Bethel Park High SchoolBethel Park, PA
Weekly Progress SlideshowApril 13, 2012
Crushing Continues
Retention Tank
Retention Tank
Demolition of Building 2
Continue to break up and sort demolition debris.
Smoke stack ready for removal.
Stormwater piping delivered.
Scheduled Work for Next Few Weeks:
• Complete demolition of Building 2• Complete backfill of retention tank• Continuation of punch list activity.• Begin site fencing at rear of building.• Drop stack• Continue masonry crushing for
underlayment.• Removal of construction trailers.