Bidding Form T-15 Operation and Maintenance Information
The Bidder shall submit the following operation and maintenance information:
a. Spare Parts concept .
b. Recommendation on the organization on of O&M personnel including total staffing
by section
c. Training program for O&M personel
d. Information on Bidder's and sub-suppliers' maintenance services, technical support
and availability of spare parts
e. IO&M Manuals
Contents
a Spare Parts concept: .............................................................................................. 4
b Recommendation on the organization on of O&M personnel including total
staffing by section ................................................................................................. 5
c Training program for O&M personel: ................................................................... 6
d
-
7/26/2019 T15-Operation and Maintenance Info
2/14
BiddingformT13ElectricalInformation
Trang2/14
Information on bidders and sub-suppliers maintenance services, technical
support and availability of spare parts:................................................................. 7
e
-
7/26/2019 T15-Operation and Maintenance Info
3/14
BiddingformT13ElectricalInformation
Trang3/14
IO&M Manuals: ................................................................................................... 9
-
7/26/2019 T15-Operation and Maintenance Info
4/14
BiddingformT13ElectricalInformation
Trang4/14
a. Spare Parts concept:
N
o.
DESCRIPTIO
N
LifeyearRemark1
st
2n
d
3r
d
4t
h
5t
h
6t
h
7t
h
8t
h
9t
h
10
th
11
th
12
th
13
th
14
th
15
th
10
th
1 Air handling uint
Pre. Filter x xbag filter x x
Belt x x x x
Bearing x x x x
2 Chiller
Sensor x x x x
Transducer x x x x
Board x x x x x x x x
Fan motor x x x x x x x x
Compressor x x x x x x x x x x x x x x x x
Valve x x x x x x x xFuse x x x x x x x x
3 Air split unit package
Indoor Fan x x x x x x
Indoor Fanmotor
x x x x x x
Indoor Board x x x x x
Outdoor Fan x x x x x
Outdoor Fan
motorx x x x x
Accumolator x x x x x
Compressor x x x x x4 Chiller water pump
Bearing x x x
Oring x x x
Wear ring x x x
Shaft seal x x x
Impeller x x x x
Mech.seal x x x
5 Fan
Bearing x x x
Fan motor x x x x xBelt x x x x
Fan x x x x x x
-
7/26/2019 T15-Operation and Maintenance Info
5/14
BiddingformT13ElectricalInformation
Trang5/14
b. Recommendation on the organization on of O&M personnel including total staffing
by section
MANAGER
RECOMMENDATION ON THE ORGANIZATION ON OF O&M PERSONNEL
SUPERVISOR 1
ONE PERSON
ONE PERSON
SUPERVISOR 1
ONE PERSON
I&C TEAM
3 PERSON
I&C SYSTEM
HVAC TEAM
5 PERSON
HVAC SYSTEM
Note:
Reccommedation for key manager:
o HVAC Engineer.
o 5 year experience minimum
Reccommedation for Supervisor 1:
o Electric/Electronic Engineer.
o 4 year experience minimum
Reccommedation for Supervisor 2:
o HVAC Engineer.
o 3-4 year experience minimum
Reccommedation for I&C team:
o Skill worker.
o 3-4 year experience minimum
Reccommedation for HVAC team:
o Skill worker.
o 3-4 year experience minimum
-
7/26/2019 T15-Operation and Maintenance Info
6/14
BiddingformT13ElectricalInformation
Trang6/14
c. Training program for O&M personel:
No. DescriptionTimes
(hrs)
Theory
training
Field
trainingRemark
I Chiller system
1 Training for operation 2 X
2 Training for manternace 6 X X
3Training for
setup/monitoring4 X X
IIAir handling unit, air split
unit
1 Training for operation 1 X
2 Training for manternace 4 X X
3Training for
setup/monitoring2 X X
III I&C system
1 Training for operation 4 X
2 Training for manternace 4 X X
3
Training for
setup/monitoring of
parameter
4 X X
VI FAN & PUMP
1 Training for operation 2 X
2 Training for manternace 4 X X
V HVAC SYSTEM
1 Training for operation 3 X
2
Training for manternace
and funtion of equipment
on system
5 X X
-
7/26/2019 T15-Operation and Maintenance Info
7/14
BiddingformT13ElectricalInformation
Trang7/14
d. Information on bidders and sub-suppliers maintenance services, technical support
and availability of spare parts:
1. Information for Bidders and sub-suppliers
N
o
Descriptio
n
Company
nameCompany information
Maintenanc
e services
Technic
al
support
Remark
1HVAC
system
RoseInvestment
Corporation
- 9 Dinh Tien Hoang Street,
Dakao Ward, District 1, HoChi Minh City, Viet Nam.
- Tel: 84-8-3910 7993- Fax: 84-8-3910 7998
- Email: [email protected]
Y Y Bidder
2Chiler,AHU, Split
air unit
Daikin air
conditiong(Viet
Nam) joint
stockcompany
- Service center:- 100-102 Vu Tong Phan
Street, An Phu Ward,
District 2, Ho Chi MinhCity, Viet Nam.
- Tel: 84-8-628 11 248- Fax: 84-8-628 11 249
- Email:[email protected]
Y YSub-
supplier
3 Fan
Quoc Tien
ProductionTechnolog
y Co.,
LTD
- 167E Thich Quang Duc
Street, Ward 4, Phu NhuanDistrict, Ho Chi Minh City,
Viet Nam.
- Tel: 84-8-3995 1188
- Fax: 84-8-3995 1199
- Email: [email protected]
Y YSub-
supplier
4 Pump
Toan CauPumpsTrading
and
Engineerin
g Co.,LTD
368/24/28 Tan Son Nhi
Street, Tan Son Nhi WardTan Phu District. Ho ChiMinh City, Viet Nam
Tel: 84-08-3812 7327 -
3812 7329
Fax: 84-08-3812 7343Email:toancaupumps@vnn.
vn
Y YSub-
supplier
5I&Csystem
Niem TinCo., LTD
142 Doi Can, Ha Noi, Viet
NamTel: 84-04-722 29 39
Fax: 84-04- 722 29 40
Email: [email protected]
Y YSub-supplier
-
7/26/2019 T15-Operation and Maintenance Info
8/14
BiddingformT13ElectricalInformation
Trang8/14
2. spare parts list information
No.
Description
Available
in
stock
Delivery
time
RemarkWeek
1 Air handling uint
Pre. Filter X
bag filter XBelt X
Bearing X
2 Chiller
Sensor X
Transducer X
Board 6-8
Fan motor 4-6
Compressor 8-10
Valve X
Fuse X
3Air split unit
package
Indoor Fan 4-6
Indoor Fan motor 4-6
Indoor Board 4-6
Outdoor Fan 4-6
Outdoor Fan motor 4-6
Accumolator 4-6
Compressor 4-6
4 Chiller water pumpBearing X
Oring X
Wear ring X
Shaft seal X
Impeller X
Mech.seal X
5 Fan
Bearing X
Fan motor 6-8
Belt XFan 6-8
-
7/26/2019 T15-Operation and Maintenance Info
9/14
BiddingformT13ElectricalInformation
Trang9/14
e. IO&M Manuals:
HVAC Control system
I. OPERATION INSTRUCTION FOR THE HVAC CONTROL SYSTEM
1. Chiller system:
The Chiller system will be monitored and controlled by the HMI on the HVAC controlpanel.
There are 3 modes: Manual/Maintenance/Auto
1.1Manual mode :
In manual mode, at HMI the operators shall manually start or stop the chiller and the
corresponding equipments of selected chiller shall be run/stop automatically.
1.2Maintenance mode :
Operator can disable a chiller to maintenance purpose. The rest of chillers and
corresponding equipments shall be still in manual mode or auto mode for systemoperation.
1.3Auto mode :
1.3.1 Call chiller follow min working time
HCP call priority chiller has min working time
Chiller is trip, HCP will be called another chiller have min working time
to replace.
Chiller is trip after reset will go to standby
1.3.2 Chiller water pump running follow min working time
When CHWP is call, BMS will call CHWP1 or 2 or have min working
time to run.
CHWP is trip, BMS will be called another CHWP have min working time
to replace
CHWP is trip after reset will go to standby.
CHWP is control by 2 speed by operator.
The chilled water plant shall be automatically run/stop in schedule, the schedule can
be adjustable by operators.
The run chiller/pump shall be automatically scheduled to change over in order to
balance the totalized running time of each equipments is about the same.
When the BMS calls for the operation of 1 no. chiller in the auto mode, the
motorised valve at the chilled pipe of the chiller shall be sequenced open,1 No.
condenser chiller water pump shall be activated.
-
7/26/2019 T15-Operation and Maintenance Info
10/14
BiddingformT13ElectricalInformation
Trang10/14
All Chillers shall be started or stop in the auto mode as required to meet required by
operator.
The BMS shall provide auto changeover to the standby/other Chiller/ pump in the
event of failure of the running chiller/pump.
2. AHU system:
At the HMI in the HVAC control panel, the operator can monitor and control the AHU
system with properly functions.
HCP operate the AHU system with 2 mode: automation mode and Manual mode.
2.1Manual mode :
In manual mode, at HMI the operators shall manually start or stop the AHU and the
corresponding equipments of selected AHU shall be run/stop automatically.
2.2Automation mode :
HCP monitor the filter status, send alarm if the filter is dirty. So the maintenance man can
replace the new one for AHU.
The operator can set a setpoint for the return temperature and moisture. To adjust the
return temperature and moisture, the PXC will control the modulating valve 0 to 100%
and control the heater 0 -100%.
And PXC will change the speed of fan to maintain the pressure in duct as required by
operator.
The damper of the return duct will be controlled ON/OFF when AHU is run or off mode.
In the case of fire alarm, BMS Apogee InsightTM system, PXC will stop the AHU to
minimize the air volume through the room, minimize the factor occur fire.
On the HMI graphic, the operator can command the AHU and monitor the sensors:
temperature, moisture, status of the fan and alarm from the fire system.
II. INSTRUCTION FOR TROUBLE AND MAINTENANCE THE EQUIPMENTS
1. Instruction for troubles
Power failure trouble
o The fail power will take the controller and the device will stop working completely .
o Overcome
Step1: Check the power supply to DDC panels
If there is no power then check and turn on the power, if not skip to
step 2
Step 2: Check the trasformers in the DDC panels.
If the device is damaged the replace the new one, if not skip to step 3
-
7/26/2019 T15-Operation and Maintenance Info
11/14
BiddingformT13ElectricalInformation
Trang11/14
Step 3: Check the power cable
Change the new cable if it is damaged
o After overcoming the system will automatically recognize the device
o The power failure will lead to alert, to restore the operating procedures by pressing the
Reset icon to start the recovery process
*** When troubles occur, if the operator can not overcome, then transferred to the
manual operation mode and contact the administrator to resolve the problem .
2.
Maintenance the HVAC control system
o Should every day check the environmental conditions (temperature and humidity) where
the installation of the sensors, the control unit of the HVAC control panel system,
ensure the device operates in allowed value (temperature 0500C, huminity
-
7/26/2019 T15-Operation and Maintenance Info
12/14
BiddingformT13ElectricalInformation
Trang12/14
-
7/26/2019 T15-Operation and Maintenance Info
13/14
BiddingformT13ElectricalInformation
Trang13/14
-
7/26/2019 T15-Operation and Maintenance Info
14/14
BiddingformT13ElectricalInformation
Trang14/14
CHILLER Equipment : view the catalog accompanying the machine
Low operating cost and extended operating lifeThis chiller range is the result of careful
design, aimed to optimize the energy efficiency of the chillers, with the objective of bringing
down operating costs and improving installation profitability, effectiveness and economical
management.
The chillers feature a high efficiency single screw Inverter driven compressor design, large
condenser coil surface area for maximum heat transfer and low discharge pressure, advanced
technology condenser fans and a shell&tube evaporator with low refrigerant pressure drops.
Outstanding reliabilityThe chillers have two or three truly independent refrigerant circuits,
in order to assure maximum safety for any maintenance, whether lanned or not. They are
equipped with a rugged compressor design with advanced composite compressor gaterotors
material, a proactive control logic and are full factory-run-tested to optimized trouble-free
operation.
Infinite capacity controlCooling capacity control is infinitely variable by means of a
Inverter driven screw compressor controlled by microprocessor system. Each unit has
infinitely variable capacity control from 100% down to 13,5%. This modulation allows the
compressor capacity to exactly match the building cooling load without any leaving
evaporator water temperature fluctuation. This chilled water temperature fluctuation is
avoided only with a stepless control.
Note:
For other euipment IO&M wille be supplied follow to equipment in installation process
and training at site.