question setpmp no 4

Upload: mani-selvan

Post on 03-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Question SetPMP No 4

    1/44

    PMP Mock Examination- Wishing You Success!!!

    PMP Mock Examination-

    Set IVVersion 1.0

  • 7/28/2019 Question SetPMP No 4

    2/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 1) A Project Manager is at the project kick-off meeting. He confidently states the vision and

    mission for the project. This Project Manager is exhibiting the following leadership style:-

    A. HierarchalB. AuthoritarianC.

    CharismaticD. Associative

    (Question 2) You are in charge of developing a new product for an organization. Your quality metrics are

    based on the 80th percentile of each of the last three products developed. This is an example of:

    A. Statistical samplingB. MetricsC. BenchmarkingD. Operational definitions

    (Question 3) The two Closing Processes are called:-

    A. Contract close out and Verify ScopeB. Close Project or Phase and Close ProcurementsC. Close Project and product verificationD. Close Project or Phase and Lessons Learned

    (Question 4) During the Develop Schedule process the Project Manager may have to go through several

    iterations of the schedule before establishing the schedule baseline. All of the following are tools and

    techniques that may be used during this process:-

    A. Critical Path Method, Expert Judgment, Resource RequirementsB. Alternative Analysis, Mathematical Analysis, CalendarsC. Schedule compression, Resource Leveling Heuristics, Critical PathD. Reserve Analysis, Template Decomposition

    (Question 5) Which of the following models of conflict resolution allows a cooling off period, but seldom

    resolves the issue in the long term?

    A. Problem solvingB. WithdrawalC. Forcing

  • 7/28/2019 Question SetPMP No 4

    3/44

    PMP Mock Examination- Wishing You Success!!!

    D. Smoothing

    (Question6) In Communications Model, the receiver filters messages based on all except the following:-

    A. CultureB. SemanticsC. LanguageD. DistanceE. Knowledge

    (Question 7) How much time does the typical project manager spend communicating both formally and

    informally?

    A. 40-60%B. 50-70%C. 60-80%D. 75-90%

    (Question 8) Group brainstorming encourages all of the following except:

    A. Team buildingB.

    Analysis of alternativesC. Convergent thinking

    D. Uninhibited verbalization

    (Question 9) The critical element in a project's communication system is the:

    A. Progress reportB. Project directiveC. Project managerD.

    Vendor

    (Question 10) Project Integration comprises of:

    A. Assuring that the pieces of a project come together at the right timeB. Planning for contingencies that may occur throughout the life cycle of the project

  • 7/28/2019 Question SetPMP No 4

    4/44

    PMP Mock Examination- Wishing You Success!!!

    C. Making Sure that the pieces of the project function as an integration unitD. Both A and C

    (Question 11) Performance reviews are held to:

    A. Correct the project manager's mistakes.B. Provide for answers for upper levels of managementC. To assess project status or progressD. To apprise the project costs and cost trends of the project

    (Question 12) A complex project will fit best in what type of organization?

    A. FunctionalB. Cross-functionalC. MatrixD. Balanced

    (Question 13) Which of the following could be an appropriate WBS code for a work package at the

    fourth level in a WBS where the top level code is 1.0?

    A. 1.4B.

    1.1.1.1C. 1.2.3.4

    D. Both A and CE. Both B and C

    (Question 14) Which of the following Project Scope Management Processes involves subdividing the

    major project deliverables into smaller, more manageable components?

    A. Collect RequirementsB.

    Verify ScopeC. Control Scope

    D. Define ScopeE. Create WBS

  • 7/28/2019 Question SetPMP No 4

    5/44

  • 7/28/2019 Question SetPMP No 4

    6/44

    PMP Mock Examination- Wishing You Success!!!

    E. A and D.

    (Question 20) Change requests can occur due to:

    A. An external event such as a change in government regulationB. An error or omission in defining the scope of the productC. An error or omission in defining the scope of the projectD. A and C OnlyE. All of the above

    (Question 21) A project plan is:

    A. A formal, approved document used to guide both project execution and project controlB. A document issued by senior management that provides the project manager with the authorityto apply organizational resources to project activities

    C. A narrative description of products or services to be suppliedD. A document describing the organizational breakdown structure of the company

    (Question 22) Which of the following is NOT an example of a type of schedule report?

    A. Gantt chartB.

    Milestone chartC. Fishbone diagram

    D. Network diagram

    (Question 23) The most important criteria in selecting project selection method is:-

    A. Cost of using itB. Available expertiseC. CapabilityD.

    Reality based on Business Situation

    (Question 24) What is Team Development?

    A. Setting up a team of people with the skills set that are requiredB. Sending you project team to a Conference

  • 7/28/2019 Question SetPMP No 4

    7/44

    PMP Mock Examination- Wishing You Success!!!

    C. Motivating your project team membersD. Enhancing the ability of stakeholders to contribute as individualsE. Enhancing the ability of the team to function as a team

    (Question 25) Three major processes in Project Human Resource Management:

    A. Staff recruitment, project staff planning and team buildingB. Develop HR Plan, Acquire Project Team, Develop Project TeamC. Rewarding, salary reviews and penaltiesD. Staff acquisition, staff training, staff deployment

    (Question 26) A project is defined as:

    A. A process of considerable scope that implements a plan.B. An endeavor, which is planned, executed, and controlled; performed by people; and constrained

    by limited resources.

    C. A temporary endeavor undertaken to create a unique product or service.D. An objective based effort of temporary nature.

    (Question 27) General management encompasses:

    A.

    Planning, organizing, staffing, executing, and controlling the operations of an ongoing enterpriseB. Business policy, financial management, business economics, contract administration, and legalservices necessary for operating an enterprise

    C. Business strategy, planning and controlling, organizational behavior, procurement, and personneladministration required for managing the ongoing aspect of a business venture

    D. Organizational development, staffing, marketing and sales, procurement, and contractadministration as part of an ongoing organization

    (Question 28) Project management processes can be organized into:

    A. Initiating, planning, contracting, executing, and administrationB. Designing, developing, testing, and implementingC. Initiating, designing, planning, executing, controlling, and implementationD. Initiating, planning, executing, controlling, and closing

  • 7/28/2019 Question SetPMP No 4

    8/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 29) ___________ must be measured regularly to identify variance from the plan.

    A. Stakeholder requirementsB. Project performanceC. Schedule progressD.

    Cost and schedule

    (Question 30) A project kick off meeting is usually conducted to:

    A. Setup project team and announce the Project Manager assignmentB. To draft project charterC. Build up team spiritD. Define project scope and develop WBS

    (Question 31) Which of the following is generally not considered an external-unpredictable risk?

    A. Changes in government regulationsB. Natural hazardsC. Unexpected environmental side effectsD. Inflation

    (Question 32) Maslow ranked Human needs from the highest to lowest:

    A. Self actualization; self promotion; social; security and physiological needsB. Self esteem; self actualization; social; security and physiologicalC. Self actualization; self esteem; social; security and physiologicalD. Self fullfilment; self esteem; social; security and physiological

    (Question 33) Which of the following statements concerning contract type is correct?

    A.

    A fixed price contract contains the most risk for the buyerB. Cost reimbursable contracts offer sellers the highest profit potentialC. Lump sum contracts offer sellers the greatest profit potentialD. Unit price contracts are illegal in many jurisdictions

  • 7/28/2019 Question SetPMP No 4

    9/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 34) Herzberg identified factors, which, if present, will lead to increased motivation. A typical

    factor would be:

    A. Good supervisionB. Job securityC.

    Regular promotionsD. Good salary

    E. A dental plan

    (Question 35) Your customer ask for a small change in the project, which was not budgeted in the

    project. It is a small effort as compared to the total project and you need the goodwill for a multimillion

    dollar on the pipeline. You will

    A. Refuse to do the workB. Agree to do the work at no chargeC. Do the work and bill him laterD. Assess the cost and schedule impact and tell them you will decide later

    (Question 36) You are responsible for ensuring that your seller's performance meets contractual

    requirements. For effective Contract Administration, you should:

    A. Hold a bidders conferenceB. Establish the appropriate contract typeC. Implement the contract change control systemD. Develop a statement of work

    (Question 37) The three major causes of change on a project are:

    A. Replacement of the project manager or key project team members; changes in priorities by seniormanagement; and contractual difficulties.

    B. Changes in the relative importance of time, resources, or cost ; new knowledge about thedeliverable; and technological uncertainty

    C. Errors in the initial assessment of how to achieve the goal of the project; new information aboutthe project deliverable; and a new mandate

    D. Unavailability of resources promised by the functional managers; cost overruns; and changes incustomer requirements

    (Question 38) The purpose of the review of deliverables and project performance at the conclusion of a

    project phase is to:

  • 7/28/2019 Question SetPMP No 4

    10/44

    PMP Mock Examination- Wishing You Success!!!

    A. Determine how many resources are required to complete the project according to the projectbaseline

    B. Adjust the schedule and cost baselines based on past performanceC. Obtain customer acceptance of project deliverablesD. Determine whether the project should continue to the next phase

    (Question 39) Your project is in the final test stage, the user acceptance test. It meets all the product

    specs and is under planned costs. In term of schedule, this project is ahead. Your customer meets you

    and requested that he will not accept the product unless you make several changes. What you should do

    is:

    A. Get the list of the changes and estimate all of them. If the total cost is still within the baseline, youjust do it

    B. Estimate the costs and send this to your customer requesting contract modificationC. Ask the customer to file a Change requestD. Sit with the customer to review the product specs and tell him/her that you have completed the

    project.

    (Question 40) The Delphi Method is best suited for:

    A. Decision-makingB. Cost ControlC. Overhead rate estimatingD. Team discussions

    (Question 41) Which of the following methods is least likely to be used for explaining project planning

    guidelines to the team?

    A. Project Office MemoB. Project office directiveC. Project team meetingD. Formal project report

    (Question 42) Projects are typically initiated in response of:

    A. Stakeholder's pressureB. Business needsC. Technological obsolescenceD. All of the above

  • 7/28/2019 Question SetPMP No 4

    11/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 43) The party that needs the change resulting from the project, and who will be its custodian

    on completion is the:-

    A. OwnerB. SponsorC. CustomerD. Client

    (Question 44) A document or tool which describes when and how human resources will be brought onto

    and taken off the project team is called a:

    A. Staffing Management PlanB. Responsibility Assignment Matrix (RAM ).C. Organizational Breakdown Structure (OBS).D. Resource Assignment Chart

    (Question 45) In which type of organization is team building likely to be most difficult?

    A. FunctionalB. ProjectizedC. MatrixD.

    None of the above

    (Question 46) A tool which links the project roles and responsibilities to the project scope statement is

    called:

    A. Scope Definition MatrixB. Responsibility Assignment MatrixC. Roles Assignment MatrixD. Project Scope and Roles Matrix

    (Question 47) Which of the following are outputs from the Plan Communications process?

    A. Project recordsB. Communications management planC. Performance reports

  • 7/28/2019 Question SetPMP No 4

    12/44

    PMP Mock Examination- Wishing You Success!!!

    D. Formal acceptance

    (Question 48) The receiver filters messages based on all but the following:

    A. CultureB. SemanticsC. LanguageD. ReligionE. Knowledge

    (Question 49) The sending or conveying of information from one place to another is the process of:

    A. NetworkingB. TransmittingC. EncryptingD. Promoting

    (Question 50) The three major types of communication are:

    A. Written, verbal, and non-verbalB. Verbal, formal documentation, informal documentationC.

    Verbal, written, and graphicD. Verbal, written, and electronic

    (Question 51) All of the following are communication tools EXCEPT:

    A. MemosB. Verbal circulation of a rumorC. VideosD. Body languageE. Inputing data into a spreadsheet

    (Question 52) Communication is the PRIME responsibility of the which of the following role:

  • 7/28/2019 Question SetPMP No 4

    13/44

    PMP Mock Examination- Wishing You Success!!!

    1.Project Manager in a weak matrix2.Project Manager in a projectized environment3.Project Coordinator4.Project Expeditor

    (Question 53) What are the four elements of the communications model?

    A. Sending, Receiving, Decoding, and ComprehendingB. Sender, Message, Medium, ReceiverC. Communicator, Message, Receiver, DecoderD. Communicating, Transmitting, Receiving, Comprehending

    (Question 54) In negotiating with functional department managers, project managers often findthemselves using what two-party conflict management approach?

    1.Win-Lose2.Win-Win3.Lose-Lose4.None of the above

    (Question 55) A leadership style in which the project manager shares problems with team members and

    formulates solutions as a group is called:

    A. AutocraticB. Consultation in a groupC. ConsensusD. One-to-one consultation

    (Question 56) A type of organization in which the project manager is most likely to have the strongest

    influence is called:

    1.Functional2.Weak matrix3.Strong Matrix4.Projectized

  • 7/28/2019 Question SetPMP No 4

    14/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 57) Create WBS process belongs to:

    A. Initiation Process GroupB. Planning Process GroupC. Executing Process GroupD.

    Monitoring & Controlling Process Group

    (Question 58) Project Management processes are:

    A. A series of actions bringing about a result

    B. Concerned with describing and organizing the work of the project

    C. Concerned with specifying and creating the product

    D. Broken into core and non-core processes

    (Question 59) Project Risk Management includes all of the following processes except:

    A. Plan Risk ManagementB. Plan Risk ResponsesC. Monitor and Control Project WorkD. Perform Qualitative Risk AnalysisE. Perform Quantitative Risk Analysis

    (Question 60) Using the PMBOK definition of contingency reserve, which of the following statements

    about contingency reserves is false?

    A. A contigency reserve is a separately planned quantity used to allow for future situations whichmay be planned for only in part

    B. Contigency reserves may be set aside for known unknownsC. Continency reserves may be set aside for unknown unknownsD. Contingency reserves are normally included in the project's cost and schedule baselines

    (Question 61) Which of the following is true about pure risk?

    A. The risk can be deflected or transferred to another party through a contract or insurance policy.B. Pure risks involve the chance of both a profit and a loss.C. No opportunities are associated with pure risk, only losses.D. Both A and C

  • 7/28/2019 Question SetPMP No 4

    15/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 62) A contingency plan is:

    A. A planned response that defines the steps to be taken if an identified risk event should occur.B. A workaroundC. A reserve used to allow for future situations which may be planned for only in part.D.

    Both A and CE. Both A and B

    (Question 63) Deflection or transfer of a risk to another party is part of which of the following risk

    response categories?

    A. MitigationB. AcceptanceC. AvoidanceD. Analysis

    (Question 64) Management reserves are used to handle which type of risk?

    A. Unknown unknownsB. Known unknownsC. business risksD. pure risks

    (Question 65) Which of the following is considered during the Procurement Planning Process?

    A. Whether to procureB. How to procure and how much to procureC. What and when to procureD. Both b and cE. All of the above

    (Question 66) From a buyer's standpoint, which of the following is true?

    A. Procurement planning should include consideration of potential subcontractsB. Procurement planning does not include consideration of potential subcontracts since this is the

    duty of the contractor.

    C. Subcontractors are first considered during the Conduct Procurement ProcessD. none of the above

  • 7/28/2019 Question SetPMP No 4

    16/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 67) Which of the following is true about procurement documents?

    A. Procurement documents are used to solicit proposals from prospective sellers.B. Invitation for Bid and Request for Proposal are two examples of procurement documents.C. Procurement documents should be structured to facilitate accurate and complete responses from

    prospective sellers.D. Both b and cE. All of the above

    (Question 68) Which of the following is a method for quantifying qualitative data in order to minimize

    the effect of personal prejudice on source selection?

    A. Weighting systemB. Screening systemC. Selecting systemD. none of the aboveE. all of the above

    (Question 69) Which of the following are examples of indirect costs?

    A. Salaries of corporate executivesB. Salaries of full-time project staffC. Overhead costsD. Both a and bE. Both a and c

    (Question 70) Which of the following contract types places the greatest risk on the seller?

    A. Cost-plus-fixed-fee contractB. Cost plus-incentive-fee contractC. Fixed-price-incentive contractD. Firm-fixed-price contract

    (Question 71) In which of the following contract types is the seller's profit limited?

    A. Cost-plus-percentage-cost contractB. Cost-plus-fixed-fee contractC. Fixed-price-plus-incentive

  • 7/28/2019 Question SetPMP No 4

    17/44

    PMP Mock Examination- Wishing You Success!!!

    D. Both b and cE. None of the above

    (Question 72) A cost-plus-percentage-cost (CPPC Contract) has an estimated cost of $120,000 with anagreed profit of 10% of the costs. The actual cost of the project is $130,000. What is the total

    reimbursement to the seller?

    A. $143,000B. $142,000C. $140,000D. $132,000

    (Question 73) A fixed-price-plus-incentive-fee (FPI) contract has a target cost of $130,000, a target profitof $15,000, a target price of $145,000, a ceiling price of $160,000, and a share ratio of 80/20. The actual

    cost of the project was $150,000. How much profit does the seller make?

    A. $10,000B. $15,000C. $0D. $5,000

    (Question 74) Under what circumstances is it better for a contractor to subcontract?

    A. The subcontractor possesses special technical and engineering skills that the contractor does nothave.

    B. The work to be subcontracted represents almost all of the overall work effort.C. The subcontractor can perform the work at a lower cost than the contractor.D. All the aboveE. Both a and c

    (Question 75) Which type of bilateral contract is used for high dollar, standard items?

    A. Purchase orderB. Request for proposal (RFP)C. Invitation for bid (IFB)D. Request for quotation (RFQ)E. all of them are appropriate

  • 7/28/2019 Question SetPMP No 4

    18/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 76) In which stage of the negotiation meeting are points of concession identified?

    1.Probing2.Closure3.Agreement4.

    Scratch bargaining

    (Question 77) Which of the following is generally NOT a method of government procurement?

    A. AssistanceB. Sealed BiddingC. Competitive proposalsD. Acquisition

    (Question 78) The "rule of seven" as applied to process control charts means that :

    A. Seven rejects typically occur per thousand inspectionsB. Seven consecutive points are the same side of the mean or they trend in the same direction, they

    should be investigated

    C. At least seven inspectors should be in place for every thousand employeesD. A process is not out of control even though seven measurements fall outside the lower and upper

    control limits

    (Question 79) A narrative description of products or services to be supplied under contract is called:

    A. The project planB. A statement of workC. An exception reportD. Pareto analysis

    (Question80) A collection of generally sequential project phases whose name and number are

    determined by the control needs of the organization or organizations involved in the project, is called:

    A. Project life cycleB. Product life cycleC. Project life eventD. All of the above

  • 7/28/2019 Question SetPMP No 4

    19/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 81) A precise description of a physical item, procedure, or service for implementation of an

    item or service is called a:

    A. Work packageB. BaselineC.

    Product descriptionD. Work breakdown structure (WBS) element

    (Question 82) Acontractor is working on a fixed price contract that calls for a single, lump sum payment

    upon satisfactory completion of the contract. About halfway through the contract, the contractors

    project manager informs their contract administrator that financial problems are making it difficult for

    them to pay their employees and subcontractors. The contractor asks for a partial payment for work

    accomplished. Which of the following actions by the buyer is most likely to cause problems for the

    project?

    A. Starting partial payments for work accomplished.B. Making no payments because it would violate the conditions of the contract.C. Paying for work accomplished to date.D. Negotiating a change to the payment conditions in the contract.

    (Question 83) Three Point Statistical Estimating Formula Group. Expected Value =

    1.(Optimistic + (4 X Most Likely) + Pessimistic ) x 62.(Optimistic + (4 X Most Likely) + Pessimistic ) divided by 63.(Optimistic + (4 X Most Likely) x Pessimistic ) divided by 64.(Optimistic + (4 + Most Likely) + Pessimistic ) divided by 6

    (Question 84) Two Point Delphi Estimate, The Best and Worst Case effort calculation:

    1.Calculate (Best + Worst) / 22.Calculate (Best +2 ) / Worst3.Calculate (2 + Worst) / Best4.none of the above

    (Question 85) A Work Breakdown Structure (WBS) numbering system should allow project staff to:

    A. Identify the level at which individual WBS elements are found.B. Identify configuration management milestones.C. Estimate the costs of WBS elements.

  • 7/28/2019 Question SetPMP No 4

    20/44

    PMP Mock Examination- Wishing You Success!!!

    D. Provide project justification

    (Question 86) Responses to risk threats include all of the following except:

    A. AvoidanceB. AcceptanceC. MitigationD. Rejection

    (Question 87) Rearranging resources so that constant resource levels are maintained is called:

    A. FloatingB. LevelingC. RestructuringD. Crashing

    (Question 88) ________ implies that every project has a definite beginning and a definite end.

    A. OverallB. Project ChartC. TemporaryD. Duration

    (Question 89) The smallest unit of time used in scheduling the project is known as:

    A. Calendar UnitB. Scope unitC. Time MeasurementD. All of the Above

    (Question 90) Who should be involved in the project planning phase?

    A. The Project Manager.B. The customer.C. The Sub-contractors/vendors.D. The project team members.E. All of the above.

    (Question 91) The successful project managers spend most of their time:

  • 7/28/2019 Question SetPMP No 4

    21/44

    PMP Mock Examination- Wishing You Success!!!

    A. Planning with their personnelB. Planning with top managementC. Communicating with project personnelD. Studying project results

    (Question 92) Cost Plus Percentage of Cost (CPPC) contracts provide:

    A. A reimbursement of allowable cost of services performed plus an agreed upon percentage of theestimated cost as profit.

    B. A reimbursement of allowable costs plus a fixed fee which is paid proportionately as the contractprogresses.

    C. The supplier with a fixed price for a delivered performance plus a predetermined fee for superiorperformance.

    D. None of the above.

    (Question 93) An example of Verify Scope Process is:

    A. Reviewing the performance of an installed software moduleB. Managing changes to the project scheduleC. Decomposing the WBS to a work package levelD. Performing a benefit/cost analysis to determine if we should proceed with the project

    (Question 94) All of the following are contract types except:

    A. Unit-priceB. Make-or-buy.C. Cost reimbursable.D. Lump sum.

    (Question 95) The process of performance reporting includes all of the following except:

    A. Status reportingB. Progress reportingC. ForecastingD. Product analysis.

    (Question 96) Pareto Analysis, cause and effect diagrams and flow charts are used in Quality..

    A. ControlB. AssurancesC. PlanningD. Verification

  • 7/28/2019 Question SetPMP No 4

    22/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 97) Interviews, Focus Groups, Facilitated Workshops, Observations, Prototypes are typically

    used in . Process of Project Scope Management: -

    A. Verify ScopeB. Define ScopeC.

    Collect RequirementsD. Control Scope

    (Question 98) All of the following are outputs of Estimate Activity Resources Process except:

    A. Activity Resource RequirementsB. Resource Breakdown StructureC. Activity ListD. Project Document Updates

    (Question 99) The contemporary view of conflict is that:

    A. Conflict is badB. Conflict is caused by trouble makersC. Conflict should be avoidedD. Conflict can often be beneficialE. A, B and C

    (Question 100) In general a project charter covers: -

    A. Project justification, background, scope, objectives, available resources, organizationalresponsibilities, a project schedule, estimates, procurement schedule, and any imitations that top

    management wants to apply.

    B. Project justification, background, scope, objectives, available resources, organizationalresponsibilities, detailed project schedules, estimates, and detailed procurement schedules

    responsibilities, a project schedule, and any limitations that top management wants to apply.

    C. Project justification, background, scope, objectives, available resources, organizational apply.D. Project scope, objectives, available resources, responsibilities, a project schedule, estimates,

    procurement schedules, and any limitations that top management wants to apply.

    (Question 101) A project manager has increased project costs by US $75,000, but completed the project

    six weeks earlier than planned. What tool is best described here?

    A. Resource levelingB. Duration compression

  • 7/28/2019 Question SetPMP No 4

    23/44

    PMP Mock Examination- Wishing You Success!!!

    C. CrashingD. Fast tracking

    (Question 102) Which of the following statements concerning contract type is correct?

    A. A fixed price contract contains the most risk for the buyerB. Cost reimbursable contracts offer sellers the highest profit potential.C. Lump sum contracts offer sellers the greatest profit potential.D. Unit price contracts are illegal in many jurisdictions.

    (Question 103) All except the following are inputs to Define Activities Process:-

    A. Scope BaselineB. Enterprise Environmental FactorsC. Organizational Process AssetsD. Activity Attributes

    (Question 104) The behavioral responsibilities of a project manager may also include dealing with:

    A. Regulatory PersonnelB. The legal environmentC. Environmental IssuesD. All of the above

    (Question 105) The major purpose of project status reports is to:

    A. Organize and summarize the information so that all stakeholders were informedB. Inform upper management of the project problemsC. Inform the client about the changes that have completedD. Provide information to management and client

    (Question 106) Most project management leadership theories focus on all of the following except :

    A. Personal characteristics of the project managerB. Personality traits of the subordinatesC. Behavioral styles of the project managerD. Usefulness of authority and power and leadership

  • 7/28/2019 Question SetPMP No 4

    24/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 107) Project Charter is developed during the______ phase of the project:

    A. InitiatingB. PlanningC. ExecutingD. Closing

    (Question 108) Historical records during close-out are useful to __________ and ____________ for

    future projects:

    A. Predict trends, highlight problemsB. Analyze successes, shortfallsC. Analyze strengths, document resultsD. Justify results, set standards

    (Question 109) Your client informs that his company has a problem with the current design specs of

    your product and how it will interface with the existing systems. If this occurs, it could be a major

    problem for your project. The client is coming to your office in one week to discuss the problem and to

    see what your team can do to overcome this setback. All previous meetings were informal with this

    client, but now he wants a formal meeting. What should you do to prepare for this meeting ?

    A.

    Update the schedules and assume an active role since the client has not given you the specifics ofthe potential problem

    B. Make sure that the team has increased productivity so the client can see how efficient your teamis performing

    C. Assemble the team and ask them to prepare an agenda and/or questions for topics to bediscussed

    D. Make sure that each team member has his assignment in preparation for any handouts andneeded plans

    (Question 110) In some cases, contract termination refers to:-

    A. Contract Close Out by Mutual Agreement/ArbitrationB. Contract Close Out by delivery of goods and/or servicesC. Contract Close Out by successful performanceD. Certification of receipt of final payment

    (Question 111) A document that formally recognizes the existence of a project is a :

  • 7/28/2019 Question SetPMP No 4

    25/44

    PMP Mock Examination- Wishing You Success!!!

    A. Gantt ChartB. WBSC. Project CharterD. Scope statement

    (112) All of the following elements must be present in the written contract to make it legally enforceable

    except:-

    A. Mutual StructureB. Legal CapacityC. Pricing StructureD. Appropriate Capacity

    (Question 113) Reducing the impact of a risk event by reducing the possibility of its occurrence is:

    A. Risk avoidanceB. Risk acceptanceC. Risk mitigationD. Contingency planning

    (Question 114) In which of the following project management process groups are the most time and

    money typically spent?

    A. InitiatingB. PlanningC. ExecutingD. Controlling

    (Question 115)______ recognizes that a project or phase should begin and commits the organization to

    do so:

    A. Initiation Process GroupB. Execution Process GroupC. Scoping ProcessD. Planning process

  • 7/28/2019 Question SetPMP No 4

    26/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 116) A supplier has withdrawn from your project. A new supplier has been retained. His labor

    forces are due to arrive at the job site tomorrow. At the very outset, You should:-

    A. Meet with the supplier and his forces and establish yourself as the authority in charge.B. Bring your team in for introductions and establish a communications exchangeC.

    Bring out the communication management planD. Bring out the project plan

    (Question 117) A new project manager is about to begin creating the project's scope of work. One

    stakeholder wants to add many items to the scope of work. Another stakeholder only wants to describe

    the functional requirements. The project is important for the project manager's company but a seller

    will do the work. Which of the following would you advise the project manager to do?

    A. The scope of work should be general to allow the seller to make its own decisions.B. The scope of work should be general to allow clarification later.C. The scope of work should be detailed to allow clarifications later.D. The scope of work should be as detailed as necessary for the type of project.

    (Question 118) After the kickoff meeting, two team members engage in a casual conversation about the

    project objectives and deliverables. It is clear they heard different messages during the meeting. One

    member is so adamant that the other member gives up arguing the point. After talking to the project

    manager, the second member confirms that the first member is mistaken. At this point, what is the BEST

    course of action?

    A. The second team member should send the other team member an e-mail describing what hediscovered.

    B. At the next project meeting, the team member should ask the mistaken team member to describehis interpretation so the project manager can get everyone on the same page.

    C. The project manager should send out an e-mail to the team restating the project objectives anddeliverables.

    D. At the next project meeting, the project manager should spend time reviewing a documentedscope statement with the goal of identifying this and other false assumptions.

    (Question 119) During project execution, a project team delivers a project deliverable to the customer.However, the customer neither acknowledges the deliverable nor says if it is acceptable, although an

    approval is required. What is the BEST thing to do?

    A. Continue with the projectB. Document the situationC. Contact and seek managements interventionD. Call a meeting of the team

  • 7/28/2019 Question SetPMP No 4

    27/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 120) You are managing a six months project and have held bi-weekly meetings with your

    project sponsors. After five-and-a-half months of work, the project is on schedule and budget, but the

    sponsors are not satisfied with the deliverables. This situation will delay the project completion by one

    month. The MOST important process that could have prevented this situation is:

    A.

    Monitor and Control RisksB. Control ScheduleC. Define ScopeD. None of the above

    (Question 121) When you are closing out a project, the most critical activity that must you perform is

    A. Perform project feedback on the teamB. Obtain sign off from the customerC. Review project documentation for completenessD. Update the project plans

    (Question 122) Financial controls that need to be considered for project plan development do not

    include:

    A. Time reportingB. Standard contract provisionsC. Process auditsD. Accounting codes

    (Question 123) A project manager has been working on a project for six months with the same team yet

    the team still shows a lack of support for the project. The best thing for the project manager to do would

    be to?

    A. Re-evaluate the effectiveness of the reward system put in placeB. Talk to each team member's bossC. Re-plan the projectD. Tell the team he needs its support

    (Question 124) A project has several teams. Team C has repeatedly missed several deadlines in the past

    causing Team D to have to crash the critical path several times. As the project leader for Team D, what

    should you do?

  • 7/28/2019 Question SetPMP No 4

    28/44

    PMP Mock Examination- Wishing You Success!!!

    A. Meet with management aloneB. Meet with the project manager aloneC. Meet with the project manager and managementD. Meet with the project manager and the team C leader and sensitize them about the whole

    situation

    (Question 125) The current update to the schedule performance report shows no schedule variance.

    Based upon the reporting, you have told the client that the project is on time. However, your team

    members know that a major milestone is about to be missed and that the project will not meet its

    startup date. This is an indication of poor?

    A. Communication Management PlanningB. Scope management planningC. Team trustD. Schedule planning

    (Question 126) A project manager is assigned a project with a team that has already been selected. The

    first thing the project manager should find out about the team is?

    A. What is each team member's favorite colorB. Each team member's objectives for working on the projectC. A list of each team member's tasksD. Each team member's role in the project plan

    (Question 127) An advisor to a new project manager tells the project manager to create lessons learned

    document at the end of a project. A lessons learned document most important element is -:

    A. Any variance and the cause/causes of the varianceB. Reports from the customerC. Reports from managementD. A list of all the plans

    (Question 128) The most crucial time for project risk assessment is:

    A. When a problem surfacesB. During the planning phaseC. During the close-out phaseD. After the project schedule has been published.

  • 7/28/2019 Question SetPMP No 4

    29/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 129) The project is completed and the final deliverable given to the customer but the

    customer refuses to take any action to give final acceptance on the project. The project manager

    should?

    A. Repeatedly ask for final acceptanceB.

    Ask the team for assistanceC. Document the situation and seek Senior Managements Intervention

    D. Do nothing because there is nothing that can be done

    (130) Your new product development project has resulted in a highly successful new product. The

    property, equipment, materials, and personnel of your project are now being integrated into the

    functional organization. Your project is being terminated by:

    A. ExtinctionB. AdditionC. IntegrationD. Starvation

    (Question 131) One common way to compute estimated at completion (EAC) is to take the project

    budgeted-at-completion and:

    A. Divide it by the schedule performance index.B. Multiply it by the schedule performance index.C. Multiply it by the cost performance.D. Divide it by the cost performance index.

    (Question 132) All except the following is an output from Create WBS Process:-

    A. WBSB. WBS DictionaryC. Scope BaselineD. Project Scope Statement

    (Question 133) Ultimate responsibility for quality management in the project rests with the?

    A. Project engineerB. Purchasing agentC. Quality managerD. Team members

  • 7/28/2019 Question SetPMP No 4

    30/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 134) Design of experiments is an analytical technique that:-

    A. identifies which variables have the most influence on a quality outcomeB. identifies which variables have the least influence on a quality outcomeC. determines what a quality outcome isD. is a method for research and development

    (Question 135) You are a project manager for a major information systems project. Someone from the

    quality department comes to see you about beginning a quality audit of your project. The team, already

    under pressure to complete the project as soon as possible, takes objection to the audit. You should

    explain to the team that the primary purpose of a quality audit is?

    A. Part of an ISO 9000 investigationB. To check if the customer is following its quality processC. To identify lessons learned that can improve performance on the projectD. To check the accuracy of the costs submitted by the team

    (Question 136) All of the following are examples of tools often used in Estimate Cost except:

    A. Parametric modelingB. Analogous estimatingC. Bottom-up estimatingD. Activity duration estimates

    (Question 137) The types of power that have substantial influence on both subordinates and upper

    management are:

    A. Formal & expertB. Reward & penaltyC. Expert & referentD. Formal & referent

    (Question 138) Your preferred resource is not available at the time needed. What is the best thing to

    do?

    A. Negotiate with management to get the resourceB. Assess your alternativesC. Begin the task earlyD. Use reserves to increase resources assigned to those tasks.

  • 7/28/2019 Question SetPMP No 4

    31/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 139) In a project your are working, An important piece of hardware will be late. What is the

    first thing to do?

    A. Discuss with team to arrive at a workaroundB. Use schedule reservesC. Use alternate vendorD. Go to customer or management

    (Question 140) A project has experienced significant delays due to equipment problems, staff attrition,

    and slow client reviews. The project is 40% complete and has used 60% of the available calendar time.

    What is the FIRST thing you should do?

    A. Re-baseline the schedule to reflect the new dateB. Analyze the critical path activities for potential to fast track or crash the scheduleC. Document the lack of progress and associated issues to managementD. Identify tasks that have required more time than planned

    (Question 141) A functional manager wants to make a change to the time associated with a task, but

    there is not enough reserve to accommodate the change. Who should authorize the change?

    A. Senior managementB.

    The functional managerC. The project manager

    D. The team member performing the work

    (Question 142) During the course of a project you have motivated team members, managed conflict,

    performed personnel administrative functions and negotiated for more resources. These are examples

    of:

    A. General ManagementB. Project Human Resource ManagementC. Project ExecutionD. A Projectized organization

    (Question 143) You have been promoted to Manager, Continuous Process Improvement. Your new

    position:

    1.Is a project because the work will be performed by people

  • 7/28/2019 Question SetPMP No 4

    32/44

    PMP Mock Examination- Wishing You Success!!!

    2.Is not a project because Continuous Process Improvement will most likely continue indefinitely till thetime organization is in business

    3.Is a project because it is constrained by limited resources4.Is a project because improvements must be planned, executed, and controlled

    (Question 144) Which of the following is not a Project Management knowledge area?

    1.Project Quality Management2.Project Procurement Management3.Project Configuration Management4.Project Risk Management

    (Question 145) The state of being totally answerable for the satisfactory completion of a specificassignment is called:

    A. AuthorityB. AccountabilityC. ResponsibilityD. Fiduciary

    (Question 146) You are responsible for the design of Communication Controls for the Genesis Series of

    satellites. Your current assignment is most likely:

    A. Project managementB. Functional managementC. Facility managementD. Program management

    (Question 147) Work packages are used to :

    A.

    Represent units of work at a level where work is performed.B. Distinguish one package from all others assigned to a single functional group.C. Limit work to be performed to relatively short periods of time.D. All of the above.

    (Question 148) Network planning methods(PERT/CPM/PDM):

  • 7/28/2019 Question SetPMP No 4

    33/44

    PMP Mock Examination- Wishing You Success!!!

    A. Are usually too complicated for practical use on most projectsB. Require highly trained specialists for effective useC. Always require computer support to be practicalD. Are based on flow charts and they allow observation of what happens to the project schedule

    when changes occur to a task's start and stop dates

    (Question 149) Earned value can be described as:

    A. The value of the equipment that has been installed as of the current dateB. The sum of the labor costs that have been incurred on the project dateC. A method of measuring project performanceD. A method of measuring the amount of money that has been spent to date

    (Question 150) A role of the change control board is to:

    A. issue change requestsB.represent top management interests in initiating innovationC.review the impact of change requests on project costs, schedule, and specificationsD. schedule changes into PERT networksE.identify new areas of project work

    (Question 151) Perform Quality control is:

    A. Identifying which quality standards are relevant to the project and determining how to satisfythem

    B. Monitoring specific project results to determine if they comply with relevant quality standards andidentifying ways to eliminate causes of unsatisfactory performance

    C. Evaluating overall project performance on a regular basis to provide confidence that the projectwill satisfy the relevant quality standards

    D. Taking action to increase the effectiveness and efficiency of the project so as to provide addedbenefits to both the performing organization and the project customer

    E. Assuming the production of goods that meet the highest standards of luxury

    (Question 152) Cost of quality is a concept that includes:

    A. The cost necessary for ensuring conformance to requirementsB. The life cycle cost of the projectC. All research and development costs related to the projectD. Only the cost of the quality control function

  • 7/28/2019 Question SetPMP No 4

    34/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 153) All except the following are tools to Perform Quality Control:

    A. Cause and Effect DiagramB. Control ChartsC. Flow ChartsD.

    Quality Audits

    (Question 154) Quality assurance is:

    A. Top management's intention regarding qualityB. Functions determining implementation of the quality policyC. Actions to provide confidence of satisfying quality requirementsD. Responsibilities and processes which implement quality managementE. All of the above

    (Question 155) Including a contingency reserve in the project budget is intended to:

    A. Reduce the probability of scope changesB. Increase the probability of scope changesC. Reduce the probability of a cost overrunD. Increase the probability of a cost overrun

    (Question 156) When appointed, a project manager has the inherent forms of legitimate power

    conveyed to him. The three forms of legitimate power are:

    A. absolute, direct, and indictB. direction, coordination, and liaisonC. formal, informal, and persuasiveD. formal, reward, and directE. formal, reward, and penalty

    (Question 157) The five types of conflict resolution are listed below and represent, in general order of

    importance, the methods a project manager should use to manage conflict. The one used most often by

    project managers to resolve conflict is:-

    A. ConfrontationB. CompromiseC. SmoothingD. ForcingE. Withdrawal

  • 7/28/2019 Question SetPMP No 4

    35/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 158) The process of getting a group of diverse individuals to work effectively together as a

    team is the purpose of :-

    A. LeadershipB. Project ManagementC.

    ImplementationD. Team building

    (Question 159) Which contract type should be used by the owner on a high risk project?

    A. Cost plus percentage of costB. Cost plus incentive feeC. Lump sumD. Fixed price plus incentive feeE. C and D

    (Question 160) PMI suggests which of the following behaviors as part of contract negotiations?

    A. Probing, scratching, and small bitesB. Sniffing and smelling (olfactory)C. Touching and caressing (tactile)D. Mind-reading and extra-sensory perceptionE. None of the above

    (Question 161) Project risk is characterized by three factors:

    A. Severity of impact, duration of impact and cost of impactB. Identification, type of risk category and probability of impactC. Risk event, risk probability and the amount at stakeD. Occurrence, frequency and cost

    (Question 162) Name the ethical code you'll be required to adhere to as a PMP:

    A. Project Management Policy of EthicsB. Project Management Professional StandardsC. Project Management Code of Professional Ethics & StandardsD. Project Management Professional Code of Professional Conduct

  • 7/28/2019 Question SetPMP No 4

    36/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 163) Which is not another term for contract?

    A. AgreementB. Purchase OrderC. ProposalD.

    Memorandum of Understanding

    (Question 164) Which of the following situations describes a violation of the PMP Professional Code of

    Conduct ?

    1.Accepting a gift that is within the customary guidelines of the country or province you are currentlyworking in.

    2.Use of confidential information to advance your position or influence a critical decision.3.Complying with laws and regulations of the state or province in which project management servicesare provided

    4.Disclosing information to a customer about a situation that may have an appearance of impropriety.

    (Question 165) You are working in a country where it is customary to exchange gifts between contractor

    and customer. Your company code of conduct clearly states that you cannot accept gifts from any client.

    Failure to accept the gift from this client may result in termination of the contract. The action to take in

    this case would be:

    A. Provide the customer with a copy of your company code of conduct and refuse the gifts.B. Exchange gifts with the customer and keep the exchange confidentialC. Contact your project sponsor and /or your legal office for assistance.D. Ask the project sponsor or project executive to exchange gifts.

    (Question 166) An example of a conflict of interest would be:

    A. As a public official you make a decision about a contract award that will benefit you personallyB. You and a functional manager disagree with a task cost estimateC. Your sponsor decides to cancel your project because it no longer supports the company strategyD. Your personality conflicts with that of a key member of your project team.

    (Question 167) Your project is running out of cash and significant work remains. You are directed by

    senior management to instruct your people to use another project's charge numbers while working on

    your project. You should:

  • 7/28/2019 Question SetPMP No 4

    37/44

    PMP Mock Examination- Wishing You Success!!!

    A. Follow instructionsB. Inform the corporate auditorsC. Understand the background of management's instructions before taking any actionD. Try to close down the project

    (Question 168) Project Managers can contribute to their organization's knowledge base and to the

    profession of project management most effectively by:

    A. Developing and implementing a project review and lessons learned processB. Establishing strict guidelines for protecting intellectual propertyC. Promote the use of ad hoc project managementD. Ensuring that all project plans are developed before the project team is formed

    (Question 169) For a festival, you give your government client a leather brief case. You are in violation of

    the responsibility to:

    A. Comply with the law.B. Comply with regulations.C. Provide accurate information.D. Protect conflict of interest.

    (Question 170) You have just changed jobs and discovered that your new employer routinely violatesOSHA/EPA and affirmative action requirements on projects. You should:

    A. Do nothing; it's not your problemB. Start by asking management if they are aware that regulations are being violatedC. Talk to the corporate legal departmentD. Inform the appropriate government agencies about the violations

    (Question 171) During your assignment as project manager you add a new member to your project

    team. This new team member was recently hired from a competitor and offers to share a substantial

    amount of proprietary information from his previous company.

    This information could put you and your team in a very strong position for future business. You are

    aware of a non-compete clause in the new hire's condition of employment. You should:

    A. Accept the information and agree to keep it confidential between you and the new hire.B. Review the condition of employment with the new hire and advise her to reconsider the offer.

  • 7/28/2019 Question SetPMP No 4

    38/44

    PMP Mock Examination- Wishing You Success!!!

    C. Review the information and only accept only what may have a direct impact on the project'sfinancial status.

    D. Ignore the offer to share and move forward with the project

    (Question 172) Before reporting a perceived violation of an established rule or policy the project

    manager should:

    A. Determine the risks associated with the violationB. Ensure there is a reasonably clear and factual basis for reporting the violationC. Ignore the violation until it actually affects the project resultsD. Convene a committee to review the violation and determine the appropriate response

    (Question 173) A response to a negative risk event is known as a:

    A. Work ItemB. Work PackageC. WorkaroundD. Work breakdown structure

    (Question 174) Perform Qualitative Risk Analysis will be performed under :

    A.

    Initiation Process GroupB. Planning Process GroupC. Executing Process GroupD. Monitoring & Controlling Process Group

    (Question 175) Acquire Project team process will be performed under:

    A. Initiation Process GroupB. Planning Process GroupC.

    Executing Process GroupD. Monitoring & Controlling Process Group

    (Question 176) You are in the process of numerically analyzing the effects of identified risks. Which of the

    following is the LEAST helpful input?

    A. Risk register

  • 7/28/2019 Question SetPMP No 4

    39/44

    PMP Mock Examination- Wishing You Success!!!

    B. Risk management plan

    C. Project schedule management plan

    D. Project scope statement

    E. Risk related contractual agreements

    (Question 177) In a group of 4 members, 1 member has been added. How many communication

    channels are there now :

    A. 5B. 3C. 10D. 20

    (Question 178) Which of the following is not an input to Develop Project Charter:

    A. ContractB. Project Statement of WorkC. Enterprise Environmental FactorsD. Organizational Process AssetsE. Project Management Information System

    (Question 179) Which of the following is a tool used to Create WBS:

    A.

    Organizational Process AssetsB. Work Breakdown Structure TemplatesC. WBS DictionaryD. Configuration Management System

    (Question 180) Which of the following is not an input to Define Activities process:

    A. Scope BaselineB. Organizational Process AssetsC. Enterprise Environmental FactorsD. Work Breakdown Structure

    (Question 181 ) Which of the following is not an output of Estimate Activity Resources:

    A. Activity Resource Requirements

  • 7/28/2019 Question SetPMP No 4

    40/44

    PMP Mock Examination- Wishing You Success!!!

    B. Resource Breakdown StructureC. Requested ChangesD. Resource Management Plan

    (Question 182) Which of the following is a tool used in Estimate Activity Duration:

    A. Analogous EstimatingB. Work Breakdown Structure TemplatesC. Critical Path MethodD. Schedule Network Templates

    (Question 183) Crashing, and Fast tracking are techniques used in the following process:

    A. Develop ScheduleB. Activity DefinitionC. Create WBSD. Resource Allocation

    (Question 184) Which is not a technique used for Estimate Costs :

    A. Analogous EstimatingB.

    Bottom-up EstimatingC. Parametric Estimating

    D. Vendor Bid AnalysisE. Resource Leveling

    (Question 185) Which is not a tool used in Plan Quality Process :

    A. Cost-Benefit AnalysisB. BenchmarkingC.

    Design of ExperimentsD. Cost of Quality (COQ)

    E. Process Analysis

    (Question 186) What are three tools used in Perform Quality Control Process:

  • 7/28/2019 Question SetPMP No 4

    41/44

    PMP Mock Examination- Wishing You Success!!!

    A. Benchmarking, Cost of Quality (COQ) and Cause and Effect DiagramB. Cost of Quality (COQ), Cause and Effect Diagram and Control ChartsC. Control Charts, Flowcharting and Process AnalysisD. Pareto Chart, Control Charts and Cause and Effect Diagram

    (Question 187) Which of the following Human Resource process generates Roles & Responsibilities :

    A. Develop Human Resource PlanB. Acquire Project TeamC. Develop Project TeamD. Manage Project Team

    (Question 188) Co-Location is a techniques which means:

    A. Placing many or all of the most active project team members in the different physical locationsB. Placing many or all of the most active project team members in the same physical location to

    reduce the cost of the project

    C. Performing a complete project at a single locationD. Performing a project at various locations.

    (Question 189) Manage Stakeholders Expectation is a part which of the following Knowledge Areas:

    A. Human Resource ManagementB. Project Time ManagementC. Project Cost ManagementD. Project Communications ManagementE. Project Risk Management

    (Question 190) Which is not correct about a typical Communications Management Plan document:

    A.

    It contains Stakeholder communication requirementsB. It contains Person responsible for communicating the informationC. It contains Frequency of the communication, such as weeklyD. It contains Methods or technologies used to convey the information, such as memoranda, e-mail,

    and/or press releases

    E. It contains total cost required for performing communication.

  • 7/28/2019 Question SetPMP No 4

    42/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 191) Which of the following is not a technique used for Identify Risks:

    A. Checklist AnalysisB. Assumption AnalysisC. SWOT AnalysisD.

    Risk CategorizationE. Expert Judgment

    (Question 192) Which is not a tool used for Report Performance:

    A. Stakeholder AnalysisB. Variance AnalysisC. Forecasting MethodsD. Reporting Systems

    (Question 193) Advertising is a technique used in which of the following process:

    A. Select SellersB. Request Seller ResponsesC. Contract AdministrationD. Contract Closure

    (Question 194) Which of the following statements are true regarding cost and schedule variances?

    A. The amount of variance of CV and SV values tend to increase as

    the project reaches completion

    B. The amount of variance of CV and SV values remain the same as

    the project reaches completion

    C. Schedule variance will ultimately equal to cost variance when

    project is completed

    D. The amount of variance of CV and SV values tend to decrease as

    the project reaches completion

    (Question 195) During what phase of project lifecycle is the level of risk and uncertainty is

    the lowest?

    A. Closing

    B. Executing

  • 7/28/2019 Question SetPMP No 4

    43/44

    PMP Mock Examination- Wishing You Success!!!

    C. Initiating

    D. Controlling

    E. Planning

    (Question 196) Which of the following is not correct:

    A. PMO - Program Management Office / Project Management OfficeB. RBS - Resource Breakdown StructureC. RAM - Resource Assignment MatrixD. RFP - Request for ProposalE. TQM - Total Quality Management

    (Question 197) Which of the following statements are false regarding the cost change control system?

    A. It defines the procedures by which the cost baseline may be changes

    B. It defines the approval level necessary for authorizing the changes

    C. It provides information on the project scope and cost performance, such as which budgets have been

    met and which are not.

    D. It should be integrated into the Perform Integrated change control system

    E. Perform Integrated change control system

    (Question 198) Most schedule simulations are based on some form of which of the following?

    A. DelphiB. PERTC. CPMD. Monte Carlo Analysis

    (Question 199) What is critical path?

    A. The shortest path through the network, which represents the longest amount of time in which aproject can be completed.B. The path with zero float.

    C. The longest path through the network, which represents the shortest amount of time in which aproject can be completed.

    D. The path with the most activities with the longest durations.E. b and c

  • 7/28/2019 Question SetPMP No 4

    44/44

    PMP Mock Examination- Wishing You Success!!!

    (Question 200) In the communication process, "noise" is the word used to describe factors and forces

    inhibiting the exchange of information between two or more parties. Noise includes all of the following

    but __________

    1.Culture2.

    Behavior3.Language

    4.Traditional way of doing things5.Loud talking