resettlement planning document - asian development …€¦ · resettlement planning document ......

71
Resettlement Planning Document The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in nature. Resettlement Plan (17+500 to 33+250 km) Project Number: L2540 December 2011 Pakistan: National Highway Development Sector Investment Program, Project 2 (Sukkur-Jacobabad Road Project [N-65], Section 2) The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Prepared by the Office of the General Manager (N-65), National Highway Authority, Ministry of Communications, Government of Pakistan.

Upload: hatu

Post on 12-Jul-2018

236 views

Category:

Documents


0 download

TRANSCRIPT

Resettlement Planning Document

The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in nature.

Resettlement Plan (17+500 to 33+250 km) Project Number: L2540 December 2011

Pakistan: National Highway Development Sector Investment Program, Project 2 (Sukkur-Jacobabad Road Project [N-65], Section 2)

The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Prepared by the Office of the General Manager (N-65), National Highway Authority, Ministry of Communications, Government of Pakistan.

CURRENCY EQUIVALENTS (as of 16 December 2011)

Currency Unit – Pakistan rupee/s (PRs) PRs1.00 = $0.0117 $1.00 = PRs89.50

ABBREVIATIONS

NOTE

In this report, “$” refers to US dollars.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

AD – Assistant Director ADB – Asian Development Bank APs – affected persons COI CWD

– corridor of impact Communication and Works Department

DCR – District Census Report DDO – Deputy District Officer EALS – Environment, Afforestation, Land and Social

EDO – Executive District Officer

EMA – External Monitoring Agency Ft. – feet GM – General Manager

GOP – Government of Pakistan

GRC – grievance redress committee IP’s – indigenous people Km – kilometers LAA – Land Acquisition Act, 1894 LAR – land acquisition and resettlement LARP – land acquisition and resettlement plan MandE – monitoring and evaluation NESPAK – National Engineering Services Pakistan, (Pvt.) Ltd. MFF – multitranche financing facility NGO – nongovernmental organization NHA – National Highway Authority NHDSIP – National Highway Development Sector Investment Program PD – Project Directorate Rft – running feet RoW – right of way Sft – square feet Updated RP (Section-II) – updated resettlement plan (Section-II)

1

TABLE OF CONTENTS

ACRONYMS AND ABBREVIATIONS .............................................................................. i 

DEFINITIONS OF TERMS................................................................................................ ii 

I. INTRODUCTION ........................................................................................................ 4 

1.1  Background ..................................................................................................................... 4 1.2  The Project ...................................................................................................................... 4 1.3  Rationale for Updating of Land Acquisition and Resettlement Plan (LARP) ........................................................................................................................................ 5 1.4  Project Description ................................................................................................. 6 1.5  Objectives of the Short Resettlement Plan .............................................................. 10 

2.  SOCIOECONOMIC PROFILE OF APs .................................................................. 11 

2.1  Administrative Setting ................................................................................................. 11 2.2  Literacy Status .............................................................................................................. 12 2.3  Income Status .............................................................................................................. 12 2.4  Borrowing Status .......................................................................................................... 12 2.7  Status of Agriculture in the Project Area .................................................................. 13 2.8  Economic Activity in the Project Area ....................................................................... 13 2.9  Social Impacts ............................................................................................................ 13 

3.  IMPACT ASSESSMENT ........................................................................................ 14 

3.1  Impact Assessment Survey and Cut-off Date ............................................................ 14 3.2  Project Impacts ............................................................................................................. 15 3.2.1  Land Acquisition ........................................................................................................... 15 3.2.2  Building/ Structures (Shops/ Room) ......................................................................... 16 3.2.4  Public Structures .......................................................................................................... 17 3.2.5  Inventory of Trees ........................................................................................................ 17 3.2.6  Affected Crops .............................................................................................................. 18 3.3  Vulnerable AFs/APs. ................................................................................................. 19 3.4.  Price Assessment of Land and other Assets .................................................... 20 4.1  Compensation Eligibility and Entitlements for the Project ..................................... 22 4.2  Eligibility for Entitlements of Compensation ............................................................ 22 4.3   Compensation Entitlements ....................................................................................... 22 4.4  Eligibility and Entitlements ............................................................................................ 24 

5.  PUBLIC CONSULTATIONS AND DISCLOSURE ................................................. 26 

6  COMPENSATION, RELOCATION AND INCOME RESTORATION .................... 27 

6.1   General .......................................................................................................................... 27 6.2 Compensation for Land Acquisition .............................................................................. 28 6.3  Compensation for Privately Owned Structures ................................................ 28 6.4  Compensation for Community Owned Structures/Assets ............................. 29 6.5  Compensation for Public infrastructure/Assets ............................................... 29 6.6  Compensation For Crop Losses ........................................................................... 30 6.7  Compensation For Tree Losses ............................................................................ 30 Table: Table 17 B: Valuation of Affected Timber wood tree ................................... 31 6.8  Provisions for Compensatory Plantation ............................................................ 31 6.9  Relocation Options ...................................................................................................... 31 6.9.1  Privately owned Structures ................................................................................. 31 6.9.2  Religious Structures ............................................................................................. 32 

6.10  Income Restoration ..................................................................................................... 32 6.11  Transportation Allowance ........................................................................................... 33 

7.  INSTITUTIONAL ARRANGEMENTS .................................................................... 33 

7.1  Land Acquisition and Resettlement Unit at Project Level .............................. 33 7.2  Grievance Redress Cell. .......................................................................................... 34 7.3  Affected Persons and Citizen Liaison Committee .................................................. 34 

8.  IMPLEMENTATION SCHEDULE OF UPDATED RP (SECTION-II) ..................... 37 

9.  RESETTLEMENT BUDGET .................................................................................. 38 

10.  MONITORING AND EVALUATION ....................................................................... 40 

10.1  Internal Monitoring ....................................................................................................... 40 10.2  External Monitoring ...................................................................................................... 40 

List of Tables Table-1: Major Crops with their Average Yields…………………………………………… ….14 Table-2: Land Acquired for Shikarpur Bypass ……………………………………………… .17 Table 3: No. of Structures (shops/ room) located within the Project Alignment ROW ….....17 Table 4: No. of Community Structures located within the Project Area. ……… … 18 Table-5: No. of Public Structures located within the Project Alignment… …………….….18 Table-6: No. of privately owned Trees Located within the Project Alignment……………… .19 Table-7: No. of Forest owned Trees Located within the Project Alignment………… ……… .20 Table-8: Area cropped on Affected land and average yeildstion-I.…………..…………... ..20 Table-9: No. of Affected Persons due to the Construction of Section-II………..……… …... ..21 Table-10: Unit Rates and Source of Information……………….………….………………. …22 Table-11: Entitlement Matrix ………………………………………………………………... …….27 Table-12: Valuation of Private Land ……… ………….32 Table-13: Valuation of Privately owned Affected Structures/Assets…………..…………….…...32 Table-14: Valuation of Affected Community owned Structures/Assets.……………………....…33 Table-15: Valuation of Affected Public Structures/Assets……………..........………… …...…..33 Table-16: Valuation of Affected Crops… ……… ……….34 Table-17A: Valuation of Affected Fruit Trees… ……… ……….34 Table-17 B: Valuation of Timber wood Trees… ……… ……….34 Table-18: Estimation of Livelihood Allowance for Affected Households.…………………….….36 Table-19: Implementation Schedule of LARP ……………………...…..........………………….….41 Table-20: Resettlement Budget.………………………………………………………….,,,………..42

ii

DEFINITIONS OF TERMS

For the purpose of preparing Updated Resettlement Plan (Section-III) , the following terms are defined below:

Affected Person/People - Any person affected by Project-related changes in use of land, water, natural resources, or income losses.

Affected Family - All members of a household residing under one roof and operating as a single economic unit, who are adversely affected by the Project, or any of its components. It may consist of a single nuclear family or an extended family group.

Business Renter- Any person other than structure owner, who is operating his business in rented in structure (shop, kiosk or cabin), and is subject to relocate his business due to project impacts.

Compensation - Payment in cash or in kind of the replacement cost of the acquired assets.

Cut-off-date shall confirm to the date of commencement of census in the specified area.

Entitlement - Range of measures comprising compensation, income restoration, transfer assistance, income substitution, and relocation which are due to affected people, depending on the nature of their losses, to restore their economic and social base.

Hari-Farmer who cultivates the land owned by others on sharecropping basis.

Household - The people or families residing under one roof, using the same hearth and operating as a single economic unit.

Income Restoration includes reestablishing income sources and livelihood of the affected persons according to their status.

Involuntary Resettlement – Any resettlement, which does not involve willingness of the persons being adversely affected, but are forced through an instrument of law.

Shops are commercial structures, like groceries, vulcanizing shops, tailoring shops, beauty parlor, market stalls, hotels, and similar establishments.

Land Acquisition - The process whereby a person is compelled by a government agency to alienate all or part of the land a person owns or possesses to the ownership and possession of the government agency for public purpose in return for a consideration.

Market Value - the value of asset determined by market transaction of similar assets and finally arrived at after negotiations with the stakeholders, and it includes transaction costs and without the depreciation and deductions for salvaged building material. Participation is a process that allows APs and other stakeholders to influence and share control over development initiatives, decisions and the use of resources that affect them.

Rehabilitation - Compensatory measures provided under the Policy Framework on involuntary resettlement other than payment of the replacement cost of acquired assets.

Relocation - The physical relocation of AP from his/ her pre-Project place of residence.

iii

Replacement Cost - Replacement cost means the cost of replacing lost assets and income. In the case of land, it means the cost of buying replacement land near the lost land with equal productive potential plus the cost of preparing the land to levels similar to those of the affected land and the cost of any registration and transfer taxes. If alternative land is not available in the vicinity of the lost land, it means the cost of buying land with similar attributes and productive and/or residential potential plus the cost of preparing the land to levels similar to those of the affected land and cost of any registration and transfer taxes. In selecting alternative lands, affected people will be informed and consulted.

Severely Affected land or structure means more than 10% of the land or structure is affected or even less than 10% but the remaining portion is no longer viable for use.

Squatters are the persons who occupy and use an asset without possessing it or having any legal title, or a right to use/possess the same.

Vulnerable Affected Persons are the marginalized affectees or those distinct people who might face the risk of marginalization and suffer disproportionately from resettlement affects, including the women, children, destitute persons, disable, handicapped, squatters; those with historical or cultural usufruct rights; and landless groups.

Local Terms

Pacca - House or building constructed with concrete or bricks.

Semi-Pacca- House or building constructed with burnt bricks and mud.

Katcha- House or building made of un-burnt bricks and mud with wooden roof.

Chapra- The temporary structure constructed by erecting pillars or installing wood logs on each corner with roof made of twigs and grass etc.

4

I. INTRODUCTION 1.1 Background 1. The Government of Pakistan has identified road infrastructure as prerequisite for sustained economic growth and poverty alleviation. The government development priorities have been formulated in the form of “National Trade Corridor Improvement Program.” The program focus on regional connectivity through improving linkages with the neighbouring countries, developing inter provincial linkages to improve sub regional connectivity and construction of a North South Expressway Trade Corridor to overcome the network deficit. 2. National Highway Authority (NHA) is implementing National Highway Development Sector Investment Program (NHDSIP) with the assistance of Asian Development Bank (ADB) through a multi-tranche financing facility through which separate multiple loans will be extended to finance a range of subprojects. The subprojects under Tranche 1 have been completed. The Loan 2540 for Tranche 2 was signed on 3 September 2009, which became effective on 21 September, 2009. 3. The Sukkur–Jacobabad road is one of the subprojects of this tranche1. The Land Acquisition and Resettlement Plan (LARP) for Sukkur–Jacobabad was approved by ADB in May 2009. However, discrepancies were observed in the number of project affected persons and the related impacts during the physical verification of LARP by ADB through an independent consultant in May 2010. ADB required that the LARP should be updated to ensure that all APs are included and all the impacts are properly analysed. 4. Before the LARP could be updated the project highway was extensively damaged by the floods. A meeting was held at ADB Resident Mission, Islamabad on 26 August, 2010 to discuss the contract signing and pending safeguard requirements. It was agreed that NHA will provide the section wise construction plan along with a linear road map indicating areas and stretches of road with and without LAR impacts and an action plan on dated 26-08-10 Land Acquisition and Resettlement (LAR) requirements with first requirement being the preparation, approval, implementation and monitoring of section wise LARP with the section NHA wants to construct first. The minutes of meeting were communicated with ADB letter dated 30th August reiterating that the civil works will commence, with prior approval of ADB Safeguard Team, only when the LARP for the section is fully implemented and verified by the External Monitoring Agency (EMA). 1.2 The Project 5. Road Sukkur–Jacobabad N-65 is an important interprovincial highway connecting Quetta, the capital city of Baluchistan with the province of Sindh, Punjab and the port city of Karachi. A 68km section of this road is planned for up gradation and improvement of Section of this highway between Sukkur–Jacobabad. The scope of work include i) rehabilitation & capacity up gradation of the existing road section (63 km) between Sukkur–Jacobabad to 4-lane dual carriageway, and constructing a bypass for Shikarpur (5 km) city. 6. For the purpose of widening of the existing road into four lanes highway with an adequate available ROW (i.e. 35 m wide) owned by NHA from Sukkur–Shikarpur and Shikarpur–Jacobabad, where no land acquisition is involved, however, the ROW has been encroached by the locals at many places, who have to be compensated in accordance with the entitlement criterion and compensation matrix prepared under the

1. This tranche includes, (i) Sukkur–Jacobabad, and (ii) Qilla Saifullah–Zhob.

5

Land Acquisition & Resettlement Framework agreed with ADB. The measuring of 35.5 acres of land has to be acquired for 4.9 km long Shikarpur Bypass which falls in this Section-II. Following land award announced by the Land Acquisition Collector in 2008, the required amount (land cost) was deposited with the District Treasury. Subsequently, the disbursement of compensation to the extent of Land Costs is in progress since 2010 as per previsions of approved Resettlement Plan for Sukkur-Jacobabad (N-65). The award did not include entitled compensations for land owners against structures, trees and crop losses due to land acquisition. The updated RP included disbursement of entitled compensation for structure, tree and crop loss to the titled land holders and share croppers (if any), as well as disbursement of compensations to the entitled encroachers for loss of their structures and business throughout road corridor falling within Section-II. All such disbursements are to be made through project account wherein sufficient Funds have been made available to ensure timely disbursement of the entitled compensations. 7. National Highway Authority (NHA) is currently implementing two major road sector projects with the financial assistance of Asian Development Bank through Multi Tranche Financing Facilities (MFF). The National Highway Development Sector Investment Program (NHDSIP) is one of them, which includes 7 major roads2. The Sukkur–Jacobabad (N-65) is one of the seven roads including one bypass (Shikarpur Bypass). The implementation of these projects will be subjected to the compliance of Social Safeguards of ADB. The ADB Policy on "Involuntary Land Acquisition & Resettlement” requires preparation and implementation of "Land Acquisition & Resettlement Plans (LARP)", and finally conducting its independent monitoring (IM). 8. The construction of dual carriage way from Sukkur–Shikarpur-Jacobabad road is a step towards strengthening and expansion of the road network. Its total length is 63 km and one bypass of 4.9 km. It is a 4 lanes dual carriageway road. The project involved land acquisition and other associated impacts such as loss of structures, loss of squatters-business, relocation of community infrastructure, loss of crops and finally loss of trees especially wood trees. Accordingly, the NHA through hiring the consultancy services of NESPAK has prepared Land Acquisition and Resettlement Plan (LARP) in May 2009, which have specified and quantified the impacts of the project, eligibility and entitlements for compensation through establishing institutional arrangements and setting of redressal of community grievances. 9. Sukkur to Jacobabad Section of N-65 passes through the districts of Sukkur, Shikarpur and Jacobabad of Sindh Province and links the province of Sindh with Punjab and Baluchistan. Major settlements along the road are Shikarpur City and many villages, i.e. Soomar, Sheikh Suleman, Lakhi, Jahaan Khan and Sultan kot, Hamayun etc. The whole project road falls under the administrative jurisdiction of Sukkur, Jacobabad and Shikarpur Districts of Sindh Province. The project starts from Sukkur Bus stand and ends at starting point of Jacobabad. There is already existing 2 lane paved carriage way varying from 6.0 meters to 7.5 meters at various locations. The right of way (RoW) of the road is 110 ft (i.e. 55 ft. on each side from the center of road). 10. The various components of the project include widening of the existing road from Sukkur to Jacobabad City and constructing a Shikarpur bypass of about 5 km. After the completion of the project the two lane road will be converted to a 4 lane dual carriage way. 1.3 Rationale for Updating of Land Acquisition and Resettlement Plan (LARP) 11. The LARP implementation started in early 2009 but was delayed due to various

2. Hub Uthal (N-25), Multan–Muzaffargarh (N-70), Muslim Bagh–Qila Saifullah, Qila Saifullah–Zhob, Sukkur–

Jacobabad (N-65), Zhob–Mughal Kot and Qila Saifullah–Loralai–Walgum Rud.

6

factors including the gaps in the inventory of losses. With this realization, NHA and a staff consultant form ADB jointly carried out a field survey in October 2010. The team noted3 that there were gaps in the LARP, updated by NESPAK for NHA in May 2009. The impacts relating to the loss of building/ structures, and trees were significantly under assessed while the identification of owners/ inventory of land, trees and other assets were not considered in the plan. Furthermore, the ROW considered in the LARP was significantly less as compared with the actual alignment. Having highlighted these gaps in the LARP, NHA considered it essential to finally update the LARP, based on the gaps and findings of joint survey by NHA and the consultant. 12. To update the LARP for the whole project corridor is a time taking process, in this context, ADB accepted that NHA may prepare the Sectional LARPs and NHA can prepare and submit the LARP first for the Section, where there are minimum impacts, so that after its approval, the implementation of the LARP could be completed in a shorter time. Accordingly, NHA divided the LARP into the following four sections:

(i) K.M. 00+000 to 17+500 (Zero to end of Lakki Town) (ii) K.M. 17+500 to 33+250 (End of Lakki Town to end of Shikarpur Bypass) (iii) K.M. 33+250 to 53+450 (End of Shikarpur Bypass to end of Humayun

Town) (iv) K.M. 53+450 to 68+358 (End of Humayun town to start of Jacobabad).

13. In accordance with the above division of LARP, NHA has prepared this Updated Resettlement Plan4 for Section-II (17+500 to 33+250). This updated RP (Section-II) is based on a fresh impact assessment survey and consultative meetings with the APs held during March-April 2011 by NHA. 14. However, during review of updated RP (Section-II) in July 2011 it was observed that the inventory of land and structures appended with the updated RPs (Section-II) is based on the identified loss of land and structure to the AFs falling in land and structure owner category only without identifying other categories of AFs and determining the impacts on them. To fill the gap a detailed survey of duly identified land for Shikarpur Bypass and structures falling within RoW of existing carriageway was again carried out in consultation with ADB’ s Consultant (Social Safeguard Specialist, Transport Sector Projects) during October 2011 and all categories of the AFs were recorded. Resultantly, the AFs falling in land owners, Haris (Cultivators of land owned by others as sharecroppers), structure (residential/commercial) owners, business renters and employees were also identified and impacts were evaluated. The Inventory and text of the updated RP (Section-II) is adjusted accordingly. 1.4 Project Description 15. The 63 Km road section form Sukkur to Jacobabad (N-65) is an important highway and plays a vital role in connecting Quetta, the capital city of Baluchistan with the province of Sindh and Punjab. During construction, the scope of work for section II (17+500 to 33+250) includes: (i) widening and improvement of project road as 4 lane dual carriageway, and (ii) construction of a 4.9 Km long bypass for Shikarpur city. Besides, updating of the resettlement Plan for Section-II between Sukkur–Jacobabad is also to be considered during the project implementation.

3 Comments made by Consultant ADB and similar observations were also made by external monitoring

consultant in his Inception report. 4 The Section-II involves compensation for Land, crops/trees and structures (residential/livestock) on

acquired land as well as encroacher’s -business structures which will be relocated by the owners at their own in the nearby place outside ROW after receiving payment of their losses. On the whole, there would be a minor impact on the livelihood of the APs due to the construction of this section.

7

16. For the purpose of widening of the existing road to a four lanes highway with an adequate available ROW (i.e., 35 m wide) owned by NHA from Sukkur–Shikarpur and Shikarpur–Jacobabad, where no land acquisition is involved. However, the ROW has been encroached by the locals at some places near settlements along the road corridor, who have to be compensated in accordance with the entitlement criterion and compensation matrix prepared under the Land Acquisition & Resettlement Framework agreed with ADB. The acquisition of private land involved only in case of the construction of Shikarpur bypass, while rest of whole required land is already owned by NHA. The requisite private land will be acquired in accordance with the Land Acquisition Act 1894 and ADB Policy on Involuntary Resettlement. The land from revenue villages (Deh) Chand, Phulpota, Jano, Dhakan and Chhawani fall in corridor of Shikarpur bypass. 17. The location map of the whole length of the project road is presented in Figure 1 and the part of the road under Section-II (17+500 to 33+250) is highlighted in Figure 2. For more clarity, a linear plan of Section-II of the Sukkur- Jacobabad (N-65) is presented in Figure 3 showing the details regarding the magnitude of impacts at various chain-ages (km) of this section.

8

Figure 1: Location Map of Sukkur – Jacobabad Road Project

Layout Plan of Sukkur – Jacobabad Road Project (N-65)

Project Sit

Section‐II (17+500 – 33+250)

9

Figure 2: Linear Plan of Section-II (17+500 to 33+250 Km) Sukkur – Jacobabad Road Project (N-65)

10

1.5 Objectives of the Updated Resettlement Plan

18. The LARP for Sukkur-Jacobabad (N-65) was prepared in 2009, which was categorized as A based on the project impacts, and a full Resettlement Plan was prepared, which ADB approved in 2009. Delayed implementation of the project required to update Resettlement Plan to capture additional impacts (if any) due to time lag and cap the gaps in the inventory of losses identified in October 2010 by a joint survey team of NHA and a staff consultant form ADB. However, to facilitate the commencement of works, following IR policy requirements, sectional approach was agreed for updating of Resettlement Plan. So, the subproject is divided into four Sections for updating and implementation of LARP independent to each other (See para. 12). This updated resettlement plan is to the extent of Section-II (17+500 to 33+250) of Sukkur-Jacobabad (N-65). 19. The updated Resettlement Plan (Section-II) of the Sukkur – Jacobabad project has been prepared in line with the ADB Policy on Involuntary Resettlement (1995) and applicable national laws for making payment of compensation of, land buildings/ structures, trees/crops, livelihood losses and other assets. Furthermore, this updated RP (Section-II) includes the project impacts on livelihood of the people, compensation/ rehabilitation eligibility and entitlements provisions; institutional arrangements, complaints/ grievance redress, implementation schedules, budget, and monitoring program. 20. About 35.5 acres of land has to be acquired for 4.9 km long Shikarpur Bypass while rehabilitation works for remaining stretch under this section will be confined in the ROW. The land being acquired for Shikarpur By pass is owned by 58 Affected Families. Thus, acquisition of small piece of land from each affected family will not have a significant impact on livelihood of AF falling in land owner categories. Besides, to compensate the losses, the land is being acquired on prevailing market price/replacement cost basis following land award announced by the Land Acquisition Collector on 10-01-2008, under Land Acquisition Act 1894. NHA has deposited adequate funds with the District Treasury and disbursement of land cost is in progress following the approved Resettlement plan (2009). However, the land award did not include compensations for structures (constructed on land subject to acquisition), trees and crop losses to titled land holders and other categories of AFs as per entitlement matrix prepared under agreed Land acquisition and Resettlement Framework for NHDSIP. To fill the gap this updated Resettlement Plan Section-II identifies the impact on structures, crops trees located in the acquired land and provides compensation to the entitled AFs including land owner, residential/commercial structure owner and Hari (Cultivators of land owned by others as sharecroppers) categories. Detail of the AFs falling in different categories is provided in para 22 below. 21. Except for bypass reach, all proposed civil work activities for widening of existing road into 4 lane carriageway are to be confined in the ROW for the proposed section-II which is encroached near settlements. Thus, the impacts are also identified on the commercial structures constructed in the RoW by the encroachers. There are 4 impacted structures5 located in encroached ROW and the owners of such structures have no title of land. 22. The identified AFs in updated RP Section-II, include land owners, Haris (Cultivators of land owned by others as sharecroppers), structure owners, business renters (business owners doing business in rented in structures) and the employees if any. In total 85 are affected households (AFs) out of which 58 AFs fall in land owners category, 8 AFs in Hari (share croppers) category, 15 AFs in structure owners category, 3 AFs in business renters category and one AFs under employee category. Out of 15 AFs falling in structure owner

5 Four commercial structures in encroached ROW are three shops and one logo of a filling station.

11

category 12 AFs6 will be relocated due to loss of their residential structures located on acquired land falling in alignment of Shikarpur Bypass. While, remaining three AFs are facing loss of commercial structures constructed in encroached ROW of the existing carriageway near settlements. During consultative meetings the structure owners confirmed that they will reconstruct damaged/dislocated structures in adjoining land owned by them, outside ROW and the business activities will not be disrupted permanently and shall be retained continue after rehabilitation or reconstruction of their impacted structures. The business renters will shift their business in alternate rented in structures without any business interruption and will not face income loss as such except for loss of monthly rent paid in advance. Therefore, to restore the livelihood of AFs the income losses of the commercial structure owners (encroachers) against temporarily loss of income and for business renters the loss of monthly rent paid in advance due to relocating their business in alternate place is compensated as per provisions of entitlement matrix as detailed in para 79. So, it is perceived that the project impact will be transitory and temporary in nature regardless of dislocation of residential structures of 12 AFs. However, all compensation will be paid prior to physical possession of the land and confirmed by the external monitor.

2. SOCIOECONOMIC PROFILE OF APs

23. The information regarding socioeconomic conditions of APs were derived from primary data (field survey) from project alignment falling in Section-II and data collected from secondary sources, i.e. data from Population Welfare Department (2010), data from Development Statistics of Sindh (2008), District Population Census (District Shikarpur), Agriculture Extension Department Shikarpur, Design Utility Folders of the Project and other. The primary data include census survey of all affected families which covered the socio-economic profile of each affected family. It is used to determine the project impacts on each AP with respect to asset/income losses and provide compensation accordingly to mitigate the identified impacts. However, the macro level demographic and socio economic profile of the area is derived by use of socio-economic profile of randomly selected 25% sample from total affected population in the project area and information provided in the approved Resettlement Plan and secondary data collected from in line departments.

2.1 Administrative Setting

24. The project road, i.e. Section-II falls in the jurisdiction of District Shikarpur. The District Shikarpur is located at north-east from Jacobabad and at south-west from Sukkur. The Shikarpur District borders the districts of Larkana, Jacobabad, Khairpur and Sukkur. Two National Highways (N-65 & N-55) intersect the city of Shikarpur, making it the junction points for 4 provinces. The district is subdivided into 4 Talukas (sub-districts); these are, (i) Garhi Yaseen, (ii) Khanpur, (iii) Lakhi, and (iv) Shikarpur.

25. As per data of Population Welfare, District Shikarpur (2010), the total population of district Shikarpur is 1.470 million, out of which, 841,462 and 628,968 are male and females respectively. The gender ratio estimated as 1.33, and the proportion of male and females in total population is 57.2% and 42.8% respectively. Regarding, the settlement pattern, of the total population, about three-fourth population is belonging to the rural population, while rest one-fourth is belonging to the urban population. The major castes groups of district Shikarpur are Dahani, Mangi, Sanch, Machi, Gurgigi, Channas, Mangwal and other.

6 12 AFs are subject to relocate due to loss of their residential structures constructed on privately owned land

acquired for Shikarpur bypass with no impact on their source of livelihood. This land on which these structures are located is not owned by the structure owners and thus they are not entitled for replacement land or land cost. During consultation the AFs informed that they have alternate land available at a distance of about 500-700 meter away from existing location to relocate their residential structures.

12

2.2 Literacy Status

26. The average literacy rate is 37.3%, out of which 32% had primary level of education, 29% had education up to Matriculation level and 23% had qualification up to intermediate level and only 16% were graduate and postgraduate.

2.3 Income Status

27. On overall basis of the census inventory for the project alignment falling in Section-II, 31% APs had their income ranging below Rs.10000 / month, 30% were belonging to the income group of Rs. 11000-20000/ month, 13% come under the income category of Rs. 21000 to 30000/ month, 8% had the income between Rs. 31000 to 40000/ month and remaining 18%had income above Rs 40,000/ month. The Land/Structure owners or share croppers/business renters AFs falling in the income level below Rs 10000 will encounter income loss due to loss of their assets. However, to determine the AFs living below poverty level with respect to Officially Declared Poverty Line (OPL)7, per-capita income of each family was calculated by using census data on income status and household size. The analysis reflected that there are 31 affected families (Land owners, share croppers, structure owner and business renter categories) which have earning below poverty level and thus are identified as vulnerable. All such Land/structure owners, sharecroppers/Business Renters falling in Section-II project area will be paid vulnerability allowance along with other entitled compensations. While The APs falling in employee category will be provided with one employment allowance equivalent one month’s wage base on official minimum wage rate to safe guard any adverse impact on their income status.

2.4 Borrowing Status

28. About one-third of the Sample population (i.e., 37%) had obtained credit from both formal and informal sources such as bank, landlords, and relatives.

2.5 Housing Characteristics

29. As the housing conditions are concerned, about 27% of the respondents located along the project road had their katcha houses and 49% respondents had semi-pacca houses, while remaining 24% had pacca houses.

2.6 Social Amenities

30. As far as access to social amenities is concerned, survey results have shown that on overall basis, almost all the respondents had electricity in their houses whereas 43% had the facility of water supply. About 15% to 20% sample respondents had access to the facility of gas, landline phone and sewerage system. Communication network (especially road network) is a prerequisite for undertaking the economic activity. In this context, the adjoining villages along the project area are well connected with the road network through both link and main roads. Project area lies on the belt where underground water is brackish and is not suitable for drinking or even for agriculture purpose, but ironically most of the villagers have no other source of water supply and they have to fetch water from other adjoining areas.

31. Health conditions are one of the major indicators of a society’s social development and quality of life. Healthy manpower is imperative for the advancement and economic growth. The health conditions are good in the area, as no serious disease was reported

7 The OPL of Rs. 944 per capita / month was determined by the government in 2005–2006 (Pakistan

Economic Survey, 2005–06, Table 41) which has been taken as base to assess the vulnerability of Project Affected Persons. This OPL is adopted as base because the government has not updated the OPL since then. However, keeping in view worldwide increase in food basket prices during recent years and increasing trend in poverty level in Pakistan the project Affected Persons earning below Rs. 1200/ per capita/month are taken as vulnerable.

13

there. Qualified lady health visitors are mostly non-existent in the area with major reliance on traditional child birth attendant for assisting the delivery. Comparatively, larger villages have the facility of basic health units/ dispensaries. In most of the village people used to consult private practitioner and quacks.

2.7 Status of Agriculture in the Project Area

32. Agriculture in the vicinity of N-65 is predominantly irrigated agriculture. The project area depends on non-perennial canals. The shortage of water is generally experienced in winter and it greatly hampers the crop cultivation for Rabi season. The area is irrigated by canals originating from Guddu Barrage. The project area is mainly a rice growing area. The main crop grown during Kharif season is Rice. Cotton is also grown but there is a significant variation in its production. Major Rabi season crop is wheat. Vegetable and fodder is also cultivated but at small proportion of the cropped area. In this section of the road, the impacts are identified on the crops due to land acquisition for Shikarpur by pass for which crop/tree compensation and severity impact allowence is provided in the updated Resettlement Plan.

33. Besides, some encroachment related impacts also exist within the ROW, owned by NHA. During field survey it is identified that crops are grown in the ROW by the adjoining landowners by encroaching into the ROW. Under ADB policy (1995) requirements, one crop (six month) earlier notice to vacate the ROW encroached for agriculture use is served to all respective encroachers, hence no crop compensations are included for encroachers in this updated RP (Section-II).

Table 1: Major Crops with their Average Yields Kharif Crops Yield/ acre (kgs) Rabi Crops Yield/acre (kgs) Rice (Basmati) 1400-1700 Wheat 1000-1200 Cotton 200-1000 Fodder 10000-12000 Fodder 10000-12000 Vegetable 1800-3600 Tomatoes 18000-25000 Sunflower 600-800

Source: Agriculture Extension Department Sukkur and Shikarpur.

2.8 Economic Activity in the Project Area

34. There are few industrial and commercial activities in the project area. Only some small industries are lying in the vicinity of the project road, i.e. some Rice husking factories, a textile mills, a Rice mill and some temporary brick kilns. Some crop storage depots are also located along the roadside, oil and gas explorations are also in progress around the project area.

35. The livestock in the area includes cows, buffaloes, goats and bullocks, which are mainly reared at domestic level and for agricultural farming and domestic use.

2.9 Social Impacts

36. The project will exert some social impacts on the project affected persons (land/structure and business owners), which are transitory and temporary corresponding to the execution of civil works only within the ROW. The partial loss of land due to land acquisition for Shikarpur by pass will have some tangible impacts on the Affected Families which are compensated by providing due compensation of land, crops and other productive assets on replacement cost basis. The commercial structures within encroached ROW will be rehabilitated or reconstructed outside ROW limits by the encroachers and the business activities will be resumed accordingly. The construction works within ROW will affect the agriculture activity being carried out within encroached ROW by the adjoining land owners. But it may not exert any tangible social impacts on the agricultural community as the Land owners (who have encroached adjoining ROW) had sufficient privately owned land to continue their agricultural activities. However, keeping in view the temporary interruption in

14

the economic activity transitory support is provided to the Affected Persons. 2.10 Resolution of Community Disputes 37. Community disputes generally depend on the nature of conflict. Minor disputes are normally settled within the community. The village leader known as “Wadera” takes the leading role regarding disputes resolution. However, larger disputes, political differences are referred to the court of law but sometimes the influential people may play a vital role to resolve the issues amicably. 2.11 Women Involvement 38. Women have less opportunity to get education as there are a limited number of educational facilities (schools) for women in the area as reported by the 44% of the sample women. In some cases, women have to go in other villages to get education. About 30% women are literate, while 70% are illiterate. About 28% are working women and 72% are housewives. About 44% women were of the view that they had access to education, while majority of the women (56%) have no such opportunity to get education. This shows lack of education facilities and relatively less trend to educate the females in the project area. About 26% of women said that they had just a little access to lady health visitors, while 18% had access to government doctors. However, 32% women visited private doctors in case of sickness, whereas 24% women consult the quacks. In general, most of the local women involved in farming activities as daily wage laborers like transplanting and harvesting of rice and picking of vegetables etc. along with their male members. The construction activity is confined within the ROW and there are no economic activities currently taking palce within the ROW, which could have been the source of women’s movement in the ROW. Therefore, the project does not envisage any restriction on women’s daily activities outside the ROW. 2.12 Existence of Community based Organizations 39. In the Sukkur and Shikarpur district, an NGO named as ‘Marrie Stopes Pakistan’ is working on reproductive health. However this NGO does not have any direct or indirect role in land acquisition and resettlement matters. 3. IMPACT ASSESSMENT 3.1 Impact Assessment Survey and Cut-off Date 40. The resettlement survey conducted on 10-10-2010 to 19-10-2010 includes the impact assessment/ Census of 100% APs, socioeconomic profile of APs and consultations with APs and other local community members. NHA has updated8 the impacts of the project considering the site situation. In this context, this resettlement plan has covered the project impacts for Section-II (17+500 to 33+250). 41. The previous cut-off date was 31 December 2010. Fresh survey of project impacts was carried out in March-April 2011, and based on the findings, inventory of impacts and list of APs were finalized. Therefore, new cut off date was fixed as 30 April 2011 and it was communicated to the APs along the road during the fresh field survey and consultation meetings with APs. This indicates that all APs who will settle in the project area and buildings built after this date will not be entitled to compensation or rehabilitation under the provisions of this updated RP (Section-II).

8. The impact of the project was significantly under assessed keeping in view the site situation.

15

42. Under this Section, the proposed project civil work activities include construction of: (i) 4.9 Km Shikarpur By pass on new alignment for which 35.5 acres of privately owned land is being acquired as per provisions of Land Acquisition Act 1894 and ADB policy on Involuntary Resettlement 1995, and (ii) widening of existing road into 4 lane dual carriageway for which all civil works will be retained in the designated ROW and no land acquisition is required. The strip of land required for widening of the road is already the property of NHA that will need clearance within settlements where people have constructed commercial structures (Shops, hotels and Chapras etc) by encroaching into the ROW. To compensate all assets facing impact due to project activity, price assessment has been carried out by the respective government departments to determine the unit rates. For land, award announced by the Land Acquisition Collector/Deputy District Officer Revenue (Annex- 1) is based on the Price assessed by the Revenue Authorities of Shikarpur. For structures the price assessment was made by the Communication and Works Department and the rates in case of compensation for wood trees were assessed by the Forest Department while, compensation for crops and fruit trees is assessed by the agriculture extension departments of Shikarpur District on prevailing market prices of 2010-211. (Annex- 8). 3.2 Project Impacts 38. The project impacts include the following:

(i) Acquisition of private land; (ii) Loss of residential and commercial structures and temporary interruption of

business/commercial activity; (iii) Loss of public/ community structures; (iv) Loss of trees (fruit and non-fruit trees); and (v) Loss of crops.

3.2.1 Land Acquisition 39. Total 35.5 acres private agricultural land was required under the Section-II (17+500 to 33+250 km) for the construction of Shikarpur bypass (26+100 – 30+900 km). In this context, an award for the acquisition of land was announced on dated 10-01-2008. Thus, construction of shikarpur by pass under Section-II will affect 58 families due to acquisition of land in varying degree between 10% to 30% loss of their productive assets. Besides, the land owners the land acquisition will also impact 8 AFs falling in Hari category (Conventional Land cultivators as sharecroppers in Sindh Province) to the extent of their respective share in crop harvest. This land acquisition will only have a minor impact on the livelihood of the AFs (land owners and haris). All land owners/haris have adequate land available to retain agricultural activities continued and maintain their livelihood/ household income. The data regarding land acquisition and owners of land is summarized in Table 2. List of AFs is presented in Annex- 2. Table 2: Land Acquisition for the Construction of Shikarpur Bypass under Section-II

Land Use Category

Land Acquired (Acres)

Affected Families

Remarks Land Owners (Nos.)

Haris (Nos.)

Private Agri. Land

35.5 58 8

Out of 58 Land owners 50 are self cultivator while 8 Land owners have Haris (Sharecroppers) to cultivate their lands.

16

3.2.2 Building/ Structures (Shops/ Room) 43. It was noted that there are 12 residential structures and 3 farm houses falling in alignment of Shikarpur Bypass while, four commercial structures (shops and POL logo) located within the ROW of existing road in project alignment. The data summarized in Table 1 depicts that on the whole, there are total 48 Nos. structures located within the project area. Out of which, 36 are permanent structures (including shops, rooms, veranda, kitchen, bathrooms, animal shed and a signboard of filling station etc), while 4 temporary structures includes thatched sheds (Chapras) are also located within the project ROW. Besides above structures, six hand pumps are also falling under project impacts. The inventory of structures is Annex- 3 and the census inventory of APs with their respective entitlement is provided as Appendix - 1.

Table 3: No. of Structures (shops/ room) located within the Project Alignment

Sr. No. Detail of Structure No of

StructuresTotal Built-up Area

(ft2) 1 Resedential/Commercial Structures (Rooms, Shops, walls etc.)

(i) Pacca T-Iron Girder 9 1431 (ii) Katcha 6 713 (iii) Girder and Wooden Roof 15 4391 2 Others

(i) Walls upto 5 feet height (Pacca) 4 76Rft (ii) Walls upto 5 feet height (Kacha) 2 39.5 Rft (iii) Chapra 4 626.5 (iv) P Pump Logo 1 1 (v) Hand Pumps 7 7

Total 48

3.2.3 Private/ Community Structures 44. As far as community structures/infrastructure is concerned, there are 5 community structures including four brick mosque rooms and one sabeel room (drinking water tank and room constructed along road side for community use). Caretakers of the community structures or the Mosque Committees will be provided with replacement cost for rehabilitation of the remaining structures or reconstruction of the mosques at alternate place out of ROW. And, if owners want, NHA will also facilitate reconstruction of such structures through civil works contractor. The detail regarding affected community structures is given in Annex -4.

Table 4: No. of Private/ Community Structures located within the Project Area

Type of Structure

No. Total area (ft2)

Remarks

Water Sabeel Room (concrete)

1 64In consultation with the community, NHA will re-construct a similar water tank at nearby place.

Mosque (small praying places along the road)

4 945Compensation to be paid to the caretakers/mosque committee based on replacement cost.

Total 5 1,009 -

17

3.2.4 Public Structures

45. The data given in Table 4 indicates that there are 4 public structures (including police check post (Kacha/earthen) and two bus stand waiting rooms (Pacca, RCC) located within the RoW of the existing road, which will need to be relocated. The concerned public offices/occupants of these structures have been requested to relocate these structures to clear the ROW and facilitate execution of the project works while the bus waiting rooms shall be constructed by NHA. However, the detailed costs for relocating these structures are worked out on replacement cost basis and are provided in the budget of the RP to meet the financial implications if required. Details regarding these public structures are given in Annex- 4.

Table 5: No. of Public Structures located within the Project Alignment

Sr. No. Detail of Structure

No of Structures

Total Built-up Area

(ft2) Remarks Public Infrastructure

(i) Pacca Rcc Rooms 2 802 The concerned government departments / occupants of these structures will be requested to relocate these structures at their own. However, costs for relocating these structures are worked out on replacement cost basis and are provided in the budget of this RP to meet the financial implications if required.

(iv) Kacha 2 528

Total 4

3.2.5 Inventory of Trees

46. There are total 423 privately owned trees grown in land to be acquired for Shikar pur Bypass. Out of these 423 tree 109 trees are fruit trees including date palm, mango, bain and jaman and 314 timber wood tress of different species are located within the project alignment, which will be cut down/ removed due to the acquisition of land. Table 6 provides the detail of fruit and timber wood trees.. The compensation for the loss of private trees will be made in accordance with the Entitlement matrix. Owner-wise details of trees are presented in Annex- 5 and compensation details are provided in the Appenddix-1.

Table 6: No. of Trees Located within the Project Alignment

a) Fruit Trees (Private)

S. No

Name /Category of Fruit Tree No. of Trees Date palm 65

1 Mango 33 2 Bain (Bair) 10 3 Jaman 1

Total 109

18

b) Wood/ Timber Trees (Private)

S.No Name of Tree Classification

Girth No

Total No. of Trees

1

Shisham (Dalbergia sisso)

Up to 2' girth 41 58

2'-4' girth 14

4'-6' girth 3

2 Kikar (Acacia nilotica)

Up to 2' girth 33 67

2'-4' girth 31

4'-6' girth 3

3 Shareen (Sarsh)

Up to 2' girth 2 9 2'-4' girth 7

4 Majhandri 180 180

Total 314 314 47. In addition to privately owned trees, there are 254 wood/ timber (non-fruit) trees owned by the Forest Department, which will need to be cut-down. Most of the trees were of Shisham, Eucalyptus, Kikar (Acacia) etc. (Table 7). NHA will request to the Forest Department Shikarpur to remove these trees for clearing the requisite ROW. The details are given in Annex-6. 48. NHA is willing to contribute for replenishment of these trees, or do the –re-plantation along the ROW. The requisite budgetary provisions are made in the Civil Works Contract in bill No.6 ancillary works. No sooner the civil works are completed the NHA will ensure plantation of required number of trees in supervision of afforestation wing working under GM EALS.

Table 7: No. of Trees owned by Forest Department Located in ROW.

Name of Tree No. of Trees Remarks Shisham (Dalbergia sisso) 3 Owned by

Forest Deptt. Kikar (Acacia nilotica) 92 “ Eucalyptus 151 “ Pepal (Ficus religiosa) 2 “ Date palm (non-fruit bearing) 6 “

Total 254 “

3.2.6 Affected Crops

49. The construction of 4.9 Km Shikarpur bypass under this section envisaged land acquisition measuring 35.5 Acres. Thus, the project will exert impact on the crops to the extent of the land to be acquired that needs to be compensated as per provisions of LAA 1894 and ADB IR Policy (1995). So, during fresh survey the crops losses were documented for each AF falling in land owners category and Hari (Sharecropper) category. Main crops grown in the area were documented to determine the prevailing cropping practices to determine the unit rates against crop losses due to land acquisition. According to survey findings predominant crops are Rice and wheat with fodder during Kharif and Rabi Seasons. Table below provides the details about average crop production and per acre gross value and net income from each crop.

19

Table 8: Area Cropped and Average Yields of Crops on the Affected Land

Crops Area

Cropped (acre)

Average Yield

(40kgs/ acre)

Unit rates/ 40 kg (Rs.)

Gross Value of

crop/ acre (Rs.)

Net income @ 50% of

Gross Value (Rs)

Kharif

Rice 35.5 58 953 55274 27637

Rabi Wheat 35.5 30 950 28500 14250

Total 83774 41887

50. Besides, above, during the fresh survey it was observed that the adjoining land owners are practicing crops cultivation in parts of ROW on both sides of the road by encroaching into the ROW. Main crops grown include wheat, Rice and fodder crops during Rabi and Kharif seasons. The Land owners have been given a notice to vacate the ROW with effect from 30t October i.e., after harvesting of the current Kharif crop and refrain cultivation of ensuing Rabi crop in the encroached strips of ROW. Thus, there will be no substantial impact on the crops or income of the encroacher land owners to be compensated under project.

3.2.7 Number of Affected Families (AFs) 49. There are a total 85 families who will be affected due to construction of the project in section II. The AFs have been categorized as follows: (i) land owners, 58 AFs, ii) Hari/sharecroppers (AFs doing cultivation on share cropping basis in land of the AFs loosing land) 8 AFs, iii) Residential Structure owners 12 AFs, iv Busness structure owners 3 AFs, v) Business renters (AFs doing business in rented in business structures) 3 AFs and vi) and 1 AF is employee of one of the business renter. Inventory/ census List of AFs with their respective entitlements is attached Appendix-1.

Table 9: No of Affected Persons due to the Construction of Road Section-II

Sr. No.

Category of APs No. of AFs Total

individuals/ family

members (Nos.)

Remarks

1 Owners of land 58 712 - 2 Hari/Sharecropper 8 118 3 Owners of residential structures 12 156 4 Owners of business structure 3 43 5 Business renters 3 30 6 Employee 1 6 Total 85 1035

3.3 Vulnerable AFs/APs. 51. The AFs earning below poverty level are accounted as vulnerable due to their income status and are eligible for special treatment/support to restore their livelihoods. The income status of all AFs was analyzed to calculate the per-capita income of AFs to determine vulnerability and the AFs earning Rs. 1200/- or below per-capita/month9 are defined as vulnerable for the purpose of this updated Resettlement Plan (Section-II). There

9 Please see Footnote at page 13.

20

are 31 Affected Families falling in this range of per-capita income and are identified as eligible for vulnerability allowance. 3.4. Price Assessment of Land and other Assets 52. A brief description of unit prices for affected assets and source of information is given in following text and table 8 below:

(i) Land 53. As per provisions of Land Acquisition Act, 1894 the Land Prices are assessed by the Revenue Department and land award is announced. Following request from NHA for land acquisition for Shikarpur Bypass the Revenue Department has announced the land award as below and copy of award is attached as Annex- 1 54. Land: Land award announced by the Land Acquisition Collector/Deputy District Officer Revenue District, Shikarpur. Provides Rs. 300,000 per acre for 35.5 acres of land (284 kanals) plus 15% compulsory acquisition surcharge, (Office letter No. DDO(R) 429 dated 03-12-2007).

(ii) Crops 55. Similarly for crop compensation, the unit market rate are assessed by Agriculture Department using the market rate criterion of gross crop value for current year based on average yield per acre of different crops. These unit rates have been provided in Annex- 8. On the basis of these rates the unit rates for crop compensation and severity impact allowances are determined. For crop losses the AFs are compensated with gross production value/Acre of predominant Rabi and Kharif crops i.e wheat and Rice (one year crop compensation) while to provide severity impact allowance, net income (50% of gross production value) of two cropping seasons is adopted as unit rate.

(iii) Trees 56. In case of wood/timber trees, the price per plant is assessed by the Forest Department keeping in view the “girth” of plant. All types of fruit tress are assessed by the Agriculture Extension Wing of Agriculture Department, Shikarpur District. These departments assessed and approved the unit rates which have been adopted as unit rates for calculation of compensation, and are provided in Annex-8. For wood and fruit trees unit rates of June 2011 have been used for calculating compensation.

(iv) Other Assets/ Properties 57. For affected buildings and other structures, the unit rates have been approved by Works and Services/ Buildings Department, district Shikarpur based on June 2011 rates as replacement value unit rates. More details are provided in annex-8.

21

Table 10: Unit Rates and Source of Information

Items/ Assets Unit

and qty

*Unit rates (June 2011)

(Rs.) Remarks

Agricultural Land 35.5

Acres

300,000/Acre + 15%

compulsory LA Surcharge

Following Land Award announced on 10-01-2008 NHA has deposited total Cost of land amounting Rs. 12,317,142/ in treasury for disbursement as per provisions of LAA 1894

Crop Compensation 35.5

Acres 83774/Acre

Average rate adopted from 2010-2011 rates by Agri.deptt. Shikarpurr wheat @ Rs. 28500 Rice @ Rs 55274

Fruit and Timber Wood Trees Fruit Trees

Mango Date Palm Jaman Bain

10800/plant 6250/ plant 6000/plant 2000/plant

2010-2011 rates by Agri.deptt. Shikarpur

Timber Wood Trees Majhandri Tahli/Shesham upto 2’ Tahli/Shesham upto 2’-4’ Tahli/Shesham upto 4’-6’

Other Species Kiker/ Accacia and Shareen upto 2’ Kiker/ Accacia and Shareen upto 2’ Kiker/ Accacia and Shareen upto 2’

175/plant

2000/tree 5000/tree

12000/tree

1000/tree 2000/tree 3500/tree

2010-2011 rates by Agri.deptt. Shikarpur. Forest Department Notification No. G.II(b)/600/2010-2011, Shikarpur dated 11/6/2011

Structures/ Houses Structures (a) Pacca (Commercial structure) made

of RCC and T-Iron material. Rs./ Sq.ft

**RCC structures Rs./Sq.ft 850Notification of Building Department is at Annex-8.

T-iron girder Rs./Sq.ft 710Notification of Building Department is at Annex-8.

(b) Semi Pacca (Commercial Structure) Rs./ Sq.ft 530 “

(c) Katcha (Commercial Structure) Rs./ Sq.ft 265 “

(d) (i) Pacca (Boundary Wall) above 5 feet height

(ii) Pacca (Boundary Wall) upto 5 feet height (iii) Kacha (Boundary Wall) above 5 feet height (iv) Kacha (Boundary Wall) upto 5 feet height

Rs./ rft 950

870

200

100 “

Hand Pump 6000

a) Wooden chappra Rs./ sq. ft. 100

b) Petrol pump logo/ signboard Rs./ unit 60,000 “ * Approved unit rates by the concerned Department, June, 2011, e.g Works and Services Department, Buildings Department, Forest Department District Shikarpur.

22

4. OBJECTIVES AND POLICY FRAMEWORK

58. 54. The updated RP (Section-II) was prepared in line with the ADB’s Involuntary Resettlement Policy (1995) and Resettlement Framework Document of the Project (NHDSIP) and the Land Acquisition Act (LAA) of 1894 with its amendments. 59. ADB Involuntary Resettlement Policy discusses the three major points, i.e. i) IRP emphasizes that the absence of formal legal title to land is not a bar to entitlements and assistance, ii) the LAA assesses compensation based on the market value of acquired property, where the IRP emphasizes the payment of replacement value of all affected assets, iii) follow the participatory approach, information disclosure and discussion with APs and appointment of special committees such as grievance redress committees.

4.1 Compensation Eligibility and Entitlements for the Project

60. Land Acquisition and Resettlement tasks under the project will be implemented according to compensation eligibility and entitlements in line with Pakistan’s LAA 1894 and ADB involuntary resettlement policy. Under the LAA, only legal owners and tenants officially registered with the Revenue Department or with formal lease agreements are considered “eligible” for land compensation. As per the provisions of the LAA, cash compensation is assessed (under Section 5) on the basis of 1 year average registered market rate. To fit the requirements of the ADB policy, however, under this updated RP (Section-II) also non-titled land users will be given a rehabilitation allowance for loss of land use (if any).

4.2 Eligibility for Entitlements of Compensation

61. All APs which will be entitled for compensation and / or rehabilitation provisions under this subproject are:

(i) All APs losing land covered by legal title/ or without legal status; (ii) Tenants and sharecroppers whether registered or not; (iii) Owners of buildings/ structures, crops, trees; (iv) APs losing business, income, and salaries.

62. Fresh survey of project impacts was carried out in March-April 2011, and based on the findings, inventory of impacts and list of APs were finalized. So, for entitlement eligibility cutoff date was fixed as 30 April 2011 and it was communicated to the APs along the road during the fresh field survey and consultation meetings with APs. 63. APs who settle in the affected areas after the cut-off date will not be eligible for compensation. However, they will be given sufficient advance notice to vacate premises and dismantle their affected structures prior to project implementation.

4.3 Compensation Entitlements

64. Entitlement provisions for APs losing land/ other assets and income losses, the assistance/ allowance will include provisions for permanent and temporary land/ property losses, crops and trees losses, relocation assistance, and a business losses allowance based on government minimum per capita income/ minimum official wage rate. These entitlements are discussed in following paragraphs.

65. Entitlement provisions for APs losing land, houses, and income losses and rehabilitation allowance will include provisions for permanent and temporary land losses, house and buildings losses, crops and trees losses are discussed as below:

23

(i) Agricultural land impacts. These impacts will be compensated at replacement value in cash based on current market rates plus 15% compulsory land acquisition surcharge. Eventual transaction taxes/fees will be paid by the EA or waived by local governments.

(ii) Severe Agricultural Land Impacts. When >10% of an AP of the productive land and other income generating asset is affected, AP (owners, leaseholders and sharecroppers) will get an additional allowance for severe impacts equal to the market value of a year’s net income crop yield of the land lost (inclusive `of both winter (Rabi) and summer (Kharif) harvest).

(iii) Houses, buildings, structures damages. These impacts will be compensated in cash at replacement cost free of depreciation, salvaged materials, and transaction costs deductions. The compensation will include the cost of lost water supply, electricity or telephone connections. When a House/building is affected for more than 25% (or less than that but is structurally damaged or is no more viable for use) it will be compensated in its entirety.

(iv) Income form crops losses. These impacts will be compensated through Cash compensation at current market rates for the full harvest of 1 agricultural season (inclusive of winter and summer crop i.e Rabi and Kharif). In case of sharecropping crop compensation will be paid both to landowners and tenants based on their specific sharecropping agreements.

(v) Tree losses: These impacts will be compensated in Cash based on the principle of income replacement. Fruit trees will be valued based on age category (a. not yet productive; b. productive). Productive trees will be valued at gross market value of 1 year income for the number of years (not less than 5 years) needed to grow a new tree with the productive potential of the lost tree. Non-productive trees will be valued based on the multiple years investment they have required. Non-fruit trees (Timber wood Trees) will be valued according to the girth of the trees following current market rates notified by the forest department. However, the owners of the trees will be allowed to take away the wood of felled/ trees.

(vi) Government Trees: The government owned trees will be removed through Forest Department. As per Law and govt. policy the forest department is not entitled for compensation for trees subject to felling for public interest projects. However, as per policy the provision for replenishment of trees with a ratio of 1:10 is notified to ensure growing new trees in the public corridors to enhance forest area of the country. Following government policy, NHA in consultation with forest department shall made available adequate funds for replenishment/compensatory plantation.

(vii) Businesses: compensation for permanent business losses will be in cash for the period deemed necessary to re-establish the business up to a maximum of 6 months period; compensation for temporary business losses will be cash covering the income of the interruption period up to 3 months. While the business renters (AFs doing their business in rented in shops) will shift and re-establish their business by moving to premises available on rent outside ROW in same locality. However, such AFs wiil face loss of monthly rent paid in advance to structure owners and will have to pay monthly rent for new premises as well. To compensate this, they will be given cash assistance equivalent to two months rent / official wage rate (whichever is more) to relocate their business at alternate premises.

(viii) Agricultural land sharecroppers, and workers: Affected Sharecroppers will receive their share of harvest at market rates (if impact is temporary) plus 1 additional crop compensation (if the land is lost permanently).

24

(ix) Structure owners facing loss of residential structures due to land acquisition for Shikarpur by pass: The squatters/residential structure owners without legal title facing loss of structures due to land acquisition for Shikarpur by pass will not be eligible for land compensation, however, such AFs will be provided structure losses at replacement cost basis and relocation assitance equal to three months official wage rate. However, they will be allowed to take the slavage material for which transportation allowance will be provided.

(x) Transportation/relocation Allowance: One time assistance/ allowance at rate of Rs 5000 will be paid as transportation cost covering loading and unloading charges for transportation of salvage material or his belongings from the impacted structure to each and every house hold eligible for this allowance.

(xi) Relocation Assistance: one time assistance to the residential structure owners without legal title of land (Residential Structures constructed on land owned by some other Person), falling in alignment of the Shikarpur bypass, for its relocation. The relocation assistance will be equivalent to 3 months income calculated on the basis of minimum official wage rate.

(xii) Community Structures and Public Utilities: Will be fully replaced or rehabilitated so as to satisfy their pre-project functions.

(xiii) Vulnerable people Livelihood: Vulnerable people (APs below the poverty line and or widow, orphans, women household heads, landless etc.) falling in Corridor of Impact require special assistance/support to restore their livelihood and sustain their living standards. All such APS will be provided with one special allowance equivalent to one month’s official wage rate. Besides, they will be given priority in employment in project-related jobs through civil works contractor during execution of the project. The relevant contract clauses have been included in the civil works contract.

4.4 Eligibility and Entitlements 66. All families residing in affected areas and holding affected assets or incomes before the eligibility cut-off date for the project set as 30 April, 2011 will be entitled for compensation and/or rehabilitation for their losses. Based on the project situation and impacts assessment, there was impact and compensation pertaining to the loss of land structures and trees as well as crops. However, other impacts so far unidentified may occur during the implementation which will also be compensated based on the entitlement matrix given in the following Table 11.

Table 11: Entitlement Matrix

Asset Specification Affected People Compensation Entitlements Permanent impact on Arable Land

All land losses independently from impact severity

Farmer/Titleholder

Cash compensation for affected land at replacement cost based on market value plus a 15% Compulsory Land acquisition surcharge and free of taxes, registration, and transfer costs

Sharecroppers (registered or not)

cash compensation equal to market value of lost harvest to be shared with landowner based on the sharecropping contract/arrangement

Additional provisions for severe impacts (More than 10% of land loss)

Farmer/TitleholderLeaseholder

1 severe impact allowance equal to net income from a 1 year harvest (winter and summer crop) additional to standard crop compensation.

Sharecroppers (registered or not)

1 severe impact allowance equal to market value of share of harvest lost (additional to standard crop compensation)

Building and Structures

All APs (including

Cash compensation at replacement rates for affected structure and other fixed assets free of salvageable

25

Asset Specification Affected People Compensation Entitlements squatters) materials, depreciation and transaction costs. In case

of partial impacts full cash assistance to restore remaining structure.

Crops Crops affected due to land acquisition

All APs (also squatters)

Crop compensation in cash at full market rate for 1 year harvest (inclusive of winter and summer crop) by default.

Private Trees

Trees affected due to land acquisition

All APs (also squatters)

Cash compensation at income replacement: i) for productive fruit trees: compensation at

production value for a period of years to grow a new tree with productive potential of lost tree.

Ii) Timber wood tree compensated at it market value of the wood. .

Government Trees10

To be replenished or replanted Re-plantation/ replenishment will be provided at a ratio of 1:10 (for each felled tree 10 new trees will be planted) to enhance the forest resource base of the country).

Business/ Employment

Temporary or permanent loss of business or employment

All APs (also squatters)

Business owner11: (i) Cash compensation equal to 6 months income, if loss permanent; (ii) cash compensation for the business interruption period up to 3 months, if loss temporary.

Business renters12 will be entitled cash compensation equivalent to two months rent/official wage rate to relocate their business at alternate premises.

Employees: i) Cash compensation equivalent to one month’s Salary based on minimum wage rate approved by GOP. .ii) Employment priority in project-related jobs.

Relocation Transport Allowance Relocation Assistance

All APs so affected (including squatters) AFs (without legal land title), losing residential structures due to land acquisition for Shikarpur Bypass

Provision of one time assistance as Transportation allowance at the rate of Rs. 5,000 to all

entitled. Relocation assistance in cash equivalent to three

months official wage rate to .AFs (without legal land title), facing loss of residential structures due to land acquisition for Shikarpur bypass.

Communal assets

Rehabilitation/substitution of the affected structures/utilities at replacement value without any deductions/depreciation

Livelihood/ Vulnerability Allowance AP

AP under poverty line

One special allowance of Rs. 7000 Employment priority in project-related jobs.

10 Forest Department is responsible to remove the government owned trees to facilitate execution of public

interest projects. However, the EA has to send a formal request to Forest Department with details of trees subject to be removed. Upon receipt of the request the Forest Department auctions the identified trees as per Government Policy. For such removal Forest Department is not entitled for compensation of trees. However, as per government policy the EA has to ensure funds for replenishment/compensatory plantation at a ratio of 1:10 i.e for each felled tree 10 new plants to be grown as compensatory plantation.

11 Business owner: AFs, who themselves are running business in their owned affected structure and are subjected to permanent or temporary business loss due to loss of structure are entitled for compensation as proposed along with compensation for structure loss.

12Business renters: AFs, who are running their business in rented in affected structures, will shift their business in other rented in structures outside ROW and there will be no impact on their business as such. However, they will face loss of monthly rent paid in advance to the structure owner, which has been compensated to minimize the adverse impacts (if any) and facilitate the shifting of business articles at alternate place with financial support equal to two month’s rent.

26

5. PUBLIC CONSULTATIONS AND DISCLOSURE 67. Before the commencement of the Project fresh consultations during March, to May and September, October 2011, were held in which about 30 APs participated from Shikarpur, Lakhi, Habibkot, Chand, Phulpota and Chhawni etc from project area. List of participants is given in Annex.7 The local community/ APs provided the details regarding their issues associated with the implementation of this project. Furthermore, all APs have been informed regarding the implementation of LAR activities, cut-off date, eligibility and entitlements for compensation by the Land Section, office of the Project Directorate, Sukkur during their consultations and coordination meetings with the APs. 68. The major concerns/ issues and feedback highlighted are discussed as below:

(i) All APs were interested in this road project and willing to provide all requisite

land for the construction of bypass required for this road and they were willing to provide all cooperation in this respect. The construction of the Shikarpur bypass is appreciated as there are heavy settlements/ populated area along the existing road. This bypass will also shorten the distance.

(ii) Land compensation should be made before to start work. (iii) All APs were satisfied with this whole project plan and were willing to provide

all cooperation in this regard. (iv) Local labour should be hired during the construction of this road project.13 (v) Traffic control measures should be adopted to regulate the traffic flow. (vi) Corridors/ Passages should be built for cattle’s at suitable locations along

the road.14 (vii) Over loading of the vehicles should be monitored for the long lasting life of

the road. (viii) To minimize the accidents speed control measures should be adopted. (ix) During the construction phase the dust pollution should be minimized. (x) Trees should be planted along the road side to minimize the impact on

environment as well as cutting of trees. (xi) Avoid dismantling of social/ religious infrastructure like mosque and schools,

graves. (xii) Proper traffic diversion system should be adopted in order to avoid traffic

congestion and related hazards. 69. Some other problems relating to the local women and children are as follows: Construction should be done as fast as can be because, in some emergencies, women and children will have to go hospitals for heath care purposes. 70. The community/APs had been informed about LAR impacts and the eligibility criteria in consultative meetings during preparation of updated RP (Section-II). However, the disclosure of the approved RP before its implementation is mandatory under ADB’s communication policy. Therefore after endorsement of RP by ADB, the APs will be provided all project related information including information brochures covering all necessary details about entitlement matrix, details of project impacts and compensation, grievance redress system and contact persons, etc, before starting payment of compensation and physical displacement. 71. The LAR Unit will have the responsibility to translate the summary of updated RP (Section-II) in local language (Urdu/ Sindhi) and disclose it to the APs and other notable local community members located in the jurisdiction of Section-III. Disclosure of updated RP (Section-II) will be done, after its approval by the ADB. Copies of Urdu/ Sindhi version of

13 Contractor will engage the requisite local staff through contract agreement 14 It is the desire of the people as identified during consultations. In fact, this will not be required as this road is

already constructed.

27

updated RP (Section-II) (Brochure) will also be placed at the office of Project Directorate and PIUs and will also ensure its availability to the APs. 72. Addressed Issues:

(i) All necessary facilities (like foot bridges and crossings) will be provided to the APs

(ii) In relevance to existing tracks/routes to facilitate communication and daily routine activities for the local population.

(iii) All the construction work will be confined within the proposed Right of Way (RoW).

(iv) Payment of structures/ properties assets will be made prior to start the civil work.

(v) All important infrastructures will be restored by providing culverts, bridges, waiting sheds, flyovers & underpasses.

(vi) A tree plantation program to compensate for the anticipated loss of vegetation during the construction activities, and to help abate pollution caused by emissions, dust, and noise during highway operation; and

(vii) Project construction camp will be located at a minimum distance of 500 meters away from existing settlements and built-up areas. In order to avoid restricting the mobility of local people, construction vehicles will remain confined within their designated areas of movement.

(viii) Sensitivity towards local customs and traditions will be encouraged to minimize social friction. In this respect, good relations with local communities will be promoted by encouraging contractors to provide opportunities for skilled and unskilled employment to locals, as well as on job training in construction for young people.

6. COMPENSATION, RELOCATION AND INCOME RESTORATION 6.1 General 73. As discussed in chapter 35.5 acres of land is required for construction of 4.9 Km long Shikarpur Bypass. Under LAA 1894, the process of Land acquisition was initiated at the time of inception of project in 2006 and the amount required as land compensation for land acquisition was deposited in treasury. After announcement of land award in October 2008 and approval of the Resettlement Plan for Sukkur-Jacobabad (N-65) in May 2009 the process of disbursement was started. Presently, 81% of AFs have been paid by the LAC against land compensation as per announced award. However, during award the costs for structure located on acquired land, crop and tree compensations and other applicable allowences for AFS under ADB IR Policy (1995) were not included in the award. So this RP details the impacts on structures, crops, trees and other applicable allowances for the AFs falling under land owner and share croppers to the extent of their lost assets and entitled compensations to redress/mitigate the adverse impact if any. Besides impact due to land acquisitionunder this RP impacts are identified on the privately owned structures without legal title of land, constructed in the alignment of the Shikarpur by pass and commercial structures constructed in the ROW (NHA owned property) by the encroachers. This section deals with the compensations for affected, structures and assets identified during the Census Survey. The updated RP (Section-II) focuses on providing compensations for the lost assets of APs and suggests measures to restore their livelihoods to former living standards. The compensation is based on the provisions of the EM and the unit rates provided in Table 10.

28

6.2 Compensation for Land Acquisition 74. In total 58 AFs lost a part of their land due to project alignment. To compensate the land, the land price was assessed by the Revenue authorities on the basis of current market value at that time and the award was announced on 10-01-2008. The awarded price for land acquisition is rupees, 300000/Acre. Besides land price the award also includes 15% compulsory land acquisition charge. NHA has deposited Rs. 12,317,142 in treasury for disbursement of land costs and the 80% AFs have been paid their respective land compensation. The award did not include compensation for the structures, crop and tree losses. To estimate the compensation for structures, crops and trees the structures are standardized to determine unit rate while the unit rates for crops and tree compensation are determined by use of 2010-2011 rates provided by the Communication & works and Agricultural Extension Wing of Agriculture Department Shikarpur respectively and are provided under the section for crop compensation. The table below provides the brief about the AFs entitled for land compensation and respective amount deposited in treasury while details are provided in the appendix-1. The crop and tree compensation is detailed in the respective sections below.

Table 12: Valuation of Privately owned Affected/Acquired Land

No of AFs

Land Acquired

Acres

Unit Rate

Acres

Compulsory LA

Surcharge

Land cost Deposited

in TreasuryDisbursement Status

58 35.5 300000 15% 12137142

46 AFs out 58 have been paid their land compensation. To effect early disbursement to remaining 12 AFs NHA is following up Revenue Authorities for processing of their claims.

6.3 Compensation for Privately Owned Structures 75. The privately owned affected structures are mostly residential structure and farm houses constructed on agricultural land acquired for Shikarpur by pass and include residential rooms, verandahs, walls, cattle sheds and chapras etc, while commercial structures constructed in the encroached ROW by the APs are include shops and one logo of a petrol pump. There are 15 Affected Families losing residential structures/houses out of which 3 are the owners of land while rest 12 don’t have legal title of land. The cost of land as well as structures located on privately owned land is provided to legal title holders, however, compensation for residential structure owned by the AFs without legal title of land is provided to them on replacement cost basis. The commercial structures located in ROW are compensated to the extent of replacement value of structures cost and no land cost is provided to them. To estimate the replacement value of the affected structures, the assets have been standardized for compensation on an average unit rate per sq. ft. as given in Table 7 and updated unit rates have been provided by the respective C&W department of Shikarpur District.

29

Table 13: Valuation of Privately Owned Affected Structures/Assets

Sr. No. Detail of Structure

No of Structures

Total Built-up Area

(ft2)

Unit Rate (Rs./ ft2 )* (approved June 2011)

Total Cost

(Rs. M.) Remarks1 Commercial Buildings (Shops, hotels, veranda etc.) (i) Pacca T-Iron Girder 9 1431 710 1016010 - (ii) Katcha 6 713 265 188945 - (iii) Girder and Wooden Roof 15 4391 530 2327230 2 Others

(i) Walls upto 5 feet height (Pacca) 4 76Rft 870 66120 (ii) Walls upto 5 feet height (Kacha) 2 39.5 Rft 150 5925 (v) Chapra 4 626.5 100 62650 (vi) P Pump Logo 1 1 60000 60000 (vii) Hand Pumps 7 7 6000 42000

48 3768880* Approved unit rates by the concerned Department, June, 2011, e.g., Works and Services Department, Buildings Department, District Shikarpur.

6.4 Compensation for Community Owned Structures/Assets 76. There are 28 community owned affected structure / assets including mosques, school and a wall. The loss to these structures is compensated adequately on replacement cost basis. The extent of impact both in quantity and estimated costs has been summarized in Table 10 and details are provided in Annex-3.

Table 14: Valuation of Affected Community Owned Structures/Assets

Sr. No Detail of Structure

No. of Structures

Total Area (ft2)

Unit Rate (Rs./ ft2 )*

Total Cost

(Rs. M.) Community Structures (Mosque Rooms, Verandhas and walls etc) Pacca T&G 4 945 710 670950 Sabeel Room Pacca T&G 1 64 710 45440

Total 5 716390 6.5 Compensation for Public infrastructure/Assets 77. The survey has revealed that 4 structures falling in public infrastructure category are being affected in this sub-project. Out of 4 two are the police checkposts constructed in the encroached ROW by the government departments i.e sindh rangers/police, while two are the bus waiting rooms constructed for passengers. The structures include rooms used as police and customs check posts Nonetheless, two structures include the community bus stands along the road corridor near settlements. All the concerned departments will be requested to clear the ROW by relocating the identified structures at their own. However, if required the structures/assets may be compensated on replacement cost basis through relevant departments. To meet the financial implications (if any) the cost of all the structure encountered during census survey is worked out on replacement cost basis in accordance with unit rates provided by the C&W department of respective district. The details of the structures and the cost estimates are provided in table 11 below.

30

Table 15: Valuation of Affected Public Structures/Assets

Sr. No. Detail of Structure

No of Structures

Total Built-up Area (ft2)

Unit Rate (Rs./ ft2 )* (approved June 2011)

Total Cost (Rs. M.)

Public Infrastructure Pacca Rcc Rooms 2 528 850 212530 Kacha 2 802 265 448800 Total 4 661330

* Approved unit rates by the concerned Department, June, 2011, e.g Works and Services Department, Buildings Department, District Shikarpur. 6.6 Compensation for Crop Losses 78. 35.5 Acres of land is acquired for Shikarpur by pass for which crop compensation is to be provided to the entitled persons as per provisions of the entitlement matrix. There are 66 entitled persons for crop compensation out of which 58 are the land owners and remaining 8 are Haris (sharecroppers). The appendix-1 provide the details about the entitled crop compensation for each AF, however, table below depict summary costs to be disbursed for each category with respect to the crop loss and severity impact allowance to the extent of their entitlement.

Table 16: Valuation of Affected Crops

Persons entitled

Area Cropped

AFs Cost for crop compensation

Cost for Severity Impact

Total Cost

(acre) No Unit

rate/Acre

Cost RsUnit

rate/Acre

Cost Rs Rs

Land owners 35.5 58

83774

2718927

41887

1348992

4067919

Share Croppers Included in above

8 218943

109472

328415

Total 66 4396334 6.7 Compensation For Tree Losses 79. There are total 423 privately owned trees grown in land acquired for Shikar pur Bypass. Out of these 423 tree 109 trees are fruit trees including date palm, mango, bain and jaman and 314 timber wood tress of different species. The total estimated cost for compensation tree losses is calculated on the basis of unit rates provided by the Agricultural Extension wing Shikarpur Agricultural department and Forest departments. The tables below provide estimated compensation for fruit and timber wood trees,

Table 17A: Valuation of Affected Fruit Tree

Name of Tree No. of Trees

Unit Rate(Rs./ Tree)/year (Ref.

para 40) Compensation for No of Years

Replacement Value (Rs.)

Privately owned Fruit Trees Date palm 65 6,250 5 2031250Mango 33 10,800 5 1782000Bain (Bair) 10 2,000 5 100000Jaman 1 6,000 5 30000

Total 109 - 3943250

31

Table: Table 17 B: Valuation of Affected Timber Wood Trees

Name of Tree Total No. of Trees

Classification Girth and No of trees

Unit Rate/tree

Total Value (Rs)

Shisham (Dalbergia sisso)

58

Up to 2' girth 41 2000 82,0002'-4' girth 14 5000 70,0004'-6' girth 3 12000 36,000

Kikar (Acacia nilotica)

67

Up to 2' girth 33 1000 33,0002'-4' girth 31 2000 62,000

4'-6' girth 3 3500 10,500Shareen (Sarsh)

9

Up to 2' girth 2 1000 2,0002'-4' girth 7 2000 14,000

Majhandri 180 180 175 31,500

Total 314 314 341,000 6.8 Provisions for Compensatory Plantation 80. In total 234 trees owned by the Forest Department, which will be removed from ROW to execute project civil works. Out of these 231 trees are the timber wood trees while 3 trees of different size and age are the date trees grown within the ROW limits. The NHA will request Forest Department for removal of these trees to avoid any damage and consequent compensations to forest department. However, for replenishment of these trees, compensatory plantation at a ratio of 1:10 is proposed in consultation with Forest Department and will be carried out by NHA under supervision of afforestration wing in EALS Section. The adequate budgetary provision is made in civil works contract in BOQ (Bill No 6 “ancillary works”). So, this updated RP (Section-III) do not include cost for compensatory plantation. 6.9 Relocation Options 6.9.1 Privately owned Structures 81. Residential structures of 12 AFs falling in the alignment of Shikarpur by pass are subject to relocation due to land acquisition. The owners of these structures (AFs) do not have legal title of the land on which these structures are located and thus they are not entitled for replacement land or compensation of land. During consultative meetings the AFs affirmed that they have alternate land available in same locality (about 500~700 meter away from existing site) to relocate their residential structures at their own. So, these structure owners have been provided with relocation assistance15 as per entitlements proposed in the approved Resettlement Frame work to compensate any adverse impact on their income during relocation of their residential structures at alternate place. All such AFs will be compensated for the loss of structure on replacement cost basis, relocation assistance allowance equivalent to 3 months income calculated on the basis of minimum official wage rate in addition to transport allowance for shifting of salvage material and other entitled allowances. The cost of relocation assistance is estimated to be Rs. 252000. While, the four commercial structures falling under project impacts are constructed by encroaching land within the RoW of existing carriageway, by the adjoining land owners. The owners of these structures will be compensated for structures only at replacement cost basis as per entitlement provision provided in the approved resettlement frame work for NHDSIP. Besides compensation of structure loss, for transportation of salvage material to structure owners and shifting of business articles to business renters a lump sum amount as

15 The relocation assistance is provided to the 12 residential structure owners only to provide them financial

assistance during construction and relocation of their residential structures at alternate place.

32

transportation allowance will be provided to each entitled AH16. Alternate land or compensation for land will not be provided to relocate these structures. During consultative meetings the structure owners affirmed that they will rehabilitate their remaining structure outside ROW or reconstruct new structure at their own in their land available outside ROW. 6.9.2 Religious Structures 82. The most of the mosques are constructed along the road in ROW by the adjoining land owners for providing prayer places to the passersby. All mosques will need to be relocated due to project works. Construction of dual carriageway will left no space to reconstruct or relocate these structures in the nearby NHA owned ROW. Thus NHA will provide compensation for structures on replacement cost basis while, the Community/Custodians of these community structures will relocate and reconstruct these religious structures outside ROW. 6.93 Additional Assistance for Vulnerable Households 83. 31 AFs falling in structure owner and business renter category having per-capita monthly earnings below Rs. 1200 are identified as vulnerable. For such households, in addition to the compensation for their affected assets, an additional allowance of Rs. 7000 (amount equal to minimum official wage rate) will be paid as additional assistance. The amount of compensation to be paid on this account comes to be Rs. 217,000/=. 6.10 Income Restoration 84. It is anticipated that the project will make a positive impact on the economy of the area in general. A number of business and employment opportunities will be created during the construction and operation phase, for the business entrepreneurs and skilled/un-skilled labor respectively resulting into increased economic activity in the project corridor. However, to compensate the adverse impacts on source of livelihood due to loss of agricultural land and commercial structures the crop compensation, severity impact allowance due to land loss (See para 73 above) and business/employment interruption allowance is provided on the basis of entitlement matrix (table 10) prepared in accordance with approved Resettlement Framework for NHDSIP. The table 18 below gives the detail of the AFs facing business/employment loss and their entitled compensation.

Table 18: Estimation of Livelihood Allowance for Affected Households Sr. No.

Type of Loss AHs (Nos.) Allowance Rate** Total (Rs.)

1

Temporary Loss of Income a. Structure/business

owners b. Business Renters

2

3

21000

14000

42000

4200

2 Employment loss 1 7000 7000

Total: 6 - 91000 ** The allowance rate is based on the approved official wage rate @ Rs: 7000/month and for each category is calculated on the basis provided in EM i.e:

Permanent loss of income = 6 months x official wage rate. Temporary loss of income = 3 months x official wage rate . Business renters = 2 months x official wage rate. Employee = 1 months x official wage rate.

16 As a matter of equity, the transportation allowance is provided to all AFs facing loss of structure

(permanent/partial) or business renter to handle/shift/transport salvage material or shift business articles from impacted structure to new rented in structure. Detail of transportation allowance is provided in para 80.

33

6.11 Transportation Allowance 85. One time Transportation allowance is provided to All the AFs falling in structure owner and business renter categories, subject to shift/transport slavage material of their demolished structures or their business items from the impacted structure to alternate place. In total 19 AFs are entitled for Transportation Allowance for which Rs. 95000/- is provided in the budget. 7. INSTITUTIONAL ARRANGEMENTS 86. Overall responsibility for planning, implementation and monitoring of the Land Acquisition and Resettlement activities in accordance with the agreed LARF and loan agreement rest with the Executing Agency i.e NHA. The EA has a compact institutional setup for managing all LAR activities. NHA has appointed a Member for Aided Projects, and in his supervision a General Manager ADB Projects and General Manager Environment, Afforestation, Land and Social (EALS) wing at Head Quarter are working with an overall responsibility of ensuring safeguard compliance requirements under the aided Projects.

87. The NHA will exercise its all functions at project level through Project Management Unit/project directorate established at Sukkur. For updating, implementation and monitoring of the RP the project directorate will be facilitated by Land Acquisition and resettlement Unit, which will ensure timely establishment of Grievance Redress committees, Affected Persons and Citizen Liaison Committee, effective consultation and coordination with line department during prepration and implementation of the updated RP (Section-II).

7.1 Land Acquisition and Resettlement Unit at Project Level

88. At project level a Land Acquisition and Resettlement Unit has been constituted and notified for streamlining of the Land Acquisition and Resettlement Activities relating to Sukkur Jacobabad (N-65) vide notification No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010, comprising of the following:

(i) General Manger (N-65) Chairman (ii) Project Director (N-65) Member (iii) DD (Environment) Member (iv) Resettlement Specialist, NHA Member (v) AD (L&S), HQ Coordinator

89. The scope of work of LAR Unit includes:

(i) The unit shall also act as a steering body for the LAR activities at the project and shall formally assemble once in a quarter. For routine LAR matters, special meeting/routine discussions can take place, as and when required.

(ii) It shall ensure timely implementation of LAR activities and monitor the progress thereon during execution of the civil works.

(iii) In order to efficiently deal with APs grievances, the unit shall coordinate on regular basis with the grievance redress and consultation committees (e.g. grievance redress committee and affected persons and citizens liaison committee; GRC and ACLC).

(iv) Resettlement and land staff of EALS to coordinate and visit the project office on regular basis to provide guidance to the project level LARU in implementing the updated RP (Section-II) and preparing the internal monitoring reports.

34

(v) LARU will have one male and one female social mobilizer to assist in consultation meetings, disclosure of project information, information sharing with APs related to disbursement of compensation and related tasks.

(vi) LARU and EALS shall review all RPs before submitting to ADB. (vii) All EALS in consultation with LARU shall submit the final RP to ADB for

review/concurrence. (viii) The LARU resettlement specialist shall prepare the internal monitoring

reports on monthly basis and provide to ADB for review. 7.2 Grievance Redress Cell. 90. The grievance procedures at different stages of the Land Acquisition is provided in the Land Acquisition Act 1894, but in case of grievance arising from non-land impacts and issues there is no statutory mechanism provided in the LAA 1894. In this context and inline with the requirements of LARF and ADB IR policy a grievance redress committee has been constituted and notified vide notification No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010.. The GRC will have following members and roles and responsibilities:

(i) Project Director Chairman (ii) Assistant Director (L&S-Resettlement) (Focal Member) (iii) LAC assisted by Patwari / Qanoongo (to deal with crops and related matters) (iv) Representative of ACLC Member (v) External monitoring consultant. Member

91. The scope of work of grievance redress cell/committee is discussed as below.

(i) The GRC shall prepare a register for the purposes of entering each and every complaint either received directly from the AP or through H.Q or other outside agencies i.e. EDOR / DOR office, irrigation department forest department etc.

(ii) These complaints shall be carefully categorized in separate heads as against price fixation of Land, crop, trees, structures etc. OR problems in relocation and seeking assistance for rehabilitation etc. Such complaints shall be disposed of within 30 days.

(iii) The focal person of GRC shall submit its reports containing detail status of implementation i.e. internal monitoring reports (IMR) and regarding the disposal of complaints / Grievance of APs to Chairman LARU and Chairman PMU on monthly basis.

(iv) Subsequent to receiving a formal complaint, LARU or EALS in consultation with project team (GM and PD) will review the complaint and inform ADB about the actions to be taken to resolve the complaint.

(v) The GRC shall ensure that all field visits and consultations with the APs are properly documented, snapped and recorded on the video; such record shall be placed in the Project Office (PO).

(vi) GRC after site visit shall prepare a report with recommendations and solution submits the same to the LARU/Project Directorate and resolves the problem accordingly.

(vii) GRC shall close the complaint file by communicating with complainant.

7.3 Affected Persons and Citizen Liaison Committee 92. For improved coordination between the Project Management Team, LAR Unit, GRC and the APs, an Affected Persons and Citizen Liaison Committee has been notified by EA vide Notification No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010 dated and comprised of following:

35

(i) Assistant Director (L&S; resettlement specialist) (ii) Tapedar / Patwari (iii) Social Mobilizer (iv) Representative of affected village Member of ACLC

93. The ACLC will be responsible for the following activities:

(i) Shall establish the accessible information and conduct frequent consultative meetings with APs.

(ii) Publicity of the designated office from where all information regarding alignment, design, road maps, (naqsha parcha) Revenue Maps of land to be acquired, price assessment and information regarding complaints status/ redress can be obtained by the APs, with name of the focal person to contact with. Mobile phone no. of all personnel of this unit must be mentioned for the convenience of the APs.

(iii) It will also include announcement from village mosque. (iv) Shall place posters containing relevant information; on the particular places

in the villages from where land has been acquired. (v) ACLC will ensure that the ‘LARP preparation Consultants’ MUST include all

the affected persons (APs) along with the details of their property held e.g. land, structures, trees, crops, shops etc. Preparation of LARP shall be strictly in the light of LARF mutually prepared by NHA and ADB.

(vi) The ACLC shall ensure that all field visits and consultations with the APs are properly documented, snapped and recorded on the video; such record shall be placed in the ACLC and GRC office.

(vii) In parallel, Land acquisition activity after publication of section 4 is followed by the correct assessment price of land. The ACLC at the project shall ensure that adequate, just and proper price compensation is determined.

(viii) The team of LARP preparation Consultants’ when mobilized shall be accompanied by officers / officials / members of ACLC and members of EALS if deputed by the H.Q. this is for the reason to avoid variation in reports, plans and to address the issues immediately on site.

(ix) This inter-alia officers and members of ACLC shall include: i) Disclosure and sharing of information to APs, ii) Information through the local notables, Councilor and Chairman of the union Council; and iii) Distribution of copies of LARP in local language, prices of land and award must be disclosed to the local at this stage.

94. An Organogram showing the institutional arrangements for the implementation of land acquisition and resettlement activities has been illustrated through a diagram presented in Figure 4.

36

Figure 4: Institutional set-up for the Implementation of updated RP (Section-III)

General Manger Project Director DD (Environment) Resettlement Specialist, NHA AD (L&S), HQ

Grievance Redress Cell (GRC)1. Project Director PD (N-65) 2.Assistant Director (L&S) 3. LAC assisted by patwari/Qanoongo 4. Representative of ACLC 5. EM Consultant

GM (Aided Projects)

GM (EALS), HQ

APs/ Local Community

District Level Departments

Member (Aided Projects)

EMA

Contractor

Consultants

Revenue Department (DOR/ LAC) Agri. Department Forest Department W&C department WAPDA Telecommunication Other concerned

LAR Unit (Sukkur)

APs & Citizens Liaison Committee (ACLC) 1. Assistant Director (L&S) 2. Tapedar/Patwari 3. Social Mobilizer 4. Representative of Affected Village ACLC

37

8. IMPLEMENTATION SCHEDULE OF UPDATED RP (SECTION-II)

95. Considering the magnitude of resettlement impact and other property issues, it is expected that the Project Directorate will be able to implement the updated RP (Section-II) in 2 to 3 months from 10 December to January 31, 2011. Within this timeframe, the updated RP (Section-II) milestones will be implemented as per following time schedule (Table 19).

Table 19: Implementation Schedule of LARP

Action Timeline (Year 2011)

Responsibility

To date Status

Updated RP (Section-II) Implementation

Establishment of Project Management Unit (PMU) at Sukkur

- NHA PMU is already in place at Sukkur.

Setting-up the LAR Unit (LARU)

- NHA LARU has already been notified vide NHA office letter No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010.

Establish Grievance Redress Cell (GRC)

1st July - NHA GRC has already been notified vide NHA office letter No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010.

Establishment of ACLC 1st July - NHA ACLC has already been notified vide NHA office letter No. 1(1)/NHA/EALS/2009/49 dated 17-8-2010.

Approval of updated RP (Section-II)

December 10,,2011

ADB -

Urdu/Sidhi translation and disclosure of updated RP (Section-II)

December 20, 2011

PD/ LAR Unit

To be done.

Payments for Crop Losses, structures and all potential impacts

January 30, 2012.

LARU/APs -

Payments of allowances January 30, 2012.

LARU/APs -

Internal Monitoring report of updated RP (Section-II)

Monthly- First Report January 10. 2012.

LARU To be done.

Date of contract award 31st Oct. 2010 - - Commencement of civil works in Section-II

February, 2012 - -

Redress of community complaints

Continuous activity

GRC/ LARU

This will be a continuous activity till project completion.

38

External monitoring External Monitoring Report confirming full implementation of Updated RP. January 30, 2012.

EMA Field survey to be completed by the Feburary 01, 2012.

9. RESETTLEMENT BUDGET 96. The RP section –II includes Land acquisition for construction of 4.9 Km of Shikarpur by pass for which the land costs amounting Rs. 12317142 had been deposited in the treasury since 2008 as per announced award on 10-1-2008. About 81 % APs had already received compensation against land cost from Land Acquisition Collector while the disbursement of land costs for remaining APs is in process. No further amount in lieu of land costs is envisaged at this stage so the budget of updated RP do not include additional budgetary provision for land costs. 97. The resettlement budget includes (i) crop and tree compensation for land owners facing loss of land due to Shikarpur by pass, (ii) costs of residential /commercial structures, (iii) community infrastructure, (iv) public and private structures, (v) other entitled allowances for AFs as per entitlement and other costs (i.e., independent monitoring and evaluation etc.). As shown in Table , the total cost for resettlement is estimated to be of Rs. 37536559 /= equivalent to US $ 623028. 98. Upon EA’s request ADB has agreed to finance implementation of resettlement plans from available contingencies amount under approved loan and required funds have been re-appropriated for resettlement costs. Thus, the EA (NHA) has provided the above amount of budget to implement this LARP in an efficient and timely manner during the course of the project (Table 20). 99. However, the finances from loan component shall not be utilized for payment of land acquisition costs. The Loan part shall be exclusively used for making payments against resettlement costs attributed to encroachers/squatters for their assets (excluding land) and other resettlement entitlements/allowances to AFs/APs as proposed in the Entitlement Matrix of this updated Resettlement Plan. An itemized budget for implementation of the updated Resettlement Plan (Section-II) is as under:

Table 20: Resettlement Budget

Sr. No. Detail of Structure No of

StructuresTotal Area

(ft2) Unit Rate (Rs./ ft2 )*

Total Cost (Rs. M.)

A Land and land based Assets

Cost of Land including all charges with 15% compulsor surcharge deposited in treasury

A Land Cost 35.2 Acres 300000 12317142

B Private Structures (Resdential and Commercial) (i) Pacca T-Iron Girder 9 1431 710 1016010(ii) Katcha 6 713 265 188945(iii) Girder and Wooden Roof 15 4391 530 2327230 Sub Total C 30 3532185

39

C Others

(i) Walls upto 5 feet height (Pacca) 4 76Rft 870 66120

(ii) Walls upto 5 feet height (Kacha) 2 39.5 Rft 150 5925

(iii) Chapra 4 626.5 100 62650(iv) P Pump Logo 1 1 60000 60000(vi) Hand Pumps 7 7 6000 42000

Sub Total C 18 236695D Public Infrastructure (i) Pacca Rcc Rooms 2 528 850 448800

(iii) Kacha 2 802 265 212530 Sub Total D 4 661330E Community Structures (Rooms, Verandhas and walls etc) (i) Pacca T&G 5 1009 710 716390

Total Sub Total E 5 716390

F Crops Compensation cost and severity impact allowence

Crop Compensation 35.5 Acres 83774 2937870

Severity Impact Allowance 35.5 41887 1458463

Sub Total F 4396333

G Tree Compensation (Privately owned fruit and timber wood trees

Fruit Trees 109 Different 3943250

Timberwood Trees 314 Different 341000 Sub Total G 4284250

H Other Costs (i) Assistance Allowance to

vulnerable APs AFs 31 7000 217000(ii) Restoration of Livelihood / Business Loss

a) Structure owners with temporary income loss AFs 2 21000 42000

b) Business Renters AFs 3 14000 42000

c) Employees AFs 1 7000 7000(iii) Transportation allowance AFs 19 5,000 95000(iv) Relocation assistance AFs 12 21,000 252000 Sub Total H 403000 Total (B+C+D+E+F+G+H) Cost (Rs.) 14230183

Monitoring & evaluation 1% Job 1 142301.83

Contingencies (@10%) 1423018.3

Total Cost (Rs.) 15795503

US$ @ of 87 Rs/$ 181557.507*Approved unit rates by the concerned Department, June, 2011, e.g Works and Services Department, Buildings Department, Forest Department District Shikarpur.

40

10. MONITORING AND EVALUATION 100. The LAR activities under the Project will be subjected to both internal and external monitoring. Internal monitoring will be carried out by the Project Directorate, Sukkur through its LAR Unit with the assistance of resettlement specialist of supervisory consultants, while the external monitoring will be conducted by an independent external monitoring agency (EMA), which has already been deployed under the project. External monitoring reports will be prepared quarterly and semi-annually during the first and second year respectively of the implementation of the project.

10.1 Internal Monitoring

101. The internal monitoring will be carried out periodically by the LARU (NHA). Their results will be communicated to ADB through the monthly project implementation reports. The internal monitoring reports will cover these aspects:

(i) Information dissemination and consultation with APs; (ii) Implementation of entitlement matrix (iii) Payments for loss of income; (iv) Selection and distribution of replacement land areas (if required) (v) Income restoration activities; and (vi) Grievance/ complaints redress mechanism (vii) Physical and financial progress of LAR activities bifurcating the GoP and

Loan components separately (viii) Other

10.2 External Monitoring 102. The external monitoring will be done on quarterly basis by an external monitoring agency to examine the process involved for the implementation of resettlement policy framework/ entitlement matrix and grievance redress mechanism. External monitoring will be carried out on quarterly basis during the first year and bi-annually during the second year of the project implementation. There would be the final external monitoring report after the completion of resettlement activities. 103. As it is indicated earlier that there will be no land acquisition involved in this section of the project, so that the proposed timeline given to implement this updated RP (Section-II), as per proposed plan given in the updated RP (Section-III) implementation schedule and compensation for the loss of trees and other assets will also be completed. On the completion of LAR activities of this section, the external monitoring report will be prepared. In this context, an independent external monitoring agency has already in place and will be involved till the completion of the LAR activities for the whole project. 104. In general, the indicators for External Monitoring will include the following:

(i) Review and verify internal monitoring reports prepared by the Project Directorate, Sukkur;

(ii) Review of the socio-economic baseline information during the pre-project conditions;

(iii) Impact assessment through interviews, group discussions/ community consultations using structured and semi-structured data collection formats;

(iv) Review the status of implementation of compensation matrix (v) Review the mechanism and status of community complaints (vi) Assess the resettlement efficiency, effectiveness, impact and sustainability,

drawing lessons for future resettlement policy formulation and planning.

41

105. Regarding external monitoring, an external monitoring agency has been in place since April, 2010. On the approval of updated RP (Section-II) and its subsequent implementation the external monitoring report will be prepared and submitted to ADB confirming the Resettlement Plan is fully implemented before commencement of civil works. A tentative date for the completion of field survey will be the mid of January, while the report will be submitted before Feburary 15, 2012.

42

ANNEXURES

43

44

ANNEX-1: Land Award Announced by LAC/Deputy District Officer Revenue Shikarpur.

45

46

47

48

ANNEX: 2  INVENTORY FOR LAND ACQUISITION WITH COMPENSATION STATUS, (SHIKARPUR BY PASS), SECTION‐II

S# 

Location  Affected House Hold  Land Acquired   Compensation Status 

Chainage 

Settlement 

ID No  Name of AF Araea 

AcquiredAcres 

Award AnnouncedDtae/year

Awarded price/Acre + 15 % Comp 

ChargesRs

Payable Amount

Payment Status

Amount Paid (Rs) 

Out Stan‐ding (Rs) 

Voucher No. Paid on Remarks/Reasons for 

delyed payment  

26+100~31+00 

Shikarpur Bypass 

1  Rahib Ali S/O Iqbal Ahmed Lashari  1.025  9/1/2008 345000 353625 353625     45  2/2/2011    

2  2  Nizamulddin S/O Pathan Khan Mahar  0.275  9/1/2008 345000 94875 94875     G 806899  10/9/2008    

3  3  Mohd Saleh S/O Ali Mohd Lashari  0.625  9/1/2008 345000 215625 215625     G 807900  25/09/2008   

4  4  Mohd Daim S/O Mohd Sadique Shaikh  0.350  9/1/2008 345000 120750 120750     G‐806894  7/8/2008    

5  5  Manthar Ali S/O Mohd  Sachal Shaikh  0.350  9/1/2008 345000 120750 120750     G‐806895  7/8/2008    

6  6  Qadir Bux Alias Sawai S/O Imam Bux  0.250  9/1/2008 345000 86250 86250     191  29/04/2010   

7  7  Shamasuddin S/O Nangar Ali Bhutto  0.450  9/1/2008 345000 155250 155250     G‐806890  12/1/2008    

8  8  Mohd. Panjal S/O Arbab Khan  Bhutto  0.425  9/1/2008 345000 146625 146625     L‐168802  18/03/2009   

9  9  Khan Mohammad S/O Gaman Khan  0.563  9/1/2008 345000 194063 194062     L168809  17/03/2010   

10  10  Lal Shah S/O Hyder Shah  0.563 9/1/2008 345000 194235    194235      

Payment still a waited Due to Tranfer of Recod of Rights 

11  11  Abdul Rasheed S/O Ghulam Nabi Bhutto 1.025 

9/1/2008 345000 353625    353625      

Payment still a waited Due to Tranfer of Recod of Rights 

12  12  Manzoor Ahmed Mahar   0.150 

9/1/2008 345000 51750    51750      

Payment still a waited Due to Tranfer of Recod of Rights 

13  13  Tariq Ahmed S/O Mohd Ramzan  0.025  9/1/2008 345000 8625 8625     45  2/2/2011    

14  14 Altaf Ahmed S/O Abdul Hameed Soomro 

0.525 9/1/2008 345000 181125 181125     172  11/4/2011    

15  15  Faiz Mohd S/O Allah Dino Mahar  0.175 

9/1/2008 345000 60375    60375      

Payment still a waited Due to Tranfer of Recod of Rights 

16  16  Ghulam Rasool S/O Mohd Chutal Bhutto 0.650  9/1/2008 345000 224250 224250     L‐168801  15‐11‐2008   

49

S# 

Location  Affected House Hold  Land Acquired   Compensation Status Chainage 

Settlement 

ID No  Name of AF Araea 

AcquiredAcres 

Award AnnouncedDtae/year

Awarded price/Acre + 15 % Comp 

ChargesRs

Payable Amount

Payment Status

Amount Paid (Rs) 

Out Stan‐ding (Rs) 

Voucher No. Paid on Remarks/Reasons for 

delyed payment  

17  17  Nazeer Ahmed S/O Abdul Khaliq Bhutto 1.850 9/1/2008 345000 638250 638250    

L‐168808    L168803 

10/3/2010   04/03/2009   

18  18 Abbas Ali S/O Noor Mohd Bhutto 

0.100 9/1/2008 345000 34500 34500     L‐168811

22/08/2010    

19  19 Hakim Ali S/O Kareem Bux Mahar 

0.650 9/1/2008 345000 224250 224250    L‐168807 6/5/2009   

20  20 Mohd Ashraf S/O Shafi Mohd Bhutto 

0.825 9/1/2008 345000 284625 284625    L‐168805 7/3/2009   

21  21 Long Khan S/O Mohd Ibraheem ( M. Ayoub) 

0.350 9/1/2008 345000 120750 120750    L‐168804 3/3/2009   

22  22 Badarudin S/O Mohd Saleh Soomro 

1.200 9/1/2008 345000 414000 414000    168  11/4/2011   

23  23 Sikandar Ali S/O A. Hameed Soomro 

0.750 9/1/2008 345000 258750 258750    174  11/4/2011   

24  24  Bello Khan Bhutto  0.100 

9/1/2008 345000 34500    34500      

Payment still a waited Due to Tranfer of Recod of Rights 

25  25  Khuda Bux Bhutto (Mst Zuhran)  0.775  9/1/2008 345000 267375 267375    151  12/4/2010   

26  26  Mohd Ali S/O Sabir Ali   1.500 9/1/2008 345000 517500 517500    193 

23/04/2011    

27  27 Hakim Ali S/O Mughal Khan  Banglani 

0.521 

9/1/2008 345000 179745    179745      

Payment still a waited Due to Tranfer of Recod of Rights 

28  28  Ali Murad S/O Shahbazi Malik  1.000  9/1/2008 345000 345000 345000    349  9/7/2010   

29  29  Ghulam Hyder S/O Veeram 0.500 9/1/2008 345000 172500 172500    336  7/7/2011   

50

S# 

Location  Affected House Hold  Land Acquired   Compensation Status Chainage 

Settlement 

ID No  Name of AF Araea 

AcquiredAcres 

Award AnnouncedDtae/year

Awarded price/Acre + 15 % Comp 

ChargesRs

Payable Amount

Payment Status

Amount Paid (Rs) 

Out Stan‐ding (Rs) 

Voucher No. Paid on Remarks/Reasons for 

delyed payment  

Khan Banglani

30  30 Mohd Hassan S/O Veeram Khan Banglani

0.400 9/1/2008 345000 138000 138000    283 

30/06/2011    

31  31 Shahzado S/O Mohd Hassan Khoso 

0.150 

9/1/2008 345000 51750    51750      

Payment still a waited Due to Tranfer of Recod of Rights 

32  32 Abdullah Shaikh  S/O Haji Mir Mohd Shaikh  

0.475 9/1/2008 345000 163875 163875    450 

24/09/2010    

33  33 

Jamaluddin Khoso 0.300 9/1/2008 345000 103500 103500    91  2/3/2011   

Abdul Khaliq 0.650 9/2/2008 345000 224250 224250    201 

23/04/2011    

34  34 Raban Khan S/O Mohd Hassan Luhar 

0.600 9/1/2008 345000 207000 207000    487 

14/10/2010    

35  35 Ghulam Hussain S/O Mohd Bux Luhar 

0.100 9/1/2008 345000 34500 34500     486 

14/10/2010    

36  36 Rahim Bux S/o Qalandar Bux Mari Baloch 

0.150 9/1/2008 345000 51750 51750     183 

18/04/2011    

37  37 Mohd Murad S/O Piral Khan Mari 

0.175 9/1/2008 345000 60375 60375     460 

29/09/2010    

38  38 Piral Alias Pir Bux S/o Haji

Abullah Chohan 0.575

9/1/2008 345000  198375

103500    254 

   20/05/201

0     

94875     266 19/05/201

1    

39  39  Gul Sher S/O Abdullah Chohan  0.525 9/1/2008 345000 181125 181125    242 

18/05/2010    

51

S# 

Location  Affected House Hold  Land Acquired   Compensation Status Chainage 

Settlement 

ID No  Name of AF Araea 

AcquiredAcres 

Award AnnouncedDtae/year

Awarded price/Acre + 15 % Comp 

ChargesRs

Payable Amount

Payment Status

Amount Paid (Rs) 

Out Stan‐ding (Rs) 

Voucher No. Paid on Remarks/Reasons for 

delyed payment  

40  40 Gh Rasool S/o Mohd Soomar  Chohan 

2.000 9/1/2008 345000 690000 690000    366 

22/07/2010    

41  41  Zulfiqar Ali S/O Ali Nawaz Luhar 0.625 9/1/2008 345000 215625 215625    241 

18/05/2010    

42  42  Ghulam Sarwar Soomro  3.000 9/1/2008 345000

1035000   

1035000       Court Matter 

43  43 Ali Dost S/O Wadal Khan Luhar Baloch 

0.550 9/1/2008 345000 189750 189750    225  11/5/2010   

44  44 Tofique Ahmed S/O Mohd Waryal Abbasi 

0.275 9/1/2008 345000 94875 94875     398  3/8/2010   

45  45  Bijar Khan S/O Jan Mohd Brohi  0.800 

9/1/2008 345000 276000    276000      

Payment still a waited Due to Tranfer of Recod of Rights 

46  46 Abdul Hameed S/O Bahadur Khan Shaikh 

0.975 9/1/2008 345000 336375             Court Matter 

47  47 Abdul Wahab Sanjrani (Rasool Bux) 

0.675 9/1/2008 345000 232875 232875    G‐806891

23/01/2008    

48  48 Maqbool Ahmed S/O A. Rehman Shaikh 

1.500 

9/1/2008 345000 517500    517500      

Payment Still awaited due to aggrioved  to Land Rate 

49  49 Nawab Khan S/O Mohd Khan Khoso 

0.525 9/1/2008 345000 181125 181125    168810 

22/03/2010    

50  50 Sajjad Ahmed S/O Yar Mohd Kalhoro 

0.325 9/1/2008 345000 112125 112125    399  3/8/2010   

51  51  Umed Ali S/O Dilawar Khan  0.025  9/1/2008 345000 8625 8625     400  3/8/2010   

52

S# 

Location  Affected House Hold  Land Acquired   Compensation Status Chainage 

Settlement 

ID No  Name of AF Araea 

AcquiredAcres 

Award AnnouncedDtae/year

Awarded price/Acre + 15 % Comp 

ChargesRs

Payable Amount

Payment Status

Amount Paid (Rs) 

Out Stan‐ding (Rs) 

Voucher No. Paid on Remarks/Reasons for 

delyed payment  

Kalhoro 

52  52  Mehmood Ahmed Soomro  0.225 

9/1/2008 345000 77625    77625      

Payment still a waited Due to Tranfer of Recod of Rights 

53  53  Amanullah  Soomro  0.203 

9/1/2008 34500069862.

5    69862.5      

Payment still a waited Due to Tranfer of Recod of Rights 

54  54  Paryo S/O Mohd Azeem Mahar  0.100 

9/1/2008 345000 34500    34500      

Payment still a waited Due to Tranfer of Recod of Rights 

55  55  Iqbal Ahmed Pathan  0.263 

9/1/2008 345000 90735    90735      

Payment still a waited Due to Tranfer of Recod of Rights 

56  56  Liaqat Ali   0.263 

9/1/2008 345000 90735    90735      

Payment still a waited Due to Tranfer of Recod of Rights 

57  57 Mohd Ramzan S/O M. Sharif Brohi 

0.700 9/1/2008 345000 241500 241500    G‐806897

16/08/2008    

58  58 Mohd Sharif S/O Bahadur Khan Brohi 

0.525 9/1/2008 345000 181125 181125    G‐806896

13/08/2008    

53

ANNEX 3: INVENTORY OF OWNERS OF AFFECTED STRUCTURES

S#

Location Affected House Hould Structure category, type and Affected Area

Chainage

Road Side Settlement

Name F. No

AP Name/Depertment Structure Category

Structure affetced

Structure type

H L W Area L/R Ft Ft Ft Sq.Ft

1 20+950 L  Habib Kot 1 Ubdedullah Mahar Commercial Shop  Paka(T&G)    5  14  70 

2 L  Habib Kot 2 Deedar Hussain Mahar Commercial Shop 

Kacha (Mud) 8  14  112 

Commercial Shop Kacha (Mud) 8  14  112 

3 24+000 R  Jamra Stop 3 Hamadullah Commercial

P.O.L Logo (Hescol)           1.No 

4

26+800

Vill at ByPass

4 Kandiro Private House Room  Paka (GWR)    

17.66 

18.50  326.71 

L Private

House Varanda  Paka (GWR)    

17.66 

12.75  225.165 

5 L 

5 Allah Dino Private House Room  Paka (GWR)     9  16  144 

L Private

House Varanda  Paka (GWR)     8  9  72 

6

6 Soomar Ali

Private House Room  Paka (GWR)     12  16  192 

  Private

House Varanda  Paka (GWR)     8  12  96 

  Private Kittchen Wall  Kacha (Mud)  2 

17.3  0  17.3 

7

C/L

7 Punahal Private House Room  Paka (GWR)    

14.75 

13.42  197.945 

C/L Private

House Varanda  Paka (GWR)     8 

13.42  107.36 

Private Kittchen Wall  Paka  4  19     19 

8 C/L

8 Dilawar Private House Room  Paka(T&G)     11 

12.66  139.26 

Private

House Varanda  Paka(T&G)     12  9  108 

9 C/L

9 Sikander Ali Private House Room  Paka(T&G)     12  12  144 

Private House  Paka(T&G)     12  9  108 

54

S#

Location Affected House Hould Structure category, type and Affected Area

Chainage

Road Side Settlement

Name F. No

AP Name/Depertment Structure Category

Structure affetced

Structure type

H L W Area L/R Ft Ft Ft Sq.Ft

Varanda

10 C/L 10 Sher Mohammad Private Wall   Kacha (Mud)  5  22     22 

11 C/L 11 Gh: Mustafa Private Room  Kacha (Mud)     14  14  196 

12 C/L 12 Rahmatullah Private

Chapra(Wooden)  Kacha     13 

13.58  176.54 

13

C/L C/L

13 Imam din

Private Room  Paka(T&G)    13.66 

13.58  185.5028 

Private Bath Room Wall  Paka  5 

17.5     17.5 

Private Bath Room Wall  Paka  5 

17.5     17.5 

Private Hand Pump              1.No 

14

C/L

14 Shahzore

Private House Room   Paka (T&G)    16.33 

12.75  208.2075 

Private Bath Room Wall  Paka  5  22     22 

Private Hand Pump              1.No 

Private Hand Pump              1.No 

15 C/L 15 Gul Bahar Private Room  Kacha (Mud)     15  12  180 

13

28+725  C/L Banglani Vill: at By

Pass

29 SB 

Gh: Hyder Banglani

Private Room (Cattles) Paka (GWR)    24  16  384 

Private Room (Cattles) Paka (GWR)    20  16  320 

Private House Room Paka(T&G)    13  18  234 

Private House Room Paka(T&G)    13  18  234 

Private House Varanda Paka (GWR)    29  13  377 

Private Kitchen Paka (GWR)    12  7.5  90 

Private Hand Pump          1.No 

55

S#

Location Affected House Hould Structure category, type and Affected Area

Chainage

Road Side Settlement

Name F. No

AP Name/Depertment Structure Category

Structure affetced

Structure type

H L W Area L/R Ft Ft Ft Sq.Ft

14

28+750 

30 SB 

Mohammad Hassan Banglani

Private House Room Paka((GWR)   

20.5 

15.75  322.875 

Private House Varanda

Kacha (Mud)    8  6  48 

Private Kittchen Kacha (Mud)    13  5  65 

Private Hand Pump          1.No 

Private

Cattle Wooden Shade Kacha    15  10  150 

15

30+970 

58 SB 

Mohd Sharif Brohi

Private House Room Paka (GWR)    50  30  1500 

Private Bath Room Paka (GWR)    6  6  36 

Private Hand Pump          1.No 

Private Chapra(Wooden) Kacha    10  15  150 

Private Chapra(Wooden) Kacha    10  15  150 

Private Hand Pump          1.No 

56

ANNEX-4: DETAILS OF AFFECTED PUBLIC AND COMMUNITY STRUCTURES/ INFRASTRUCTURES LOCATED WITHIN THE PROJECT ALIGNMENT A. Public Structures

S#

Location Public Structures located in ROW

Chainage Road Side Settlement Name AP Name/Depertment

Structure affetced Structure

type

H L W Area L/R Ft Ft Ft Sq.Ft

1  20+775  L  Jara Waha  Chowki  Rangers/Irigation Deptt Sindh Room    Kacha     26  21  546 

Room  Kacha     16  16  256 

2  20+980  L  Habib Kot  NHA (Main) Sukkur. Bus Waiting Room  Paka(RCC)     13  24  312 

3  24+325  R  Ejaz Phulapota   Local Govt.of Sindh (Shikarpur) Waiting Room   Paka(RCC)     12  18  216 

B. Community Structures

S#

Location Structure category, type and Affected Area

Chainage

Road Side Settlement Name

AP Name/Depertment Structure

Category Structure affetced

Structure type

H L W Area

L/R Ft Ft Ft Sq.Ft1 17+620 R Near Lakhi Masque Community Mosque Room Paka(T&G) 12 15 180 2 20+990 L Habib Kot Masque Community Masque Room Paka(T&G) 12 14 168 3 22+020 L Vill: Yaqoob Jatoi Masque Community Masque Room Paka(T&G) 16 17 272

4 24+180 L Jamra Stop Masque Community Masque Room Paka(T&G) 13 25 325 5 25+300 L Pir Zubair Pir Zubair Dargah Community Sabeel Room Paka(T&G) 8 8 64

57

ANNEX-5: DETAILS OF AFFECTED CROPS AND TREES DUE TO LAND ACQUISTION OF SHIKARPUR BYPASS

S# Chainage 

Settlement 

ID No.  Name of AF

Area Acquired 

Cultivation arrangement 

Tree with type and number  Crops 

Fruit Trees  Wood Trees Area Type of Crop  /  

Acres Self/Shar‐ecroping 

Share% Type  Nos  Type  Nos Acres  Croping Season

26+100~31+00 

Shikarpur Bypass 

1 SB  Rahib Ali S/O Iqbal Ahmed Lashari  1.025  Self   100%  Date Palm  2  Keker (B)  3  1.025 Wheat + Rice / Rabi + Kharif

2  2 SB  Nizamulddin S/O Pathan Khan Mahar  0.275  Self   100%  Date Palm  2 Keker (A)  2 

0.275 Wheat + Rice / Rabi + KharifKeker (B)  6 

3  3 SB  Mohd Saleh S/O Ali Mohd Lashari  0.625  Self   100%              0.625 Wheat + Rice / Rabi + Kharif

4  4 SB  Mohd Daim S/O Mohd Sadique Shaikh 0.35  Self   100%              0.350 Wheat + Rice / Rabi + Kharif

5  5 SB  Manthar Ali S/O Mohd  Sachal Shaikh  0.35  Self   100%              0.350 Wheat + Rice / Rabi + Kharif

6  6 SB  Qadir Bux Alias Sawai S/O Imam Bux  0.25  Self   100%        Kekar (A)  5  0.250 Wheat + Rice / Rabi + Kharif

7  7 SB  Shamasuddin S/O Nangar Ali Bhutto  0.45  Self   100%  Date Palm  3 

Shesham (B) 1 

0.450 Wheat + Rice / Rabi + Kharif

Kekar (A)  1 

Kekar (B)  3 

8  8‐SB  Mohd. Panjal S/O Arbab Khan  Bhutto  0.425  Self   100% 

Mango  15 

      0.425 Wheat + Rice / Rabi + Kharif

Date Palm  1 

Jaman  1 

9  9 SB  Khan Mohammad S/O Gaman Khan  0.563  Self   100%              0.563 Wheat + Rice / Rabi + Kharif

10  10 SB  Lal Shah S/O Hyder Shah  0.563  Self   100%              0.563 Wheat + Rice / Rabi + Kharif

11  11 SB  Abdul Rasheed S/O Ghulam Nabi  1.025  Sharecroppi 50%  Date Palm  3  Kekar(B)  1  1.025  Wheat + Rice 

58

Bhutto  ng  / Rabi + Kharif

12  12 SB  Manzoor Ahmed Mahar   0.15  Self   100%       Kekar (B)   2 

0.150 Wheat + Rice / Rabi + KharifMajhandri  180

13  13 SB  Tariq Ahmed S/O Mohd Ramzan  0.025  Self   100%              0.025 Wheat + Rice / Rabi + Kharif

14  14 SB Altaf Ahmed S/O Abdul Hameed Soomro 

0.525 Sharecroppi

ng 50%              0.525 

Wheat + Rice / Rabi + Kharif

15  15 SB  Faiz Mohd S/O Allah Dino Mahar  0.175 Sharecroppi

ng 50%              0.175 

Wheat + Rice / Rabi + Kharif

16  16 SB Ghulam Rasool S/O Mohd Chutal Bhutto 

0.65  Self  100% 

Date Palm  12  Kekar (A)  1 

0.650 Wheat + Rice / Rabi + Kharif

Mango  18 Kekar (B)  4 

Kekar (C)  1 

17  17 SB Nazeer Ahmed S/O Abdul Khaliq Bhutto 

1.85  Self  100%              1.850 Wheat + Rice / Rabi + Kharif

18  18 SB  Abbas Ali S/O Noor Mohd Bhutto  0.1  Self   100%              0.100 Wheat + Rice / Rabi + Kharif

19  19 SB  Hakim Ali S/O Kareem Bux Mahar  0.65  Self   100%              0.650 Wheat + Rice / Rabi + Kharif

20  20 SB  Mohd Ashraf S/O Shafi Mohd Bhutto  0.825  Self  50%              0.852 Wheat + Rice / Rabi + Kharif

21  21 SB  Long Khan S/O Mohd Ibraheem   0.35  Self   50%              0.350 Wheat + Rice / Rabi + Kharif

22  22 SB  Badarudin S/O Mohd Saleh Soomro  1.2  Self   100%              1.200 Wheat + Rice / Rabi + Kharif

23  23 SB  Sikandar Ali S/O A. Hameed Soomro  0.75  Self   100%              0.750 Wheat + Rice / Rabi + Kharif

24  24 SB  Bello Khan Bhutto  0.1  Self   100%              0.100  Wheat + Rice 

59

/ Rabi + Kharif

25  25 SB  Khuda Bux Bhutto  0.775  Self  100%              0.775 Wheat + Rice / Rabi + Kharif

26  26 SB  Mohd Ali S/O Sabir Ali   1.5  Self   100%  Date Palm  1 

Shesham (A) 

1 1.500 

Wheat + Rice / Rabi + Kharif

Shesham (B) 1 

27  27 SB  Hakim Ali S/O Mughal Khan  Banglani  0.95 Sharecroppi

ng 75%              0.950 

Wheat + Rice / Rabi + Kharif

28  28 SB  Ali Murad S/O Shahbazi Malik  1 Sharecroppi

ng 50%  Bain  4 

Shesham (A) 

18 

1.000 Wheat + Rice / Rabi + Kharif

Shesham (B) 6 

Kekar (A)  1 

29  29 SB Ghulam Hyder S/O Veeram Khan Banglani

0.5 Sharecropp

ing 50%

Bain  5 

 Shesham (A) 

22 

0.500 Wheat + Rice / Rabi + Kharif

Shesham (B) 6 

Shesham ( C) 

Date Palm  8 

Keker (A)  12 

Keker (B)  8 

Keker (C)  2 

Sherian(A)  2 

60

Sherian (B) 7 

30  30 SB Mohd Hassan S/O Veeram Khan Bangni

0.4 Self 100%             0.4 Wheat + Rice / Rabi + Kharif

31  31 SB  Shahzado S/O Mohd Hassan Khoso  0.15  Self  100%              0.15 Wheat + Rice / Rabi + Kharif

32  32 SB Abdullah Shaikh  S/O Haji Mir Mohd Shaikh  

0.475 Sharecroppi

ng 50%              0.475 

Wheat + Rice / Rabi + Kharif

33  33 SB Jamaluddin S/o Ghulam Hussain Khoso

0.95 Sharecropp

ing 50%  0.950 

Wheat + Rice / Rabi + Kharif

34  34 SB  Raban Khan S/O Mohd Hassan Luhar  0.6  Self  100%              0.600 Wheat + Rice / Rabi + Kharif

35  35 SB  Ghulam Hussain S/O Mohd Bux Luhar  0.1  Self  100%              0.100 Wheat + Rice / Rabi + Kharif

36  36 SB Rahim Bux S/o Qalandar Bux Mari Baloch 

0.15  Self  100%              0.150 Wheat + Rice / Rabi + Kharif

37  37 SB  Mohd Murad S/O Piral Khan Mari  0.175  Self  100%              0.175 Wheat + Rice / Rabi + Kharif

38  38 SB Piral Alias Pir Bux S/o Haji Abullah Chohan

0.575 Sharecropp

ing 50% 0.575 

Wheat + Rice / Rabi + Kharif

39  39 SB  Gul Sher S/O Abdullah Chohan  0.525  Self  100%              0.525 Wheat + Rice / Rabi + Kharif

40  40 SB Gh Rasool S/o Mohd Soomar  Chohan  2.000 Self  100%  2.000  Wheat + Rice 

61

/ Rabi + Kharif

41  41 SB Zulfiqar Ali S/O Ali Nawaz Luhar 0.625 Self  100%  0.625 Wheat + Rice / Rabi + Kharif

42  42 SB  Ghulam Sarwar Soomro  3  Self  100%              3.000 Wheat + Rice / Rabi + Kharif

43  43 SB  Ali Dost S/O Wadal Khan Luhar Baloch 0.55  Self  100%              0.550 Wheat + Rice / Rabi + Kharif

44  44 SB Tofique Ahmed S/O Mohd Waryal Abbasi 

0.275  Self  100%  Bain  1 Kekar (A)  2 

0.275 Wheat + Rice / Rabi + KharifKekar (B)  2 

45  45 SB  Bijar Khan S/O Jan Mohd Brohi  0.8  Self  100%              0.800 Wheat + Rice / Rabi + Kharif

46  46 SB Abdul Hameed S/O Bahadur Khan Shaikh 

0.975  Self  100%              0.975 Wheat + Rice / Rabi + Kharif

47  47 SB  Abdul Wahab Sanjrani   0.675  Self  100%       Kekar (A)  2 

0.675 Wheat + Rice / Rabi + KharifKekar (B)  2 

48  48 SB Maqbool Ahmed S/O A. Rehman Shaikh 

1.5  Self  100%  Date Palm  1  Kekar (A)  2  1.500 Wheat + Rice / Rabi + Kharif

49  49 SB  Nawab Khan S/O Mohd Khan Khoso  0.525  Self  100%              0.525 Wheat + Rice / Rabi + Kharif

50  50 SB  Sajjad Ahmed S/O Yar Mohd Kalhoro  0.325  Self  100%              0.325 Wheat + Rice / Rabi + Kharif

51  51 SB  Umed Ali S/O Dilawar Khan Kalhoro  0.025  Self  100%              0.025 Wheat + Rice / Rabi + Kharif

52  52 SB  Mehmood Ahmed Soomro  0.225  Self  100%              0.225 Wheat + Rice / Rabi + Kharif

53  53 SB  Amanullah  Soomro  0.2025  Self  100%              0.203 Wheat + Rice / Rabi + Kharif

54  54 SB  Paryo S/O Mohd Azeem Mahar  0.1  Self  100%              0.100 Wheat + Rice / Rabi + Kharif

62

55  55 SB  Iqbal Ahmed Pathan  0.263  Self  100%              0.263 Wheat + Rice / Rabi + Kharif

56  56 SB  Liaqat Ali   0.263  Self  100%              0.263 Wheat + Rice / Rabi + Kharif

57  57 Sb  Mohd Ramzan S/O M. Sharif Brohi  0.7  Self  100%              0.700 Wheat + Rice / Rabi + Kharif

58  58 SB  Mohd Sharif S/O Bahadur Khan Brohi  0.525  Self  100%  Date Palm  32  Kekar (A)  5  0.525 Wheat + Rice / Rabi + Kharif

 

   

  

 INVENTORY OF HARIS CATEGORY (SHARECROPPERS) WITH THEIR RESPECTIVE SHARE.  

ocat

on 

I.D No  Name of Share Cropper  Area  Type  Share Trees if any  Area  Crops 

26+100~31+000 

Shikarpur Bypass 

11‐1 SB  Mumtaz Ali Bhutto 1.025  Sharecroper 50%  No Trees to share croppers 

name     1.025 

Wheat + Rice / Rabi + Kharif

2  14‐1 SB  Azizullah S/O Rustam Ali 0.525  Sharecroper 50%  No Trees to share croppers 

name     0.525 

Wheat + Rice / Rabi + Kharif

3  20‐1 SB  Azizullah S/O Jamaluddin Bhutto 0.825  Sharecroper 50%  No Trees to share croppers 

name     0.852 

Wheat + Rice / Rabi + Kharif

4  21‐1 SB  Arbello S/O M. Paryal 0.35  Sharecroper 50%  No Trees to share croppers 

name     0.350 

Wheat + Rice / Rabi + Kharif

5  27‐1 SB  Inayat Ali Pathan 0.95  Sharecroper 25%  No Trees to share croppers 

name     0.950 

Wheat + Rice / Rabi + Kharif

6  32‐1 SB  Rasool Bux Khoso  0.475  Sharecroper 50%  No Trees to share croppers 

name     0.475 

Wheat + Rice / Rabi + Kharif

 7 

33‐1 SB  Hussain Bux Khoso  0.95 Sharecroper 50%  No Trees to share croppers 

name  0.950 

Wheat + Rice / Rabi + Kharif

 8 

38‐1 SB  Qalandar Bux Chohan  0.575 Sharecroper 50%  No Trees to share croppers 

name  0.575 

Wheat + Rice / Rabi + Kharif

63

ANNEX 6: DETAIL OF TREES OWNED BY FOREST DEPARTMENT LOCATED WITHIN THE DEMARCATION OF SECTION-II

Sr. No.

Chainage (km)

Location Species of Tree

No. of Trees Location from the centre of

road From To

Wood/ Timber

Fruit

1 17+600 - Lakhi Eucalyptus 3 - Right

2 20+000 21+000 - Eucalyptus 64 - Right

3 20+000 21+000 - Eucalyptus 46 - Left

4 20+000 21+000 - Kikar (Acacia nilotica) 9 - Left

5 21+000 22+000 Habibabad Kikar (Acacia nilotica) 29 - Left

6 22+000 - - Kikar (Acacia nilotica) 17 - Left

7 22+000 - - Date Plam  - 2 Right

8 23+100 - - Kikar (Acacia nilotica) 1 - Right

9 24+500 - Jamhra Kikar (Acacia nilotica) 6 - Left

10 24+500 - Jamhra Eucalyptus 8 - Left

11 24+550 - Jamhra Kikar (Acacia nilotica) 2 - Right

12 24+502 - Jamhra Eucalyptus 8 - Right

13 24+700 - Jamhra Kikar (Acacia nilotica) 2 - Left

14 24+504 - Jamhra Eucalyptus 3 - Right

15 25+300 - Jamhra Kikar (Acacia nilotica) 12 - Left

16 24+506 - Jamhra Date Plam - 1 Left

17 24+550 - - Eucalyptus 6 - Left

18 25+300 - - Kikar (Acacia nilotica) 3 - Right

19 25+325 - - Date Plam - 1 Right

20 25+500 - - Date Plam - 2 Left

21 25+500 - - Eucalyptus 3 - Left

22 25+500 - - Kikar (Acacia nilotica) 3 - Right

23 25+500 - - Shesham 3 - Right

24 25+700 - - Kikar (Acacia nilotica) 7 - Right

25 33+200 - Shikarpur Kikar (Acacia nilotica) 1 - Left

26 33+250 - Shikarpur Eucalyptus 10 - Left

27 33+300 - Shikarpur Pepal 2 - Right

Total 248 6

64

ANNEX 7: LIST OF CONSULTATION MEETINGS WITH THE AFFECTED PEOPLE

Sr. Meeting Date Name of Participants Venue Remarks

1 20-10-2011Hamadullah

Habib Kot

2Habibullah

3Gul Dad Brohi

4Mithal Brohi

5Jan Mohammad

1 21-10-2011 Hakim Ali S/o Mughal Khan Janno

2 Ghulam Hyder

3 Haji Muhammad Hassan

4 Soomar s/o Gulbahar

5 Punhal S/o Ellahi Bux

1 22-10-2011 Sher Muhammad S/o dilawar Phulpoto

2 Shahzor s/o Ellahi Bux

3 Khuda Bux Bhutto

4 Muhammad Arbella

5 Muhammad Mureed Malik

1 23-10-2011 Imam Din S/o Ahmed Bux Chand

2 Rahematullah S/o Rasool Bux

3 Mohd Daim Shaikh

4 Rahib Ali Bhutto

5 Ghulam Mustafa S/o dilawar

6 Amjad Ali Bhutto

NATIONAL HIGHWAY AUTHORITYOffice of The Project Director (Sukkur- Shikarpur- Jacobabad) Road Project (ICB-5) NHA Complex Airport Road, Sukkur Tel. 071 – 5630501 Fax. 071 –

5633136

Consultation Meetings with Affectees of Shikarpur Bypass

65

66

Annex 8. 2010- 2011. Rates for Timber Wood Trees, Fruit Trees and Crops By Forest Department, C&W Department, and Agriculture Extension

Wing.

67

Annex 7

68

ANNEX 8: ASSESSMENT OF CROP COMPENSATION FOR YEAR 2010-2011