resettlement planning document -...

of 54 /54
Resettlement Planning Document The short resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Short Resettlement Plan – Kodiyampalayam Bridge Document Stage: Final Project Number: 39114 March 2007 INDIA: Tsunami Emergency Assistance (Sector) Project Prepared by Public Works Department, Government of Kerala for the Asian Development Bank (ADB)

Author: buikhanh

Post on 28-Aug-2018

222 views

Category:

Documents


1 download

Embed Size (px)

TRANSCRIPT

  • Resettlement Planning Document

    The short resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADBs Board of Directors, Management, or staff, and may be preliminary in nature.

    Short Resettlement Plan Kodiyampalayam Bridge Document Stage: Final Project Number: 39114 March 2007

    INDIA: Tsunami Emergency Assistance (Sector) Project

    Prepared by Public Works Department, Government of Kerala for the Asian Development Bank (ADB)

  • INDIA: TSUNAMI EMERGENCY ASSISTANCE PROJECT (TAMIL NADU)

    SHORT RESETTLMENT PLAN for

    Kodiyampalayam Bridge

    Prepared by

    HIGHWAYS DEPARTMENT Government of Tamil Nadu

    India

    March 2007

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    2

    Contents

    List of Abbreviations ...................................................................................3

    Executive Summary of the Short Resettlement Plan ........................................4

    Section A. Description of the Project .............................................................8

    Section B. Definitions and Terminologies .......................................................9

    Section C. Scope of Land acquisition and Resettlement.................................. 11

    Section Section D. Objectives of the Short Resettlement Plan ......................... 13

    Section E. Socioeconomic Profile of the Affected Household............................ 14

    Section F. Gender Impacts and Mitigation Measures ...................................... 19

    Section G. Resettlement Principles and Policy Framework .............................. 19

    Section H. Stakeholder Participation and Disclosure of RP .............................. 24

    Section I. Istitutional Responsibility ............................................................ 25

    Section J. Implementation Arrangements .................................................... 27

    Section K. Grievance Redressal .................................................................. 28

    Section L. Compensation and Livelihood Restoration ..................................... 28

    Section M. Budget.................................................................................... 29

    Section N. Implementation Schedule........................................................... 31

    Section O. Monitoring & Evaluation ............................................................. 31

    Appendices

    I. Summary of Affected Persons ............................................................... 33

    II. Public Consultation and Disclosure Plan.................................................. 35

    III. TOR for NGO / Agency......................................................................... 37

    IV. TOR for an External Monitoring & Evaluation Consultant/Agency ................ 42

    V. Livelihood Support Programme.............................................................. 45

    VI. List of Participants in Consultation ......................................................... 49

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    3

    List of Abbreviations

    ADB Asian Development Bank

    AH Affected Household

    AP Affected Person

    BPL Below Poverty Line

    EA Executing Agency

    GoTN Government of Tamil Nadu

    GRC Grievance Redressal Committee

    HLB High Level Bridge

    IA Implementing Agency

    IAY Indira Awaas Yojana

    IR Involuntary Resettlement

    IRC Indian Road congress

    IRP Involuntary Resettlement Policy

    LA Land Acquisition

    LVAC Land Value Assessment Committee

    NGO Non Governmental Organization

    NPRR National Policy on Resettlement and Rehabilitation

    PMU Project Management Unit

    RADMMD Revenue Administration, Disaster Management and Mitigation Department

    RF Resettlement Framework (Tamil Nadu)

    RoW Right of Way

    RP Resettlement Plan

    SC Scheduled Caste

    SHGs Self Help Groups

    ST Scheduled Tribe

    TEAP Tsunami Emergency Assistance Project

    WHH Women Headed Household

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    4

    Executive Summary of the Short Resettlement Plan

    A. Description of the Project

    Government of Tamil Nadu has proposed to construct 5 high level bridges (HLB)

    under the Tsunami Emergency Assistance Project (TEAP) funded by the Asian Development

    Bank (ADB). Kodiyampalayam HLB is one among the 5 HLBs and is being proposed across

    Uppanar between Kaattur Village and Kodiyampalayam Island Village.

    In line with ADBs operational manual on involuntary resettlement and resettlement

    framework for TEAP, the Highways Department of Government of Tamil Nadu (GoTN), the

    Implementing Agency (IA), has prepared this Short Resettlement Plan (RP). This short RP

    identifies the broad scope of the project and outlines the policy, procedures for acquisition

    of land, magnitude of impact, compensation and other support measures for affected

    persons and institutional requirements for the implementation.

    B. Scope of Land Acquisition & Impacts

    The project involves the construction of a high level bridge across Uppanar river

    connecting the eastern side Kodiyampalayam island village with the western side main

    land, Kaattur village. The construction of the bridge does not involve any land acquisition

    as it is being built across the Uppanar and the land for approaches proposed with

    embankment will also not involve any land acquisition as it is river poramboke.

    The project also involves strengthening the approach roads on both sides. While

    the strengthening of the approach road on the western side is along the existing road and

    does not involve any land acquisition, 445 metres of the approach road on the eastern side

    will involve land acquisition.

    The census survey undertaken during the 2nd week of August 2006 has identified

    15 families as project affected families involving 69 persons (project affected persons).

    Further, the project causes indirect impact to 4 families operating ferry service (5 boats i.e

    two boats operated by members of same family) involving 20 persons and the boats

    employ 29 persons on daily wages for loading and unloading. Therefore, this project will be

    categorized as Category-B as the involuntary resettlement impact is not significant1. The

    summary of project affected families is given vide Appendix-I. The magnitude of impact is

    given in the following table.

    1 Not significant means less than 200 people will be (i) physically displaced from housing, or (ii) losing 10% or more of their productive assets (income generating).

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    5

    Magnitude of Impact

    Details of Affected Population

    Type of Loss Details of Affected Asset No. of Affected

    Households (HH)

    No. of Affected Persons (APs)

    1. Agricultural land

    These households comprise of those losing their agricultural land. 13 HH losing agricultural land are

    losing more than 10% of their total land holding and

    2 HH losing agricultural land are losing less than 10% of their total land holding

    - Entire land being acquired is dry land.

    15 69

    2. Indirect impact

    These households comprise of those losing their income from the boat ferry service operation. 3 HH operating ferryboat service

    losing their income (includes the boat operated by wife of a boat operator)

    1 HH operating ferryboat service losing their income (operated by a woman)

    Loss of wages for 29 persons working as load man in the boats

    4 20

    Total 19 89

    Source: Census Survey, August 2006

    C. Objectives of the Short Resettlement Plan

    This Short Resettlement Plan is prepared in accordance with ADBs policy on

    involuntary resettlement that aims at (i) avoiding involuntary resettlement wherever

    feasible; (ii) minimizing resettlement where population displacement is unavoidable by

    choosing alternative viable project options; and (iii) where involuntary resettlement is

    unavoidable, to ensure that affected people receive assistance, preferably under the

    project, so that they will be at least as well off as they would have been in the absence of

    the project.

    D. Gender Impacts & Mitigative Measures

    The women will directly benefit by the proposed bridge as it would provide them

    easy approach to the main land from their homes. It will also benefit school going female

    children who can avoid the unsafe boat ride and in case of emergency this bridge will

    provide easy access to health care. During Tsunami, majority of the dead were women and

    children who were caught in the tidal waves and to these vulnerable category this bridge

    will be a boon. However, the construction of the bridge will have indirect impact on 1

    Woman Headed Household (WHH). There will be loss of income to the 4 member family

    due to the construction of the bridge, as the woman boat operator will lose her income

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    6

    from boat operated by her for ferrying men and material. This AP will be adequately

    supported in this RP so as to restore her earlier standard of living.

    E. Resettlement Principles and Policy Framework

    The resettlement principles adopted for this subproject recognize the Land

    Acquisition (LA) Act 1894 and the entitlement benefits as listed in the National Policy on

    R&R, (Govt of India) as notified in February 2004 and the relevant Asian Development

    Banks (ADB) policies and operations manuals, in particular the policy on Involuntary

    Resettlement (1995), and Operations Manual F2 on involuntary Resettlement (2003), and

    agreed Resettlement Framework.

    The RP is based on the general findings of the census survey, field visits, and

    meetings with various project-affected persons in the project area. The Entitlement Matrix

    for TEAP projects in Tamil Nadu provides for compensation and resettlement assistance to

    all affected persons including the non-titleholders in the project area. In general terms, the

    people affected by the Project will be entitled to the following types of compensation and

    assistance - (i) Compensation for loss of land and crops/trees at replacement value; (ii)

    assistance for restoration of income and livelihoods and (iii) additional assistance to

    vulnerable groups namely - Female-headed households, Scheduled Castes (SC), Scheduled

    Tribes (ST), those below poverty line, elderly and disabled. A detailed Entitlement

    Matrix for the project is provided in Table 18 in the main text.

    F. Stakeholder Participation and Disclosure of RP

    A public consultation was held on 12.08.2006 to seek the views and preferences of

    the community with regard to the project and as well as their suggestions for successful

    implementation of the project. The Resettlement Plan (RP) will be translated into Tamil and

    will be made available to the affected people by the Implementing Agency (IA), the

    Highways Department, for review and comments on the policy and mitigation measures by

    means of project-level disclosure workshops prior to loan negotiation. Copies of short RP

    will also be made available at the local level public office, Sirkazhi Taluk office, to

    stakeholders for local inputs prior to award of civil work contract. The proceedings of the

    disclosure workshop and the feedback received will be sent to ADB for review.

    G. Implementation Arrangement, Schedule & Grievance Redressal

    The Revenue Administration, Disaster Management and Mitigation Department

    (RADMMD) at the state-level will be the EA of the project, while the Highways Department

    will be responsible for the implementation of the RP. Highways Department, the

    implementing agency, will engage a qualified social/resettlement specialist to assist it in

    the implementation of the RP. The project director of PMU will recruit and appoint a local

    NGO to help implement resettlement activities. The highways department will assign the

    task of implementation to the concerned Divisional Engineer who will be supported by one

    Assistant Engineer.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    7

    A Grievance Redressal Committee (GRC) will be established in Nagapattinam

    district, with representation from RADMMD, concerned DE of Highways, 2 members from

    the people affected of which at least one is a women or from vulnerable group,

    Kodiyampalayam Panchayat President, and the NGO representative and will be chaired by

    the District Revenue Officer of Nagapattinam.

    The PMU will ensure resettlement budgets are delivered on time to the competent

    authority and the implementing NGOs for timely RP implementation. The PMU will ensure

    that affected persons will receive compensation and other entitlements before civil work

    contracts are awarded.

    H. Budget

    The total estimated cost for resettlement implementation including cost of

    compensation and assistance as per the Resettlement Framework (Tamil Nadu) under

    TEAP is Rs.1,152,322/-.

    I. Monitoring & Evaluation

    RADMMD will establish a monthly monitoring system and prepare monthly progress

    reports on all aspects of land acquisition and resettlement activities. The report will contain

    progress made in RP implementation with particular attention to monitoring and the

    delivery of entitlements. The deputed official in charge of land acquisition and resettlement

    in the PMU with assistance from the social development and resettlement specialist,

    through the Highways Department and NGOs will monitor the progress of land acquisition

    and resettlement and also prepare biannual reports, forwarding them to ADB for review.

    An independent agency/monitoring expert will be engaged by the PMU in agreement with

    ADB to undertake biannual external monitoring of the subproject implementation.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    8

    Short Resettlement Plan

    A. Description of the Project 1. Government of Tamil Nadu has proposed to construct 5 high level bridges

    (HLBs) under the Tsunami Emergency Assistance Project (TEAP) funded by the

    Asian Development Bank (ADB). Kodiyampalayam HLB is one among the 5 HLBs

    and is being proposed across Uppanar river between Kaattur Village and

    Kodiyampalayam Island Village.

    2. The Project will involve the construction of a high level bridge and

    strengthening of the existing approach roads in accordance with the IRC

    standards.

    3. In line with the ADBs sector assistance project for Tamil Nadu under the

    Tsunami Emergency Assistance Project, construction and rehabilitation works are

    being carried out as far as possible within the original right-of-way. However,

    improvements to the approach roads on eastern side to the HLB at

    Kodiyampalayam village will involve minimal land acquisition. The various

    components proposed for the HLB is given in Table 1.

    Table 1. Project Components

    Component Description Requirement of Land

    1. Bridge The bridge is 140m long and 8.5 m wide from outer to outer of crash barrier.

    No land acquisition involved as it is being built across the river.

    2. Approach road Western side 290m long approach road.

    Existing road and no land acquisition involved.

    Eastern side 445m long approach road.

    Formation of road involving acquisition of land.

    4. The village Kodiyampalayam has no road approach and the people of this

    village use boats to reach the main land. The island village is just 200 metres

    away from the Bay of Bengal and in the event of an emergency like tsunami,

    cyclone or storm, the administration becomes helpless and finds it extremely

    difficult to reach to the people. This bridge will provide the people of

    Kodiyampalayam comfortable and safe access to the main land. The bridge will

    not only serve as an emergency escape route, it will also improve the standard of

    living of the island villagers. Further, the bridge will provide easy and safe access

    to the people and traders from the mainland villages who currently depend on

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    9

    ferry services to reach Kodoyampalayam. However, the census survey

    undertaken during project preparation stage reveals that there will be involuntary

    resettlement.

    5. In line with ADBs operational manual on involuntary resettlement and

    resettlement framework for TEAP, the Highways Department of Government of

    Tamil Nadu (GoTN), the Implementing Agency (IA), has prepared this Short

    Resettlement Plan (RP). This short RP identifies the broad scope of the project and outlines the policy, procedures for acquisition of land, magnitude of impact,

    compensation and other support measures for affected persons and institutional

    requirements for the implementation.

    6. The Project Management Unit (PMU), Disaster Management and Mitigation

    Department, Revenue Administration of GoTN would be responsible for ensuring

    compliance of this short RP. The highways department of GoTN will be the

    implementing agency of the HLB and will have the primary responsibility for RP

    implementation.

    B. Definitions and Terminologies

    7. The definitions of key terminologies or concepts used in this resettlement

    plan are as follows.

    Affected Person includes any people, households, firms, or private institutions

    who, on account of changes that result from the project will have their (i)

    standard of living adversely affected; (ii) right, title, or interest in any house,

    land (including residential, commercial, agricultural, forest, and/or grazing

    land), water resources, or any other moveable or fixed assets acquired,

    possessed, restricted, or otherwise adversely affected, in full or in part,

    permanently or temporarily; and/or (iii) business, occupation, place of work or

    residence, or habitat adversely affected, with or without displacement.

    Compensation means compensation paid for the property under the Land

    Acquisition Act, 1894 or through private negotiation vide GoTN government

    order Ms.No.885, Revenue dated 21.9.1995.

    Encroacher is any person(s) illegally occupying public property by extending

    their land boundary or a portion of their building onto the RoW.

    Entitled Persons means the male 21 years and female 18 years having

    entitlement for compensation and rehabilitation assistance.

    Involuntary resettlement addresses social and economic impacts that are

    permanent or temporary and are (i) caused by acquisition of land and other

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    10

    fixed assets, (ii) by change in the use of land, or (iii) restrictions imposed on

    land as a result of an ADB operation.

    Land Acquisition means the process through which land and properties are

    acquired for the purpose of project construction.

    Major impacts are defined as involving affected people being physically

    displaced from housing and/or having 10% or more of their productive,

    income generating assets lost.

    Owners are persons who have legal title to structures, land or other assets.

    These property owners are entitled to compensation under the Land

    Acquisition Act of 1894.

    Project Affected Family/Household means a family consisting of father,

    mother, children living together with common kitchen and are affected by the

    project, irrespective of their legal status resulting in loss of homestead, other

    assets, sources of income / livelihood, common assets and cultural properties.

    Rehabilitation means the measures provided under the resettlement plan

    other than payment of the compensation of acquired property.

    Replacement cost means the method of valuing assets to replace the loss at

    market value, or its nearest equivalent, plus any transaction costs such as

    administrative charges, taxes, registration, and titling costs. Where national

    law does not meet this standard the replacement cost will be supplemented as

    necessary. Replacement cost is based on market value before the project or

    dispossession, whichever is higher. In the absence of functioning markets, a

    compensation structure is required that enables affected people to restore

    their livelihoods to levels at least equivalent to those maintained at the time

    of dispossession, displacement, or restricted access.

    Resettlement means all the measures taken to mitigate all or any adverse

    impacts of the project on the APs property and/or livelihoods including

    compensation, relocation (where relevant), and rehabilitation.

    Squatter is any person occupying structures entirely within the ROW (with no

    legal rights to occupy that parcel of land) for residential or business purposes.

    Tenant is any person by whom or on whose account rent is payable for any

    property.

    Vulnerable people are the poorest affected people and groups that may be at

    high risk of impoverishment. This may include those without legal title to land

    or other assets, households headed by females, the elderly or disabled and

    other vulnerable groups, particularly indigenous peoples.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    11

    C. Scope of Land acquisition and Resettlement

    8. The project involves the construction of a high level bridge across Uppanar

    connecting the eastern side Kodiyampalayam island village with the western side

    main land, Kaattur village. The construction of the bridge portion does not involve

    any land acquisition as it is being built across the Uppanar and the land for

    approaches proposed with embankment in Kaattar village will also not involve any

    land acquisition as it is river poramboke.

    9. The project also involves strengthening the approach roads on both sides.

    While formation of the approach road on the western side is along the existing

    road and does not involve any land acquisition, 445 metres of the approach road

    on the eastern side in Kodiyampalayam village will involve land acquisition.

    10. In line with ADBs principles of involuntary resettlement planning, the

    project avoided involuntary resettlement wherever possible by constructing

    approach road along the existing available space. However, the project will

    require 0.44.30 hectare of private land for formation of 445 metres of approach

    road. This will cause minor2 impact to the livelihood of 2 landowners; major3

    impact to 13 landowners; and indirect impact to 5 ferry service operators

    (belonging to 4 households) and 29 daily wage earners.

    11. The census survey undertaken during the 2nd week of August 2006 has

    identified 15 families as project affected families involving 69 persons (project

    affected persons). Further, the project causes indirect impact to 4 families

    operating ferry service involving 20 persons and the boats employ 29 persons on

    daily wages for loading and unloading. Therefore, this project will be categorized

    as Category-B as the involuntary resettlement impact is not significant4. The

    summary of project affected families is given vide Appendix-I. The magnitude of

    impact is given in Table 2.

    12. The ferry service operators transport local population and goods to the

    island village Kodiyampalayam. One among the operators is a woman who

    mainly transports people and sometimes transports goods. Of the 5 boats,

    members of one family a husband and wife duo operate 2 boats and the other

    3 boats are operated by different families. Amongst these 3 boats, 2 are operated

    by men and 1 is operated by a woman (WHH). Since two boats are operated by

    2 Losing less than 10% of their productive assets (income generating). 3 Losing more than 10% of their productive assets (income generation). 4 Not significant means less than 200 people will be (i) physically displaced from housing, or (ii) losing 10% or more of their productive assets (income generating).

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    12

    members of the same family (husband and wife), though there are 5 boats in

    operation only 4 families are affected. One among these 4 families is a Woman

    Headed Household (WHH).

    Table 2. Magnitude of Impact

    Details of Affected Population

    Type of Loss Details of Affected Asset No. of Affected

    Households (HH)

    No. of Affected Persons (APs)

    1. Agricultural land

    These households comprise of those losing their agricultural land. 13 HH losing agricultural land are losing

    more than 10% of their total land holding and

    2 HH losing agricultural land are losing less than 10% of their total land holding

    - Entire land being acquired is dry land.

    15 69

    2. Indirect impact

    These households comprise of those losing their income from ferry service operation. 3 HH operating ferryboat service losing

    their income (includes the boat operated by wife of a boat operator)

    1 HH operating ferryboat service losing their income (operated by a woman - WHH)

    Loss of wages for 29 persons working as load man in the boats

    4 20

    Total 19 89 Source: Census Survey, August 2006

    13. The 15 households losing portion from their agricultural land parcels are

    not getting any income from the land. The main source of income is from fishing

    and for some income is through non-farm wages. The land being acquired is dry

    land and the extent of land lost to their total land holding is less than 10 percent

    for 2 households and more than 10 percent for 13 households. The percentage of

    land lost to the total land holding is given in Table 3.

    Table 3. Percentage of Land Lost

    Extent of Land Lost

    Frequency Percentage

    Less than 2% 1 06.7

    2% and 10% 1 06.7

    >10% and 20% 2 13.3

    Above 20% 11 73.3

    Total 15 100.0

    Source: Census Survey, August 2006

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    13

    14. There is no loss of income to the 15 households on account of proposed

    land acquisition. However, the 4 households operating ferry service will lose their

    entire source of income as an indirect impact of the project.

    Table 4. Loss of Income due to Project

    Type of Impact Total number of

    households

    Number of households

    losing income

    Direct Impact 15 0

    Indirect Impact 4 4

    Total 19 4

    Source: Census Survey, August 2006

    15. The total land required for the project is 1.68.50 hectare of which 0.44.30

    hectare of land is private land belonging to 15 households. The various

    components that require land, classification of land and the number of households

    getting affected is given in Table 5.

    Table 5. Details of Land Loss

    Classification Project

    Components Total Land

    requirement Govt. Private Present Use No. of

    affected HH

    1. Bridge 0.11.90 0.11.90 - River and river poramboke

    -

    2. Approach road on the eastern side

    0.96.41 0.52.11 0.44.30 Dry land 15

    3. Approach road on the western side

    0.60.19 0.60.19 - Existing PWD road for traffic

    -

    Total 1.68.50 1.24.20 0.44.30 - 15

    Source: Census Survey, August 2006

    D. Objectives of the Short Resettlement Plan 16. This Short Resettlement Plan is prepared in accordance with ADBs policy

    on involuntary resettlement that aims at (i) avoiding involuntary resettlement

    wherever feasible; (ii) minimizing resettlement where population displacement is

    unavoidable by choosing alternative viable project options; and (iii) where

    involuntary resettlement is unavoidable, to ensure that affected people receive

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    14

    assistance, preferably under the project, so that they will be at least as well off as

    they would have been in the absence of the project.

    17. This short RP briefly describes the findings of the census survey, identifies

    the nature and types of losses, provides for payment of compensation and

    resettlement benefits as per the entitlement matrix developed for TEAP and the

    institutional arrangement for implementation.

    E. Socioeconomic Profile of the Affected Household 18. The census survey identified 15 households as directly affected households

    comprising of 69 persons and 4 households as indirectly affected households

    comprising of 20 persons. Of the 19 households, one household is headed by a

    woman. The male-female profile amongst the affected household (AHs) is given

    in Table 6.

    Table 6. Head of Household (HH) by Sex

    Head of Household

    Sex Frequency Percentage

    Male 18 94.7

    Female 1 05.3

    Total 19 100.0

    Source: Census Survey, August 2006

    19. The male- female profile amongst all members of the project-affected

    household is given in the following table. The male outnumber the female and is

    in the ratio of 6:4

    Table 7. APs by Sex

    All Members (APs)

    Sex Frequency Percentage

    Male 53 59.6

    Female 36 40.4

    Total 89 100.0

    Source: Census Survey, August 2006

    20. The above 60 age group comprise of about 2 percent. Thirty six percent

    are below 18 years.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    15

    Table 8. Age group of APs

    Age classification

    Frequency Percentage

    Upto 5

    6 17

    18 24

    25 40

    41 60

    > 60

    4

    28

    19

    17

    19

    2

    4.5

    31.5

    21.3

    19.1

    21.3

    2.3

    Total 89 100.0

    21. Thirty two percent of the affected households have a small family of size

    four or less. The average size of a family is 4.7.

    Table 9. Size of household

    Size of household

    Frequency Percentage

    1 3

    4

    5

    6 7

    5

    1

    8

    5

    26.3

    5.3

    42.1

    26.3

    Average Size is 4.7

    22. All the affected households are Hindus.

    Table 10. Affected household by Religion

    Religion Frequency Percentage

    Hindu

    Muslim

    Christian

    19

    -

    -

    100.0

    -

    -

    Total 19 100.0

    23. Eighty four percent of the affected household belong to the most backward

    class. There is 5 percent belonging to scheduled caste (1 AH) who would come

    under the vulnerable category.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    16

    Table 11. Afected household by Social Group

    Community Frequency Percentage

    FC

    BC

    MBC

    SC

    -

    2

    16

    1

    -

    10.5

    84.2

    5.3

    Total 19 100.0

    24. The literacy level amongst male is 72 percent and amongst women is only

    56 percent. The literacy level of both male and female is lower compared to the

    state average (82%). The level of educational attainment is given in Table 13.

    Table 12. Literacy by Sex of APs (> 6 age group)

    Male Female Literacy

    Frequency Percentage Frequency Percentage

    Can read and write 34 72.3 20 55.6

    Cannot read and write 13 27.7 16 44.4

    Total 47 100.0 36 100.0

    Table 13. Education level by Sex of APs

    Male Female Education

    Frequency Percentage Frequency Percentage

    Below primary

    Primary

    Upper primary

    High school

    Higher secondary

    Graduate

    Post graduate

    Technical education

    None

    Children (

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    17

    Table 14. Occupation of Head of Household

    Head of HH All members (APs) Main Activity

    Frequency Percentage Frequency Percentage

    Cultivation

    Casual labour

    Salaried

    Household shop

    Business

    Other workforce

    Unemployed

    Not in workforce

    -

    2

    1

    -

    -

    15

    -

    1

    -

    10.5

    05.3

    -

    -

    78.9

    -

    05.3

    2

    4

    1

    -

    1

    25

    -

    56

    02.3

    04.5

    01.1

    -

    01.1

    28.1

    -

    62.9

    Total 19 100.0 89 100.0

    Source: Census Survey, August 2006

    26. About 20 percent of the APs are below poverty line. Income of about 10

    percent is less than Rs.1000/- per month.

    Table 15. Income of AHs

    Income Range (per annum)

    Frequency Percentage

    1 - 12000

    12001 18000

    18001 24000

    24001 36000

    Above 36000

    Dependant

    2

    2

    4

    7

    3

    1

    10.5

    10.5

    21.1

    36.8

    15.8

    05.3

    Total 19 100.0

    Source: Census Survey, August 2006

    27. The average income of the employees is Rs.3000/- per month. There is

    one employee who is 18 years old, but is a family member of the boat owner.

    Thirty eight percent are in the 19 to 24 age group, 31 percent in the 25 to 40 age

    group and the rest (28%) in 41 to 60 age group. The average number of

    dependants on the salary drawn by these employees is 4.7.

    28. Among the project affected households, in 74 percent of the household

    only men are involved in income earning activities and the head is invariably the

    principle earner for the family. One household (boat operator) has a woman as

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    18

    the principal bread earner. In 16 percent of the household both men and women

    are involved in income earning activities.

    Table 16. Primary income earner in the AHs

    Primary Income Earner

    Frequency Percentage

    Men alone

    Women alone

    Both Men and Women

    Dependant

    14

    1

    3

    1

    73.7

    05.3

    15.7

    05.3

    Total 19 100.0

    Source: Census Survey, August 2006

    29. The census survey also aimed at identifying socially and economically

    vulnerable5 groups amongst those affected households who would require

    additional assistance. Seven households (vulnerable) will require additional

    support under ADBs livelihood programme6 assistance.

    Table 17. Income of Vulnerable AHs

    WHH BPL SC Elderly / Disabled

    Income Range (per annum)

    Fre

    qu

    en

    cy

    Perc

    en

    tag

    e

    Fre

    qu

    en

    cy

    Perc

    en

    tag

    e

    Fre

    qu

    en

    cy

    Perc

    en

    tag

    e

    Fre

    qu

    en

    cy

    Perc

    en

    tag

    e

    1- 12000

    12001 18000

    18001 24000

    24001 36000

    Above 36000

    Dependant

    -

    -

    -

    -

    1

    -

    -

    -

    -

    -

    100.0

    -

    2

    2

    -

    -

    -

    -

    50.0

    50.0

    -

    -

    -

    -

    -

    -

    -

    -

    1

    -

    -

    -

    -

    -

    100.0

    -

    -

    -

    -

    -

    -

    1

    -

    -

    -

    -

    -

    100.0

    Total 1 100.0 4 100.0 1 100.0 1 100.0

    Source: Census Survey, August 2006

    30. If there is any change in the alignment or in the design prior to award of

    civil works contract or during implementation, the RP will be accordingly updated 5 (a) those who are below the poverty line (BPL); (b) those who belong to scheduled castes (SC),

    scheduled tribes (ST); (c) women-headed households (WHHs); (d) elderly and (e) disabled persons. 6 The ADB is financing The Livelihood Restoration programme of GoTN under Tsunami (details of the

    programme is provided in Appendix-IV)

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    19

    and the revised RP will be submitted to ADB by the Highways Department. The

    final RP will be submitted to ADB prior to award of civil works contract.

    F. Gender Impacts and Mitigation Measures 31. The sex ratio of 9877 in Tamil Nadu is higher than the all-India figure of

    933 and the juvenile sex ratio is 942 compared to all-India figure of 927. Though

    the sex ratio in Tamil Nadu is better than the national figure, considering the

    relative disadvantage of the women in the society, the census survey captured

    the current status of women and their socio-economic profile.

    32. The women will directly benefit by the proposed bridge as it would provide

    them easy approach to the main land from their homes. It will also benefit school

    going female children who can avoid the unsafe boat ride and in case of

    emergency this bridge will provide easy access to health care. During Tsunami,

    majority of the dead were women and children who were caught in the tidal

    waves and to these vulnerable category this bridge will be a boon.

    33. However, the construction of the bridge will have indirect impact on 1

    Woman Headed Household (WHH). There will be loss of income to the 4 member

    family due to the bridge as the woman who operates the boat will lose her income

    from the boat occupation after the construction. This AP will be adequately

    supported in this RP so as to restore her earlier standard of living.

    G. Resettlement Principles and Policy Framework

    34. The National Policy on Resettlement and Rehabilitation (NPRR) provides

    broad guidelines and executive instructions and will be applicable to projects

    displacing 500 families or more in flat lands and 250 families or more in hilly

    areas. The NPRR requires projects to (i) minimize displacement and identify non-

    displacing or least-displacing alternatives; (ii) plan the resettlement and

    rehabilitation of project-affected families including special needs of tribal and

    vulnerable sections; (iii) provide a better standard of living to project-affected

    families; and (iv) facilitate harmonious relationships between the requiring body

    and project-affected families through mutual cooperation.

    35. While the NPRR recognizes most of the significant resettlement principles

    in the Asian Development Banks (ADB) Involuntary Resettlement Policy (IRP),

    the NPRR does not meet some of the IRPs safeguards. First, the NPRRs threshold

    of applicability is limited to land acquisitions for highways, railway lines,

    7 Source: Census of India, 2001

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    20

    transmission lines, and pipelines. Second, each project-affected family will be

    offered an ex-gratia payment of Rs10,000/- and no other resettlement and

    rehabilitation benefits. Third, replacement value is not clearly defined and is not

    taken into account in calculating lump-sum compensation. Fourth, no specific

    entitlements are available for squatters and encroachers.

    36. The Land Acquisition Act 1894 and its amendments to date generally

    govern land acquisition and compensation in Tamil Nadu. The Act covers only

    legal titleholders and provides for (i) market value of the land; (ii) compensation

    of 30% on the market value for compulsory acquisition; (iii) an additional amount

    for trees, crops, houses, or other immovable properties; (iv) damage due to

    severing of land, residence, or place of business; and (v) an interest of 12% on

    the market value from the date of notification to award. The IRP has some

    additional complementary provisions especially with regard to displacement and

    resettlement of squatters and other informal settlers.

    37. To reduce inherent delays in the land acquisition process from 18 to 6

    months or less, the Government of Tamil Nadu (GOTN) issued a government

    order in 1995Acquisition of Land for various purposes, Acquisition through

    negotiationUniformity in procedure, fixation of land value and Constitution of

    Committee. The order sets out the principles of fixing of land value for

    negotiation. It allows negotiations up to 150% of the market value/guideline

    value for each hectare of land.

    38. Based on these state laws and regulation on land acquisition, the ADB IRP

    and the NPRR, the following resettlement principles will be applied to all TEAP

    subprojects:

    a) land acquisition and other involuntary resettlement impacts will be minimized

    as much as possible;

    b) wherever possible, Government land will be utilized which is free from

    encumbrances and will not include land that is squatted upon;

    c) those affected will be informed and consulted on compensation options and in

    formulating the RPs in accordance with the agreed RF;

    d) land and other property compensation will be paid at replacement costs;

    e) payment of compensation for lost land, housing, assets, and other

    resettlement assistance will be given in full before awarding civil contracts;

    f) compensation at replacement cost and resettlement assistance will be given

    to all non-titled people affected (e.g., informal dwellers/squatters, and

    encroachers) before acquiring land and their properties;

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    21

    g) all those affected will receive assistance to restore their income and to

    rehabilitate their livelihood; and

    h) special assistance will be given to households headed by women and other

    vulnerable groups.

    39. In case of land acquisition, compensation will be paid at mutually agreed

    rates through negotiations as outlined in the 1995 government order at

    replacement costs. In the event the landowner does not agree to acquisition

    through negotiation and the land is acquired as per the Land Acquisition Act,

    compensation will be paid at replacement costs. If the compensation amount

    assessed by a district collector is lower than that of the replacement cost

    determined by the land acquisition and valuation committee, the difference will be

    paid in the form of a special grant to the affected person. The Government will

    bear transaction costs such as stamps/registration costs in case of purchase of

    replacement land. Non-titled affected people will be entitled to both compensation

    and rehabilitation assistance based on the nature of their losses. Replacement

    cost of structures will also be paid to squatters/informal dwellers, and

    resettlement assistance, such as shifting allowance and compensation for loss of

    workdays/income. Households headed by women and other vulnerable

    households (such as scheduled tribe/scheduled caste, disabled, elderly) will be

    eligible for additional assistance in terms of income restoration.

    40. Cut-off Date is established to identify the Entitled Persons. The date on

    which the census survey was undertaken will be the cut-off date for non-

    titleholders. For legal owners, the cut-off date will be the notification declaring the

    intention to acquire the property. For those legal owners who are not agreeable to

    compensation through negotiations, the date of serving the notice u/s 4(1) of

    Land Acquisition Act of 1894 will be established as the cut-off date.

    41. The entitlement matrix (Table 18) lists types of losses, eligibility, and

    entitlements, and provides basic parameters for the preparation of compensation

    and resettlement benefits. The matrix will apply to this project.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    22

    Table 18. Entitlement Matrix

    No Type of Loss Application Unit of

    entitlement Entitlement Details of Entitlements

    1 Agricultural land, homesteads, commercial land (private property)

    Land on the project right of way (ROW)

    Titleholders

    Compensation at replacement cost.

    1. Cash compensation through negotiation as per government order (1995) at mutually agreed rates equal to replacement value and/or GO Ms. No. 75 (2005).

    2. Cash compensation as per Land Acquisition Act at replacement costs. If the replacement cost of land determined by land acquisition and valuation committee is more than the compensation determined by district collector, the difference will be paid as a special grant by the Project directly to those affected.

    3. Transaction costs will be paid by the Project (registration cost, stamp fees etc., incurred in the purchase of replacement land).

    2 Residential and commercial structures (private property)

    Structure within the ROW

    Titleholders

    Compensation at replacement cost

    1. Cash compensation to be paid by the district collector at replacement costs. If the replacement cost of structure determined by land acquisition and valuation committee is more than the compensation determined by district collector, the difference will be paid as a special grant by the Project directly to those affected.

    2. A lump sum shifting assistance for shifting household assets including cost of transportation and labor costs.

    3. Project will assist those affected to purchase land to relocate to a new site.

    4. Right to salvage material from the demolished structure.

    3 Loss of income from business and loss of wages

    Businesses and employees affected by project ROW

    Individual

    Lump sum

    1. Owners of businesses will be compensated for their loss of income for 3 months based on actual income lost assessed on a case-by-case basis.

    2. Employees directly affected by displacement of employer will receive wages for 3 months calculated on the basis of minimum wages.

    3. Support to those affected, through the livelihoods programs (Appendix V) under the Project (training, capacity building, and enterprise development) for restarting or new income-generating activities.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    23

    No Type of Loss Application

    Unit of entitlement

    Entitlement Details of Entitlements

    4 Annual/seasonal crops and trees

    Crops and trees on ROW

    Cultivator household

    Compensation at market value

    1. Advance notice for harvesting standing crops.

    2. Owner will receive grant equal to market value of crop lost for 10 years plus cost of replacement of seeds.

    3. Sharecroppers/tenants will be compensated at market value for the crop lost plus cost of replacement of seeds for the next seasons harvest.

    4. Compensation for trees based on timber value at market prices, to be determined by Forest Department and Horticultural Department.

    5. For perennial trees, compensation will be 35 times the market value.

    5 Structures by squatters and informal settlers (residential/ commercial)

    Structures affected by ROW

    Household

    No compensation for land; compensation for structure at replacement cost and other assistance

    1. Compensation for loss of structure at replacement cost.

    2. A lump sum shifting assistance for shifting household assets including cost of transportation and labor costs.

    3. Affected people to relocate to a new site provided by the project.

    4. Support to those affected losing commercial structures, through the livelihoods program (Appendix V) under the Project (training, capacity building and enterprise development) for restarting/new income-generating activities.

    6 Additional assistance for vulnerable groups below poverty line (BPL), households headed by women, elderly and disabled

    Households affected by ROW

    Individual

    Assistance for income restoration and training

    1. Preferential employment in the Project, especially for women and the poor

    2. Support those affected through the livelihoods programs under the Project (Appendix V) which will include- Support for capacity building,

    enterprise training, and economic activities to already organized self-help groups (SHGs).

    Support for capacity building, enterprise training for new SHGs (male and female) not yet organized into community-based groups.

    Replacement of productive assets, skill upgrading, risk mitigation through insurance.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    24

    No Type of Loss Application Unit of

    entitlement Entitlement Details of Entitlements

    7 Specific action for indigenous people/ scheduled tribe (ST)

    Land and other assets affected by ROW

    Individual

    Assistance for income restoration and training

    1. Preferential employment in the Project, especially for women and the poor

    2. Support those affected through the livelihoods programs under the Project (Appendix V) which will include- Support for capacity building,

    enterprise training, and economic activities to already organized self-help groups (SHGs).

    Support for capacity building, enterprise training for new SHGs (male and female) not yet organized into community-based groups.

    Replacement of productive assets, skill upgrading, risk mitigation through insurance.

    8 Community infrastructure and amenities

    Affected by ROW

    Community

    Replacement

    1. Complete rehabilitation / restoration by the Project.

    9 Other impacts not identified

    1. Unforeseen impacts will be documented and mitigated based on the principles agreed in this RF.

    H. Stakeholder Participation and Disclosure of RP

    42. Appropriate consultation on the resettlement plan and participation of

    affected population in decision making will improve the understanding of their

    needs, resources and preferences. This will help in reducing reluctance and

    thereby increase the acceptance of the project. Consultations have been held at

    the time of carrying out the baseline socio-economic survey.

    43. Further, a public consultation was held on 12.08.2006 to seek the views

    and preferences of the community with regard to the project and as well as their

    suggestions for successful

    implementation of the project.

    The likely resettlement impact

    and the mitigation measures

    proposed under the RP were

    explained to the people. The

    consultation was conducted by the

    R&R Expert and about 31 persons,

    including village leaders,

    participated in the consultation.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    25

    44. The salient findings of the consultations on various issues covered are

    presented below.

    People were unanimous and

    equivocal in conveying the

    need for a bridge in

    Kodiyampalyam.

    The advantages as perceived

    by the people are; the bridge

    would become an escape

    route; facilitate easy access to

    school and health facilities;

    fisheries will improve; and will

    pave way for introduction of

    mini-bus (public transport) service to the village.

    On the compensation and assistance, the APs wanted valuation for the land to

    reflect the market rates, though there has been no cultivation in these lands

    for over 15 years.

    The participants signed attendance sheet is enclosed as Appendix-VI.

    45. In addition, a Public Consultation and Disclosure Plan has been prepared

    for the project and is enclosed as Appendix-II.

    46. The Resettlement Plan (RP) will be translated into Tamil and will be made

    available to the affected people by the Implementing Agency (IA), the Highways

    Department, for review and comments on the policy and mitigation measures by

    means of project-level disclosure workshops prior to loan negotiation. Copies of

    short RP will also be made available at the local level public office, Sirkazhi Taluk

    office, to stakeholders for local inputs prior to award of civil work contract. The

    proceedings of the disclosure workshop and the feedback received will be sent to

    ADB for review.

    47. The final RP will also be disclosed on the ADB Website, EA website and IA

    website whereas the Project Management Unit (PMU) will continue consultations

    throughout the project implementation period.

    I. Istitutional Responsibility

    48 The Revenue Administration, Disaster Management and Mitigation

    Department (RADMMD) at the state-level will be the Executing Agency (EA) of the

    TEAP, while the State Level Steering Committee (SLSC) will have the overall

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    26

    advice and guidance with the departments and the Implementing Agencies (IAs).

    The Project Management Unit (PMU) formed within RADMMD and headed by the

    project director will be responsible for overall coordination, planning,

    implementation, monitoring, and financing of all resettlement and rehabilitation

    activities under the TEAP. RADMMD will depute an official within the PMU to be in

    charge of land acquisition and resettlement operations, and will report to the

    project director. Each IA in their project implementation unit will also have

    qualified social/resettlement professionals. The social development and

    resettlement specialist will assist the PMU and IAs/line departments in preparing

    RPs. The project director will recruit and appoint local NGOs, as required, to help

    prepare and implement resettlement activities. The concerned staff at the PMU,

    IAs/field offices, project NGOs, and revenue department officials will undergo a

    week long orientation and training in resettlement policy and management. The

    deputed official in the PMU with the assistance from the social development and

    resettlement specialist will work in close coordination with the respective IAs and

    project NGOs on the day-to-day activities of RP implementation.

    49. A land value assessment (LVAC) for the project committee headed by the

    district collector or his/her representative will also be formed with representatives

    from RADMMD, IAs, district/tehsil Land Revenue office, representatives of those

    affected, local government, village leaders, professional assessors, and

    implementing NGO to assess replacement value of lost assets through a land

    market value survey and through compiling and comparing other available

    sources of information.8 RADMMD will ensure that any land acquisition and

    resettlement/relocation is preceded by a satisfactory RP, formulated according to

    the agreed Resettlement Framework (RF). RADMMD will also ensure that

    appropriate entitlements and mitigation measures are included in the RP

    especially for the benefit of vulnerable groupshouseholds headed by women,

    below poverty line, scheduled caste/scheduled tribes, the elderly, and disabled.

    The PMU will submit RPs for ADB review and approval, and will ensure that

    affected persons will receive compensation and other entitlements before civil

    work contracts are awarded.

    8 District Level Monitoring Committees and Village Level Monitoring Committees will be extensively utilized for this purpose.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    27

    J. Implementation Arrangements

    50. The Revenue Administration, Disaster Management and Mitigation

    Department (RADMMD) at the state-level will be the EA of the project, while the

    Highways Department will be responsible for the implementation of the RP.

    51. The PMU formed within RADMMD and headed by the project director will

    be responsible for overall coordination, monitoring and financing of the RP.

    RADMMD will depute an official within the PMU to be in charge of land acquisition

    and resettlement operations, and will report to the project director.

    52. Highways Department, the implementing agency, will engage a qualified

    social/resettlement specialist to assist it in the implementation of the RP. The

    project director of PMU will recruit and appoint a local NGO to help implement

    resettlement activities. The highways department will assign the task of

    implementation to the concerned Divisional Engineer who will be supported by

    one Assistant Engineer.

    53. The concerned staff at the Divisional Office of the Highways Department

    and project NGO will undergo a week long orientation and training on issues

    concerning - resettlement policy; principles and procedures of land acquisition;

    public consultation and participation; entitlements and compensation

    disbursement mechanisms; Grievance Redressal and monitoring of resettlement

    operation. The drafts TOR for the appointment of NGO / Agency is given vide

    Appendix-III

    54. Further, the PMU will ensure resettlement budgets are delivered on time to

    the competent authority and the implementing NGOs for timely RP

    implementation. The PMU will ensure that affected persons will receive

    compensation and other entitlements before civil work contracts are awarded.

    The organizational structure for implementation of SRP activities is as under:

    PMU (RADMMD)

    LVAC DE Highways

    AE Highways

    NGO

    PAP

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    28

    K. Grievance Redressal

    55. A Grievance Redressal Committee (GRC) will be established in

    Nagapattinam district, with representation from RADMMD, concerned DE of

    Highways, 2 members from the people affected of which at least one is a women

    or from vulnerable group, Kodiyampalayam Panchayat President, and the NGO

    representative and will be chaired by the District Revenue Officer of

    Nagapattinam. Through public consultations, those affected will be informed that

    they have a right to redress their grievance. They can call upon the support of the

    NGO to assist them in presenting their grievances or queries to the GRC, which is

    expected to settle many grievances. The committee must resolve grievances

    within a fortnight time. The decision of GRC will be binding unless challenged in a

    court of law. The committee will meet at least four times a month during the first

    6 months of project implementation, and twice a month from the seventh month.

    L. Compensation and Livelihood Restoration i) Arrangement for Valuing and Disbursing Compensation

    56. A land value assessment committee headed by the district collector or

    his/her representative will also be formed with representatives from RADMMD,

    Highways Department, L.A. Tahsildar, representatives of those affected,

    panchayat President, professional assessors, and implementing NGO to assess

    replacement value of lost assets through a land market value survey and through

    compiling and comparing other available sources of information. Replacement

    value of agriculture land will be paid to make up for the loss incurred due to land

    acquisition. All payment will be made in a transparent manner in public.

    ii) Assistance to Livelihood Restoration

    57. APs living below the poverty line, women headed, elderly and destitute will

    be provided preferential employment opportunities in project construction works

    to compensate the partial loss of livelihood.

    58. Of the 19 households (15 households losing agricultural land and 4

    households operating ferryboat services who will be indirectly affected) 7

    households fall under the vulnerable category (WHH, elderly and BPL) and will be

    supported through the livelihood programme under TEAP. Further, the ferryboat

    operators numbering 5 (belonging to 4 families) and 29 employees employed by

    the ferry boat operators will also be supported through the livelihood programme

    under TEAP. The livelihood support programme under TEAP supports; i) capacity

    building, enterprise training, and economic activities to already organized self-

    help groups (SHGs); ii) formation of new SHGs, for both men and women, from

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    29

    affected households not yet organized in community-based groups for restoring

    livelihoods through micro-enterprise training and establishment support; and iii)

    skills upgrading.

    M. Budget

    59. The total estimated cost for resettlement implementation including cost of

    compensation and assistance as per the Resettlement Framework (Tamil Nadu)

    under TEAP is Rs.1,152,322/-.

    60. Notes and assumptions to costing: The cost estimate is based on

    information collected in the field, consultations had with the APs and revenue

    staff and findings of census survey.

    a. Guideline value for Land is as of 2003 and is yet to be revised and made

    public. For current prices, a 7% variation has been taken for one year

    (current inflation has been taken as the basis) and 2006 prices have been

    arrived.

    i. Further, on the basis of G.O. Ms. No. 885, Revenue dated

    21.9.1995, compensation for land has been calculated at 150% of

    the guideline value.

    ii. The 150% is arrived on the following basis. Under acquisition

    invoking LA Act, normally the valuation of land includes guideline

    value of land, plus additional 30% of solatium for compulsory

    nature of acquisition, plus a 12% of interest per annum from the

    date of publishing notification of section 4(1). Under private

    negotiation the competent authority is empowered vide above

    referred GO, to pay up to 150% that includes an additional 8%

    over and above solatium and interest.

    iii. Registration charges and stamp duty is currently 9% of the

    purchase price / guideline value, which ever is higher.

    iv. Since the purchase of land with the compensation amount paid is

    dependant on availability of suitable land and may take some time,

    all APs will be paid the registration charges and stamp duty along

    with land compensation. The same has been reflected in the

    budget.

    b. For loss of income three months income declared during census survey is

    provided as assistance and for loss of wages / salary, three months minimum

    wages is budgeted for.

    c. Livelihood support for loss of income and vulnerable category will be as per

    ADBs $51.15 million livelihood support programme and will implemented by

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    30

    Rural Development Department, GoTN. The eligible people will be linked to

    the ongoing programme and hence no separate budgetary allocation has

    been made in this RP. The livelihood support programme will be extended to

    38 families [4 ferry service operators, 29 persons employed in boat service,

    and 5 vulnerable (out of 7 vulnerable 1 WHH, 4 BPL, 1 SC and 1 Old age

    2 come under income loss category)] having loss of income and those

    belonging to vulnerable.

    d. The following assistance are provided as per comments given on the draft

    report.

    a. Those who are vulnerable or losing significant income as a result of

    the subproject will be given an Economic rehabilitation grant at the

    rate of Rs.3,000/- per household.

    b. Training would be provided for up-gradation of skills @ Rs.2,500/ -

    per family to the APs belonging to those loosing significant income

    as result of the loss and becoming vulnerable.

    Table 19. Budget Estimate

    S.No Item Description Unit Quantity Rate Amount

    A. Compensation

    1 Private Land Sq.m. 4430 79 349,970

    2 Registration charges and stamp duty Land Value 349,970 0.09 31,498

    3 Perennial Trees Number 0 - -

    4 Trees having fuel wood Value Number 0 - -

    5 Kutcha Residential Structure Number 0 - -

    6 Semi Permanent Residential Structure Number 0 - -

    7 Commercial Structure - Kutcha Sq.m. 0 - -

    B. RP Assistance and Activities

    1 Shifting Assistance Number 0 2,000 -

    2 Loss of business (boat) Income Number 4 12,500 50,000

    3 Loss of wages Number 29 7,200 208,800

    4 Economic Rehabilitation Grant Number 38 3,000 114,000

    5 Additional assistance to vulnerable groups

    Number 7 3,000 21,000

    6 Training assistance to affected households

    Number 38 2,500 95,000

    C: Support for RP Implementation

    1 NGO Assistance for RP updation and implementation

    Lump sum

    50,000

    2 Independent M&E Lump sum

    30,000

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    31

    3 Training and orientation to the NGO / Agency staff by the Social Development & Resettlement Specialist (PMU)

    Lump sum

    10,000

    Sub total 960,268

    Contingency @ 20% 192,054

    Total 1,152,322

    N. Implementation Schedule 61. The timeframe for various activities of RP is depicted in the Gantt Chart in

    page 32.

    O. Monitoring & Evaluation

    62. RADMMD will establish a monthly monitoring system and prepare monthly

    progress reports on all aspects of land acquisition and resettlement activities. The

    report will contain progress made in RP implementation with particular attention

    to monitoring and the delivery of entitlements. The deputed official in charge of

    land acquisition and resettlement in the PMU with assistance from the social

    development and resettlement specialist, through the Highways Department and

    NGOs will monitor the progress of land acquisition and resettlement and also

    prepare biannual reports, forwarding them to ADB for review. An independent

    agency/monitoring expert will be engaged by the PMU in agreement with ADB to

    undertake biannual external monitoring of the subproject implementation. This

    expert will submit the reports biannually via PMU to ADB. The drafts TOR for the

    appointment of M&E consultancy firm / expert is given vide Appendix-IV.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    32

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    33

    Appendix I

    Summary of Affected Persons

    Entitlement

    AHs S.No

    Present Owner Extent

    Acquired in sq.m.

    Percent acquired of total holding

    Type of Loss Land

    Compensation

    Income loss assistance

    Support through ADBs

    Livelihood Programme

    Direct Impact

    1 Muthiah. K 636 12.6 Land

    54,766 -

    2 Muniyasamy Padayachi. A 422 42.2 Land

    36,338 -

    @ #

    3 Kannagi. C 432 34.6 Land

    37,200 -

    @ #

    4 Samithurai. P 248 38.2 Land

    21,355 -

    5 Muthukrishnan. L 330 30.0 Land

    28,416 -

    6 Rathinavel. V 315 22.5 Land

    27,125 -

    7 Selvamani. P 325 21.0 Land

    27,986 -

    8 Gunasekaran. C 495 55.0 Land

    42,624 -

    9 Ramachandran. T 179 15.6 Land

    15,414 -

    10 Rajagopal. G 120 60.0 Land

    10,333 -

    11 Ramasamy. G 141 40.3 Land

    12,142 -

    @ #

    12 Balakrishnan. M 99 0.8 Land

    8,525 -

    @ #

    13 Somu. P 83 41.5 Land

    7,147 -

    14 Somu. C 90 45.0 Land

    7,750 -

    @ #

    15 Rajendran. T 515 5.2 Land

    44,347 -

    Indirect Impact (Ferry Owners)

    16 Ramar. S - - Income - 12,500 @ # 17 Valli.S (Mrs) - WHH - - Income - 12,500 @ #

    18 Kothandapani.P and Chandra - - Income -

    12,500 @ #

    19 Rajangam. A - - Income - 12,500 @ # Indirect Impact (Ferry Staff)

    20 Sashi - - Income - 7,200 @ #

    21 Oli - - Income - 7,200 @ #

    22 Rajesh - - Income - 7,200 @ #

    23 Kumar - - Income - 7,200 @ #

    24 Chinna Kunju - - Income - 7,200 @ #

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    34

    Entitlement

    AHs S.No

    Present Owner Extent

    Acquired in sq.m.

    Percent acquired of total holding

    Type of Loss Land

    Compensation

    Income loss

    assistance

    Support through

    ADBs Livelihood

    Programme

    25 Gajendran - - Income - 7,200 @ #

    26 Aruldas - - Income - 7,200 @ #

    27 Saminathan - - Income - 7,200 @ #

    28 Gothandam - - Income - 7,200 @ #

    29 Kuppusamy - - Income - 7,200 @ #

    30 Ramesh - - Income - 7,200 @ #

    31 Murugan - - Income - 7,200 @ # 32 Kathir - - Income - 7,200 @ # 33 Balamurugan - - Income - 7,200 @ #

    34 Ilayaraja - - Income - 7,200 @ #

    35 Selvamani - - Income - 7,200 @ #

    36 Rayar - - Income - 7,200 @ #

    37 Gajendran - - Income - 7,200 @ # 38 Natesan - - Income - 7,200 @ # 39 Ramasamy - - Income - 7,200 @ # 40 Thangasamy - - Income - 7,200 @ # 41 Chinna Pillai - - Income - 7,200 @ # 42 Ramu - - Income - 7,200 @ # 43 Vasanth - - Income - 7,200 @ # 44 Balakrishnan - - Income - 7,200 @ # 45 Ramadoss - - Income - 7,200 @ #

    46 Backiyaraj Rajangam - - Income -

    7,200 @ #

    47 Vasanth Rajangam - - Income - 7,200 @ # 48 Sasi Ramar - - Income - 7,200 @ #

    Total 3,81,468 258,800

    @ --- Livelihood support for loss of income and vulnerable category will be as per ADBs $51.15 million livelihood support programme and will be implemented by Rural Development Department, GoTN. The eligible people will be linked to the ongoing programme and hence no separate budgetary allocation has been made in this RP. # --- They will be entitled for Rs.3,000/- as Economic Rehabilitation Grant and Rs.2,500/- as Training Assistance. The vulnerable will get additional grant of Rs.3,000/-

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    35

    Appendix II

    Public Consultation and Disclosure Plan

    Activity Task Timing (Date/ Period)

    No of People

    Agencies Feedback/

    Issues/ Concerns Raised

    Remarks

    Stakeholder Identification

    Mapping of the project area

    June 06 -

    SAI Consulting Engineers, Chennai

    - -

    Project information Dissemination

    Distribution of information leaflets to affected persons (APs)

    August 06

    89 NGO / Agency

    The project disclosure meeting was held in the project village.

    -

    Consultative Meetings with APs during Scoping Phase

    Discuss potential impacts of the project

    12.8.06 36 Economic Perspectives, Chennai

    The APs wanted The bridge to be built quickly

    Reasonable valuation for land and trees

    Reduce the approach road width to minimise impact

    -

    Public Notification

    Publish list of affected land parcels/sites in a local newspaper; Establish eligibility cut-off date

    March 07 - Highways Dept.

    LA process through private negotiations is in progress and will be completed by March 2007.

    -

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    36

    Activity Task Timing (Date/ Period)

    No of People

    Agencies Feedback/

    Issues/ Concerns Raised

    Remarks

    Socio-Economic Survey Collect socio-economic information on APs perception on the project

    July 06 89 Economic Perspectives, Chennai

    Information was collected on Socio-economic profile of

    the households; Access to services Awareness & perception of the sample households on the Project and its impact

    -

    Consultative Meetings on Resettlement Mitigation Measures

    Discuss entitlements, compensation rates, grievance redress mechanisms

    April 07 - NGO / Agency

    - -

    Publicize the resettlement plan (RP)

    Distribute Leaflets or Booklets in local language

    April 07 - NGO / Agency

    -

    -

    Full Disclosure of the RP to APs

    Distribute RP in local language to APs

    April 07 - Highways Dept

    - -

    Web Disclosure of the RP RP posted on ADB and/or EA website

    March 07 - Highways Dept

    Expecting full clearance for RP by mid March 2007

    -

    Consultative Meetings during DMS

    Face to face meetings with APs

    April 07 - NGO / Agency

    -

    Disclosure after Detailed Measurement Survey (DMS)

    Disclose updated RP to APs

    May 07 - NGO / Agency

    -

    Web Disclosure of the Updated RP

    Updated RP posted on ADB and/or EA website

    May 07 - RADMMD & ADB

    -

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    37

    Appendix III

    TERMS OF REFERENCE FOR THE NON-GOVERNMENT ORGANIZATION

    (NGO)/AGENCY

    I. Project description

    Government of Tamil Nadu has proposed to construct 5 high level bridges (HLB)

    under the Tsunami Emergency Assistance Project (TEAP) funded by the Asian

    Development Bank (ADB). Kodiyampalayam HLB is one among the 5 HLBs and is

    being proposed across Uppanar between Kaattar Village and Kodiyampalayam

    Island Village

    The Project intends to engage an experienced agency to assist with the

    implementation of the social and resettlement aspects of the Project namely the

    subproject Resettlement Plan (RP).

    II. Scope of work

    In general, the Project Management Unit (PMU) in Chennai, Tamil Nadu will be

    responsible for the effective, timely and efficient execution of the RP. The key

    tasks of the selected organization will be: -

    (i) Information Campaign on Resettlement Entitlements

    The agency will design, plan and implement an information campaign in the

    project area primarily to inform the APs about the entitlement policy and how to

    avail their respective entitlements. In particular, the agency will be responsible

    for undertaking a public information campaign at the project areas to inform the

    affected persons regarding:-

    The need for Land Acquisition (LA), wherever necessary;

    The likely consequences of the project on the communities;

    The R&R policy and entitlements;

    Assist APs in getting the compensation for their land and properties

    acquired for the project;

    Ensure proper utilization by the APs of various grants available under the

    R&R package. The agency will be responsible for advising the APs on how

    best to utilize any cash that may be provided under the RP, with emphasis

    placed on using such funds in sustainable way e.g. purchasing replacement

    land for that acquired.

    The campaign would include measures such as distribution of information

    booklets, leaflets, notices and other materials among the APs, community

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    38

    meetings, public announcements, and any other measures necessary to provide

    information to all the APs.

    (ii) Identification of APs and Issuance of Identity (ID) Cards

    The agency will identify and verify APs, on the basis of the resettlement census

    survey carried out and will facilitate the distribution of ID cards. This work will

    include identification of APs based on a census survey, preparation of ID cards,

    taking photograph of APs in the field, issuance of ID cards to APs and updating of

    ID cards, if required. An identity card would include a photograph of the AP,

    his/her socioeconomic profile and vulnerability, the nature and extent of loss

    suffered due to the project construction, and the choice AP with regard to the

    mode of compensation and assistance (if applicable, as per the RP).

    The agency shall prepare a list of APs, enlisting the losses and the entitlements as

    per the RP, after verification. During the identification and verification of the

    eligible APs, agency shall ensure that each of the APs are contacted and consulted

    either in groups or individually. The agency shall especially ensure consultation

    with vulnerable groups namely (a) those who are below the poverty line (BPL);

    (b) those who belong to scheduled castes (SC), (c) women-headed households

    (WHH); (d) elderly and (e) disabled persons.

    (iii) Updation of AP Database and Creation/Computerization of Database

    and AP Files

    The agency will be responsible for updating and preparing a comprehensive

    computerized database containing the data on land, structure, trees and other

    affected properties of the APs which will be used to prepare AP files and

    entitlements cards (EC). The database will contain information from land records

    and resettlement census data. The AP and EC files will be used for making

    payments of entitlements to the APs and monitoring the progress of resettlement

    work.

    (iv) Participation in Grievance Redress

    The agency will play a key role in assisting the APs in presenting their grievances

    or queries to the Grievance Redress Committee (GRC) which will be established at

    the PMU level with the primary objective of providing a mechanism to mediate

    conflict and cut down on lengthy litigation.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    39

    (v) Income Restoration

    The agency will also play a key role in providing income restoration assistance to

    the affected households losing their primary sources of livelihood/income as a

    result of the Project. The agency shall undertake consultations with the affected

    households on finalizing the skills training and also undertake a market feasibility

    survey to ascertain the feasibility of the skills being imparted to those affected.

    Based on the outputs of these, the NGO will plan out livelihood restoration

    activities as per ADBs livelihoodc support programme and link them to Nodal

    NGOs under TNCWD, GoTN. Emphasis will be paid on the vulnerable groups such

    as female headed households, SC households, poor etc.

    In addition, the agency would also be responsible for liasoning with the various

    government departments, in order to create a link up between the existing

    government schemes and the affected groups.

    (vi) Relocation assistance

    The development agency shall facilitate the process of relocation of the affected

    households getting displaced as a result of the project as per the RP.

    (vii) Community Participation

    In addition to the resettlement activities, the NGO will implement Community

    Participation Strategy for the Project. As part of this, the NGO will mobilize the

    various stakeholders in the community and organize focus group discussions

    (FGDs) at the subproject level, with community leaders, eminent citizens, local

    community based Organization (CBOs), as well as women and other socio-

    economically vulnerable groups such as Indigenous groups, scheduled caste and

    poor households, in order to establish direct public contact. The FGDs will aim at

    sharing information regarding the Project in each of the subproject area so as to

    ascertain views of the various groups in the community on their priorities, choice

    of technology, their views and concerns on the Project design and any other

    concern on safety and other issues. In particular the NGO will undertake the

    following:

    Formation of Community based groups in the subproject areas so as

    to promote organized community participation and representation.

    Special focus will be made on formation of womens groups representing

    women belonging to various socioeconomic groups to act as active

    agents and change makers in the process of participation thereby

    leading to their empowerment.

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    40

    Awareness Building Component would be undertaken on road safety

    measures with a focus on women and children .

    Capacity Building Component: Under this component, training and

    sensitization inputs would be provided to the community based

    organizations and groups such as womens groups and village Panchayat

    about leadership and management and maintenance of the assets

    created under the subprojects.

    III. Time frame

    The work is scheduled to start in ******** and will continue till the end of the

    Project i.e. ************. The agency should be fully prepared in terms of all

    logistics support to tackle and carry out the resettlement activities and tasks laid

    down above.

    IV. Selection criteria, Staffing, Implementation Plan

    The NGO/agency to be selected for the tasks must have proven experience in

    resettlement planning and implementation. Specifically, key quality criteria

    include: -

    Experience in direct implementation of programs in local, similar and/or

    in other districts in Tamil Nadu;

    Availability of trained staff capable of including into their programme

    Competence, transparency and accountability based on neutral

    evaluations, internal reports, and audited accounts;

    Integrity and experience to represent vulnerable groups against abuses

    and demonstrable mandate to represent local groups.

    Demonstrated experience in computerizing and managing resettlement-

    related database, and

    Experience in resettlement survey, planning, monitoring and evaluation.

    The agency chosen will have to agree to the terms and conditions under the RP.

    The following staffing provision may be necessary for smooth and effective

    implementation of the RP within the time frame:

    Team Leader ;

    Field coordinator ;

    Resettlement Implementation Worker

    Interested agency should submit proposal for the work with a brief statement of

    the approach, methodology, and field plan to carry out the tasks. The proposal

    should include: -

  • Short Resettlement Plan Construction of High Level Bridges Under TEAP Kodiyampalayam Bridge

    41

    (i) Relevant information concerning previous experience on resettlement

    implementation and preparation of reports.

    (ii) The proposal should also include samples of ID cards, information brochures,

    AP files etc. to be used during the implementation phase.

    (iii) The field plan must address training and mobilization of resettlement

    workers.

    Full CVs (2-3 pages) of key personnel (for e.g. the Team Leader, Field Co-

    coordinator) must be submitted along with the proposal. The Team Leader must

    have degree in social science (preferably economics, sociology, anthropology,

    development studies) and familiar with the local language. The Field coordinator

    must have prior experience in resettlement operation and management and

    familiar with the local language. The agency must be an established organization

    registered with the Government of Tamil Nadu / India.

    V. Budget

    ****** copies of the proposal - both technical and financial - should be

    submitted. The budget should include all expenses such as staff salary, training,

    computer/database, transport, field and any ot