©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special SO Meeting February 20, 2004

Upload: anabel-wilkins

Post on 21-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 1

OASIS Phase IIApproaching the Problem

General Discussion on Strategy and PhilosophyAndy Rodriquez - PJM

Presented to the NERC OC Special SO MeetingFebruary 20, 2004

Page 2: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 2

How did we get here?

• OASIS 1A• Fax Tagging• E-Mail Tagging• Electronic Tagging• XML Electronic Tagging

• OASIS Phase II/Electronic Scheduling ANOPR

Page 3: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 3

Core Objectives

• Customer-driven Development• Incremental Value• Cost Effective• Market Design Neutral• Encourage “seamless” boundaries whenever possible• Leverage Existing Tools…

without being bound by those tools

Page 4: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 4

How do we start?

• Begin with the ESC Use Cases• Evaluate and Define OASIS functionality• Identify Modular Components• Determine Architecture• Develop Approach

Page 5: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 5

Architecture

• This should NOT necessarily be a discussion on technical issues

• Focus should be on deployment strategy that meets core objectives

• Identify modular groups where appropriate

Page 6: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 6

Approach

• Should focus on incremental deliverables to provide ongoing value

• Staged approached to functionality will allow amortized cost burden to companies

• Can also be utilized to address regional diversity– If upgrades can be done on an incremental basis, we can

work to ensure backward compatibility where possible

Page 7: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 7

Ongoing Efforts

• IDC – Next Generation– No dependence on tags

• CIM Market Extensions– Coordination between RTOs

• PJM/MISO Congestion Management– Quantifying internal dispatch

• Information Technology Council– Facilitated Checkouts, Other Initiatives

Page 8: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 8

Collaboration

• Should encourage participation to meet openness goals and ensure coordinated attack – minimal duplication of effort– NAESB Groups

• Seams Collaborative• Information Technology Subcommittee

– NERC Community• Interchange Subcommittee• Transaction Information Systems Working Group• Operations Reliability Subcommittee• Interchange Distribution Calculator Working Group• DEWG?• What about the Registry?????

– ISO/RTO Council• Information Technology Council

Page 9: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 9

What is OASIS (my thoughts)?

• A market-oriented solution that optimizes the market interchange scheduling function– This would be developed by NAESB

• A reliability-oriented solution that meets the needs of the functional model with regard to operational interchange scheduling– This would be developed by NERC

• A set of interfaces to allow for market activity within a ISO/RTO/TP– This would be developed by the ISO/RTO/TP, but would align

with the NAESB functions• A “market/reliability interface” between the two, called the

Interchange Authority, that would tie markets and reliability together– This would jointly be developed by NERC, NAESB, and the IRC

Page 10: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

Proposed Vision

MarketScheduling

Node

MarketScheduling

Node

MarketScheduling

Node

TP A (Legacy TP) RTO B RTO C

OASIS 1ANODE(TSP)

E-TagApproval

Market System

Energy, TX, AS(TSP)

LMPCongestion

Management

TLRInterface

NERC ReliefAnalyzer

InterchangeAuthority

GPE PSE LSE

Legacy Bridge

Bilateral Marketw/PTP Service

Energy, TX, AS(TSP)

LLR

OperationsScheduling

Node

OperationsScheduling

Node

OperationsScheduling

Node

CA A RTO B RTO C

OASIS P2Connector

OASIS P2Connector

OASIS P2Connector

OASIS P2Connector

NERC

NAESB

RTO/FERC

BA RA TO RA TO BA RA TO

Page 11: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 11

Suggested Process Steps

Time (not sequential) Deliverable(s)

5 months Vision and Scope

5 months Use Cases

6 months Functional Requirements

4 months Structure Design Document

3 months Implementation Plan

8 months Stage 1 S&CPs, BPs

11 months

Implement Stage 1

Legacy Bridge for OASIS Phase 1

Legacy Bridge for E-Tag (including Tag Authority to IA)

Strategic Split of IDC (Impact Calculator and TLR Process)

Page 12: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 12

Suggested Process Steps

Time (not sequential) Deliverable(s)

8 months Stage 2 S&CPs, BPs

14 months

Implement Stage 2

Enhanced OASIS Functions (OP2)

Operations Scheduling Tools (to support FM)

Enhanced IA to Ops Sched Interface

Enhanced Legacy Bridge (v2)

IDC Next Generation

12 months Stage 3 S&CPs, BPs

17 months

Implement Stage 3

Market Scheduling

Enhanced Market to IA Interface(v2)

Page 13: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 13

Suggested Schedule

ID Task Name Duration Start Finish

1 Vision and Scope 5 mons Wed 2/18/04 Tue 7/6/04

2 Use Cases 5 mons Wed 6/9/04 Tue 10/26/04

3 Functional Requirements 6 mons Wed 9/29/04 Tue 3/15/05

4 Structure Design Document 4 mons Wed 1/19/05 Tue 5/10/05

5 Implementation Plan 3 mons Wed 4/13/05 Tue 7/5/05

6 Write Stage 1 S&CPs, BPs 8 mons Wed 3/16/05 Tue 10/25/05

7 Implement Stage 1 283 days Wed 8/31/05 Sun 10/1/06

8 Design 3 mons Wed 8/31/05 Tue 11/22/05

9 Develop 6 mons Wed 10/26/05 Tue 4/11/06

10 Test 2 mons Mon 8/7/06 Sun 10/1/06

11 Write Stage 2 S&CPs, BPs 8 mons Wed 11/23/05 Tue 7/4/06

12 Implement Stage 2 364 days Wed 5/10/06 Mon 10/1/07

13 Design 4 mons Wed 5/10/06 Tue 8/29/06

14 Develop 8 mons Wed 8/2/06 Tue 3/13/07

15 Test 2 mons Tue 8/7/07 Mon 10/1/07

16 Write Stage 3 S&CPs, BPs 12 mons Wed 8/30/06 Tue 7/31/07

17 Implement Stage 3 366 days Wed 5/9/07 Wed 10/1/08

18 Design 4 mons Wed 5/9/07 Tue 8/28/07

19 Develop 9 mons Wed 8/1/07 Tue 4/8/08

20 Test 4 mons Thu 6/12/08 Wed 10/1/08

Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 12004 2005 2006 2007 2008 2009

Note: Schedule Must Not Implement During Summer or Winter peaks

Page 14: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 14

Key Components

• Develop appropriate representation across the industry• Establish “governance” issues

– Identify leadership

– Determine other key liaisons and roles

– Set up meeting schedules

– Agree to vision and scope

– Establish milestones and deliverables

Page 15: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

NAESB OASIS II Development Overview

Information Technology

Subcommittee

Electronic Scheduling

Subcommittee

OASIS II Structural

Design Task Force

OASIS II Scoping Task

Force

ESC Deliverables

Vision and Scope

Structural Design

Document

Use CaseDocument

Functional Requirements

S&CP Documents

Business Practices

Implementation Plan

Joint OASIS II IMPLEMENTATION TASK

FORCE

(Temporary merger of OP2 SDTF and OP2 STF)

FERC Filed Documents

Collaborative Internal Documents

Business Practices Task Force

S&CP Task Force

Transition after

JOP2ITF Disbanded

Transition after

JOP2ITF Disbanded

Page 16: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 16

Vision and Scope

NERCIS

NERCORS

NAESBESS STF

Visionand

Scope

IRC,Customers,

Others

Functional Model Vision – “Downstream of the IA”

Next Generation IDC Vision RTO Internal Systems

(Current and Future), General Guidance

Customer-driven focus – “Upstream of the IA”

Overall long-term vision – where do we

want to be?

NERCRCWG

Next Generation IDC Vision

Page 17: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 17

Use Case Document

UseCase

Document

NERCTISWG

NERCIDCWG

Functional Model Component – “Operational Scheduling”

Next Generation IDC Functions

NAESBESS JOP2ITF

NAESBESS STF

NAESBITC SDTF

Business Analysis, Facilitation, Customer Focus

Detailed walkthrough of functionality, business logic

IRC,Customers,

Others

RTO Internal Systems (Current and Future), General Guidance

Page 18: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 18

Functional Requirements

FunctionalRequirements

NAESBESS JOP2ITF

NAESBESS STF

NAESBITC SDTF

IRC,Others

RTO internal Systems (Current and Future)

Beyond Use Cases – “blueprints” for S&CP

Includes System Requirements

Documentation and Technical Guidance

Page 19: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 19

Structure Design Document

StructureDesign

IRC,Customers,

Others

NAESBESS JOP2ITF

NAESBESS STF

NAESBITC SDTF

How do we want to organize the functional

pieces?

Business Analysis, Facilitation, Customer Focus

Logical Guidance, Priorities

Page 20: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 20

Implementation Plan

ImplementationPlan

NERCIS

NERCORS

IRC,Customers,

Others

NAESBESS JOP2ITF

NAESBESS STF

NAESBITC SDTF

How do we roll everything out?

How do we coordinate with the Functional Model Implementation?

How do we coordinate with the Next Generation IDC? How can we bring in

new and existing systems?

Facilitation and Technical Guidance

Page 21: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 21

S&CP

S&CP

NERCTISWG

NERCIDCWG

IRC ITC

NAESBITC

How do you build it?

How do we coordinate with the Functional Model Implementation?

How do we coordinate with the Next Generation IDC?

How can we integrate new and existing systems?

Facilitation and Technical Guidance

EPRI CME

What parts of the CIM can we leverage?

Vendors

What technologies can we leverage?

NERCDEWG?

Page 22: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 22

Business Practices

BusinessPractices

NERCIS

NERCORS

IRC,Customers,

Others

NAESBESS

How do you operate it?

What criteria does NERC have we need to coordinate with?

What BP Standards can we agree to?

Facilitation and Technical Guidance

IRC Seams,NAESB Seams

Can BP Standards fix some seams?

Page 23: ©2004 PJM 1 OASIS Phase II Approaching the Problem General Discussion on Strategy and Philosophy Andy Rodriquez - PJM Presented to the NERC OC Special

©2004 PJM 23

Questions?