Traditional Grid Traditional Ceiling Panels Traditional Utilities Traditional Grid Logix Ceiling Panel Logix Utility Channels Created with UMB Accessory USG is offering a new accessory option making it easy to create stylish and organized utility channels using standard grid. The USG Brand Utility Module Bracket (UMB) enables a versatile and economic approach to integrated ceiling design. The USG Utility Module Bracket can be used to create a dramatic suspended ceiling design statement with standard suspension system grid components. This innovative grid accessory gives everyone from the architect and designer to the contractor and the installation crew the freedom and flexibility to transform traditional acoustical ceiling grid into a tailored design that integrates overhead functions, systems, and components. Now, even small spaces can be easily transformed into exciting, inspirational environments using standard suspension system grid. The UMB can be used to create 4 in., 6 in., 100 mm, and 150 mm utility channels and is compatible with three USG standard grid types. More details and step-by-step instructions for installing the UMB are included in this guide. LOGIX INTEGRATED CEILING SYSTEMS USG UTILITY MODULE BRACKET INSTALLATION GUIDE USG Ceiling Solutions LOGIX Integrated Ceiling Systems

Upload: others

Post on 26-Oct-2021

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: USG Logix™ Brand Integrated Ceiling Systems USG Uility

• Traditional Grid

• Traditional Ceiling Panels

• Traditional Utilities

• Traditional Grid

• Logix Ceiling Panel

• Logix Utility Channels Created with UMB Accessory

USG is offering a new accessory option making it easy to create stylish and organized utility channels using standard grid. The USG Brand Utility Module Bracket (UMB) enables a versatile and economic approach to integrated ceiling design. The USG Utility Module Bracket can be used to create a dramatic suspended ceiling design statement with standard suspension system grid components.

This innovative grid accessory gives everyone from the architect and designer to the contractor and the installation crew the freedom and flexibility to transform traditional acoustical ceiling grid into a tailored design that integrates overhead functions, systems, and components. Now, even small spaces can be easily transformed into exciting, inspirational environments using standard suspension system grid. The UMB can be used to create 4 in., 6 in., 100 mm, and 150 mm utility channels and is compatible with three USG standard grid types. More details and step-by-step instructions for installing the UMB are included in this guide.

LOGIX™ INTEGRATED CEILING SYSTEMSUSG UTILITY MODULE BRACKETINSTALLATION GUIDE

USG Ceiling Solutions

LOGIX™

Integrated Ceiling Systems

Page 2: USG Logix™ Brand Integrated Ceiling Systems USG Uility

2 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

The USG Utility Module Bracket (UMB) is a convenient and versatile suspension system accessory designed to easily create 4 in., 6 in., 100 mm, and 150 mm utility channels with standard USG ceiling grid. The USG Utility Module Bracket is designed to work with USG Centricitee™ DXT™/DXLT™, DX®/DXL™, and Identitee® DXI™ ceiling grid.

GRID PROFILES USG Centricitee DXT™/DXLT™ DX®/DXL™ Identitee® DXI™

9/16" 15/16"3/16"

9/16"

IMPERIAL 4-6 Utility Module Bracket (Imperial)

5/32"

11/2" nom.

81/4" nom.

6" channel tabs

4" channel tabs

center indexing tab

METRIC 100-150 Utility Module Bracket (Metric)

4 mm

36 mm

206 mm

150 mm channel tabs

100 mm channel tabs

center indexing tab

UTILITY CHANNELOPTIONS

4 in. or 100 mm Utility Channel 6 in. or 150 mm Utility Channel

Overview

USG UTILITY MODULE BRACKET

Page 3: USG Logix™ Brand Integrated Ceiling Systems USG Uility

3 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

Overview

GENERAL CONSIDERATIONS

Indexing Tab In-Line with Keyhole Indexing Tab Off-Line with Keyhole

Ashlar DH3 Seismic Application

screw attached in top or side holes

DH3 connector

cross tee

main tee

Utility Module Bracket

6" channel tabs

4" channel tabs

center indexingtab

DXT and DXI Web Tabs

With some products, there will be interference between the UMB and the panel centering tabs along the grid body. In order to install the UMB properly, these tabs need to be compressed with a channel lock or large pliers.

USG UTILITY MODULE BRACKET USG UTILITY MODULE BRACKET

Page 4: USG Logix™ Brand Integrated Ceiling Systems USG Uility

4 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

Main Tee

Cross Tee

TYPES OF CONDITIONS Before installing the UMBs, review the placement of the utility channels relative to the main tees and cross tees in the Logix installation to determine the place-ment and number of UMB brackets required at each junction. There are three types of conditions.

ASHLAR CONDITION

• Utility channel is non-

continuous, positioned

independently between

two main tees.

• One UMB required on

each end.

• DH3 for seismic applications.

See page 11.

CONTINUOUS CONDITION

• Utility channels continue

across main tees creating

linear, uninterrupted

appearance.

• Two UMBs required at each

main tee.

See page 6.

ASHLAR CONDITION, ALTERNATE

• Utility channel is non-

continuous, positioned

independently between

two main tees and placed

opposite a single cross tee.

• One UMB required on

each end.

See page 15.

Overview

USG UTILITY MODULE BRACKET

Page 5: USG Logix™ Brand Integrated Ceiling Systems USG Uility

5 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

UTILITY MODULE • Eight brackets

BRACKET PACKAGING • 250 pop rivets

• convenient pail

TOOLS FOR INSTALLATION

Hole Punch Rivet Gun

Aviation Snips Channel Locks

Overview

USG UTILITY MODULE BRACKET USG UTILITY MODULE BRACKET

Page 6: USG Logix™ Brand Integrated Ceiling Systems USG Uility

6 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

Continuous Condition View from Above

cross tee

main tee

Utility Module Brackets

cross tee

6" channel tabs

4" channel tabs

attach tabs with pop rivets

UMB with Folded Tabs Completed Assembly

cross tee

cross tee

main tee

Utility Module Brackets

6" channel tabs

6" channel tabs

4" channel tabs

attach tabs with pop rivets

GENERAL CONSIDERATIONS

• Utility channels continue across main tees creating linear, uninterrupted appearance.

• Two UMBs are required.

• Install all the necessary UMBs prior to securing the cross tees.

• For DXT and DXI, compress the web tabs with large pliers or channel locks prior to installing the UMB.

• Where the centerline of the utility channel does not align with a cross tee hole in the main tee, the UMB may be secured to the main tee without inserting the center indexing tab through the tee.

Main Tee

Cross tee

INSTALLATION

CONTINUOUS CONDITION

Page 7: USG Logix™ Brand Integrated Ceiling Systems USG Uility

7 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

Continuous Condition View from Above

cross tee

main tee

Utility Module Brackets

cross tee

6" channel tabs

4" channel tabs

attach tabs with pop rivets

STEP 1 Determine the centerline of the utility opening.

`

.

STEP 2 Fold out the center indexing tab on the first UMB 90° and insert it through the cross tee hole on the main tee. Then, bend it back 90°.

STEP 3 Using the UMB as a template, punch attachment holes through the main tee.

INSTALLATION

CONTINUOUS CONDITION CONTINUOUS CONDITION

Page 8: USG Logix™ Brand Integrated Ceiling Systems USG Uility

8 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

STEP 6 Fold out the attachment tabs per the utility channel opening on both UMBs.

4 in. or 100 mm utility channels Fold inner tabs.

6 in. or 150 mm utility channels Fold outer tabs.

4 in. or 100 mm Utility Channel

6 in. or 150 mm Utility Channel

STEP 4 Repeat Step 2 on the opposing side of the main tee.

STEP 5 Secure both UMBs to the main tee by inserting pop rivets through the pilot holes created in Step 3.

INSTALLATION

CONTINUOUS CONDITION

Page 9: USG Logix™ Brand Integrated Ceiling Systems USG Uility

9 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

STEP 7 Using snips, cut off the cross tee clips through the center of the hourglass shape.

cut line

STEP 8 Place the tee aligning the hole against the out-folded tabs (four tabs total)

STEP 9 With the tee held tight against the outside of the UMB tab, secure the tee with the two pop rivets provided (four tabs total).

INSTALLATION

CONTINUOUS CONDITION CONTINUOUS CONDITION

Page 10: USG Logix™ Brand Integrated Ceiling Systems USG Uility

10 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

FINISHED ASSEMBLY

INSTALLATION

CONTINUOUS CONDITION

Page 11: USG Logix™ Brand Integrated Ceiling Systems USG Uility

11 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

UMB with Folded Tabs Completed Assembly

cross tee

center indexingtab

main tee

Utility Module Bracket

6" channel tabs

4" channel tabs

Ashlar Condition View from Above

cross tee

main tee

Utility Module Bracket

cross tee

6" channel tabs

4" channel tabs

attach tabs with pop rivets

GENERAL

CONSIDERATIONS

• Utility channel is non-continuous, positioned independently between two main tees.

• One UMB is required.

• Install all the necessary UMBs prior to securing the cross tees.

• For DXT and DXI, compress the web tabs with large pliers or channel locks prior to installing the UMB.

• Where the centerline of the utility channel does not align with a cross tee hole in the main tee, the UMB may be secured to the main tee without inserting the center indexing tab through the tee.

Main Tee

Cross tee

INSTALLATION

CONTINUOUS CONDITION ASHLAR CONDITION

Page 12: USG Logix™ Brand Integrated Ceiling Systems USG Uility

12 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

STEP 1 Determine the centerline of utility opening.

STEP 2 Fold out the center indexing tab on the UMB 90° and insert it through the cross tee hole on the main tee. Then, bend it back 90°.

STEP 3 Using the UMB as a template, punch attachment holes through the main tee.

INSTALLATION

ASHLAR CONDITION

Page 13: USG Logix™ Brand Integrated Ceiling Systems USG Uility

13 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

STEP 6 Using snips, cut off the cross tee clips through the center of the hourglass shape.

cut line

STEP 4 Secure the UMB to the main tee by inserting pop rivets through the pilot holes from Step 3.

STEP 5 Fold out the attachment tabs per the utility channel opening.

4 in. or 100 mm utility channels Fold inner tabs.

6 in. or 150 mm utility channels Fold outer tabs.

4 in. or 100 mm Utility Channel

6 in. or 150 mm Utility Channel

INSTALLATION

ASHLAR CONDITIONASHLAR CONDITION

Page 14: USG Logix™ Brand Integrated Ceiling Systems USG Uility

14 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

STEP 7 Place the tee aligning the hole against the out-folded tabs.

STEP 8 With the tee held tight against the outside of the UMB tab, secure the tee with the two pop rivets provided.

FINISHED ASSEMBLY

INSTALLATION

ASHLAR CONDITION

Page 15: USG Logix™ Brand Integrated Ceiling Systems USG Uility

15 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

Ashlar Condition, Alternate View from Above

cross tee

main tee

Utility Module Bracket

cross tee

cross tee

6" channel tabs

4" channel tabs

attach tabs with pop rivets

attach tabs with pop rivets

center indexing tab

UMB with Folded Tabs Completed Assembly

attach tabs with pop rivets

cross tee

center indexingtab

main tee

Utility Module Bracket

cross tee

6" channel tabs

4" channel tabs

GENERAL

CONSIDERATIONS

• Utility channel is non-continuous, positioned independently between two main tees and placed opposite a single cross tee.

• One UMB is required.

• Install all the necessary UMBs prior to securing the cross tees.

• For DXT and DXI, compress the web tabs with large pliers or channel locks prior to installing the UMB.

• Where the centerline of the utility channel does not align with a cross tee hole in the main tee, the UMB may be secured to the main tee without inserting the center indexing tab through the tee.

Main Tee

Cross tee

INSTALLATION

ASHLAR CONDITION ASHLAR CONDITION, ALTERNATE

Page 16: USG Logix™ Brand Integrated Ceiling Systems USG Uility

16 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

STEP 1 Determine the centerline of the utility opening.

STEP 2 Fold out the center indexing tab on the UMB 90° and insert it through the cross tee hole on the main tee.

STEP 3 Using the UMB as a template, punch attachment holes through the main tee.

INSTALLATION

ASHLAR CONDITION, ALTERNATE

Page 17: USG Logix™ Brand Integrated Ceiling Systems USG Uility

17 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

STEP 6 Using snips, cut off the cross tee clips through the center of the hourglass shape.

cut line

STEP 4 Secure the UMB to the main tee by inserting pop rivets through the pilot holes from Step 3.

STEP 5 Fold out the attachment tabs per the utility channel opening.

4 in. or 100 mm utility channels Fold inner tabs

6 in. or 150 mm utility channels Fold outer tabs

4 in. or 100 mm Utility Channel

6 in. or 150 mm Utility Channel

INSTALLATION

ASHLAR CONDITION, ALTERNATEASHLAR CONDITION, ALTERNATE

Page 18: USG Logix™ Brand Integrated Ceiling Systems USG Uility

18 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

STEP 7 Place the tee aligning the hole against the out-folded tabs.

STEP 8 With the tee held tight against the outside of the UMB tab, secure the tee with the two pop rivets provided.

STEP 9 Insert the remaining opposing tee into the keyhole as normal, aligning the hole against the out-folded center indexing tab.

INSTALLATION

ASHLAR CONDITION, ALTERNATE

Page 19: USG Logix™ Brand Integrated Ceiling Systems USG Uility

19 INSTALLATION GUIDE Logix Integrated Ceiling Systems Utility Module Bracket

STEP 10 With the tee held tight against the center index tab of the UMB, secure the tee with the two pop rivets provided.

FINISHED ASSEMBLY

INSTALLATION

ASHLAR CONDITION, ALTERNATEASHLAR CONDITION, ALTERNATE

Page 20: USG Logix™ Brand Integrated Ceiling Systems USG Uility

AC3307/rev. 4-14 © 2014, USG Corporation or its affiliates. All rights reserved.The trademarks CENTRICITEE, DONN, DX, DXI, DXL, DXLT, DXT, IDENTITEE, LOGIX, USG, IT’S YOUR WORLD BUILD IT, the USG logo and related marks are trademarks of USG Interiors, LLC or a related company.

Manufactured byUSG Interiors, Inc.550 West Adams StreetChicago, IL 60661

PRODUCT INFORMATIONSee usg.com for the most up-to-date product information.

INSTALLATIONMust be installed in compliance with ASTM C636, ASTM E580, CISCA and standard industry practices, within all applicable code requirements. Alternative assemblies and installation methods may be utilized when approved by the Authority Having Jurisdic-tion. USG recommends checking with the Authority Having Jurisdiction prior to designing and installing a suspended ceiling system.

CODE COMPLIANCECODE COMPLIANCEThe information presented is correct to the best of our knowledge at the date of issuance. Because codes continue to evolve, check with a local official prior to designing and installing a ceiling system. Other restric-tions and exemptions may apply. This is only intended as a quick installation reference.

ICC EVALUATION SERVICE, INC., REPORT COMPLIANCESuspension systems manufactured by USG Interiors, Inc., have been reviewed and are approved by listing in ICC-ES Evaluation Report 1222. Evaluation Reports are subject to reexamination, revision and possible cancel-lation. Please refer to usgdesignstudio.com or usg.com for current reports.

L.A. RESEARCH REPORT COMPLIANCEDONN brand suspension systems manufactured by USG Interiors, Inc., have been reviewed and are ap-proved by listing in the following L.A. Research Report number: 25764.

NOTICEWe shall not be liable for incidental and consequential damages, directly or indirectly sustained, nor for any loss caused by application of these goods not in ac-cordance with current printed instructions or for other than the intended use. Our liability is expressly limited to replacement of defective goods. Any claim shall be deemed waived unless made in writing to us within thirty (30) days from date it was or reasonably should have been discovered. SAFETY FIRST! Follow good safety/industrial hygiene practices during installation. Wear appropriate personal protective equipment. Read MSDS and literature before specifica-tion and installation.

WEBSITESusg.comcgcinc.comusgdesignstudio.comcgcdesignstudio.com

TECHNICAL SERVICE800 USG.4YOU 800 874.4968

CUSTOMER SERVICEUSG 800 950.3839CGC 800 387.2690