rfi form - connecticut...rfi form rfi no.192 project: rockwell elementary school renovations and...

29
RFI FORM RFI NO. 191 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins Eastman CONSTRUCTION MANAGER: Rizzo Corporation DATE: 11/30/18 FROM: Roger Ward COMPANY NAME: Mather Corp. SUBJECT: Site Scope DISCIPLINE/TRADE: BP#17 Site Work DWG./SPEC. REFERENCE: Scope of Work QUESTION: BP #17-Sitework Scope Item 13: Is this contractor also responsible for snow and ice removal for the old Police Department located at 49 Plumtrees Rd where the contractors are allowed office trailers and storage? ANSWER: No. Johnson School Project Site Contractor is responsible for the old Police Department. RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Upload: others

Post on 06-Oct-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 191

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Roger Ward

COMPANY NAME: Mather Corp.

SUBJECT: Site Scope

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE: Scope of Work

QUESTION:

BP #17-Sitework Scope Item 13: Is this contractor also responsible for snow and

ice removal for the old Police Department located at 49 Plumtrees Rd where the

contractors are allowed office trailers and storage?

ANSWER:

No. Johnson School Project Site Contractor is responsible for the old Police

Department.

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 2: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 192

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Roger Ward

COMPANY NAME: Mather Corp.

SUBJECT: Site Scope

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE: Scope of Work

QUESTION:

BP #17-Sitework Item 7: The following spec sections are listed but not included in

the specifications. Section 321400 Concrete Unit Pavers and Section 323223

Modular Block Retaining Walls. Please clarify if this work is part of this project

and if so where are these items proposed on site?

ANSWER:

Delete from Scope

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 3: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 193

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Roger Ward

COMPANY NAME: Mather Corp.

SUBJECT: Site Scope

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE: Scope of Work

QUESTION:

BP #17-Sitework Item 36e: States final topsoil and lawn seeding is by BP #17B

Landscaping. Is it the intent to have BP #17 Sitework contractor strip and stockpile

existing topsoil and BP #17B will screen, amend as necessary and place topsoil?

Or is it up to BP #17 Sitework to remove and dispose of existing topsoil and BP

#17B will furnish and install imported topsoil?

ANSWER:

Topsoil can be stockpiled on site. Coordination location with Rizzo Corp. BP#17B

– Landscaping will screen, amend as necessary and place topsoil.

RESPONSE BY: SUSAN M. CHIPOURAS DATE: 12/6/18

Page 4: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 194

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Roger Ward

COMPANY NAME: Mather Corp.

SUBJECT: Site Scope

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE: Scope of Work

QUESTION:

BP #17-Sitework Item 30: References drawing SL 1.0 as a logistics plan. Please

supply a logistics plan for this site and if necessary the old Police Station.

ANSWER:

Logistics Plans are included in Addendum #4.

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 5: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 195

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Roger Ward

COMPANY NAME: Mather Corp.

SUBJECT: Site Scope

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE: Scope of Work

QUESTION:

BP #17-Sitework Item 35e: Refers to crane pads. Please clarify how many are

required and the size of each that should be installed.

ANSWER:

BP#17 shall provide a flat area for crane placement. Crane Pads are by the Bid

Package using the crane.

RESPONSE BY: DATE:

Page 6: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 196

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Roger Ward

COMPANY NAME: Mather Corp

SUBJECT: Spec for Round Rail Fence

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE: 2/C-600.2

QUESTION:

BP #17-Sitework Item 1: Has Timber Guide Rails (spec section 329400) listed as

part of the Sitework bid package but does not list the proposed Round Rail Fence

shown on plan sheet C 200.1 and also detail 2/C 600.2. Please clarify if both of

these items should be installed by BP #17 Sitework and not BP #17A Fencing.

Please furnish a spec section for the proposed Round Rail Fence.

ANSWER:

There is no specification for the round rail fence. Bid per detail.

BP#17 shall furnish & install Timber Guide Rails. (SMC – Rizzo)

RESPONSE BY: COLLEEN FOWLER - MMI DATE: 12/6/18

Page 7: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 197

PROJECT: Rockwell Elementary SchoolRenovations and Additions400 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Roger WardCOMPANY NAME: Mather Corp

SUBJECT: Generator Pad

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE: C-200.1

QUESTION:1. Plan Sheet C 200.1: Has a proposed concrete utility pad for generator. Please furnish a detail for this pad.

ANSWER:

REFER TO DETAIL ON SHEET E-501 FOR UTILITY PAD DETAIL.

RESPONSE BY: BRIAN POELTL DATE: 12/5/18

Page 8: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 198

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Roger Ward

COMPANY NAME: Mather Corp

SUBJECT: Dumpster Pad

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE: C-200.1

QUESTION:

Plan Sheet C 200.1: For the proposed dumpster pad there is a call out to use detail

6/C 600.2 but on plan sheet C 600.3 detail 9 dumpster enclosure there is also a

detail for the concrete pad. Which one should be used?

ANSWER:

Both details are applicable. Detail 9 is for the enclosure fencing and the concrete

dumpster pad detail is for the concrete pad.

RESPONSE BY: DAN KROEBER, MMI DATE: 12/4/18

Page 9: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 199

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Roger Ward

COMPANY NAME: Mather Corp

SUBJECT: Existing Water Line

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE: C-301.1

QUESTION:

Plan Sheet C 301.1: Has a proposed 4” tapping valve proposed for the new 6” fire

line. What is the size of the existing waterline to be tapped?

ANSWER:

The tapping sleeve should be a 6” tapping sleeve to match the size of the 6” fire

service. The exact size of the existing water line is unknown. Please assume that

it is an 8” main that is being tapped.

RESPONSE BY: DAN KROEBER, MMI DATE: 12/4/18

Page 10: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 200

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Roger Ward

COMPANY NAME: Mather Corp

SUBJECT: Exterior Grease Trap

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE: Scope

QUESTION:

BP #17-Sitework Item 35.g: Has BP #14 Plumbing furnishing and installing the

proposed exterior grease trap. Detail 9/ P-500 shows a 12” concrete pad at finished

grade and a 12’ (item F) prefabricated concrete deadmen. Which trade is

responsible for the furnishing and install of concrete pad and deadmen?

ANSWER:

BP#17 - Sitework

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 11: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 201

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ryan Davis

COMPANY NAME: Schenectady Steel

SUBJECT: Equipment Screens

DISCIPLINE/TRADE: BP#4 – Structural Steel & Misc. Metals

DWG./SPEC. REFERENCE: Scope

QUESTION:

Please reconsider the roof top equipment screens and exterior sound screens to be

part of BP6 or 7.

There is no structural support steel shown on the structural drawings or on 9 / A-

324.

ANSWER:

There are no Rooftop Equipment Screens on Rockwell.

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 12: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 202

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ryan Davis

COMPANY NAME: Schenectady Steel

SUBJECT: Anchor Bolt Survey

DISCIPLINE/TRADE: BP#4 – Structural Steel & Misc. Metals

DWG./SPEC. REFERENCE: Scope

QUESTION:

Does BP#4 own an anchor bolt survey?

ANSWER:

Yes

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 13: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 203

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ryan Davis

COMPANY NAME: Schenectady Steel

SUBJECT: Scope of Work

DISCIPLINE/TRADE: BP#4 – Structural Steel & Misc. Metals

DWG./SPEC. REFERENCE: Scope

QUESTION:

All demolition, shoring, and abatement covered by BP#1?

ANSWER:

Demolition and Shoring by BP#1 – Demolition & Abatement. All contractors are

responsible for lead removal work and cost wherever they are attaching to existing

painted surfaces.

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 14: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 204

PROJECT: Rockwell Elementary SchoolRenovations and Additions400 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Richard MeloCOMPANY NAME: MJ Daly

SUBJECT: Piping Insulation

DISCIPLINE/TRADE: BP#15 – HVAC

DWG./SPEC. REFERENCE: 23 07 19

QUESTION:HVAC Piping Insulation Spec (23 07 19, page 26 #G), states to insulate the Engine Exhaust Piping and Silencer with Calcium Silicate: 4 inches thick? There is no engine exhaust piping, silencer or generator shown on the HVAC drawings? Please verify this spec section can be ignored for this project?

ANSWER:Engine exhaust / silencer insulation does not apply to this project.

RESPONSE BY: Jesse Vose, PE DATE: 12-05-2018

Page 15: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 205

PROJECT: Rockwell Elementary SchoolRenovations and Additions400 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Richard MeloCOMPANY NAME: MJ Daly

SUBJECT: Equipment Insulation

DISCIPLINE/TRADE: BP#15 – HVAC

DWG./SPEC. REFERENCE: 23 07 19

QUESTION:"HVAC Equipment Insulation Spec (23 07 16, page 24 #J) states that the Piping system filter-housing insulation shall be one of the following:1. Cellular Glass: 3 inches thick.2. Mineral-Fiber Board: 2 inches thick and 3-lb/cu. ft. nominal density.3. Mineral-Fiber Pipe and Tank: 2 inches thick.Please provide a detail on the filter housings needed so the HVAC Insulation Contractors can account for this, if necessary?"

ANSWER:Piping system filter-housing insulation does not apply to this project.

RESPONSE BY: Jesse Vose, PE DATE: 12-05-2018

Page 16: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 206

PROJECT: Rockwell Elementary SchoolRenovations and Additions400 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Richard MeloCOMPANY NAME: MJ Daly

SUBJECT: Heat Trace

DISCIPLINE/TRADE: BP#14 – Plumbing

DWG./SPEC. REFERENCE: P-300

QUESTION:Please verify that the Plumbing Contractor would only own furnishing and installing the heat tracing found on drawing P-300. The Heat Trace spec has extensive requirements including Gutters & Downspouts, Snow & Ice Melting on Roofs, etc., but none of these items are shown on the Plumbing drawings? Please advise on the scope of work to carry for Heat Tracing, if additional items are required, other than what is shown on the P-300 Plumbing drawing.

ANSWER:

The Construction Manager is responsible to advise you on your scope of the project.

RESPONSE BY: JIM STENQVIST DATE: 12/5/18

schipouras
Typewritten Text
schipouras
Typewritten Text
schipouras
Typewritten Text
schipouras
Typewritten Text
schipouras
Typewritten Text
schipouras
Typewritten Text
schipouras
Typewritten Text
schipouras
Typewritten Text
BP#14 - Plumbing owns heat trace shown on plumbing drawings. BP#16 - Electrical owns final power connections. (SMC @ Rizzo)
schipouras
Typewritten Text
Page 17: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 207

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Michelle Shuler

COMPANY NAME: Tull Brothers

SUBJECT: Hardware

DISCIPLINE/TRADE: BP#6 – General Trades

DWG./SPEC. REFERENCE: P-300

QUESTION:

Opening #120 is a single opening asking for hardware set #14 which is for a paired

opening. Please confirm correct hardware set.

ANSWER:

Provide HW set #01.

RESPONSE BY: JC@PE DATE: 12/5/18

Page 18: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 208

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Michelle Shuler

COMPANY NAME: Tull Brothers

SUBJECT: Door Schedule

DISCIPLINE/TRADE: BP#6 – General Trades

DWG./SPEC. REFERENCE: P-300

QUESTION:

Opening # ST-102B is an exterior opening that is calling out for a wood door and

an aluminum frame. Head and jamb detail shows a hollow metal frame. Should this

opening be an aluminum door and frame seeing it is exterior? Please confirm?

ANSWER:

Provide Aluminum door and frame.

RESPONSE BY: JC@PE DATE: 12/5/18

Page 19: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 209

PROJECT: Rockwell Elementary SchoolRenovations and Additions400 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ken HuntCOMPANY NAME: Rizzo Corp.

SUBJECT: Kitchen FCU power

DISCIPLINE/TRADE: BP#16 – Electrical

DWG./SPEC. REFERENCE: EP-101B, 1/E-202, M-101B

QUESTION:EP-101B Kitchen send you to detail 1/E-202. I do not see power for FCUs (refer to M-101B)

ANSWER:

ELECTRICAL DRAWING EP-101B SHOWS POWER TO FCU-1 IN KITCHEN OFFICE 122A. (CIRCUIT 18,20,SB-1). FCU NOT LOCATED IN KITCHEN CALL OUT AREA SHOWN ON E-202.

RESPONSE BY: BRIAN POELTL DATE: 12/6/18

Page 20: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 210

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: David Lukesky

COMPANY NAME: Barrett Roofing

SUBJECT: Roof Color

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

There are details that call out White EPDM Membrane. The color of the membrane

in Spec Section 075323 is called out as black. What shall be the color of the

furnished EPDM membrane?

ANSWER:

EPDM shall be Black as Specified.

RESPONSE BY: A.DOBBERTIN@PE DATE: 12/05/2018

Page 21: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 211

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: David Lukesky

COMPANY NAME: Barrett Roofing

SUBJECT: Phenolic Shelf Box

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

Reference detail 3&6/A-322. Is top of the phenolic shelf/box covered with EPDM,

or is that a flashing for the phenolic panel assembly? Who is responsible for this

condition?

ANSWER:

BP#7 – Roofing is responsible for flashing on details 3 & 6/A-322.

RESPONSE BY: Ken Hunt DATE: 12/6/18

Page 22: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 212

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: David Lukesky

COMPANY NAME: Barrett Roofing

SUBJECT: Wood Blocking Scope

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

Please clarify which contractor(s) are to furnish and install the wood blocking,

plywood, sheathing and insulation materials at the roof edge conditions. Reference

details 3, 6, 9 & 12 on A-321 and 3, 6, 7 & 9 on A-322.

ANSWER:

BP#6 – General Trades owns details 3,6,9 & 12 on A-321 and details 3,6,7 & 9 on

A-322.

RESPONSE BY: Ken Hunt DATE: 12/6/18

Page 23: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 213

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: David Lukesky

COMPANY NAME: Barrett Roofing

SUBJECT: Roofing

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

Specification section 076200 references a 3-coat fluoropolymer finish which is an

expensive finish. Is a 2-coat finish acceptable?

ANSWER:

Provide 3-coat finish as specified.

RESPONSE BY: J. CULOTTA @ PE DATE: 12/06/2018

Page 24: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 214

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: David Lukesky

COMPANY NAME: Barrett Roofing

SUBJECT: Canopy Plywood

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

Please identify which contractor is to furnish and install the plywood sheathing for

the roof deck on the Canopy at the Bus Loop.

ANSWER:

BP#6 - General Trades

RESPONSE BY: Ken Hunt DATE: 12/6/18

Page 25: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 215

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Peter Maddox

COMPANY NAME: Richards Corp.

SUBJECT: Topsoil

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE:

QUESTION:

Which bid package is responsible for screening and placing topsoil?

ANSWER:

BP#17B - Landscaping

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 26: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 216

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Peter Maddox

COMPANY NAME: Richards Corp.

SUBJECT: Timber Rails

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE:

QUESTION:

Please confirm Site Contractor shall furnish the timber rails.

ANSWER:

BP#17 - Site Work shall furnish and install timber rails.

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 27: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 217

PROJECT: Rockwell Elementary SchoolRenovations and Additions400 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Mark HaberCOMPANY NAME: Rizzo Corp.

SUBJECT: Feeders for LS Panels

DISCIPLINE/TRADE: BP#16 – Electrical

DWG./SPEC. REFERENCE:

QUESTION:Per E-401 it shows that the Feeders for the LS panels are to be run at a 2 Hour Fire rating. The rest of the cabling that runs out of this panel is not 2 hour rated. Because of this can Normal Conduit/Conductors be run in lieu of having the 2 hour fire rating on the main feeder only?If the 2 hour fire rating is to be maintain can 2 hour fire rated cable be used in lieu of conduit/conductors?

ANSWER:

ALL FEEDER CIRCUITS SHALL BE 2 HOUR RATED (HORIZONTAL AND VERTICAL), LISTED/LABELED, AND INSTALLED IN ACCORDANCE WITH UL 2196 (E.G. MINERAL INSULATED CABLES) AS INDICATED ON E-401. BRANCH WIRING DOES NOT HAVE TO BE 2 HOUR RATED.

RESPONSE BY: BRIAN POELTL DATE: 12/6/18

Page 28: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 218

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Michael Walton

COMPANY NAME: Northeast Interior Systems

SUBJECT: Addendum #4, RFI-040

DISCIPLINE/TRADE: BP#5 – Architectural Woodwork

DWG./SPEC. REFERENCE:

QUESTION:

RFI 040 was asked specifically about the doors and drawer fronts. My RFI applies

to all of the core material. We request FSC ULEF M2 particleboard be included as

an acceptable core material for the case body and doors of the plastic-laminate

cabinets on this project. (NU GREEN 2 Product Data attached).

ANSWER:

FSC ULEF M2 particle board is acceptable for use for the core material.

RESPONSE BY: JC@PE DATE: 12/6/18

Page 29: RFI FORM - Connecticut...RFI FORM RFI NO.192 PROJECT: Rockwell Elementary School Renovations and Additions 400 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 219

PROJECT: Rockwell Elementary School

Renovations and Additions

400 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Tom Rodrigue

COMPANY NAME: Imperial Roofing

SUBJECT: Existing Roof Insulation

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

Is the Existing Roof insulation to remain in place? See Demo Note “F” on AD-

102A. Indicates Existing Roof Insulation to remain…..

ANSWER:

No. See updated note in Addendum #5.

RESPONSE BY: A. DOBBERTIN@PE DATE: 12/05/2018