    You are here: Home - Primavera Tutorial - How to manage risk in Primavera P6 Professional

    OCTOBER 7, 2013

    LEAVE A COMMENT

    Posted in: Primavera Tutorial Started by MSS Team Member

    How to manage risk in Primavera P6Professional

    Risk Manag emen t in Prim avera P6Release 8.2Risks are uncertain events/conditions that have the potential to

    negatively (or positively) impact proje ct o bjectives. Prim avera P6

    Release 8.2 Professional includes an integrated Risk Management

    feature that enables you to identify, categorize and prioritize risks,assign a responsible person for managing the risk, assign risks to

    one or more activities that may be impacted by the risk, and

    conduct qualitative analysis on each risk. Additionally, you have

    the ability to record a risk response.

    BLOGS

    Primavera P6 Release 8.2:TSLD with Color CodedActivity Codes

    November 15, 2012

    Chec k Res ource Over-allocation Service inPrimavera P6 Web 8.2

    September 4, 2013

    1-800-931-1582

    HOW TO MANAGE RISK IN PRIMAVERA P6 PROFESSIONAL

    Search

    http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/author/admin/http://projectmanagementblog.mssprojectsanalytics.com/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://www.linkedin.com/company/mss-projects-analyticshttp://www.youtube.com/user/MidStateSolutionshttp://projectmanagementblog.mssprojectsanalytics.com/feed/http://projectmanagementblog.mssprojectsanalytics.com/feed/http://www.youtube.com/user/MidStateSolutionshttp://www.linkedin.com/company/mss-projects-analyticshttps://www.facebook.com/pages/MSS-Projects-Analytics/281560165239879https://twitter.com/MSS_Inc_USAhttp://projectmanagementblog.mssprojectsanalytics.com/check-resource-over-allocation-service-in-primavera-p6-web-8-2/http://projectmanagementblog.mssprojectsanalytics.com/primavera-p6-release-8-2-tsld-with-color-coded-activity-codes/http://projectmanagementblog.mssprojectsanalytics.com/author/admin/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/
  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    2/19

    P6 generates a Risk Score based on information that is entered

    for each risk. The Risk Score can then be used to help you

    evaluate the significance of the risk. This tutorial demonstrates the

    process of using the Risk Management functionality in P6 R8.2.

    Step 1. We will document a possible risk to our project involvingthe Design and Engineering process. We want to document that if

    the customer changes the design of our Office Building Addition,

    the project may incur additional costs as well as schedule delays.

    The image below illustrates the Design and Engineering WBS

    element (work breakdown structure). As you can see below, this

    portion of the project is currently scheduled to start on Jan. 11 and

    finish on Feb. 9, and the total budgeted cost is $3120. We can alsoview the activities comprising this WBS element and their

    corresponding dates & budgeted cost. Please note that we have

    added the Risks tab in our Activity Details.assigning project codes in p6

    attachment tools

    calculate estimate to complete in p6

    calculating performance percent

    complete

    claimdigger

    display multiple windows

    Primavera Tutorial: How touse Role Limits in P6

    December 10, 2012

    SUBSCRIBE BY EMAIL

    Email Subscription

    Your email here

    Subscribe Me

    TAGS

    http://projectmanagementblog.mssprojectsanalytics.com/primavera-tutorial-how-to-use-role-limits-in-p6/http://projectmanagementblog.mssprojectsanalytics.com/tag/display-multiple-windows/http://projectmanagementblog.mssprojectsanalytics.com/tag/claimdigger/http://projectmanagementblog.mssprojectsanalytics.com/tag/calculating-performance-percent-complete/http://projectmanagementblog.mssprojectsanalytics.com/tag/calculate-estimate-to-complete-in-p6/http://projectmanagementblog.mssprojectsanalytics.com/tag/attachment-tools/http://projectmanagementblog.mssprojectsanalytics.com/tag/assigning-project-codes-in-p6/
  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    3/19

    Step 2. Access the Risks icon on the directory bar and click the

    add icon on the Command Bar to begin the process of

    documenting the potential risk. The details pertaining to the risk

    are added using the detail tabs. The General tab is used to

    identify the risk category, risk type, owner or person responsible

    for resolving the risk, and status. The Exposure Start and

    Exposure Finish dates correspond to the start and finish of the

    activities in the Design and Engineering WBS. These dates

    represent the earliest and latest dates this risk may occur. The

    Pre-Response Exposure Cost represents the possible cost this

    earned value management

    how to assign project codes in

    primavera

    how to manage resources

    Index Performance Portlet

    learn primavera managing risk

    oracle primavera

    over-allocated resources p6

    p6 tutorial p6 tutorials

    performance percent complete

    ppm software primavera

    primavera contract manager

    primavera EPPM primavera p6

    primavera p6 professional

    primavera p6 project management

    primavera p6 release 8

    primavera p6 release 8.2

    http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/Risk-Management-1.pnghttp://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-release-8-2/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-release-8/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-project-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-professional/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-eppm/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-contract-manager/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-2/http://projectmanagementblog.mssprojectsanalytics.com/tag/ppm-software/http://projectmanagementblog.mssprojectsanalytics.com/tag/performance-percent-complete/http://projectmanagementblog.mssprojectsanalytics.com/tag/p6-tutorials/http://projectmanagementblog.mssprojectsanalytics.com/tag/p6-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/tag/p6/http://projectmanagementblog.mssprojectsanalytics.com/tag/over-allocated-resources/http://projectmanagementblog.mssprojectsanalytics.com/tag/oracle-primavera/http://projectmanagementblog.mssprojectsanalytics.com/tag/managing-risk/http://projectmanagementblog.mssprojectsanalytics.com/tag/learn-primavera/http://projectmanagementblog.mssprojectsanalytics.com/tag/index-performance-portlet/http://projectmanagementblog.mssprojectsanalytics.com/tag/how-to-manage-resources/http://projectmanagementblog.mssprojectsanalytics.com/tag/how-to-assign-project-codes-in-primavera/http://projectmanagementblog.mssprojectsanalytics.com/tag/earned-value-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/display-multiple-windows/
  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    4/19

    risk may impose, and the Post-Response Exposure Cost is the

    cost the risk may impose based on your risk response. We will

    discuss the calculations behind these values shortly. Notice that

    you can also provide the date the risk was identified as well as the

    resource that identified the risk.

    Step 3. The impact tab enables you to identify both pre-response

    and post-response parameters. Notice that you can select the

    Probability that the risk will occur, the impact that the risk may

    have on the schedule, and the monetary impact on the project if

    this risk occurs. The Risk Score is calculated based upon the

    values selected for the above mentioned parameters. The impact

    tab can also be utilized to document a response plan as well as

    response impact parameters to arrive at a Post-Response Risk

    Score.

    primavera p6 tutorial

    primavera resource management

    primavera resource wizard

    primavera risk management

    primavera software

    primavera training

    primavera tutorial

    project management

    project management softwareimplementation

    project scheduling

    resource duration

    resource management

    resource over-allocation

    risk management

    timescaled logic diagram tutorial

    using filter options

    http://projectmanagementblog.mssprojectsanalytics.com/tag/using-filter-options/http://projectmanagementblog.mssprojectsanalytics.com/tag/tutorial/http://projectmanagementblog.mssprojectsanalytics.com/tag/timescaled-logic-diagram/http://projectmanagementblog.mssprojectsanalytics.com/tag/risk-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/resource-over-allocation/http://projectmanagementblog.mssprojectsanalytics.com/tag/resource-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/resource-duration/http://projectmanagementblog.mssprojectsanalytics.com/tag/project-scheduling/http://projectmanagementblog.mssprojectsanalytics.com/tag/project-management-software-implementation/http://projectmanagementblog.mssprojectsanalytics.com/tag/project-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-tutorial-2/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-training/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-software/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-risk-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-resource-wizard/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-resource-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-tutorial/
  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    5/19

    The Help menu indicates how the Risk Score (both Pre-

    Response and Post-Response) is calculated:

    The overall risk score based on the values you select for three

    fields: Probability, Cost, and Schedule. Two of these fields, Cost

    and Schedule, are known as the impact fields.

    The Probability field and each impact field have these possible

    values: Very High, High, Medium, Low, Very Low, and Negligible.

    The application uses the highest value selected for the Cost and

    Schedule fields as the overall impact value. The application

    using resource lag

    http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/Risk-Management-3.pnghttp://projectmanagementblog.mssprojectsanalytics.com/tag/using-resource-lag/
  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    6/19

    determines the Score by plotting the overall impact value with the

    value entered for Probability, as shown in the table below.

    For example, if you enter the value Low for Cost and the value

    Medium for Schedule, the application uses Medium, the higher of

    the two, as the overall impact value. The application then uses the

    table below to determine the Score value by plotting the overall

    impact and Probability values. The columns in the table represent

    the overall impact values (Negligible through Very High), while the

    rows represent the Probability values (Very High through

    Negligible). The application determines the Score as the number

    that corresponds to the intersection of the applicable Impact

    column and Probability row. So, to continue our example, if youentered a value of High for Probability, the Score would display as

    14, the number shown where the Impact Medium column

    intersects the Probability High row.

    Impact

    Negligible

    Impact

    Very

    Low

    Impact

    Low

    Impact

    Medium

    Impact

    High

    Impact

    Very

    High

    Probability

    Very High

    0 5 9 18 36 72

    Probability 0 4 7 14 28 56

  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    7/19

    High

    Probability

    Medium

    0 3 5 10 20 40

    Probability

    Low

    0 2 3 6 12 24

    Probability

    Very Low

    0 1 1 2 4 8

    Probability

    Negligible

    0 0 0 0 0 0

    The Help menu identifies how the Pre-Exposure and Post-Exposure cost values are calculated. These values can be

    viewed on the General tab (see the image for Step 2 above):

    The application calculates the potential cost of a risk. The potential

    cost displays in the Pre-Response Exposure Cost and Post-

    Response Exposure Cost fields on the Risks, General tab. (The

    Post-Response Exposure Cost field displays only after a responseis made to a risk using the Post-Response fields on the Impact

    tab.) The following discussion refers to both the Pre- and Post-

    Response Exposure Cost fields generically as Exposure Cost

    fields because both are calculated using the same equation.

  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    8/19

    The value for the Exposure Cost field is based on the values

    selected for the Probability and Cost fields, located on the Risks,

    Impact tab, and on cost figures associated with the activities

    assigned to the Risk or to the project, if no activity assignments

    have been made.

    The application calculates the Exposure Cost value using this

    equation: Exposure Cost = Planned/Budgeted Total Cost *

    (Probability Midpoint * Cost Midpoint).

    The Planned/Budgeted Total Cost is the sum of the

    Planned/Budgeted Cost values for each activity assigned to the

    risk (or the planned project cost, if no activities are assigned to the

    risk).

    The Probability Midpoint is the midpoint of the Probability field

    value for the selected risk. The Cost Midpoint is the midpoint of the

    Cost field value for the selected risk. The way each is calculated is

    discussed below.

    Note: The Cost and Probability midpoint for the value Negligible is

    always zero, so the value of Negligible is not relevant to the

    following discussion.

    The equation for the calculation of Probability Midpoint and

    Cost Midpoint varies, depending on which values are selected

  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    9/19

    for the Probability and Cost fields:

    When using a value between highest and lowest:

    When a value of High (50% to 70%), Medium (30% to

    50%), or Low (10% to 30%) is selected for the Probability

    field, then the Probability Midpoint is calculated using this

    equation: Probability Midpoint = (lower range for selected

    value + higher range of selected value)/2. So if the

    Probability value is Medium (30% to 50%), then the

    Probability Midpoint is calculated as follows: (30+50)/2 =

    40%.

    When a value of High (20% to 40%), Medium (10% to

    20%), or Low (1% to 10%) is selected for the Cost field,then the Cost Midpoint is calculated using the same

    equation as Probability Midpoint. So if the Cost value is

    Medium (10% to 20%), then the midpoint is calculated as

    follows: (10 + 20)/2 = 15%

    For highest values:

    When the value Very High (70% or higher) is selected for

    the Probability field, then the Probability Midpoint iscalculated as the midpoint between the lower value and

    100%. So the Probability Midpoint for the value Very High

    (70% or higher) midpoint is calculated as follows: (70 +

    100)/2 = 85%.

    When the value Very High (40% or higher) is selected for

  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    10/19

    the Cost field, then the Cost Midpoint is calculated using

    this equation: ((the lower range for the selected value * 2) +

    the high range for the selected value)/2. So the Cost

    Midpoint for the value Very High (40% or higher) is

    calculated as follows: ((40 * 2) + 100)/2 = 90%.

    For lowest values:When the value Very Low (

  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    11/19

    Step 5. Use the Description tab to further describe the risk.

    http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/Risk-Management-4.png
  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    12/19

    Step 6. Use the Cause tab to document the cause of the risk.

    http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/risk-management-5.png
  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    13/19

  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    14/19

    Step 8. Additional Notes can be entered.

    http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/Risk-management-7.png
  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    15/19

    Step 9. In the Activities window, you can view and/or assign risks

    to activities using the Risks tab in activity details.

    http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/Risk-management-8.png
  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    16/19

  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    17/19

    Managing Over-allocatedResources in Primavera

    Posted on: September 18, 2012Filed in: Primavera Tutorial

    How to display multiplewindows at once inPrimavera P6 R8.2

    Posted on: November 12, 2012

    Filed in: Primavera Tutorial

    The Index PerformancePortlet

    Posted on: August 7, 2012Filed in: Primavera Tutorial

    Primavera Software Over-Allocated Resources

    Posted on: October 10, 2013Filed in: Primavera Tutorial

    LEAVE A REPLY

    Tags: managing risk , primavera risk management , risk

    management

    RELATED POSTS

    http://projectmanagementblog.mssprojectsanalytics.com/tag/risk-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-risk-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/managing-risk/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/primavera-software-over-allocated-resources/http://projectmanagementblog.mssprojectsanalytics.com/primavera-software-over-allocated-resources/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/index-performance-portlet/http://projectmanagementblog.mssprojectsanalytics.com/index-performance-portlet/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/how-to-display-multiple-windows-at-once-in-primavera-p6-r8-2/http://projectmanagementblog.mssprojectsanalytics.com/how-to-display-multiple-windows-at-once-in-primavera-p6-r8-2/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/managing-over-allocated-resources-in-primavera/http://projectmanagementblog.mssprojectsanalytics.com/managing-over-allocated-resources-in-primavera/
  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    18/19

    OLDER POST NEWER POST

    Name

    Email

    Website

    Submit Comment

    http://projectmanagementblog.mssprojectsanalytics.com/how-to-utilize-the-timescaled-logic-diagram/http://projectmanagementblog.mssprojectsanalytics.com/green-project-management/
  • 8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf

    19/19

    CONTACT DETAILS

    Copyright 2013 MSS Inc., All rights reserved. EPPM SOLUTIONS SERVICES PROJECT MANAGEMENT TRAINING

    PRODUCTS BLOG ABOUT

    Address: 20333 State Hwy. 249 Suite 200 Houston, TX 77070

    Phone: 1-800-931-1582

    Email: [email protected]

    Facebook: Follow US

    Twitter: Follow US

    https://twitter.com/MSS_Inc_USAhttps://www.facebook.com/pages/MSS-Projects-Analytics/281560165239879mailto:[email protected]://mssprojectsanalytics.com/about/http://projectmanagementblog.mssprojectsanalytics.com/http://projectmanagementblog.mssprojectsanalytics.com/how-to-manage-risk-in-primavera-p6-professional/mssprojectsanalytics.com/products/http://mssprojectsanalytics.com/project-management-training/http://mssprojectsanalytics.com/services/http://msssilo.cloudprojectmanagement.com/solutions/http://mssprojectsanalytics.com/eppm/http://mssprojectsanalytics.com/