    Project Risk Management X440

    Sonja Koppensteiner, PhD, MSM,

    PMP

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Interglobeconsulting.com

    Welcome

    Introduction:

    Your Name

    Professional Background

    Project Management Experience Motivation for taking this class

    Expectations

    Favorite cuisine

  • 7/31/2019 RiskMgmt Session 2012 Handout

    2/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Interglobeconsulting.com

    Logistics

    Thursdays, 6.30pm to 9.30 pm

    Time for in class project

    Breaks as needed

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Interglobeconsulting.com

    Logistics Cont.

    3 Short Quizzes (20%)

    Student Project (50%)

    Attendance & Participation (30%)

  • 7/31/2019 RiskMgmt Session 2012 Handout

    3/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Quizzes

    In Class

    Multiple Choice & Short Answers & Exercises

    Closed Book

    3 Quizzes

    Best two out of three will be

    Counted for grade

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Team Project

    Identify team

    Each team works on the same projectthroughout the duration of this course

    Each team member contributes to the project.

  • 7/31/2019 RiskMgmt Session 2012 Handout

    4/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Individual Presentation

    Risk Management Topic of your choice

    10 Minute Presentation & ending with an

    engaging discussion question for class.

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    What is a Project?

    A Project is an output-oriented activity with

    the following characteristics:

    Unique final product

    Definite start and stop times

    Tasks requiring a variety of skill sets Team members with well-defined roles and

    responsibilities

    What is the definition in PMBOK?

  • 7/31/2019 RiskMgmt Session 2012 Handout

    5/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Examples of Projects

    Generic examples: Building a house

    Holding a wedding

    Organizing a conference

    Installing a network

    Implementing a new service/process

    Developing and implementing new software

    What are some current projects at your work?

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    What is Project Management?

    Serving Market Need

    Unique & Time Limited

    Finances for Resources

    Infrastructure

    The application of knowledge, skills, tools, and

    techniques to project activities to meet the project

    requirements (Source PMBoK)

  • 7/31/2019 RiskMgmt Session 2012 Handout

    6/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Projects can be Difficult .

    Goal confusion

    Role confusion

    Lack of team buy-in

    Poor (or no) planning

    Unrealistic schedules

    Scope creep

    Unforeseen project risks Inconsistent management support

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    What is a Successful Project?

    A project is a success when:

    End product is delivered complete,

    on-time, and within budget.

    Customers are delighted

    Project Team is enthusiastic The organization is better off

  • 7/31/2019 RiskMgmt Session 2012 Handout

    7/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    The Triple Constraint

    Quality

    Good, Fast, Economical-- Pick one ...

    Scope

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Project Roles

    Executive Sponsor

    Project Manager

    Core Team Members

    Extended Team Members

  • 7/31/2019 RiskMgmt Session 2012 Handout

    8/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Organizational Structure Options

    Functional

    Projectized

    Strong Matrix

    Weak Matrix

    Composite

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    ChiefExecutive

    FunctionalManager

    Staff

    Staff

    Staff

    FunctionalManager

    Staff

    Staff

    Staff

    FunctionalManager

    Staff

    Staff

    Staff

    Project Coordination

    Functional Organization

  • 7/31/2019 RiskMgmt Session 2012 Handout

    9/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    ChiefExecutive

    ProjectManager

    Staff

    Staff

    Staff

    ProjectManager

    Staff

    Staff

    Staff

    ProjectManager

    Staff

    Staff

    Staff

    Project Coordination

    Project Organization (Projectized)

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    ChiefExecutive

    FunctionalManager

    Staff

    Staff

    Staff

    FunctionalManager

    Staff

    Staff

    Staff

    FunctionalManager

    Staff

    Staff

    Staff

    PM Group

    ProjectManager

    ProjectManager

    ProjectManager

    Strong Matrix Organization

  • 7/31/2019 RiskMgmt Session 2012 Handout

    10/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    ChiefExecutive

    FunctionalManager

    Staff

    Staff

    Staff

    FunctionalManager

    Staff

    Staff

    Staff

    FunctionalManager

    Staff

    Staff

    Staff

    Project Coordination

    Weak Matrix Organization

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    ChiefExecutive

    FunctionalManager

    Staff

    Staff

    Staff

    FunctionalManager

    Staff

    Staff

    Staff

    FunctionalManager

    Staff

    Staff

    Staff

    PM Group

    ProjectManager

    ProjectManager

    ProjectManager

    Composite Organization

    A

    B

  • 7/31/2019 RiskMgmt Session 2012 Handout

    11/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Organizational Structures Key Characteristics

    Functional Project Matrix

    One supervisor PM is supervisor Two supervisors

    Slower information flow Project focus Decision process canslow down progress

    PM no authority PM has authority Weak strong Matrix

    Problems in integration ofproject components

    Duplicated job functions Conflicting priorities

    Team member notaffiliated with project

    Dedicated teammember

    Shared project resources

    Better career path No home for teammember

    In-depth expertise Less development ofexpertise

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Balance of Influence

    Projectized

    OrganizationFunctional

    Organization

    Balance of Influence & Power

    Strong

    Matrix

    Weak

    Matrix

    Project Managers

    Influence & Power in

    decision making

    Functional Managers

    Influence & Power in

    decision making

  • 7/31/2019 RiskMgmt Session 2012 Handout

    12/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Seven Factors for PM Structure

    Size of project

    Strategic importance

    Novelty and need for innovation

    Number of departments

    Number of external interfaces

    Budget and time constraints

    Stability of resource requirements

    AuthorityAutonomy

    ofProject Manager

    Project Team

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Project Life Cycle

    Starting

    the project

    Organizing

    and preparingCarrying out the work

    Closing the

    project

    Project

    Charter

    Project Management

    Plan

    Accepted

    Deliverables

    Archived

    Project

    Documents

    Staffing & Cost Level

  • 7/31/2019 RiskMgmt Session 2012 Handout

    13/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Why a Project Charter?

    Clarifies the project objectives

    Documents the expected project results

    Obtains executive commitment

    to the project approach

    Provides a foundation for

    making project decisions

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Example Project Charter

    Project Name: Quick Answer Help Desk

    Sponsor: Sally Green

    Project Mgr: George Boyd

    Charter Version #: V 1.1

    Updated by: George Boyd

    Approved By: Sally Green

    Approval Date: Oct 15, 2000

    Project Objective Statement:

    Implement an automated Expert Solutions Databaseand Request Tracking system that enables Help Deskstaff to provide top quality service to our expandingcustomer base.

    Project Deliverables:

    1. Vendor Selection Documentation2. Software Interface Tailoring3. Installed Help Desk Server and network4. Installed Expert Solutions Database5. Installed Service Request Tracking Database6. Help Desk Escalation Procedure7. Training Materials for Help Desk Analysts

    Customer:

    Help Desk Staff

    IT Support Organization

    Division Employees who make Service Request

    Customer Benefits:

    1. Ability to provide correct response to frequentlyasked questions

    2. Ability to build knowledge base of successfulresponses

    3. Automated tracking of call volume andresponse time

    4. Improved response time and customer service

    Successful Completion Criteria:

    1. Expert Solution Database includes answersto 60% of all expected customer requests

    2. Maximum wait time for solution databasesearch is 30 seconds

    Estimated Start Date: Sept 1, 2000

    Estimated End Date: June 30, 2001

    Level of Uncertainty: -25% - + 75%

    Triple Constraint Trade-off:

    Resources S

    Schedule N

    Scope M

    Select a different flexibility letterfor each constraint.Flexibility letter choices are:

    N = Not FlexibleS = Somewhat FlexibleM = Most Flexible

    Project Core Team Members

    Team Member RoleSally Green SponsorGeorge Boyd Project ManagerAlicia Monfort Network SupportJerry Smith IT ArchitectKen Davis Business AnalystWilma Ellis DeveloperLouise Roberts Procurement Analyst

    Project Scope:

    In Scope: Help Desk process to coverApplications Support, Desk TopSupport, and Network Supportcalls

    Purchasing of software andhardware

    Expert Solutions databases forstandard office automationapplications

    Out of scope: Organizational changes to create

    the Help Desk Help Desk process to cover

    procurement and trainingassistance calls.

    Development of Expert Solutionsdatabase for in-house applications

    Assumptions and Constraints:

    1. The current budget cycle allocated sufficientmoney for purchasing hardware and softwarefor this project.

    2. Minimal tailoring of the purchased solutionsdatabases.

    3. The procurement cycle for new equipmentrequires no more than a 3 month l ead time.

    Estimated Budget: $500,000

    Funding Source: ITSD Annual Budget

    Level of Uncertainty: -25% - + 75%

  • 7/31/2019 RiskMgmt Session 2012 Handout

    14/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Creating a Project Charter

    Identify the

    Problem/Opportunity

    Define the Project

    Outcome

    Determine the Project

    Approach

    Project Charter

    Name: Immediate Support Help DeskBackground: Current method ofprocessing customer support calls isinefficient and often inaccurate. Needa centralized facility with automatedsupport

    POS:Implement a Help Desk process and anautomated solutions database andrequest tracking system ----Scope:In: Application and Desktop supportOut: Procurement & Planning supportSponsor: Sally Green

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Short Form Project Charter TemplateProject Name: Project Name?

    Sponsor: Who champions project?

    Project Mgr: Who leads the project?

    Charter Version #: What is this version #?

    Updated by: Who created this version?

    Approved By: Who approved this version?

    Approval Date: When was it approved?

    Project Objective Statement:

    What must the project do? By When? Keep thisstatement short --- 25 words or less. Make it SMART(Specific, Measurable, Achievable, Relevant, andTime-based.)

    Project Deliverables:

    What is the project going to produce? (Create anumbered list of tangible products that will be availableas a result of this project.)

    Customer:

    Who is the Customer?

    Customer Benefits:

    What customer business requirements does thisproject address? Relate these to one of the following:increase revenue, avoid costs, improve service, and/or comply with a mandate? (Create a shortnumbered list of customer benefits.)

    Successful Completion Criteria:

    How will the success of the project be determinedfrom the customers perspective? Make these criteriameasurable so there is no doubt as to the projectssuccess. (Create a short numbered list.)

    Estimated Start Date: Start date?

    Estimated End Date: When will it finish?

    Level of Uncertainty: Plus or minus %?

    Triple Constraint Trade-off:

    Resources

    Schedule

    Scope

    Select a different flexibility letterfor each constraint.Flexibility letter choices are:

    N = Not FlexibleS = Somewhat FlexibleM = Most Flexible

    Project Core Team Members

    Team Member RoleWho is on the project? What role do they play?

    Project Scope:

    In Scope: List the business areas andfunctionality that will be included in thisroject.

    Out of scope: List the business areas andfunctionality that will not be included inthis project.

    Assumptions and Constraints:

    What assumptions were made in defining the project?Assumptions can affect scope, schedule, resources,stakeholders, etc. Are there constraints to theexecution of the project? Constraints describeboundaries within which the project must operate.(Create a numbered list of assumptions andconstraints.)

    Estimated Budget: $$$ Allocated?

    Funding Source: Where $$ come from?

    Level of Uncertainty: Plus or minus %?

    See PM for small

    projects Pg 48 to 54

  • 7/31/2019 RiskMgmt Session 2012 Handout

    15/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Project Business Reasons

    Customer/Stakeholders

    Customer Benefits

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Identify Stakeholders

    Who are your customers?Are they external or internal to your organization?

    Who will use the end product?

    Who will need to change their processes as a result ofyour project?

    Who interfaces with your project? What agencies can regulate the project?

    Is there anyone else who needs to know about yourproject?

  • 7/31/2019 RiskMgmt Session 2012 Handout

    16/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Project Outcomes

    Project Objective Statement

    Project Deliverables

    Successful Completion Criteria

    Project Scope

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Project Objective Statement (POS)

    Make it SMART*

    Make it SHORT

    Make it ENERGIZING!

    * Specific,Measurable,Achievable,

    Relevant,Time-based

  • 7/31/2019 RiskMgmt Session 2012 Handout

    17/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    POS Examples

    The Apollo Project: By the end of the decade, send a man tothe moon and return him safely to earth. (19 words).

    Photograph 16 landscapes around the world that are selectedin consultation with leading climate-change scientists andjournalists, in order to show persuasive visual evidence ofclimate change and its potential for devastation. Complete theproject by 2008. (38 words).

    Provide a single web platform for the integrated delivery ofinformation, services and online communication tools to theUniversity community. Complete the project by February 2008and a maximum cost of $250,000. (33 words).

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Identifying Deliverables

    What will the customer have when we finish?

    What will the support staff have when we

    finish?

  • 7/31/2019 RiskMgmt Session 2012 Handout

    18/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Defining Completion Criteria

    How do we know we are done??

    Acceptable

    Measurable

    Testable

    Achievable

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Whats in Scope?

    What will the project address?

    Geographic areas?

    Business functions?

    Equipment?

    Training?

    Installation?

    Infrastructure?

    What will the project notaddress?

  • 7/31/2019 RiskMgmt Session 2012 Handout

    19/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Management

    PMBoK:

    Includes the processes concerned with

    conducting risk management planning,

    identification, analysis, responses , monitoring

    & controlling

    Risk described by Probability, Impact, timing

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Probability

    P(A) =The Number Of Ways Event A Can Occur

    The total number Of Possible Outcomes

  • 7/31/2019 RiskMgmt Session 2012 Handout

    20/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Project Risk

    Definition

    An uncertain event or condition that, if it occurs,

    has a positive or a negative effect on project

    objectives.

    PMBOK Guide, fourth edition

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Project RiskManagement

    Plan RiskManagement

    Identify RiskPerform

    QualitativeRisk Analysis

    PerformQuantitativeRisk Analysis

    Plan RiskResponses

    Monitor andControl Risks

    Project Risk Management

  • 7/31/2019 RiskMgmt Session 2012 Handout

    21/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Categorization

    Comprehensive process

    Systematically identifies risk

    Consistent level of detail

    Provides a structure

    Effectiveness and Quality of risk identification

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Benefits of Risk Categorization

    Identify where risks are concentrated

    Focus on specific areas to develop risk

    responses

    View of total risk exposure from different

    perspectives

    Point out risk exposures that are not apparent

  • 7/31/2019 RiskMgmt Session 2012 Handout

    22/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Common Risk Categories

    General categories

    Technical

    External

    Organizational

    Project Management

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Common Risk Categories

    Project area

    Information

    Personnel

    Material

    Machinery Urgency

    Availability of resources

    Root causes

    Outdated machinery

    Inadequate training of

    personnel

  • 7/31/2019 RiskMgmt Session 2012 Handout

    23/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Common Risk Categories

    Political Government

    Planning mechanisms

    Safety mechanisms

    Trade Policy

    Customer Changes in strategic

    orientation

    Partner and Supplier Difficulties of collaboration

    People Availability

    Skills

    Market Competitors

    Customer expectations

    Financial

    Currency rates Economic environment

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Categorization - Methods

    Simple approach Make a list

    Use a Risk Breakdown Structure (RBS) A tool that arranges risks by categories and characteristics

    Can be broken down by project type

    Reminds participants of the many sources of project risks

  • 7/31/2019 RiskMgmt Session 2012 Handout

    24/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Project

    Technical

    Requirements

    Technology

    Complexity andInterfaces

    Performances

    and Reliability

    Quality

    External

    Subcontractorsand Suppliers

    Regulatory

    Market

    Customer

    Weather

    Organizational

    ProjectDependencies

    Resources

    Funding

    Prioritization

    ProjectManagement

    Estimating

    Planning

    Controlling

    Communication

    Example of RBS adapted from PMBOK Guide, 2004

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Categorization - ExampleRisk Category and Potential Risks Comments

    Physical Risks

    -Natural Hazards

    -Damage to structures and material due

    to fire

    -Natural disasters may occur

    - Negligent acts or improper use of

    safety methods

    Financial and Economic Risks

    -Exchange rate variation

    - Default of subcontractors

    -Increase (or decrease) in costs

    - Inadequate maintenance of quantity,

    schedule and cost performance

    Environmental Risks

    -Material and equipment transport

    problems due to inadequate

    infrastructure

    -Increase costs and delay the schedule

  • 7/31/2019 RiskMgmt Session 2012 Handout

    25/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Categorization - Example

    Risk Category and Potential Risks Comments

    Design Risks

    -Design errors and omissions

    -Incomplete design scope

    -Design errors have crucial effects on

    project

    - Lack of design stability can increase

    costs

    Legal Risks

    -Civil petitions of neighbors around the

    site

    -Contractual misinterpretation

    -Delay in construction due to petitions

    and complaints

    - Increase in costs due to difficulties in

    interpreting contract

    clauses

    Government-Permits and regulations

    -Delay in obtaining permits- Increase in costs and delays due to

    failed inspections

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Plan Risk Management

    Project ScopeStatement

    Costmanagementplan

    Schedulemanagementplan

    Communications managementplan

    EEF/OPA

    Planning meetingsand analysis

    Riskmanagementplan

    INPUTS TOOLS & TECHNIQUES OUTPUTS

    Source: PMBoK, 4th edition, PMI

  • 7/31/2019 RiskMgmt Session 2012 Handout

    26/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Management Process

    Risk

    Uncertain events that planning can not control.

    Can be positive -> Opportunity

    Can be negative -> Threat

    Risk Management

    A proactive attempt to recognize and manage uncertain

    events that affect the likelihood of a projects success.

    Issue vs. Risk

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    The Risk Event Graph

    FIGURE 7.1Source: Project Management, McGraw-Hill, 2006

  • 7/31/2019 RiskMgmt Session 2012 Handout

    27/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    External Risk Examples

    External Unpredictable Government intervention

    Standards

    Export/Import

    Natural Hazards

    Postulated Events Vandalism

    Completion Failure to complete the

    project due to failure offinancial support to the endof the project

    External Predictable Market Risks

    Economics

    Competition

    User rejection

    Operational Maintenance needs

    Safety

    Environmental Impacts

    Social Impacts Currency Impacts

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Internal Risk Examples

    Internal, non-technical Management

    Unrealistic schedule

    Lack of coordination

    Schedule

    Late deliveries

    Scope changes Cost

    Under-estimating

    Contractor claims

    Technical Changes in Technology

    Complexity introduced asa result of using newtechnology

    Performance

    Quality

    Reliability

    Design

    Inadequate data

    Suitability of specification Legal

    Licenses

    Patent Rights

    Contractual

  • 7/31/2019 RiskMgmt Session 2012 Handout

    28/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Managements Benefits

    Proactive approach.

    Reduces surprises & negative consequences.

    Provides better control over the future.

    Improves chances of reaching project performanceobjectives within budget and on time.

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Key Items of Risk Management Plan

    Methodology

    Roles/Responsibilities

    Budgeting

    Risk categories (PMBoK pg 280) Definitions of probability and impact

    Probability and impact matrix (PMBoK pg 281)

    Reporting format and Tracking

  • 7/31/2019 RiskMgmt Session 2012 Handout

    29/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Methology

    Defines what approach, tools and data

    sources team uses to perform risk

    management on the project.

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    The Risk

    Management

    Process

    FIGURE 7.2

    Source: Project Management, McGraw-Hill, 2006

  • 7/31/2019 RiskMgmt Session 2012 Handout

    30/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Roles and Responsibilties

    Defines the roles and responsibilities of risk

    management team members for each type of

    the activity in the risk management plan.

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Project

    Technical

    Requirements

    Technology

    Complexity andInterfaces

    Performancesand Reliability

    Quality

    External

    Subcontractorsand Suppliers

    Regulatory

    Market

    Customer

    Weather

    Organizational

    ProjectDependencies

    Resources

    Funding

    Prioritization

    ProjectManagement

    Estimating

    Planning

    Controlling

    Communication

    Example of RBS adapted from PMBOK Guide, 2004

  • 7/31/2019 RiskMgmt Session 2012 Handout

    31/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Defining Probability and Impact

    Probability or Likelihood

    Likelihood that the risk will occur

    Qualitative High, Medium, Low

    Quantitativenumeric probability in percentage

    Impact

    Qualitative High, Medium, Low

    Quantitativenumeric probability and $ value

    Timing

    Phase of project phase

    Trigger

    Frequency One time

    Multiple eventsRefers to qualitative and quantitative risk analysis

    in PMBoK

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Probabilityand impact matrix

    HL HM HH

    ML MM MH

    LL LM LH

    LIKELIHOOD

    Low Medium High

    IMPACT

    High

    Medium

    Low

    Source: Project Management, McGraw-Hill, 2006

    * Simplified version of the risk matrix shown in PMBoK, PMI

  • 7/31/2019 RiskMgmt Session 2012 Handout

    32/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Reporting format and Tracking

    Reporting Format

    How outcomes of risk management process will

    be documented, analyzed and communicated.

    Format of risk register

    Tracking

    How risk activities will be recorded

    How risk management processes will be audited.

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Simple Risk Register Example

    RiskID

    Description Owner Impact Likelihood Priority

    1 Use of newtechnologycan delayproject

    FunctionalManager

    Medium High MH

    2

    3

  • 7/31/2019 RiskMgmt Session 2012 Handout

    33/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Identify Risks

    Risk managementplan

    Activity costestimates

    Activity durationestimates

    Scope baseline

    Stakeholder register

    Cost managementplan

    Schedule

    management plan Quality management

    plan

    Project documents

    EEF/OPA

    Documentationreviews

    Informationgatheringtechniques

    Checklist analysis

    Assumptionsanalysis

    Diagrammingtechniques

    SWOT analysis

    Expert judgment

    Risk Register

    INPUTS

    TOOLS & TECHNIQUES OUTPUTS

    Source: PMBoK, 4th edition, PMI

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Identification T&T Overview

    Documentation reviews review of projectdocumentation

    Information gatheringtechniques Examples:

    Brainstorming

    Delphi Technique

    Interviewing

    Root Cause Analysis

    Checklist analysis riskidentification checklist

    Assumptions analysis

    Diagrammingtechniques Examples:

    Cause and Effectdiagrams

    System or process flowcharts

    SWOT analysis

    Expert judgment

  • 7/31/2019 RiskMgmt Session 2012 Handout

    34/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Example: Risk ChecklistExample: Partial Risk Profile for Product Development Project

    FIGURE 7.3Source: Project Management, McGraw-Hill, 2006

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Root Cause Analysis

    Root cause analysis is not a single, sharplydefined methodology; there are many differenttools, processes, and philosophies for performingRCA analysis.

    Common techniques

    Failure mode and effects analysis

    5 Whys ask why why why why over until exhausted

    Ishikawa diagram, also known as the fishbone diagramor cause-and-effect diagram.

    Pareto analysis "80/20 rule"

    http://en.wikipedia.org/wiki/Failure_mode_and_effects_analysishttp://en.wikipedia.org/wiki/5_Whyshttp://en.wikipedia.org/wiki/Ishikawa_diagramhttp://en.wikipedia.org/wiki/Pareto_analysishttp://en.wikipedia.org/wiki/Pareto_analysishttp://en.wikipedia.org/wiki/Pareto_analysishttp://en.wikipedia.org/wiki/Ishikawa_diagramhttp://en.wikipedia.org/wiki/Ishikawa_diagramhttp://en.wikipedia.org/wiki/5_Whyshttp://en.wikipedia.org/wiki/5_Whyshttp://en.wikipedia.org/wiki/Failure_mode_and_effects_analysishttp://en.wikipedia.org/wiki/Failure_mode_and_effects_analysis
  • 7/31/2019 RiskMgmt Session 2012 Handout

    35/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Management Oversight Risk Tree(MORT)

    Materials Defective raw material

    Wrong type for job

    Lack of raw material

    Man Power Inadequate capability

    Lack of Knowledge

    Lack of skill

    Stress

    Improper motivation

    Machine / Equipment Incorrect tool selection

    Poor maintenance or design

    Poor equipment or tool placement

    Defective equipment or tool

    Environment Orderly workplace

    Job design or layout of work

    Surfaces poorly maintained

    Physical demands of the task

    Forces of nature

    Management No or poor management involvement

    Inattention to task

    Task hazards not guarded properly

    Other (horseplay, inattention....)

    Stress demands

    Lack of Process

    Lack of Communication

    Methods No or poor procedures

    Practices are not the same as written procedures

    Poor communication Management system

    Training or education lacking

    Poor employee involvement

    Poor recognition of hazard

    Previously identified hazards were not eliminated

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    FMEA

    Failure Mode and Effects Analysis (FMEA)

    A step-by-step approach for identifying all possible

    failures in a design, a manufacturing or assembly

    process, or a product or service.

    Identification of

    failures, their priorities

    their impact on system,

    their causes

    Process controls

    Source: http://www.asq.org/

  • 7/31/2019 RiskMgmt Session 2012 Handout

    36/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Fishbone Diagram

    Also know as Cause and Effect Diagram or

    Ishikawa

    To identify possible causes for a problem and

    relates them to categories.

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Method Personnel

    Effect

    MaterialSite &

    Equipment

    Cause

    Cause

    Cause

    Cause

    Cause

    Cause

    Cause

    Cause and Effect Diagram /Fishbone

    Source: Effective Project Management by R. Wysocki, Wiley

  • 7/31/2019 RiskMgmt Session 2012 Handout

    37/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    We have 15 causes forfailure (A O).

    Which cause do weaddress first?

    Pareto Principle = the80/20 rule:

    20% of sources cause80% of the problems

    Gather the frequencies,sort and chart

    Cause # Failures

    35

    250

    15

    8

    36

    25

    15

    14

    350

    150

    75

    18

    30

    42

    ID

    1000

    Late

    arrival

    Missing part

    Access

    A

    B

    C

    D

    E

    F

    G

    H

    I

    J

    KL

    M

    N

    O

    Pareto Analysis Cont.

    Source: Effective Project Management

    by R. Wysocki, Wiley

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Cause

    0%

    5%

    10%

    15%

    20%

    25%

    30%

    35%

    I B J O E A N F M C G H D K L

    Percentage

    Pareto Chart

    Source: Effective Project Management

    by R. Wysocki, Wiley

  • 7/31/2019 RiskMgmt Session 2012 Handout

    38/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Flowcharting

    Process step

    Direction of Flow

    Begin and end of

    process

    Document

    Shows inputs and

    outputs

    Decisions

    Delays

    Connector to other

    page or part of chart

    Source: http://www.asq.org/learn-about-quality/process-analysis-tools/overview/flowchart.html

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Haircut

    needed?

    No

    Yes

    B

    Car

    ready?No

    Yes

    Drive Walk

    Barber

    ready?No

    Yes

    >3 people

    waiting?

    Yes

    B

    Wait

    Haircut

    B

    No

    Start

    Stop

    Flow Chart Example

    Source: Effective Project Management

    by R. Wysocki, Wiley

  • 7/31/2019 RiskMgmt Session 2012 Handout

    39/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    SWOT Analysis

    INTERNAL EXTERNAL

    Strength Opportunities

    Weaknesses Threats

    E.g.: specific section or set of activities

    of a project are being outsourced

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    SWOT Some Questions: Strength

    What are the advantages of the proposition?

    How competent is the project team?

    What are the Unique Selling Points of the

    proposition or project?

    Do we have the necessary resources, assets, andpeople?

    What is the estimated profitability of the project?

    Source: http://www.brighthub.com/office/project-management/articles/45156.aspx

    http://www.brighthub.com/office/project-management/articles/45156.aspxhttp://www.brighthub.com/office/project-management/articles/45156.aspx
  • 7/31/2019 RiskMgmt Session 2012 Handout

    40/51

  • 7/31/2019 RiskMgmt Session 2012 Handout

    41/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    SWOT Some Questions: Threats

    Is the market demand sustainable?

    Are there any competing technologies or servicesthat'll make success challenging?

    How will we account for staff attrition?

    Do we have sustainable financial backing?

    What are the current global economical implications?

    Are there any threats that'll make Cost PerformanceIndex (CPI) go under one or the Schedule

    Performance Index (SPI) over one (usefulecomputations Earned Value Management)?

    Source: http://www.brighthub.com/office/project-management/articles/45156.aspx

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Description

    Two Sections

    Description of the risk

    Impact on the project.

    Example:

    Use of new technology XYZ can delay project schedule.

    http://www.brighthub.com/office/project-management/articles/45156.aspxhttp://www.brighthub.com/office/project-management/articles/57944.aspxhttp://www.brighthub.com/office/project-management/articles/57944.aspxhttp://www.brighthub.com/office/project-management/articles/57944.aspxhttp://www.brighthub.com/office/project-management/articles/57944.aspxhttp://www.brighthub.com/office/project-management/articles/57944.aspxhttp://www.brighthub.com/office/project-management/articles/57944.aspxhttp://www.brighthub.com/office/project-management/articles/45156.aspx
  • 7/31/2019 RiskMgmt Session 2012 Handout

    42/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Perform Qualitative Risk Analysis

    Risk register

    Risk managementplan

    Project scopestatement

    OPA

    Risk probability/Impactassessment

    Probability/ImpactMatrix

    Risk data qualityassessment

    Risk categorization

    Risk urgency

    assessment

    Expert judgment

    Risk Registerupdates

    INPUTS TOOLS & TECHNIQUES OUTPUTS

    Source: PMBoK, 4th edition, PMI

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Describing a Risk

    Probability or Likelihood

    Likelihood that the risk will occur

    Qualitative High, Medium, Low

    Quantitativenumeric probability in percentage

    Impact

    Qualitative High, Medium, Low

    Quantitativenumeric probability and $ value

    Timing

    Phase of project phase

    Trigger

    Frequency

    One time

    Multiple events

  • 7/31/2019 RiskMgmt Session 2012 Handout

    43/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Qualitative Risk Assessment

    RiskID

    Description Owner Impact Likelihood Priority

    1 Use of newtechnologycan delayproject

    FunctionalManager

    Medium High

    2

    3

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Qualitative Approach to Prioritizing Risks

    HL HM HH

    ML MM MH

    LL LM LH

    LIKELIHOOD

    Low Medium High

    IMPACT

    High

    Medium

    Low

    See also PMBoK, page 292

  • 7/31/2019 RiskMgmt Session 2012 Handout

    44/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Priority

    RiskID

    Description Owner Impact Likelihood Priority

    1 Use of newtechnologycan delayproject

    FunctionalManager

    Medium High MH

    2

    3

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    More Qualitative Risk Analysis

    Risk Categorization by

    Sources of risk

    Affected project area

    Project phase

    Grouping by common rootcauses can guide to effective

    risk responses.

    Risk Urgency Assessment

    Urgent Risk

    Risk that requires upcoming

    risk responses.

    Can be combined with risk

    ranking (impact/probability

    matrix)

  • 7/31/2019 RiskMgmt Session 2012 Handout

    45/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Perform Quantitative Risk Analysis

    Risk register

    Risk managementplan

    Cost managementplan

    Schedulemanagement plan

    OPA

    Data gathering andrepresentationtechniques

    Quantitative riskanalysis and modelingtechniques

    Expert judgment

    Risk Registerupdates

    INPUTS TOOLS & TECHNIQUES OUTPUTS

    Source: PMBoK, 4th edition, PMI

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Examples for Quantitative Risk Analysis

    Data gathering andrepresentation techniques

    Interviewing Identifying risk ranges for

    low, medium, highprobability distributions

    Document rational of risk

    ranges Probability Distribution

    Continuous distribution

    Quantitative risk analysisand modeling techniques

    Sensitivity Analysis Which risk has most

    potential impact onproject

    Expected Monetary

    Value Analysis Calculated average

    outcome for possiblefuture scenarios

    Modeling and Simulation Monte Carlo Simulation

  • 7/31/2019 RiskMgmt Session 2012 Handout

    46/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Decision Tree Example

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Quantitative Risk Assessment

    RiskID

    Description Owner Cost Probability EMV

    1 Use of newtechnologycan delay

    project

    FunctionalManager

    $100k 0.5 $50k

    2

    3

  • 7/31/2019 RiskMgmt Session 2012 Handout

    47/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Process: Plan Risk Responses

    Purpose: Develop options and establish actions to

    enhance opportunities and reduce threats project

    objectives.

    Updates of the project plan required due to adding risk

    response activities and resources into the scope, schedule,

    and cost baselines.

    Key Outputs: Updated risk register,

    Risk-related contract agreements

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Plan Risk Responses

    Risk register

    Riskmanagementplan

    Strategies for negativerisks or threats

    Strategies for positiverisks or opportunities

    Contingent responsestrategies

    Expert judgment

    Risk registerupdates

    Risk-relatedcontract

    decisions Project

    managementplan updates

    Projectdocumentupdates

    INPUTS TOOLS & TECHNIQUES OUTPUTS

    Source: PMBoK, 4th edition, PMI

  • 7/31/2019 RiskMgmt Session 2012 Handout

    48/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Response Types - Threat

    Mitigating Risk

    Transferring Risk

    Avoiding Risk

    Acceptance

    Contingency

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Response Types - Opportunity

    Exploit

    Share

    Enhance

    Acceptance

    Contingency

  • 7/31/2019 RiskMgmt Session 2012 Handout

    49/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Risk Response Matrix

    FIGURE 7.7

    RiskID

    Description Owner RiskResponse

    Trigger ResponseType

    1 Use of newtechnologycan delayproject

    FunctionalManager

    Train teammembers innewtechnology

    AfterProjectBudget isapproved

    Mitigation

    2

    3

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Contingency Funding and Time Buffers

    Contingency Reserve

    Cover potentially required changes related to the

    outcome of identified risks

    Management Reserves unforeseen risks/changes

    are not part of the project cost baseline

    May be included in total budget

    Not included for earned value analysis

  • 7/31/2019 RiskMgmt Session 2012 Handout

    50/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Monitor and Control Risks

    Risk register

    Projectmanagementplan

    Workperformanceinformation

    Performancereports

    Risk reassessment

    Risk audits

    Variance and trendanalysis

    Technicalperformancemeasurement

    Reserve analysis

    Status meetings

    Risk registerupdates

    Organizationalprocess assets

    Change Requests

    Projectmanagementplan updates

    Projectdocumentupdates

    INPUTS TOOLS & TECHNIQUES OUTPUTS

    Source: PMBoK, 4th edition, PMI

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Key Tools and Techniques

    Risk Audits

    Examine and document effectiveness of risk responses and

    risk management process

    Technical Performance Measurement

    Compares technical accomplishments to the schedule of

    technical achievement.

    Requires definition of objective quantifiable measures of

    technical performance, e.g.: weight, transaction times,

    etc..

    compares actual results against targets.

  • 7/31/2019 RiskMgmt Session 2012 Handout

    51/51

    3/24/20

    InterGlobe Consulting. All Rights Reserved. Email: [email protected]

    Key Tools and Techniques

    Reserve Analysis

    Compare remaining amount of reserve to the remaining

    amount of risks

    Status Meetings

    Project risk management should be an agenda item at

    periodic status meetings.

    References

    Ackermann F, Eden C, Williams T, and Howick S. (2007, January). Systemic risk assessment: a

    case study. The Journal of the Operational Research Society, 58(1), 39-52.

    Blackwood KB. (2009, April). A data-driven approach to managing operational risk The RMA

    Journal, 91(7), 68-73.

    Hillson D. (2002). Using the risk breakdown structure (RBS) to understand risks. Proceedinsgs

    of the 33rdAnnual PMI Seminars and Symposium.

    Kim S, Bejaj D. (2000, January). Risk management in construction: An approach for

    contractors in South Korea. Cost Engineering,42(1), 38-44.

    Project Management Institute (2004). A Guide to the Project Management Body of

    Knowledge (PMBOK Guide). Third ed. Project Management Institute, Philadelphia.