strategic programmatic overview of the operating reactors ... · presentation 60 mins.* margaret...
TRANSCRIPT
)
Title:
Purpose:
Scheduled:
Duration:
Location:
SCHEDULING NOTE
STRATEGIC PROGRAMMATIC OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE (Public)
Provide the Commission with a discussion of strategic considerations associated with the Operating Reactors Business Line
September 27, 2018 10:00 am
Approximately 2 hours
Commissioners' Conference Room, 1st floor OWFN
Participants:
NRC Staff1
Presentation
60 mins.*
Margaret Doane, Executive Director for Operations
Ho Nieh, Director, Office of Nuclear Reactor Regulation (NRR) Topic:
• Key Focus Areas and Challenges • Implementing Organizational Vision - Integrating Risk Insights
Russell Felts, Deputy Director, Division of Risk Assessment, NRR Topic:
• Workload management o Increased Use of Integrated Teams o Risk-Informed Decision Making Training for Managers o Graded Approach to Reviews Using Risk Insights
Chris Miller, Director, Division of Inspection and Regional Support, NRR Topic:
• Potential Reactor Oversight Process Changes
Anton Vegel, Director, Division of Reactor Projects, Region IV Topic:
• Regional Key Focus Areas • Oversight Implementation Issues
1 Other business line partner office directors will be located in the well 1
)
Marissa Bailey, Director, Division of Security Operations, Office of Nuclear Security
and Incident Response Topic:
• Security Program Updates o Baseline Updates o Force on Force Exercise Plans
Robert Tregoning, Senior Level Advisor for Material Engineering Issues, Office of Nuclear Regulatory Research
Topic: • International Testing Capabilities
Commission Q & A
Discussion - Wrap-Up
50 mins.
5 mins.
*For presentation only and does not include time for Commission Q & A's
2
U.S.NRC United Stares Nuclear Regulatory Commission
Protecting People and the Environment
Strategic Programmatic Overview of the Operating Reactors Business
Line
Commission Meeting
September 27, 2018
Agenda
• ·Margaret Doane - Introductions
• Ho Nieh - Programmatic Overview
• Russell Felts - Workload Management
• Chris Miller - Potential Reactor Oversight Process Changes
• Anton Vegel - Regional Focus Areas and Oversight Implementation Issues
• Marissa Bailey - Security Program Updates
• Ro·bert Tregoning - International Testing Ca pa bi I ities
2 U.S.NRC United Stai u Nuclear Rcgul nory Commiuioo
Protecting hopk and the Environmmt
Continued Focus on Our Core Mission - Safety and Security
• Strategic Direction - Enhancing focus on issues of greatest safety
significance
- Expanding risk-informed decision making
• Programmatic Priorities - Digital Instrumentation and Control (Dl&C)
- Lead Test Assemblies (LTAs)/Accident Tolerant Fuel (ATF)
- NRR/NRO Merger
- Resource Planning
3 ,) U.S.NRC Prot«tint lnpl~ n11d IIN Environmnu
Advancing Risk-Informed Decision Making
• SECY-17-0112 enumerated challenges
• NRR RIDM Action Plan strategies
- Evaluate/Update guidance
- Develop graded licensing approach
- Enhance mandatory training
- Advance risk-informed initiatives
- Enhance communication
- -----·- -· . - . ·- - ------------- ----
Addressing RIDM Challenges through an Action Plan
• Comprehensive action plan with two phases
• Phase I is now complete with 19 recommendations
• Implementing Phase II with 13 action items - Use of Integrated Review Teams
- Sustainable guidance and expectations
- Communicating with external stakeholders
• Action Plan to be completed by December 30, 2018
• Working with ORBL offices and Regions on RIDM practices
5 / U.S.NRC
Improving Knowledge and Acceptance · of RIDM
• Extensive risk training courses have been available to all staff
• Piloted new RI DM training course for managers: - Provide perspectives on how risk and deterministic
information is used together to make regulatory decisions
- Review risk-informed licensing guidance and recent actions
- Illustrate risk management tools and practices at utilities
• Evaluating next steps
6 ,;U.S.NRC
------ - - -- -----·--
Optimizing Risk-Informed Licensing Review Efficiency
• Same staff performing like
(LAR) reviews
• Feedback loop on lessons
learned
• Discipline in RAls (draft SE with gaps, audits)
• Increased use of contractors to address riskinformed licensing surge
• Close _management oversight
• Risk-Informed Steering Committee (RISC)
7 ,; U.S.NRC
Sharing Lessons Learned to Improve . Efficiency
• Clarity and completeness of LAR submittals - key assumptions - sources of uncertainty - peer review facts & observations (F&O)
• Staff focus on F&Os that impact the particular application of the PRA
• NRC-accepted F&O closure process facilitates LAR streamlining
• Communicating via RISC, conferences, and other forums
• Preparing Regional staff for wider industry deployment of 50.69 and TSTF-505
8 ,) U.S.NRC
Ongoing Activities to Improve the ROP
• Enhancing the Replacement Reactor Program System (RRPS)
• Evaluating operating experience to improve inspections
• Enhancing engineering inspections
• Implementing Inspection Finding Resolution Management (IFRM)
9 U.S.NRC
Sources of Feedback for Improving the ROP
• NRC's transformation initiative suggestions • Nuclear Energy Institute (NEI) publ.ication
and follow-up letter • National Regional Utility Group (NRUG)
letter • Union of Concerned Scientists (UCS)
feedback
Protrcti11g Prop/, 1111d rl,r Em,iroumrnt
---- - - - - --
Suggestions Binned From Transformation Initiative
• Organization/staffing supporting inspections • Inspection report efficiencies • Numerous ROP program improvements • Recognition of Column 1 licensee
performance in several program areas
Prot«rint hop/, 1111d thr E11viro11mn1t
------- - --- -- --
Feedback From NEI, NRUG and UCS • Focus ROP on issues with higher risk
significance, reduce unnecessary regulatory burden, improve program efficiencies, and improve NRC and industry communications (NEI) .
• Use a more forward looking approach to oversight - i.e., consider licensee corrective actions (NRUG)
• Maintain regulatory independence in efforts to modify engineering inspections (UCS)
· Potential Changes
• Extend engineering inspection improvements to other areas
• Credit licensee self-assessments • Recognize sustained Col.umn 1 licensee
performance with reduced inspections • Enhance Pis and reduce inspection based on
performance
Prot«tillf Ptop/1,md ti~ E11viro11mntr
Potential Changes to the ROP (cont'd)
• Evaluate the treatment of White findings and White Pl's - numerous suggestions
• Assess numerous changes to SDP program and associated decision-making
• Improve assessment of Cross-Cutting Issues
14 ,)U.S.NRC Un11rd Sui<., N11elt'u kkguluory Comnnu,011
Proucting Ptoplt tt11d tht E11viro11mn11
Conducting Next Steps
• Establish working group • Communicate with stakeholders • Obtain Commission approval per Commission
direction • Address NRC resource challenges • Revise applicable ROP program documents
and conduct training, if required
Thorough and Independent Verification of Nuclear Plant Safety
• Continued effective
implementation of reactor
oversight inspections - Regional examples of
findings related to safe
operation
• Continued safety of plants that have announced premature closure
16 / U.S.NRC
Regional Key Focus Areas
• Improve coordination and consistency across the regions
• Support of ROP improvement initiatives
• People: Sustaining a strong cadre of talented and professional inspection staff
---- - - --- - ----- --- ----- - --·
Completing Assessment of Cyber Security Controls at Operating
Reactors
• Controls implemented in two phases • Full implementation inspections through 2020 • Results show licensees have adequately
implemented programs • Next steps
Protrcti11: Prop/, 1t11d ,J,, £ ,,virtmmrltl
------ - - --- ---- - ·--
Improving the Baseline Physical Security Inspection Program
• Identified efficiencies for baseline security inspections
• Aligned the baseline security SDP with the ROP
• Ensured significance of security findings are characterized appropriately
Protrctint Prop/, anti t/,r L,vironmmt
Continuously Improving the Force-onForce Inspection Program
• Fifth Force-on-Force (FOF) inspection cycle in progress
• Identified three options to further improve the FOF inspections (SECY-17-0100) l)Two NRC-conducted FOF exercises (status quo) 2)0ne NRC-conducted FOF exercise and one
defe_nse-in-depth exercise 3)0ne NRC-conducted FOF exercise and an
enhanced NRC inspection of a licensee-conducted annual FOF exercise
• Ensuring exercise scenarios are realistic
Protttti111 Prop/1,r11d th~ £11viromnrm
Assessing Long-Term Options for the Mock Adversary Force
• NEl-managed CAF used since 2004 • JCAF approved for 2018 and 2019
• Provided oversight of JCAF during selection, training an.d exercises
• Assessment of long-term options to the Commission in December 2018
Protrni111 hop/, nntl tlH' E11viro11mnt1
Enhancing Regulatory Decision Making
Th rough Research
• Core of research activities support licensing and oversight of nuclear power plants
• Recentsuccesses - Subsequent License Renewal guidance documents
- Boiling water reactor operating flexibility
• Current focus areas - Accident tolerant fuels
- Dl&C regulatory infrastructure
- Realism in risk assessment
- -- --- - - - ---------- --- - ------------
Relying on International Partnerships to Effectively Support the ORBL
• Cooperating through diverse strategies and extensive partnerships
• Leveraging operating experience, expertise, and facilities - Thermal-hydraulic, severe
accident, and radiological release codes
- Concrete aging
- Fire propagation Containment Construction for N EA Test Program
23 / U.S.NRC
Maintaining Critical Infrastructure & Capabilities
• Continued importance of large-scale, flexible facilities - Validate analytical codes - Address complex,
multidisciplinary issues
• Increased challenges - High operating and
maintenance costs - Aging facilities - Decreased demand
PAN DA Reactor Pressure Vessel
24 / U.S.NRC Prorrning Ptop/1 n11d thr Enviro11111r1t1
Addressing Infrastructure Challenges
• Identifying needs and preservation strategies • Mitigating impacts due to closure
of Halden reactor - Halden Reactor Project
developing path forward - NRC staff pursuing alternatives to
address gaps
Melt Coolability and Concrete Interaction Facility
25 / U.S.NRC Unuitd S,.-,~, Nudnt MA-g•lsiorv ..omm,uioa
Proru ri111 Pt-opt, 11.11d tlN E11viro11mntt
i - --- - - ·---- - - - ---------
I
Acronyms
• ATF - Accident Tolerant Fuel
• CAF - Composite Adversary Force
• Dl&C - Digital Instrumentation and Controls
• FOF - Force-On-Force
• F&O - Facts and Observations
• JCAF - Joint Composite Adversary Force
• LAR - Licensing Amendment Request
• LTA - Lead Test Assembly
Ptouf'fing Prop/, a11d 1/1t' E11vlro11mrm
Acronyms (continued)
• NEA- Nuclear Energy Agency
• NEI - Nuclear Energy Institute
• NRUG - National Regional Utility Group
• ORBL - Operating Reactors Business Line • Pl - Performance Indicator • PRA - Probabilistic Risk Assessment
• RAI - Request for Additional Information
27 ,) U.S.NRC U1111NI Suia Nuc:lnr MA-1•l,.1orr mm,uio•
Prot«tint Ptoplt nnd ,I~ Enviromttnlt
-1
Acronyms (continued)
• RIDM - Risk-Informed Decision Making
• RISC - Risk-Informed Steering Committee
• ROP - Reactor Oversight Process
• SDP - Significance Determination Process
• SE - Safety Evaluation
• TSTF - Technical Specifications Task Force
• UCS - Union of Concerned Scientists