var/www/apps/Local%20Settings/Temp/Rar$EX25.4922/web/01-04%20HOP%20Commissioning%20Guide.htmhttp://localhost/var/www/apps/Local%20Settings/Temp/Rar$EX25.4922/web/01-04%20HOP%20Commissioning%20Guide.htm
  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    43/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 43

    Aligning the Dual-PolarizedAntenna(cont.)

    10.Repeat 3to 9to adjust the feed boom slightly (ranging

    from D1 to D2), and ensure that XPD1 and XPD2 are not

    less than 30 dB.

    11.Tighten all the screws of the antennas.

    http://localhost/var/www/apps/Local%20Settings/Temp/Rar$EX25.4922/web/01-04%20HOP%20Commissioning%20Guide.htmhttp://localhost/var/www/apps/Local%20Settings/Temp/Rar$EX25.4922/web/01-04%20HOP%20Commissioning%20Guide.htmhttp://localhost/var/www/apps/Local%20Settings/Temp/Rar$EX25.4922/web/01-04%20HOP%20Commissioning%20Guide.htmhttp://localhost/var/www/apps/Local%20Settings/Temp/Rar$EX25.4922/web/01-04%20HOP%20Commissioning%20Guide.htm
  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    44/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 44

    Testing the ECC

    Prerequisites

    Antenna alignment must be complete.

    The NE must have access to the Web LCT.

    Tools and Instruments

    Web LCT

    Precautions

    Test the ECC at one end of the radio link.

    Procedure Add and set the attributes of the remote NE in Web LCT

    Observe Login Statusof the newly added remote NE.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    45/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 45

    Testing the E1 Service

    Prerequisites

    The E1 service must be available.

    Antenna alignment must be complete.

    Tools and Instruments

    BER tester and Web LCT

    Procedure

    BER tester connected to local site.

    Remote site set the loopback.

    No errors in 5 or 10 minutes.

    Release all loopbacks.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    46/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 46

    Testing the E1 Service (con.)

    When there isnt BER tester, the PRBS function of

    PDH board can test the E1 service instead of BER

    tester.

    Setting the loop-back of an E1 interface at remote site.

    Configuring PRBS function at local site.

    Observing the testing result.

    Releasing loop-back

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    47/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 47

    Testing the Ethernet Service

    Prerequisite

    The Ethernet service must be configured between stations.

    Tools, Instruments, and Materials

    Web LCT

    One laptop

    Connection diagram for testing the Ethernet service

    Configuration for testing the Ethernet service

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    48/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 48

    Testing the Ethernet Service(cont.)

    Cable connection for the IDU (NE 1)

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    49/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 49

    Testing the Ethernet Service(cont.)

    Cable connection for the IDU (NE 2)

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    50/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 50

    Testing the Ethernet Service(cont.)

    Procedure

    1.On the IDU side of NE 1, use an Ethernet cable to connect the

    Ethernet port of the laptop to the Ethernet service port of the Ethernet

    board, as shown in The Ethernet service port enables service

    transmission between NEs.

    2.On the IDU side of NE 2, use an Ethernet cable to connect the

    Ethernet port of the SCC to the Ethernet service port of the Ethernet

    board, The Ethernet service port enables service transmission

    between NEs.

    3.Set the IP address of the laptop, and ensure that the IP

    address and the IP address of NE 2 belong to the same

    network segment.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    51/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 51

    Testing the Ethernet Service(cont.)

    Display the Command Prompt window of laptop A, and run the ping

    129.9.0.2 -n 200 -l 2000 command.

    After you run the command, check the result. There should not

    be lost packets, that is, the output display should contain the

    following information: Lost = 0 (0% loss)

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    52/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 52

    Testing the WS Service

    Prerequisites

    The WS service must be configured.

    Antenna alignment must be complete.

    Tools and Instruments

    BER tester

    Procedure

    At local site, connect the BER tester to the WS port.

    At remote site, perform the hardware inloop for the WS port.

    Test the BER for 5 to 10 minutes by BER tester. No bit errors shouldoccur.

    Release the loopback.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    53/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 53

    Testing the order wire

    Prerequisites

    The order wire phone must be correctly installed at the station.

    The data of the order wire must be configured.

    Antenna alignment must be complete.

    Tools and Instruments

    None.

    Procedure

    Dial the number of remote site.

    Check the voice is clear or not.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    54/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 54

    Testing the Clock Tracing

    Prerequisites

    The clock tracing priority list must be configured.

    Tools and Instruments

    Web LCT

    Procedure

    Query the current clock priority table by using the Web LCT.

    Query the current . Manual switch the PXC board.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    55/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 55

    Testing the IF 1+1 Switching

    Prerequisites

    The equipment must be configured with the IF 1+1 protection.

    Antenna alignment must be complete.

    Tools and Instruments

    BER tester and Web LCT

    Procedure

    Connect E1 tester in local E1 port and set loopback in remote site.

    Query the working status of IF board.

    Mute the active ODU to start the IF switch.

    Check status and alarms.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    56/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 56

    Testing the IF 1+1 Switching (cont.)

    Procedure (cont.)

    Check the bit errors generate in switching.

    Test the restoration of IF 1+1 switching.

    Power on the main ODU.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    57/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 57

    Testing the SNCP Switching

    Prerequisites

    The equipment must be configured with the SNCP protection.

    Antenna alignment must be complete.

    Tools and Instruments

    BER tester and Web LCT

    Procedure

    Connect tester for E1 ports and perform the bit error testing.

    Power of the ODU to trigger the SNCP switch.

    Check the service status, alarms and bit errors.

    Test the restoration of SNCP.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    58/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 58

    Testing the 24-Hour BER

    Prerequisites

    Antenna alignment must be complete.

    Tools and Instruments

    BER tester and Web LCT

    Procedure

    Cascade the E1 ports with the BER

    tester at one site.

    Perform the loopback at the other

    sites.

    Test bit error for 24 hours.

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    59/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 59

    Questions

    What is the procedure to aligning antennas?

    How long should it take to test the E1 service and WS service

    respectively by using the BER tester?

    What alarms occur after the IF 1+1 switching is complete?

    How can we ensure that SNCP switching is successful?

    How should we handle bit errors occurring in the 24-hour BER test?

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    60/61

    Copyright 2006 Huawei Technologies Co., Ltd. All rights reserved. Page 60

    Summary

    The commissioning items in hop commissioning: 3.1 Aligning the Single-PolarizedAntenna

    3.2 Aligning the Dual-Polarized Antennas

    3.3 Testing the ECC

    3.3 Testing the E1 Service

    3.3 Testing the Ethernet Service

    3.4 Testing the WS Service

    3.5 Testing the order wire

    3.6 Testing the Clock Tracing

    3.7 Testing the IF 1+1 Switching

    3.8 Testing the SNCP Switching 3.9 Testing the 24-Hour BER

  • 8/12/2019 OTF101702 OptiX RTN 600 Equipment Commissioning ISSUE 1.01

    61/61

    Thank youwww.huawei.com