You are here: Home - Primavera Tutorial - How to manage risk in Primavera P6 Professional
OCTOBER 7, 2013
LEAVE A COMMENT
Posted in: Primavera Tutorial Started by MSS Team Member
How to manage risk in Primavera P6Professional
Risk Manag emen t in Prim avera P6Release 8.2Risks are uncertain events/conditions that have the potential to
negatively (or positively) impact proje ct o bjectives. Prim avera P6
Release 8.2 Professional includes an integrated Risk Management
feature that enables you to identify, categorize and prioritize risks,assign a responsible person for managing the risk, assign risks to
one or more activities that may be impacted by the risk, and
conduct qualitative analysis on each risk. Additionally, you have
the ability to record a risk response.
BLOGS
Primavera P6 Release 8.2:TSLD with Color CodedActivity Codes
November 15, 2012
Chec k Res ource Over-allocation Service inPrimavera P6 Web 8.2
September 4, 2013
1-800-931-1582
HOW TO MANAGE RISK IN PRIMAVERA P6 PROFESSIONAL
Search
http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/author/admin/http://projectmanagementblog.mssprojectsanalytics.com/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://www.linkedin.com/company/mss-projects-analyticshttp://www.youtube.com/user/MidStateSolutionshttp://projectmanagementblog.mssprojectsanalytics.com/feed/http://projectmanagementblog.mssprojectsanalytics.com/feed/http://www.youtube.com/user/MidStateSolutionshttp://www.linkedin.com/company/mss-projects-analyticshttps://www.facebook.com/pages/MSS-Projects-Analytics/281560165239879https://twitter.com/MSS_Inc_USAhttp://projectmanagementblog.mssprojectsanalytics.com/check-resource-over-allocation-service-in-primavera-p6-web-8-2/http://projectmanagementblog.mssprojectsanalytics.com/primavera-p6-release-8-2-tsld-with-color-coded-activity-codes/http://projectmanagementblog.mssprojectsanalytics.com/author/admin/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/ -
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
2/19
P6 generates a Risk Score based on information that is entered
for each risk. The Risk Score can then be used to help you
evaluate the significance of the risk. This tutorial demonstrates the
process of using the Risk Management functionality in P6 R8.2.
Step 1. We will document a possible risk to our project involvingthe Design and Engineering process. We want to document that if
the customer changes the design of our Office Building Addition,
the project may incur additional costs as well as schedule delays.
The image below illustrates the Design and Engineering WBS
element (work breakdown structure). As you can see below, this
portion of the project is currently scheduled to start on Jan. 11 and
finish on Feb. 9, and the total budgeted cost is $3120. We can alsoview the activities comprising this WBS element and their
corresponding dates & budgeted cost. Please note that we have
added the Risks tab in our Activity Details.assigning project codes in p6
attachment tools
calculate estimate to complete in p6
calculating performance percent
complete
claimdigger
display multiple windows
Primavera Tutorial: How touse Role Limits in P6
December 10, 2012
SUBSCRIBE BY EMAIL
Email Subscription
Your email here
Subscribe Me
TAGS
http://projectmanagementblog.mssprojectsanalytics.com/primavera-tutorial-how-to-use-role-limits-in-p6/http://projectmanagementblog.mssprojectsanalytics.com/tag/display-multiple-windows/http://projectmanagementblog.mssprojectsanalytics.com/tag/claimdigger/http://projectmanagementblog.mssprojectsanalytics.com/tag/calculating-performance-percent-complete/http://projectmanagementblog.mssprojectsanalytics.com/tag/calculate-estimate-to-complete-in-p6/http://projectmanagementblog.mssprojectsanalytics.com/tag/attachment-tools/http://projectmanagementblog.mssprojectsanalytics.com/tag/assigning-project-codes-in-p6/ -
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
3/19
Step 2. Access the Risks icon on the directory bar and click the
add icon on the Command Bar to begin the process of
documenting the potential risk. The details pertaining to the risk
are added using the detail tabs. The General tab is used to
identify the risk category, risk type, owner or person responsible
for resolving the risk, and status. The Exposure Start and
Exposure Finish dates correspond to the start and finish of the
activities in the Design and Engineering WBS. These dates
represent the earliest and latest dates this risk may occur. The
Pre-Response Exposure Cost represents the possible cost this
earned value management
how to assign project codes in
primavera
how to manage resources
Index Performance Portlet
learn primavera managing risk
oracle primavera
over-allocated resources p6
p6 tutorial p6 tutorials
performance percent complete
ppm software primavera
primavera contract manager
primavera EPPM primavera p6
primavera p6 professional
primavera p6 project management
primavera p6 release 8
primavera p6 release 8.2
http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/Risk-Management-1.pnghttp://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-release-8-2/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-release-8/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-project-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-professional/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-eppm/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-contract-manager/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-2/http://projectmanagementblog.mssprojectsanalytics.com/tag/ppm-software/http://projectmanagementblog.mssprojectsanalytics.com/tag/performance-percent-complete/http://projectmanagementblog.mssprojectsanalytics.com/tag/p6-tutorials/http://projectmanagementblog.mssprojectsanalytics.com/tag/p6-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/tag/p6/http://projectmanagementblog.mssprojectsanalytics.com/tag/over-allocated-resources/http://projectmanagementblog.mssprojectsanalytics.com/tag/oracle-primavera/http://projectmanagementblog.mssprojectsanalytics.com/tag/managing-risk/http://projectmanagementblog.mssprojectsanalytics.com/tag/learn-primavera/http://projectmanagementblog.mssprojectsanalytics.com/tag/index-performance-portlet/http://projectmanagementblog.mssprojectsanalytics.com/tag/how-to-manage-resources/http://projectmanagementblog.mssprojectsanalytics.com/tag/how-to-assign-project-codes-in-primavera/http://projectmanagementblog.mssprojectsanalytics.com/tag/earned-value-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/display-multiple-windows/ -
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
4/19
risk may impose, and the Post-Response Exposure Cost is the
cost the risk may impose based on your risk response. We will
discuss the calculations behind these values shortly. Notice that
you can also provide the date the risk was identified as well as the
resource that identified the risk.
Step 3. The impact tab enables you to identify both pre-response
and post-response parameters. Notice that you can select the
Probability that the risk will occur, the impact that the risk may
have on the schedule, and the monetary impact on the project if
this risk occurs. The Risk Score is calculated based upon the
values selected for the above mentioned parameters. The impact
tab can also be utilized to document a response plan as well as
response impact parameters to arrive at a Post-Response Risk
Score.
primavera p6 tutorial
primavera resource management
primavera resource wizard
primavera risk management
primavera software
primavera training
primavera tutorial
project management
project management softwareimplementation
project scheduling
resource duration
resource management
resource over-allocation
risk management
timescaled logic diagram tutorial
using filter options
http://projectmanagementblog.mssprojectsanalytics.com/tag/using-filter-options/http://projectmanagementblog.mssprojectsanalytics.com/tag/tutorial/http://projectmanagementblog.mssprojectsanalytics.com/tag/timescaled-logic-diagram/http://projectmanagementblog.mssprojectsanalytics.com/tag/risk-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/resource-over-allocation/http://projectmanagementblog.mssprojectsanalytics.com/tag/resource-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/resource-duration/http://projectmanagementblog.mssprojectsanalytics.com/tag/project-scheduling/http://projectmanagementblog.mssprojectsanalytics.com/tag/project-management-software-implementation/http://projectmanagementblog.mssprojectsanalytics.com/tag/project-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-tutorial-2/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-training/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-software/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-risk-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-resource-wizard/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-resource-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-p6-tutorial/ -
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
5/19
The Help menu indicates how the Risk Score (both Pre-
Response and Post-Response) is calculated:
The overall risk score based on the values you select for three
fields: Probability, Cost, and Schedule. Two of these fields, Cost
and Schedule, are known as the impact fields.
The Probability field and each impact field have these possible
values: Very High, High, Medium, Low, Very Low, and Negligible.
The application uses the highest value selected for the Cost and
Schedule fields as the overall impact value. The application
using resource lag
http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/Risk-Management-3.pnghttp://projectmanagementblog.mssprojectsanalytics.com/tag/using-resource-lag/ -
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
6/19
determines the Score by plotting the overall impact value with the
value entered for Probability, as shown in the table below.
For example, if you enter the value Low for Cost and the value
Medium for Schedule, the application uses Medium, the higher of
the two, as the overall impact value. The application then uses the
table below to determine the Score value by plotting the overall
impact and Probability values. The columns in the table represent
the overall impact values (Negligible through Very High), while the
rows represent the Probability values (Very High through
Negligible). The application determines the Score as the number
that corresponds to the intersection of the applicable Impact
column and Probability row. So, to continue our example, if youentered a value of High for Probability, the Score would display as
14, the number shown where the Impact Medium column
intersects the Probability High row.
Impact
Negligible
Impact
Very
Low
Impact
Low
Impact
Medium
Impact
High
Impact
Very
High
Probability
Very High
0 5 9 18 36 72
Probability 0 4 7 14 28 56
-
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
7/19
High
Probability
Medium
0 3 5 10 20 40
Probability
Low
0 2 3 6 12 24
Probability
Very Low
0 1 1 2 4 8
Probability
Negligible
0 0 0 0 0 0
The Help menu identifies how the Pre-Exposure and Post-Exposure cost values are calculated. These values can be
viewed on the General tab (see the image for Step 2 above):
The application calculates the potential cost of a risk. The potential
cost displays in the Pre-Response Exposure Cost and Post-
Response Exposure Cost fields on the Risks, General tab. (The
Post-Response Exposure Cost field displays only after a responseis made to a risk using the Post-Response fields on the Impact
tab.) The following discussion refers to both the Pre- and Post-
Response Exposure Cost fields generically as Exposure Cost
fields because both are calculated using the same equation.
-
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
8/19
The value for the Exposure Cost field is based on the values
selected for the Probability and Cost fields, located on the Risks,
Impact tab, and on cost figures associated with the activities
assigned to the Risk or to the project, if no activity assignments
have been made.
The application calculates the Exposure Cost value using this
equation: Exposure Cost = Planned/Budgeted Total Cost *
(Probability Midpoint * Cost Midpoint).
The Planned/Budgeted Total Cost is the sum of the
Planned/Budgeted Cost values for each activity assigned to the
risk (or the planned project cost, if no activities are assigned to the
risk).
The Probability Midpoint is the midpoint of the Probability field
value for the selected risk. The Cost Midpoint is the midpoint of the
Cost field value for the selected risk. The way each is calculated is
discussed below.
Note: The Cost and Probability midpoint for the value Negligible is
always zero, so the value of Negligible is not relevant to the
following discussion.
The equation for the calculation of Probability Midpoint and
Cost Midpoint varies, depending on which values are selected
-
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
9/19
for the Probability and Cost fields:
When using a value between highest and lowest:
When a value of High (50% to 70%), Medium (30% to
50%), or Low (10% to 30%) is selected for the Probability
field, then the Probability Midpoint is calculated using this
equation: Probability Midpoint = (lower range for selected
value + higher range of selected value)/2. So if the
Probability value is Medium (30% to 50%), then the
Probability Midpoint is calculated as follows: (30+50)/2 =
40%.
When a value of High (20% to 40%), Medium (10% to
20%), or Low (1% to 10%) is selected for the Cost field,then the Cost Midpoint is calculated using the same
equation as Probability Midpoint. So if the Cost value is
Medium (10% to 20%), then the midpoint is calculated as
follows: (10 + 20)/2 = 15%
For highest values:
When the value Very High (70% or higher) is selected for
the Probability field, then the Probability Midpoint iscalculated as the midpoint between the lower value and
100%. So the Probability Midpoint for the value Very High
(70% or higher) midpoint is calculated as follows: (70 +
100)/2 = 85%.
When the value Very High (40% or higher) is selected for
-
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
10/19
the Cost field, then the Cost Midpoint is calculated using
this equation: ((the lower range for the selected value * 2) +
the high range for the selected value)/2. So the Cost
Midpoint for the value Very High (40% or higher) is
calculated as follows: ((40 * 2) + 100)/2 = 90%.
For lowest values:When the value Very Low (
-
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
11/19
Step 5. Use the Description tab to further describe the risk.
http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/Risk-Management-4.png -
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
12/19
Step 6. Use the Cause tab to document the cause of the risk.
http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/risk-management-5.png -
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
13/19
-
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
14/19
Step 8. Additional Notes can be entered.
http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/Risk-management-7.png -
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
15/19
Step 9. In the Activities window, you can view and/or assign risks
to activities using the Risks tab in activity details.
http://projectmanagementblog.mssprojectsanalytics.com/wp-content/uploads/2013/12/Risk-management-8.png -
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
16/19
-
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
17/19
Managing Over-allocatedResources in Primavera
Posted on: September 18, 2012Filed in: Primavera Tutorial
How to display multiplewindows at once inPrimavera P6 R8.2
Posted on: November 12, 2012
Filed in: Primavera Tutorial
The Index PerformancePortlet
Posted on: August 7, 2012Filed in: Primavera Tutorial
Primavera Software Over-Allocated Resources
Posted on: October 10, 2013Filed in: Primavera Tutorial
LEAVE A REPLY
Tags: managing risk , primavera risk management , risk
management
RELATED POSTS
http://projectmanagementblog.mssprojectsanalytics.com/tag/risk-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/primavera-risk-management/http://projectmanagementblog.mssprojectsanalytics.com/tag/managing-risk/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/primavera-software-over-allocated-resources/http://projectmanagementblog.mssprojectsanalytics.com/primavera-software-over-allocated-resources/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/index-performance-portlet/http://projectmanagementblog.mssprojectsanalytics.com/index-performance-portlet/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/how-to-display-multiple-windows-at-once-in-primavera-p6-r8-2/http://projectmanagementblog.mssprojectsanalytics.com/how-to-display-multiple-windows-at-once-in-primavera-p6-r8-2/http://projectmanagementblog.mssprojectsanalytics.com/category/primavera-tutorial/http://projectmanagementblog.mssprojectsanalytics.com/managing-over-allocated-resources-in-primavera/http://projectmanagementblog.mssprojectsanalytics.com/managing-over-allocated-resources-in-primavera/ -
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
18/19
OLDER POST NEWER POST
Name
Email
Website
Submit Comment
http://projectmanagementblog.mssprojectsanalytics.com/how-to-utilize-the-timescaled-logic-diagram/http://projectmanagementblog.mssprojectsanalytics.com/green-project-management/ -
8/11/2019 How to manage risk in Primavera P6 Professional - Project Management Blog _ Up-to-Date PPM Training, News & Resources.pdf
19/19
CONTACT DETAILS
Copyright 2013 MSS Inc., All rights reserved. EPPM SOLUTIONS SERVICES PROJECT MANAGEMENT TRAINING
PRODUCTS BLOG ABOUT
Address: 20333 State Hwy. 249 Suite 200 Houston, TX 77070
Phone: 1-800-931-1582
Email: [email protected]
Facebook: Follow US
Twitter: Follow US
https://twitter.com/MSS_Inc_USAhttps://www.facebook.com/pages/MSS-Projects-Analytics/281560165239879mailto:[email protected]://mssprojectsanalytics.com/about/http://projectmanagementblog.mssprojectsanalytics.com/http://projectmanagementblog.mssprojectsanalytics.com/how-to-manage-risk-in-primavera-p6-professional/mssprojectsanalytics.com/products/http://mssprojectsanalytics.com/project-management-training/http://mssprojectsanalytics.com/services/http://msssilo.cloudprojectmanagement.com/solutions/http://mssprojectsanalytics.com/eppm/http://mssprojectsanalytics.com/