no time for delays, snap-tite pipe provides the fix in a day...m t t no time for delays, snap-tite®...

2
www.culvert-rehab.com FIELD REPORT 1-800-CULVERT No time for delays, Snap-Tite ® pipe provides the fix in a day Northglenn, Colorado BACKGROUND School was in session at D.B. Stukey Elementary, and the road leading there was badly deteriorated from the corrosion of two underground corrugated metal pipes (CMPs). The city of Northglenn needed to act fast. Digging up and replacing the twin CMPs was too costly, both for the city and for the drivers who depended on using that road every day. One of the existing culverts was originally an 84- inch CMP. The pipe deteriorated extensively over time, resulting in massive deflection and a severe dip in the road above. At some points in the pipe the diameter was as low as 60 inches – 24 inches less than the original installation. “Grant Street [the affected roadway] is one of the only ways to access the neighborhood and school,” said Snap-Tite representative Russ Wosk. “Since school had recently started, repairs needed to be made without digging up the road.” Snap-Tite offered the solution. WHY Snap-Tite ® ? The city needed to fix the corroded and collapsing twin 84-inch CMPs. And they needed to do it quickly, in the most cost-effective and least disruptive means available. Snap-Tite HDPE pipe was the clear choice. Wosk worked with the city and Danny Branning, of C&L Water Solutions, to rehabilitate the failing culvert with 54-inch diameter Snap-Tite in 24-foot lengths. Due to Snap-Tite s superior flow characteristics, the decrease in diameter was not an issue. The Installation Branning and his crew completed slip-lining the 54-inch Snap-Tite liner, from start to finish, in one day. Annular grouting between the failing CMP and the 54-inch Snap-Tite liner was also completed in a day. “This is the type of work I’d like to do more often,” Branning said. The no-dig HDPE Snap-Tite culvert-lining pipe, The annular space between the original CMP and the new HDPE Snap-Tite liner pipe. The construction crew installed the Snap-Tite HDPE pipe liner, from start to finish, in a single day with no digging or roadway delays necessary.

Upload: others

Post on 31-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: No time for delays, Snap-Tite pipe provides the fix in a day...m T T No time for delays, Snap-Tite® pipe provides the fix in a day Northglenn, Colorado BACKGROUND School was in session

www.culvert-rehab.comFIELD REPORT

1-800-CULVERT

No time for delays, Snap-Tite® pipe provides the fix in a dayNorthglenn, Colorado

BACKGROUND

School was in session at D.B. Stukey Elementary, and the road leading there was badly deteriorated from the corrosion of two underground corrugated metal pipes (CMPs). The city of Northglenn needed to act fast. Digging up and replacing the twin CMPs was too costly, both for the city and for the drivers who depended on using that road every day.

One of the existing culverts was originally an 84-inch CMP. The pipe deteriorated extensively over time, resulting in massive deflection and a severe dip in the road above. At some points in the pipe the diameter was as low as 60 inches – 24 inches less than the original installation.

“Grant Street [the affected roadway] is one of the only ways to access the neighborhood and school,” said Snap-Tite representative Russ Wosk. “Since school had recently started, repairs needed to be made without digging up the road.”

Snap-Tite offered the solution.

WHY Snap-Tite®?

The city needed to fix the corroded and collapsing twin 84-inch CMPs. And they needed to do it quickly, in the most cost-effective and least disruptive means available. Snap-Tite HDPE pipe was the clear choice.

Wosk worked with the city and Danny Branning, of C&L Water Solutions, to rehabilitate the failing culvert with 54-inch diameter Snap-Tite in 24-foot lengths. Due to Snap-Tite’s superior flow characteristics, the decrease in diameter was not an issue.

The Installation

Branning and his crew completed slip-lining the 54-inch Snap-Tite liner, from start to finish, in one day. Annular grouting between the failing CMP and the 54-inch Snap-Tite liner was also completed in a day.

“This is the type of work I’d like to do more often,” Branning said.

The no-dig HDPE Snap-Tite culvert-lining pipe, The annular space between the original CMP and the new HDPE Snap-Tite liner pipe.

The construction crew installed the Snap-Tite HDPE pipe liner, from start to finish, in a single day with no digging or roadway delays necessary.

Page 2: No time for delays, Snap-Tite pipe provides the fix in a day...m T T No time for delays, Snap-Tite® pipe provides the fix in a day Northglenn, Colorado BACKGROUND School was in session

www.culvert-rehab.comFIELD REPORT

1-800-CULVERT

which has patented male/female machining at each end of the HDPE, is ‘snapped’ together, piece-by-piece, and pushed into the full length of an existing pipe. Any annular space and voids between the old culvert and new liner are filled in with grout.

The pipe liner is available in lengths from two feet to 50 feet, and is available for culverts with diameters from eight inches to 84 inches. Snap-Tite also meets American Association of State Highway and Transportation Officials (AASHTO) Standard M326 for rehabilitating culverts.

About Snap-Tite®

• Meets AASHTO Standard M326 for rehabilitating culverts.

• Offers flexibility for insertion into misaligned concrete or rusted deteriorated corrugated

metal pipe.• Offers a safe method for installers and doesn’t

require traffic control.• Tough but lightweight, the Snap-Tite joint

makes a solid water-tight mechanical connection that can be pushed or pulled.

• Due to the Snap-Tite system’s installation flexibility and cost-effectiveness, it continues to provide successful results for many projects throughout the U.S. and internationally.

For more information on Snap-Tite, please visit www.culvert-rehab.com.

To view Snap-Tite installation videos, visit Snap-Tite’s YouTube Channel atwww.youtube.com/SnapTiteChannel.