A General Requirements:
A6
Installation of isolation valves serving mains or branch piping to fire
fighting equipment or any firewater system shall meet the requirements
of SAES-B-017.
SAES-S-040,
Para. 5.7.3
A5Each pressure control valve shall be provided with an upstream and
downstream manual isolation valves, designated "locked open".
SAES-B-017,
Para. 14.4.2
Isolation valves between the hydrant and fire water main, if provided,
shall be buried in accordance with SAES-S-040.
SAES-B-017,
Para. 7.2.2 g A2
A3Each utility line shall be provided with an isolation valve just upstream of
the specified hose connector at the termination.
SAES-L-310,
Para. 19.8
A4
Installation of Fire Water Isolation Valves SAIC-L-2056 25-May-05
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO INSPECTION CHECKLISSAIC NUMBER DATE APPROVED QR NUMBER
MECH-
PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER
MH's SP ENT TRAVEL TIMQUANTITY INSP.SCHEDULED INSPECTION DATE & TIME
PASS FAIL
CONTRACTOR INSPECTION LEVEL
WORK PERMIT REQUISAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO INSPECTION LEVEL
ITEM
No. ACCEPTANCE CRITERIA REFERENCE N/A RE-INSP DA
ACTUAL INSPECTION DATE & TIME
EC / PMCC / MCC NO.
PLANT NO.
A branch piping of a raw/firewater combined distribution system, serving
firewater systems of a building or a facility is connected upstream of the
isolation valve of the raw water supply piping.
SAES-S-040,
Para. 5.5.17
A7Isolation valves between the hydrant and fire water main, if provided,
shall be buried
SAES-B-017,
Para 7.2.2
A8Underground piping, valves, and fittings shall be externally protected
against corrosion per SAES-X-600.
SAES-B-017,
Para 7.3.4
A9
The spray system shall be considered to start at the inlet flange of the
isolation valve connecting to the distribution piping. The spray system
shall consist of an isolation valve, a strainer, actuation valve, and spray
system piping.
SAES-B-017,
Para 10.5.1
A10Isolation and actuation valves shall be accessible from grade and shall
otherwise meet the access requirements of SAES-B-054
SAES-B-017,
Para 10.5.2
A11 The entire spray system downstream of the isolation valve shall be
capable of being drained by low point drains
SAES-B-017,
Para 10.5.4
A12 The deluge system shall be considered to start at the inlet flange of the
isolation valve connecting to the distribution piping
SAES-B-017,
Para 11.6.1
A13 The system shall consist of an isolation valve, deluge valve, piping, and
deluge heads.
SAES-B-017,
Para 11.6.2
A14 Deluge valves may be manually operable except as specified in Section.SAES-B-017,
Para 11.7.1
A15
Sectionalizing valve handwheels shall be accessible from deck level and
located at a convenient operating height, hand wheels or other extension
shall not obstruct walk ways or equipment access ways.
SAES-B-009,
Para 4.8.6.7
Steel body valves shall be used for above ground firewater system block
valves to avoid failure due to fire, and AG to be equipped with position
indicator or showing full open and close positions.
SAES-L-008
Para 8.2 A1
Page 1 of 2
7/27/2019 SAIC-L-2056 Rev 0
http://slidepdf.com/reader/full/saic-l-2056-rev-0 2/2
*Person Responsible for Completion of Quality Work / Test Y =YES N =NO F =FA
Name, Organization,
Initials and Date:
T&I Witnessed QC Record Reviewed Work Verified
Name, Sign and Date:
Quality Record Approved:
QC Inspector PID Representative
Name, Initials and Date:
Performed Inspection Work / Rework May Proceed
Name, Initials and Date:
T&I Witnessed QC Record Reviewed Work Verified
T&I Witnessed QC Record Reviewed Work Verified
Proponent and Others
Name, Initials and Date:
Contractor / Third-Party Saudi AramcoConstruction Representative* PMT Representative
Work is Complete and Ready for Inspection:
Name, Initials and Date:
PASS FAIL N/A RE-INSP DAITEM
No. ACCEPTANCE CRITERIA REFERENCE
2. SAES-B-009, Fire Protection and Safety Requirements for Offshore Production Facilities, (30 J anuary, 2002)
PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR
0 0 25-May-05 MECH-
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO INSPECTION CHECKLISSAIC NUMBER DATE APPROVED QR NUMBER
QC Superviso r
4. SAES-S-040, Saudi Aramco Water Systems, 31 December 2003
A17Buried sectionalizing valves in FW system shall be provided with
indicator posts.
SAES-L-008
Para 7.7
SAES-B-017,
Para 9.2 A20
Block valves shall be provided in piping to isolate line failures for
repair,and assure flow of FW to all risk areas in case of failure in fire.
A19Gate valves are used above ground, they shall be installed so that the
stems are horizontal.
Flanged valves shall be provided at the ends of Fire Water loops tosectionalizing/Flushing upon completion of construction and at intervals.
A18Chain wheel operation shall not be installed on emergency isolation
valves.
SAES-B-009,
Para 4.8.6.2
A16
REMARKS:
REFERENCE DOCUMENTS:
SAES-B-017,
Para 12.4c
SAES-B-009,Para 4.8.6.8