Engineering and Commercial Infrastructure -
Waste Services
Monthly Review -
1 October 2016 – 30 October 2016
Page 2
Engineering & Commercial Infrastructure Monthly Review > October 2016
Overview……………………………………………………………………………....….…...………3
1.0 Safety...........................................................................................................................4
1.1 Safety Incidents and Lost Time Injuries 1.2 Lost Time Injuries 2.0 Finance…………………………………………………………………………...…………..5 2.1 Community Service Obligations – Fee Waivers 2.2 Waste Operating Revenue less Expenditure 2.3 Accrued Waste Operating Revenue less Expenditure 2.4 Capital Expenditure 3.0 Client Service..............................................................................................................7 3.1 Client Requests 3.2 Number of Bin Requests Actioned by Bin Contractors 3.3 Contractor Service Delivery Performance 3.4 Education
3.4.1 Material Recovery Facility tours 3.4.2 Education programs given out in the community
3.5 Dump Vouchers 3.6 Community Engagement 4.0 Asset Management...................................................................................................13 4.1 Hogan’s Pocket Landfill Waste Disposal Tonnages 4.2 Landfill Gas 4.3 Greenwaste Management 4.4 Projects 4.4.1 Significant Projects 4.4.2 Significant Non-Capital Projects 4.5 Materials Recovery Facility Operations 5.0 Regulatory/Compliance..............................................................................................18
5.1 Surface Water Discharge Management 5.2 Waste Facility Audits
Page 3
Engineering & Commercial Infrastructure Monthly Review > October 2016
Overview
This report is for Waste Services activities for October 2016. Significant items in this period include:
The significant Change of Waste and Recycling Bin Collection Day Project was completed successfully during the reporting period where the service day for 15,109 properties was changed.
As part of the Council implemented Change of Waste and Recycling Bin Collection Day Project, the Community Engagement implementation was an outstanding success with 48,575 people reached via Facebook.
A new graph has been introduced to illustrate the key customer service requests for bin collection services as a time series to provide better context for analysis.
Director Engineering & Commercial Infrastructure
Page 4
Engineering & Commercial Infrastructure Monthly Review > October 2016
SAFETY
1.1 Safety Incidents and Lost Time Injuries
The incident statistic details a summary of the Waste Services safety incident performance. Waste Services aspires to achieve zero harm with a stretch target of zero injuries.
No Lost Time Injuries were recorded in October 2016.
There were 10 incidents reported during October with all incidents reported by contractors. This is due to a recent increased focus on ensuring that contractors are reporting all incidents.
2
1
2
3
5
6
4
2
0
3
5
2
10
0 0 0 0 0 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0
1
0 0
1
0 0 0 0 0 0
1 1
0
1 1 1
2
0
2
4
6
8
10
12
Number of Incidents
Total Incidents Lost Time Injuries Total Recordable Injuries All Injuries
1.2 Lost Time Injuries
Waste Services aspires to achieve zero Lost Time Injuries by improving safety performance and developing a proactive safety culture while implementing the best practice of safety management across the whole of Waste Services
Page 5
Engineering & Commercial Infrastructure Monthly Review > October 2016
The table below shows the Lost Time Injuries over previous years
FINANCE
2.1 Community Service Obligations – Fee Waivers
Not for Profit Organisations – Total Waste Disposals 1 October to 31 October 2016
Spend for the quarter July -October is lower than budgeted due to some charities not using their allocated budget.
Data is for 2016/2017 Financial Year, as at 31 October 2016
$16,291.50
$48,980
$- $10,000 $20,000 $30,000 $40,000 $50,000 $60,000
$ (inclGST)
Budget for 2016/2017 YTD Expenditure 2016/2017
Year to date expenditure for not for profit organisations is reported on a calendar month.
Page 6
Engineering & Commercial Infrastructure Monthly Review > October 2016
2.2 Waste Operating Revenue Less Expenditure
The following chart shows the actual budget and forecast Earnings before Interest, Taxes and Amortization (EBITA) based on cash accounting for the 2015/2016 financial year. The saw tooth nature of the graph is reflective of the timing of waste revenue due.
-
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
16,000,000
Re
ve
nu
e le
ss e
xp
en
dit
ure
(m
arg
in)
$
Budget - Waste Actuals - Waste Projected Actuals - Waste
YTD Actuals exceed YTD budget by $1.7M. Revenue is less than budget by $344K mainly due to Gate Fees being less than budgeted by $332K. Goods & Services is under budget by $2M mainly due to $1.2M contract invoices and $393K Waste Collection invoices not yet being received. Employee costswere underspent by $49K mainly due to 0.62 fulltime vacancy and one week's wages not being included.
Financial data to October 2016
2.3 Accrued Waste Operating Revenue less Expenditure
The following chart shows the estimation of the accrued revenue less expenditure. The capital revenue has been excluded.
-
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
9,000,000
Rev
enu
e le
ss e
xpen
dit
ure
(m
arg
in)
$
Budget - Waste Accrual Actual - Waste Accrual Proj. Accrual Actuals - Waste
YTD Accrued Actuals exceed YTD budget by $65K (i.e. $49K saving in Employee Cost) and a surplus of $139K has been projected for end of year. This is mainly as a result of the variable cost component of waste collection and processing that is down as a result of the downward trend of waste tonnages processed and forecasted.
Finance data is to October 2016
Page 7
Engineering & Commercial Infrastructure Monthly Review > October 2016
2.4 Capital Expenditure
The following graph provides an overview of the capital expenditure and monitors forecast expenditure against actual expenditure.
-
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
1,800,000
Exp
end
itu
re (
$)
Forecast Cash Flow Capital YTD Actual Capital Expenditure
YTD Actual + Committals Capital Expenditure Amended Budget
Amended Budget Cashflow
For the month 41% of the budget spent and YTD 31%. Including comittals 80% of budget spent. Forecast to spent 106% of total budget due to delays in Hogans Pocket Cell construction completion -$95K.
Financial data is up to October 2016
CLIENT SERVICE
3.1 Client Requests
The following graph shows the number of Client Requests actioned by staff according to type, for October 2016.
0
5
10
15
20
25
30
35
Total Clients Requests
Client Services ‐ October 2016
Spike in Miss by Client and Multiple Bin Complaints due to the new bin day changes.
Date is for the the period 1 October to 31 October 2016
Page 8
Engineering & Commercial Infrastructure Monthly Review > October 2016
3.2 Number of Bin Requests Actioned by Bin Contractors
The following graph shows the number of bin requests actioned by Bin Contractors for October 2016.
4
64
4
25
2
130
198
4
0
50
100
150
200
250
Bin Requests Actioned
No. of Bin Requests Actioned by Contractor ‐ October 2016
Highernumber of Missed by Contractor occurred during collection changes but was significantly lower than expected with 64 actually missed.
The following new graph illustrates the key customer service requests for bin collection services as a time series, to provide better context for analysis.
Page 9
Engineering & Commercial Infrastructure Monthly Review > October 2016
3.3 Contractor Service Delivery Performance The following graph identifies the total number of requests for the reporting period. The columns are illustrated to demonstrate the number of requests that were met by the contractor according to the Service Level Agreement (SLA) target of three days or as a breach of the SLA.
4% of requests exceeded theSLA.
Data is for the period of 1 October / November 2015 to 31 October 2016
0
100
200
300
400
500
600
700
800
No
of
Req
ues
ts
Bin Contractor within SLA Bin Contractor Breach
The following graph illustrates the completion time for the service delivery requests versus the target day of three days or less.
During the reporting period, Council implemented the change of Waste and Recycling Bin Collection Day Project. The change of collection day for 15,109 properties has occurred to help Council achieve the objectives of improving the collection service efficiencies and customer service by simplifying collection runs. To support this transition a full Community Engagement Plan was developed that included actions involving: A flyer sent to property at least two weeks in advance; Message within clear parcel slip stickered onto the bin; Social Messaging; Media Release; and Radio Advertising
Page 10
Engineering & Commercial Infrastructure Monthly Review > October 2016
The following charts illustrate the analysis of the impact of the Change of Waste and Recycling Bin Collection Day Project on customer requests received.
Three request types are identified as related to the change of collection day and these are categorised as:
Bin Service Improvement; Missed by Contractor; and Missed by Client Requests
Although 54 customer requests triggered this criteria analysis identified that there were only 32 actual missed services out of 15,109 which equates to 0.21% of the changed services. All missed bins were emptied either on the day of reporting or the day after reporting. Further analysis identified three causes of a request being lodged and these are:
Missed – The contractor missed the bin; Misunderstood Information – Information was provided but misinterpreted by the customer;
and Not Missed – The customer although reported bin was missed was identified as mistaken in
their belief. This is established through J-Track footage. This graph depicts the request types and causes:
1 1 29 11 6 2 2 20
5
10
15
20
25
30
35
Missed Misunderstoodinformation
Missed Misunderstoodinformation
Not missed Missed Misunderstoodinformation
Not missed
Bin Service‐Improve exist / add collectionday
Missed Bin by Contractor Missed Bin Collection by Client
The above graph illustrates the makeup of requests received during the changeover week. Although in total 46 missed requests were lodged, only 32 requests were identified as being missed. 14 requests occurred where the customer misunderstood the information provided. Overall, the Change of Waste and Recycling Bin Collection Day Project was an outstanding success. The implementation of the Transition Plan, which included a detailed Community Engagement Plan and detailed the allocation of appropriate contingency resources, has meant that despite the potential there was very minimal negative impact to Council’s residents. The success of the project has ensured that the objectives of improving the collection service efficiencies and customer service will be met.
Page 11
Engineering & Commercial Infrastructure Monthly Review > October 2016
The following chart illustrates service reliability through missed general and recycle waste bin services:
Increase of missed services in week 4 relates to the waste and recycling collection day changes.
Data is for the period for October 2016
0
5
10
15
20
25
30
35
No
of
Bin
s M
isse
d f
or
Co
llect
ion
Missed General Waste Missed Recycle
3.4 Education 3.4.1 Material Recovery Facility tours: Kinchant Dam Outdoor Education Centre staff MacKillop Catholic School (joint waste & water education)– two groups of Year 4 Kookaburra Kindergarten Mirani State School (joint waste & water education)– two groups of Year 4
3.4.2 Education programs given out in the community Recycling education at Goodstart Bridge Road West Mackay Regional Council Recycling education at Goodstart Andergrove Waste education given at Northern Beaches State High School to students studying Certificate III
in Early Childhood Education Recycling and worm farming education given at Eaglemount Retirement Resort 3.5 Dump Vouchers Voucher Season No Vouchers issued No Vouchers used %
15' (valid to 31 March 2015) 145,344 34,747 23.9%
15A' (valid to 30 Sept 2015) 146,313 32,733 22.4%
15B' (valid to 31 March 2016) 146,790 38,256 26.0%
16A' (valid to 30 Sept 2016) 144,174 36,070 25.0%
16B' (valid to 31 March 2017) 144,000 6,983 4.8%
2014/2015 Financial Year (to 30.06.2015) 58,276 $419,227
2015/2016 Financial Year (to 30.06.2016) 75,459 $553,204
2016/2017 Financial Year (to 31.10.2016) 19,962 $139,734
Total number and $ value of vouchers presented to date:
Page 12
Engineering & Commercial Infrastructure Monthly Review > October 2016
Increase in usage due to expiry of previous season and new vouchers being issued
Data is for the period of 1 Oct/Nov 2015 to 31October 2016
0
1000
2000
3000
4000
5000
6000
7000
8000V
ou
cher
s P
rese
nte
d f
or
Per
iod
Green Waste Trans. Using Vouchers General Waste Trans. Using Vouchers
3.6 Community Engagement This section monitors Waste Services' engagement on the service provided. The following chart shows the number of media releases, media updates and the number of people reached by media releases on Facebook. The 48,575 people reached in relation to the Changes to Waste and Recycling Collection Services is extraordinary when compared to the usual reach.
Press Release during the period:
" Recycling bins are no place for dangerous waste "
Media Update during this period:
"Changes to Waste and Recycling collection
services"
48,575 people were reached on Facebook
Data is for the period 1 October 2016 to 31 October 2016
0
10000
20000
30000
40000
50000
60000
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5R
each
on
Fac
ebo
ok
(Peo
ple
)
Rel
ease
s
Media Releases Media Update Facebook People Reached
Page 13
Engineering & Commercial Infrastructure Monthly Review > October 2016
The following chart shows the number of likes and positive comments, the number of neutral comments and the number of negative comments received on Facebook from media releases and media updates for Waste Services:
There were 340" Likes" & 88 "Shares" regarding the waste and recycling collection changes.
There were no neutral or negative comments over this period.
Data is for the period 1 October 2016 to 31 October 2016
0
50
100
150
200
250
300
350
400
Likes Neutral Negative
ASSET MANAGEMENT 4.1 Hogan’s Pocket Landfill Waste Disposal Tonnages
The following chart represents the monthly tonnes disposed of at Hogan's Pocket Landfill. This chart shows that tonnes this financial year have been down when compared with previous financial years.
5500
6000
6500
7000
7500
8000
8500
9000
9500
10000
Tonnes Waste Received
11/12 13/14 14/15 15/16 16/17
Waste tonnes have hit a historic 5 year low falling below the previous month’s total. The tonnes received remain volatile and is contributing towards difficulty in modelling.
Data is for period 01 July 2016 to 31 October 2016
Page 14
Engineering & Commercial Infrastructure Monthly Review > October 2016
4.2 Landfill Gas
The following chart depicts the monthly tonnes of CO2-e destroyed.
0
500
1000
1500
2000
2500
3000
Tonnes CO2
15/16 15/16 16/17
Gas production has stabilised due to 100% flare up time during the month. The previous months fault diagnosis identified a defective solenoid valve and replacement part was sourced from Brisbane. The second failure determined PLC had failed. This is a critical component that our WA contractor was required to program and install and could not be sourced locally.
Data is for period 1 July 2015 to 31 October 2016
4.3 Greenwaste Management
The following graph illustrates the tonnage rates for green waste processed for the period, the cumulative tonnes of green waste processed for the year to date and the tonnes of green waste projected to be processed early. The production of processed green waste remains highly variable and the projected totals are a guide only.
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
Tonnes of Greenwaste Processed
Greenwaste Processed Cumulative Total Projected Tonnes
The production of greenwaste remains well below projections which is attributable to a dryer than normal year.
Data as at 31 October 2016
Page 15
Engineering & Commercial Infrastructure Monthly Review > October 2016
The following graph illustrates the historical tonnes of greenwaste processed. The graph demonstrates that there is no clear pattern in terms of tonnes processed due to neither seasonality nor the timing of the actual processing. Due to this volatility modelling will remain linear.
4.4 Projects
4.4.1 Significant Projects
Waste Services undertakes a range of projects across the business. Projects take the form of capital projects, planning, research and investigations.
Council Project Management Phases 1. Planning (Plan) 2. Design (Des) 3. Procurement (Proc) 4. Construction (Con)
Indicators On Track
Potential Issue
Definite Issue
Project Phase Phase % Complete
Budget Time Comments
Cell 3 Construction
Construction
100%
The project has now been completed. The landfill operations contractor will remain filling in Cells one and two until the 2017 dry season.
MRF Fire System Upgrade
In-Progress
15%
This project covers the installation of an updated fire warning system. This provides reduced risk protection of staff and the asset. The project is being conducted under variation through the operating contractor and is currently in design stage. Design expected to be achieved mid-November with installation
Page 16
Engineering & Commercial Infrastructure Monthly Review > October 2016
Project Phase Phase % Complete
Budget Time Comments
complete in December.
Regional Collection Changes
Completed
100%
This project saw implementation of regional changes to collection days for 15,109 services. A Community Engagement Plan was developed and actions within that progressed. Week of change was 24th to 28th of October 2016. Only 32 missed services were recorded for the 15,109 properties changed.
Plant & Equipment
Planning 5% This project sees replacement of rented site offices at Koumala and Kuttabul Transfer Stations.
Hogan's Pocket Communication
tower
Land negotiation
10%
Project is reliant on securing suitable elevated land. Waste Services is currently negotiating lease arrangements with neighbour.
Hogan's Pocket weeds wash bay
Procurement 0%
Pursuant to the recently developed Site Pest Management Plan, a weeds wash-down bay is required for the site. Waste Services is seeking design pricing.
Paget Transfer station dust suppression
system
Procurement 0%
Replacement of dust suppression system required to meet environmental and workplace health and safety obligations. Waste Services currently developing a performance specification for the work.
Bucasia gatehouse
realignment
Concept design
10%
In order to meet site operational requirements, as well as workplace health and safety requirements, the site office needs to be relocated (including introduction of traffic management infrastructure). This project will prolong the current single site operator maintaining operational costs.
Closed landfill risk review
Strategy 15%
Waste Services is undertaking a review of the Closed Site Remediation Program. The former landfill site remediation obligations currently represent one third of the Waste Services' twenty year capital forecast budget. The review will undertake a triple bottom line risk assessment priority ranking based on relative risks as well as a revised budget framework. Golder Associates has been
Page 17
Engineering & Commercial Infrastructure Monthly Review > October 2016
Project Phase Phase % Complete
Budget Time Comments
engaged to assist with the first stage of the project that will include consultation with Council.
4.4.2 Significant Non-Capital Projects
Project Phase Phase % Complete
Budget Time Comments
Waste Services Contracts Development
In-Progress
75%
The Waste Haulage and Landfill Operation Services and the Paget Transfer Station Services tenders continue to be evaluated. Evaluation is planned to be finalised in November 2016.
The Green Waste Processing Services tender evaluation has commenced.
Page 18
Engineering & Commercial Infrastructure Monthly Review > October 2016
4.5 Material Recovery Facility Operations
The following graph identifies tonnages inbound and product to market for the Material Recovery Facility.
Types of product output will vary each reporting period. A pleasing result as again no glass fines went to landfill during October 2016.
0
200
400
600
800
1000
1200
1400
1600
Inbound tonnages Product to Market 2015/2016
Waste 2015/2016 Glass Fines to Landfill 2015/2016
To
nn
es
MRF operations continued to achieve zero glass fines to landfill. 50 tonnes of crushed glass went on the market during the period. 94% of inbound tonnage was recycled during October 2016
Data is from 1 November2015 to 31 October 2016
The following graph shows tonnages for inbound product received from domestic collections within the Mackay Region, Commercial collections and Isaac Regional Council.
0
200
400
600
800
1000
1200
1400
1600
Tonnes
MRC Commingled Inbound Isaac Regional Council Comingled Inbound Commercial Inbound
During the month 50 tonnes of crushed glass was used for commercial purposes. 7 tonnes went to local businesses for use in sandblasting.
Data is from 1 November 2015 to 31 October 2016
REGULATORY COMPLIANCE
5.1 Surface Water Discharge Management
Page 19
Engineering & Commercial Infrastructure Monthly Review > October 2016
No matters to report.
5.2 Waste Facility Audits
Internal audits of MRC Waste Facilities continue to be conducted. During September 88% of sites were inspected.
As recording of this new performance metric has commenced it will assist Waste Services to focus on the delivery of this key service. Planned audits that were not achieved are to be conducted within 7 days of the end of the scheduled month. Issues that prevented Waste Services achieving this target were related to key staff being on leave. Waste Services will review this for future periods. Pleasingly there were no significant issues to report for this period.
This section of the report will evolve to include the rate of compliance and non-compliance.
Inspection Frequency
Number required
% Complete
Completed/ Carryover
Risk Comments
Bi-monthly 16 sites 100% 16 completed
0 carried over
No significant safety, environmental or asset issues identified in audits.
All carry overs completed in September 2016.
Six-monthly 0 100% Nil required
Nil safety, environmental or asset issues reported. Sites low risk. All carry overs completed in September 2016.