Cost Benefit Analysis and Value for Money 17 June 2014

Upload: indonesia-infrastructure-initiative

Post on 20-May-2015

319 views

Category:

Business


1 download

TRANSCRIPT

Page 1: Cba makassar port (english)

Cost Benefit Analysis and Value for Money

17 June 2014

Page 2: Cba makassar port (english)

2

ContentsCost Benefit Analysis1. Introduction to Cost Benefit Analysis2. Defining the problem3. Methodology for Makassar4. Results for Makassar

Value for Money Analysis

Page 3: Cba makassar port (english)

3

Benefit-Cost Analysis (BCA)• Benefit-Cost Analysis is a systematic process for

calculating and comparing benefits and costs of a project for two purposes:o to determine if it is a sound investment

(justification/feasibility)o to see how it compares with alternate projects

(ranking/priority assignment)

• Benefit-Cost Analysis works by defining the project and any alternatives; then by identifying, measuring, and valuing the benefits and costs of each.

Page 4: Cba makassar port (english)

4

When to Use Benefit-Cost Analysis• Benefit-Cost Analysis is most applicable for evaluating proposed

projects that meet the following criteria:

o The potential project expenditure is significant enough to justify spending resources on forecasting, measuring and evaluating the expected benefits and impacts.

o The project motivation is to improve efficiency rather than to meet some legal requirement or social goal.

o Environmental or social impacts that are outside of the transportation system efficiency measurement are either: • negligible in magnitude• measurable in ways that can be used within the benefit-

cost framework; or• to be considered by some other form of project appraisal

outside of the benefit-cost analysis.

Page 5: Cba makassar port (english)

5

When to Use Benefit-Cost Analysis• Benefit-Cost Analysis is neither necessary nor desirable to

justify all transportation projects. It may not always be appropriate in the following cases:

o Projects motivated by a need to meet legal requirements — such as safety standards or environmental impact standards.

o Projects motivated primarily by a need to address distributional equity concerns — i.e., legal, political or moral desires for fairness.

o Projects that are merely maintaining, renovating or rehabilitating already-built transportation facilities, which are necessary to avoid losing the already-demonstrated benefits of those existing facilities (unless there are viable alternatives present)

Page 6: Cba makassar port (english)

6

BCA vs Economic Impact Assessment (EIA) • Economic impacts are the effects a project or policy has on

the economy of a designated project area

• Economic impacts can result from various sources, including time savings to businesses, operating cost savings, the strengthening of local and regional market connectivity, etc.

• Economic impacts arise because a transportation investment causes a change in prices, or a change in business behavior that improves business investment, attraction, expansion, retention, or competitiveness

Page 7: Cba makassar port (english)

7

BCA vs Economic Impact Assessment (EIA)

BCA EIA

A systematic evaluation of the economic advantages (benefits) and disadvantages (costs) of a set of investment alternatives.

Exercise to determine how a project or policy affects the amount and type of economic activity in a region. This kind of analysis focuses on macroeconomic indicators and forecasts the influence of the project on these indicators.

Addresses whether society is better off by performing a certain action (such as building a road/port) versus doing nothing.

Addresses how an economy is likely to change as a result of an action.

Page 8: Cba makassar port (english)

8

BCA vs Economic Impact Assessment (EIA)

BCA EIA

Compares benefits and costs of a project to calculate net change in welfare.

Calculates change in output, income, value add and employment. This tells how the economy has changed.

Page 9: Cba makassar port (english)

9

Difference between financial and economic analysis

Financial Analysis Economic AnalysisThe analysis carried out from the point of view of the project operator to:• verify and guarantee cash

balance (financial sustainability); • calculate the indices of financial

return on the investment project based on the net time-discounted cash flows.

Analysis that is undertaken using economic values, reflecting the values that society would be willing to pay for a good or service. In general, economic analysis values all items at their value in use or their opportunity cost to society.

The main purpose of the financial analysis is to use the project cash flow forecasts to calculate suitable net return indicators, particularly from the market point of view of the Investor.

The economic analysis appraises the project’s contribution to the economic welfare of the region or country. It is made on behalf of the whole of society instead of just the owners of the infrastructure, as in the financial analysis.

Page 10: Cba makassar port (english)

10

Consumer and Producer Surplus• Consumer Surplus is

the difference between the price that consumers pay and the price that they are willing to pay. It is the area between the equilibrium price and the demand curve

• Producer surplus is the difference between the price that a producer receives and the minimum amount that the producer would be willing to accept for the good/service.

Page 11: Cba makassar port (english)

11

Consumer and Producer Surplus• In the case of the expansion of the Port of Makassar, there

are three types of user benefits (Consumer Surplus) as a result of a port expansion: o Benefits to existing traffic from efficiency improvementso Benefits to diverted traffic (it is assumed that there is no

diverted traffic due to the high costs to use alternative ports)

o Benefits to deterred traffic avoided

• In the case of the expansion of the Port of Makassar, the producer surplus is the revenue generated through operations less all operating and maintenance costs, also subtracted is the revenue that would have gone to the existing port for traffic that switches over to the new port.

• It is assumed that none of the revenue would have been directed to alternative container ports due to their distance from Makassar.

Page 12: Cba makassar port (english)

12

Transport CBAs• A key aim of an economic appraisal of a transport project is

to measure the magnitude of the economic impact resulting from the investment.

• When it comes to transport, price alone is not an appropriate measure of the consumer's WTP, instead generalized cost is used.

Overall Economic

Impact

Change in transport

user benefits

(Consumer Surplus)

Change in system

operating costs and revenues (Producer

Surplus and Government

impacts)

Change in costs of

externalities (Environment

al costs, accidents,

etc.)

Investment costs

(including mitigation measures)

= + + -

Page 13: Cba makassar port (english)

13

Project description• Makassar Port is the largest port in Sulawesi and the fourth

largest container terminal in Indonesia The Makassar Port Master Plan predicts that the Makassar Port would cater up to 33M tonnes by 2022 and 64M tonnes by 2032, far outstripping the current capacity of the port (over 7M tonnes in containers and another 7M tonnes in general cargo and bulk).

• Given the long term limitation in capacity under the current configuration of the existing terminals at Makassar Port, the 2013 Makassar Port Master Plan suggests the development of container terminal facilities in three phases to the north of existing port.

• The master plan suggests that the capacity of the port would thus be increased to approximately 3M TEUs by 2032.

Page 14: Cba makassar port (english)

14

Project objectives and impacts• The development of the new Makassar Port will increase

the capacity to around 1,000,000 TEU p.a. with the first terminal expected to have around one-third of this.

• It will also improve the efficiency of the existing traffic at the current Makassar port.

• New Makassar Port will serve as a model for the preparation of potential PPP projects by port administrations in future, particularly because until now private investment in public ports has been limited.

• New Makassar Port is expected to give significant contribution to increasing economic growth in South Sulawesi. The increasing trend of economic growth would be attractive to international port investors.

Page 15: Cba makassar port (english)

15

Perspective and scope• The perspective of the new Makassar Port benefit cost

analysis is taken from South Sulawesi viewpoints which includes the stakeholders who incur some costs and who receive the benefits:

o The consumers of port services (the exporters and importers in South Sulawesi).

o The producer of port services (the port operator).

Page 16: Cba makassar port (english)

16

Time period• The time period for the new Makassar Port benefit-cost

analysis is 30 years, starts with the first project expenditures, and extends through the useful life of the project which maximizes the estimated economic efficiency of the project.

Page 17: Cba makassar port (english)

17

Level of effort• Considering that the development of the Makassar Port

has very high costs and significant effects, it is clearly worth considerable effort to determine whether benefits exceed costs and to identify the most economically advantageous alternative.

• It is necessary to compare the benefits and costs that would exist in the event that the project was carried out, with the benefits and costs without carrying out the project by taking into account the key aspects of port development such as engineering, financial, and economic.

Page 18: Cba makassar port (english)

18

Defining the Base Case and project option

• The current Makassar port constrained at an ‘efficient’ capacity of 550,000TEU p.a.

• It has been assumed that the port can continue accepting container traffic beyond this capacity, however this will introduce additional delays.

• These delays will cause waiting time to increase as the capacity increases.

• The port will continue accepting freight up until the ‘hard’ capacity of 1,000,000TEU p.a.

BASE CASE• Develop the new Makassar

Port with container terminal facilities to the north of existing port.

• The new Makassar Port will have a capacity of around 1,000,000 TEU p.a. with the first terminal expected to have around one-third of this.

ALTERNATIVE

Page 19: Cba makassar port (english)

19

Timing of costs and benefits• With Phase 1 of the Port of Makassar expansion project,

the total container capacity will be increased to the extent that Demand will not exceed supply until after 2030.

Page 20: Cba makassar port (english)

20

DiscountingA dollar today is worth more than a dollar five years from now even if there is no inflation because today's dollar can be used productively in the ensuing five years, yielding a value greater than the initial dollar. Future benefits and costs are discounted to reflect this fact. The purpose of discounting is to put all present and future costs and benefits in a common metric, their present value. Discounting is present in all benefit-cost.Discount rates are typically based on interest rates for government borrowing, which has little risk, with the inflation component removed, yielding the "real" interest rate. Although some development agencies such as the World Bank and ADB recommend using a standard 12% for all projects.

Page 21: Cba makassar port (english)

21

Benefits StreamItem Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7

Benefits 30 80 100 130 150 180Costs 200 80 15 15 15 15 15Net Benefit Stream -200 -50 65 85 115 135 165Discount Factor 1.000 0.893 0.797 0.712 0.636 0.567 0.507PV Benefit Stream

-200.0 -44.7 51.8 60.5 73.1 76.5 83.7Net Present Value

101

Page 22: Cba makassar port (english)

22

Net Present ValueThe sum of discounted costs are subtracted from the sum of discounted benefits. Projects with positive net present value should be considered; the greater the net present value, the more justifiable the project. However, a large project could have a higher net present value than a smaller project, even if it has a lower benefit-cost ratio.

Page 23: Cba makassar port (english)

23

Benefit Cost RatioTo calculate the benefit cost ratio, total discounted benefits are divided by the total discounted costs. Projects with a benefit-cost ratio greater than 1 have greater benefits than costs; hence they have positive net benefits. The higher the ratio, the greater the benefits relative to the costs. It is important to remember that simple benefit-cost ratio is insensitive to the magnitude of net benefits. Therefore if comparing two project options it may favour the option with the small costs and benefits over those with higher net benefits.

Page 24: Cba makassar port (english)

24

Benefit Cost RatioOption A: Benefits $150m

Costs $100mNPV $50mBCR 1.5

Option B: Benefits $100mCosts $60mNPV $40mBCR 1.66

Which option to choose?

Page 25: Cba makassar port (english)

25

Economic Internal Rate of Return (EIRR)The EIRR determines the discount rate where the PV of benefits is just equal to the PV of costs.The EIRR is often compared to the discount rate to assess economic viability. Often there will be a hurdle rate that the EIRR must be above for the project to be accepted. Sometimes this is the discount rate although it may be higher.

NPV BCR EIRR

If > 0 then >1 > Discount rate

If < 0 then < 1 < Discount rate

If = 0 then 1 = Discount Rate

Page 26: Cba makassar port (english)

26

Methodology for Ports• In order to develop a CBA, it is necessary to compare the benefits

and costs that would exist in the event that the project was carried out, with the benefits and costs without carrying out the project by considering three types of user benefits as a result of a port expansion:o Benefits to existing traffic from efficiency improvements –

Improved efficiency of the existing port as throughput above ‘efficient’ capacity is shifted to new port.

o Benefits to diverted traffic – If traffic is diverted to alternative ports due to capacity constraints this will impose extra costs on cargo owners. The new port will remove those extra costs.

o Benefits to deterred traffic avoided – These are the benefits to traffic that couldn’t be transported through the port at the current capacity but can be transported if the capacity is increased.

• In this case, benefits are represented by the consumer and producer surplus and costs are represented by the capital and O&M costs.

Page 27: Cba makassar port (english)

27

Methodology for Ports

Fig. A) Case with competitive alternative port

Fig. B) Case with non-competitive alternative port

Supply and demand for port services before and after a port expansion

Page 28: Cba makassar port (english)

28

Methodology for Ports

Supply and demand for port services before and after a port expansion

Case with competitive alternative port

• The supply is fixed at S0 which is the current ‘hard’ capacity of the port.

• There is an excess of demand over available supply made up by diverted (QS-Q0) and deterred traffic (Q1 – QS).

• If capacity is expanded to S1 to meet demand, then both the diverted traffic and deterred traffic will use the existing port.

• The consumer surplus is the difference between the demand curve and the generalised cost at the existing port GC0.

• The producer surplus is the price received for port services multiplied by the quantity of deterred traffic (Q1-QS).

Page 29: Cba makassar port (english)

29

Methodology for Ports

Supply and demand for port services before and after a port expansion

Case with non-competitive alternative port

• The Port of Makassar case is slightly different because the only other port on the island currently moving significant container volumes could not be considered a realistic alternative as it is over 1000 km away from Makassar and the costs to transport goods by road would be prohibitively expensive.

• In this case where the generalised cost to transport from the alternative port (GCS) is above the willingness-to-pay, all demand beyond the existing capacity is deterred traffic. Therefore an expansion in port capacity will result in a larger consumer and producer surplus.

Page 30: Cba makassar port (english)

30

BREAK

Page 31: Cba makassar port (english)

31

Methodology for MakassarEstimating Benefitso Benefits to existing traffic from efficiency improvements –

Improved efficiency of the existing port as throughput above ‘efficient’ capacity is shifted to new port.

o Benefits to diverted traffic – due to the high costs to use alternative ports it is assumed that there is no diverted traffic for Makassar.

o Benefits to deterred traffic avoided – These are the benefits to traffic that couldn’t be transported through the port at the current capacity but can be transported if the capacity is increased. These have been treated separately for imports and exports due to the different impact of each.

Page 32: Cba makassar port (english)

32

Methodology for Makassar• The demand forecasts are used as the unconstrained

demand for container trade.

• Without detailed data regarding the shape of the demand curve it is difficult to estimate the total consumer surplus.

• The approach taken is to use the average value-add of the export volumes as an estimate of the profit margin which is essentially the differences between the generalised cost of transport and the consumer’s willingness-to-pay.

• Due to the difference in commodity types and economic impacts of imports and exports, these have been treated separately in the analysis.

Page 33: Cba makassar port (english)

33

Methodology for MakassarBenefits to existing traffic from efficiency improvements

Queueing as a % of the time in port for a 660 m berth terminal with random ship arrivals

(This assumes an average of 3 berth points with this ship profile)

0%

20%

40%

60%

80%

100%

120%

% 5% 10%15%20%25%30%35%40%45%50%55%60%65%70%75%80%85%90%95%100%

Berth occupancy

Qu

eu

ing

%

Page 34: Cba makassar port (english)

34

Methodology for MakassarBenefits to existing traffic from efficiency improvements

Page 35: Cba makassar port (english)

35

Methodology for MakassarBenefits to existing traffic from efficiency improvements

This additional delay is quantified using:- the value of the containerised goods converted to a daily value

based on borrowing rates.- The value of a shipping container converted to a daily value based

on borrowing rates.- Daily charter rate of the average size ship on a per TEU basis.

Item Daily Cost

Daily charter rate per TEU IDR 77,050

Daily cost of container IDR 15,753

Daily cost of cargo per TEU IDR 40,485

IDR 133,288

Page 36: Cba makassar port (english)

36

Methodology for MakassarBenefits to deterred export trafficThese are the benefits to traffic that couldn’t be transported through the port at the current capacity but can be transported if the capacity is increased. An estimate of consumer surplus for each exported container has been made using the average value-add of export products. This has been calculated using a breakdown of trade products, production quantities, estimated export percentages and value of products.

Page 37: Cba makassar port (english)

37

Methodology for MakassarBenefits to deterred export trafficThe following charts shows the estimated quantity of export TEUs that will move through Phase 1 of the new terminal, that would not have otherwise been shipped due to capacity constraints.

Page 38: Cba makassar port (english)

38

Methodology for MakassarBenefits to deterred import trafficManufacturing in Sulawesi relies on a much higher level of imported products including machinery and chemicals than the Agriculture industry. The manufacturing industry has been growing at an average annual rate of 7.2%p.a (real) over the past decade and, for the purposes for this analysis, has been assumed to continue growing at 6%p.a, in line with the GDP growth forecasts for South Sulawesi. However, this growth rate assumes companies have the ability to import and export at unconstrained levels. It is assumed that once capacity is reached the excess demand for imported containers goes unmet (due to the previously discussed lack of alternative container ports).

Page 39: Cba makassar port (english)

39

Methodology for MakassarBenefits to deterred import traffic

Page 40: Cba makassar port (english)

40

Methodology for MakassarProducer surplus – benefit to new port operators

The producer surplus is the revenue generated through operations less all operating and maintenance costs, also subtracted is the revenue that would have gone to the existing port for traffic that switches over to the new port. The revenue from all throughput at the new port is included in the producer surplus as it is assumed that none of this revenue would have been directed to alternative container ports due to their distance from Makassar.

Page 41: Cba makassar port (english)

41

Methodology for MakassarTotal Benefits

Page 42: Cba makassar port (english)

42

Methodology for MakassarDiscounted Benefits

Page 43: Cba makassar port (english)

43

Results for Makassar

ItemValue

(IDR million)Benefits

Consumer Surplus – Existing Port Traffic Efficiencies 2,530,096

Consumer Surplus – Deterred Imports 3,623,668 Consumer Surplus – Deterred Exports 12,725,680 Producer Surplus 319,033

Present Value of Benefits 19,198,478 CostsPresent Value of Costs 3,874,501 Net Present Value (NPV) 15,323,977 Benefit Cost Ratio (BCR) 5.0 Economic Internal Rate of Return (EIRR) 27%

Results of the

economic cost

benefit analysis

• The result of a benefit cost ratio of 5.0 and an economic internal rate of return of 27% shows the project will provide a large net welfare benefit to the region.

Page 44: Cba makassar port (english)

44

Results for Makassar• There are two elements to this project that result in the high

stream of benefits across the appraisal period:

o The strong growth in container traffic demand is forecast to continue, quickly outstripping the capacity of the current port and creating a large amount of unmet demand.

o Due to the lack of an alternative container port in South Sulawesi, coupled with the distance and poor infrastructure connections to container ports in North Sulawesi, once the existing port reaches capacity the excess demand is unlikely to be able to shift to an alternative port. Therefore the benefit to the shipper of goods is not merely in reduced transport costs but in providing the ability to economically import or export at all.

Page 45: Cba makassar port (english)

45

Results for Makassar

ScenarioNPV

(IDR million) BCR EIRRBase Case 15,323,977 5.0 27%High Trade Forecasts 21,820,534 6.6 35%Low Trade Forecasts 8,674,181 3.2 20%High Discount Rate (14%) 10,401,958 3.8 27%Low Discount Rate (10%) 22,638,490 6.6 27%

Results of the

sensitivity analysis

• The results of the sensitivity analysis demonstrates the findings are quite robust with strong results even at the lower trade forecasts or high discount rate.

• The positive result of the economic cost benefit analysis highlights the crucial role the Port of Makassar plays in the economy of South Sulawesi.

Page 46: Cba makassar port (english)

46

Results for Makassar• Without significant capacity expansion the delays will

increase exponentially at the existing port adding additional costs to freight transport costs.

• The financial analysis shows there is an opportunity for a private operator to make a commercial return from the facility.

• The economic benefits shown in this project arise without the need for significant government support.

• For this reason, any government support required to facilitate the success of the project such as providing supporting transport connections, would represent excellent value for money.

Page 47: Cba makassar port (english)

47

Break

Page 48: Cba makassar port (english)

48

Value for Money AnalysisValue for Money (VFM) is the optimum combination of whole-of-life costs and quality (or fitness for purpose) of the good or service to meet the user’s requirements.

Broadly speaking, a PPP may provide value for money compared to traditional procurement models if the advantages of risk transfer combined with private sector incentives, experience and innovation outweigh the increased costs of contracting and financing. This raises challenges for policy-makers: how to assess the value for money of different procurement and delivery options—that is, carry out “value for money (VFM) analysis”—and how to use the results of this analysis in PPP decision-making.

Page 49: Cba makassar port (english)

49

Value for Money AnalysisVFM analysis plays an important role in many PPP programs: a recent OECD study found that 19 of 20 surveyed countries apply some kind of value for money assessment to proposed PPPs. However, even in countries with well-established PPP programs, the approach to and use of this analysis is evolving, and is often the subject of controversy and debate.

Page 50: Cba makassar port (english)

50

Value for Money AnalysisAchieving VfM in PPP projects is in large part derived from their ability to transfer risk from the public entity to the private partner (Aldrete et al., 2010). The fundamental idea is that the private sector is more skilled at managing certain types of risk than the public sector (Mzikayise Binza, 2008). Risk in PPPs can be defined as the chance that an expected outcome for a project does not occur. More technically, this can be stated as the chance that the benefits and costs of a project are not allocated to the public and private entities as expected at the project’s onset (Aldrete et al., 2010).

Page 51: Cba makassar port (english)

51

Value for Money AnalysisA common misperception regarding the use of PPPs is that as much risk as possible should be transferred to the private entity. However, if a portion of the risk can be more efficiently managed by the public sector, that risk should be borne by the public sector; by transferring risk to the private sector that can be more efficiently managed by the public entity, money will be wasted since, ultimately, the public sector must pay the private entity to bear the risk.

Page 52: Cba makassar port (english)

52

Value for Money AnalysisVFM analysis typically involves a combination of qualitative and quantitative analysis.Qualitative VFM analysis typically involves sense-checking the rationale for using PPP—that is, asking whether a proposed project is of a type likely to be suitable for private financing.

“Suitability” criteria include the long-term, predictable need for the service; the ability to allocate risk effectively; the likely ability of the private sector party to manage risk and take responsibility for delivery; presence of stable and adequate policy and institutions; and a competitive bidding market.“Unsuitability” criteria include projects that are either too small or too complicated; sectors where needs are likely to change or there is a risk of obsolescence (for example, PFI projects are no longer used in the ICT sector in the UK); or where the contracting authority is inadequately skilled to manage PPP.

Page 53: Cba makassar port (english)

53

Value for Money AnalysisQuantitative VFM analysis involves comparing the value for money of a proposed PPP (or actual bids received) with a “Public Sector Comparator” (PSC)—that is, a model of the project if implemented through traditional public procurement.This is done by looking at the discounted cash flows from both a PPP and public sector perspective. Generally, the approach taken is to add back to the analysis the cost of any significant risks that will be Transferred under the PPP model—that is, risks that are retained by government under both public sector and PPP models are assumed to cancel out.

Page 54: Cba makassar port (english)

54

Value for Money Analysis

Page 55: Cba makassar port (english)

55

Port of Makassar - Value for Money•Value-for-Money Analysis is designed to assess if a PPP project represents better value for money than the traditional government procurement model. In the case of the ports sector DGST has not and does not operate ports and therefore there is no way to have realistic PSC for a full government owned and operated case.

•For other infrastructure such as water treatment, schools and roads where the government does operate these facilities it is possible to test a PPP case against a Public Sector case because full government ownership and operation is a possible alternative.

Page 56: Cba makassar port (english)

56

Port of Makassar - Value for Money•The value for money question then turns to the structure of the PPP project. There are several options available to DGST to structure the project. •If it is a BOT requiring no government support then the issue of Value for Money is irrelevant because there is no cost to governmental. •In the case of Makassar there is likely to be VGF required if the tariff is to remain at an acceptable level. •The LOH case becomes the pseudo PSC because it is has as much public ownership and involvement as is possible under the current structure of the Indonesian port system.

Page 57: Cba makassar port (english)

57

Port of Makassar - Value for Money

Page 58: Cba makassar port (english)

58

Port of Makassar - Value for Money•While, the landlord model provides better value for money of the two modalities, the decision cannot be based on value for money alone.• Other factors such as the ability of the MPA to borrow the required funds and manage the construction process are critical. •If due to these complications the BOT model is selected the value for money proposition simply becomes allowing the highest charges that are acceptable in order to minimise VGF.

Page 59: Cba makassar port (english)

59

Value for Money AnalysisProblems with quantitative analysis-Putting a dollar value on the transfer of risk can be subjective. This can lead to the Public Sector Comparator being manipulated to get a desired outcome. -A major risk of quantitative VFM analysis is that the results are seen as “overly-scientific” and that the results are taken as proof of a particular outcome. In reality it is an estimated based on a range of assumptions with incomplete information. -If a quantitative assessment is conducted the it should be assessed alongside other factors.

Page 60: Cba makassar port (english)

60

Value for Money AnalysisVFM analysis in many countries is limited to social sector PPPs that will be paid for entirely by Government availability payments. In economic sectors such as transport, user charging is seen as the more economically efficient way to pay for infrastructure, and as more politically and socially feasible under a PPP—the decision to implement a project as a PPP in these sectors is therefore driven by the financial viability of the proposed project.