process capability training
TRANSCRIPT
-
8/18/2019 Process Capability Training
1/54
1
Using control charts,distribution analysis, rational
sampling and Ppk to betterunderstand manufacturing
process capability
Process Capability
-
8/18/2019 Process Capability Training
2/54
2
Process Capability
StandardPPAP Ppk > 1.67
OngoingProduction
Ppk > 1.33
-
8/18/2019 Process Capability Training
3/54
3
What is the problem that needs to be addressed?
First we will examine the components of
variation that are measured by Cpk and Ppk
-
8/18/2019 Process Capability Training
4/54
4
Subgroup Number
20
90
Total Variation
Components of Variation
-
8/18/2019 Process Capability Training
5/54
5
Subgroup Number
20
90
Between Subgroup Variation
Components of Variation
-
8/18/2019 Process Capability Training
6/54
6
Subgroup Number
20
90
Within Subgroup Variation
Components of Variation
-
8/18/2019 Process Capability Training
7/54
7
Subgroup Number
20
90
Within
Within Between
Between Total
Total
+ =
Components of Variation
-
8/18/2019 Process Capability Training
8/54
8
Total VariationWithin Subgroup
Variation
Between Subgroup
Variation+ =
Cpk measures within
Subgroup variation Ppk measuresTotal variation
Ppk and Cpk
σ2within σ2between σ2total
-
8/18/2019 Process Capability Training
9/54
9
Ppk and Cpk
Now for a look at the formulas
-
8/18/2019 Process Capability Training
10/54
10
)ˆ3
)X(or
ˆ3min(
22 / / d Rd R
LSL) X (USLCpk
σ σ
−−
=
Cpk (Process Potential Capability)
Ppk (Process Performance)
)ˆ3
)(orˆ3
min(S S
LSL X ) X (USLPpk
σ σ
−−
=
What is the difference above?
Ppk vs. Cpk Formulas
-
8/18/2019 Process Capability Training
11/54
11
Standard Deviation
2 / / ˆ:Cpk 2 d Rd R =σ
∑=
−
−
=
n
i
i
S
n
X X
1
2
1
)(ˆ :Ppk σ
Ppk vs. Cpk Formulas
Uses all of the data
to estimate sigma!
Uses min and max of each
subgroup to estimate sigma.For subgroup size of 5, this amounts
to only 40% of the data.
-
8/18/2019 Process Capability Training
12/54
12S u b g r o u p Nu m b e r54321
9 0
8 0
7 0
6 0
5 0
4 0
3 0
2 0
S u b g r o u p Nu m b e r
54321
9 0
8 0
7 0
6 0
5 0
4 0
3 0
2 0
R1
R2
R3
R4
R5
X
Ppk standard deviation uses the
difference between each reading and
the mean
Ppk
Cpk
Cpk vs. Ppk Training
Total Variation
Within Subgroup VariationCpk standard deviation uses the
average range divided by D2.
Rave. = (R1+R2+R3+R4+R5)/5
D2 is a constant.
X
-
8/18/2019 Process Capability Training
13/54
13
Risks of using only Cpk
• Cpk ignores between subgroup variation(It is possible to have out of specification parts and have a Cpk > 1.67)
• Note: OK to use Pp, Cpk, Cp, etc. with Ppk forinvestigation
-
8/18/2019 Process Capability Training
14/54
14
Results – Cpk vs. Ppk
Now consider the following example
-
8/18/2019 Process Capability Training
15/54
15
Sample
D y n a m i c R a t e
24222018161412108642
100
80
60
40
20
0
Run Chart with Less Between Variation
Sample
D y n a m i c R a t
e
24222018161412108642
100
80
60
40
20
0
Run Chart with More Between Variation
Ppk vs. Cpk ResultsThe subgroups have the same ranges
Cpk = 2.53
Ppk = 0.52
Cpk = 2.53
Ppk = 1.65
In the bottomexample Cpk = 2.53
even though parts
are out of
specification,
because Cpk
measures only
within subgroupvariation.
USL = 100, LSL = 10
-
8/18/2019 Process Capability Training
16/54
Rational Sampling
How do I sample parts so the controlcharts show process shifts?
16
-
8/18/2019 Process Capability Training
17/54
Rational Subgroup
• Includes only short term variation(No shifts in the process)
• Consecutive parts
• Typically 3-7 consecutive parts
• Typical 300 piece PPAP rational sampling plan (Measure 5,skip 7)
• Measure parts 1- 5,
• Skip parts 6-12,
• Measure parts 13 – 17,
• Skip parts 18-24)………
• Options for 1000 piece run when measuring 125 samples
1. subgroups of 5 evenly spaced: Measure 5 parts, skip 36 parts…2. subgroups of 3 evenly spaced: Measure 3 parts, skip 21 parts…..
17
Why would you use a subgroup of 5 vs. 3 or 3 vs. 5?
-
8/18/2019 Process Capability Training
18/54
1501401301201101009080706050403020101
0.007
0.006
0.005
0.004
0.003
0.002
Order of Production
Run Chart of Profile
Rational Subgroups Example
18
Good Rational Sampling
Subgroups are parts builtconsecutively and most include
only short term variation.
1501401301201101009080706050403020101
0.007
0.006
0.005
0.004
0.003
0.002
Order of Production
Run Chart of Profile
Subgroup 1 Subgroup 4
Subgroup 3
Subgroup 2
Subgroup 6
Subgroup 5
Incorrect Sampling
Single subgroup includes
multiple shifts in the process.
Is this an acceptable rational sampling plan?
-
8/18/2019 Process Capability Training
19/54
-
8/18/2019 Process Capability Training
20/54
1501401301201101009080706050403020101
0.007
0.006
0.005
0.004
0.003
0.002
Order of Production
Run Chart of Profile
20
Subgroup Subgroup
Subgroup
Subgroup
Subgroup
Subgroup
What happens when consecutive parts are chosen for subgroups?
28252219161310741
0.006
0.005
0.004
0.003
Sample
S a m p l e M e a n
_ _ X=0.004453
UCL=0.005093
LCL=0.003813
28252219161310741
0.003
0.002
0.001
0.000
Sample
S a m p l e R a n g e
_ R=0.001109
UCL=0.002346
LCL=0
11111
1111
1
11111111
11
111
1
11
1111
1
Xbar-R Chart of Subgroup - Consecutive Parts
Process ShiftsARE Detected!
-
8/18/2019 Process Capability Training
21/54
21
Subgroups – Charts below are from same process
Subgroups that include
Process Shifts
Rational Subgroups
(Consecutive Samples)
Process Shifts Detected NO Yes
X bar Control Limits 0.0027 - 0.006 (Inflated) 0.0038 - 0.005
Range Upper ControlLimit
0.006 (Inflated) 0.002
28252219161310741
0.006
0.005
0.004
0.003
Sample
S a m p l e M e a n
_ _ X=0.004425
UCL=0.006095
LCL=0.002756
28252219161310741
0.0060
0.0045
0.0030
0.0015
0.0000
Sample
S a m p l e R a n g e
_ R=0.002894
UCL=0.006120
LCL=0
Xbar-R Chart (Subgroups include Process Shifts)
28252219161310741
0.006
0.005
0.004
0.003
Sample
S a m p l e M e a n
_ _ X=0.004453
UCL=0.005093
LCL=0.003813
28252219161310741
0.003
0.002
0.001
0.000
Sample
S a m p l e R a n g e
_ R=0.001109
UCL=0.002346
LCL=0
11111
111
1
1
11111111
11
111
1
11
1111
1
Xbar-R Chart (Subgroups with Consecutive Parts)
-
8/18/2019 Process Capability Training
22/54
Rational Subgroup Take Away
• If parts in a subgroup span process shifts then
control limits are inflated and process shifts areNOT detected.
• Use 3-7 consecutive parts to minimize risk ofincluding process shifts inside a given subgroup
22
-
8/18/2019 Process Capability Training
23/54
Sampling Plan – Initial Capability Study
What parts should I measure and what variablesdo I need to keep track of?
23
-
8/18/2019 Process Capability Training
24/54
Sampling Plan - Exhaust Manifold
• 500 manifolds are being produced for phase 0 PPAP.
• MFG Equipment: One milling machine with two spindles.One broaching bar is used to make the spline.
• Time constraints and resources only allow for themeasurement of roughly 150 samples.
How should samples be collected for the capability study of theSCs?
Increase number of subgroups (Use 3 parts instead of 5 parts)
25 subgroups of 3 from spindle 1, 25 subgroups of 3 from spindle 2
Evenly space subgroups (e.g. spindle 1 – measure parts 1-3, skip 4- 10,
measure 11-13, skip 14-20…. Same process for spindle 2.
-
8/18/2019 Process Capability Training
25/54
Sampling Plan - Rear Differential Side Gear
• Supplier can measure all SCs on 250 parts• 1040 gears are being manufactured
1. Two CNC lathes.2. Two spindles per CNC lathe3. After the CNC operation all parts enter the process to machine
the spline. This process uses two broaching bars.4. After broaching the parts are heat treated in one of the two furnaces
each of which hold 520 parts.5. Each furnace is known to have a risk for variation between top and
bottom and left and right.6. Parts cannot be etched and any mark put on parts prior to heat treat
will be burned off during the heat treatment.
Put together a sampling plan for the PPAP run.
21 subgroups of 3 for each of the 4 spindles
Keep track of which broach is used on each part and order of broaching
Divide parts between two furnaces and area of furnaces (top, bottom, left, right)
-
8/18/2019 Process Capability Training
26/54
Sampling Plan – Cast Aluminum Engine Block
• Process: Molten aluminum forms around 14 sand cores to make anengine block. Sand is then removed leaving a cast block withpassage ways. Block is then cubed (Sides are machined)
• Seven molds make a total of the 14 sand cores
• There are 6 sets of the seven molds each of which makes a set ofthe 14 needed sand cores.• Sets 1-3 are run on production line 1 and sets 4-6 are run on
production line 2.• One machining cell machines all of the parts.
• Part has one SC (cast locator to machined surface), and eight HICs(as cast bore locations to cast datum)
Put together a sampling plan for the PPAP run.
Run 300 pieces for each of the 6 core sets (1800 pieces total)
Rational sampling of 25 subgroups of 5 for each 6 core set (Total of 750 measured parts).
Measure parts 1-5, skip 6-12, measure parts 13-17…..
-
8/18/2019 Process Capability Training
27/54
Sampling Plan Summary
• Number samples and divide subgroups evenly overproduction run (e.g. measure 5, skip 7………)
• Allocate subgroups across important variables(e.g. machines, spindles, mold cavities, furnace area etc.)
• Keep track of important variables for each measuredpart so their affect can be analyzed
• If possible divide subgroups so control charts can bedone separately for key variables(e.g. 25 subgroups of 3 for spindle 1 and 25 subgroups of 3 for spindle 2.
• Think of the initial PPAP runs as passive DOEs that canbe used to help quantify affect of critical variables
27
Good sampling strategy can lead to quicker improvements!
-
8/18/2019 Process Capability Training
28/54
28
Normality, Control, & Stability
• Capability numbers (Ppk, Pp, Cpk, Cp) must beignored pending a review of the Control, Stability
and the Distribution.
-
8/18/2019 Process Capability Training
29/54
29
Control and Stability
Sample
S a m p l e M e a
n
464136312621161161
180
175
170
165
160
_ _ X=171.59
UC L=177.19
LCL=166.00
Sample
S a m p l e R a n g e
464136312621161161
24
18
12
6
0
_ R=7.68
UC L=17.51
LCL=0
111
1111
1
11
1111
1
11
11
1
1
1
1
11
Xbar-R Chart of C15
Not Stable
Not In ControlC p 2.68
CPL 2.82
CPU 2.54
Cpk 2.54
Pp 1.59
PPL 1.67
PPU 1.50
Ppk 1.50
C pm *
O v erall C apability
Potential (Within) C apability
Within
Overall
XX
Out of control points = Special Cause
(Do
NOTuse Ppk, Pp, Cpk, Cp to predict future performance)
3 sigma
limits
-
8/18/2019 Process Capability Training
30/54
30
Is this process in control?
UCL
LCL
BoreDiameter
Time
Does the answer change
if the source of variation
is from known Non-Random
variation such as tool wear?
Demonstrating e idence of stabilit and
-
8/18/2019 Process Capability Training
31/54
31
Demonstrating evidence of stability andcontrol with Non-Random variation
UCL One solution is to use
Modified Control Limits
BoreDiameter
Time
LCL
Demonstrating evidence of stability and
-
8/18/2019 Process Capability Training
32/54
32
UCL
LCL
Modified control charts are sometimes difficult to
manage. An alternative is endpoint control.
Insuring the tool begins and ends where it should.
Any variation from the expected outcome would be
analogous to a “trend” failure for random systems.
First piece inspection to get in the ball park
add 4 more pieces to form a sub-group
Variation from “best fit line” is common cause.
Dotted line is the desired
“Saw Tooth Pattern”
A five piece sub-group to ensuring weended the tool in the right spot
Control limitscentered on
nominal
A second solution is
to use endpoint control
Demonstrating evidence of stability andcontrol with Non-Random variation
Control and Stability with Non Random
-
8/18/2019 Process Capability Training
33/54
33
Control and Stability with Non-RandomVariation
• Some processes have known causes of variation (Non-
Random) that can cause a process to shift or drift (e.g. batch
to batch variation, machining – tool wear)
• Non-Random variation may be acceptable if there are controls
in place for the shifts and drifts
Reference the Ford STA SPC training and see your site STA or
Master Black Belt for further guidance
-
8/18/2019 Process Capability Training
34/54
34
Control and Stability Take Away
1. The chances of a subgroup falling outside the 3 sigma limits is
extremely small (1 subgroup out of 370) thus any out of control
points indicate special causes.
Reference the Ford STA SPC training and see your
Master Black Belt for help.
2. For future production the special causes may come back and triggerthe process to make wild swings and out of specification parts.
3. When special causes exist Ppk does not predict the future
performance
5. If special causes exist they must be fixed or controlledprior to using any capability calculations to predict the
future or for approval of PPAP
4. Non-Random variation may be acceptable if there are controls in
place for the shifts and drifts
P k & C k ti
-
8/18/2019 Process Capability Training
35/54
35
Distribution and Normality
8 . 88 . 07 . 26 . 45 . 64 . 8
Pilot OD
P e r c e n t
0.68450.68400.68350.68300.68250.6820
99.9
99
95
90
80
7060504030
20
10
5
1
0.1
Mean 0.6830
StDev 0.0004121
N 125
AD 3.361
P-Value .05
Skewed – Non-
Normal
P value < .05
Ppk & Cpk equations assume
Normal Distribution (Bell Curve).
Calculations are often extremelyinaccurate if data is not normal.
-
8/18/2019 Process Capability Training
36/54
36
Distribution and Normality
If process experts or a review of historical data
indicates that the process output is not normally
distributed (and should not be), then the data can be• Fitted to the correct distribution (you should
be working with a Master Black Belt)
This will ensure a more accurate estimate of Ppk.
See example on next page
-
8/18/2019 Process Capability Training
37/54
Is this process capable?
37
Ppk
Normal Distribution Model 1.73
Weibull Distribution Model 0.77
11.29.68.06.44.83.21.60.0
LB USL
LB 0
Target *
USL 7
Sample Mean 0.901049
S ample N 5000
S hape 0.769151
Scale 0.77244
Process Data
Pp *
PPL *
PPU 0.77
Ppk 0.77
Overall Capability
Process Capability of Dimension
Calculations Based on Weibull Distribution Model
121086420-2
LB USL
LB 0
Target *
USL 7
Sample Mean 0.901049
Sample N 5000
StDev(Within) 1.17469
StDev(Overall) 1.17466
Process Data
CPU 1.73
Cpk 1.73
PPU 1.73
Ppk 1.73
O v erall C apability
Potential (Within) C apability
Process Capability of Dimension
Calculations Based on Normal Distribution Model
Should the data shown below be fit to the lognormal or the
-
8/18/2019 Process Capability Training
38/54
Should the data shown below be fit to the lognormal or thenormal distribution?
38
252321191715131197531
6.0
5.5
5.0
Sample
S a m p l e M e a n
_ _ X=5.261
UCL=5.588
LCL=4.934
252321191715131197531
1.2
0.9
0.6
0.3
0.0
Sample
S a m p l e R a n g e
_ R=0.567
UCL=1.199
LCL=0
1
111
111
1
111
Xbar-R Chart of Hole Diameter
Based on the control chart does
your answer change?
Looking at the control chart what
is a potential cause for the data
being non-normal?
7.6.56.05.55.04.54.0
99.9
99
95
80
50
20
5
1
0.1
Hole Diameter
P e r c
e n t
Goodness of Fit Test
Lognormal
AD = 0.604
P-Value = 0.114
Probability Plot for Hole DiameterLognormal - 95% CI
7.06.56.05.55.04.54.0
99.9
99
95
80
50
20
5
1
0.1
Hole Diameter
P e r c e
n t
Goodness of Fit Test
Normal
AD = 0.820
P-Value = 0.033
Probability Plot for Hole Diameter
Normal - 95% CI
P value > 0.05 P value < 0.05
Wh t if th d t i d b / t hift?
-
8/18/2019 Process Capability Training
39/54
6.46.26.05.85.65.45.2
99
95
90
80
70
60
50
40
30
20
10
5
1
Hole Diameter(Post-tool change)
P e
r c e n t Mean 5.726
StDev 0.2296
N 40 AD 0.391
P-Value 0.366
Post Tool Change - Probability Plot of Hole Diameter
Normal
6.05.55.04.54.0
99.9
99
95
90
8070605040
3020
10
5
1
0.1
Hole Diameter (Pre-tool change)
P e
r c e n t
Mean 5.042
StDev 0.2607N 85
AD 0.128
P-Value 0.984
Pre-tool Change - Probability Plot of Hole Diameter
Normal
What if the data is grouped by pre/post process shift?
39
Analyzing the pre & post toolchange data separately shows
the process is normally
distributed.
252321191715131197531
6.0
5.5
5.0
Subgroup
S a m p l e M e a n
Pre-tool change Post-tool change
252321191715131197531
1.2
0.9
0.6
0.3
0.0
Subgroup
S a m p l e R a n g e
Pre-tool change Post-tool change
Xbar-R Chart of Hole Diameter
Always check the control chartto see if a process shift or out of
control point is causing the data
to be non-normal.
If the process is expected to have a normal distribution and robust controls
-
8/18/2019 Process Capability Training
40/54
If the process is expected to have a normal distribution and robust controlsare in place for tool changes is this data acceptable for PPAP?
40
252321191715131197531
6.0
5.5
5.0
Subgroup
S a m
p l e M e a n
Pre-tool change Post-tool change
252321191715131197531
1.2
0.9
0.6
0.3
0.0
Subgroup
S a m p l e R a n g e
Pre-tool change Post-tool change
Xbar-R Chart of Hole Diameter
6.05.55.04.54.0
99.9
99
95
90
807060504030
20
10
5
1
0.1
Hole Diameter (Pre-tool change)
P e r c e n t
Mean 5.042
StDev 0.2607N 85
AD 0.128
P-Value 0.984
Pre-tool Change - Probability Plot of Hole Diameter
Normal
6.46.26.05.85.65.45.2
99
95
90
80
70
60
5040
30
20
10
5
1
Hole Diameter(Post-tool change)
P e r c e n t Mean 5.726
StDev 0.2296N 40
AD 0.391
P-Value 0.366
Post Tool Change - Probability Plot of Hole Diameter
Normal
Pre-tool change data is stable
Post-tool change
data is stable
Pre-tool change data is on control
Post-tool change
data is in control
Pre-tool change
data is normal
Post-tool change
data is normal
7.26.66.05.44.84.23.63.0
LSL USL
Cp 3.08
CPL 3.09
CPU 3.06
Cpk 3.06
Pp 1.85
PPL 1.85
PPU 1.84Ppk 1.84
Cpm *
Overall Capability
Potential (Within) Capability
Within
Overall
Process Capability of Hole Diameter
Ppk > 1.67
Yes
Resolution and Normal Distributions
-
8/18/2019 Process Capability Training
41/54
5.45.35.25.15.04.94.84.74.64.5
99.99
99
95
80
50
20
5
1
0.01
Length
P e r c e n t
Mean 4.950
StDev 0.1042
N 5000
AD 188.900
P-Value
-
8/18/2019 Process Capability Training
42/54
42
Distribution and Normality Take Away
1. Use process experts and historical data to determine
expected distribution. This is a physics discussion.
(Do NOT blindly fit data to a distribution)
Reference the Ford STA SPC training and see your
Master Black Belt for help.
2. If the data does not match the expected distribution determine the
special causes and fix the process.
3. If the data matches the expected distribution but is not normal
(Anderson-Darling P value < .05) fit the data to the correctdistribution and calculate Ppk. (If process is stable and in
control)
4. If data matches the expected distribution and is normal or
symmetrical calculate Ppk. (If process is stable and in control)See following slide for list of non-normal distributions
N l di t ib ti
-
8/18/2019 Process Capability Training
43/54
43
Non-normal distributions
Manufacturing ProcessDescription
Expected Process Distribute type
Bilateral Process Normal
Grinding process with auto correction Uniform
Tapered roller bearing Fatigue Weibull
Output signal Voltage Log Normal
Flatness/Roundness Log Normal
Plating Thickness Family of Weibull Distributions
FTT - Non Normal - piled up near 100% Log Normal
Sensor output transient voltage Exponential
PPAP O i P d i
-
8/18/2019 Process Capability Training
44/54
44
PPAP vs. Ongoing Production
When does the process change from a PPAP (Ppk> 1.67) to ongoing Production (Ppk > 1.33) ?
The ongoing production requirement of 1.33 is used afterPPAP once the process and data contains the expectedsources of variation that occur over time.
With many commodities the initial Phase 2 PPAP run will notexperience all of the sources of variation (e.g.: different shifts,lots of components, machine wear, etc.)
The PPAP Ppk requirement of 1.67 is higher than the ongoing
production requirement of 1.33 because it is recognized thatthere will be a degradation as all of the expected sources ofvariation are experienced in ongoing production.
-
8/18/2019 Process Capability Training
45/54
45
Summary
Process must be in control and stable before looking at
capability index values
The data must be fit to the expected
distribution
(Do NOT blindly fit the data to a distribution.
Exercise 1
-
8/18/2019 Process Capability Training
46/54
46
Exercise 1
42363024181260
USL
LSL *
Target *
USL 10
Sample Mean 1.64497
S ample N 10000
StDev (O v erall) 2.11492
Process Data
Pp *
PPL *
PPU 1.32
Ppk 1.32
C pm *
O v erall C apability
PPM < LSL *
PPM > USL 9700.00
PPM Total 9700.00
O bserv ed Performance
PPM < LSL *
PPM > USL 38.99
PPM Total 38.99
Exp. Ov erall Performance
Process Capability of C1
Ppk = 1.32 for ongoing production. Assuming the Engineer is
willing to modify the specification so the Ppk is greater than
1.33 is this process capable?
Exercise 1 Answer
No
-
8/18/2019 Process Capability Training
47/54
47
Exercise 1 Answer
Ppk
Original data 1.32
Lognormal DistributionModel
0.46
We don’t know if process is stable and in control. We also need historicaldata or process expert to help determine the expected distribution.
42363024181260
USL
Pp *
PPL *
P PU 0.46
P pk 0.46
O verall C apability
PPM < LSL *
PPM > USL 10940.34
PPM Total 10940.34
Exp. Ov erall Performance
Process Capability of C1Calculations Based on Lognormal Distribution Model
Answers are drastically
different depending upon
the distribution that is used.
No
Exercise 2
-
8/18/2019 Process Capability Training
48/54
48
Exercise 2
Sample
S a m p l e
M e a n
554943373125191371
32
28
24
20
_ _ X=22.17UC L=22.87
LCL=21.47
Sample
S a m p l e R a n g e
554943373125191371
2.4
1.8
1.2
0.6
0.0
_ R=1.210
UC L=2.559
LCL=0
1
Xbar-R Chart of Rule 1 Data
Given that the Ppk = 1.87 can the PPAP be signed?
No: There is an out of control point which is likely from aspecial cause. Do NOT look at capability numbers until the process
is stable and in control.
Exercise 3
-
8/18/2019 Process Capability Training
49/54
49
Exercise 3
With a Ppk = 1.66 can the PPAP be signed?
Pilot OD
P e r c e n t
0.68450.68400.68350.68300.68250.6820
99.9
99
95
90
80
7060504030
20
10
5
1
0.1
Mean 0.6830
StDev 0.0004121
N 125
AD 3.361
P-Value USL 0.00
PPM Tota l 0.00
Observ ed Performance
PPM < LSL 0.34
PPM > USL 0.12
PPM Tota l 0.46
Exp. Within Performance
PPM < LSL 1.04
PPM > USL 0.39
PPM Tota l 1.43
Exp. Ov erall Performance
Within
Overall
Process Capability of Pilot OD
Sample
S a m p l e M e a n
252321191715131197531
0.68350
0.68325
0.68300
0.68275
0.68250
_ _ X=0.68296
UC L=0.683489
LCL=0.682431
Sample
S a m p l e R a n g e
252321191715131197531
0.0020
0.0015
0.0010
0.0005
0.0000
_ R=0.000918
UC L=0.001941
LCL=0
1
Xbar-R Chart of Pilot OD
Out of control condition
Rule # 1
X
X
Answer: No
Data is notnormal
P value < .05
Exercise 4
-
8/18/2019 Process Capability Training
50/54
50
I n d i v
i d u a l V a l u e
10987654321
0.0
-0.8
-1.6
_ X=-0.596
UCL=0.388
LCL=-1.580
M o
v i n g R a n g e
10987654321
1.0
0.5
0.0
__ MR=0.37
UCL=1.209
LCL=0
Observation
V a l u e s
108642
0.0
-0.5
-1.0
1.81.20.60.0-0.6-1.2-1.8
LSL USL
LSL -2
USL 2
Specifications
0.0-0.5-1.0-1.5
Within
Overall
Specs
StDev 0.328014
C p 2.03
C pk 1.43
Within
StDev 0.26604
Pp 2.51
Ppk 1.76
C pm *
O v erall
Process Capability Sixpack of 10 Parts
I Chart
Moving Range Chart
Last 10 Observations
Capability Histogram
Normal Prob Plot
A D: 0.234, P: 0.723
Capability Plot
With a Ppk = 1.76 can this acceptable for PPAP?
NoOnly 10 pieces used in study are not enough toallow a robust assessment of normality, stability or control.
The PPAP requirement is 25 subgroups with typical subgroup size of 5
Exercise 5
-
8/18/2019 Process Capability Training
51/54
51
With a process that has an expected normal distribution are these
results acceptable for PPAP?
25 subgroups with 5 parts each were used per Ford
Specific PPAP
S a m p
l e M e a n
252321191715131197531
-0.4
-0.6
-0.8
_ _ X=-0.5726
UCL=-0.2586
LCL=-0.8865
S a m
p l e R a n g e
252321191715131197531
1.0
0.5
0.0
_ R=0.544
UCL=1.151
LCL=0
Sample
V a l u e s
252015105
0.0
-0.5
-1.0
1.81.20.60.0-0.6-1.2-1.8
LSL USL
LSL -2
USL 2
Specifications
0.0-0.5-1.0-1.5
Within
O verall
Specs
StDev 0.234026
C p 2.85
Cpk 2.03
Within
StDev 0.238404
Pp 2.8
Ppk 2
C pm *
O v erall
Process Capability Sixpack of 125 Parts
Xbar Char t
R Chart
Last 25 Subgroups
Capability Histogram
Normal Prob Plot A D: 0.665, P: 0.081
Capability Plot
Process is stable
Process is normal
P value > .05
Process is in control
Ppk > 1.67
Yes
Exercise 6
-
8/18/2019 Process Capability Training
52/54
1501401301201101009080706050403020101
0.007
0.006
0.005
0.004
0.003
0.002
Order of Production
Run Chart of Profile
Exercise 6
52
Is this a rational sampling plan?
SubgroupNo – subgroup
includes process shifts
Exercise 7b
-
8/18/2019 Process Capability Training
53/54
1501401301201101009080706050403020101
0.007
0.006
0.005
0.004
0.003
0.002
Order of Production
Run Chart of Profile
Exercise 7
53
Is this a rational sampling plan?
Yes – subgroups are
consecutive pieces and are lesslikely to include process shifts
Subgroup 1Subgroup 4
Subgroup 3
Subgroup 2
Subgroup 6
Subgroup 5
Exercise 8
-
8/18/2019 Process Capability Training
54/54
1501401301201101009080706050403020101
0.007
0.006
0.005
0.004
0.003
0.002
Order of Production
Run Chart of Profile
54
SubgroupUsing the subgroup sampling
plan shown on the left results
in the control chart shownbelow
What is wrong with thissampling plan and what is the
effect on the X bar R chart?
28252219161310741
0.006
0.005
0.004
0.003
Sample
S a m p l e M e a n
_ _ X=0.004425
UCL=0.006095
LCL=0.002756
28252219161310741
0.0060
0.0045
0.0030
0.0015
0.0000
Sample
S a m p l e R a n g e
_ R=0.002894
UCL=0.006120
LCL=0
Xbar-R Chart of Subgroup with Process Shifts
1. Subgroups are not consecutive partsand include process shifts
2. Process shifts will NOT be detected
Control limits are inflated (too large)