resettlement action plan (rap) for ayer-kamdini...

167
RURAL ELECTRIFICATION AGENCY Resettlement Action Plan (RAP) for Ayer-Kamdini- Minakulu-Bobi and Environs in Northern Uganda (75 km) Final Report RESCO PROPERTY CONSULTANT SURVEYORS 11/12/2010 RP1490

Upload: others

Post on 11-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

RURAL ELECTRIFICATION AGENCY

Resettlement Action Plan (RAP) for Ayer-Kamdini-Minakulu-

Bobi and Environs in Northern Uganda (75

km)Final Report

RESCO PROPERTY CONSULTANT SURVEYORS11/12/2010

RP1490 V4

Page 2: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

ii

Page 3: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

TABLE OF CONTENTS

GLOSSARY OF TERMS............................................................................................................................. VI

EXECUTIVE SUMMARY..........................................................................................................................VIII

1. INTRODUCTION.........................................................................................................................................11.1. PROJECT DESCRIPTION..........................................................................................................................11.2. THE AIM OF THE RESETTLEMENT ACTION PLAN..............................................................................21.3. OBJECTIVES OF THE RAP.....................................................................................................................2

1.3.1. Approach and Methodology..............................................................................................21.3.1.2.Census...........................................................................................................................................31.3.1.7.Inventory of lost and affected Assets.........................................................................41.3.1.8.Socio-economic Surveys and Studies..........................................................................51.3.2. Analysis of Surveys and Studies....................................................................................7

2. PROJECT IMPACTS AND AFFECTED PERSONS.......................................................................9

2.1. PROJECT AFFECTED PERSONS.............................................................................................................92.2. SOCIO-ECONOMIC BASELINE OF PAPS.............................................................................................9

2.2.1. Age and Gender.......................................................................................................................92.2.2. Educational Attainment.....................................................................................................102.2.3. Ethnicity.....................................................................................................................................112.2.4. Livelihoods and Employment.........................................................................................112.2.5. Ownership and Particulars of the affected Person............................................112.2.6. Burial Sites................................................................................................................................132.2.7. Income Sources......................................................................................................................132.2.8. General Information about Children..........................................................................142.2.9. Impaired Persons..................................................................................................................152.2.10. Production Systems.............................................................................................................172.2.11. Social Network and Support System.........................................................................19

3. LEGAL FRAMEWORK FOR LAND ACQUISITION AND COMPENSATION.......................20

3.1. RELEVANT NATIONAL LAWS....................................................................................................................203.2. OTHER LAWS...........................................................................................................................................213.2.1. THE LOCAL GOVERNMENT ACT (1997)............................................................................................21

3.2.2. Land Acquisition Act (1965)...................................................................................................223.2.3. Land Tenure Regimes and Transfer of Land....................................................................22

3.3. VALUATION AND COMPENSATION OF ASSETS........................................................................................243.4. WORLD BANK REQUIREMENTS................................................................................................................254. INSTITUTIONAL RESPONSIBILITIES...................................................................................................27IN IMPLEMENTING THIS RESETTLEMENT ACTION PLAN, THREE KEY STAKEHOLDERS HAVE BEEN IDENTIFIED INCLUDING THE MINISTRY OF LOCAL GOVERNMENT, MINISTRY OF LANDS, HOUSING AND URBAN DEVELOPMENT AND REA.....................................................................................................................................27

4.1. Rural Electrification Agency.......................................................................................................274.2. Ministry of Local Government...................................................................................................27

iii

Page 4: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

4.3. Ministry of Lands, Housing and Urban Development........................................................274.4. Related Line Ministries.................................................................................................................284.4.1. Ministry of Energy and Mineral Development......................................................284.4.2. Ministry of Agriculture, Animal Industry and Fisheries..................................284.4.3. Ministry of Health.................................................................................................................284.4.4. Ministry of Education and Sports................................................................................284.4.5. Ministry of Water, Lands and Environment...........................................................294.4.6. Ministry of Works, Housing and Communication................................................294.4.7. Ministry of Finance, Planning and Economic Development..........................29

4.5. IMPLEMENTATION SCHEDULE.............................................................................................................29

5. COMPENSATION FRAMEWORK..................................................................................................30

5.1. KEY PRINCIPLES....................................................................................................................................305.1.1. COMPENSATION AND RESETTLEMENT PACKAGES.....................................................................305.2. ELIGIBILITY.............................................................................................................................................325.3. RATES APPLIED.....................................................................................................................................335.3.1. GENERAL REMARKS AND ASSUMPTIONS....................................................................................335.3.2. CUT-OFF DATE..................................................................................................................................345.3.3. VALUATION CERTIFICATE................................................................................................................34

6. RESETTLEMENT ASSISTANCE AND RESTORATION OF LIVELIHOODS........................37

6.1. LIVELIHOOD RESTORATION STRATEGIES.........................................................................................376.2. SPECIAL ASSISTANCE FOR WOMEN AND VULNERABLE GROUPS...............................................37

7. PUBLIC CONSULTATION, PARTICIPATION AND DEVELOPMENT PLANNING...........39

7.1. COMMUNITY PERCEPTIONS OF THE PROJECT.................................................................................397.2. COMMUNITY CONCERNS......................................................................................................................397.2.1. IMPACT ON PROPERTY AND CULTURAL SITES...........................................................................39

8. GRIEVANCE MECHANISM.............................................................................................................. 41

8.1. MECHANISMS OF GRIEVANCE AND APPEALS.................................................................................418.1.1. Reconciliatory Procedure.................................................................................................418.1.2. Written Complaints to REA..............................................................................................418.1.3. Legal Redress..........................................................................................................................42

8.2. PUBLIC DISCLOSURE............................................................................................................................42

9. MONITORING, EVALUTION AND REPORTING FRAMEWORK..........................................43

9.1. Internal monitoring process.......................................................................................................439.1.1. During resettlement............................................................................................................439.1.2. After resettlement................................................................................................................449.1.3. Key Activities and Responsibilities.............................................................................44

9.2. EXTERNAL EVALUATION PROCESS..........................................................................................................449.2.1. Process Indicators................................................................................................................459.2.2. Outcome Indicators..............................................................................................................459.2.3. Key activities and responsibilities.......................................................................................46

9.3. RAP COMPLETION REPORT......................................................................................................................46

iv

Page 5: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

9.4. COMPLETION AUDIT.................................................................................................................................46

v

Page 6: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

GLOSSARY OF TERMSCompensation—Payment in cash or in kind for an asset or a resource that is acquired or affected by a project at the time the asset needs to be replaced.

Cut-off date—Date of completion of the census and assets inventory of persons affected by the project. Persons occupying the project area after the cutoff date are not eligible for compensation and/or resettlement assistance. Similarly, fixed assets (such as built structures, crops, fruit trees, and woodlots) established after the date of completion of the assets inventory, or an alternative mutually agreed on date, will not be compensated.

Host population—People living in or around areas to which people physically displaced by a project will be resettled who, in turn, may be affected by the resettlement.

Economic displacement—Loss of income streams or means of livelihood resulting from land acquisition or obstructed access to resources (land, water, or forest) resulting from the construction or operation of a project or its associated facilities.

Involuntary resettlement—Resettlement is involuntary when it occurs without the informed consent of the displaced persons or if they give their consent without having the power to refuse resettlement.

Land expropriation—Process whereby a public authority, usually in return for compensation, requires a person, household, or community to relinquish rights to land that it occupies or otherwise uses

OD 4.30—The World Bank Group Operational Directive on Involuntary Resettlement. OD 4.30 embodies the basic principles and procedures that underlie IFC’s approach to involuntary resettlement associated with its investment projects.

Project-affected household—All members of a household, whether related or not, operating as a single economic unit, who are affected by a project.

Project-affected person—Any person who, as a result of the implementation of a project, loses the right to own, use, or otherwise benefit from a built structure, land (residential, agricultural, or pasture), annual or perennial crops and trees, or any other fixed or moveable asset, either in full or in part, permanently or temporarily.

vi

Page 7: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Physical displacement—Loss of shelter and assets resulting from the acquisition of land associated with a project that requires the affected person(s) to move to another location.

Replacement cost—The rate of compensation for lost assets must be calculated at full replacement cost, that is, the market value of the assets plus transaction costs. With regard to land and structures, IFC defines “replacement costs” as follows:

agricultural land—the market value of land of equal productive use or potential located in the vicinity of the affected land, plus the cost of preparation to levels similar to or better than those of the affected land, plus the cost of any registration and transfer taxes;

land in urban areas—the market value of land of equal size and use, with similar or improved public infrastructure facilities and services preferably located in the vicinity of the affected land, plus the cost of any registration and transfer taxes;

household and public structures—the cost of purchasing or building a new structure, with an area and quality similar to or better than those of the affected structure, or of repairing a partially affected structure, including labor and contractors’ fees and any registration and transfer taxes. In determining the replacement cost, depreciation of the asset and the value of salvage materials are not taken into account, nor is the value of benefits to be derived from the project deducted from the valuation of an affected asset.

Resettlement Action Plan (RAP)—The document in which a project sponsor or other responsible entity specifies the procedures that it will follow and the actions that it will take to mitigate adverse effects, compensate losses, and provide development benefits to persons and communities affected by an investment project.

Resettlement assistance—Support provided to people who are physically displaced by a project. Assistance may include transportation, food, shelter, and social services that are provided to affected people during their relocation. Assistance may also include cash allowances that compensate affected people for the inconvenience associated with resettlement and defray the expenses of a transition to a new locale, such as moving expenses and lost work days.

vii

Page 8: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

EXECUTIVE SUMMARYThe Government of Uganda, recognizing the importance of energy in transforming the quality of life of Ugandans, embarked on the process of systematic energy planning with the formulation of a National Energy Policy for Uganda in September 2002. The Energy Policy Goal is “ to meet the energy needs of Uganda’s population for social and economic development in an environmentally sustainable manner

Project DescriptionThe Government of Uganda has received financing from the World Bank towards the cost of the Energy for Rural Transformation Project Phase II, and intends to apply part of the loan proceeds to make payments under the contracts for Consultancy Services for Detailed Action Plan (RAP) for the Ayer-Kamdini-Minakulu-Bobi and Environs in Northern Uganda (75km). The proposed 75 kilometres Ayer-Kamdini-Bobi-Minakulu power distribution line project covers three district of Kole Oyam and Gulu, 10 sub countries and 84 villages/LCI cells. The study was to prepare a Resettlement Action Plan to establish compensation and resettlement costs for the PAPs before the implementation of the project.

The aim of the Resettlement Action Plan The purpose of the consultancy is to prepare a detailed RAP to establish the social impacts associated with setting up of these 33kV lines, ROW of clearing and setting of temporary camps for equipment storage construction and compensation of other resettlement costs for the Project Affected Persons (PAPs). The RAP has been carried out in a way that respects Uganda Government Policies as well as the World Bank’s O.P. 4.12 Involuntary Resettlement.Objectives of the RAPSpecifically, the resettlement action plan focused on determining the extent of resettlement impacts associated with establishment of the distribution line, and put in place measures to mitigate those impacts. The impacts here are to do with land/way-leaves acquisition and the accompanying loss or interruption of the livelihoods of the project affected people due to construction activities related to the proposed distribution lines. Additionally, this resettlement action plan aimed at carrying out consultations with relevant stakeholders, including potentially affected persons, to obtain their views and suggestions regarding the social impacts of the proposed project and measures to cover the losses.

Approach and Methodology

viii

Page 9: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

The first task in planning resettlement was to identify a project’s adverse impacts and the populations that will be affected. As noted above, this usually requires the participation of qualified experts who have appropriate training and experience. Resettlement planning involves more than simple cadastral surveys or inventories of affected assets. Consultation with officials of local government, community leaders, and other representatives of the affected population was essential to gaining a comprehensive understanding of the types and degrees of adverse project effects. Property valuation and assessment of compensation awards has been carried out within the broad terms of reference (TOR) of the RAP study for the proposed Ayer-Kamdini- Minakulu -Bobi power distribution line project.

An inventory of lost and affected assets at the household, enterprise, and community level was undertaken in order to ascertain all losses that will result for each household, enterprise, or community affected by the project. Socioeconomic surveys and studies of all affected people were undertaken in order to understand socio-economic condition of the potentially affected persons in the project areas the study will used the sustainable livelihoods approach which is a way to improve understanding of the livelihoods of poor people. Analysis of surveys and studies to establish compensation parameters were undertaken in order, to design appropriate income restoration and sustainable development initiatives, and to identify baseline monitoring indicators; and analysis of the data collected in the census, assets inventory, and socioeconomic studies.

Project Impacts and Affected PersonsDetailed list of affected persons is attached as an annex to this report. Given that a 10 meter strip will be required for the way leaves and noting that most of the affected plots are within road reserves, this assessment team found that only crops and trees will be affected. There are Eighty Four (84) affected villages, in Kole, Oyam and Gulu Districts. The total number of claimants is 1143 and the assessed total compensation is Shs.95,675, 252/- (Ninety Five Million Six Hundred Seventy Five Thousand Two Hundred Fifty Two Thousand Shillings Only). Implementation ScheduleHaving assigned the different organizational responsibilities, this team anticipates that the RAP implementation is likely to cover a period of 13 months. The sequencing of activities bears in mind that some activities can be undertaken at the same time.

Compensation FrameworkInformation from the socio-economic survey and census guided the selection of the most appropriate compensation packages while bearing in mind the different scenarios. Due to lack of Area Compensation Rates for newly created districts of Oyam and Kole, the consultant applied/used the current

ix

Page 10: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Area Compensation Rates of Gulu district to arrive at the compensation awards to the PAPs.

Cut-off DateThe date of the valuation/assessment is November 2010

BudgetThere are Eighty Four (84) affected villages, in Kole, Oyam and Gulu Districts. The total number of claimants is 1143 and the assessed total compensation is Shs.95,675,252/- (Ninety Five Million Six Hundred Seventy Five Thousand Two Hundred Fifty Two Thousand Shillings Only). Resettlement Assistance and Restoration of LivelihoodsWherever possible, the Government of Uganda tries to avoid or minimize the displacement of people by exploring alternative project designs The Rural Electriction Agency guided by the Wayleaves Act, provides for realignment of power lines in order to minimize displacement of households or businesses. International guidelines like the IFC recommends that project sponsors undertake the necessary actions on behalf of all affected people, including members of the host communities in which displaced people will be settled.

Special Assistance for Women and Vulnerable GroupsThe Resettlement Planning team identifies this as the most appropriate option for resettlement assistance and livelihood restoration given that although women form a small percentage of the affected households, the nature of tenure agreements in Northern Uganda that is customary in nature makes women more vulnerable to access to productive resources. As a result women tend to suffer more than men as a result of social changes. Therefore throughout the development of this RAP some of the immediate and practical measures are proposed to improve women’s adaptation to resettlement.

Public Consultation, Participation and Development PlanningGenerally, most communities that were consulted were happy with the proposed project. They noted that some of the villages were previously connected to power but the facilities got vandalized during the war. It was observed that most of the trading centers had the potential to grow like Corner Mowlem but this was hampered by no power in the area. Most communities wondered when the actual work would begin given the need for power in schools, health centers and other related infrastructure including the trading centre. Other issues that were raised include impact of the power line on cemeteries and graveyards and payment for the crops destroyed, and were informed on the crops that would be identified during the census and valued, impact on structures and whether property would

x

Page 11: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

be lost whether trees were not allowed under the wayleaves and would have to be compensated. On the compensation framework, one community member wondered whether compensation rates were negotiable suggesting that previous rates that have been found to be unfavorable and the method of compensation would be adopted. Additionally, community members wondered whether they will be given work to help in putting up the power line and were informed that should transmission come, employment opportunities would be availed where need. Members suggested that some of the opportunities that they should benefit from include cutting of trees, clearing of land and digging holes. On grievances, one community member narrated that previous power line planners did not compensate them for the crops lost and wondered what procedure they should use in case they have complaints. Considering that there is no structure at the moment, they were advised to inform or report this to the RDC. However, a grievance mechanism has been recommended in this report to manage the grievance process. Grievance MechanismRegardless of its scale, involuntary resettlement inevitably gives rise to grievances among the affected population over issues ranging from rates of compensation and eligibility criteria to the location of resettlement sites and the quality of services at those sites. There is need to ensure that procedures are in place to allow affected people to lodge a complaint or a claim (including claims that derive from customary law and usage) without cost and with the assurance of a timely and satisfactory resolution of that complaint or claim.

Monitoring, Evaluation and Reporting FrameworkThe purpose of monitoring and evaluation for this RAP will be to report about the effectiveness of the implementation of the RAP, covering resettlement, disbursement of compensation and effectiveness of public involvement, amongst others. Monitoring and purposeful evaluation will be key factors for successful resettlement activities. Monitoring will also entail evaluation of effectiveness of the grievance management process. The monitoring Framework proposed in this RAP includes a review of financial disbursements, compensation complaints and grievance redress, adherence to compensation payment schedule, support of vulnerable PAPs. RAP completion report During RAP implementation the consultant will submit to REA quarterly progress reports, after completion of resettlement, a final report will be submitted by REA prior to preparation of the project implementation report. This report will give overall assessment of the RAP process indicating activities undertaken, success of mitigation action ns and monitoring and well as useful lessons learnt.

xi

Page 12: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Completion AuditThe purpose of Completion Audit will be to establish whether REA implemented all activities needed to ensure compliance proposed resettlement commitments and applicable national and international policies.

xii

Page 13: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

1. INTRODUCTIONThe Government of Uganda, recognizing the importance of energy in transforming the quality of life of Ugandans, embarked on the process of systematic energy planning with the formulation of a National Energy Policy for Uganda in September 2002. The Energy Policy Goal is “ to meet the energy needs of Uganda’s population for social and economic development in an environmentally sustainable manner”. The Policy covers the various energy sub-sectors including: Power, Petroleum, New and Renewable Sources of Energy, and Atomic Power. While the sub-sectors are supply based, the Policy also covers energy demand issues and proposes strategies and plans for supplying the required energy. One of the strategies highlighted is the implementation of the Rural Electrification Strategy and Plan 2001-2010 (RESP) which has been passed by Cabinet in February 2001, as dictated by Section 63 of the Electricity Act 1999. Statutory Instrument No. 75 of 2001, The Electricity (Establishment and Management of the Rural Electrification Fund) Instrument 2001, established three inter-related mechanisms for management of Uganda’s rural electrification program namely, the Rural Electrification Fund (REF), the Rural Electrification Board (REB) and the Rural Electrification Agency (REA) all supervised by the Minister responsible for Energy. REA serves as the Secretariat to the Board whose principal responsibility is to ensure management of the Fund for equitable promotion of rural electricity access and connectivity.

1.1. Project DescriptionThe Government of Uganda has received financing from the World Bank towards the cost of the Energy for Rural Transformation Project Phase II, and intends to apply part of the loan proceeds to make payments under the contracts for Consultancy Services for Detailed Action Plan (RAP) for the Ayer-Kamdini-Minakulu-Bobi and Environs in Northern Uganda (75km). The proposed 75 kilometres Ayer-Kamdini-Bobi-Minakulu power distribution line project covers three district of Kole Oyam and Gulu, 10 sub countries and 84 villages/LCI cells. The study was to prepare a Resettlement Action Plan to establish compensation and resettlement costs for the PAPs before the implementation of the project. The study was carried in the way that takes into account the Uganda Laws/policies as well as the social safeguard policies of the World Bank and other funding agencies.

The proposed construction of distribution lines is associated with

Construction of HV power lines consisting of line structures, accessories and conductors;

Cleaning of right of way as necessary Construction of HV/LV sub stations and associated infrastructure;

Page 14: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Construction of the low voltage reticulation for the covered trading centres and towns;

Construction of the workers’ camp and storage facilities for the project materials

The project located in Northern Uganda will include the construction of 33kv line of a route length of at least 65 km with LV networks at selected potential load centers divided up as detailed below:

1. 43.5 km of 33 kV power line from Corner Aboke to Kamdini Township including tee-offs to Atapara Mission and Loro Teacher Training College;

2. Tee-offs of 4km to Aber, 2km to Loro PTC, and 3.5km to Atapara Mission;

3. 25 km of 33kV power line from Bobi to Minakulu to Kamdini

1.2. The aim of the Resettlement Action Plan The purpose of the consultancy is to prepare a detailed RAP to establish the social impacts associated with setting up of these 33kV lines, ROW of clearing and setting of temporary camps for equipment storage construction and compensation of other resettlement costs for the Project Affected Persons (PAPs). The RAP has been carried out in a way that respects Uganda Government Policies as well as the World Bank’s O.P. 4.12 Involuntary Resettlement.

1.3. Objectives of the RAPSpecifically, the resettlement action plan focused on determining the extent of resettlement impacts associated with establishment of the distribution line, and put in place measures to mitigate those impacts. The impacts here are to do with land/way-leaves acquisition and the accompanying loss or interruption of the livelihoods of the project affected people due to construction activities related to the proposed distribution lines.

Additionally, this resettlement action plan aimed at carrying out consultations with relevant stakeholders, including potentially affected persons, to obtain their views and suggestions regarding the social impacts of the proposed project and measures to cover the losses. The outcome of the consultations are reflected in the RAP report and incorporated into the project design as appropriate. The results of the consultations will be made available to all relevant stakeholders, including potentially affected persons.

1.3.1. Approach and Methodology

1.3.1.1. Reconnaissance and consultations

2

Page 15: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

The consultancy team comprising valuers, surveyors, sociologists and the RAP specialist visited the district of Kole, Oyam and Gulu and went through the areas of the proposed wayleaves route/project site. The objective of this activity was to get firsthand experience of the project area as to well as introduce the tam and the project to the local leaders.The consultant met and made consultations with the district and subcounty leaders in Kole, Oyam and Gulu districts. The purpose of these meetings was for the consultant to introduce himself and the project and seek support/assistance and cooperation of the leaders in having easy entry to the communities while doing fieldwork. Consultation meetings enabled the consultant to receive guidance in planning sensitization and public awareness meetings for the project affected persons at a village levels.

1.3.1.2. CensusProperty valuation and assessment of compensation awards was carried out within the broad terms of reference (TOR) of the RAP study for the proposed Ayer-Kamdini- Minakulu -Bobi power distribution line project. In accordance with the scope, the valuation task of the study were to:-

(a) Identify the project affected person using procedures approved by the Chief Government Value, carry out detailed valuation of all affected land, properties and livelihoods affected by the project, which provided the basis for compensation/resettlement.

(b) Compile land acquisition and resettlement costs for areas that PAPs are to be resettled if any.

(c) Ensure the data collection during valuation is done on forms acceptable to the Chief Government Valuer and the process is properly witnessed by the client.

(d) Ensure that all property such as houses and PAPs are photo document, including damaged crops, for easy identification during disclosure and payments.

(e) Witnessing the valuation exercise: REA staff shall sign on behalf of the client during the valuation exercise. Other signatories were be the Consultant and local council and the independent NGO

(f) The valuation data base is to be duplicated one copy to the client and the other to the consultant during the valuation process.

(g) An independent Witness NGO were appointed by the client to witness the valuation exercise.

1.3.1.3. Mobilization and SensitizationThe consultant carried out mobilization and sensitization of the PAPs at village levels in all areas affected by distribution line. Mobilization and sensitization was aimed at preparing the PAPs for the activities under the

3

Page 16: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

assignment. The consultant was able to explain to the PAPs the possible route (project site) the likely damage to be caused, the process and basis of assessment of damages for compensation. The PAPs were also told of the benefits that would accrue to the area in general because of the provision of electricity supply. The consultant informed the PAPs of the available mechanism to address any grievances that may arise during project implementation. The views and concerns of the communities would be recorded.

1.3.1.4. Identification of the Project siteThe client provided the consultant with maps defining the routes of the proposed power line. The consultant sought further information from the design consultants which were used by the surveyors to define the route on the ground. The route of the power line determined the districts, the sub counties, parishes, villages and individual land holdings affected by the project.

1.3.1.5. Sensitization of PAPsGuided by the route and in consultation with the district and sub county officials the consultant was able to identify locations venues for PAPs sensitization meetings. Then the consultant prepared a program for the meetings. In the meetings the valuation team together with other members of the consultancy team explained the Government policies on rural electrification, assessment and payment compensation for any damages and urged communities to cooperate and support the field team. The consultancy team explained the basis of assessment, the methodology and how grievances would be addressed.

1.3.1.6. Field Data CaptureAfter carrying out consultations and sensitization, the surveyors defined the 10 metres wayleaveas corridors including the different individual land holdings and identified of the land owners. The crops, economic trees and other assets to be affected were referenced, enumerated and detailed entered on the assessment forms. The exercise was witnessed by the beneficiaries and the LCI chair persons. The forms were stamped by LCI chairperson as proof of the data collected. This census was undertaken in order to enumerate the affected people and register them according to location; register the affected population by residence or locality; establish a list of legitimate beneficiaries before the project’s onset that counters spurious claims from those moving into the project area solely in anticipation of benefits; lay a framework for subsequent socioeconomic research needed to establish fair compensation rates and to design, monitor, and evaluate sustainable income restoration or development interventions; and providing a baseline for monitoring and evaluation.

4

Page 17: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

1.3.1.7. Inventory of lost and affected AssetsAn inventory of lost and affected assets at the household, enterprise, and community level was undertaken in order to ascertain all losses that will result for each household, enterprise, or community affected by the project. The survey accounted for land acquisition and loss of physical assets as well as loss of income—temporary or permanent—resulting from displacement of household members from employment or income-generating resources.

1.3.1.8. Socio-economic Surveys and StudiesThe RAP identified all people affected by the project and all adverse impacts on their livelihoods associated with the project’s land acquisition. Typical effects include breakup of communities and social support networks; loss of dwellings, farm buildings, and other structures (wells, boreholes, irrigation works, and fencing), agricultural land, trees, and standing crops; impeded or lost access to community resources such as water sources, pasture, forest and woodland, medicinal plants, game animals, or fisheries; loss of business; loss of access to public infrastructure or services; and reduced income resulting from these losses.

Socioeconomic surveys and studies of all affected people were undertaken in order to understand socio-economic condition of the potentially affected persons in the project areas the study will used the sustainable livelihoods approach which is a way to improve understanding of the livelihoods of poor people. It draws on the main factors that affect poor people's livelihoods and the typical relationships between these factors. The two key components of the Sustainable Livelihoods Approach are: a framework that helps in understanding the complexities of poverty and a set of principles to guide action to address and overcome poverty. The framework places people, particularly rural poor people, at the centre of a web of inter-related influences that affect how these people create a livelihood for themselves and their households.

Closest to the people at the centre of the framework are the resources and livelihood assets that they have access to and use. These can include natural resources, technologies, their skills, knowledge and capacity, their health, access to education, sources of credit, or their networks of social support. The extent of their access to these assets is strongly influenced by their vulnerability context, which takes account of trends (for example, economic, political, and technological), shocks (for example, epidemics, natural disasters, civil strife) and seasonality (for example, prices, production, and employment opportunities). Access is also influenced by the prevailing social, institutional and political environment, which affects the ways in which people combine and use their assets to achieve their goals. These are their livelihood strategies.

5

Page 18: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

People are the main concern, rather than the resources they use or their governments. SLA is used to identify the main constraints and opportunities faced by poor people, as expressed by them. It builds on these definitions, and then supports poor people as they address the constraints, or take advantage of opportunities. The framework is neither a model that aims to incorporate all the key elements of people's livelihoods, nor a universal solution. Rather, it is a means of stimulating thought and analysis, and it needs to be adapted and elaborated depending on the situation.

Therefore, the methodology that was used for this assessment is that of mixed methods, integrating both quantitative and qualitative methods. It includes a review of related literature on policies, a socio-economic survey that will be used to determine the vulnerability context of community members that are translated into negative or positive socio-economic impacts as well as strategies that will be proposed to help them cope or adapt to the negative impacts in order to improve their livelihood outcomes. The qualitative aspects of this assessment include meetings, in-depth interviews with key informants and community meetings.

Figure 1: Sustainable Livelihoods Framework

The study was undertaken in three main phases:

a.) Mobilization and Planning: This phase included the desk study and development of field instruments. The literature that was reviewed included policy documents, district development plans of affected districts as well as other related literature. It also includes mobilization for sensitization meetings

b.) Fieldwork: Data Analysis and Synthesisc.) Report Writing

Mobilization and Planning

6

Page 19: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

This phase included the desk study and development of field instruments. The literature that was reviewed included policy documents, district development plans of sub counties covered by the project areas as well as other related literature. A reconnaissance visit of sub counties and districts was undertaken in order to help plan for the sensitization meetings and the detailed field activities. A structured questionnaire will be developed and pretested for accuracy as well as interview guides that were to be used for the key informant interviews. Two research assistants were selected from the localities and trained for a period of two days. During the training sessions, we will be able to agree on terms and descriptions of different phenomenon that will help in the interpretation of the data.

Fieldwork

The fieldwork was undertaken between the months of September and October where a census of the potentially affected households was undertaken. In situ, local characteristics of different social groups within communities will be taken into account while selecting respondents and indicators such gender, ethnicity and age will be taken into consideration in order to understand labor dynamics, employment opportunities and gaps, literacy levels and access to social services amongst others. Community meetings were conducted in the project affected area in order to understand the social cultural set up within the communities that would help determine the fears that communities have towards the project. Key informant interviews were undertaken with local government staff and other development partners in the area to determine the strength of local institutions and national policies that would help sustain the project mitigation measures.

The processing of the socio-economic data began soon after the start of fieldwork, completed questionnaires were returned periodically from the field to a data processing center, first in the field where they were checked for consistency and check for response errors. The data was then entered into SPSS coded and cleaned in Kampala. The data entry ended in October and data analysis was completed within two weeks.

1.3.2. Analysis of Surveys and Studies

Analysis of surveys and studies to establish compensation parameters were undertaken in order, to design appropriate income restoration and sustainable development initiatives, and to identify baseline monitoring indicators; and analysis of the data collected in the census, assets inventory, and socioeconomic studies serves three ends: 1) it provides information needed to establish an entitlement matrix for household- and community-level compensation; 2) it yields basic economic and social information needed to design appropriate livelihood restoration and development

7

Page 20: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

interventions; and 3) it provides quantifiable demographic, economic, educational, occupational, and health indicators for future monitoring and evaluation of RAP implementation.

This information was essential to designing livelihood restoration measures for affected households and communities. Likewise, the assessments of losses resulting from the effects of the project are better understood in the context of the overall household and community economies. Household data can, in turn, was disaggregated to identify economic strata within communities (the poorest and most vulnerable households, households dependent on remittances, etc.) and to identify appropriate assistance as well as development strategies for the populations affected by the project. Socioeconomic studies also yield important information on the ways in which affected communities are organized and function. These studies provided the team with an understanding of leadership and decision making processes within the community that may function independently of the prevailing political and administrative structures. This understanding also helps resettlement planners to identify informal social support networks that are important for the survival of the community, particularly more vulnerable members of the community such as households headed by women, the impoverished, and groups that suffer social and economic discrimination.

8

Page 21: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

2. PROJECT IMPACTS AND AFFECTED PERSONS

This chapter is a presentation of the project affected persons as identified in the census and registration exercise. Census and registration provide information on the scale and complexity of the required resettlement planning (for example, the size, distribution, and socioeconomic diversity of the population). The census must encompass all people adversely affected by the project, regardless of their legal status—landowner, holder of land rights, tenant, illegal squatter—or whether they are actually living on an affected site at the time of the census. In other words, lack of legal land title does not disqualify people from resettlement assistance. Private landowners and holders of rights to land as well as any person currently occupying public or private land for shelter, business purposes, or other sources of livelihood (caretakers, squatters, scavengers) should be included in the census.

While landless people or squatters may not be eligible for land compensation, they may be eligible for resettlement assistance, compensation for assets (such as shelters and standing crops, orchards, or woodlots), and, where practicable, the benefits of development interventions, which may include provision of land. Resettlement planners must give particular attention to vulnerable groups living in the project area. These groups may include households headed by women or children, people with disabilities, the extremely poor, the elderly, and groups that suffer social and economic discrimination, including indigenous peoples and minorities. Members of vulnerable groups may require special or supplementary resettlement assistance because they are less able to cope with the physical and/or economic displacement than the affected population in general.

2.1. Project Affected PersonsDetailed list of affected persons is attached as an annex to this report. The affected persons are presented as an annex in this report. Given that a 10 meter strip will be required for the way leaves and noting that most of the affected plots are within road reserves, this assessment team found that only crops and trees will be affected. There are Eighty Four (84) affected villages, in Kole, Oyam and Gulu Districts. The total number of claimants is 1143 and the assessed total compensation is Shs.95,675,252/- (Ninety Five Million Six Hundred Seventy Five Thousand Two Hundred Fifty Two Thousand Shillings Only).

2.2. Socio-Economic Baseline of PAPs2.2.1. Age and Gender

Results from the socio-economic survey suggest that a bigger percentage of the PAPs fall within the 40 – 64 age bracket. This age group is still economically active and forms a significant proportion of the labor force.

9

Page 22: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

39%

46%

9%7%

Age Distribution of Project Affected Persons

18 - 39 years40 - 64 years65+ yearsNR

85%

15%

Gender Distribution in Affected Areas

MaleFemale

85% of the affected households are men while 15% are females, suggesting that female households form part of the vulnerable groups of this study given that are a minority. Recommendations have been made in the resettlement and livelihood restoration component.

2.2.2. Educational Attainment

Investment in education contributes to the accumulation of human capital, which is essential for higher incomes and sustained income growth. Formal education is highly instrumental and even necessary to improve the production capacity of a nation and discusses the rationality behind investment in human capital. Empirical evidences of human capital model reveal that investment in education has positive correlation with economic growth and development. Results from the socio-economic survey suggest that most of the respondents interviewed had maximum level of educational attainment of primary school level.

Education affects many aspects of life, including individual demographic and health behavior. Studies have shown that educational level is strongly associated with contraceptive use, fertility, and the general health status, morbidity, and mortality of children. In each household, for all persons age five years or older, data were collected on the highest level of education attended and the highest grade completed at that level.

Results from the socio-economic survey suggests that 59% of the affected household Upper Primary as their highest level of educational attainment. The implication for these levels is that a bigger proportion of the population would need more skills in order to engage in nonfarm income generating activities. In order to transform livelihood assets into livelihood outcomes, communities need software processes that can help strengthen their coping and livelihood strategies.

10

Page 23: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

2.2.3. Ethnicity

The ethnic groups in an area give an indication on how diverse a community is and also which minority groups exist in the area. 98% of affected households are Langi.

2.2.4. Livelihoods and Employment

Results from the socio-economic survey that over 78% of households interviewed were engaging in subsistence agriculture this means that over reliance on agro-based that are the least in terms of economic returns is the main reason why there is mass poverty in the affected areas. Benefits from non farm income generating activities can help boost the production and productivity of a household, however due to low levels of education attainment, this is not possible.

1%

12%

78%

2% 0%7%

1%

Occupations of Project Affected Persons

Casual LaborerCivil ServantFarmerNRRetiredSelf EmployedStudent

2.2.5. Ownership and Particulars of the affected Person

In order to understand the vulnerability context of affected persons it was important to understand their level of access to natural or productive assets like land. The results from the socioeconomic survey suggest that 98% of affected persons that were identified own the land that is affected while the

11

10%

59%

17%

5%7%1%

Highest Level of Edu-cational Attainment

Lower Primary (P1 - P4)

Upper Primary (P5 - P7)

O'Level A'LevelTertiary Other

Page 24: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

other 2% include co-owners and tenants. It is already observed that most of the affected persons are males and hence the few that are women are likely to remain vulnerable to change due to their limited.As northern Ugandans return home, land is becoming a major source of tension, and it is the most vulnerable members of society – women, children, former abductees – who will suffer most. The majority of land in northern Uganda is held by customary tenure i.e. through informal rules enforced by traditional clan structures. Results from the socio-economic survey confirm this observation by revealing that 93% of affected households have land under the customary tenure agreement. Under customary tenure, the concept of land ‘ownership’ is misleading, because future generations are considered to have rights to the land. People are ‘custodians’ rather than owners of land. But to function as it should, the system of customary tenure is reliant on social cohesion and stable family units. It has difficulty accommodating the breakdown in social order, the greater number of children born out of wedlock, and the increase in cohabitation that conflict and displacement have produced. Results from the socio-economic survey suggest that of those who own land 98% have encumbrances on that land given that family members can claim the land and are thus licencees. 98% of these structures are used for both residential and small businesses. Hence maintaining cohesion between families is important for sustainable livelihoods and ensuring access to housing.

98%

2%1%

Encumberances On Af -fected Land

Claim by Family MembersDocuments AvailableNo Idea

90%

10%

Usage of Structures on Affected Plot

Residential OnlyResidential & Small Busi-ness

However, this cohesion is threatened by the fact that Northern Uganda’s population is extraordinarily young, with a median age of 14 for females and 13 for males.16 Many young people having grown up in the camps, knowledge of customary land law has diminished, including about the rights of widows and orphans, who under Acholi customary law are granted access

12

Page 25: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

to land. Formal structures for dealing with land disputes, such as local council courts, are weak and often corrupt. Efforts should be made both to strengthen formal legal structures and to integrate the traditional clan system and knowledge within those structures, for example by calling elders to sit as witnesses on local council courts during cases involving land.

2.2.6. Burial Sites

Project affected persons were asked whether they have any graveyards or burial sites located within the 10 me way leave area. According to the constitution of the Republic of Uganda, under Article 37 every person has a right to belong to, enjoy, practice and profess, maintain and promote any culture, cultural institution or tradition in community with others. Under the National Objectives and Directive Principles Of State Policy, the State is obliged under objective XXIV and XXVII To promote protect and preserve cultural values and practices which enhance the dignity and wellbeing of Ugandans. Under objective XXV the State is obliged to preserve, promote and generally promote the culture of preservation of public property and Uganda’s heritage the state is also obliged under the objective to promote and implement energy policies that will ensure that people’s basic needs and those of environmental protection are met.According to the socio-economic studies, 70% of affected households were found to have burial sites on the affected plots. However, further analysis revealed that of those burial sites and graveyards, only 4% were likely to be located under the way leaves. In this regard and with consultation of communities, graveyards will be avoided so that they don’t have to be relocated. The impact on graveyards is therefore not significant given the mitigation measure that has been integrated in the compensation framework.

2.2.7. Income Sources

PAPs were asked what their primary, secondary and tertiary sources of income with the aim of assessing the project impacts in relation to the livelihoods. Results from the socio-economic survey suggest that 87% primarily depend on crop production as an income sources.

13

1%

29%

71%

Households With or Without Burial Sites in Affected Plot

N/ANo Burial Site in Affected PlotBurial sites in Affected Plot

Page 26: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

0% 3%

9%

87%

1%

Primary Income Sources of Affected Households

Animal HusbandryBusinessFormal Employ-mentCrop Hus-bandryNone

Given the subsistence nature of crop production, marketing constraints and price fluctuations, farmers in the project area remain vulnerable to price and climatic shocks. Furthermore, as the major income source in the project affected area, crop damage causes a significant income loss. Moreover, even without any agricultural shock, crop production under rain fed conditions is subject to seasonality. Thus, other sources of income are needed to smooth consumption and income across the cropping season and post-harvest season. Under risky environments, risk-averse poor households tend to diversify sources of income away from agriculture to decrease risk ex ante.

In adapting to these shocks, farmers in the project area have opted for animal rearing as a tertiary source of income. Engaging in livestock provides an opportunity to gain access to liquid assets that they can use during times of need specifically economic hardships while enhancing food security. During the socio-economic survey, 99% of the households have small ruminants with mainly include goats followed by poultry which suggests that most have adopted alternative approaches to achieving food security. The absence of large ruminants could be attributed to the fact that most households are still building their physical assets that would help them in adapting to the changing economic needs. Prior to the conflict, the Acholi people kept large numbers of cattle, which were a source of wealth and pride. Because much of the livestock was wiped out and virtually all other assets destroyed during the conflict, land has become the only resource for many. Restocking cattle populations could reduce the pressure on land. This is one of many policy tools that will need to be employed if future land disputes are to be mitigated.

2.2.8. General Information about Children

On average each household has 1.447619 children under 5 years, 2.52 are of school going age, 2.07 are in primary school, 1.57 are in secondary school,

14

1% 1%

99%

Others Sources of Income for Project

Affected Households

Crop Hus-bandryBusinessAnimal Husbandry

Page 27: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

while 1.42 are attending tertiary institutions. Although the USE and UPE programmes are in place, many parents are still burdened with provision of scholastic materials and food amongst others and hence still have a high dependency ratio. School enrolment in Oyam has been on increase since inception of UPE from about 20,613 from inception of UPE in 1997 (10,817 boys and 9,796 girls), 97,506 in 2006 when Oyam started as a District to the present enrolment of 112,091 (57,043 boys and 55,048 girls). At household level, only 11.4% of survey respondents were of school going age but not attending school. As shown in the graph below, most of the children walk to school and hence any impact relating to relocating schools take into account the impact on children.

68%

23%

1%8%

Means of Transport for School Going Children

WalkPublic MeansPrivate MeansOthers

This assessment team has found that no physical infrastructure will be affected by this project and there is no impact on children in the affected villages relating to increased walking distance to schools that would reduce their performance.

2.2.9. Impaired PersonsPreviously referred to as disabled persons, persons with impairment are identified as vulnerable given the existing institutions that constrain their participation in all activities of life. Results from the socio-economic survey suggest that only 4% of the affected persons are living with some form of impairment. As shown in the graph below, of those who were impaired, only small percentages had physical, visual, mentally and hearing impairments.

15

Page 28: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

1% 1% 4%2%

92%

Nature of Impairement in Project Af -fected Households

HearingVisualPhysicalMentalOther

The category of other forms of impairment could include people living with HIV/AIDs or any other persons that are chronically ill including the elderly. The restoration packages proposed in this plan have taken care of these vulnerable groups.Against this background, PAPs were asked to identify the type of health facilities that they have access to. Results suggest that 52% have access to health facility III only 32% have access to referral hospitals.

32%

2%52%

14%

0%

Access to Health Facilities in Project Area

HospitalHealth facility IVHealth facility IIIHealth facility IIHealth facility I

In terms of distance to the nearest health facility, the majority have to walk less than 5km to their nearest health facility. This means that in terms of health infrastructure, community members remain vulnerable and poor.

16

Page 29: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

According to the community, poor health is one of the effects of poverty. It produces a vicious cycle. Poor health leads to inability to work, which in turn leads to failure to produce food/earn income. This eventually leads to poverty. A person who is in such a trap is vulnerable to disease and death.

Less than 5km

5 – 10km 10 or more0

50100150200250

Distance to the Nearest Health Facility

Series1

Distance

Freq

uency

Having appreciated the health vulnerability, the assessment team integrated these concerns in the design of the power line and when community members were asked whether they foresaw that the health facilities would be affected; 82% said that they would be affected while 18% said that they would not be affected. In the planning phase, such institutions were avoided.

2.2.10. Production Systems

Understanding production systems in important in addressing gender production constraints at household level as they give an indication of the contribution of crops grown on affected plot affect total household income. Results suggest that on a scale of 1 – 10, there is a 50% chance that affected crops will have a significant impact on household incomes as shown in the graph below.

17

Page 30: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

The most predominant crop grown is maize and is considered as a cash crop for many households. The price of maize per kilo fluctuates depending on the production levels. At the moment a kilo goes for 200 Uganda Shillings.

However, further analysis revealed that of those crops that are likely to be affected, most are either in the background of the plot or in the right of way.

18

Page 31: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

2.2.11. Social Network and Support System

Given that no household will be physically relocated, the analysis on social networks and support system has been excluded from this baseline survey. Most community members will continue associating with community organizations in the area.

19

Page 32: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

3. LEGAL FRAMEWORK FOR LAND ACQUISITION AND COMPENSATION

The legal framework of a RAP describes all laws, decrees, policies and regulations relevant to the resettlement activities associated with a project. Using the IFC guidelines, this RAP identifies, reviews and abides by all laws of the host country that are applicable to land acquisition and involuntary resettlement including the scope of the power of eminent domain and the nature of compensation associated with it, both the procedures for assessing compensation values and the schedule for making compensation payments; the legal and administrative procedures applicable, including the appeals process and the normal time for such procedures; land titling and registration procedures; and laws and regulations relating to the agencies responsible for implementing resettlement and those related to land compensation, consolidation, land use, environment, water use, and social welfare.

The Constitution of the Republic of Uganda and the Land Act Cap 227 require that compensation is paid if a development project would damage structures or other property, or take private land. The same requirement is provided by World Bank policies and guidelines. World Bank’s Operational Policy 4.12 “Involuntary Resettlement" requires that displaced persons are compensated at full replacement cost and assisted during the relocation. While it is noted that no person shall be physically displaced by the project this section below, national laws and those of WB relevant to this RAP are discussed.

3.1. Relevant National LawsFor land take and displacement of people, specific attention is drawn to two Ugandan laws that are applicable to land tenure, compensation and resettlement, namely:

i) The Constitution of the Republic of Uganda, 1995ii) The Land Act, Cap 227

a) The Constitution of the Republic of Uganda (1995) creates for government and local authorities a statutory power of compulsory acquisition of land in public interest, and makes provision, inter alia, for the “prompt payment of fair and adequate compensation” prior to the taking of possession of any privately-owned property.

20

Page 33: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Such compensation is assessed in accordance with the valuation principles laid out in Section 78 of the Land Act (Cap 227), briefly outlined below:

i) The value for customary land is the open market value of unimproved land;

ii) The value of buildings on the land is taken at open market value for urban areas, and depreciated replacement cost for rural areas;

iii) The value of standing crops on the land is determined in accordance with the district compensation rates established by the respective District Land Board. Annual crops which could be harvested during the period of notice to vacate given to the landowner/ occupier of the land are excluded in determining compensation values;

iv) In addition to the total compensation assessed, there is a disturbance allowance paid of 15% or, if less than six months’ notice to vacate is given, 30% of the total sum assessed.

b) The Land Act principally addresses four issues namely; holding, control, management and land disputes. As regards tenure, the Act repeats, in Section 3, provisions of Article 237 of the Constitution which vests land ownership in the citizens of Uganda, to be held under customary, freehold, mailo or leasehold tenure systems. However, the Land Act provides for acquisition of land or rights to use land for public works.

Regarding control of land use, the Act reaffirms statutory power of compulsory acquisition conferred on the government and local authorities under articles 26 (2) and 237(2) (a) of the Constitution (Section 43). Since the Act does not repeal the Land Acquisition Act No. 14 of 1965, it is assumed that this legislation, meets requirements of Article 26(2) of the Constitution that requires a law to be in place for the payment of compensation and access to the courts. The Act also requires that landowners manage and utilize land in accordance with regulatory land use planning (Sections 44 and 46). Section 77(2) of the revised edition (2000) of the Land Act 1998 provides for a disturbance allowance on top of the computed compensation amount as shown below:

i) 30% of compensation amount if quit notice is given within 6 months.

ii) 15% of compensation amount if quit notice is given after 6 months.

21

Page 34: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

The above will be two key legal instruments under which compensation and resettlement will be implemented in this RAP but there are other relevant laws as discussed below.

3.2. Other Laws3.2.1. The Local Government Act (1997)

Local Government Act 1997 provides for the system of Local Governments, which is based on the District. Under Kole, Gulu and Oyam (the districts traversed by the power line) there are lower local governments and administrative units, namely Local Council I, II, II, IV and V. Chairperson of LC IV is the political head of a district while the Chief Administrative Officer (CAO) is its technical head. This system provides for elected Councils whereby chairmen nominate the executive committee of each council, functions of which include:a.) Initiating and formulating policy for approval by council;b.) Overseeing the implementation of Government and Council policies,

and monitoring and coordinating activities of Non-Government Organizations in the district; and

c.) Receiving and solving disputes forwarded to it from lower local governments.

3.2.2. Land Acquisition Act (1965)This Act makes provision for procedures and method of compulsory acquisition of land for public purposes whether for temporary or permanent use. The Minister responsible for land may authorize any person to enter upon the land, survey the land, dig or bore the subsoil or any other actions necessary for ascertaining whether the land is suitable for a given public purpose. However, compensation should be paid to any person who suffers damage as a result of such actions.The Land Acquisition Act stops at payment of compensation to affected people. In Uganda, it is not a legal requirement for a project to purchase alternative land for affected people. Once affected people are promptly and adequately compensated, the project proponent’s obligations stop at this extent and there is no legal requirement or provision that people should be moved or provided with alternative land. Therefore, in Ugandan legal context, once people are compensated, they are expected to vacate affected properties without further claim and in this lies a major contrast with WB requirements.

22

Page 35: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

3.2.3. Land Tenure Regimes and Transfer of LandArticle 237 of the Constitution, 1995, vests land ownership in citizens of Uganda and identifies four land tenure systems, namely: customary; freehold; mailo; and leasehold. The incidents of these systems are detailed under Section 4 of the Land Act (Cap 227). These tenure systems are provided relevant to the road project are outlined below:

3.2.3.1. Customary TenureThe customary tenure is the most dominant tenure arrangement in the Acholi region. Important attributes include the following:

The tenure is governed by rules generally accepted as binding and authoritative by the class of persons to which it applies. In other words customary regime is not governed by written law.

Land is owned in perpetuity. Customary occupants are occupant of former public land, and occupy

land by virtue of their customary rights; they have proprietary interest in the land and are entitled to certificates of customary ownership which may be acquired through application to the Parish Land Committee and eventual issuance by the District Land Board.

3.2.3.2. Freehold TenureA number of households have free hold tenure and this tenure has the following attributes:

This tenure derives its legality from the Constitution of Uganda and its incidents from the written law.

It involves the holding of land in perpetuity or for a period less than perpetuity fixed by a condition.

It enables the holder to exercise, subject to the law, full powers of ownership.

3.2.3.3. Leasehold TenureThis tenure system is:

Created either by contract or by operation of the law; A form under which the landlord of lessor grants the tenant or

lessee exclusive possession of the land, usually for a period defined and in return for a rent;

The tenant has security of tenure and a proprietary interest in the land.

23

Page 36: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Although only these latter forms of tenure are legally defined under the Land Act, the context of common law also recognizes the statute of “Licensee” or “Sharecroppers”, these terms having similar meanings in practice.Licensees are persons granted authority to use land within for agricultural production. Traditionally, such production would be limited to annual crops. Licensees have no legal security of tenure or any propriety right in the land. Their tenure is purely contractual.

3.2.3.4. Mailo TenureThe Mailo Land Tenure was not found in most of the villages that are covered by the project area

3.2.3.5. Right of Spouse and ChildrenThe rights of spouse and children are protected under the Constitution of Uganda and the Land Act (Cap 227). The consent of spouse and children must be acquired prior to any transaction by the head of household on land on which the family ordinarily resides. Section 40 of the Land Act, 1998 requires that no person shall:

a. Sell, exchange, transfer, pledge, mortgage or lease any land; or enter into any contract for the sale, exchange, transfer, pledge, mortgage or lease of any land;

b. Give away any land inter vivos, or enter into any transaction in respect of land: In the case of land on which the person ordinarily resides with his

or her spouse, and from which they derive their sustenance, except with the prior written consent of the spouse;

In the case of land on which the person ordinarily resides with his or her dependent children of majority age, except with the prior written consent of the dependent children of majority age;

In the case of land on which the person ordinarily resides with his or her dependent children below the majority age, except with the prior written consent of the Committee1;

In the case of land on which ordinarily reside orphans below majority age with interest in inheritance of the land, except with prior written consent of the Committee.

1 “Committees “ are defined under Section 65 of the Land Act ; they are Parish Land Committees.

24

Page 37: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

3.3. Valuation and Compensation of Assets Land take, compensation and relocation were the most frequent issues of debate encountered during consultations with PAP. Hence, at the core of this RAP is an aim to ensure project development embraces equitable and appropriate compensation approaches that meet Ugandan law and international requirements. Valuation and compensation are in accordance with rates set at district level for crops and “non-permanent” structures. The rates, which are enacted by District Land Boards, are established and updated at District level. Permanent structures are valued on a case-by-case basis. However, to meet World Bank requirements, in some cases, additional compensation measures will have to be identified by the Project in order to ensure that all households improve, or at least restore, their livelihoods and standards of living. Since no household will be moved by the project, this applies to income restoration where roadside businesses are temporarily disrupted or lost.

3.4. World Bank RequirementsWorld Bank’s Operational Policy 4.12 on involuntary resettlement requires that affected persons should be compensated at full replacement cost and assisted during relocation. There are some stark gaps between Uganda and WB resettlement requirements. For example, as earlier mentioned, a project proponents are not legally bound to neither procure alternative land nor provide relocation assistance to affected people if they provided fair financial compensation based on a legally accepted valuation process. In a number of situations, as shown in table above, WBG requirements are more favorable to affected persons than Ugandan law. REA is committed to undertaking appropriate compensation approaches to meet both Ugandan law and World Bank requirements such as;a.) Compensating for loss of income after affected persons are displaced.b.) Compensation for tenants who might not have legal land rights, but

have undertaken development or farming activities on affected land.c.) Wherever feasible and acceptable to affected persons, provide land-

for-land compensation. d.) Provide property owners with cash compensation at full replacement

cost.e.) Wherever appropriate, provide skills assistance to affected farmers in

areas such as improved crop and animal husbandry and records keeping.

However, regarding to project impacts identified in this RAP a gap analysis was undertaken so as to plan for unforeseen circumstances.

25

Page 38: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Table 1: analysis of gaps between World Bank Requirements and Ugandan requirements

Impact World Bank requirement

Uganda requirement Gaps and how these will be addressed

Loss of crops and trees

Compensation for crops, trees, and other fixed assets at full replacement cost and should be sufficient to enable affected people to restore their standard of living after resettlement.

Sharecroppers: Not entitled to compensation for land, entitled to compensation for crops.

Annual (seasonal) crops: No compensation since the 3 or 6-month notice is supposed to allow people to harvest their annual crops.

Perennial crops: Cash compensation based upon rates per square meter /bush/tree/plant established at District level plus disturbance allowance (15% or 30%). Rates are calculated as the one-year net agricultural income. Disturbance allowance is meant to compensate the re-establishment period for these crops.

Gap.

Crops and temporary structures affected have been documented in this report and will be compensated. A disturbance allowance will be paid to overcome any time delays.

For perennial crops, compensation will be based on estimated income lost for 3 years, so as to provide replacement value. A disturbance allowance will be paid as per Uganda law.

Loss of structures and other improvements (fences, etc) including communal structures

Compensation for structures should cover full replacement cost exclusive of depreciation and inclusive of all fees (such as construction permits and title charges) and labour costs.

Owners of “Permanent” Buildings:Valuation by valuer + disturbance allowance (15%). Valuation is based on depreciated market value.

Walls: classed as permanent structures, but value calculated on investment method.

Owners of “Non-permanent” Buildings:Cash compensation based upon rates per square meter established at District level plus disturbance allowance (15%).

Note: Rates are based on depreciated market value.

Tenants of structures: repayment of unused rent, and 6 months notice to vacate structure.

Fences: barbed wire fences valued by government rate,

Gap.

Where affected project will provide compensation based on replacement value. This will include the payment of government valuation rates and payment of a disturbance allowance. However, no permanent structures are likely to be affected.

26

Page 39: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

based on the investment method.

27

Page 40: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

4. INSTITUTIONAL RESPONSIBILITIESIn implementing this resettlement action plan, three key stakeholders have been identified including the Ministry of Local Government, Ministry of Lands, Housing and Urban Development and REA.

4.1. Rural Electrification AgencyREA has a lean management structure comprising of four departments responsible for Project Planning, Project Monitoring & Evaluation, Public Information & Outreach, and Finance & Administration, respectively. The Agency has, in addition, positions of Internal Audit and Legal Services (reporting to the Board). An Environmental Officer has recently been recruited to address and ensure compliance to social and environmental safeguards. Therefore in implementing this RAP, this official will oversee the implementation with support from the Project Planning, Monitoring and Evaluation Unit. However, given its lean structure, a consultant is likely to implement the RAP

4.2. Ministry of Local Government The staff at the district level and sub county level is mandated to ensure that there are minimal disruptions in communities. The District Environment Officers, Community Development Officers and the Sub County Chiefs have been actively involved in the planning processes for this RAP. This is in line with the national policies and guidelines of the Government of Uganda and is done to ensure equitable compensation and minimize social disruptions or negative effects on people’s livelihoods arising from construction of roads. Compensations assist those who have lost assets as a result of a development project to maintain their livelihood through income restoration. Local Councils are responsible for local policy matters, economic development, resolving local conflicts and providing orderly leadership and democratic practices at the grass roots level in their respective areas. The system has facilitated mass participation in government affairs and awakened the rural population to their rights of citizenship and obligations particularly regarding involvement in development programs and projects. In the project-affected area LC1s and LC3s are very active and directly interact with the affected population. These councils will thus be helpful during identification of rightful property owners and resolving compensation grievances.

4.3. Ministry of Lands, Housing and Urban DevelopmentThe Chief Government Valuer in the Valuation Division in the Ministry of Housing and Urban Development is responsible for approving the Valuation Roll. This demands fair and transparent compensation and as such all property valued are first inspected by the Chief Government Valuer. Chief

28

Page 41: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Government Valuer’s office is also involved in resolving public complaints that arise from land acquisition valuations and compensation payments.

4.4. Related Line MinistriesThe Government of Uganda recognizes energy as a key input in all sectors. The implementation of rural electrification therefore, necessitated a multi-sectoral approach. The project design includes specific components for key sectors namely; Health, Education, Water, Local Government, Private Sector, Community Based Organizations and Financial Institutions.

4.4.1. Ministry of Energy and Mineral DevelopmentThe Minister of Energy and Mineral Development is the principal political head responsible for Electricity policy formulation, planning and development. The Ministry prepares the Energy Policy and Strategic Plans. The Minister appoints the members of the Rural Electrification Board. In the RAP implementation, REA will be guided by the scrotal polices and guidelines regarding compensation for affected persons.

4.4.2. Ministry of Agriculture, Animal Industry and FisheriesConsidering that most of affected items are trees and crops, the The Ministry of Agriculture, Animal Industry & Fisheries would be brought on board to help support livelihood restoration strategies. The agricultural modernization program (PMA and NAADS) could be used as opportunities for increasing incomes by raising farm productivity through use of appropriate energy. Additionally, the Energy for Rural Transformation (ERT) agricultural support component has identified key projects where energy is a major constraint like coffee, tea and fish processing; horticulture production, processing and marketing; dairy and poultry production. It is also developing subsidy guidelines. Rural Electrification Agency (REA) should provide the leadership for policy guidelines to ensure effective coordination and harmonization of incentive measures for Rural Electrification development in the country.

4.4.3. Ministry of HealthThe Ministry of Health is involved in energy projects targeting improvement of health institutions, diagnostic services/laboratory equipment, cold storage for blood and vaccines, water supply pumping and heating, communication, health education and data management. The strategy is to use electricity and other renewable sources of energy to improve energy efficiency and management in the health sector. Once again, Rural Electrification Agency (REA) is a major player in establishing demand trends and patterns and ensuring coordinated efforts.

4.4.4. Ministry of Education and SportsThe Ministry of Education & Sports, through its Department of Education Planning (DEP), is interested in rural electrification to facilitate improvement of the quality of education in rural areas and develop energy policy

29

Page 42: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

guidelines for energy and Information Communication Technology (ICT) in post-primary education. A pilot phase is already underway in some 10 districts. Ministry of Education and Sports is, therefore, REA’s important client in terms of meeting the ministry’s expectations.

4.4.5. Ministry of Water, Lands and EnvironmentThe Ministry of Water, Lands & Environment’s Department of Water Development (DWD) aims to improve water supply services through adaptation of appropriate energy packages to water supply systems in small towns and rural growth centres. Fourteen towns are targeted under the pilot phase. Rural Electrification Agency (REA) has to encourage investment in small power projects to support realization of the vision of “water for all” within the shortest time possible.

4.4.6. Ministry of Works, Housing and CommunicationThe Ministry of Works, Housing & Communications is responsible for infrastructure policy and development including roads and communications, crucial for successful development of Rural Electrification. Ministry of Works, Housing & Communications also participates in the annual meetings of stakeholders.

4.4.7. Ministry of Finance, Planning and Economic DevelopmentThe Ministry of Finance, Planning & Economic Development is responsible for mobilization of development funds within the framework of the Poverty Eradication Action Plan (PEAP). Accordingly, the Poverty Monitoring and Analysis Unit in the ministry undertake regular Monitoring & Evaluation of Rural Electrification to assess the impact of the initiatives on the quality of life of the people. REA has to coordinate its Monitoring & Evaluation strategies and operations with the ministry.

4.5. Implementation ScheduleHaving assigned the different organizational responsibilities, this team anticipates that the RAP implementation is likely to cover a period of 13 months. The sequencing of activities bears in mind that some activities can be undertaken at the same time. Details are shown in the table below.

Table 2: RAP Implementation Schedule

Activities 1 2 3 4 5 6 7 8 9 10 11 12 13RAP ApprovalRAP DisclosureAgreement with EntitlementsCompensation Payment

Contractor Begins work,

Grievance Management

RAP MonitoringCompletion Audit

30

Page 43: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

31

Page 44: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

5. COMPENSATION FRAMEWORK

This section is a presentation of the compensation framework that include a description of the compensation guidelines established by the Government of Uganda; the methodology used to value losses, the proposed types and levels of compensation to be paid, the compensation and assistance eligibility criteria and how the compensation will be paid.

5.1. Key Principles

The key principles committed upon by REA in this RAP are the following:- Resettlement and compensation of Project-Affected People (PAP) will

be carried out in compliance with Ugandan legislation, IFC’s Performance Standard 5 and WB OP 4.12,

- All physically or economically displaced people will be offered an option between either a full resettlement package, including the provision of replacement residential land and a house, or cash compensation,

- Past experience in Uganda has shown that cash compensation, although very sought after by many household heads, could be detrimental in the medium term, to other household members, particularly the females and children; the Project will make every effort to promote resettlement rather than cash compensation, and this plan is designed accordingly,

- The economies in the affected villages are largely agro-based and that most households are just beginning to restore their livelihoods after a war. Hence compensation measures have taken into account this vulnerability context,

- The RAP will be implemented in a gender-sensitive manner: consents of female spouses will be sought, as provided by Ugandan regulations,

- Given that REA works through partnerships with lead Government Ministries, the Agency will help link PAP’ that will help them in restoring their affected livelihoods, and will provide transitional assistance as necessary as long as livelihoods are not restored to their previous level; specific livelihood restoration activities will target women,

- The RAP implementation and outcomes will be monitored and evaluated as part of a transparent process,

- PAPs be informed and consulted during the whole course of RAP development, implementation and evaluation.

5.1.1. Compensation and Resettlement Packages

Information from the socio-economic survey and census guided the selection of the most appropriate compensation packages while bearing in mind the scenarios below.

32

Page 45: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

5.1.1.1. The Affected Household Is Neither Physically Nor Economically Displaced

This means in practice that the remaining land is deemed economically viable and no residential building has to be removed. Such situations of rather benign impact apply to the overwhelming majority of affected households. In these cases, cash compensation will be offered and no resettlement option will be offered. Cash compensation will be at District Land Board rates for land, crops, and structures, with payment of disturbance allowance as per Ugandan regulations. An uplift will be added to this compensation to meet full replacement value requirements, as rates established by District Land Boards usually do not meet this requirement.

5.1.1.2. The Affected Household Is Physically Displaced but not Economically Affected

The construction of a replacement house will be offered wherever the residential building has to be removed or relocated nearby. Depending on situations, resettlement may involve the construction of a replacement house: - either on the remaining part of the plot if the remaining land holding in the neighborhood of the affected plot is deemed economically viable, or if the household’s livelihood is not based on agriculture, and if the affected household agrees to such a solution; in such cases, no replacement agricultural land will have to be provided and the household will simply continue to use the land they previously farmed or continue to engage in their non-agricultural activities, while dwelling in their new residence;- or on another resettlement plot if the remainder of the affected plot is not economically viable; in such situations, replacement agricultural land of similar potential will also have to be provided in the vicinity of the residential resettlement plot. Residential land will be provided to resettlers under secure tenure (either freehold or very long term leases), regardless of the previous regime of occupation. Agricultural land will be provided under the same regime of occupation as the land it replaces in the previous location.

5.1.1.3. The Affected Household Is Economically Displaced but not Physically Displaced

In such situations, the residential building of the affected household is not affected, but land take is such that their agricultural sustainability is jeopardized. In these situations, compensation will be provided through the provision of replacement agricultural land, with or without physical relocation of the homestead, depending on whether replacement land is available in the vicinity.

Given the nature of the development, situation 1 was selected as the most appropriate on the basis that although a 10 meter is needed to set up the way leave, the land owner can continue to utilize land under the way leave

33

Page 46: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

for crops but not trees. No structures will be demolished but rather if found that some will be affected, the line will be diverted. Furthermore, while trees are not allowed under the wayleaves, cash compensation is proposed for trees and crops affected. Hence, cash compensation will be at District Land Board rates for land, crops, and structures, with payment of disturbance allowance as per Ugandan regulations.

5.2. Eligibility

The basis of valuation for compensation lies in the constitution of the Republic of Uganda 1995 and the Land Act 1998

The Constitution of the Republic of Uganda, 1995, Article 26

a.) Every person has a right to own property either individually or in association with others.

b.) No person shall be compulsorily deprived of property or any interest in or right over property of any description except where the following conditions are satisfied

a. The taking of possession or acquisition is necessary for public use or in the interest of defense, public safety, public order, public morality or public health; and

b. The compulsory taking of possession or acquisition of property is made under a law, which makes provision

i. Prompt payment of fair and adequate compensation, prior to the taking of possession or acquisition of the property; and

ii. A right of access to a court of law by any person who has an interest or right over the property.

The Land Act, 1998:a.) The District Land Tribunal shall, in assessing compensation referred to

in paragraph (b) of subsection (1) of section 77 take into account the following:-

a. In the case of a customary owner, the value of land shall be the Market Value of the unimproved land;

b. The value of the buildings, which shall be taken at Market Value in urban areas and Depreciated Replacement Cost in rural areas;

c. The value of standing crops on the land, excluding annual crops which could be harvested during the period of notice given to the owner, tenant or licence.

b.) In addition to compensation assessed under this section, there shall be paid as a Disturbance Allowance of fifteen per cent or if less that six months’ notice to give vacant possession is given, thirty present of any sum assessed under subsection (1) of this section.

34

Page 47: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

c.) The rates set out in the list of District Compensation Rates referred to in paragraph (e) of subsection (1) of section 60 of this Act shall be used in determining the amount of compensation payable.

The crops, trees and other assets likely to be damaged affected recorded on compensation assessment were carefully analyzed and rates applied and computations made to determine the compensation payable to the PAPs. The handwritten information on the assessment form including the location of every individual PAP, entries of crops/trees and the rates applied were typed to produce schedules for the valuation report of the PAP study. These are the guiding principles and strategies used to establish what and who should qualify to be assessed for compensation payment:-

i. TORs emphasize physical identification, verification and valuation for compensation of properties to be affected/damaged by the construction of the power line and not acquisition of wayleaves.

ii. Valuation and assessment of properties to be based on approved area district compensation rates.

iii. Land and buildings to be left out except if considered adversely affected/damaged by the construction of the proposed power line.

iv. Trees in forests owned by government to be paid if claimed by individual complainants who have licenses/permits.

v. Complainants/Claimants to retain copy of the field assessment form.vi. Compensation Assessment to cover only crops and trees to be

destroyed/affected during the survey and construction of the power line

vii. Obtain consents from registered land owners and occupants in accordance with the law.

viii. Assess damage of destroyed crops/trees found in the road reserves such as fruit trees and perennial crops.

ix. Disturbance Allowance of 15% be allowed x. Prepare separate compensation assessment reports for the whole

proposed line route.

5.3. Rates Applied

Due to lack of Area Compensation Rates for newly created districts of Oyam and Kole, the consultant applied/used the current Area Compensation Rates of Gulu district to arrive at the compensation awards to the PAPs.

5.3.1. General Remarks and Assumptions

Inspection, survey and data capture of the affected property were carried out in the presence of the PAPs or their representatives, local leaders LCI officials of the villages and the neighbors. In urban centers where plots for building were genuinely affected by the proposed power line, assessment for

35

Page 48: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

compensation was done on full value. Assessment of crops and economic trees was carried out using Gulu District Area Compensation Rates. In commercial forest assessment was limited to 10 meters wayleaves corridor and more trees may be affected during the construction of the power line. A Statutory Disturbance Allowance of 15% as been allowed. Details of assessment/valuation of every claimant’s properties have been provided in this report.

5.3.2. Cut-off Date

The date of the valuation/assessment is November 2010

5.3.3. Valuation Certificate

There are Eighty Four (84) affected villages, in Kole, Oyam and Gulu Districts. The total number of claimants is 1143 and the assessed total compensation is Shs.95,675,252/- (Ninety Five Million Six Hundred Seventy Five Thousand Two Hundred Fifty Two Thousand Shillings Only). A summary of affected crops and trees as well as the numbers of affected persons are presented in the table below.

Item Name of Village Number of Affected Persons

Value of crops/Trees

15% Dist Allowance

Total Compensation Award

1. Corner Mowlem 13 490,125 73,519 563,6442. Te-Okole 11 979,000 146,850 1,125,8503. Acero ‘A’ 11 195,500 29,325 224,8254. Alyat ‘A’ 4 115,500 17,325 132,8255. Alyat ‘B’ 17 600,000 90,000 690,0006. Acero ‘B’ 9 743,000 111,450 854,4507. Acero ‘A’ 10 125,500 18,825 144,3258. Ajaya 24 1,304,000 195,600 1,499,6009. Aguga ‘A’ 16 338,000 50,700 388,700

10. Alidi ‘A’ 3 1,196,000 179,400 1,375,40011. Ongor 33 1,982,775 297,416 2,280,19112. Atyeto ‘A’ 7 366,500 54,975 421,47513. Komcankweri 8 4,127,000 619,050 4,746,05014. Pip 3 218,000 32,700 250,70015. Iyanyi ‘A’ 5 157,000 23,550 180,55016. Iyanyi ‘B’ 8 448,000 67,200 515,20017. Obinga Omii 8 607,851 91,178 699,02918. Adyeda 7 321,680 48,252 369,93219. Anyalo 17 757,400 113,610 871,010

36

Page 49: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

20. Odong Oyere 6 582,300 87,345 669,64521. Akaidebe ‘B’ 33 1,565,500 234,825 1,800,32522. Akaoidebe ‘A’ 3 1,798,000 269,700 2,067,70023. Alica 17 2,033,750 305,063 2,338,81324. Acan Koma 11 1,903,825 285,574 2,189,39925. Barmwony 14 1,782,500 267,375 2,049,87526. Barlye C 16 6,233,125 934,969 7,168,09427. Otwe 17 1,253,750 188,063 1,441,81328. Abongo Okere 8 1,467,326 220,099 1,687,42529. Aboloneno 43 1,374,000 206,100 1,580,10030. Awe Ikwo 36 1,650,500 247,575 1,898,07531. Dam Amalo 20 1,133,225 169,984 1,303,20932. Dam Apiny 10 879,000 131,850 1,010,85033. Lwala 8 746,500 111,975 858,47534. Alobo Lac 15 266,000 39,900 305,90035. Barcal 21 1,010,252 151,538 1,161,79036. Adak ‘B’ 12 515,500 77,325 592,82537. Adak ‘A’ 33 2,023,750 303,563 2,327,31338. Alyec 10 1,977,000 296,550 2,273,55039. Twocan Ikweri 4 137,000 20,550 157,55040. Cekwere 7 341,500 51,225 392,72541. Corner Atapara 14 1,588,138 238,221 1,826,35942. Abuli 9 450,825 67,624 518,44943. Awelo Makweri 28 1,919,525 287,929 2,207,45444. Oketo Bito 4 2,772,000 415,800 3,187,80045. Awaripiny 11 473,288 70,993 544,28146. Okarawok 17 1,038,500 155,775 1,194,27547. Arok 6 136,250 20,438 156,68848. Dog Abam 2 211,000 31,650 242,65049. Amukugungu 5 235,500 35,325 270,82550. Kamdini town 19 1,310,500 196,575 1,507,07551. Abanya ‘B’ 5 339,500 50,925 390,42552. Abanya ‘A’ 18 1,043,800 156,570 1,200,37053. Alyec 21 1,974,500 296,175 2,270,67554. Pukica 8 261,000 39,150 300,15055. Boroboro ‘B’ 9 366,500 54,975 421,47556. Boroboro ‘A’ 9 221,000 33,150 254,15057. Barolimo 6 132,000 19,800 151,80058. Aruku Long 6 352,000 52,800 404,80059. Abang Trading 17 565,163 84,774 649,937

37

Page 50: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

centre60. Abako 10 251,788 37,768 289,55661. Amwa trading

centre36 2,049,375 307,406 2,356,781

62. Amwa Headquarters

17 681,118 102,168 783,286

63. Waring 17 439,200 65,880 505,08064. Opati ‘B’ 2 224,000 33,600 257,60065. Opati ‘A’ 5 243,000 36,450 279,45066. Lango 14 395,250 59,288 454,53867. Bobi 12 1,081,875 162,281 1,244,15668. Teyao 3 68,650 10,298 78,94869. Omolo 13 925,188 138,778 1,063,96670. Alati ‘A’ 9 218,893 32,834 251,72771. Arak East 22 1,195,000 179,250 1,374,25072. Odyanyo 1 4,000 600 4,60073. Akuki East 29 1,053,804 158,071 1,211,87574. Alolekwe 3 167,113 25,067 192,18075. Ngutcati 19 910,926 136,639 1,047,56576. Coo Pe Bwone 2 2,089,875 313,481 2,403,35677. Centre ‘B’ 15 1,090,786 163,618 1,254,40478. Minakulu

trading centre40 1,321,500 198,225 1,519,725

79. Aromonyongo 22 3,740,500 561,075 4,301,57580. Idipo 20 1,011,875 151,781 1,163,65681. Obalowat 12 130,428 19,564 149,99282. Awii Mon Ward 14 683,903 102,585 786,48883. Kulu Otit 18 1,201,300 180,195 1,381,49584. Pato trading

centre16 878,401 131,760 1,010,161

1143 878401 12,479,381 3328136

38

Page 51: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

6. RESETTLEMENT ASSISTANCE AND RESTORATION OF LIVELIHOODS

Wherever possible, the Government of Uganda tries to avoid or minimize the displacement of people by exploring alternative project designs The Rural Electriction Agency guided by the Wayleaves Act, provides for realignment of power lines in order to minimize displacement of households or businesses. International guidelines like the IFC recommends that project sponsors undertake the following actions on behalf of all affected people, including members of the host communities in which displaced people will be settled:

6.1. Livelihood Restoration StrategiesThe livelihood restoration strategies proposed, aim at increasing participation of all stakeholders so that affected persons do not become more vulnerable. Hence this team has undertaken the following in order to ensure that affected persons are not significantly affected.

a.) The team informed affected people of their options and rights concerning resettlement;

b.) Provided technically and economically feasible options for resettlement based on consultation with affected people and assessment of resettlement alternatives;

c.)Given that no physical relocation is required, the team has not provided affected people with prompt and effective compensation at full replacement value for loss of assets due to project activities; but only compensation for crops;

d.) Since no physical relocation is necessary, disturbance allowance has been factored in the compensation package

e.) It is recommended therefore, that where necessary, affected persons be linked to other projects that can provide them with development assistance in addition to compensation for lost assets described above such as land preparation, agricultural inputs, and credit facilities and for training and employment opportunities.

6.2. Special Assistance for Women and Vulnerable Groups

The Resettlement Planning team identifies this as the most appropriate option for resettlement assistance and livelihood restoration given that although women form a small percentage of the affected households, the nature of tenure agreements in Northern Uganda that is customary in nature makes women more vulnerable to access to productive resources. As a result women tend to suffer more than men as a result of social changes. Therefore throughout the development of this RAP some of the immediate and practical measures are proposed to improve women’s adaptation to resettlement including:

39

Page 52: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

ensuring that land titles and compensation entitlements are issued in the name of both spouses;

reducing women’s workloads by providing, for example, standpipes, hand pumps, grinding mills, woodlots, fuel efficient stoves, ox carts, and plows by linking them to other projects like NUSAF, NAADS, LGSMD that are implementing such activities;

improving health services by providing training for village midwives, primary health care centers, child spacing/family planning counseling, clean water supply, and sanitation training by linking them to development partners in specific locations;

improving family services by providing immunizations; and Increasing incomes by setting up credit groups, skills training, and

access to markets.

40

Page 53: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

7. PUBLIC CONSULTATION, PARTICIPATION AND DEVELOPMENT PLANNING

Considering that the project has both environmental and social impacts, consultation was not a single conversation but a series of opportunities to create understanding about the project among those it has affected or and those it is likely to affect or interest, and to learn how these external parties view the project and its attendant risks, impacts, opportunities, and mitigation measures. Listening to stakeholder concerns and feedback gave the team valuable source of information that can improve project design and outcomes and help a company to identify and control external risks. It can also form the basis for future collaboration and partnerships. For stakeholders, a company’s consultation process is an opportunity to get information, as well as to educate company staff about the local context in which a project will take place, to raise issues and concerns, ask questions, and potentially help shape the project by making suggestions for the company to consider and respond to.

7.1. Community Perceptions of the Project

Generally, most communities that were consulted were happy with the proposed project. They noted that some of the villages were previously connected to power but the facilities got vandalized during the war. It was observed that most of the trading centres had the potential to grow like Corner Mowlem but this was hampered by no power in the area. Most communities wondered when the actual work would begin given the need for power in schools, health centres and other related infrastructure including the trading centre.

7.2. Community Concerns7.2.1. Impact on Property and Cultural Sites

Aside from the development, local leaders urged the team to compensate affected persons given that they were still restoring their livelihoods. Some community members were concerned about the impact of the power line on cemeteries and graveyards. However, they were informed that REA was going to use the road reserve so their areas will not be heavily affected. In addition to this community members raised concerns regarding payment for the crops destroyed, and were informed on the crops that would be identified during the census and valued. However, there was need for PAPs to cooperate with the team so that the identification process was undertaken in a participatory manner including affected persons and their leaders as witnesses. Furthermore, community members wondered whether there would be any impact on structures and whether property would be lost. The team allayed these fears noting that since most of the work would be done in the road reserve, it was unlikely that any structure would be

41

Page 54: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

affected. Another community member wondered what he would do if he wanted to build on his land that already has a pole. For safety concerns, he was advised to construct 15meters from the pole and for others who wished that a mango should not be cut down but rather pruned, they were advised that trees were not allowed under the wayleaves and would have to be compensated.

7.2.2. Compensation Framework

On the compensation framework, one community member wondered whether compensation rates were negotiable suggesting that previous rates that have been found to be unfavorable. However, members were informed that some items like trees and poles for fences are fixed based on the district compensation rates generated by District Land Board. The compensation rates are updated every year to address price changes and inflation issues. Others wondered what the method of compensation would be adopted. They are informed that the results from the socio-economic survey and census would serve as an input in the method of compensation though cash compensation has been found to be the preferred option by most PAPs.

7.2.3. Community Benefits

Other concerns were relating to access to the power including whether they would be given a transformer or whether they would get security lights in their areas. Furthermore, community members wondered whether community infrastructure close to the line would be connected to the power line will pass nearby their school (primary) will government give the primary school power. They were informed that after the installation, the facility would be given to the relevant authorities that would ably meet these needs. Community members wondered whether they will be given work to help in putting up the power line and were informed that should transmission come, employment opportunities would be availed where need. Members suggested that some of the opportunities that they should benefit from include cutting of trees, clearing of land and digging holes.

7.2.4. Community Health and SafetyRegarding community health and safety, one community member wondered whether if a pole fells and killed someone what would Government compensate the affected one. The team informed members that there are laws that address issues of workers’ compensation and these are planned for in the Environmental and Social Management Plan. The contractor is mandated to comply with provision of working gear that protects the lives of the workforce.

7.2.5. Grievance Mechanism42

Page 55: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

On grievances, one community member narrated that previous power line planners did not compensate them for the crops lost and wondered what procedure they should use in case they have complaints. Considering that there is no structure at the moment, they were advised to inform or report this to the RDC. However, a grievance mechanism has been recommended in this report to manage the grievance process.

8. GRIEVANCE MECHANISM

Regardless of its scale, involuntary resettlement inevitably gives rise to grievances among the affected population over issues ranging from rates of compensation and eligibility criteria to the location of resettlement sites and the quality of services at those sites. Timely redress of such grievances is vital to the satisfactory implementation of resettlement and to completion of the project on schedule. There is need to ensure that procedures are in place to allow affected people to lodge a complaint or a claim (including claims that derive from customary law and usage) without cost and with the assurance of a timely and satisfactory resolution of that complaint or claim.

In addition, the project may have to make special accommodations for women and members of vulnerable groups to ensure that they have equal access to grievance redress procedures. Such accommodation may include employment of women or members of vulnerable groups to facilitate the grievance redress process or to ensure that group representing the interests of women and other vulnerable groups take part in the process.

8.1. Mechanisms of Grievance and AppealsIn this regard, this resettlement planning team proposes that grievances are best redressed through project management, local government staff, political leadership and customary leaders. The traditional mechanisms for conflict resolution in the Acholi region have been widely used in providing psychosocial support for post conflict process management.

8.1.1. Reconciliatory ProcedureThis is an informal mechanism that will be applied to reach a resolution whenever minor contradictions and disagreements that may occur. It will include and oral or written appeal to the community based conflict resolution structure constituting of 1 member of the RAP implementation team (consultant), Sub County Chief/Community Development Officer, one Political Leader, 2 Elders and I religious leader. In order to build credibility of the commission, it is important that it includes different stakeholders that bring on board agreed principles and values that are attached to the Acholi Region. This approach is a mutual coordination mechanism to guarantee that mutual interests are served and disputes and contradictions are solved.

43

Page 56: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

8.1.2. Written Complaints to REAWhen the complainant is dissatisfied and feels that a member of the RAP implementation unit in the community has infringed upon his legal rights and interests or is dissatisfied with the decision made he or she can write to the REA to lodge a written complaint. This complaint should be addressed within two weeks of receipt.

8.1.3. Legal RedressIf the complainant feels dissatisfied with the administrative arbitration decision by the REA under the supervision of the Environmental and Social Safeguards officer, the complainant will then seek legal redress in courts of law. If the complainant is not satisfied with the decision made above, he or she may logde an appeal to the civil court and an independent will be set up to supervise and inspect the compensation process.

8.2. Public DisclosureProject Affected persons will be informed of this mechanism during the RAP disclosure for their input and refinement so that they can fully understand their rights for grievance and appeal. When grievance and appeal happen, the related institutions including Village committee, REA should keep good record about it, and make it available to the external monitor for inspection and verification.

44

Page 57: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

9. MONITORING, EVALUTION AND REPORTING FRAMEWORK

The purpose of monitoring and evaluation for this RAP will be to report about the effectiveness of the implementation of the RAP, covering resettlement, disbursement of compensation and effectiveness of public involvement, amongst others. Monitoring and purposeful evaluation will be key factors for successful resettlement activities. Monitoring will also entail evaluation of effectiveness of the grievance management process. The monitoring Framework proposed in this RAP includes a review of financial disbursements, compensation complaints and grievance redress, adherence to compensation payment schedule, support of vulnerable PAPs.

The Monitoring and Evaluation (M&E) mechanism provides a basis to assess overall success and effectiveness of various resettlement processes and measures. This mechanism is based on two components:

a) Internal monitoring – undertaken by the implementation unit / Monitoring Officer in the Planning Department of REA; and,

b) External evaluations –by development partners, community development officers and/or environmental focal persons at district level and other national stakeholders.

9.1. Internal monitoring processThe specific objectives and tasks of the internal monitoring process include: a.) identification of suitable indicators; b.) Measurement of indicators at appropriate intervals; c.) creation of a mechanism to analyze M&E data against a pre-resettlement baseline; and d.) Setting up a system to regularly respond to M&E findings by adapting existing measures or by modifying implementation processes. This monitoring process will be used to analyze progress and change at regular intervals. It shall be linked to the various stages of the RAP, as follows:-

9.1.1. During resettlement

During resettlement, M&E should focus on resettlement issues such as:

Number of families that have been compensated; Number of people who have acquired legal papers to new property, Number of business owners who have restored their businesses, Efficiency and effectiveness of grievance redress mechanism.

45

Page 58: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

9.1.2. After resettlement

Post resettlement monitoring should focus on rehabilitation issues and status on each of the measures should be assessed, for example: Success level of restoration of livelihoods Success level of restoration of assets Efficiency and effectiveness of grievance redress mechanism.

9.1.3. Key Activities and Responsibilities i) Set up a system: The RAP implementation team will provide a

monitoring form to be completed monthly by the M&E officer at each sub-county. The forms will cover aspects in Section 10.1.1 above. The information collected will be entered in an existing database at REA for further analysis and compilation into quarterly reports.

ii) Ongoing Monitoring: The M&E Officer for each location will be in-charge of regular monitoring of the implementation process. This will involve:

a) Feedback and inputs from the Implementation Officers.b) Reviewing of the resettlement database.c) Receiving reports from Grievance Officer and of the grievance

database.d) Receiving information from local representatives.e) Direct consultation with the resettled community at each

location.iii) Monthly reports: Consolidated monthly reports with key findings

from the on-going monitoring should be submitted to the implementation team and discussed every month and action points determined. This monthly progress review should aim to ensure that important issues are immediately rectified.

iv) Vulnerability assessment: It is essential that vulnerability is closely monitored in order to provide timely support to susceptible households. A vulnerability assessment shall occur as part of quarterly auditing of all households, and those households that are most vulnerable shall be prioritized for monthly auditing and targeted assistance. This may be undertaken by the implementation Officer. Key activities are:

a) Develop a set of criteria to identify vulnerable households (Note that this is intended to act as a guideline only and should be modified as appropriate).

b) Every three months visit vulnerable households to assess key needs/ issues (e.g. unemployment) with the rehabilitation process.

c) Develop a plan to address these issues in conjunction with the members of the household.

46

Page 59: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

9.2. External Evaluation ProcessIn addition to the internal monitoring process, external assessment of the resettlement process should be undertaken through an external evaluation agency appointed by REA. The external evaluation process will be informed by internal monitoring reports prepared by REA, and also through independent surveys and consultation conducted by the evaluation agency. The evaluation system will be based on process and outcome indicators.

9.2.1. Process IndicatorsProcess indicators measure effectiveness of processes (consultation, grievance) and inputs like people, equipment and materials and identify areas where improvements to existing processes are required. These may include the following:

Transparency of the implementation process. Adequacy of staff and capacity of the implementation agencies. Compliance of the resettlement process with Ugandan law and

World Bank standards. Effectiveness of the Grievance Process. Adequacy and effectiveness of public involvement. Effectiveness of the internal monitoring mechanism.

9.2.2. Outcome IndicatorsOutcome indicators will assess effectiveness of the resettlement and changes that have occurred to the communities’ standard of living. Key indicators are outlined in Table below.

Table 3: Monitoring indicators during resettlementCategory Indicator

Fund disbursement

Number of PAPs paid Amount of money disbursed Number of PAPs not paid in prescribed time (respective quarter) Reasons for not paying PAPs who are due for payment Projected disbursements in the next quarter

Restoration of and assets livelihoods

Number of PAPs who have benefited from related entrepreneurial training Number of businesses restored Reasons for not re-establishing businesses Number of NGOs that have been linked to PAPs

Public involvement

Number of community level meetings Participation rates of local leaders and community in resettlement process

disaggregated by genderGrievance management

Number of grievances received Number of grievances resolved (at what level) Number of complaints reported to other government oversight bodies and outcomes

including how grievance was resolved Number of grievances refereed to Uganda Courts of Law Number of outstanding grievances and reasons for not resolving them

Custody of legal documents

Land title deeds received Land title returned to owners

Resettlement of vulnerable PAPs

Number of vulnerable PAPs resettled Kind of special assistance provided

47

Page 60: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

9.2.3. Key activities and responsibilities REA will liaise with relevant ministries (MoLGD, MAAIF, MoFPED, Development partners) to undertake external evaluation of resettlement mid-term and at end of resettlement. These evaluations will focus on reviewing the process to-date and making necessary recommendations for modification to existing rehabilitation measures and other processes (e.g. grievance). This will allow modifications to the process and design packages that would help improve the effectiveness of REA in implementing the RAP. Considering that socio-economic baseline information is included in this report, a socio-economic survey at the external evaluation is necessary in order to assess the impact of the resettlement exercise.

9.3. RAP completion report During RAP implementation the consultant will submit to REA quarterly progress reports, after completion of resettlement, a final report will be submitted by REA prior to preparation of the project implementation report. The report shall indicate effectiveness of project implementation and disbursement of compensation payments, effectiveness of public consultations and socio-economic impacts of the road on roadside communities. This report will give overall assessment of the RAP process indicating activities undertaken, success of mitigation action ns and monitoring and well as useful lessons learnt.

9.4. Completion AuditA key aim of resettlement is to ensure compensation and other mitigation measures restore or enhance affected people’s quality of life and income levels. If affected PAPs quality of life can be demonstrated to have been restored, the resettlement and compensation process can be deemed “complete”. The purpose of Completion Audit will therefore be to establish whether REA implemented all activities needed to ensure compliance proposed resettlement commitments and applicable national and international policies. Specifically, the completion audit will be based on progress indicators and on outcome evaluation indicators and shall aim to assess whether compensation for all impacts of all affected people was undertaken; whether timely delivery of entitlements and compliance with Uganda’s and international resettlement requirements was undertaken; whether compensation frameworks were developed and implemented in a fair and transparent manner and adequate attention made to mitigating social impacts; and whether livelihoods have been restored.

48

Page 61: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

ANNEXES

49

Page 62: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

ANNEX 1: DETAILED LIST OF AFFECTED PERSONS

75KM AYER-KAMDINI AND BOBI-MINAKULU 33KV POWER LINE PROJECTVALUATION AND COMPENSATION ASSESSMENT REPORT

Item Name of Claimant Value of

crops/Trees

15% Dist Allowanc

e

Total Assessed

Compensation

ABOKE SUBCOUNTY CORNER MOWLEM

REA/AKBM/001 Lango Organic 30,000

4,500

34,500

REA/AKBM/002 Alele 50,000

7,500

57,500

REA/AKBM/003 Ekora William 97,000

14,550

111,550

REA/AKBM/004 Lokori Tom 59,375 8,906

68,281

REA/AKBM/005 Christine Lukeri 13,000

1,950

14,950

REA/AKBM/006 Obong Peter 71,875 10,781

82,656

REA/AKBM/007 Obong Peter 4,500

675

5,175

REA/AKBM/008 Okecha Sam 21,250

3,188

24,438

REA/AKBM/009 Evlyne Okecha Sam 1,125

169

1,294

REA/AKBM/010 Olugu Joel 2,000

300

2,300

REA/AKBM/011 Ogola Ray 25,000

3,750

28,750

REA/AKBM/012 Judith Okello Patrick 108,000

16,200

124,200

REA/AKBM/013 Olwata Lawrence 7,000

1,050

8,050

TE-OKOLEREA/AKBM/014 Omara Caroline

164,000 24,60

0 188,60

0

REA/AKBM/015 Ogwal Sam 9,000

1,350

10,350

REA/AKBM/016 Sylfo Akello 7,000

1,050

8,050

50

Page 63: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/017 Acen Stella 281,000

42,150

323,150

REA/AKBM/018 Awino Mary 6,000

900

6,900

REA/AKBM/019 Joseph Opio Odongo 60,500

9,075

69,575

REA/AKBM/020 Opio Jimmy 80,000

12,000

92,000

REA/AKBM/021 Ajok Hellen 235,000

35,250

270,250

REA/AKBM/022 Onapa Parick 91,000

13,650

104,650

REA/AKBM/023 Okello Lawrence 20,500

3,075

23,575

REA/AKBM/024 Ekwaro Ambrose 25,000

3,750

28,750

ACERO 'A'REA/AKBM/025 Omara Jasper

6,000 90

0 6,90

0

REA/AKBM/026 Omara Francis 4,000

600

4,600

REA/AKBM/027 Phobe Okello Dick 5,000

750

5,750

REA/AKBM/028 Francis Ogwang 1,000

150

1,150

REA/AKBM/029 Okello Fred 50,000

7,500

57,500

REA/AKBM/030 Ocen James 25,000

3,750

28,750

REA/AKBM/031 Okello T. and Topachu J.

50,000

7,500

57,500

REA/AKBM/032 Topachu James 12,500

1,875

14,375

REA/AKBM/033 Omara David 7,000

1,050

8,050

REA/AKBM/034 Ongom Tabu 10,000

1,500

11,500

REA/AKBM/035 Owaca J. and kello T. 25,000

3,750

28,750

ALYAT 'A'REA/AKBM/036 Ogwang Richard A.

25,000 3,75

0 28,75

0

51

Page 64: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/037 Omara Francis 10,000

1,500

11,500

REA/AKBM/038 Opio William Nickson 39,000

5,850

44,850

REA/AKBM/039 Omara Jimmy Angulu 41,500

6,225

47,725

ALYAT 'B'REA/AKBM/040 Oyar Vicent

11,500 1,72

5 13,22

5

REA/AKBM/041 Agony Vento 10,000

1,500

11,500

REA/AKBM/042 Ocen Joseph 1,000

150

1,150

REA/AKBM/043 Late Akedo N. c/o Okello Martin

1,000

150

1,150

REA/AKBM/044 Opio Selestino 94,000

14,100

108,100

REA/AKBM/045 Oming Charlse 3,000

450

3,450

REA/AKBM/046 Namm Isaac 41,000

6,150

47,150

REA/AKBM/047 Okullo Richard 95,000

14,250

109,250

REA/AKBM/048 Ogwang Nelson 90,500

13,575

104,075

REA/AKBM/049 Rose Engole 6,000

900

6,900

REA/AKBM/050 Otyang Denis 51,000

7,650

58,650

REA/AKBM/051 Omodi Yubentino 25,500

3,825

29,325

REA/AKBM/052 Ebong Patrick 85,000

12,750

97,750

REA/AKBM/053 Docus Omara 57,000

8,550

65,550

REA/AKBM/054 Ocato John 4,000

600

4,600

REA/AKBM/055 Okello Lawrence 2,000

300

2,300

REA/AKBM/056 Ocen Leonard 22,500

3,375

25,875

LORO SUBCOUNTY52

Page 65: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

ACERO 'B'REA/AKBM/057 Odong Alex

36,000 5,40

0 41,40

0

REA/AKBM/058 Opat Jimmy 55,000

8,250

63,250

REA/AKBM/059 Okullo Geofrey 47,000

7,050

54,050

REA/AKBM/060 Okello Kizito 21,000

3,150

24,150

REA/AKBM/061 Otur Robert 65,000

9,750

74,750

REA/AKBM/062 Ogwang Martin 95,000

14,250

109,250

REA/AKBM/063 Odung Geofrey 313,000

46,950

359,950

REA/AKBM/064 Iyit Francis 51,000

7,650

58,650

REA/AKBM/065 Oginya Odinga 60,000

9,000

69,000

ACERO 'A'REA/AKBM/066 Arit John

1,000 15

0 1,15

0

REA/AKBM/067 Ocen Tom 19,000

2,850

21,850

REA/AKBM/068 Ogwang Robert 4,000

600

4,600

REA/AKBM/069 Ayela Robert 14,000

2,100

16,100

REA/AKBM/070 Okello David 38,000

5,700

43,700

REA/AKBM/071 Akullu Milly 8,000

1,200

9,200

REA/AKBM/072 Ekol Moris 4,500

675

5,175

REA/AKBM/073 Tile Francis 4,500

675

5,175

REA/AKBM/074 Arit John 1,000

150

1,150

REA/AKBM/075 Obua Alfred 31,500

4,725

36,225

53

Page 66: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

AJAYAREA/AKBM/076 Otim George

7,000 1,05

0 8,05

0

REA/AKBM/077 Lenga Richard 43,500

6,525

50,025

REA/AKBM/078 Lenga Evaster 53,000

7,950

60,950

REA/AKBM/079 Next to Ocen and Okot 65,000

9,750

74,750

REA/AKBM/080 Okot Y.Y. 138,000

20,700

158,700

REA/AKBM/081 Ogwang Bosco 40,000

6,000

46,000

REA/AKBM/082 Ayo Denis 25,000

3,750

28,750

REA/AKBM/083 Opio Moses 20,000

3,000

23,000

REA/AKBM/084 Hellen Opio 60,000

9,000

69,000

REA/AKBM/085 Ogwang David 5,000

750

5,750

REA/AKBM/086 Ocen Patrick 10,000

1,500

11,500

REA/AKBM/087 Owuni Richard 40,000

6,000

46,000

REA/AKBM/088 Opio Albino 40,000

6,000

46,000

REA/AKBM/089 Florence Oyat 20,000

3,000

23,000

REA/AKBM/090 Ocen Cipriano 30,000

4,500

34,500

REA/AKBM/091 Obua Denis 25,000

3,750

28,750

REA/AKBM/092 Obote Lawrence 180,000

27,000

207,000

REA/AKBM/093 Odongo Charlse 20,000

3,000

23,000

REA/AKBM/094 Rose Okello 36,000

5,400

41,400

REA/AKBM/095 Gira John 10,000

1,500

11,500

54

Page 67: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/096 Okeny Vicent 73,000

10,950

83,950

REA/AKBM/097 Ojok Benson 147,000

22,050

169,050

REA/AKBM/098 Okello Alice 105,500

15,825

121,325

REA/AKBM/099 Lucy Olet 111,000

16,650

127,650

AGUGA 'A'REA/AKBM/100 Owiny Tito

10,000 1,50

0 11,50

0

REA/AKBM/101 Omara Kosia 50,000

7,500

57,500

REA/AKBM/102 Munu Denis Kalulu 1,000

150

1,150

REA/AKBM/103 Odyek Jonan 7,000

1,050

8,050

REA/AKBM/104 Okullo James 5,000

750

5,750

REA/AKBM/105 Ananga James 3,000

450

3,450

REA/AKBM/106 Omara Denis 5,000

750

5,750

REA/AKBM/107 Y.B Okello 25,000

3,750

28,750

REA/AKBM/108 Ekii Newton 29,000

4,350

33,350

REA/AKBM/109 Ongom Engenio 4,000

600

4,600

REA/AKBM/110 Okoya Jasper 5,000

750

5,750

REA/AKBM/111 Obong George 30,000

4,500

34,500

REA/AKBM/112 Okullo David 85,000

12,750

97,750

REA/AKBM/113 Ocen George 55,000

8,250

63,250

REA/AKBM/114 Okuku Anthony 14,000

2,100

16,100

REA/AKBM/115 Etenyu Emmanuel 10,000

1,500

11,500

55

Page 68: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

ALIDI 'A'REA/AKBM/116 Alidi Primary School

1,176,000 176,40

0 1,352,40

0

REA/AKBM/117 Odongo Bonny 10,000

1,500

11,500

REA/AKBM/118 Omara Bosco 10,000

1,500

11,500

ONGOR

REA/AKBM/119 Okot Peter 44,000

6,600

50,600

REA/AKBM/120 Ojok William 342,565 51,385

393,950

REA/AKBM/121 Amuku Ambrose 61,550

9,233

70,783

REA/AKBM/122 Geofrey Ojok Newton 13,000

1,950

14,950

REA/AKBM/123 Oyar Martin 150,460

22,569

173,029

REA/AKBM/124 Rezabwani Otyang 135,700

20,355

156,055

REA/AKBM/125 Bongo Daniel 253,000

37,950

290,950

REA/AKBM/126 Grace Odyek 123,500

18,525

142,025

REA/AKBM/127 Okoo Alfred 21,000

3,150

24,150

REA/AKBM/128 Amuku Patrick 15,500

2,325

17,825

REA/AKBM/129 Omara Patrick 43,500

6,525

50,025

REA/AKBM/130 Elen Benson 10,000

1,500

11,500

REA/AKBM/131 Obong John 106,000

15,900

121,900

REA/AKBM/132 Abur Sylvia Otyang 106,000

15,900

121,900

REA/AKBM/133 Ojede Benson 46,000

6,900

52,900

REA/AKBM/134 Omara Jimmy 48,000

7,200

55,200

56

Page 69: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/135 Olila Charlse 5,000

750

5,750

REA/AKBM/136 Opio Nickson 10,000

1,500

11,500

REA/AKBM/137 Okello Alfred 66,000

9,900

75,900

REA/AKBM/138 Ojede Milton 12,000

1,800

13,800

REA/AKBM/139 Okello Vicent 2,000

300

2,300

REA/AKBM/140 Odongo Jonan 60,000

9,000

69,000

REA/AKBM/141 Okullo David 50,000

7,500

57,500

REA/AKBM/142 Awany Paspiko 50,000

7,500

57,500

REA/AKBM/143 Owiny John Alfonse 62,000

9,300

71,300

REA/AKBM/144 Okello Vicent 20,000

3,000

23,000

REA/AKBM/145 Okello Wilfred 32,000

4,800

36,800

REA/AKBM/146 Doi (Prison Officer) 2,000

300

2,300

REA/AKBM/147 Opio (Builder) 1,000

150

1,150

REA/AKBM/148 Luzino Opiny 40,000

6,000

46,000

REA/AKBM/149 Odong Quintino 41,000

6,150

47,150

REA/AKBM/150 Ogwal 2,000

300

2,300

REA/AKBM/151 Odyek Tony C/o Okori Sam

8,000

1,200

9,200

ATYETO 'A'

REA/AKBM/152 Omara Emmy 10,000

1,500

11,500

REA/AKBM/153 Otyang George 10,000

1,500

11,500

57

Page 70: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/154 Ongol Moses 16,000

2,400

18,400

REA/AKBM/155 Opio Tony 20,000

3,000

23,000

REA/AKBM/156 Ongol Moses 150,000

22,500

172,500

REA/AKBM/157 Okello Peter Odyek 70,500

10,575

81,075

REA/AKBM/158 Geofrey Okello Opio 90,000

13,500

103,500

KOMCANIKWERIREA/AKBM/159 Omor Charlse

3,019,000 452,85

0 3,471,85

0

REA/AKBM/160 Oboo Emmanuel 15,000

2,250

17,250

REA/AKBM/161 Aida Okedi 8,000

1,200

9,200

REA/AKBM/162 Omor Charlse 978,000

146,700

1,124,700

REA/AKBM/163 Okeng Moses 5,000

750

5,750

REA/AKBM/164 Oleke Dickens 51,000

7,650

58,650

REA/AKBM/165 Omara Augustine 50,000

7,500

57,500

REA/AKBM/166 Bua Bosco 1,000

150

1,150

PIP

REA/AKBM/167 Odongo Denis 25,000

3,750

28,750

REA/AKBM/168 Iyanyi Primary School 141,000

21,150

162,150

REA/AKBM/169 Rev. Omara Francis 52,000

7,800

59,800

IYANYI 'A'REA/AKBM/170 Opio Denis

40,000 6,00

0 46,00

0

REA/AKBM/171 Okello Moris 2,000

300

2,300

58

Page 71: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/172 Abule Francis 20,000

3,000

23,000

REA/AKBM/173 Ogwal James 25,000

3,750

28,750

REA/AKBM/174 Ogwal J.B. 70,000

10,500

80,500

IYANYI 'B'

REA/AKBM/175 Odongo Bosco 20,000

3,000

23,000

REA/AKBM/176 Okello Peter 40,000

6,000

46,000

REA/AKBM/177 Olila Francis 17,000

2,550

19,550

REA/AKBM/178 Ameny Richard 12,000

1,800

13,800

REA/AKBM/179 Olobo George 32,000

4,800

36,800

REA/AKBM/180 Anam Silvesto 30,000

4,500

34,500

REA/AKBM/181 Obua Denis 197,000

29,550

226,550

REA/AKBM/182 Okello Denis 100,000

15,000

115,000

OBANGA OMII

REA/AKBM/183 Ngole William 4,000

600

4,600

REA/AKBM/184 Ogal Jonan 22,000

3,300

25,300

REA/AKBM/185 Ongom Beatrice 58,538 8,781

67,319

REA/AKBM/186 Omara Nickson 54,563 8,184

62,747

REA/AKBM/187 Okello Nelson 78,000

11,700

89,700

REA/AKBM/188 Odyek Geofrey 3,000

450

3,450

REA/AKBM/189 Ocen Nickodemus 64,750

9,713

74,463

REA/AKBM/190 Ongom Peter Jenty 323,000

48,450

371,450

59

Page 72: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

ADYEDAREA/AKBM/191 Corina Odyek

156,000 23,40

0 179,40

0

REA/AKBM/192 Ogwang Nelson 88,680

13,302

101,982

REA/AKBM/193 Ogwal Christopher 11,000

1,650

12,650

REA/AKBM/194 Odongo Alex 10,000

1,500

11,500

REA/AKBM/195 Ogwal Emmanuel 4,000

600

4,600

REA/AKBM/196 Okello Charlse 10,000

1,500

11,500

REA/AKBM/197 Okello Alfred 42,000

6,300

48,300

ANYALO

REA/AKBM/198 Olugu James 60,000

9,000

69,000

REA/AKBM/199 Onapa Omara 7,000

1,050

8,050

REA/AKBM/200 Ongom Stephen 76,000

11,400

87,400

REA/AKBM/201 Otim Matiya 31,000

4,650

35,650

REA/AKBM/202 Agen John 90,000

13,500

103,500

REA/AKBM/203 Akaki Simon 7,000

1,050

8,050

REA/AKBM/204 Ogwang Moses 10,000

1,500

11,500

REA/AKBM/205 Next to Ogwang Moses 30,000

4,500

34,500

REA/AKBM/206 Obong William 60,000

9,000

69,000

REA/AKBM/207 Moro Jasper 20,000

3,000

23,000

REA/AKBM/208 Lama George 87,000

13,050

100,050

REA/AKBM/209 Okello John 10,000

1,500

11,500

60

Page 73: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/210 Odongo Dick 25,000

3,750

28,750

REA/AKBM/211 Igach Godfrey 40,000

6,000

46,000

REA/AKBM/212 Omara Godfrey 10,000

1,500

11,500

REA/AKBM/213 Olugu James 124,400

18,660

143,060

REA/AKBM/214 Alip Joseph 70,000

10,500

80,500

ODONG OYERE

REA/AKBM/215 Farmer Field School 76,800

11,520

88,320

REA/AKBM/216 Olobo Geofrey 210,500

31,575

242,075

REA/AKBM/217 Erike Willy 10,000

1,500

11,500

REA/AKBM/218 Adenge Alterio 185,000

27,750

212,750

REA/AKBM/219 Odyeny Richard 7,500

1,125

8,625

REA/AKBM/220 Lucy Okello 92,500

13,875

106,375

AKAIDEBE 'B'REA/AKBM/221 Ouma Richard

70,000 10,50

0 80,50

0

REA/AKBM/222 Ekwaro Robert 120,000

18,000

138,000

REA/AKBM/223 Obua Peter 7,000

1,050

8,050

REA/AKBM/224 Okullo Alfred 14,000

2,100

16,100

REA/AKBM/225 Okwir Oscar 60,000

9,000

69,000

REA/AKBM/226 Apeuyo Tom 25,000

3,750

28,750

REA/AKBM/227 Okori Patrick 82,000

12,300

94,300

REA/AKBM/228 Okot James Wacha 5,000

750

5,750

61

Page 74: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/229 Tyan Peter 8,000

1,200

9,200

REA/AKBM/230 Owiny Anthony 9,000

1,350

10,350

REA/AKBM/231 Obote Benson 30,000

4,500

34,500

REA/AKBM/232 Dunyiro Jasper 23,000

3,450

26,450

REA/AKBM/233 Ayoo Martin 31,500

4,725

36,225

REA/AKBM/234 Santa Okwir 60,000

9,000

69,000

REA/AKBM/235 Odongo Charlse 100,000

15,000

115,000

REA/AKBM/236 Odai David 20,000

3,000

23,000

REA/AKBM/237 Obonyo T.G 150,000

22,500

172,500

REA/AKBM/238 Rose Obuga 60,000

9,000

69,000

REA/AKBM/239 Ongiro George 20,000

3,000

23,000

REA/AKBM/240 Ouma Richard 65,000

9,750

74,750

REA/AKBM/241 Olobo Edward 5,000

750

5,750

REA/AKBM/242 Ebabu Joe 10,500

1,575

12,075

REA/AKBM/243 Angulu Bonny 2,500

375

2,875

REA/AKBM/244 Ogwok 46,000

6,900

52,900

REA/AKBM/245 Eagle Wings Academy 65,200

9,780

74,980

REA/AKBM/246 Omach James 20,000

3,000

23,000

REA/AKBM/247 Ogwal Patrick 20,000

3,000

23,000

REA/AKBM/248 Otak Charlse 10,000

1,500

11,500

REA/AKBM/249 Otim James 20,000

3,000

23,000

62

Page 75: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/250 Okello Tablique 15,000

2,250

17,250

REA/AKBM/251 Loro Sub County Head Quarters

174,800

26,220

201,020

REA/AKBM/252 Loro Health Centre II 40,000

6,000

46,000

REA/AKBM/253 Loro S.S.S 177,000

26,550

203,550

AKAOIDEBE 'A'

REA/AKBM/254 St. Peters Church of Uganda

50,000

7,500

57,500

REA/AKBM/255 Loro Primary School 1,152,000

172,800

1,324,800

REA/AKBM/256 Loro Core Primary Teachers College

596,000

89,400

685,400

ALICAREA/AKBM/257 Ajwang Milly

25,500 3,82

5 29,32

5

REA/AKBM/258 Okullo Benson 35,000

5,250

40,250

REA/AKBM/259 Ongar Charlse 10,000

1,500

11,500

REA/AKBM/260 Aboko John 75,000

11,250

86,250

REA/AKBM/261 Okello Washington 10,000

1,500

11,500

REA/AKBM/262 Ojok Alfred 10,000

1,500

11,500

REA/AKBM/263 Otim Alele 12,000

1,800

13,800

REA/AKBM/264 Olwata okullo Richard 883,750 132,563

1,016,313

REA/AKBM/265 Ongwen Rashid 194,000

29,100

223,100

REA/AKBM/266 Scovia Tuma 67,000

10,050

77,050

REA/AKBM/267 Ogwal Inasimu 30,000

4,500

34,500

REA/AKBM/268 Lucy Atoma 27,600

4,140

31,740

63

Page 76: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/269 Wacha Alfred 14,000

2,100

16,100

REA/AKBM/270 Apio Molly 14,000

2,100

16,100

REA/AKBM/271 Ana Akullo 396,900

59,535

456,435

REA/AKBM/272 Pastor Ongiru 209,000

31,350

240,350

REA/AKBM/273 Okech Esakali 20,000

3,000

23,000

ACAN KOMA

REA/AKBM/274 Loro Model Primary School

44,000

6,600

50,600

REA/AKBM/275 Odwe James 64,000

9,600

73,600

REA/AKBM/276 Agnes Ogwal 123,500

18,525

142,025

REA/AKBM/277 Apio Alice 204,025

30,604

234,629

REA/AKBM/278 Olak Dickson 45,000

6,750

51,750

REA/AKBM/279 Obong Sam 955,000

143,250

1,098,250

REA/AKBM/280 Opio Richard 24,500

3,675

28,175

REA/AKBM/281 Owacha Geofrey 170,000

25,500

195,500

REA/AKBM/282 Farmer Field School 118,800

17,820

136,620

REA/AKBM/283 Benson Opio 97,000

14,550

111,550

REA/AKBM/284 Ocen Alfred 58,000

8,700

66,700

BARMWONYREA/AKBM/285 Ogwal Simon

87,000 13,05

0 100,05

0

REA/AKBM/286 Ebong John 80,000

12,000

92,000

REA/AKBM/287 Obong George 70,000

10,500

80,500

64

Page 77: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/288 Opio Bosco 50,000

7,500

57,500

REA/AKBM/289 Community Land Barmwony

20,000

3,000

23,000

REA/AKBM/290 Obura Sam 158,000

23,700

181,700

REA/AKBM/291 Okwir Charlse 62,500

9,375

71,875

REA/AKBM/292 Ogwal Richard Odur 8,000

1,200

9,200

REA/AKBM/293 Apollo Enesta 27,500

4,125

31,625

REA/AKBM/294 Odora Jimmy 148,000

22,200

170,200

REA/AKBM/295 Acai Francis 116,000

17,400

133,400

REA/AKBM/296 Calvin Erem 71,000

10,650

81,650

REA/AKBM/297 Otim Patrick 658,500

98,775

757,275

REA/AKBM/298 Alobo Dickens 226,000

33,900

259,900

BARLYE CREA/AKBM/299 Ayo Jasper

318,000 47,70

0 365,70

0

REA/AKBM/300 Olweny Geofrey 920,250

138,038

1,058,288

REA/AKBM/301 Ducu Gabriel 52,500

7,875

60,375

REA/AKBM/302 Ducu Emmanuel 198,750 29,813

228,563

REA/AKBM/303 Oyite Ambrose 26,250

3,938

30,188

REA/AKBM/304 Okwiji Michael 4,000

600

4,600

REA/AKBM/305 Emaro Sam 253,750 38,063

291,813

REA/AKBM/306 Ongom Israel 167,000

25,050

192,050

REA/AKBM/307 Esau Omara 345,000

51,750

396,750

65

Page 78: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/308 Ongenga Jacob 433,000

64,950

497,950

REA/AKBM/309 Levi Niye 1,990,000

298,500

2,288,500

REA/AKBM/310 Ogwal Peter 25,000

3,750

28,750

REA/AKBM/311 Opara John 723,625 108,544

832,169

REA/AKBM/312 Okullo Peter Arach 698,500

104,775

803,275

REA/AKBM/313 Milly Okii 30,000

4,500

34,500

REA/AKBM/314 Okullo Peter Arach 47,500

7,125

54,625

ASABA SUBCOUNTY

OTWE

REA/AKBM/315 Ongwech David 227,000

34,050

261,050

REA/AKBM/316 Kiiza Washington 10,000

1,500

11,500

REA/AKBM/317 Okene Alex 50,000

7,500

57,500

REA/AKBM/318 Ojok Robert 12,000

1,800

13,800

REA/AKBM/319 Aporo George 20,000

3,000

23,000

REA/AKBM/320 Erume John 107,000

16,050

123,050

REA/AKBM/321 Apwony Ongom Denis 15,000

2,250

17,250

REA/AKBM/322 Okwe Richard 50,000

7,500

57,500

REA/AKBM/323 Omara Joe 50,000

7,500

57,500

REA/AKBM/324 Amony Nelson 70,250

10,538

80,788

REA/AKBM/325 Oyengo David 26,500

3,975

30,475

REA/AKBM/326 Etuk John 71,000

10,650

81,650

66

Page 79: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/327 Arach Lawrence 50,000

7,500

57,500

REA/AKBM/328 Ojuko Quinto 50,000

7,500

57,500

REA/AKBM/329 Oyengo David 100,000

15,000

115,000

REA/AKBM/330 Apul Isaac 150,000

22,500

172,500

REA/AKBM/331 Abeja Charlse 195,000

29,250

224,250

LORO SUBCOUNTY ABONGO OKERE

REA/AKBM/332 Ogwang Leo 175,000

26,250

201,250

REA/AKBM/333 Molly Atim 50,370

7,556

57,926

REA/AKBM/334 Elen Tony 28,000

4,200

32,200

REA/AKBM/335 Odong Felix 247,375 37,106

284,481

REA/AKBM/336 Ongom Patrick 574,000

86,100

660,100

REA/AKBM/337 Odongo David 191,625 28,744

220,369

REA/AKBM/338 Otim Bob 106,456 15,968

122,424

REA/AKBM/339 Okullo Franco 94,500

14,175

108,675

ABOLONENOREA/AKBM/340 Okori Nelson

94,000 14,10

0 108100

REA/AKBM/341 Next to Okori Nelson 30,000

4,500 34500

REA/AKBM/342 Ekii Michael 9,000

1,350 10350

REA/AKBM/343 Ekwaro Peter 20,000

3,000 23000

REA/AKBM/344 Odila Richard 24,000

3,600 27600

67

Page 80: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/345 Acak Joel 10,000

1,500 11500

REA/AKBM/346 Omara Nelson 77,500

11,625 89125

REA/AKBM/347 Omara Thomas 10,000

1,500

11,500

REA/AKBM/348 Next to Omara Thomas 25,000

3,750

28,750

REA/AKBM/349 Ayo Francis 43,000

6,450

49,450

REA/AKBM/350 Opio Alex 11,000

1,650

12,650

REA/AKBM/351 Opio Edward 7,000

1,050

8,050

REA/AKBM/352 Ayo Yoventino 10,000

1,500

11,500

REA/AKBM/353 Adong Lucy 8,000

1,200

9,200

REA/AKBM/354 Ana Okao 27,500

4,125

31,625

REA/AKBM/355 Opio Lawrence 10,000

1,500

11,500

REA/AKBM/356 Next to Opio Lawrence 6,000

900

6,900

REA/AKBM/357 Simao Engole 9,000

1,350

10,350

REA/AKBM/358 Ayo Yoventino 76,000

11,400

87,400

REA/AKBM/359 Obura Geofrey 1,000

150

1,150

REA/AKBM/360 Next to Obura Geofrey

20,000

3,000

23,000

REA/AKBM/361 Okullo (1) 5,000

750

5,750

REA/AKBM/362 Ogwang Nelson 30,000

4,500

34,500

REA/AKBM/363 Okullo (2) 156,000

23,400

179,400

REA/AKBM/364 Oloro Solomon 45,000

6,750

51,750

REA/AKBM/365 Ajwang Milly 12,000

1,800

13,800

68

Page 81: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/366 Ojede Moses 40,000

6,000

46,000

REA/AKBM/367 Okot Christopher 32,000

4,800

36,800

REA/AKBM/368 Opio Solomon 13,000

1,950

14,950

REA/AKBM/369 Ocen William 6,000

900

6,900

REA/AKBM/370 Ongom Sam 36,000

5,400

41,400

REA/AKBM/371 Okello Edward 25,000

3,750

28,750

REA/AKBM/372 Owani Charlse 134,000

20,100

154,100

REA/AKBM/373 Ogwang Nelson 60,000

9,000

69,000

REA/AKBM/374 Grace Wani 22,000

3,300

25,300

REA/AKBM/375 Atim Stella 30,000

4,500

34,500

REA/AKBM/376 Engole George 10,000

1,500

11,500

REA/AKBM/377 Stella Atim 9,000

1,350

10,350

REA/AKBM/378 Wani Simon Peter 17,000

2,550

19,550

REA/AKBM/379 Obua Sam 11,000

1,650

12,650

REA/AKBM/380 Owani Patrick 65,000

9,750

74,750

REA/AKBM/381 Orinaya Atim 53,000

7,950

60,950

REA/AKBM/382 Ekii Walter 35,000

5,250

40,250

AWE IKWO

REA/AKBM/383 Charlse Opio Ojuka 41,500

6,225

47,725

REA/AKBM/384 Amonya Patrick 516,000

77,400

593,400

REA/AKBM/385 Okullo Vicent 40,000

6,000

46,000

69

Page 82: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/386 Owiny Aloysious 18,000

2,700

20,700

REA/AKBM/387 Sarah Ogwang 5,000

750

5,750

REA/AKBM/388 Atim Buruno 110,000

16,500

126,500

REA/AKBM/389 Opido Jimmy 149,000

22,350

171,350

REA/AKBM/390 Oming Tom 20,000

3,000

23,000

REA/AKBM/391 Opiny Jimmy 90,000

13,500

103,500

REA/AKBM/392 Alur Charlse 3,000

450

3,450

REA/AKBM/393 Adyang Kenneth 90,000

13,500

103,500

REA/AKBM/394 Amonya Patrick 15,000

2,250

17,250

REA/AKBM/395 Otim Patrick Olwa 45,000

6,750

51,750

REA/AKBM/396 Ocen Jimmy 1,000

150

1,150

REA/AKBM/397 Ocrach Nicholas 40,000

6,000

46,000

REA/AKBM/398 Olipa James 40,000

6,000

46,000

REA/AKBM/399 Oder Thomas 10,000

1,500

11,500

REA/AKBM/400 Ogwal Lawrence 50,000

7,500

57,500

REA/AKBM/401 Amonya Patrick 20,000

3,000

23,000

REA/AKBM/402 Oyota Alfred 40,000

6,000

46,000

REA/AKBM/403 Achili John 20,000

3,000

23,000

REA/AKBM/404 Owani Pilate 40,000

6,000

46,000

REA/AKBM/405 Tia Albino 17,000

2,550

19,550

REA/AKBM/406 Onyany Alfred 20,000

3,000

23,000

70

Page 83: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/407 Omara Sam 20,000

3,000

23,000

REA/AKBM/408 Semi Olot 41,000

6,150

47,150

REA/AKBM/409 Otak Patrick 60,000

9,000

69,000

REA/AKBM/410 Ecum Patrick 31,000

4,650

35,650

REA/AKBM/411 Ojok Ceaser 10,000

1,500

11,500

REA/AKBM/412 Okello Kosia 20,000

3,000

23,000

REA/AKBM/413 Odeng Bosco 1,000

150

1,150

REA/AKBM/414 Odyek Lawrence 5,000

750

5,750

REA/AKBM/415 Acanga Edonge Agoro 5,000

750

5,750

REA/AKBM/416 Etonga Silvesto 5,000

750

5,750

REA/AKBM/417 Okecha Patrick 5,000

750

5,750

REA/AKBM/418 Ocan Michael 7,000

1,050

8,050

ABER SUBCOUNTY DAM AMALO

REA/AKBM/419 Agenowong Sam 32,000

4,800

36,800

REA/AKBM/420 Agong Peter 10,000

1,500

11,500

REA/AKBM/421 Onedi Bosco 20,000

3,000

23,000

REA/AKBM/422 Arya Polly 75,000

11,250

86,250

REA/AKBM/423 Odyek Willy 38,725 5,809

44,534

REA/AKBM/424 Okullo Sam 115,000

17,250

132,250

REA/AKBM/425 Odongo Richard 27,000

4,050

31,050

71

Page 84: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/426 Otyal Francis 10,000

1,500

11,500

REA/AKBM/427 Awuchu Daniel 2,000

300

2,300

REA/AKBM/428 Alyata Lawrence 21,000

3,150

24,150

REA/AKBM/429 Ayo Patrick 10,000

1,500

11,500

REA/AKBM/430 Odongo Santo 85,000

12,750

97,750

REA/AKBM/431 Ongom David 106,000

15,900

121,900

REA/AKBM/432 Odongo Simon 40,000

6,000

46,000

REA/AKBM/433 Amoko Joseph 20,000

3,000

23,000

REA/AKBM/434 Ocen Moses 20,000

3,000

23,000

REA/AKBM/435 Otuke Benard 35,000

5,250

40,250

REA/AKBM/436 Olunyi William 80,000

12,000

92,000

REA/AKBM/437 Obwor Emmanual 326,500

48,975

375,475

REA/AKBM/438 Olwa 60,000

9,000

69,000

DAM APINYREA/AKBM/439 Okwanga Quirino

95,000 14,25

0 109,250

REA/AKBM/440 Otim Kenneth 20,000

3,000

23,000

REA/AKBM/441 Okech Godfrey 170,000

25,500

195,500

REA/AKBM/442 Okacha Geofrey 19,000

2,850

21,850

REA/AKBM/443 Ogwal David 24,000

3,600

27,600

REA/AKBM/444 Owiny Okwonga 18,000

2,700

20,700

REA/AKBM/445 Ogwang Robert 12,000

1,800

13,800

72

Page 85: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/446 Acipa Pasca 90,000

13,500

103,500

REA/AKBM/447 Amuja Denis 7,000

1,050

8,050

REA/AKBM/448 Ogwang Robert 424,000

63,600

487,600

LWALAREA/AKBM/449 Oryem Vicent

60,000 9,00

0 69,000

REA/AKBM/450 Okello Bonny 25,000

3,750

28,750

REA/AKBM/451 Opio Robert 50,500

7,575

58,075

REA/AKBM/452 Onyang Kassim 138,000

20,700

158,700

REA/AKBM/453 Adupa Robert 50,000

7,500

57,500

REA/AKBM/454 Oyite Jasper 13,000

1,950

14,950

REA/AKBM/455 Oceng George 100,000

15,000

115,000

REA/AKBM/456 Fr. Oryang Mem. Primary School

310,000

46,500

356,500

ALOBO LAC

REA/AKBM/457 Okwany Alfred 15,000

2,250

17,250

REA/AKBM/458 Obira Bosco 4,000

600

4,600

REA/AKBM/459 Akao Roseline 2,000

300

2,300

REA/AKBM/460 Odyek Mike 5,000

750

5,750

REA/AKBM/461 Florence Adong 10,000

1,500

11,500

REA/AKBM/462 Angwen Kerobina 58,000

8,700

66,700

REA/AKBM/463 Ogwal Denis 10,000

1,500

11,500

REA/AKBM/464 Okeny Geofrey 18,000

2,700

20,700

73

Page 86: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/465 Adeli Seraphino 18,000

2,700

20,700

REA/AKBM/466 Ebila Robert 20,000

3,000

23,000

REA/AKBM/467 Odongo Mark 70,000

10,500

80,500

REA/AKBM/468 Onap Richard 10,000

1,500

11,500

REA/AKBM/469 Ogwal Anthony 1,000

150

1,150

REA/AKBM/470 Alunya Odongo 10,000

1,500

11,500

REA/AKBM/471 Okwanga Robert 15,000

2,250

17,250

BARCALREA/AKBM/472 Amuko Tom

10,000 1,50

0 11,500

REA/AKBM/473 Okello Paskali 15,000

2,250

17,250

REA/AKBM/474 Nyangkoni Julius 10,000

1,500

11,500

REA/AKBM/475 Agonyo Robert 7,000

1,050

8,050

REA/AKBM/476 Ojok David 115,000

17,250

132,250

REA/AKBM/477 Pastor Ayee Benson 7,000

1,050

8,050

REA/AKBM/478 Okello Nelson 60,000

9,000

69,000

REA/AKBM/479 Okii David 15,000

2,250

17,250

REA/AKBM/480 Obyelo Tommy 40,000

6,000

46,000

REA/AKBM/481 Santa Eyit 10,000

1,500

11,500

REA/AKBM/482 Obyelo Patrick 15,000

2,250

17,250

REA/AKBM/483 Omara Vicent 101,000

15,150

116,150

REA/AKBM/484 Ebil Tom 39,375 5,906

45,281

74

Page 87: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/485 Okello Bosco 5,000

750

5,750

REA/AKBM/486 Ebil George 15,000

2,250

17,250

REA/AKBM/487 Owiny Robert 10,000

1,500

11,500

REA/AKBM/488 Odyek Peter 10,000

1,500

11,500

REA/AKBM/489 Obyelo Hudson 48,877 7,332

56,209

REA/AKBM/490 Odyek Richard 10,000

1,500

11,500

REA/AKBM/491 Ongora Charlse 203,000

30,450

233,450

REA/AKBM/492 Odyek Peter 264,000

39,600

303,600

KAMDINI SUBCOUNTY

ADAK 'B'

REA/AKBM/493 Odyek Peter 54,000

8,100

62,100

REA/AKBM/494 Opio Richard 20,000

3,000

23,000

REA/AKBM/495 Okore Norbert 9,000

1,350

10,350

REA/AKBM/496 Ocen Martin 20,000

3,000

23,000

REA/AKBM/497 Opio Cipriano 25,000

3,750

28,750

REA/AKBM/498 Ogwang Cipriano 82,000

12,300

94,300

REA/AKBM/499 Oduke Ambrose 12,500

1,875

14,375

REA/AKBM/500 Odongo Tony 45,000

6,750

51,750

REA/AKBM/501 Okodi Jasper 91,000

13,650

104,650

REA/AKBM/502 Ngole Alfred 120,000

18,000

138,000

REA/AKBM/503 Okullo Walter 32,000

4,800

36,800

75

Page 88: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/504 Okodi Jasper 5,000

750

5,750

ADAK 'A'

REA/AKBM/505 Teke George 20,000

3,000

23,000

REA/AKBM/506 Ocen Nelson 40,000

6,000

46,000

REA/AKBM/507 Odyek Albino 10,000

1,500

11,500

REA/AKBM/508 Adak Church of Uganda 15,000

2,250

17,250

REA/AKBM/509 Okot Dick 20,000

3,000

23,000

REA/AKBM/510 Olum Tobby 79,500

11,925

91,425

REA/AKBM/511 Okol Michael 9,250

1,388

10,638

REA/AKBM/512 Otoo Terrence 542,500

81,375

623,875

REA/AKBM/513 Okello Fred 93,500

14,025

107,525

REA/AKBM/514 Olum Yokusafati 40,000

6,000

46,000

REA/AKBM/515 Odongo Vicent 40,000

6,000

46,000

REA/AKBM/516 Okala Alex 75,000

11,250

86,250

REA/AKBM/517 Ayo Charlse 35,000

5,250

40,250

REA/AKBM/518 Alonga Joel 20,000

3,000

23,000

REA/AKBM/519 Okodi David 25,000

3,750

28,750

REA/AKBM/520 Okali Alex 50,000

7,500

57,500

REA/AKBM/521 Oukalle Dok 30,000

4,500

34,500

REA/AKBM/522 Acin David 40,000

6,000

46,000

REA/AKBM/523 Ogwang Akodo 40,000

6,000

46,000

76

Page 89: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/524 Otia Geofrey 20,000

3,000

23,000

REA/AKBM/525 Opio Bruno 55,000

8,250

63,250

REA/AKBM/526 Ogwal Francis 50,000

7,500

57,500

REA/AKBM/527 Adupa George 20,000

3,000

23,000

REA/AKBM/528 Ongora Ray 45,000

6,750

51,750

REA/AKBM/529 Olot George 15,500

2,325

17,825

REA/AKBM/530 Owiny George 236,000

35,400

271,400

REA/AKBM/531 Opio Odyek 38,000

5,700

43,700

REA/AKBM/532 Okudu Samuel 7,000

1,050

8,050

REA/AKBM/533 Nurse 34,000

5,100

39,100

REA/AKBM/534 Ongu Ego Tom 20,500

3,075

23,575

REA/AKBM/535 Okello Simon 25,000

3,750

28,750

REA/AKBM/536 Ekii Lawrence 158,000

23,700

181,700

REA/AKBM/537 Ongada George 75,000

11,250

86,250

ABER SUBCOUNTY ALYEC

REA/AKBM/538 Ayo Tom Richard 40,000

6,000

46,000

REA/AKBM/539 Selima Olwa Shaban 10,000

1,500

11,500

REA/AKBM/540 Okullo Ojok 1,775,000

266,250

2,041,250

REA/AKBM/541 Otogo Pius 6,000

900

6,900

REA/AKBM/542 Ayo Tony 20,000

3,000

23,000

77

Page 90: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/543 Ogwang Patrick 20,000

3,000

23,000

REA/AKBM/544 Ayini Jimmy 40,000

6,000

46,000

REA/AKBM/545 Odongo Felix 30,000

4,500

34,500

REA/AKBM/546 Odongo Dick 12,000

1,800

13,800

REA/AKBM/547 Ogwang Patrick 24,000

3,600

27,600

TWOCAN IKWERIREA/AKBM/548 Otyang Jimmy

20,000 3,00

0 23,000

REA/AKBM/549 Ester Ajik 26,000

3,900

29,900

REA/AKBM/550 Ocen Egach 71,000

10,650

81,650

REA/AKBM/551 Anana Terensio 20,000

3,000

23,000

CEKWEREREA/AKBM/552 Odongo Luis

143,000 21,45

0 164,450

REA/AKBM/553 Otim Ronald 500

75

575

REA/AKBM/554 Ogwal Felix 20,000

3,000

23,000

REA/AKBM/555 Opio Francis 27,000

4,050

31,050

REA/AKBM/556 Otwal Egwel 6,000

900

6,900

REA/AKBM/557 Patricia Amyuru 45,000

6,750

51,750

REA/AKBM/558 Atim Raymond 100,000

15,000

115,000

CORNER ATAPARAREA/AKBM/559 Egwel Richard

20,000 3,00

0 23,000

REA/AKBM/560 Acire Tomoi 20,000

3,000

23,000

78

Page 91: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/561 Angulu Ceaser 10,000

1,500

11,500

REA/AKBM/562 Akello Enester 22,000

3,300

25,300

REA/AKBM/563 Olobo Robert 75,825 11,374

87,199

REA/AKBM/564 Oryang Dan 411,175 61,676

472,851

REA/AKBM/565 Ojok Stephen 108,013

16,202

124,215

REA/AKBM/566 Alele William 70,625

10,594

81,219

REA/AKBM/567 Lucy Opito 71,000

10,650

81,650

REA/AKBM/568 Obadia Oryang Estate 392,000

58,800

450,800

REA/AKBM/569 Tommy Opito 30,000

4,500

34,500

REA/AKBM/570 Opito Denis 37,500

5,625

43,125

REA/AKBM/571 Kia Florence 245,000

36,750

281,750

REA/AKBM/572 Benard Opito 75,000

11,250

86,250

KAMDINI SUBCOUNTY ABULI

REA/AKBM/573 Obadia Oryang Estate 139,000

20,850

159,850

REA/AKBM/574 Ojoka Jackson 42,325 6,349

48,674

REA/AKBM/575 Okello Santo 47,000

7,050

54,050

REA/AKBM/576 Okii Ricky 60,000

9,000

69,000

REA/AKBM/577 Owing Amos 25,000

3,750

28,750

REA/AKBM/578 Atoo James 34,500

5,175

39,675

REA/AKBM/579 Dr. Oryem Vicent 50,000

7,500

57,500

REA/AKBM/580 Oday Francis 30,000

4,500

34,500

79

Page 92: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/581 Otim Jacinta 23,000

3,450

26,450

ABER SUBCOUNTY AWELO MAKWERI

REA/AKBM/582 Selestino Okite 45,000

6,750

51,750

REA/AKBM/583 Abonyu Margret 30,000

4,500

34,500

REA/AKBM/584 Epila Robert 10,000

1,500

11,500

REA/AKBM/585 Otango 65,000

9,750

74,750

REA/AKBM/586 Omara Francis 2,000

300

2,300

REA/AKBM/587 Opio Charlse 2,000

300

2,300

REA/AKBM/588 Owiny Jimmy 256,400

38,460

294,860

REA/AKBM/589 Odung Denis 20,000

3,000

23,000

REA/AKBM/590 Onyera William 43,000

6,450

49,450

REA/AKBM/591 Otwal Wilson 14,000

2,100

16,100

REA/AKBM/592 Opio Christopher 8,000

1,200

9,200

REA/AKBM/593 Jabulon Ogwang 69,625 10,444

80,069

REA/AKBM/594 Ogwang Leko 116,000

17,400

133,400

REA/AKBM/595 Benet Odong 7,000

1,050

8,050

REA/AKBM/596 Ogwal Leko 46,000

6,900

52,900

REA/AKBM/597 Jedikea Mono C/O Ayiny Jimmy

21,000

3,150

24,150

REA/AKBM/598 Okello Oloro 20,000

3,000

23,000

REA/AKBM/599 Orech Kenneth 16,000

2,400

18,400

80

Page 93: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/600 Opio Christopher 10,000

1,500

11,500

REA/AKBM/601 Okite Nelson 33,000

4,950

37,950

REA/AKBM/602 Otim Sam 23,000

3,450

26,450

REA/AKBM/603 Okwanga Washington 40,000

6,000

46,000

REA/AKBM/604 Alinga Constance 60,000

9,000

69,000

REA/AKBM/605 Olugu Terensio 18,500

2,775

21,275

REA/AKBM/606 Ojok William 590,000

88,500

678,500

REA/AKBM/607 Okwanga Jolly Ojok 5,000

750

5,750

REA/AKBM/608 Otim Robert 325,000

48,750

373,750

REA/AKBM/609 Okodi Jimmy 24,000

3,600

27,600

OKETO BITOREA/AKBM/610 Olugu Mudu Kayo

205,000 30,75

0 235,750

REA/AKBM/611 Ayo Julius Peter 213,000

31,950

244,950

REA/AKBM/612 Dollotiya Otim 374,000

56,100

430,100

REA/AKBM/613 Dollotiya Munu Ocol 1,980,000

297,000

2,277,000

AWARIPINYREA/AKBM/614 Aber Primary School

158,500 23,77

5 182,275

REA/AKBM/615 Oluma David 10,088

1,513

11,601

REA/AKBM/616 Atik Cherulaka 40,000

6,000

46,000

REA/AKBM/617 Okello Robin 11,000

1,650

12,650

REA/AKBM/618 Opito Washington 40,000

6,000

46,000

81

Page 94: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/619 Acut Nelson 5,000

750

5,750

REA/AKBM/620 Olwit Benard 15,000

2,250

17,250

REA/AKBM/621 Odongo Francis 111,000

16,650

127,650

REA/AKBM/622 Okello Nelson 30,000

4,500

34,500

REA/AKBM/623 Otim Vicent 2,700

405

3,105

REA/AKBM/624 Ogwal Denis 50,000

7,500

57,500

OKARAWOKREA/AKBM/625 Abang Lucy

437,500 65,62

5 503,125

REA/AKBM/626 Simpo Odyek 20,000

3,000

23,000

REA/AKBM/627 Olugu Oribo 10,000

1,500

11,500

REA/AKBM/628 Anyuru Anthony 40,000

6,000

46,000

REA/AKBM/629 Maritina Kasajja 10,000

1,500

11,500

REA/AKBM/630 Florence Akech 5,000

750

5,750

REA/AKBM/631 Omara John 120,000

18,000

138,000

REA/AKBM/632 Opio Moses 11,000

1,650

12,650

REA/AKBM/633 Odongo Thomson 60,000

9,000

69,000

REA/AKBM/634 Mitolesi Okwanga 45,000

6,750

51,750

REA/AKBM/635 Nawome Obete 75,000

11,250

86,250

REA/AKBM/636 Okodi Adupa 75,000

11,250

86,250

REA/AKBM/637 Alice Engede 30,000

4,500

34,500

REA/AKBM/638 Akello Betty 22,000

3,300

25,300

82

Page 95: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/639 Atyang Charlse 30,000

4,500

34,500

REA/AKBM/640 Onyala Abdu 23,000

3,450

26,450

REA/AKBM/641 Akello Milly 25,000

3,750

28,750

AROK

REA/AKBM/642 Okello Richard 4,000

600

4,600

REA/AKBM/643 Aguma Tony 7,000

1,050

8,050

REA/AKBM/644 Opio Christopher 21,500

3,225

24,725

REA/AKBM/645 Ojok William 23,500

3,525

27,025

REA/AKBM/646 Okenyi Christopher 66,750

10,013

76,763

REA/AKBM/647 Olugu Jefenia 13,500

2,025

15,525

KAMDINI SUBCOUNTY DOG ABAM

REA/AKBM/648 Rada Grace 118,000

17,700

135,700

REA/AKBM/649 Ajok Marther 93,000

13,950

106,950

AMUKUGUNGUREA/AKBM/650 Ojuka Mark

20,000 3,00

0 23,000

REA/AKBM/651 Odongo Moses 24,000

3,600

27,600

REA/AKBM/652 Akello Rose 37,875 5,681

43,556

REA/AKBM/653 Elwa Amos 30,625

4,594

35,219

REA/AKBM/654 Alunyu Saidi 123,000

18,450

141,450

KAMDINI TOWN BOARDREA/AKBM/655 Okello Olong

3,000 45

0 3,450

83

Page 96: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/656 Odongo (Mechanic) 17,500

2,625

20,125

REA/AKBM/657 Okello Yewe 471,500

70,725

542,225

REA/AKBM/658 Ogwal Small 193,000

28,950

221,950

REA/AKBM/659 Joyce Ogwal 144,500

21,675

166,175

REA/AKBM/660 Ogwang Sam 3,000

450

3,450

REA/AKBM/661 Mama Anjelina 20,000

3,000

23,000

REA/AKBM/662 Nengo Emmanuel 50,000

7,500

57,500

REA/AKBM/663 Omony Nelson 50,000

7,500

57,500

REA/AKBM/664 Ogwang Sam's Sister 50,000

7,500

57,500

REA/AKBM/665 Owelo Lawrence 16,500

2,475

18,975

REA/AKBM/666 Adimu Simon 50,000

7,500

57,500

REA/AKBM/667 Sofia 2,000

300

2,300

REA/AKBM/668 Bank Manager (Next to Atik Serulaka)

20,000

3,000

23,000

REA/AKBM/669 Onzi Saidi 23,000

3,450

26,450

REA/AKBM/670 St. Peter and Paul Catholic Church

27,000

4,050

31,050

REA/AKBM/671 Agwa Jenesio 9,000

1,350

10,350

REA/AKBM/672 Ecat Moses 63,000

9,450

72,450

REA/AKBM/673 Joyce Obonyo 97,500

14,625

112,125

ABANYA 'B'REA/AKBM/674 Alunyu Fred

76,000 11,40

0 87,400

REA/AKBM/675 Rose Alunyu 232,500

34,875

267,375

84

Page 97: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/676 Welo 6,500

975

7,475

REA/AKBM/677 Owor Moses 1,000

150

1,150

REA/AKBM/678 Okello Albino 23,500

3,525

27,025

ABANYA 'A'REA/AKBM/679 Juspin Akello

197,000 29,55

0 226,550

REA/AKBM/680 Ocen Ambrose 50,000

7,500

57,500

REA/AKBM/681 Okello Yurumoi 14,500

2,175

16,675

REA/AKBM/682 Emat Joyce Ongom 49,500

7,425

56,925

REA/AKBM/683 Owiny Saidi 40,000

6,000

46,000

REA/AKBM/684 Ocila Odongo 38,000

5,700

43,700

REA/AKBM/685 Odongo Willy 51,000

7,650

58,650

REA/AKBM/686 Ocen Augustine 120,000

18,000

138,000

REA/AKBM/687 Kinyera John Bosco 35,000

5,250

40,250

REA/AKBM/688 Otim Justine 86,000

12,900

98,900

REA/AKBM/689 Omara Alfred 36,000

5,400

41,400

REA/AKBM/690 Obote Martin 53,000

7,950

60,950

REA/AKBM/691 Owelo Jimmy 20,000

3,000

23,000

REA/AKBM/692 Okello Vicent 40,000

6,000

46,000

REA/AKBM/693 Okello Ngai 32,900

4,935

37,835

REA/AKBM/694 Otoo Alino 32,900

4,935

37,835

REA/AKBM/695 Pamela Akello 108,000

16,200

124,200

85

Page 98: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/696 Omara Patrick 40,000

6,000

46,000

ALYEC

REA/AKBM/697 Terensio Omwony 67,000

10,050

77,050

REA/AKBM/698 Karens Apoto 16,000

2,400

18,400

REA/AKBM/699 Joyce Angiru 90,000

13,500

103,500

REA/AKBM/700 Okello Nick 92,000

13,800

105,800

REA/AKBM/701 Ogoro Alfred 2,000

300

2,300

REA/AKBM/702 Ogwal Dickens 22,000

3,300

25,300

REA/AKBM/703 Opio Charlse 67,500

10,125

77,625

REA/AKBM/704 Odongo Raymond 41,000

6,150

47,150

REA/AKBM/705 Abok John 209,000

31,350

240,350

REA/AKBM/706 Okello Jimmy 35,000

5,250

40,250

REA/AKBM/707 Otwal Nelson 50,000

7,500

57,500

REA/AKBM/708 Ojok Awar 10,000

1,500

11,500

REA/AKBM/709 Fabiano Welo 121,000

18,150

139,150

REA/AKBM/710 Ojok Jack 10,000

1,500

11,500

REA/AKBM/711 Omach Lawrence 267,000

40,050

307,050

REA/AKBM/712 Odida Vicent 50,000

7,500

57,500

REA/AKBM/713 Okello Richard 87,500

13,125

100,625

REA/AKBM/714 Ilwar Raymond 225,000

33,750

258,750

REA/AKBM/715 Omara Salvor 500,000

75,000

575,000

86

Page 99: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/716 Ojok Jimmy 2,000

300

2,300

REA/AKBM/717 Ogwang Patrick 10,500

1,575

12,075

PUKICAREA/AKBM/718 Ayang Lillian

50,000 7,50

0 57,500

REA/AKBM/719 Opendo James 50,000

7,500

57,500

REA/AKBM/720 Ocen Mark 30,000

4,500

34,500

REA/AKBM/721 Okello Richard 36,000

5,400

41,400

REA/AKBM/722 Opio Geofrey 20,000

3,000

23,000

REA/AKBM/723 Odongo Richard 5,000

750

5,750

REA/AKBM/724 Ongole Bosco 20,000

3,000

23,000

REA/AKBM/725 Aleny Primary School 50,000

7,500

57,500

BOROBORO 'B'REA/AKBM/726 C/O Ogwal Terence

180,500 27,07

5 207,575

REA/AKBM/727 Bosco Onyanga 89,000

13,350

102,350

REA/AKBM/728 Okello Ejep 17,000

2,550

19,550

REA/AKBM/729 Otuk Richard 20,000

3,000

23,000

REA/AKBM/730 Otoo Akol 20,000

3,000

23,000

REA/AKBM/731 Owingi Patrick 10,000

1,500

11,500

REA/AKBM/732 Ochen Quinto 5,000

750

5,750

REA/AKBM/733 Okoko Patrick 20,000

3,000

23,000

REA/AKBM/734 Opio Tobby 5,000

750

5,750

87

Page 100: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

BOROBORO 'A'REA/AKBM/735 Florence Opio

130,000 19,50

0 149,500

REA/AKBM/736 Adiyo Raymond 12,000

1,800

13,800

REA/AKBM/737 Achaya Richard 7,000

1,050

8,050

REA/AKBM/738 Ochol Patrick 20,000

3,000

23,000

REA/AKBM/739 Atim Robert 9,000

1,350

10,350

REA/AKBM/740 Ochon Patrick 20,000

3,000

23,000

REA/AKBM/741 Owar Sam 15,000

2,250

17,250

REA/AKBM/742 Okello Francis 6,000

900

6,900

REA/AKBM/743 Atim Quinto 2,000

300

2,300

BAROLIMO

REA/AKBM/744 Arido Joel 15,000

2,250

17,250

REA/AKBM/745 Ogwang Johnson 10,000

1,500

11,500

REA/AKBM/746 Ojok Paul 5,000

750

5,750

REA/AKBM/747 Omari 50,000

7,500

57,500

REA/AKBM/748 Odur Richard 2,000

300

2,300

REA/AKBM/749 Edule Innocent 50,000

7,500

57,500

ARUKU LONGREA/AKBM/750 Acila Felix

92,000 13,80

0 105,800

REA/AKBM/751 Ayo Alfred 40,000

6,000

46,000

REA/AKBM/752 Otim Benedict 30,000

4,500

34,500

88

Page 101: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/753 Laba 65,000

9,750

74,750

REA/AKBM/754 Otim Lawrence 120,000

18,000

138,000

REA/AKBM/755 Odongo Joseph 5,000

750

5,750

MYENE SUBCOUNTY

ABANG TRADING CENTRE

REA/AKBM/756 Ogang Alex 44,625 6,694

51,319

REA/AKBM/757 Adupa Quinto 20,000

3,000

23,000

REA/AKBM/758 Ameny Robert 10,000

1,500

11,500

REA/AKBM/759 Ogwang Amos 20,000

3,000

23,000

REA/AKBM/760 Adupa Peter 50,000

7,500

57,500

REA/AKBM/761 Adigi Charlse 40,000

6,000

46,000

REA/AKBM/762 Okola Geofrey 6,300

945

7,245

REA/AKBM/763 Okello Denis 20,000

3,000

23,000

REA/AKBM/764 Egach George 5,000

750

5,750

REA/AKBM/765 Okello Das 10,000

1,500

11,500

REA/AKBM/766 Owoola Bosco 45,000

6,750

51,750

REA/AKBM/767 Omara Felix 60,000

9,000

69,000

REA/AKBM/768 Clama Alex 50,000

7,500

57,500

REA/AKBM/769 Ministry of Works 62,000

9,300

71,300

REA/AKBM/770 Nyoro Bonny 10,238

1,536

11,774

REA/AKBM/771 Angwech Dorcus 60,000

9,000

69,000

89

Page 102: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/772 Olila Ernesto 52,000

7,800

59,800

ABAKOREA/AKBM/773 Obote Jimmy

11,000 1,65

0 12,650

REA/AKBM/774 Obote Margret 10,000

1,500

11,500

REA/AKBM/775 Odongo Florence 45,000

6,750

51,750

REA/AKBM/776 Atik Robert 10,000

1,500

11,500

REA/AKBM/777 Okello Daniel 12,000

1,800

13,800

REA/AKBM/778 Wokorach Denis 20,000

3,000

23,000

REA/AKBM/779 Okello Samuel 50,000

7,500

57,500

REA/AKBM/780 Okello Tony 9,788

1,468

11,256

REA/AKBM/781 Omara Constantino 71,500

10,725

82,225

REA/AKBM/782 Oyio Sam 12,500

1,875

14,375

AMWA TRADING CENTRE

REA/AKBM/783 Okello Tony Oguta 13,875 2,081

15,956

REA/AKBM/784 Omara Akoch 30,500

4,575

35,075

REA/AKBM/785 Ayo Sam 5,000

750

5,750

REA/AKBM/786 Wana Patrick 1,000

150

1,150

REA/AKBM/787 Ogang Hassan 50,000

7,500

57,500

REA/AKBM/788 Alodo Lilly 47,000

7,050

54,050

REA/AKBM/789 Angwe Robert 20,000

3,000

23,000

REA/AKBM/790 Ojok Patrick 22,000

3,300

25,300

90

Page 103: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/791 Ayo Kojjo 202,000

30,300

232,300

REA/AKBM/792 Okot Mustafa 75,000

11,250

86,250

REA/AKBM/793 Adupa Walter 10,000

1,500

11,500

REA/AKBM/794 Olugu Ocen 10,000

1,500

11,500

REA/AKBM/795 Ayo James 13,000

1,950

14,950

REA/AKBM/796 Opira Bonny 50,000

7,500

57,500

REA/AKBM/797 Olwa 75,000

11,250

86,250

REA/AKBM/798 Aweri Luzino 7,000

1,050

8,050

REA/AKBM/799 Odongo Pacelle 60,000

9,000

69,000

REA/AKBM/800 Egoo Richard 10,000

1,500

11,500

REA/AKBM/801 Odongo 50,000

7,500

57,500

REA/AKBM/802 Obong Jeventino 60,000

9,000

69,000

REA/AKBM/803 Olwii James 65,000

9,750

74,750

REA/AKBM/804 Olwii Robert 100,000

15,000

115,000

REA/AKBM/805 Rose Otim 285,000

42,750

327,750

REA/AKBM/806 Odongo Richard 10,000

1,500

11,500

REA/AKBM/807 Oduka Coxson 15,000

2,250

17,250

REA/AKBM/808 Odongo Geofrey 35,000

5,250

40,250

REA/AKBM/809 Awor Christine 20,000

3,000

23,000

REA/AKBM/810 Omonya Michael 287,000

43,050

330,050

REA/AKBM/811 Okello Richard 12,000

1,800

13,800

91

Page 104: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/812 Omara J.B. 50,000

7,500

57,500

REA/AKBM/813 Oyera Moses 5,000

750

5,750

REA/AKBM/814 Omuta Justo 5,000

750

5,750

REA/AKBM/815 Opio Daniel 152,500

22,875

175,375

REA/AKBM/816 Kojjo Lawrence 127,000

19,050

146,050

REA/AKBM/817 Adong Concy 39,500

5,925

45,425

REA/AKBM/818 Okiro Ojok 30,000

4,500

34,500

AMWA HEADQUARTERSREA/AKBM/819 Ekwang Jolly

41,000 6,15

0 47,150

REA/AKBM/820 Arach Fred 27,000

4,050

31,050

REA/AKBM/821 Omara Francis 41,480

6,222

47,702

REA/AKBM/822 Omara Stephen 1,000

150

1,150

REA/AKBM/823 Adong Lilly 11,700

1,755

13,455

REA/AKBM/824 Ongari Jolly 13,000

1,950

14,950

REA/AKBM/825 Odongo Robert 10,625

1,594

12,219

REA/AKBM/826 Biron Itot 2,500

375

2,875

REA/AKBM/827 Odongo Ray 47,000

7,050

54,050

REA/AKBM/828 Olwa Elbagilo 34,500

5,175

39,675

REA/AKBM/829 Agweng Molly 72,813 10,922

83,735

REA/AKBM/830 Olwa Yakobo 18,000

2,700

20,700

REA/AKBM/831 Otim Geofrey 110,000

16,500

126,500

92

Page 105: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/832 Omuta Victor 150,500

22,575

173,075

REA/AKBM/833 Ogwang Tony 39,000

5,850

44,850

REA/AKBM/834 Okello Lawrence 18,500

2,775

21,275

REA/AKBM/835 Angwet Sam 42,500

6,375

48,875

WARINGREA/AKBM/836 Okoyi Rose

10,200 1,53

0 11,730

REA/AKBM/837 Inyak Denis 5,000

750

5,750

REA/AKBM/838 Olet Silvesto 33,500

5,025

38,525

REA/AKBM/839 Otoo Tony 30,000

4,500

34,500

REA/AKBM/840 Achan Philiph 20,000

3,000

23,000

REA/AKBM/841 Okoko Richard 500

75

575

REA/AKBM/842 Oyengo Francis 15,000

2,250

17,250

REA/AKBM/843 Ojok Albino 98,500

14,775

113,275

REA/AKBM/844 Okello Quinto 40,000

6,000

46,000

REA/AKBM/845 Okello William 11,000

1,650

12,650

REA/AKBM/846 Aboke Robert 52,000

7,800

59,800

REA/AKBM/847 Olobo Geofrey 17,000

2,550

19,550

REA/AKBM/848 Tito Okello 44,000

6,600

50,600

REA/AKBM/849 Ayo Richard 22,000

3,300

25,300

REA/AKBM/850 Omara John 6,000

900

6,900

REA/AKBM/851 Olobo Geofrey 30,500

4,575

35,075

REA/AKBM/852 Otim Alex 4,000

600

4,600

93

Page 106: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

MINAKULU SUBCOUNTY OPATI 'B'

REA/AKBM/853 Ekwang Richard 67,500

10,125

77,625

REA/AKBM/854 Odongo Francis 156,500

23,475

179,975

OPATI 'A'REA/AKBM/855 Ojok Hudson

15,000 2,25

0 17,250

REA/AKBM/856 Ocen Patrick 70,000

10,500

80,500

REA/AKBM/857 Aget Kalsto 64,000

9,600

73,600

REA/AKBM/858 Abanya David 59,000

8,850

67,850

REA/AKBM/859 Obua Denis 35,000

5,250

40,250

LANGOREA/AKBM/860 Ojok Peter

10,000 1,50

0 11,500

REA/AKBM/861 Opunyo Sam 68,750

10,313

79,063

REA/AKBM/862 Kiwanuka 27,000

4,050

31,050

REA/AKBM/863 Odongo Francis 30,000

4,500

34,500

REA/AKBM/864 Ogweng Richard 65,000

9,750

74,750

REA/AKBM/865 Engola Pius 13,000

1,950

14,950

REA/AKBM/866 Okiba Sam 21,000

3,150

24,150

REA/AKBM/867 Ongom Francis 21,000

3,150

24,150

REA/AKBM/868 Oloa Robert 45,000

6,750

51,750

REA/AKBM/869 Ayo Sam 10,000

1,500

11,500

REA/AKBM/870 Engola Pius 51,250

7,688

58,938

94

Page 107: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/871 Acipa Sylvia 12,500

1,875

14,375

REA/AKBM/872 Adupa Alex 10,000

1,500

11,500

REA/AKBM/873 Engola Richard 10,750

1,613

12,363

BOBIREA/AKBM/874 Ojok Peter

90,000 13,50

0 103,500

REA/AKBM/875 Ogola Bonny 20,375

3,056

23,431

REA/AKBM/876 Abila Enestina 70,000

10,500

80,500

REA/AKBM/877 Ocen Patrick 46,500

6,975

53,475

REA/AKBM/878 Kilama 123,000

18,450

141,450

REA/AKBM/879 Sabina Kiba 575,000

86,250

661,250

REA/AKBM/880 Odongo Walter 5,000

750

5,750

REA/AKBM/881 Okello Lawrence 10,000

1,500

11,500

REA/AKBM/882 Otwal Lawrence 47,000

7,050

54,050

REA/AKBM/883 Mone David 75,000

11,250

86,250

REA/AKBM/884 Ojok Robert 10,000

1,500

11,500

REA/AKBM/885 Otim Moses 10,000

1,500

11,500

TEYAOREA/AKBM/886 Lia Richard

1,000 15

0 1,150

REA/AKBM/887 Oryenyo Joel 44,500

6,675

51,175

REA/AKBM/888 Okello Geofrey 23,150

3,473

26,623

OMOLO

95

Page 108: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/889 Atiro Shabin 13,875 2,081

15,956

REA/AKBM/890 Awuma Loy 11,875 1,781

13,656

REA/AKBM/891 Ogwang Robert 22,750

3,413

26,163

REA/AKBM/892 Nyero Moses 9,000

1,350

10,350

REA/AKBM/893 Opio Patrick 176,688 26,503

203,191

REA/AKBM/894 Otoo Quinto 157,000

23,550

180,550

REA/AKBM/895 Odongo Simon 142,500

21,375

163,875

REA/AKBM/896 Oyet Silvio 56,000

8,400

64,400

REA/AKBM/897 Omara Bob 43,000

6,450

49,450

REA/AKBM/898 Okodi Charlse 76,000

11,400

87,400

REA/AKBM/899 Bongo Felix 140,000

21,000

161,000

REA/AKBM/900 Awuma Grace 36,500

5,475

41,975

REA/AKBM/901 Abor David 40,000

6,000

46,000

ALATI 'A'REA/AKBM/902 Bongo Felix

44,000 6,60

0 50,600

REA/AKBM/903 Onyik Geofrey Paul 36,000

5,400

41,400

REA/AKBM/904 Awar George 500

75

575

REA/AKBM/905 Ocen Denis 49,705

7,456

57,161

REA/AKBM/906 Ogwang Alterio 31,250

4,688

35,938

REA/AKBM/907 Ogom Bosco 15,313 2,297

17,610

REA/AKBM/908 Ogwang Alterio 8,125

1,219

9,344

96

Page 109: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/909 Ogwete Miseari 1,000

150

1,150

REA/AKBM/910 Ogwang David 33,000

4,950

37,950

ARAK EASTREA/AKBM/911 Okite

17,000 2,55

0 19,550

REA/AKBM/912 Acen Selina 32,000

4,800

36,800

REA/AKBM/913 Ocoo Tom 40,000

6,000

46,000

REA/AKBM/914 Jooreye 20,000

3,000

23,000

REA/AKBM/915 Ogwang Peter 20,000

3,000

23,000

REA/AKBM/916 Ebong Alex 50,000

7,500

57,500

REA/AKBM/917 Erem Moses 46,000

6,900

52,900

REA/AKBM/918 Awal Francis 79,500

11,925

91,425

REA/AKBM/919 Ogwang Cipriano 2,000

300

2,300

REA/AKBM/920 Owiny Vicent 25,000

3,750

28,750

REA/AKBM/921 Erem Robert 20,000

3,000

23,000

REA/AKBM/922 Okello Charlse 120,000

18,000

138,000

REA/AKBM/923 Odeya Bosco 100,000

15,000

115,000

REA/AKBM/924 Ojok Leo 170,000

25,500

195,500

REA/AKBM/925 Erem Geofrey 9,000

1,350

10,350

REA/AKBM/926 Ojok Bosco 65,000

9,750

74,750

REA/AKBM/927 Ayo Alex 10,000

1,500

11,500

REA/AKBM/928 Obang Patrick 70,000

10,500

80,500

97

Page 110: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/929 Madam Ana Akao 1,000

150

1,150

REA/AKBM/930 Dengo Ejebyo 155,000

23,250

178,250

REA/AKBM/931 Okello Geofrey 106,000

15,900

121,900

REA/AKBM/932 Owo John Odyambo 37,500

5,625

43,125

ODYANYOREA/AKBM/933 Anyuru Richard

4,000 60

0 4,600

AKUKI EASTREA/AKBM/934 Ogwere Vincent

306,000 45,90

0 351,900

REA/AKBM/935 Olobo Kasim 30,875

4,631

35,506

REA/AKBM/936 Oyepa Simon 24,915 3,737

28,652

REA/AKBM/937 Menya Christopher 4,000

600

4,600

REA/AKBM/938 Okunu Nickson 25,000

3,750

28,750

REA/AKBM/939 Welo Vicent 101,500

15,225

116,725

REA/AKBM/940 Menya Christopher 12,000

1,800

13,800

REA/AKBM/941 Ayo Patrick 4,024

604

4,628

REA/AKBM/942 Awio Beatrice 18,870

2,831

21,701

REA/AKBM/943 Moto Wilfred 73,000

10,950

83,950

REA/AKBM/944 Akulu Aidah 7,400

1,110

8,510

REA/AKBM/945 Apio Lucy 3,000

450

3,450

REA/AKBM/946 Ogwang Simon Peter 29,500

4,425

33,925

REA/AKBM/947 Asio Betty 4,400

660

5,060

REA/AKBM/948 Odida Francis 25,000

3,750

28,750

98

Page 111: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/949 Yakobo Olugu 24,500

3,675

28,175

REA/AKBM/950 Onyeki George 16,000

2,400

18,400

REA/AKBM/951 Otoo Tom 12,000

1,800

13,800

REA/AKBM/952 Alele Jusphine 50,000

7,500

57,500

REA/AKBM/953 Tile Geofrey 1,500

225

1,725

REA/AKBM/954 Oyo Lawrence 140,800

21,120

161,920

REA/AKBM/955 Ocen Fred 12,500

1,875

14,375

REA/AKBM/956 Ochong Richard 7,000

1,050

8,050

REA/AKBM/957 Okello Martin 3,000

450

3,450

REA/AKBM/958 Odongo Jasper 10,000

1,500

11,500

REA/AKBM/959 Acut Jimmy 20,000

3,000

23,000

REA/AKBM/960 Okello Richard 11,770

1,766

13,536

REA/AKBM/961 Obua Susan 14,375 2,156

16,531

REA/AKBM/962 Arawu Rose 60,875

9,131

70,006

ALOLEKWEREA/AKBM/963 Oming Moses

26,500 3,97

5 30,475

REA/AKBM/964 Oyugi Mark 93,663 14,049

107,712

REA/AKBM/965 Oyugi Mark 46,950

7,043

53,993

NGUTCATIREA/AKBM/966 Joyce Obong

79,000 11,85

0 90,850

REA/AKBM/967 Oryet Jimmy 80,000

12,000

92,000

99

Page 112: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/968 Adoch Florence 117,875 17,681

135,556

REA/AKBM/969 Owani Bosco 30,000

4,500

34,500

REA/AKBM/970 Oryem Denis 5,000

750

5,750

REA/AKBM/971 Owani Alfonse 20,000

3,000

23,000

REA/AKBM/972 Christine Magoti 20,000

3,000

23,000

REA/AKBM/973 Ojok Santo 20,000

3,000

23,000

REA/AKBM/974 Moro Lawrence 35,000

5,250

40,250

REA/AKBM/975 Albina Otim 10,000

1,500

11,500

REA/AKBM/976 Otim Wilbert 139,063 20,859

159,922

REA/AKBM/977 Omara Alfred 171,125 25,669

196,794

REA/AKBM/978 Okello Jimmy 7,975

1,196

9,171

REA/AKBM/979 Opwonya Patrick 8,388

1,258

9,646

REA/AKBM/980 Byarugaba Richard 2,000

300

2,300

REA/AKBM/981 Moro Francis 8,000

1,200

9,200

REA/AKBM/982 Sylvester Ogwal 10,000

1,500

11,500

REA/AKBM/983 Ongulu Otim 90,500

13,575

104,075

REA/AKBM/984 Omoro Serogam 57,000

8,550

65,550

COO PE BWONEREA/AKBM/985 Adel Primary School

232,500 34,87

5 267,375

REA/AKBM/986 Minakulu Parish 1,857,375 278,606

2,135,981

MINAKULU TRADING CENTRE 'B'

100

Page 113: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/987 Ogwang Emmanuel 60,000

9,000

69,000

REA/AKBM/988 Odongo Julius Peter 36,000

5,400

41,400

REA/AKBM/989 Omara Leo 121,500

18,225

139,725

REA/AKBM/990 Atim Agnes 56,000

8,400

64,400

REA/AKBM/991 Olaka Tony 50,000

7,500

57,500

REA/AKBM/992 Okai Wilbert 80,000

12,000

92,000

REA/AKBM/993 Oryang Geofrey 60,000

9,000

69,000

REA/AKBM/994 Ogwete Vicent 31,000

4,650

35,650

REA/AKBM/995 Bala Abdalah 25,000

3,750

28,750

REA/AKBM/996 Agwata Tom 10,000

1,500

11,500

REA/AKBM/997 Agwai Raymond 351,375 52,706

404,081

REA/AKBM/998 Ogwal Francis 63,505

9,526

73,031

REA/AKBM/999 Olet Richard 80,406

12,061

92,467

REA/AKBM/1000 Otim Alfred 31,000

4,650

35,650

REA/AKBM/1001 Okori Lawrence 35,000

5,250

40,250

MINAKULU TRADING CENTRE 'A'

REA/AKBM/1002 Opio Lawrence 185,500

27,825

213,325

REA/AKBM/1003 Okot Denis 7,000

1,050

8,050

REA/AKBM/1004 Apunyu Tony 12,000

1,800

13,800

REA/AKBM/1005 Opio Albino 14,500

2,175

16,675

REA/AKBM/1006 Omonyi Tony 11,500

1,725

13,225

101

Page 114: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/1007 Oyugi Robert 50,000

7,500

57,500

REA/AKBM/1008 Okello Ceaser 92,500

13,875

106,375

REA/AKBM/1009 Opio Walter 20,000

3,000

23,000

REA/AKBM/1010 Lagada Silvesto 7,000

1,050

8,050

REA/AKBM/1011 Otoo Patrick 32,000

4,800

36,800

REA/AKBM/1012 Ocho Richard 22,500

3,375

25,875

REA/AKBM/1013 Akai Stella 2,000

300

2,300

REA/AKBM/1014 Angulu Gaetano 20,000

3,000

23,000

REA/AKBM/1015 Ekong Alfonsio 50,000

7,500

57,500

REA/AKBM/1016 Akao Stella 18,000

2,700

20,700

REA/AKBM/1017 Okumu Rose 20,000

3,000

23,000

REA/AKBM/1018 Oryang Fabio 50,000

7,500

57,500

REA/AKBM/1019 Okech Philiph 20,000

3,000

23,000

REA/AKBM/1020 Amenya Alex 20,000

3,000

23,000

REA/AKBM/1021 Adupa Doreen 20,000

3,000

23,000

REA/AKBM/1022 Obal Geofrey 20,000

3,000

23,000

REA/AKBM/1023 Akol Alfonse 84,000

12,600

96,600

REA/AKBM/1024 Ituk Sipi 10,000

1,500

11,500

REA/AKBM/1025 Ojera Martin 25,000

3,750

28,750

REA/AKBM/1026 Ogwang Sam 10,000

1,500

11,500

REA/AKBM/1027 Ogom Robert 5,000

750

5,750

102

Page 115: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/1028 Ogwang Joe 20,000

3,000

23,000

REA/AKBM/1029 Olobo John 40,000

6,000

46,000

REA/AKBM/1030 Obote Richard 20,000

3,000

23,000

REA/AKBM/1031 Atiang Lachere 45,000

6,750

51,750

REA/AKBM/1032 Orech Nelson 62,000

9,300

71,300

REA/AKBM/1033 Okot Christine 3,500

525

4,025

REA/AKBM/1034 Odongo Lwanga 47,000

7,050

54,050

REA/AKBM/1035 Ayo Nelson 45,000

6,750

51,750

REA/AKBM/1036 Ojok Innocent 12,000

1,800

13,800

REA/AKBM/1037 Owuma 35,000

5,250

40,250

REA/AKBM/1038 Okello Charlse 29,500

4,425

33,925

REA/AKBM/1039 Bua Yakobo 60,000

9,000

69,000

REA/AKBM/1040 Alobo Paul 44,000

6,600

50,600

REA/AKBM/1041 Okello Justine 30,000

4,500

34,500

AROMONYONGOREA/AKBM/1042 Akwin

5,000 75

0 5,750

REA/AKBM/1043 Okello Justine 21,000

3,150

24,150

REA/AKBM/1044 Omodo Geofrey 45,000

6,750

51,750

REA/AKBM/1045 Acako Anjuleta 2,000

300

2,300

REA/AKBM/1046 Adwong Kilara 5,000

750

5,750

REA/AKBM/1047 Odongo George 10,000

1,500

11,500

103

Page 116: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/1048 Omach Geofrey 50,000

7,500

57,500

REA/AKBM/1049 Omara Douglas 52,500

7,875

60,375

REA/AKBM/1050 Oryang Dominic 12,500

1,875

14,375

REA/AKBM/1051 Bua Thomas 100,000

15,000

115,000

REA/AKBM/1052 Okello Nobert 77,500

11,625

89,125

REA/AKBM/1053 Apolo Halima 30,000

4,500

34,500

REA/AKBM/1054 Ogwal Denis Dicken 30,000

4,500

34,500

REA/AKBM/1055 Ongom Raymond 39,500

5,925

45,425

REA/AKBM/1056 Okello Innocent 181,000

27,150

208,150

REA/AKBM/1057 Gabriel Oling Olang 254,000

38,100

292,100

REA/AKBM/1058 Ongom Basil 409,500

61,425

470,925

REA/AKBM/1059 Alobo John 47,000

7,050

54,050

REA/AKBM/1060 Opio Bul 32,000

4,800

36,800

REA/AKBM/1061 Ongom Geofrey 290,000

43,500

333,500

REA/AKBM/1062 Ocen Peter 9,000

1,350

10,350

REA/AKBM/1063 Ongom Geofrey 2,038,000

305,700

2,343,700

BOBI SUBCOUNTY IDIPO

REA/AKBM/1064 Achan Jusphine 117,500

17,625

135,125

REA/AKBM/1065 Cathrine Janjok 57,000

8,550

65,550

REA/AKBM/1066 Oryema Peter 12,000

1,800

13,800

104

Page 117: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/1067 Owor .A. Thomas 43,000

6,450

49,450

REA/AKBM/1068 Nyeko Kenedy 106,000

15,900

121,900

REA/AKBM/1069 Anek Marther 150,000

22,500

172,500

REA/AKBM/1070 Ongom Alfred 175,000

26,250

201,250

REA/AKBM/1071 Inyang Stephen 33,375 5,006

38,381

REA/AKBM/1072 Karen Okello 4,000

600

4,600

REA/AKBM/1073 Owor Ray 38,000

5,700

43,700

REA/AKBM/1074 Bhazil Opoka 4,000

600

4,600

REA/AKBM/1075 Akuru David 5,000

750

5,750

REA/AKBM/1076 Ongier-giu Kenedy 129,000

19,350

148,350

REA/AKBM/1077 Okello Onyany 7,000

1,050

8,050

REA/AKBM/1078 Acaye Goddy 2,000

300

2,300

REA/AKBM/1079 Okumu Alfred 32,000

4,800

36,800

REA/AKBM/1080 Mohammed 24,000

3,600

27,600

REA/AKBM/1081 Akello Rose 56,000

8,400

64,400

REA/AKBM/1082 Agwayi Opoka 10,000

1,500

11,500

REA/AKBM/1083 Akii Jasper 7,000

1,050

8,050

OBALOWATREA/AKBM/1084 Odongo Isaac

29,000 4,35

0 33,350

REA/AKBM/1085 Sarafino Ochong 2,500

375

2,875

REA/AKBM/1086 Atoo Geofrey 7,000

1,050

8,050

105

Page 118: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/1087 Adero Neko 18,000

2,700

20,700

REA/AKBM/1088 Ojok (Son of Olugu) 7,000

1,050

8,050

REA/AKBM/1089 Akao Cecelia 7,000

1,050

8,050

REA/AKBM/1090 Onek Caro 4,000

600

4,600

REA/AKBM/1091 Okidi Richard 6,500

975

7,475

REA/AKBM/1092 Opio Anania 4,500

675

5,175

REA/AKBM/1093 Sunday Mpairwe Patrick

8,509

1,276

9,785

REA/AKBM/1094 Ogwal Patrick 11,419 1,713

13,132

REA/AKBM/1095 Mariano Odoki 25,000

3,750

28,750

AWII MON WARDREA/AKBM/1096 Ogwal Fred

9,500 1,42

5 10,925

REA/AKBM/1097 St. Thomas P/Sch. Minakulu

84,000

12,600

96,600

REA/AKBM/1098 Palwo Parish Minakulu 36,500

5,475

41,975

REA/AKBM/1099 Olinga Boniface 20,500

3,075

23,575

REA/AKBM/1100 Odaga Bai 223,700

33,555

257,255

REA/AKBM/1101 Odongo Acha 8,813

1,322

10,135

REA/AKBM/1102 Obak Richard 38,340

5,751

44,091

REA/AKBM/1103 Ayela Patrick 14,100

2,115

16,215

REA/AKBM/1104 Okello Acit 60,875

9,131

70,006

REA/AKBM/1105 Komakech Moses 46,500

6,975

53,475

REA/AKBM/1106 Ojok Odongo Opuk 14,750

2,213

16,963

REA/AKBM/1107 Omara Ajulio 43,200

6,480

49,680

106

Page 119: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

REA/AKBM/1108 Ochen Mark 31,125 4,669

35,794

REA/AKBM/1109 Amone Alice 52,000

7,800

59,800

KULU OTITREA/AKBM/1110 Odongo Lwanga

157,500 23,62

5 181,125

REA/AKBM/1111 Okot Nuru 62,125 9,319

71,444

REA/AKBM/1112 Omony Geofrey 69,550

10,433

79,983

REA/AKBM/1113 Tereza 49,250

7,388

56,638

REA/AKBM/1114 Odong Sudan 51,250

7,688

58,938

REA/AKBM/1115 Okello Ceaser 27,250

4,088

31,338

REA/AKBM/1116 Obak Vincent 21,750

3,263

25,013

REA/AKBM/1117 Ameny Peter 19,000

2,850

21,850

REA/AKBM/1118 Aneka Ekuka Camilo 35,000

5,250

40,250

REA/AKBM/1119 Otim Albino 15,000

2,250

17,250

REA/AKBM/1120 Banya Otim 274,000

41,100

315,100

REA/AKBM/1121 Awio Innocent 67,000

10,050

77,050

REA/AKBM/1122 Ongole Celestino 1,500

225

1,725

REA/AKBM/1123 Atine Ongole 17,500

2,625

20,125

REA/AKBM/1124 Adoch Betorina 48,125 7,219

55,344

REA/AKBM/1125 Obonyo Ceke 32,000

4,800

36,800

REA/AKBM/1126 Labeja 136,000

20,400

156,400

REA/AKBM/1127 Omara Rufino 117,500

17,625

135,125

107

Page 120: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

PATO TRADING CENTREREA/AKBM/1128 Amongi Grace

5,500 82

5 6,325

REA/AKBM/1129 Okot Felix 43,000

6,450

49,450

REA/AKBM/1130 Odongo Boniface 2,000

300

2,300

REA/AKBM/1131 Atube Nelson 5,000

750

5,750

REA/AKBM/1132 Opio Jasper 41,000

6,150

47,150

REA/AKBM/1133 Opira Simon 374,500

56,175

430,675

REA/AKBM/1134 Obur 36,000

5,400

41,400

REA/AKBM/1135 Alonyo Doreen 23,513 3,527

27,040

REA/AKBM/1136 Okello Abic 44,013

6,602

50,615

REA/AKBM/1137 Otoo Bosco 6,500

975

7,475

REA/AKBM/1138 Ogwang Tony Blair 4,875

731

5,606

REA/AKBM/1139 Odongo Moses 2,000

300

2,300

REA/AKBM/1140 Olango Michael and Oyuru John

25,000

3,750

28,750

REA/AKBM/1141 Oyuru John 44,000

6,600

50,600

REA/AKBM/1142 Bobi Subcounty Headquarters

19,000

2,850

21,850

REA/AKBM/1143 Bobi Community Polytechnic

202,500

30,375

232,875

GRAND TOTAL (USH) 95,675,252

108

Page 121: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

ANNEX 2: MINUTES OF COMMUNITY MEETINGS Date Location Concerns Raised Recommendations02/09/10 Aboke

MowlemIssue of putting up a transformer rose, who will be concerned with putting it up. Local leaders suggest government does that in order to truly benefit the people.

Concern raised that since independence this issue of a step down generator has been raised but nothing done about it.

Question asked that since the power line is on one side of the road, will the people on the opposite side get power.

Issue raised that the major problem of Aboke is a step down, is needed for the improvement of Aboke health center, secondary school, primary school, trading center. All these

Members were informed that everyone will benefit no matter which side of the road they are on.

REA to follow up in project execution

109

Page 122: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

show that the area is developing but no power.

02/09/10 Loro Sub County

Concerns about whether they will be given a transformer.

Question asked about whether they will get security lights in their areas.

Issue about the questions that the social team will ask, that after being asked these questions will something be done for them after they give out their details.

Question asked that since the power line will pass nearby their school (primary) will government give the primary school power.

Question asked that the transformer to provide power in the area, will it be bought by government or the project affected persons.

Relevant district authorities to follow up

Communities were informed that information would be used to design compensation packages for affected persons as well as livelihood restoration activities.

Communities were informed that the government will provide the transformer.

110

Page 123: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

L.C.11 vice chairman, Odera Alfred in his closing remarks encouraged community to cooperate with team, and to pass on the message to those who are not around.

03/09/10 Ongor/Entebbe Trading Centre

Member asked whether they will be given work to help in putting up the power line.

Concerned about crops destroyed, how they will be compensated.

Issue of whether this project is political, informed that it is from government and has nothing to do with politics.

Issue of having poles on one side of the road, does that mean those on the other side will not get power.

Will this power line supply public institutions like churches, hospitals and schools

Contractor should give the affected communities first priority in job recruitment. REA to monitor progress of such positive benefits

Details are highlighted in this report

More sensitization on the role of REA in service delivery

Community members informed that most service delivery is driven by the needs of communities and these will be taken into accountCommunities were informed that given that impacts of the project are low it is

111

Page 124: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Concern of if people refuse to allow power officials to work or destroy property on their land.

Mr. Buluro area councilor said that the people of this area have welcomed the idea of power; his only request is that we employ the locals and buy poles from them to benefit the members.

unlikely that many people will be affected

03/09/10 Iyani Will crops found in the right of way be compensated?

That sometime back when another group came and put up cables, dug trenches they were told it was a road reserve, no one was paid.

That if a pole passes in someone’s compound or above someone’s house, what will be done?

Are compensation rates negotiable,

Informed they will and particulars of which ones exactly.

Informed that they will move the poles and avoid the houses.

Informed that trees and poles have fixed values that government has set.

Community health 112

Page 125: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

can PAP’s bargain?

What if a pole falls and kills someone, will the government compensate the affected one.

and safety mitigation measures to be highlighted in the ESIA

04/09/10 Gwokoneno Issue raised that in the past, villages around where given a transformer but they did not get. Wants to know if it will be the same this time. Asks why they do not put a transformer in the trading center.

Community members wondered whether they would be charged for poles.

Will this project provide the youth with jobs. Suggestion made that villagers are willing to do the cutting of trees, clearing and digging holes.

What if the power line is passing over the graveyard?

Informed that the transformer put in Inya will supply a big area, it does not necessarily mean every area or village gets a transformer.

Informed that if they want power in their houses they will have to buy poles for themselves and that rural electrification will be in charge of that.

Informed that yes, there is cutting of trees, putting poles. Much cheaper to get workers from here.

Informed that it is not likely because the line is passing in the road reserve.

113

Page 126: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Concern of whether those affected along the line coming from the PTC are going to be compensated.

04/09/2010 Loro Township Are we going to give transformers to every trading center?

What is the method of compensation, what is going to be compensated exactly?

Complain that there is no transformer in Amido Trading center.

Members wondered how soon the project was going to start?

Are the PAP’s going to be paid after the project or before?

Incase poles or wires break and destroy someone’s property, how will they be compensated.

Informed of the different area where the transformers are going to be put.

Informed on what crops will be considered and

Informed that after this exercise of valuation and establishing the cost of construction then it will be begin.

Informed that before the project starts.

114

Page 127: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

04/09/2010 Obangongera Trading Centre

Chairman L.C.1 asks whether they are going to pay for the coming power line or the old one as well.

When the power line passes over a house is it destroyed.

Will security lights be provided?

Will we be supplying power to people’s homes?

Will there be a gap between the existing power line and new one?

That the previous power line planners did not compensate them, what procedures should they use in case they have complaints they want to pass on?

When will they start paying for this project?

What rates do

Informed that we are concerned with the new one.

Informed that no house will be destroyed.

Informed that it is up to the community to organize themselves for this.

Informed that it is up to them to apply to REA and be connected to the grid.

Informed that they have to meet.

A grievance mechanism has been proposed in this report and will be disclosed to community members

Informed after valuation and before they put up the poles.

Informed that they 115

Page 128: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

they use for compensation and what are they.

Are surveyors going to pay them some small money when they pass in their areas or land?

can get the rates at the district office.

06/09/2010 Odike TC When a pole falls on a house, will they compensate?

Will those on the opposite side of the road get power?

What of having power in the houses?

Will there be security lights put up?

What if the mango tree is in the way of the line, is one allowed to prune it instead of having it cut down?

Informed that rural electrification will compensate them

Informed that they will have to apply to REA

Informed it is up to the town council to put up that.

Informed that no, it will cut down if it is in the way.

07/09/2010 Kamdini Sub County Headquarters

When a pole falls on a house, will they compensate?

Where will the surveyors start from?

Informed that rural electrification will compensate them

116

Page 129: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Where will the transformers be located?

Does the community pay a cost to get power in the homes?

What if one wants to build on their land but there is a pole?

Informed of the different areas where they will be.

Informed that REA is responsible for connecting them with power in their homes

Informed to build 15meters from the pole.

07/09/2010 Aruko Long Trading Centre

What if the pole is on the house?

What trees will be compensated?

When will the putting up of poles start?

That the community is ready to provide labour.

What are the compesation rates for the trees?

Concern of manual labour brought up, they kept insisting that they should be considered.

What if one does not agree with

Informed that the pole will not be placed on the house.

Informed that all those trees that individual benefits from will be compensated

Informed that right now they are just planning for the route where the power line will pass.

Informed that the district land board is responsible for that.

Informed that the land board first comes to the ground

117

Page 130: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

the compensation rates paid and refuses what’s being offered. What should they do next? Should they go to court?

before rates are fixed.

08/09/2010 Amwa Trading Centre

What about the grave yards, how do they affect electricity?

Are we going to provide them with security lines?

Are trees that are going to be cut down going to taken by us or will remain?

What if houses are in the right of way, what will be done?

Will construction of poles and putting up power lines provide us with employment?

If one is on the opposite side of the road where there are no poles, will one get power.

When will the construction start?

Informed that poles will not be put on graves

Informed the local council will be in charge of that.

Informed that the trees will remain there’s and they can do as they please with them.

Informed poles will be move to avoid the houses.

Informed yes there are opportunities to employ them.

118

Page 131: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

What will be the cost of getting a plow from one side of the road to another?

That they should be given a grace period to use power of one month for free.

Soon after the entire field information is collected.

Informed REA will be in charge of that.

08/09/2010 Aminomir Trading Centre

Why are some trees that are used for food not also valued like others?

Is compensation going to districts or owners themselves?

How much will it cost to have power in our houses?

Are community members going to be considered for some work when the construction starts?

Informed that others tress grow naturally and are not planted

Informed owners themselves

Informed that we do not know the prices but if used extravagantly then they will be charged highly.

08/09/2010 Awe Betty Trading Centre

What if the poles take a huge area of the land?

What if a pole is in line with a mango tree will it be cut down?

Informed that the poles will be in the road reserve.

119

Page 132: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Can REA buy the poles from us, informed they have to talk to rural electrification and REA for that? What is being used for payment, cards or meter box

How long will it take for the project to start?

With power in the house, how much will it cost?

Informed as soon as we take the report back and it is approved.

Informed it will depend on how much power is being used.

09/09/2010 Oyam District What about people’s houses where the wire will pass.

Who would be in charge of paying the electricity bills?

One member was told that people have already been paid; he is asking whether it is true.

Will the locals be involved in the project?

The team will put that into record but no payment will be made unless there is a destruction or damage caused on the structure.

The bills are to be paid by the beneficiary of the power, just like water

Informed no and that the payment will be done after the assessment after the field data has been processed and presented to the government and World Bank.

Informed it will be the contractors work to decide.

120

Page 133: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

What if one wants power in his house, will the government provide for that?

What is the extent of the land taken by the line?

How long will the power take to reach Minakulu tc?

Will they provide a generator metre box for all?

In case of damage caused by the power, who will be responsible?

Informed no and that they have to apply to REA.

Informed only 10m from tarmac.

Informed no, and that anyone who wants power will apply to REA for the metre box as a routine.

The government will be responsible.

09/09/2010 Bobi Sub County

What about trading centers that are off the main road; what plan is there for them?

When will the actual project start? There are many houses within the 10m length.

What if the pole is to be placed where the house is, what will be done?

The transformers distributed are effective to distribute enough power to the surrounding area the locals to write to REA if they need power in their homes.It has already started assessment of damaged and payment to be done before poles is put up.

The house will be spared and poles adjusted. However all structures will be

121

Page 134: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

noted during the assessment as earlier explained.

09/09/2010 Pato Trading Centre

Will the power serve only one side of the road? No it will serve all sides.

In all, the community leaders demonstrated their need for power and promised to cooperate when needed.

09/09/2010 Minakulu T.C Will there be need to pay for the poles on the opposite side off the road?

Who will be in charge of putting up security lights?

How much is the collection fee to other households?

Why don’t they pay for cereal crops?

How long will the programme take to start?

Someone has been asking for 20,000 for bringing electricity per

No it is in the project that those poles be distributed along the road.

The security light is managed and paid for by the town council or the community as is done in other countries.Informed that we do not know and that REA is in charge of that?Informed that they easily harvest and grow them, they have short gestation periods and farmers can easily continue to grow the crops.Informed that it started already. Informed that it is not politics but a development programme.

Informed that no money will be asked for this project except when

122

Page 135: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

household. is it part of the exercise.?

individuals want power to their houses which will be at a later stage.

10/09/2010 Wirao Trading Centre

What will be done to the residents on the opposite side of the road?

A school is located 8km from the main road. Will the government provide the school with power?

How will the prices of trees be established?

What if the poles position rests on a house what will be done?What if the transformer is not strong enough?What if the wire breaks and causes damage. Who will be responsible?If the transformer is damaged who will be

Transformers will be placed to step down power and this line will run on the opposite side of the road to distribute the power to the households.Informed that, this project is limited to the main road and a few specified links, Anymore extensions will be through a written request to REA office.The valuers will use compensation rates made by the district to value all the agriculture and forest produce. The valuers do not decide on their own. The poles will be extended away from the houses.

During construction it will be the contractor, after that it will be government to pay for the damages.

123

Page 136: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

responsible?10/09/2010 Atapara

HospitalThe hospital requires more voltage than the 200kv given because more institutions and machines are being introduced in the area.There should be community involvement in work such as digging holes and clearing the way.When will the project start?

Where will power be tapped from?

When will the crops be counted?

Will they consider newly planted crops / trees?Who will connect power to their houses?Are we allowed to continue using the land / road reserve after the wires have been placed?

Soon, though payment will be first be done.

From corner molem, moving along the tarmac; at ayer t c, a branch or link will be made to the hospital.

Starting next week; but the locals will be informed first through the L C 1.

Yes; from seedlings to maturity all will be considered.

The individuals will hire qualified technicians to do the work for them.

Yes they can, but do not grow crops/ trees that will grow tall and cause damage to the wires.

124

Page 137: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

ANNEX 3: LAND OWNER /TENANT/LICENSEE VERIFICATION QUESTIONNAIRE33 KV Ayer-Kamdini-Minakulu-Bobi Distribution LINE

Consultant: RESCO

Names of Enumerator....................................................................Date………………………………….

Section 1: Personal Identification

Project Affected Person

Age completed years

Sex Marital Status

Highest level of Education

Tribe Occupation Religion Serial no. on PAP’s copy

Date of enumeration

Section 2: Location of Information

District County Sub-County Parish LC II Village Plot Ref Designation

Section 3: Ownership and Particulars of the affected Person

What is your status in relation to the Land ownership?

How did you acquire this land?

1= Bought

Which year did you acquire the land?

From whom?

Give Name

Do you possess any land Title or agreement for ownership or tenancy?

How do you hold this land?

1= In possession of title.

For how long have you been on this affected plot?

1= Since

What is the predominant land tenure system in this Sub county?

1 =

Is there any encumbrances on this land like;

1= yes, Claim by: family members.

2= Yes,

What types of structures/Fixtures are on this land?

1= Residential

If tenant how much do you pay per month?

Page 138: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

1= Owner

2= Licensee

3= Tenant

4= Co-owner

5= Co-Tenant

6= Others (Specify)

2= Renting

3= Inherited

4= Given as a gift.

5= Just settled

6= Other (Specify)

1= Land Title

2=Agreement

3=Tenancy

2= Inherited but no title.

3=Tenant on titled land.

4= On public land (customary)

5= Other Specify

birth.

2= 0-10 years

3=10-20 years

4= over 20 years

Customary

2= Freehold tenure.

3= Leasehold

4= Mailo land

5= Other specify

mortgage/lien.

3= No, all documents available.

4= No, and no documentation available.

5= I don’t know

6= Other specify

only.

2= Residential and small business.

3=Small business

Do you have land holdings elsewhere?

Have you buried family members on this land? If yes, how many

Are they in the right of or way leave?

Do you wish to relocate them?

Which village?

Is it one of the land holdings?

Indicate the main source of income

Secondary source of Income

Other activities done on this land that generate income.

Section 4: Demographic Profile of affected Household

Name Sex

1 = M

2 = F

Age (yrs)

Relationship to HH Head

1 = Father

2= Wife

3= Son

4= Daughter

5= Sister

6= Brother

What is your/their main occupation?

1= Private formal/manufacturing

2= Private formal/service

3= Private formal/retail

4= Student

5= Private informal/service

How far is the work/school from here?

Record as stated

2= Not Applicable

How do you/they/get to work?

1= At site

2= by public means

3= by personal vehicle

4= by bicycle/motorcycle

What is your marital status?

1= Married/cohabiting

2= Single never married.

3= Single separate/ Divorced

What is the highest level of education you/ XX attained/currently in ?

1= None

2= Primary school

3= Ordinary Level

Of what religious affiliation is this HH?

1= Catholic

2= Protestant

3= Islam

2

Page 139: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

7= Grand father

8= Grand mother

9= Other

6= Private informal/retail

7= Private Agricultural

8= Public Government

9= Non-governmental

10= Religious

11= Not employment

5= by foot

6= in boarding school

7= other specify

8= Not applicable

4= Widow / widower

4= Tertiary Level

4= Other specify

Section 5: General Information concerning children

How many children are below5 years old?

How many children are going to schools?

How many are in primary level? How many are in secondary level?

How many are at University?

By what means do they get to school?

1= Walk

2= by public means

3= by private means

4= Others

Do you have any handicapped persons living in this HH?

1 = Yes

2 = No

What is the nature of handicap?

1= Blind

2= Deaf/dumb

3= Crippled

4= Mental

5= Other

What is the type of health facility in this area?

1= Hospital

2= Health facility IV

3= Health facility III

4= Health facility II

5= Health facility I

Is the healthy facility located along the power line right of way?

1= Yes

2= No

3=Don’t know

How far is the nearest Health Unit?

1= Less than 5km

2= 5 – 10km

3= 10 or more

What is the major source of food for this household?

1= Buy from the market

2= Grown on this parcel

3= Grown elsewhere

4= Other (Specify

3

Page 140: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

Section 6: Production Systems

If grown on parcel, what proportion contributes HH consumption? (Elaborate on the scale of 10 and get the number that contributes to total consumption)

Does this HH keep any animals or birds?

1= Yes

2= No

If yes, which animals?

1= Birds Poultry

2= Piggery

3= Goats

4= Cows

5= Other (specify)

If cultivation of crops, what are the main crops grown and how much does the household earn from each crop?

1=Maize

2=Sweet potatoes

3=Cassava

4=Beans

5=Rice

6=Other (specify)

Where are these crops grown? (Tick in the appropriate box)

1=In the background of the household

2=Farm

3=Along the power line right of way

Who owns the land on which you grow crops?

1=HH head

2=Uncle

3=Wife

4=Clan

5=Landlord

6=Other (Specify)

What is the land tenure for your land?

1=Customary

2=Freehold tenure

3=Leasehold

4=Mailo

5= Kibanja

6=Other (Specify).

Where do you usually sell your produce?

1= Don’t sell at all

2= Local Market

3= Outside market (far from home)

4= Outside the district

What problems have you experienced in your production activities? (Multiple response)

1= Drought

2= Lack of sufficient land

3= Lack of tools, like hoes

If livestock, what are the main animals and how much does the household earn from each livestock

(Give details in table below)

Where do you graze the livestock?

1= Private own land

2= Private borrowed land

3= Customary land

4= Public land

5= Hired

What problems have you experienced in livestock rearing?

1=drought

2=lack of pasture/land

3=Animal disease

4= cattle theft

5=Expensive drugs

4

Page 141: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

5= Others (specify 4= Lack of markets

5= Lack of good access to markets.

6= Others (specify) 6=No help from Govt

Section 6: Socio Network and Support System

Given the portion of your land that is marked for construction of a transmission line, do you think that you need to move to another place?

1= Yes

2= No

Where would you move to?

0=Not applicable

1=On same piece of land

2=Buy land else where

3=To the city

4=Further upcountry

5=Other (Specify)

Please give reasons for the location preferred…..

0=Not Applicable

1=Land is mine

2=It is cheaper

3=Schools and hospitals near

4=My clan stays there

5=Other (Specify)

How would you like your situation handled?

1=Compensation in cash

2=Land for land compensation

3=House built for me

4=Other (specify)

Do you have any relatives living in this Sub-county?

1= Yes

2= No

Do they live/is it within this parish?

1= Yes

2= No

Do you belong to any community organization in this parish?

1= Yes

2= No

From whom do you normally seek advice to solve your personal and HH problems?

(Multiple response)

1= Sister/Brother

2= Parents

3= Friends

Where do you bury;

1=Cemetery

2=Bijja

4=On this land

5=other (specify)

5

Page 142: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

4= Religious leader

5= Counseling Services

6= Other specify

Section 8: Income of Affected Household

What is the Main Source of income of the household

1= Salary

2= Husbands Salary

3= Business on land

4= Business located elsewhere

5= Rent collected from affected land

6= Rent collected from elsewhere

7= Agriculture activity on affected land

8= Agriculture activity on land elsewhere

9= Transfer income (Pension/handouts)

10= Other specify

What is the secondary source of income of the household

1= Salary

2= Husbands Salary

3= Business on land

4= Business located elsewhere

5= Rent collected from affected land

6= Rent collected from elsewhere

7= Agriculture activity on affected land

8= Agriculture activity on land elsewhere

9= Transfer income (Pension/handouts)

What other activities generate income for this household

0=No other

1= Fishing

2= Hunting

3= Poultry

4= Other

Compared to other residents in this Parish, in what category of standard of living would you put this HH?

(Enumerator use discretion to judge)

1= Rich

2= Average

3= Poor

4= Very Poor

What would you estimate to be the total income for this HH

Section 9: Health Hygiene and Sanitation

6

Page 143: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

What are the most common diseases affecting your Family?

1= Malaria

2= Respiratory Track Infection (RTI)

3= Diarrhea

4= HIV/AIDS/STD

5= Measles=

6= Intestinal Worms

7= Hernia

8= Other specify

When was a member of the family last hospitalized?

1= In the last week

2= In the last month

3= In the last 6 months

4= Never

What type of Latrine do you use?

1= Bush

2= Hole in ground

3= Pit latrine

4= VIP

5= Flush Toilet

6=Communal Latrine

What is the source of your water?

1= Pond/unprotected well

2= Protected well

3= spring

4= Borehole

5=Tap Water (Stand pipe)

6=Piped Water in house

What is the distance to the water source

1= 100 metres

2= 100-500 metres

3= 500 – 1km

4=1 – 1.5km

5= over 5 km

Next of Kin (Names) Relationship Address / Contact

1=Brother

2= Sister

3= Husband

3=Wife

4= Daughter

5=Son

6=Father

7

Page 144: Resettlement Action Plan (RAP) for Ayer-Kamdini …documents.worldbank.org/.../RP14900V40P1460MDINI… · Web viewRP1490 V4 Rural electrification agency Resettlement Action Plan (RAP)

7=Mother

8=Other (Specify)

I …………………….. Declare that the information above given by me is true and correct and I know this of my own knowledge. Signed by me

……………. …. On the …….day of ………. 2010

Representative LC! (In Witness): ………………………………………………… ……………………………………………………………………………………………

Name Signature Date

Representative Parish Land Committee ………………………………………….. ……………………………………………………………………………………………

Name Signature Date

8