saic-w-2006 rev 0

Upload: philipyap

Post on 02-Apr-2018

233 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 SAIC-W-2006 Rev 0

    1/4

    Weld joint identification markings conformed with the requirements of theapproved Weld J oint Identification System per SAIC-W-2008.

    (NOTE: Project QA/QC and PID may attach the weld numbering system

    as At tachment 1 to this checklist. )

    SAES-W-011,

    Para. 16.2

    A Join t preparation & c leanliness:

    A1

    Weld number and Welder symbol are marked adjacent to the weld joint.

    (NOTE: Markings shall be made with a suitable weather-proof marking

    material.)

    SAES-W-011,

    Para. 16.1

    A6Stainless steel and nonferrous material is cleaned with grinding wheels

    or stainless steel brushes, not previously used on other materials.

    SAES-W-011,

    Para. 11.4.3

    PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR

    In-Process Welding Inspection SAIC-W-2006 25-May-05 WELD-

    SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

    SAUDI ARAMCO INSPECTION CHECKLISSAIC NUMBER DATE APPROVED QR NUMBER

    EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID.

    LAYOUT DRAWING NUMBER

    PLANT NO.EQUIPMENT ID NUMBER(S)

    FAIL N/A RE-INSP DA

    MH's SP ENT TRAVEL TIMQUANTITY INSP.

    WORK PERMIT REQUI

    SCHEDULED INSPECTION DATE & TIME

    ITEM

    No.ACCEPTANCE CRITERIA REFERENCE PASS

    SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER

    CONTRACTOR INSPECTION LEVELSAUDI ARAMCO INSPECTION LEVEL

    ACTUAL INSPECTION DATE & TIME

    EC / PMCC / MCC NO.REV. NO. PURCHASE ORDER NUMBER

    SAUDI ARAMCO USE ONLY

    A2

    An approved Welding Procedure (WPS) is available at the weld

    site. (NOTE: Page A1 of the Welding Procedure Approval Request

    requires signature by the Saudi Aramco Inspection Agency. )

    SAES-W-011,

    Para. 7.1.8

    A2

    A4

    Oil, moisture, scale, rust, paint (except an approved weldable primer),

    metallic coatings (e.g. zinc) or other foreign matter, has been removed

    from the weld surface and at least 25mm of the adjacent base metal

    surface.

    SAES-W-011,

    Para. 11.3.1

    A3Welder(s) have been issued J ob Clearance Card, and that range of

    qualification shown matches the application of WPS being used.

    SAEP-324,

    Sec. 5

    B3Welding is not done during inclement weather e.g., wind blown sand,

    rain etc.

    SAES-W-011,

    Para. 11.2.2

    B Welding Envi ronment:

    B2The wind velocity in the weld area for GTAW, GMAW, or gas shielded

    FCAW shall not exceed 8 kph (2.2 m/s).

    SAES-W-011,

    Para. 11.2.1

    C1

    C Welding Consumables

    A5

    Coated and clad or overlaid surfaces are protected from the welding arc,

    associated weld spatter, and damage from ground clamps or other

    associated equipment.

    SAES-W-011,Para. 11.11

    B1Wind shields or tents are installed when the wind is strong enough to

    affect arc stability or shielding gas coverage.

    - - ,

    Para. 11.2.1 &

    B4For field welding, remote Current controls shall be used if the welding ismore than 30 m from the welding power source or when the welders are

    working in "remote" locations (e.g., on an elevated piperack).

    SAES-W-011,

    Para. 19.1

    Filler metal size, type and classification conform with the WPS.

    (NOTE: A change in filler metal or deposit chemistry from A-number 1

    (based on ASME SEC IX) to A-number 2 and vice-versa is not permitted

    without approval .)

    SAES-W-011,

    Para. 7.4.5

    B5

    Welding power supplies for use in welding where impact toughness test

    is required by the code or standard are verified to have been validated

    within 1 year in accordance with BS 7570.

    SAES-W-011,

    Para. 19.2

    Page 1 of 4

  • 7/27/2019 SAIC-W-2006 Rev 0

    2/4

    ITEM

    No.ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DA

    In-Process Welding Inspection SAIC-W-2006 25-May-05 WELD-

    PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR

    SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

    SAUDI ARAMCO INSPECTION CHECKLISSAIC NUMBER DATE APPROVED QR NUMBER

    E5

    Back purge for carbon and low alloy steel has reduced the oxygen level

    to below 1%.

    (NOTE: Verification is made by the use of oxygen analyzer. )

    SAES-W-011,

    Para. 11.14.4

    C2 Filler Metal and other weld consumables at weld site are maintained asper SAIC-W-2032.

    Project QualityPlan

    C3

    Welding consumables shall be of the same brand, type and maximum

    size as indicated on the WPS for the following welding processes:

    a. GMAW electrode to be used for procedures with impact

    toughness requirements

    b. SAW flux

    c. FCAW electrode

    d. WPS/PQR using any consumable with a "G" designation (ASME

    SEC IIC) per SAES-W-011, Para. 7.4.8.

    Inert gas is used for GTAW or GMAW root passes on single-sided

    groove welds, on ASME P-No. 5 materials and higher.

    SAES-W-011,

    Para. 11.14.1

    SAES-W-011,

    Para. 7.4.4

    SAES-W-011,

    Para. 12.1D2

    The actual preheat temperature was selected and used by the fabricatorthat is sufficient to prevent cracking and to achieve the required

    hardness,or, shall not be less than the greater of the following:

    a) 10C.

    b) The required or recommended preheat listed in ASME B31.3.

    c) Pre-heat temperatures from Std. Drg. W-AE-036451for all ASME

    P-No. 1 materials, including API grades up to and including X60.

    d) The preheat listed in Tables 3A and 3B for the SMAW process.

    e) Temperature determined by CSD for steels with specified

    minimum yield strengths above 60 ksi, (including API grades X65

    or greater) or for materials not listed as an ASME P-number.

    f) Temperaturee as specified in the approved welding procedure.

    D1Wet or damp weld joints are surface dried by heating to a distance of

    100mm from the toe, and are hand warm before welding.

    D5Temperature indicating crayons have not been used for any weld joint

    that is to be coated, or that will have a heat-shrink sleeve installed on it.

    SAES-W-011,

    Para. 12. 4

    SAES-W-011,

    Para. 12. 3

    Back Purging & Shielding Gas

    E1

    D6

    On wall thickness exceeding 25mm, preheat is done from the same side

    as the welding and heat source removed fro 1 minute prior to measuring

    the temperature.

    SAES-W-011,

    Para. 12. 6

    E2

    E

    For P-No. 5 materials and higher, back purging is maintained until at

    least 10mm of the weld deposit thickness is completed.

    SAES-W-011,

    Para. 11.14.2

    Preheat

    SAES-W-011,

    Para. 6.7

    D

    D4Temperature-indicating crayons, thermocouples, or contact pyrometers

    shall be used to measure preheat and interpass temperatures.

    SAES-W-011,

    Para. 12.4

    D3The preheat temperature shall be established over a minimum distance

    of 75 mm on each side of the weld.

    SAES-W-011,

    Para. 12.5

    E3 Nitrogen as a backing gas for austenitic stainless steel, is not used.SAES-W-011,

    Para. 11.14.3

    E4

    Shielding gases conformed to the following requirements:

    a. Carbon dioxide (CO2): Federal Specification BC-C-101, Type B

    or Compressed Gas Association CGA G-6.2, Type F.

    b. Argon (Ar): Compressed Gas Association CGA G-11.1,

    Grade A.

    c. Other gases and gas mixtures with approval from CSD.

    Page 2 of 4

  • 7/27/2019 SAIC-W-2006 Rev 0

    3/4

    ITEM

    No.ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DA

    In-Process Welding Inspection SAIC-W-2006 25-May-05 WELD-

    PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR

    SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

    SAUDI ARAMCO INSPECTION CHECKLISSAIC NUMBER DATE APPROVED QR NUMBER

    Hot Pass & Weld-Out

    F

    G

    G7Adjacent weld beads shall be staggered and not started from the same

    location.

    SAES-W-011,

    Para. 11.13

    SAES-W-011,

    Para. 7.4.10

    SAES-W-011,

    Para. 11.17

    Unless specified in the WPS, back welding is done using the same

    process, consumables and preheat as the fill passes.

    E6 Back purge for stainless steel and nickel alloys has reduced the oxygenlevel to below 0.05%. SAES-W-011,Para. 11.14.5

    G9

    Unless specified otherwise, the maximum interpass temperature are:

    a. 177C for P-No. 8 and P-No. 4x materials and

    b. 315C for P-1 steels.

    G10

    SAES-W-011,

    Para. 6.5.2

    Each weld pass is thoroughly cleaned and all slag or other foreign matter

    removed before the next pass is deposited. NOTE: See WPS remarks

    on cleaning method, e.g. mechanical brush.

    SAES-W-011,

    Para. 19.1

    The maximum allowable SMAW electrode sizes that can be used

    are given below.

    a) Low hydrogen electrodes - 5 mm for the 1G/1F position; 4 mmfor all other positions.

    b) Non-low hydrogen electrodes - 5 mm for all positions.

    The heat input (HI) ofeach production weld is calculated (using the

    formula below) if notch-toughness tests are specified, and then

    confirmed not to exceed the heat input limits listed in the WPS's.

    HI (kj/cm) =Voltage X Amperage X 60/Travel Speed (cm/min)

    SAES-W-011,

    Para. 19.4G6

    SAES-W-011,

    Para. 11.1

    G1

    The direction of welding conforms with the WPS.

    (NOTE: If the WPS is not qualified in the vertical position, then the

    direction of welding shall be vertical-up. )

    G5

    Remote Current controls are used if the welding is more than 30 m from

    the welding power source or when the welders are working in "remote"

    locations (e.g., on an elevated pipe rack).

    G8

    All full penetration joints requiring double sided welding shall be ground

    or gouged to sound metal and inspected by penetrant

    testing (PT) or magnetic particle testing (MT) prior to welding the reverseside, unless exempted by SAES-W-011, Para. 7.4.11as

    follows:

    a) For automatic or mechanized processes if additional PQR

    testing is conducted.

    b) For other special processes, approved by CSD, on butt joints

    where the production weld will be radiographed.

    SAES-W-011,

    Para. 11.3.4

    G3SAW Flux fused during welding shall not be reused (i.e., fluxes that use

    recrushed slag are not acceptable).

    F3Root pass is deposited without backing for WPS qualified for single-

    sided groove welds without backing.

    F4

    The GTAW process shall be used for the root pass of butt welds without

    backing in piping and nozzles of 50.8mm nominal diameter or less.

    (NOTE: Exempted are vent and drain piping open to theatmosphere or Category D piping. )

    G4

    SAES-W-011,

    Para. 12.7

    F2

    Each weld pass is thoroughly cleaned and all slag or other foreign matter

    removed before the next pass is deposited. NOTE: See WPS remarks

    for cleaning method, e.g. mechanical brush.

    SAES-W-011,

    Para. 7.4.7.1

    Root Pass

    F1

    The direction of welding conforms with the WPS.

    (NOTE: If the WPS is not qualified in the vertical position, then the

    direction of welding shall be vertical-up. )

    SAES-W-011,

    Para. 11.4.1

    SAES-W-011,

    Para. 11.4.1

    SAES-W-011,

    Para. 5.2.3

    SAES-W-011,

    Para. 7.4.7.1

    G2

    Page 3 of 4

  • 7/27/2019 SAIC-W-2006 Rev 0

    4/4

    ITEM

    No.ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DA

    In-Process Welding Inspection SAIC-W-2006 25-May-05 WELD-

    PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR

    SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

    SAUDI ARAMCO INSPECTION CHECKLISSAIC NUMBER DATE APPROVED QR NUMBER

    ATTACHMENTS:

    1. Attachment 1 - Weld J oint Identification/Markings (NOTE: This will be attached by the Project QA/QC & PID )

    QC Inspector PID Representative

    Work Verified

    Name, Initials and Date:

    Performed Inspection Work / Rework May Proceed

    Name, Initials and Date:

    Construction Representative*

    Name, Initials and Date:

    Work is Complete and Ready for Inspection:

    Name, Initials and Date:

    PMT RepresentativeT&I Witnessed QC Record Reviewed

    Work Verified

    REMARKS:

    REFERENCE DOCUMENTS:

    Contractor / Third-Party Saudi Aramco

    Work Verified

    1. SAES-W-011, Welding Requirements for On-Plot Piping, (30 October, 2002)

    2. SAEP-324, Certification Review and Registration of Project Welders and Brazers, (30 J une, 2003)

    3. Std. Dwg. W-AE-036451, Pre-Heat Levels for Welding Carbon Steel, Rev 2

    4. ASME B31.3, Process Piping, (2002)5. ASME SEC II Part C Specifications for Welding Rods, Electrodes, and Filler Metals, (1 July, 2001)

    6. ASME SEC IX - Qual. Standard for Welding and Brazing Procedures, Welders, Brazers, and Welding and Brazing Operators, (7/12001)

    QC Supervisor Proponent and Others

    *Person Responsible for Completion of Quality Work / Test Y =YES N =NO F =FA

    T&I Witnessed QC Record Reviewed

    Name, Sign and Date:

    Quality Record Approved:Name, Organization,

    Initials and Date:

    T&I Witnessed QC Record Reviewed

    G11 Forced or accelerated cooling of welds is prohibited without the specificapproval of CSD. SAES-W-011,Para. 11.18

    G12All slag, flux, weld spatters, and undercuts are removed from the

    completed weld and surrounding areas.

    SAES-W-011,

    Para. 11.4.2

    Page 4 of 4