ADB-loaned Yellow River Flood Management Sector Project RESETTLEMENT M&E MAIN REPORT (No. 7) Henan Huanghe Resettlement Economic Development Company December 2007

Upload: others

Post on 29-Sep-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project

RESETTLEMENT M&E MAIN REPORT (No. 7)

Henan Huanghe Resettlement Economic Development Company

December 2007

Page 2: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

i

Approved: Yang Jianshe

Reviewed: Zhang Hao, Zuo Ping

Task Manager: Zuo Ping

Chief Editor: Chang Quanli

Team Leader: Chang Quanli, Duan Wei, Yun Lu, Jiao Lili, Liu Fengjing

Proofreader: Jiao Lili, Zhao Hua’e, Wang Jianzhong, Liu Fengjing, Yang Tao

Contributors: Cao Jin, Cao Shurong, Chang Quanli, Chen Aiqin, Dong Kunjie, Dun Wei, Duan Yongfeng, Feng Jianmin, Guan Guosheng, Huang Jianqiang, Jiao Lili, Li Li, Li Yang, Liu Fengjing, Liu Peiying, Shen Yanlong, Shi Jianzhu, Sun Fengzhi, Sun Jupei, Wang Jianzhong, Xue Changyu, Yang Jianshe, Yang Tao, Yun Lu, Zhao Huan’e, Zhang Hao, Zuo Ping

Page 3: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

ii

Table of Contents

1. GENERAL ____________________________________________________________1

1.1 Project Brief _____________________________________________________________ 1

1.2 Monitoring and Evaluation_________________________________________________ 1

1.2.1 Completed Subprojects___________________________________________3

1.2.2 Follow-up Monitoring of Subprojects _______________________________3

1.2.3 Reporting _____________________________________________________3

1.3 Land Acquisition and Resettlement __________________________________________ 4

2. COMPENSATION______________________________________________________ 6

2.1 Compensation for Dike, Risky Spot and River Training Subprojects ______________ 6

2.1.1 Compensation Rates for Permanent Land Acquisition___________________6

2.1.2 Compensation Rates for Temporary Land Occupation _________________10

2.1.3 Compensation Rates for Housing__________________________________10

2.1.4 Payment _____________________________________________________11

2.2 Village Platform Subprojects ______________________________________________ 13

2.2.1 Enforcement of Promise Letters___________________________________13

2.2.2 Compensation Rates and Payments ________________________________14

3. LAND ACQUISITION AND ECONOMIC REHABILITATION_______________15

3.1 Land Acquisition ________________________________________________________ 15

3.2 Permanent Land Use for Dike, Risky spot and River Training Subprojects ________ 18

3.2.1 Impacts and Economic Rehabilitation ______________________________18

3.2.2 Temporary Land Occupation and Restoration ________________________21

3.3 Land Use for Village Platform Subprojects and Economic Rehabilitation _________ 21

3.3.1 Permanent Land Use and Economic Rehabilitation____________________21

3.3.2 Temporary Land Occupation and Restoration ________________________23

4. PHYSICAL RELOCATION AND REHABILITATION ______________________24

5. RECONSTRUCTION OF SCHOOLS_____________________________________27

6. REPLACEMENT OF SPECIAL FACILITIES _____________________________ 27

7. INCOME RECOVERY_________________________________________________28

7.1 Selection of Sample Households ____________________________________________ 28

7.2 Income Recovery ________________________________________________________ 30

7.2.1 Completed Subprojects__________________________________________30

7.2.2 Dike and River Training Subprojects _______________________________30

Page 4: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

iii

7.2.3 Village Platform Subprojects _____________________________________31

7.3 Remedy Measures _______________________________________________________ 32

7.4 Analysis of Income Levels _________________________________________________ 34

8. PROTECTION OF RIGHTS AND INTERESTS____________________________35

8.1 Training _______________________________________________________________ 35

8.2 Complaints Management _________________________________________________ 36

8.3 Vulnerable Groups_______________________________________________________ 36

8.4 Willingness to Move______________________________________________________ 37

9. EVALUATION AND RECOMMENDATION ______________________________39

9.1 Experience and Inspiration________________________________________________ 39

9.2 Conclusions_____________________________________________________________ 41

9.3 Problems and Recommendations ___________________________________________ 44

10. RESPONSE TO RELEVANT QUESTIONS IN ADB’S AIDE MEMOIRE ______45

ANNEX 0-1 BASELINE CENSUS AND FOLLOW-UP FOLLOWING RESULTS __48

ANNEX 0-2 APPROVAL & IMPLEMENTATION OF RESETTLEMENT BUDGETS49

ANNEX 0-3 LAND ACQUISITION FOR IMPLEMENTED SUBPROJECTS _____55

Appendixes

Appendix 1 Yuanyang Dike Subproject Resettlement M&E Report

Appendix 2 Puyang Dike Subproject Resettlement M&E Report

Appendix 3 Mudan Dike Subproject Resettlement M&E Report

Appendix 4 Juancheng Dike Subproject Resettlement M&E Report

Appendix 5 Dongpinghu Lake (77) and Dongpinghu Lake (10) Rehabilitation Subproject Resettlement M&E Report

Appendix 6 Village Platform Subproject Resettlement M&E Report

Appendix 7 River Training Subproject Resettlement M&E Report

Page 5: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

1

1. GENERAL

1.1 Project Brief

The ADB-loaned Yellow River Flood Management Sector Project includes 4 components: flood management, flood control works, village flood protection, and project management, involving 19 counties of Jiaozuo, Xinxiang, Zhengzhou, Kaifeng, Puyang (Henan), Heze, Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by the State during the period from 2004 to 2006, including 1.04508 billion RMB (126.37 million USD) ADB loan proceeds and 1.75924 billion RMB water conservancy capitals from the central government. The project includes 47 subprojects altogether, including 11 dikes, 6 village platforms, 15 risky spots and 15 river training works, together with 3 project management schemes1. Refer to the Sketch Map of Subprojects attached hereto.

Henan Huanghe Resettlement Economic Development Company (hereinafter referred to as the “HHREDC”) undertakes external resettlement monitoring and evaluation of all these 47 subprojects. These subprojects have been commenced except for 1 village platform waved.

This total number includes 32 for which both main works and associated structures have been completed, including 8 dike, 15 risky spot and 9 river training subprojects, 3 more than the figure reflected in the last report,. Main works have been completed for the remaining 14, but associated structures or infrastructures are still under construction, including 3 dike, 5 village platform, and 6 river training subprojects.

In addition, 5 dike and 14 risky spot subprojects for which completion reports were prepared as part of the last M&E report have been finally inspected and accepted, 1 dike and 9 river training subprojects initially accepted, and the main works for 5 village platform subprojects taken over. Refer to Table 1 for detailed information.

1.2 Monitoring and Evaluation

Since a baseline census and follow-up rsettlement monitoring activities of the 46 subprojects was started in the first half of 2004, the External Monitor has (1) conducted overall survey of the affected 286 villages and 760 groups, (2) established baseline data for 134 villages, 401 groups, 1,846 households and 8,479 people, with baseline census reports prepared on this basis; and (3) carried out follow-up monitoring of 619 villages, 988 groups, 4,264 households and 19,609 people, with 2-7 M&E reports prepared in both Chinese and English.

This is the 7th M&E, which is performed by 5 M&E groups. Field work was performed in September 2007, including an investigation of the Employers and Implementing Agencies. 1 “State Development & Reform Commission’s Circular Letter about Certifying the Cost Estimate of Preliminary Design

and Summary Cost Estimate of Overall Preliminary Design of the 4th Group of Subprojects under ADB-loaned Yellow River Flood Management Sector Project in Henan” (Ref No. [2006]158).

Page 6: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

2

This M&E includes the 19 subprojects for which completion reports were prepared as part of the Report No. 6 and 27 for which overall-follow-up monitoring was conducted this time (refer to Table 1), covering a total number of 117 villages, 176 groups, 317 households and 1,473 people (refer to Table 2), respectively 3, 4, 41 and 186 more than the figures covered by the last report. Annex 0-1 provides more detailed information on the baseline census and follow-up monitoring of 46 subprojects.

Table 1 Progress of Project Implementation*

No. Type Subproject Group Main Works/ Village Platform

Associated Works/ Infrastructure

Stage of Acceptance Remarks

1 Kaifeng 1 Completed Completed Final acceptance 2 Lankao (152+600-156+050) 2 Completed Completed Final acceptance 3 Lankao (135+738-138+400) 3 Completed Completed Final acceptance 4 Dongming 2 Completed Completed Final acceptance 5 Dongpinghu (55+000-77+300) 1 Completed Completed Final acceptance

Monitoring of the aspects not covered by last report

6 Yuanyang 2 Completed Under construction 7 Puyang 3 Completed Under construction 8 Mudan 3 Completed Completed Initial acceptance 9 Juancheng 3 Completed Under construction 10 Dongpinghu (10+471-55+000) 4 Completed Completed 11

Dike

Dongpinghu (77+300-88+400) 4 Completed Completed

Follow-up monitoring

12 Miaozhai 1 Completed - Main works accepted 13 Wuqiu 2 Completed - Main works accepted 14 Lankao 2 Waved 15 Fanxian 2 Completed - Main works accepted 16 Dongming 2 Partly completed Main works accepted 17

Village platform

Pingyin 3 Completed Partly completed Main works accepted

Follow-up monitoring

18 Huayuankou 3 Completed Completed Final acceptance 19 Madu 3 Completed Completed Final acceptance 20 Dongbatou 3 Completed Completed Final acceptance 21 Heigangkou 3 Completed Completed Final acceptance 22 Zhaokou 3 Completed Completed Final acceptance 23 Yangqiao 3 Completed Completed Final acceptance 24 Jiubao 3 Completed Completed Final acceptance 25 Weishan 3 Completed Completed Final acceptance 26 Fanpo 3 Completed Completed Final acceptance 27 Huangzhai 3 Completed Completed Final acceptance 28 Huozhai 3 Completed Completed Final acceptance 29 Baocheng 3 Completed Completed Final acceptance 30 Gaocun 3 Completed Completed Final acceptance 31 Likou 3 Completed Completed Final acceptance 32

Risky spot

Liuzhuang 4 Completed Completed

Monitoring of the aspects not covered by last report

33 Zhangwangzhuang 4 Completed Completed Initial acceptance 34 Dong’an 4 Completed Completed Initial acceptance 35 Laotian’an 4 Completed Completed Initial acceptance 36 Wuzhuang 4 Completed Under construction 37 Mao’an 4 Completed Under construction 38 Shunhejie 4 Completed Under construction 39 Gucheng 4 Completed Under construction 40 Caogang 4 Completed Under construction 41 Taohuayu 4 Completed Completed Initial acceptance 42 Baohezhai 4 Completed Completed Initial acceptance 43 Zhaokou 4 Completed Completed Initial acceptance 44 Weitan 4 Completed Completed Initial acceptance 45 Heigangkou 4 Completed Completed Initial acceptance 46 Fujunsi 4 Completed Completed Initial acceptance 47

River training

Laozhaizhuang 4 Completed Under construction

Follow-up monitoring

*Notes: (1) Data are provided by the External Monitor; (2) “-“ means undetermined.

Page 7: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

3

On the basis of data process and statistical analysis, M&E reports were completed one after another in November and December 2007.

We are hereby extending our sincere thanks to YRCC Project Office and Henan/Shandong Yellow River Engineering Bureau’s Project Office for their great support, local river bureaus and governments for their cooperation, and also international resettlement consultants for their guidance.

Table 2 Summary of Baseline Survey and Follow-up Monitoring Results

Baseline Survey 7th M&E Cumulative Sample Household No. Subproject

Village Group Village Group Home People

Village Group Home People Village Group Home People

Total 46 286 760 134 401 1846 8479 117 176 317 1473 619 988 4264 196091 Dike 191 448 90 223 833 3993 64 86 197 925 420 518 2397 104662 Village Platform 40 172 40 172 967 4280 12 27 70 354 93 278 1689 8712 3 Risky spot 28 57 5 1 2 8 48 78 92 119 4 River Training 27 83 4 6 46 206 36 62 48 186 58 114 86 312

1.2.1 Completed Subprojects

Interim completion reports were prepared for 5 dike and 14 risky spot subprojects as part of the last M&E, altogether 15, namely Kaifeng, Lankao (152), Lankao (135), Dongming, Dongpinghu, Huayuankou, Madu, Dongbatou, Heigangkou, Zhaokou, Yangqiao, Weishan, Fanpo, Huangzhai, Huozhai, Baocheng, Gaocun and Likou. This M&E is mainly interested in the matters not covered by the last M&E, especially the progress of economic rehabilitation.

1.2.2 Follow-up Monitoring of Subprojects

The overall follow-up monitoring covers 27 subprojects in total: Yuanyang, Puyang, Mudan, Juancheng, Dongpinghu (10), Dongpinghu (77), Miaozhai, Wuqiu, Fanxian, Dongming, Pingyin, Zhangwangzhuang, Dong’an, Laotian’an, Wuzhuang, Mao’an, Shunhejie, Gucheng, Caogang, Taohuayu, Baohezhai, Zhaokou, Weitan, Heigangkou, Fujunsi, Laozhaizhuang, and Liuzhuang.

The scope of work mainly includes: compensation rates for main physical indexes, progress of disbursement/payment, permanent land acquisition and economic rehabilitation, temporary land occupation and restoration, physical relocation and resettlement, reconstruction of schools, replacement of special facilities, recovery of incomes, protection of rights and interests, treatment of earlier problems, outstanding problems and recommendations.

1.2.3 Reporting

Since the outset of external monitoring in the first half of 2004, 7 M&E reports have been prepared in Chinese and English, which have been submitted to YRCC’s Project Office and forwarded to ADB thereby.

This M&E Report No. 7 includes a main report and 7 appendixes (subprojects).

Page 8: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

4

The main report, together with 12 appendixes, describes the present M&E in detail, covering all the 46 subprojects commenced, and responds to the questions raised in the ADB mission’s aide memoire dated July 2007. These appendixes are as follows:

Appendix 1 Yuanyang Dike Subproject Resettlement M&E Report

Appendix 2 Puyang Dike Subproject Resettlement M& Completion Report

Appendix 3 Mudan Dike Subproject Resettlement M&E Report

Appendix 4 Juancheng Dike Subproject Resettlement M&E Report

Appendix 5 Dongpinghu (77) and Dongpinghu (10) Risk Spot Subproject Resettlement M&E Report

Appendix 6 Village Platform Subproject Resettlement M&E Report

Appendix 7 River Training Subproject Resettlement M&E Report

This report is submitted to

(1) Executive agency – YRCC’s Project Office (electric file and hard copy);

(2) Lender: ADB (via YRCC’s Project Office);

(3) Henan/Shandong Yellow River Engineering Bureau (via YRCC’s Project Office);

(4) Employer: Local Yellow River Engineering Bureau (via YRCC’s Project Office).

1.3 Land Acquisition and Resettlement

Each subproject has its own Employer, Implementing Agency, Designer and Engineer, which meets the requirements of project management and basically satisfies the demands of land acquisition and resettlement.

The scope of work in land acquisition and resettlement mainly covers the following aspects: land acquisition, physical relocation, school reconstruction, special facility replacement, and payment, etc.

There are 5 village platform subprojects for which the approved budget excludes the direct costs for land acquisition and resettlement, with such costs paid out of the local counterpart funds. The approved budget for land acquisition for 11 dike, 15 risky spot rehabilitation and 15 river training subprojects is 358.7 million RMB, including 329.53 million RMB direct costs. In practice, an additional budget 95.15.38 million RMB was approved, including 29.2638 million RMB as direct costs. To sum up, 453.8537 million RMB has been approved by the time of this M&E, including 358.7938 million RMB direct costs. The completed direct costs amount to 315.8301 million RMB, accounting for 88% of the approved budget. Refer to Table 3. More details on the 41 implemented subprojects with direct costs (5 village platform subprojects not involved) are provided in Annex 0-2 “Approval and Implementation of Resettlement Budgets”.

Page 9: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

5

Table 3 Implementation of Direct Resettlement Costs Unit: 104 RMB, %

Approved Additional Total Completed No. Category Land

Acquisition Direct Cost

Land Acquisition

Direct Cost

Land Acquisition

Direct Cost 6th M%E 7th M&E % of

Total Total 35870 32953 9515.38 2926.38 45385.37 35879.38 25912.23 31583.0 88.0

1 Dike 32009 29413 9481.25 2890.51 41490.25 32303.51 24301.05 28802.79 89.2 2 Risky spot 2302 2113 -1.18 0.57 2300.82 2113.57 1490.41 1670.23 79.0 3 River training 1559 1427 35.3 35.3 1594.3 1462.3 120.78 1109.98 75.9

Permanent land use is involved in 32 of the 46 subprojects commenced, village platform land use in 5 and temporary land use in 45. By the time of this M&E, a total area of 21,946.36 mu has been completed for the permanent/platform use of these 37 subprojects, accounting for 87.2% of the resettlement plan (referred to as the “RP” hereinafter) and 90.3% of the implementation scheme (referred to as the “IS” hereinafter), and 49,151.59 mu for temporary use of these 45 subporjects, taking up 84.5% of the RP and 83.7% of the IS. More details on both permanent and temporary land uses are provided in Annex 0-2 “Land Acquisition for Implemented Subprojects”.

Table 4 Summary of Land Uses for Implemented Subprojects Unit: mu, %

Permanent Land Use No. Subproject Stage Total Subtotal Farmland Temporary Land Use

RP 83369.58 25169.01 19376.32 58200.57 IS 83043.13 24310.34 19157.78 58732.79 Agreement 76019.07 22229.23 18564.97 53789.84 Implementation 71097.95 21946.36 18130.48 49151.59 % of RP 85.3 87.2 93.6 84.5 % of IS 85.6 90.3 94.6 83.7

Total

% of agreement 93.5 98.7 97.7 91.4 RP 55014.95 15538.28 10051.24 39476.67 IS 55989.67 15465.15 10416.01 40524.52 Agreement 54101.98 14207.39 10659.00 39894.59 Implementation 49809.27 14038.85 10377.11 35770.42 % of RP 90.5 90.4 103.2 90.6 % of IS 89.0 90.8 99.6 88.3

1 Dike

% of agreement 92.1 98.8 97.4 89.7 RP 13750.24 4679.51 4646.26 9070.73 IS 13750.24 4679.51 4646.26 9070.73 Agreement 10770 4652.95 4652.95 6117.05 Implementation 10128.5 4652.95 4652.95 5475.55 % of RP 73.7 99.4 100.1 60.4 % of IS 73.7 99.4 100.1 60.4

2 Village platform

% of agreement 94.0 100.0 100.0 89.5 RP 5481.04 498.29 225.89 4982.75 IS 5548.07 528.50 458.33 5019.57 Agreement 4537.7 449.58 333.71 4088.12 Implementation 4653.536 451.80 297.66 4201.74 % of RP 84.9 90.7 131.8 84.3 % of IS 83.9 85.5 64.9 83.7

3 Risky spot

% of agreement 102.6 100.5 89.2 102.8 RP 9123.35 4452.93 4452.93 4670.42 IS 7755.15 3637.18 3637.18 4117.97 Agreement 6609.395 2919.31 2919.31 3690.09 Implementation 6506.645 2802.76 2802.76 3703.89 % of RP 71.3 62.9 62.9 79.3 % of IS 83.9 77.1 77.1 89.9

4 River training

% of agreement 98.4 96.0 96.0 100.4

Note: The land for the use of river training subprojects is totally floodland.

Page 10: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

6

The construction of 6 dike, 4 village platform and 1 river training subprojects involves the relocation of private houses, with 856 households of 45 villages involved in dike subprojects, including 827 resettled in new, bought, borrowed, rent and temporary houses. The village platform subprojects affect 71 households, which have been resettled in various modes.

There are 3 subprojects involving the reconstruction of 4 schools. Liuzhuang in Kaifeng, Xuji and Yantan in Dongming are completed, and Donglou in Puyang is under construction (note: main works are completed at the time of this report).

Special facilities affected by land acquisition are in transport, electricity, communications and water conservancy sectors. Replacement is arranged in line with the progress of construction.

2. COMPENSATION

2.1 Compensation for Dike, Risky Spot and River Training Subprojects

Different compensation rates are used: (1) rates proposed in the RP or the IS; (2) new rates provided by the county government and published in the form of government notice; (3) rates as agreed; (4) and rates adjusted at the time of payment.

2.1.1 Compensation Rates for Permanent Land Acquisition

Among these 46 implemented subprojects, 32 involve permanent land use, mainly including farmland, garden, forestland, and pond. Compensation rates are applied as proposed in the RP, IS, government notices and agreements.

Compensation rates for 22 subprojects are based on the RP or IS, specifically including 5 dike subprojects, Yuanyang, Kaifeng (Kaifeng County only), Puyang, Dongpinghu (55) and Dongpinghu (77), 3 risky spot ones, Heigangkou, Weishan and Fanpo, and 14 river training ones, Zhangwangzhuang, Dong’an, Laotian’an, Wuzhuang, Mao’an, Shunhejie, Gucheng, Caogang, Taohuayu, Baohezhai, Zhaokou, Weitan, Heigangkou and Laozhaizhuang.

Rates are used for 8 subprojects as published in government notices, namely Dongming, Mudan, Juancheng, Huangzhai, Huozhai, Baocheng, Gaocun and Liuzhuang.

Agreed rates are applied to Lankao (152) and Lankao (135). The rates applied to Kaifeng Outskirts are adjusted during implementation. Detailed information is given in Table 5.

The rates proposed in the RP or the IS are not to be discussed herein. Table 6 details the main compensation rates for 10 subprojects, which rates are not used as proposed in the RP or IS, but as published in government notices and stated in agreements in lieu.

As far as farmland compensation rates are concerned, the rates for the permanent land use of 10 subprojects are 7.2-31.1% lower than those proposed in the RP or IS. The main reasons include: (1) other local-financed projects, for which low rates have been approved earlier, are implemented in the subproject areas simultaneously, but uniform rates are used in practice to enable smooth progress and maintain social stability, e.g., Juancheng Dike Subproject; rates

Page 11: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

7

are fixed with reference to local regulations, e.g., rates for Dongming, Mudan and Juancheng are fixed on the basis of annual output values (including both main products and by-products) set forth in the “Approval of Adjusted Land Output Values and Compensation Rates for Appurtenances” by Shandong Bureau of Price and Department of Finance, with Government Notices published accordingly; and (3) account is taken of such factors as price indexes in excess of the RP or IS and other conditions of different types of land.

Table 5 Basis of Permanent Land Compensation Rates

Basis Subproject Yuanyang Kaifeng (Kaifeng County only) Puyang Dongpinghu (55) Dongpinghu (77) Heigangkou Weishan Fanpo Zhangwangzhuang Dong’an Laotian’an Wuzhuang Mao’an Shunhejie Gucheng Caogang Taohuayu Baohezhai Zhaokou Weitan Heigangkou

RP or IS

Laozhaizhuang Dongming Mudan Juancheng Huangzhai Huozhai Baocheng Gaocun

Government notice

Liuzhuang Lankao (152)

Agreement Lankao (135)

Adjustment during implementation Kaifeng (Kaifeng Outskirts only)

Regarding the use of balance resulting from lower compensation rates for permanent land use, action plans have been prepared for 7 of the 10 subprojects, including Dongming, Mudan, Juancheng, Huangzhai, Huozhai, Baocheng and Gaocun, mainly for the purpose of public services such as roads, bridges, canals and streets. The balance of the other 3 subprojects, i.e. Lankao (152), Lankao (135) and Kaifeng (Kaifeng Outskirts) is included in the compensation for appurtenances.

Page 12: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

8

Table 6 Compensation Rates for Permanent Land Acquisition (other than RP/IS rates) IS/RP Implementation Other Conditions Other Conditions

Comparison with IS

No. Subproject Basic Rate (Irrigated) Forestland Garden

(Orchard) Fishpond Lotus Pond

Reed Pond

Basis Basic Rate (Irrigated) Farmland Forestland Garden

(Orchard) Fishpond Lotus Pond

Basic Rate %

1 Mudan 11320 14500

/13300/12100

Notice 10500 Incl. young crops +2000 or+4000

+1000 or+2000 +3000 -820 -7.2

2 Lankao (152) 11350 +1104 +4800 Agreement 10366.5 Incl. young crops +3000 -983.5 -8.7

3 Lankao (135) 11350 +1104 +4800 +5600 +2800 Agreement 10366.5 Incl. young crop -983.5 -8.7

4 Kaifeng (Kaifeng Outskirts Only) 11920 2500 15000 16000 Adjustment 9614

+ 500 for young crops, if any, + attachments, if any 15000 -1806 -15.2

5 Dongming 11330 13430 +5600 +2800 4500 Notice 9050 Incl. young crop +4000 +3000 -2280 -20.1

6 Huangzhai 11330 +5600 4500 Notice 9050 Incl. young crop -2280 -20.1

7 Huozhai 11330 4500 Notice 9050 Incl. young crop -2280 -20.1

8 Baocheng 11330 4500 Notice 9050 Incl. young crop -2280 -20.1

9 Gaocun 11330 4500 Notice 9050 Incl. young crop -2280 -20.1

10 Juancheng 11320 14500 Notice 7200 360 for summer & 240 for autumn crops 5850 -3250 -31.1

Notes: (1) Figures in “IS/RP” are from the IS except for Kaifeng Dike Subproject; (2) “+” means an amount in addition to the basic rate.

Page 13: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

9

Table 7 Compensation Rates for Temporary Land Occupation (other than RP/IS rates) IS Implemented

Rate (RMB/mu.a) No. Subproject Type Irrigated Dryland Floodland

Recovery Other Conditions Basis Basic Rate Other Conditions

Excavation 492 Pumping: 1,700-10,000 RMB/mu depending upon depth 1 Yuanyang Treading

963 69073

2408 Excavation 492 2000 Pumping: plus 2,000 RMB/mu 2 Kaifeng Treading

1160 600 690500

Excavation 492 2000 Pumping: � including farmland restoration, � 1,000 RMB/mu per each meter of additional depth, until a maximum 5,000 RMB/mu 3 Lankao (135)

Treading 1135 670 690

73 493.64

Excavation 492 2000 Pumping: � including farmland restoration, � 1,000 RMB/mu per each meter of additional depth, until a maximum of 5,000 RMB/mu 4 Lankao (152)

Treading 1135 670 690

73 493.64 Excavation 492 1629 5 Dongbatou Treading

1135 69073 493-939.23 � Irrigated land: 939.23 RMB/mu, � floodland: 493.64 RMB/mu

6 Dongpinghu (77) Excavation 1146 670 492

Agreement

3500 Excavation: �depth of 1.3 m, � plus 200 RMB/mu per each additional meter

Excavation 492 1005� Including young crop and land restoration, � pumping: 4,000~9,050 RMB/mu for pond, 345+(660~2000) RMB/mu for fresh floodland, � excavation: 1005+ 1500 RMB/mu 7 Dongming

Treading

1133

690

73 350

Excavation 492 1005 � Including young crop and land restoration, � pumping: plus 1,005 RMB/mu per each meter of depth, generally 6,000 RMB/mu 8 Mudan

Treading 1132 670 690

73

� Irrigated land and dryland: rate × period of occupation

� Floodland: output value for one year, one season or one crop

500 Including young crop and land restoration Excavation 492 1005 Including land restoration 9 Huangzhai Treading

1133 670 73 700 Including land restoration

Excavation 492 1005 Including land restoration 10 Huozhai Treading

1133 670 73 700 Including land restoration

Excavation 492 1005 Including land restoration 11 Baocheng Treading

1133 670 73 700 Including land restoration

Excavation 1133 670 492 1005 Including land restoration 12 Gaocun Treading 73 700 Including land restoration Excavation 492 1005 Including land restoration 13 Liuzhuang Treading

1132 670 73 700 Including land restoration

Treading 73

Government notice

600-350 � Irrigated land: 360 RMB/mu for summer crops, 240 RMB/mu/season for autumn crops per season; � dryland and floodland: 350 RMB/mu/season 14 Juancheng

Excavation 1132

690

492

Basic rate × period of occupation

Adjustment 2300 Including land restoration

Page 14: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

10

2.1.2 Compensation Rates for Temporary Land Occupation

Temporary land use is involved in 11 dike, 14 risky spot (without temporary land use for Heigangkou) and 15 river training subprojects which have been implemented.

According to the IS, temporary land use includes, excavation and treading, both compensated for according to the type of land and the duration of occupation. The rate for irrigated land and dryland is the unit output value per mu timed by the period of occupation, while that for floodland is divided into output value/mu of one year, one season or young crop.

In fact, temporary land use for borrow areas is divided into 2 types, pumping and excavation, with compensations for excavation and treading paid as follows:

(1) 26 using the RP or IS rates, including Puyang, Dongpinghu (55) and Dongpinghu (10) dike subprojects, Huayuankou, Madu, Zhaokou, Yangqiao, Jiubao, Likou, Weishan and Fanpo risky spot subprojects, and 15 river training subprojects;

(2) 8 using the government notice rates, including Dongming, Juancheng and Mudan dike subprojects, Huangzhai, Huozhai, Baocheng, Gaocun and Liuzhuang risky spot ones;

(3) 6 adopting the agreed rates, including Yuanyang, Kaifeng, Lankao (152), Lankao (135) and Dongpinghu dike subprojects, and Dongbatou risky spot subproject;

As seen from Table 7, the period of temporary land use for Dongming, Juancheng and Mudan is generally 1.5 to 2 years. For example, the IS rate for irrigated land is 1,698-2,264 RMB/mu, but 2,300-2,500 RMB/mu is actually applied to excavation and 1,005 RMB/mu.m*depth (m) to pumping, generally a depth of 2 m and amount of 6,000 RMB/mu, and even as high as 9,050 RMB/mu in Dongming, higher than the IS rate. Temporary land use for Huangzhai, Huozhai, Baocheng, Gaocun and Liuzhuang is floodland, which is actually compensated at the rates for irrigated land as published in government notices.

Among the 6 subprojects where agreed rates are adopted, the period of temporary land use for Yuanyang, Kaifeng, Lankao (152), Lankao (135) and Dongpinghu (77) generally ranges from 1 to 2.5 years. For example, the IS rate for irrigated land is 1,160-2,408 RMB/mu, but the rate of 2,000-3,500 RMB/mu is actually adopted as agreed, plus 1,000-2,000 RMB/mu per each additional meter of pumping depth, until a maximum of 10,000 RMB/mu, much higher than the IS. According to the IS, treading is compensated for at most the output value of one year, 963-1,160 RMB/mu for irrigated land and 690 RMB/mu for floodland, but the actual rate is generally timed by the period of use, with a basic rate of 493.64-700 RMB/mu per season, or 987.23-1,400 RMB/mu if less than 2 seasons, not lower than the IS rate.

2.1.3 Compensation Rates for Housing

House relocation is involved in 6 dike and 1 river training subprojects only, i.e. Lankao (135),

Page 15: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

11

Puyang, Dongming, Mudan, Juancheng, Dongpinghu (77) and Laozhaizhuang.

Among these 7 subprojects, Lankao (135), Puyang and Dongpinghu (77) use the rates fixed in the RP or IS, while Dongming, Mudan, Juancheng and Laozhaizhuang use those published in government notices. In Juancheng, the rate for brick-timber housing is further adjusted as appropriate, in the range of 100-240 RMB/m2 according to the height and service life. The balance resulting from the difference between actual rates published in Government Notices and those fixed in the RP is used together with that resulting from the rates for permanent land use, i.e. first to cover the missing/mispresented and underestimated physical indexes before applied to developing public utilities.

Table 8 compares the main house compensation rates for Dongming, Mudan, Juancheng and Laozhaizhuang.

In addition to this, as required in the “Notice of Paying Housing Subsidies to Households” issued by Dongming Project Office’s letter No. 1 (2004), Dongming County has paid to each resettlement family 800 RMB for new house platforms and 200 RMB for temporary housings. In Lankao (135), transportation expenses are partly paid to villages. Temporary subsidies are not paid elsewhere.

Table 8 Main House Compensation Rates for Dongming, Mudan and Juancheng Unit: RMB/m2

Subproject Type RP IS Notice Implemented Remarks Brick-concrete 260 260 220 Brick-timber 220 220 160 Brick-earth 215 215 120 Earth-timber 201 201 80

Dongming

Simple 50 50 50

Notice

Brick-concrete 260 260 220 Notice

Brick-timber 220 220 160 Adjusted Based on height and service life, 100-240 RMB/m2

Auxiliary 163 163 Brick-earth 215 120 Earth-timber 201 201 80

Mudan

Simple 50 50 50

Notice

Brick-concrete 260 260 220 Brick-timber 220 220 160 Auxiliary 163 163 Brick-earth 215 120 Earth-timber 201 201 80

Juancheng & Laozhaizhuang

Simple 50 50 50

Notice

2.1.4 Payment

By the time of this report, a total amount of 315.83 million RMB has been paid for 111 dike, 15 risky spot and 15 river training subprojects, taking up 88% of 358.7938 million RMB direct costs shown in the IS, 56.7077 million more than the figure reported last time, with a balance of 43.0327 RMB. Refer to Table 9 for details.

With an additional payment of 45.0176 million RMB since the last M&E, the cumulative payment for the dike subprojects is 288.0281 million RMB, taking up 89.2% of the sum of

Page 16: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

12

323.0351 million RMB direct costs. In specific, payments for the 5 subprojects for which completion reports have been prepared can be summarized as follows. (1) Dongpinghu (55): There is no additional payment and an outstanding amount of 145,400, including a balance of 86,900 RMB and an additional budget of 58,600 RMB. The cumulative payment takes up 95.9% of the total budget. (2) Kaifeng, Lankao (152) and Lankao (135): There is a separate balance of 942,300, 414,200 and 557,500 RMB, totally paid by the time of this M&E. The additional budget of 775,400 RMB, 220,400 RMB and 217,400 RMB for young crops has not been paid yet. The cumulative payment accounts for 97.3%, 98.2% and 97.7% of the total budget respectively. (3) Dongming: An amount of 17.4051 million RMB has been paid out of the balance of 31.0437 million RMB, plus an additional budget of 3.5822 million RMB for young crops, there is an outstanding amount of 17.7208 million RMB (which is now being implemented). The total budget is completed by 84.6%. With a current payment of 10.8836 million RMB, 6.1393 million RMB, 289.75 million RMB, 0.7625 million RMB, 3.3556 million RMB and 1.77 million RMB, the cumulative payment completed for Yuanyang, Puyang, Mudan, Juancheng, Dongpinghu (77) and Dongpinghu (10) accounts for 96.6%, 94.6%, 77.1%, 50.8%, 98.9% and 100% of the total budgets respectively, with an outstanding amount of 2.5465 million RMB, 1.7741 million RMB, 611.75 million RMB, 589.29 million RMB and 96,600 RMB and none. Refer to Table 9 for details.

With an additional payment of 1.7982 million RMB, the cumulative payment for risky spot subprojects is 16.7023 million RMB, constituting 79% of the total budget. The progress of payment for the 14 subprojects for which completion reports have been prepared is as follows: (1) Huayuankou, Madu, Zhaokou, Yangqiao, Jiubao, Heigangkou, Weishan, Likou and Dongbatou: Payment was finished at the time of the last completion report. (2) Huangzhai, Huozhai, Baocheng and Gaocun: With an additional payment of 1.0598 million RMB, the cumulative payment accounts for 74.3%. (3) Fanpo: There is no additional payment, so the cumulative payment remains 79.2%. (4) Liuzhuang: No payment at the time of the last M&E, but 0.7384 million RMB is paid this time, accounting for 34.8%. Refer to Table 9.

With an additional payment of 9.892 million RMB, the cumulative payment for river training subprojects takes up 75.9% of the total budget, including, 98.3% for Taohuayu, Baohezhai, Zhaokou and Weitan, 78.9% for Wuzhuang, Mao’an, Shunhejie, Gucheng and Caogang, 89.6% for Zhangwangzhuang, Dong’an and Laotian’an, and 39.5% for Laozhaizhuang. Refer to Table 9 for detailed information.

Overrun costs are paid out of the contingencies. Our next M&E will continue to pay attention to the use of balance.

Table 9 Payment of Direct Resettlement Costs (comparison with Report No. 6) Subproject Approved Payment No. Additional Total 6th M&E Increase 7th M&E Balance % of Total

Unit 104 RMB 104 RMB 104 RMB 104 RMB 104 RMB 104 RMB 104 RMB % Total 32953 2926.38 35879.38 25912.23 5670.77 31583.00 4303.27 88.0

1 Dike 29413 2890.51 32303.51 24301.05 4501.76 28802.81 3500.70 89.2 1.1 Yuanyang 7187 271.01 7458.01 6126 1077.36 7203.36 254.65 96.6 1.2 Kaifeng 2563 341.51 2904.5 2732.73 94.23 2826.96 77.54 97.3 1.3 Lankao (152) 1145 68.68 1213.68 1150.22 41.42 1191.64 22.04 98.2 1.4 Lankao (135) 814 119.35 933.35 855.86 55.75 911.61 21.74 97.7 1.5 Puyang 2772 499.81 3271.81 2480.47 613.93 3094.4 177.41 94.6

Page 17: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

13

1.6 Dongming 10223 958.22 11181.22 7718.63 1740.51 9459.14 1722.08 84.6 1.7 Mudan 2506 164.89 2670.89 1769.39 289.75 2059.14 611.75 77.1 1.8 Juancheng 1047 149.68 1196.68 531.14 76.25 607.39 589.29 50.8 1.9 Dongpinghu (55) 99 252.03 351.03 336.49 336.49 14.54 95.9 1.10 Dongpinghu (77) 858 57.34 915.34 570.12 335.56 905.68 9.66 98.9 1.11 Dongpinghu (10) 199 8 207 30 177 207 100.0

2 Risky spot 2113 0.57 2113.57 1490.41 179.82 1670.23 443.34 79.0 2.1 Huayuankou 204 145.61 145.61 2.2 Madu 4.41 208.41 62.86 62.86 -0.06 100.0

2.3 Zhaokou 229 167.65 167.65 2.4 Yangqiao 52.14 52.14 2.5 Jiubao -0.24 228.76

8.98 8.98 -0.01 100.0

2.6 Heigangkou 28 -4.66 23.34 23.35 23.35 -0.01 100.0 2.7 Dongbatou 30 -0.12 29.88 29.84 29.84 0.04 99.9 2.8 Huangzhai 1138 275.01 37.15 312.16 2.9 Huozhai 114.60 6.99 121.59 2.10 Baocheng 196.48 39.04 235.52 2.11 Gaocun

1138

153.78 22.80 176.58

292.15 74.3

2.12 Weishan 183 109.31 110.58 110.58 -1.27 101.2 2.13 Fanpo 0.07 73.76 58.42 58.42 15.34 79.2 2.14 Likou 89 0.77 89.77 91.11 91.11 -1.34 101.5 2.15 Liuzhuang 212 0.34 212.34 73.84 73.84 138.50 34.8

3 River training 1427 35.3 1462.3 120.78 989.20 1109.97 352.33 75.9 3.1 Zhangwangzhuang 145 9.02 98.66 107.68 3.2 Dong’an 17.4 34.40 51.8 3.3 Laotian’an 70.27 215.27

0.73 32.65 33.375 22.42 89.6

3.4 Wuzhuang 539 41.66 41.66 3.5 Mao’an 10.19 52.37 62.56 3.6 Shunhejie 18.81 68.55 87.36 3.7 Gucheng 80.55 80.55 3.8 Caogang

-107 432

68.92 68.92

90.95 78.9

3.9 Taohuayu 343 8 243.78 251.78 3.10 Baohezhai 37.73 37.73 3.11 Zhaokou 17.25 6.81 24.06 3.12 Weitan

26.11 369.11

33.38 15.92 49.30

6.24 98.3

3.13 Heigangkou 59 10.63 10.63 3.14 Fujunsi 2 61 6 44.62 50.62 -0.25 100.4

3.15 Laozhaizhuang 341 43.92 384.92 151.95 151.95 232.97 39.5

2.2 Village Platform Subprojects

2.2.1 Enforcement of Promise Letters

As indicated in Table 10, the total budge of Government investments and ADB loan proceeds for 5 village platform subprojects is 209.38 million RMB, including 27.36 million RMB for Miaozhai, 25.43 million RMB for Wuqiu, 60.64 million RMB for Fanxian, 41.95 million RMB for Dongming and 54 million RMB for Pingyin. The local government is responsible for physical relocation, attachment and young crop compensation, infrastructure construction, and also poor family relocation after the completion of village platforms, but housing in new village platforms is financed by resettlement families themselves.

The Government investments and ADB loan proceeds are used in the process of construction management.

The local government responsibilities include the counterpart funds or measures promised by the provinces, cities, counties and townships involved. The total amount is 49.8704 million RMB, including 36.5 million RMB paid as of this M&E, 5 million RMB more than reported last time.

Provincial counterpart funds: A total amount of 25 million RMB has been promised. The progress of payment remains unchanged, 23.5 million RMB, including 3.5 million RMB of 5

Page 18: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

14

million RMB promised by Henan and 20 million RMB by Shandong.

City/county counterpart funds: The promised total amount of 24.8704 million RMB is paid by 13 million RMB, 5 million RMB more than the progress reported last time. The amount of 1.5 million RMB promised by Puyang for Fanxian was paid in full by the time of the last report. Fanxian has promised 0.5 million RMB but paid 9 million RMB paid actually, i.e. an increase of 2 million RMB. Jinan has paid 9 million RMB of the promised amount of 15 million RMB for Pingyin, 3 million RMB more than the figure reflected in the last report. The amount of 7.8704 million RMB promised by Heze for Dongming has not been paid yet.

Main works for village platforms are totally completed and initial taking over is finished. Plans for new villages are ready, and “Action Plans” are prepared for some village platforms, e.g. Pingyin and Fanxian. But infrastructures are still in the stage of preparation except for Pingyin, where infrastructures are nearly finished and housing in the new village platform is started.

2.2.2 Compensation Rates and Payments

These 5 subprojects involve permanent land use for village platforms, temporary land use for construction purposes, land use for roads, land restoration, appurtenance, house relocation and special facility replacement, with a total amount of 17.7338 million RMB. Due to the difference in socioeconomic conditions, the rates and methods of compensation are different from here to there. To take housing for example, compensation is based on the number of houses in Miaozhai and Wuqiu, the floor area of houses in Dongming, and the number of rooms in Fanxian and Pingyin. The following paragraphs discuss in brief the main physical indexes and compensations (refer to Table 10 and Appendix 10).

In Miaozhai, young crops and appurtenances affected by permanent land use and pumping are not compensated for, with 500 RMB/year for temporary land use for pipes only. The houses relocated as a result of village platform construction are compensated for according to the quality and floor area as agreed with the households. For permanent land use in Mayezhuang, 300 RMB/mu is paid to the affected households as compensation for one crop. In Gaozhuang, flour is provided for farmers by the villager leaders as compensation for young crops. The total amount of compensations for temporary land use for pipes and housings is 230,400 RMB, which 107,000 RMB more than the figure reported last time, mainly for young crops.

Wuqiu compensates for appurtenances only, without compensation for young crops, with an amount of 500 RMB/year for temporary land use for pipes and a lump sum of 4,000 or 5,100 RMB/mu for pumping according to the depth and the agreement. The amount for affected appurtenances, temporary land use for pipes, pumping and housing is 1.2794 million RMB, without any change since the last M&E.

In Fanxian Subproject, 610 RMB/mu is paid for permanent land use for village platforms and young crops each year until the finish of land adjustment, and 600 RMB/mu for excavation until land restoration. In addition, a lump sum of 10 and 50 RMB/mu is paid to townships and villages separately for their cooperation, 200 RMB/mu to households as award for site

Page 19: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

15

clearing and 300 RMB/room as compensation. The total amount of payment is 2.0064 million RMB, including appurtenances, with an addition payment of 54,400 RMB since the last M&E, mostly for appurtenances.

Dongming Subproject pays 650 RMB/mu as compensation for permanent land use for village platform occupation and treading. Compensation for land occupation by village platforms is paid until the completion of land adjustment or resettlement in the new village platform, while that for temporary land use is paid according to the period of occupation, with a lump sum of 1,005 RMB/mu for excavation and 3,000-9,050 RMB/mu for pumping on the basis of depth and agreement. Housings are compensated at the rate published in government notices. Plus the payment for appurtenances, a total amount of 11.2 million RMB has been paid up to date, 2.6765 million RMB more than that shown in the last report, mainly for young crops affected by village platforms.

The rate for Pingyin is based on the season and output value, in the range of 400, 500 and 650 RMB/mu, and duration of compensation determined according to the degree of difficulty in land adjustment. The total payment is 9.2739 million RMB, including an additional amount of 3.4184 million RMB for appurtenances and other entitlements.

Table 10 Budget, Compensation Rates and Payments for Village Platforms

Compensation Rate Payment

Temporary Land Use No. Subproject Budget Permanent

Land Use Treading Excavation Pumping Physical Relocation

Permanent

Land Use

Temporary

Land Use

Physical

Location &

Resettlement

Attachments

& Others Subtotal

Unit RMB/mu RMB/mu RMB/mu RMB/mu RMB 104 RMB 104 RMB 104 RMB 104 RMB 104 RMB

Total 20938 396.11 722.17 48.1 1232.6 2399.01

1 2736 300/200 500 Per house 10.7 3.43 8.91 23.04

2 Wuqiu 2543 500 4000/5100 Per house 81.19 6.04 40.71 127.94

3 Fanxian 6064 610/350 610 860/600 Per room 97.29 86.15 3.21 13.99 200.64

4 Dongming 4195 650 650 1005 3000-9050 Per floor area 288.12 551.4 29.94 250.54 1120

5 Pingyin 5400 400, 500, 650 RMB/mu/season Per room 585.55 585.55

3. LAND ACQUISITION AND ECONOMIC REHABILITATION

3.1 Land Acquisition

As shown in Table 11, the completed total area for permanent use for 10 dike, 8 risky spot and 14 river training subprojects is 21,946.36 mu, accounting for 87.2% of the IS, 1,686.97 mu or 8.3% larger than the area reported last time.

Based on the progress achieved by the Implementing Agencies, there is an additional area of 61.3 mu for Yuanyang, Dongming and Mudan, 1,625.67 mu for 12 river training subprojects, and none for the others. Permanent land acquisition is finished. Refer to Table 11 for details.

The completed temporary land use for 11 dike, 14 risky spot, 15river training subprojects and 5 village platform subprojects is 49,151.59 mu, taking up 84.5% of the RP and 83.7% of the IS, 8,182.97 mu or 20% larger than the area reflected in the last report. This part of work is finished except for Yuanyang, Juancheng, Liuzhuang and river training subprojects. Refer to

Page 20: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

16

Table 11 for details.

Further detailed information on land use for all subprojects is provided in Annex 0-3 “Land Acquisition for Implemented Subprojects”.

Table 11 Progress of Land Acquisition Progress No. Subproject RP IS 6th M&E Increase 7th M&E % of RP % of IS

Unit mu mu mu % mu % mu 1. Permanent land use 25169.01 24310.34 20259.39 1686.97 21946.36 87.2 90.3 1.1 Dike 15538.28 15465.15 13977.55 61.30 14038.85 90.4 90.8 1.1.1 Yuanyang 3672.39 3392.01 2469.13 32.09 2501.22 68.1 73.7 1.1.2 Kaifeng 1410.4 1410.4 1341.03 1341.03 95.1 95.1 1.1.3 Lankao (152) 414 414 360.17 360.17 87.0 87.0 1.1.4 Lankao (135) 358.92 404.33 404.33 404.33 112.7 100.0 1.1.5 Puyang 1363.43 1516.68 1256.2 1256.2 92.1 82.8 1.1.6 Dongming 6370.06 6343.04 6230.54 28.13 6258.67 98.3 98.7 1.1.7 Mudan 1402.55 1274.26 1227.91 1.08 1228.99 87.6 96.4 1.1.8 Juancheng 392.22 392.22 395.76 395.76 100.9 100.9 1.1.9 Dongpinghu (55) 2.71 166.61 158.5 158.5 5848.7 95.1 1.1.10 Dongpinghu (77) 151.6 151.6 133.98 133.98 88.4 88.4 1.1.11 Dongpinghu (10) 1.2 Village platform 4679.51 4679.51 4652.95 4652.95 99.4 99.4 1.2.1 Miaozhai 634.36 634.36 570.23 570.23 89.9 89.9 1.2.2 Wuqiu 597.38 597.38 591.81 591.81 99.1 99.1 1.2.3 Fanxian 1001.76 1001.76 1069.45 1069.45 106.8 106.8 1.2.4 Dongming 1080.35 1080.35 1055.8 1055.8 97.7 97.7 1.2.5 Pingyin 1365.66 1365.66 1365.66 1365.66 100.0 100.01.3 Risky spot 498.29 528.5 451.80 451.80 90.7 85.5 1.3.1 Huayuankou 32.83 32.83 1.3.2 Madu 22.5 22.5 1.3.3 Zhaokou 1.3.4 Yangqiao 0.8 0.8 1.3.5 Jiubao 1.3.6 Heigangkou 13.69 13.69 13.62 13.62 99.5 99.5 1.3.7 Dongbatou 1.3.8 Huangzhai 146.53 146.53 145.95 145.95 99.6 99.6 1.3.9 Huozhai 60.04 60.04 54.404 54.404 90.6 90.6 1.3.10 Baocheng 85.74 92.43 86.852 86.852 101.3 94.0 1.3.11 Gaocun 49.65 49.65 44.26 44.26 89.1 89.1 1.3.12 Weishan 36.66 42.5 44.09 44.09 120.3 103.7 1.3.13 Fanpo 20.54 43.22 43.22 43.22 210.4 100.0 1.3.14 Likou 1.3.15 Liuzhuang 29.31 24.31 19.4 19.4 66.2 79.8 1.4 River training 4452.93 3637.18 1177.09 1625.67 2802.76 62.9 77.1 1.4.1 Zhangwangzhuang 566 566 106.4 459.60 566 100.0 100.0 1.4.2 Dong’an 337.8 337.8 207.87 129.93 337.8 100.0 100.0 1.4.3 Laotian’an 159.93 116.9 10.5 3.40 13.9 8.7 11.9 1.4.4 Wuzhuang 352.47 352.47 56.3 103.78 160.08 45.4 45.4 1.4.5 Mao’an 477.67 477.67 186.62 124.78 311.4 65.2 65.2 1.4.6 Shunhejie 379.09 342.65 227.04 227.04 59.9 66.3 1.4.7 Gucheng 435.7 226.03 189.00 189 43.4 83.6 1.4.8 Caogang 463.72 348.72 127.71 127.71 27.5 36.6

Page 21: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

17

1.4.9 Taohuayu 209.77 80.77 75 -18.00 57 27.2 70.6 1.4.10 Baohezhai 206.37 206.37 206.37 206.37 100.0 100.0 1.4.11 Zhaokou 117 36 32.46 32.46 27.7 90.2 1.4.12 Weitan 431 431 274.9 172.64 447.54 103.8 103.8 1.4.13 Heigangkou 46.98 25.48 25.48 25.48 54.2 100.0 1.4.14 Fujunsi 197.4 1.4.15 Laozhaizhuang 72.03 89.32 100.98 100.98 140.2 113.1 2. Temporary land use 58200.57 58732.79 40968.62 8182.97 49151.59 84.5 83.7 2.1 Dike 39476.67 40524.52 30840.28 4930.14 35770.42 90.6 88.3 2.1.1 Yuanyang 11622.24 12515.42 9720.06 2511.74 12231.80 105.2 97.7 2.1.2 Kaifeng* 5038.69 5061.39 4470.09 445.62 4915.71 97.6 97.1 2.1.3 Lankao (152) 1699.06 2125.06 2114.97 104.78 2219.75 130.6 104.5 2.1.4 Lankao (135) 796.5 796.5 310.55 48.38 358.93 45.1 45.1 2.1.5 Puyang 2300.98 2359.52 937.04 1187.64 2124.68 92.3 90.0 2.1.6 Dongming 13026.7 12605.7 10794 10794.00 82.9 85.6 2.1.7 Mudan 2206.46 2206.46 987.4 171.99 1159.39 52.5 52.5 2.1.8 Juancheng 793.44 793.47 281 69.49 350.49 44.2 44.2 2.1.9 Dongpinghu (55) 328.09 314.23 341.47 341.47 104.1 108.7 2.1.10 Dongpinghu (77) 1524.38 1523.48 883.7 165.32 1049.02 68.8 68.9 2.1.11 Dongpinghu (10) 140.13 223.29 225.18 225.18 160.7 100.8 2.2 Village platform 9070.73 9070.73 5475.55 5475.55 60.4 60.4 2.2.1 Miaozhai 1422.3 1422.3 578.33 578.33 40.7 40.7 2.2.2 Wuqiu 759 759 693.94 693.94 91.4 91.4 2.2.3 Fanxian 2867.57 2867.57 822.92 822.92 28.7 28.7 2.2.4 Dongming 2089.7 2089.7 1448.2 1448.2 69.3 69.3 2.2.5 Pingyin 1932.16 1932.16 1932.16 1932.16 100.0 100.0 2.3 Risky spot 4982.75 5019.57 4140.79 60.95 4201.74 84.3 83.7 2.3.1 Huayuankou 379.26 379.24 369.73 369.73 97.5 97.5 2.3.2 Madu 193.71 193.7 125.37 125.37 64.7 64.7 2.3.3 Zhaokou 364.43 364.43 275.14 275.14 75.5 75.5 2.3.4 Yangqiao 95.7 95.7 85.72 85.72 89.6 89.6 2.3.5 Jiubao 41.2 41.2 27 27 65.5 65.5 2.3.6 Heigangkou 61.82 61.82 2.3.7 Dongbatou 55.5 55.5 62.77 62.77 113.1 113.1 2.3.8 Huangzhai 1128.64 1125.16 1021.91 1021.91 90.5 90.8 2.3.9 Huozhai 412.7 412.58 369.75 369.75 89.6 89.6 2.3.10 Baocheng 603.19 625.75 519.95 519.95 86.2 83.1 2.3.11 Gaocun 494.06 481.25 583.3 583.3 118.1 121.2 2.3.12 Weishan 226.06 217.61 216.4 216.4 95.7 99.4 2.3.13 Fanpo 131.35 127.19 112.11 112.11 85.4 88.1 2.3.14 Likou 174.83 169.14 164.19 164.19 93.9 97.1 2.3.15 Liuzhuang 620.3 669.3 207.45 60.95 268.4 43.3 40.1 2.4 River training 4670.42 4117.97 512 3191.88 3703.89 79.3 89.9 2.4.1 Zhangwangzhuang 73 73 84.3 84.3 115.5 115.5 2.4.2 Dong’an 48 48 48.0 48 100.0 100.0 2.4.3 Laotian’an 323.23 323.23 322.48 322.49 99.8 99.8 2.4.4 Wuzhuang 334.7 334.7 334.7 334.7 100.0 100.0 2.4.5 Mao’an 461.5 461.5 461.5 461.5 100.0 100.0 2.4.6 Shunhejie 200 200 199.7 199.68 99.8 99.8 2.4.7 Gucheng 736.14 736.14 577.3 577.34 78.4 78.4 2.4.8 Caogang 584 584 583.9 583.93 100.0 100.0 2.4.9 Taohuayu 574.2 16.2 30 30 5.2 185.2 2.4.10 Baohezhai 35 35 35.0 35 100.0 100.0 2.4.11 Zhaokou 252.6 252.6 120 130.7 250.69 99.2 99.2

Page 22: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

18

2.4.12 Weitan 70 70 70.0 70 100.0 100.0 2.4.13 Heigangkou 96.59 98.5 112.1 112.14 116.1 113.8 2.4.15 Fujunsi 372.7 378.26 362 16.3 378.3 101.5 100.0 2.4.15 Laozhaizhuang 508.76 506.84 215.8 215.82 42.4 42.6

*Figures before land acquisition are generally based on agreements, while those after are actual areas.

3.2 Permanent Land Use for Dike, Risky spot and River Training Subprojects

3.2.1 Impacts and Economic Rehabilitation

Permanent land use for these subprojects involves a total number of 19,789 households and 85,734 people of 588 groups in 249 villages, where there used to be a per capita farmland area of 0.821-2.814 mu, an average of 1.457 mu. With 10,285.55 mu acquired for permanent use, there is a per capita loss of 0.013-0.331 mu, or an average of 0.12 mu. A loss rate higher than 10% is suffered by 144 groups, all in dike subprojects. Refer to Table 12.

Economic rehabilitation is totally performed within villager groups, with the mode discussed repeatedly and decided as chosen by the majority. There are mainly 3 modes:

(1) Share the money and adjust the land, with land compensation equally shared by all in the group and land adjusted again (referred to “Option A”);

(2) Pay to households directly, without land adjustment (referred to as “Option B”)

(3) Exchange land with land, with public land distributed to land losers and compensation costs retained for public use or equally shared by all (referred to as “Option C”).

As indicated in Table 12, Option A is chosen by 342 of the 588 groups involved in permanent land use, Option B by 201 and Option C by 43, while the rest 2 have not decided the mode due to disagreement of the farmers.

Permanent land use and economic rehabilitation for dike subprojects remain unchanged since the last M&E, involving a total number of 15,399 households and 65,014 people from 448 groups in 181 villages, with a per capita farmland area of 0.822 – 1.825 mu before land acquisition, an average of 1.33 mu, including 8,881.228 mu acquired for permanent use, a per capita loss of 0.013-0.205 mu, or an average 0.137 mu. Option A is adopted by 263 groups, Option B by 158, Option C by 25, but Groups 1 and 7 in Jiatan have not decided due to the failure to achieve disagreement. Payment for young crops is paid out of land compensations. Details are given in Table 12.

The progress in this aspect of 8 risky spot subprojects is the same as reflected in the last report, except for an additional group in Liuzhuang. Permanent land use involves 2,067 households and 10,540 people of 57 groups in 27 villages, with a per capita farmland area of 1.067-2.196 mu or an average of 1.531 mu before land acquisition. With 262.03 mu acquired, the per capita area is reduced by 0.007-0.170 mu, or an average of 0.025 mu. These groups have adopted Option A (45 groups) or C (10 group) except that one involved in Heigangkou and another in Liuzhuang have chosen Option B. See Table 12 for details.

Page 23: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

19

Permanent land use for the 14 river training subprojects is 2,802.76 mu, including 1,142.3 mu contracted land for the use of Dong’an, Wuzhuang, Mao’an, Shunhejie, Weitan, Heigangkou and Laozhaizhuang, totally floodland, involving 2,323 households and 10,180 people from 85 groups in 31 villages, with a per capita loss of 0.036-0.331 mu, or an average of 0112 mu. Table 12 shows that Option A is used by 34, Option B by 41 and Option C by 8.

Page 24: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

20

Table 12 Progress of Permanent Land Use and Economic Rehabilitation Original Involved Mode of Reestablishment

Farmland No. Subproject Village Farmland Group Home People Per Capita Farmland Area

Area Private Group Home People

Per Capita Loss

Loss Rate

>10% Option

A Option

B Option

C To be

decidedRemarks

Unit village mu group home person mu mu mu mu group home person mu group group group group group Total 249 394012 1346 64016 270342 1.457 17293.4 13477.53 10285.55 588 19789 85734 0.120 144 342 201 43 2

1 Dike 181 252407 1003 45981 189783 1.330 14038.9 10377.11 8881.23 448 15399 65014 0.137 144 263 158 25 2 *Young crop per season 1.1 Yuanyang 36 45368 215 8946 38488 1.179 2501.22 1890.58 1350.77 139 3448 15640 0.086 23 58 79 2* 1.2 Kaifeng 15 20085 78 4685 19403 1.035 1341.03 1341.03 1287.03 46 1407 6272 0.205 20 18 28 1.3 Lankao (152) 7 15028 57 3067 13422 1.120 360.17 360.17 280.16 16 415 1781 0.157 3 4 12 1.4 Lankao (135) 4 10863 35 1808 7893 1.376 404.33 354.53 354.53 15 496 2287 0.155 5 15 Incl. mu homestead 1.5 Puyang 12 11352 61 2084 9120 1.245 1256.2 1256.2 1222.30 48 1587 6474 0.189 23 47 1 1.6 Dongming 44 68670 264 10119 41178 1.668 6258.67 3594.5 3165.9 103 4857 19325 0.164 51 85 18 1.7 Juancheng 12 30495 85 4100 16709 1.825 1228.99 1093.5 870 43 1985 8339 0.104 11 39 4 1.8 Mudan 4 2929 21 590 2350 1.246 395.76 293.75 293.75 13 352 1476 0.199 8 12 1 1.9 Dongpinghu (55) 38 41393 139 8572 33647 1.230 158.5 93.15 23.05 15 432 1840 0.013 15 1.10 Dongpinghu (77) 9 6224 48 2010 7573 0.822 133.98 99.7 33.74 10 420 1580 0.021 10 2 Risky spot 27 36523 99 5381 23861 1.531 451.796 297.66 262.03 57 2067 10540 0.025 45 2 10 2.1 Huayuankou 1 980 3 210 723 1.355 13.62 1 2 9 1 2.2 Huangzhai 6 10861 31 1520 5898 1.841 145.95 102.43 102.43 18 740 2871 0.036 18 2.3 Huozhai 3 3037 9 435 2071 1.466 54.404 39.1 39.1 4 220 1047 0.037 4 2.4 Baocheng 2 9360 11 560 4262 2.196 86.852 31.45 31.45 11 560 4262 0.007 11 2.5 Gaocun 4 2912 19 620 2729 1.067 44.26 44.26 44.26 12 429 1888 0.023 12 2.6 Weishan 3 6353 15 1489 5798 1.096 44.09 39.4 34.04 6 49 200 0.170 6 2.7 Fanpo 3 3020 11 547 2380 1.269 43.22 21.62 10.24 4 65 255 0.040 4 2.8 Liuzhuang 5 19.4 19.4 0.51 1 2 8 0.064 1 3 River training 41 105082 244 12654 56698 1.853 2802.76 2802.76 1142.30 83 2323 10180 0.112 34 41 8 3.1 Zhangwangzhuang 4 13950 47 2275 9870 1.413 566 566 All collective land 3.2 Dong’an 5 16164.8 30 1808 8148 1.984 337.8 337.8 201.6 16 448 1933 0.104 10 6 3.3 Laotian’an 1 915 2 125 613 1.493 13.9 13.9 All collective land 3.4 Wuzhuang 5 7315 23 1071 4900 1.493 160.08 160.08 143.6 9 101 514 0.279 7 2 3.5 Mao’an 6 22878 50 2415 10810 2.116 311.4 311.4 176.82 12 358 1619 0.109 6 6 3.6 Shunhejie 2 4678 10 747 3066 1.526 227.04 227.04 227.04 8 159 685 0.331 8 3.7 Gucheng 1 189 189 All collective and 3.8 Caogang 2 127.71 127.71 All collective land 3.9 Taohuayu 2 731 5 210 890 0.821 57 57 All collective land 3.10 Baohezhai 206.37 206.37 All collective land 3.11 Zhaokou 32.46 32.46 All collective land 3.12 Weitan 4 24700 20 1871 8776 2.814 447.54 447.54 289.1 8 833 3722 0.078 7 1 3.13 Heigangkou 2 6925 22 1198 5595 1.238 25.48 25.48 11.85 6 76 326 0.036 6 3.14 Laozhaizhuang 7 6825 35 934 4030 1.694 100.98 100.98 92.29 24 348 1381 0.067 15 9

Note: The land for the permanent use of river training subproject is totally floodland.

Page 25: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

21

3.2.2 Temporary Land Occupation and Restoration

By the time of this report, a total area of 43,676.04 mu has been acquired from 277 villages for the temporary use of 11 dike, 14 risky spot and 15 river training subprojects, with an increase of 8,182.97 mu and 59 villages 86 mu in comparison with the progress made by the time of the last M&E. Table 13 shows that 22,553.39 mu is used for excavation, 14,334.21 mu for pumping and 6,788.44 mu for treading, including 42,271.64 mu to be restored.

The restored area by the time of this report is 32,473.84 mu, accounting for 76.8% of the total area, 11,039.19 mu larger the area reflected in the last report. The remaining 9,797.8 mu includes 1,840.86 mu fresh floodland for pumping (totally for dike subprojects). Having received compensation costs, the farmers are not eager to restore this part of farmland close to the Yellow River and prone to flooding despite it is now farmed, instead they wait for natural restoration by the floods. The land for treading can be restored upon completion of construction, and that for excavation can be restored when leveled. Refer to Table 13.

The completed area for the temporary use of 11 dike subprojects is 35,770.42 mu from 216 villages, 4,930.14 mu and 24 villages more than the figures contained in the last report. The restored area is 26,138.61 mu, taking up 73.4% of the total area 35,617.02 mu to be restored, 8,173.47 mu larger than the figure indicated in the last report. In specific, the percentage of land restoration is 100% in Lankao (135) and Dongpinghu (22), 97.8% in Kaifeng, 69.3% in Lankao (152) and 73.8% in Dongming. Refer to Table 13 for details.

Temporary land acquisition for 15 risky spot subprojects is almost finished, with a total area of 4,201.74 mu acquired from 24 villages, with additional area of 60.95 mu from 2 villages in Liuzhuang since the last M&E. The restored area is 3520.02 mu, which is 91.7% of the total area 3,839.41 mu to be restored and 50.51 mu larger than the area reflected in the last report. Land restoration was finished at the time of the last report except for 101.5 mu being restored in Huangzhai and 217.89 not restored yet in Liuzhuang. Details are provided in Table 13.

The completed area for the temporary use of 15 river training subprojects is 3,703.89 mu in 37 villages, 3,191.89 mu and 33 villages more than the progress shown in the last report. The restoration of 2,815.22 mu has been totally finished. Refer to Table 13.

Our attention to the restoration of farmland and the willingness to restore will be continued in future follow-up monitoring activities.

3.3 Land Use for Village Platform Subprojects and Economic Rehabilitation

3.3.1 Permanent Land Use and Economic Rehabilitation

Main works for all the 13 village platforms included in 5 village platform subprojects are totally completed, with a total area of 4,652.95 mu (including service and escape roads) occupied in 37 villages. This part of work was totally completed by the time of the last M&E. Detailed information is given in Table 14.

Page 26: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

22

Table 13 Temporary Land Occupation and Restoration Temporary Land Occupation Restoration

Restored Remaining

7th M&E Total No. Subproject

Village Involved Subtotal Excavation Pumping Treading

To be restored

6th M&E Total

Increase Area %

Subtotal Pumping

Unit village mu mu mu mu mu mu mu mu % mu mu

Total 277 43676.04 22553.39 14334.21 6788.44 42271.64 21434.65 11039.2 32473.85 76.8 9797.8 1840.86

1 Dike 216 35770.42 15483.05 14334.21 5953.16 35617.02 17965.14 8173.47 26138.61 73.4 9478.41 1840.86

1.1 Yuanyang 49 12231.8 2671.2 8649.5 911.1 12231.8 4783.83 3048.27 7832.1 64.0 4399.7

1.2 Kaifeng* 18 4915.71 4189.81 305.2 420.7 4795.71 4242.4 445.73 4688.13 97.8 107.58 107.58

1.3 Lankao (152) 10 2219.75 1121.77 681.48 416.5 2219.75 1098.99 439.26 1538.25 69.3 681.5 681.5

1.4 Lankao (135) 3 358.93 292.68 54 12.25 358.93 245.55 113.38 358.93 100.0

1.5 Puyang 21 2124.68 1754.86 369.82 2124.68 849.83 849.83 40.0 1274.85

1.6 Dongming 70 10794 4409 4047 2338 10794 7073 1000 8073 74.8 2721 788

1.7 Mudan 14 1159.39 569.89 589.5 1125.99 179.9 682.31 862.21 76.6 263.78 263.78

1.8 Juancheng 11 350.49 291.87 58.62 350.49 350.49 350.49 100.0

1.9 Dongpinghu (55) 8 341.47 27.14 314.33 341.47 341.47 341.47 100.0

1.10 Dongpinghu (77) 3 1049.02 751.86 297.16 1049.02 1019.02 1019.02 97.1 30

1.11 Dongpinghu (10) 9 225.18 225.18 225.18 225.18 225.18 100.0

2 Risky spot 24 4201.74 3543.83 657.91 3839.41 3469.51 50.51 3520.02 91.7 319.39

2.1 Huayuankou 2 369.73 245.66 124.07 307.03 307.03 307.03 100.0

2.2 Madu 2 125.37 89.28 36.09 114.57 114.57 114.57 100.0

2.3 Zhaokou 275.14 195.9 79.24 275.14 275.14 275.14 100.0

2.4 Yangqiao 85.72 23.3 62.42 85.72 85.72 85.72 100.0

2.5 Jiubao 27 27 27 27 27 100.0

2.6 Heigangkou 2.7 Dongbatou 1 62.77 15 47.77 30 30 30 100.0

2.8 Huangzhai 5 1021.91 953.76 68.15 799.65 698.15 698.15 87.3 101.5

2.9 Huozhai 3 369.75 327.15 42.6 369.75 369.75 369.75 100.0

2.10 Baocheng 1 519.95 519.95 519.95 519.95 519.95 100.0

2.11 Gaocun 2 583.3 583.3 583.3 583.3 583.3 100.0

2.12 Weishan 1 216.4 173 43.4 216.4 216.4 216.4 100.0

2.13 Fanpo 1 112.11 78.7 33.41 112.11 112.11 112.11 100.0

2.14 Likou 2 164.19 120.94 43.25 130.39 130.39 130.39 100.0

2.15 Liuzhuang 4 268.4 217.89 50.51 268.4 50.51 50.51 18.8 217.89

3 River training 37 3703.89 3526.51 177.37 2815.22 2815.22 2815.22 100.0

3.1 Zhangwangzhuang 1 84.3 72.3 12 84.3 84.3 84.3 100.0

3.2 Dong’an 2 48 36 12 48 48 48 100.0

3.3 Laotian’an 3 322.49 315.29 7.20 309.95 309.95 309.95 100.0

3.4 Wuzhuang 5 334.7 325.1 9.6 334.7 334.7 334.7 100.0

3.5 Mao’an 7 461.5 444.7 16.8 461.5 461.5 461.5 100.0

3.6 Shunhejie 3 199.68 191.8 7.88 199.68 199.68 199.68 100.0

3.7 Gucheng 1 577.34 569.96 7.38 577.34 577.34 577.34 100.0

3.8 Caogang 2 583.93 567.43 16.5 583.93 583.93 583.93 100.0

3.9 Taohuayu 1 30 28.8 1.2 3.10 Baohezhai 35 29 6 3.11 Zhaokou 2 250.69 249 1.69 3.12 Weitan 2 70 46 24 3.13 Heigangkou 2 112.14 98.95 13.19 3.14 Fujunsi 1 378.3 359 19.3 3.15 Laozhaizhuang 5 215.82 193.19 22.63 215.82 215.82 215.82 100.0

Page 27: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

23

Economic rehabilitation is mostly achieved by land adjustment between villages/groups and within groups. In account of the impacts and benefits, land adjustment is needed between 36 villages and between or within groups of 43 villages as listed in Table 14. Refer to Appendix 6 for details.

As of this report, 19 of the 36 villages in the need of village-to-village land adjustment have done this work, accounting for 53%, including Miaozhai, Wuqiu and Dongming south village platform where this is completed. In comparison with the progress achieved by the time of the last M&E, one more village in Pingyin has completed village-to-village land adjustment. Among the 17 villages where village-to-village land adjustment is not started, this work for 11 villages in Fanxian and 5 in Dongming north village platform is still under discussion, because the farmers to given land are suspicious about farmland replacement with old village platforms, and 1 village in Pingyin has not acted because the land contracts have not expired yet. Refer to Table 14 and Appendix 6 for further information.

Land adjustment between and within groups is needed for 43 villages, including 26 having adjusted land between and 25 within groups, i.e. 60%, 1 more village in Pingyin than the number of villages reflected in Report No. 6. Land adjustment between and within groups is still under discussion except for Wuqiu and Dongming where this is finished. Refer to Table 14 and Appendix 6.

However, compensations for young crops will be paid to affected farmers until the completion of land adjustment.

Table 14 Land Use for Village Platform Subprojects and Economic Rehabilitation* RP Adjustment between

Villages Adjustment

between Groups Land Adjustment

within Groups No. Subproject Home People Village Moved

Affected Village

Permanent Land Use

Village Platform

Needed Done Not Needed Done Not Needed Done Not Unit home person home person mu number Village

Total 9028 37065 40 37 4652.95 13 36 19 17 43 26 17 43 26 171 Miaozhai 890 3988 4 3 570.23 1 4 4 4 3 1 4 3 12 Wuqiu 1181 4651 3 5 591.81 2 3 3 3 3 3 33 Fanxian 2178 8704 9 10 1069.45 1 11 11 11 11 11 114 Dongming 2297 9594 11 6 1055.8 2 11 6 5 11 7 4 11 7 4 South 965 4200 6 2 462.3 1 6 6 6 6 6 6 North 1332 5394 5 4 593.5 1 5 5 5 1 4 5 1 45 Pingyin 2482 10128 13 13 1365.66 7 7 6 1 14 13 1 14 13 1

*Land use for village platforms includes service roads and escape roads.

3.3.2 Temporary Land Occupation and Restoration

A total area of 5,475.55 mu is acquired for the temporary use of 5 subprojects in this category, involving 42 villages. Land restoration is needed for 5,231.55 mu, including 3,535.87 mu restored, i.e. 68%. The area of 1,695.68 mu not restored yet includes 1,403.34 mu floodland, i.e. 82.8%, most of which will be restored naturally by the Yellow River, and the rest 292.34 mu includes 156.34 mu in Wuqiu and 136 mu in Dongming. No change has ever taken place since the last M&E. Land restoration, as being included in the compensations for temporary land use, is still performed by farmers themselves. This will continue to be the focus of our

Page 28: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

24

future follow-up monitoring. Refer to Table 15 and Appendix 6.

Table 15 Temporary Land Use for Village Platform Subprojects and Restoration Restored Not Restored

Incl. Floodland No. Subproject Affected Village

Temporary Land Use

To Be Restored Area % Subtotal Area %

Unit mu mu mu % mu mu % Total 42 5475.55 5231.55 3535.87 68 1695.68 1403.3 82.8

1 Miaozhai 3 578.33 578.33 42.91 7 535.42 535.42 100 2 Wuqiu 5 693.94 693.94 92.6 13 601.34 445 74 3 Fanxian 14 822.92 822.92 400 49 422.92 422.92 100 4 Dongming 7 1448.2 1204.2 1068.2 89 136 5 Pingyin 13 1932.16 1932.16 1932.16 100

4. PHYSICAL RELOCATION AND REHABILITATION

Among the 46 implemented subprojects, 6 dike, 1 river training and 4 village platform subprojects involve the relocation of private houses.

Land acquisition for the permanent use of new village platforms is finished, with 71 affected households. Since the last M&E, 22 of the total number of 58 affected households in Pingyin have started housing at the new village platform, with 16 house foundations completed. The 13 households affected by the rest 4 village platform subprojects have been relocated, 2 more than as reported last time.

This part of work for the 6 dike subprojects is described in the following paragraphs.

Physical relocation is needed for 847 households in 44 villages, including 818 completed, i.e. of 96.6%, 32 more than the number of the last report. There is no change in Lankao (135), Dongming and Dongpinghu (77), where this work is total completed, but there is an increase of 12 households in Puyang, 8 in Dongming and 12 in Juancheng.

Homestead identification necessary for 781 households is totally completed. In comparison with the last report, there is no change in Lankao (135), Mudan and Dongpinghu (77) where this was finished by the time of the 6th M&E, but the number is increased by 21 in Dongming, 25 in Puyang and 26 in Juancheng.

Altogether 641 households have completed their new houses, accounting for 82.1% of those having received homesteads, 118 or 22.6% more than the number given in the last report.

The number of households having moved to new houses is 619, an increase of 109 or 21.4%.

All resettlement families are resettled in one way or another, with 621 resettled permanently by constructing (619) and buying (2) new houses, accounting for 75.9%, and 274 resettled temporarily by borrowing (74), renting (17), building temporarily (3) and others (103, including 86 houses elsewhere), taking up 24.1%. Refer to Table 16. The households resettled by borrowing/renting houses and other ways refer to people having not received homesteads, working at new houses or being ready to act. They use the houses lent by relatives/friends or offered by the government (e.g. in Juancheng) temporarily. Refer to Table 16.

Page 29: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

25

Relocation and homestead identification for the additional 9 families in Laozhaizhuang have been completed, including 6 having built and 5 moved into new houses. Refer to Table 16.

Page 30: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 7)

26

Table 16 Progress of Physical Relocation and Housing Restoration Relocation Homestead Identification Housing Rehabilitation

Home Planned Others No. Subproject Follow-up Monitoring Village Planned Moved Subtotal Done Not

Not needed Subtotal Built Being

BuiltReady

to start

Subtotal New Buy Borrow Rent Subtotal Other House

Unit village home home home home home home home home home home Home home home home home home home Home 52 927 898 824 824 103 824 659 104 61 898 624 2 83 65 18 106 87 Report 7 % 96.9 100.0 80.0 12.6 7.4 69.5 0.2 9.2 7.2 2.0 11.8 9.7 Home 51 906 855 787 721 119 721 535 125 61 857 510 2 132 96 19 98 73 Report 6 % 94.4 91.6 74.2 17.3 8.5 59.5 0.2 15.4 11.2 2.2 11.4 8.5

Total

Change Home 1 21 43 37 103 -16 103 124 -21 41 114 -49 -31 -1 8 14 Report 7 Home 44 847 818 781 781 66 781 641 81 59 818 619 2 74 17 3 103 86 Report 6 Home 44 835 786 770 709 65 709 523 125 61 786 510 2 125 48 4 97 72 1 Dike Change Home 12 32 11 72 1 72 118 -44 -2 32 109 -51 -31 -1 6 14 Report 7 Home 2 66 66 60 60 6 60 54 6 66 53 2 1 10 8 Report 6 Home 2 66 66 60 60 6 60 53 1 6 66 53 2 1 10 8 1.1 Lankao (135) Change Home 1 -1 Report 7 Home 6 227 227 227 227 227 177 39 11 227 177 28 10 12 12 Report 6 Home 6 215 215 215 202 202 117 85 215 115 58 40 2 2 1.2 Puyang Change Home 12 12 12 25 25 60 -46 11 12 62 -30 -30 10 10 Report 7 Home 23 335 314 295 295 40 295 261 8 26 314 240 14 7 3 50 40 Report 6 Home 23 335 314 295 274 40 274 220 24 30 314 220 24 7 3 60 40 1.3 Dongming Change Home 21 21 41 -16 -4 20 -10 -10 Report 7 Home 6 33 33 25 25 8 25 13 4 8 33 13 5 15 12 Report 6 Home 6 33 25 25 25 8 25 9 5 11 25 8 7 1 9 9 1.4 Mudan Change Home 8 4 -1 -3 8 5 -2 -1 6 3 Report 7 Home 4 101 93 91 91 10 91 64 27 93 64 26 3 3 Report 6 Home 4 101 81 92 65 9 65 55 4 6 81 52 17 1 11 8 1.5 Juancheng Change Home 12 -1 26 1 26 9 23 -6 12 12 9 -1 -8 -5 Report 7 Home 3 85 85 83 83 2 83 72 3 8 85 72 13 11 Report 6 Home 3 85 85 83 83 2 83 69 6 8 85 62 18 5 5 1.6 Dongpinghu

(77) Change Home 3 -3 10 -18 8 6 Report 7 Home 1 9 9 9 9 9 6 1 2 9 5 2 2 Report 6 Home 2 LaozhaizhuangChange Home 1 9 9 9 9 9 6 1 2 9 5 2 2 Report 7 Home 7 71 71 34 34 37 34 12 22 71 7 48 15 1 1 Report 6 Home 7 71 71 17 12 54 12 12 71 7 48 15 1 1 3 Village

platform Change Home 22 27 -22 22 22

Page 31: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

27

5. RECONSTRUCTION OF SCHOOLS

School reconstruction is involved in 3 dike subprojects only: Liuzhuang in Kaifeng, Yantan and Xuji in Dongming, and Donglou in Puyang. The approved budge has been paid in full.

New schoolrooms were handed over to Liuzhuang in December 2004, Yantan in September in 2004 and Xuji in April 2006, to take the place of simple old rooms and outdated facilities. New rooms are larger and schooling conditions are considerably better.

An obvious progress has been made in reconstructing Donglou School, with 4.5 mu acquired as the new site and 13 rooms (310 m2) completed. Pupils in higher grades are studying at the central primary school, and Grades 1 and 2 previously staying in rent rooms will move to the new school soon (already at the new school when this report is completed). The conditions and circumstances are improved. Refer to Appendix 2 for details.

6. REPLACEMENT OF SPECIAL FACILITIES

Altogether 25 subprojects involve the replacement of special facilities in transport, power and communications sectors, including all 11 dike, 12 risky spot (Huayuankou, Madu, Zhaokou, Yangqiao, Jiubao, Dongbatou, Heigangkou, Baocheng, Gaocun, Weishan, Likou, Liuzhuang) and 2 river training (Taohuayu and Laozhaizhuang) subprojects. Refer to Table 17 for details.

Table 17 Progress of Special Facilities Implementation

7th M&E No. Subproject Approved Total Agreed

6th M&E Increase Amount % of Approved

% of Total

Unit 104 RMB 104 RMB 104 RMB 104 RMB 104 RMB 104 RMB % % Total 4265.57 6006.01 5654.69 3928.34 1306.34 5234.68 122.7 87.2

1 Dike 3745.53 5315.95 5047.07 3574.59 1065.47 4640.06 123.9 87.3 1.1 Yuanyang 2473 2740.26 2643.09 2424.04 219.05 2643.09 106.9 96.5 1.2 Kaifeng* 38 56.06 54.44 53.15 1.288 54.438 143.3 97.1 1.3 Lankao (152) 45 108.34 123.94 116.66 7.28 123.94 275.4 114.4 1.4 Lankao (135) 11 22.02 38.93 7.7 31.23 38.93 353.9 176.8 1.5 Puyang 217 357.74 148.75 61.23 87.52 148.75 68.5 41.6 1.6 Dongming 433 1291 1280.32 781.38 304.68 1086.06 250.8 84.1 1.7 Mudan 198 367 384.33 53.13 164.17 217.3 109.7 59.2 1.8 Juancheng 13 37 36.51 3.93 3.93 30.2 10.6 1.9 Dongpinghu 38.53 38.53 38.53 38.53 38.53 100.0 100.0

1.10 Dongpinghu 136 147 147.23 34.84 99.25 134.09 98.6 91.2 1.11 Dongpinghu 143 151 151 151 151 105.6 100.0

2 Risky spot 216 386.02 387.42 353.75 20.67 374.42 173.3 97.0 2.1 Huayuankou 70.57 70.57 70.57 70.57 100.0 2.2 Madu

61 36.79 36.79 36.79 36.79

176.0 100.0

2.3 Zhaokou 109 109.68 109.68 109.68 100.6 2.4 Yangqiao 38.4 39 39 39 101.6 2.5 Jiubao

117 1.44 1.87 1.87 1.87

128.7 129.9

2.6 Dongbatou 2 2.18 2.18 2.18 2.18 109.0 100.0 2.7 Heigangkou 2.88 2.88 2.88 2.8 Baocheng 20.76 0.09 20.67 20.76 2.9 Gaocun 54

32.7 31.7 31.7 99.0

2.10 Weishan 14.8 12.15 12.15 12.15 82.12.11 Likou 46.84 46.84 46.84 46.84 100.0 2.12 Liuzhuang 36 12 12

3 River training 304.04 304.04 220.2 220.2 220.2 72.4 72.4 3.1 Taohuayu 216 216 216 216 216 100.0 100.0 3.2 Laozhaizhuang 88.04 88.04 4.2 4.2 4.2 4.8 4.8

Page 32: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

28

The agreed amount for this purpose is 56.5469 million RMB, which is 94.2% of the total and 8.4166 million RMB more than that of the last report. The completed payment is 52.3468 million RMB, 87.2% of the total and 13.0634 million RMB more than the figure reported last time. As indicated in Table 17, this work has been completed for Lankao (152), Lankao (135), Dongpinghu (22), Dongpinghu (10), 11 river training subprojects (excluding Liuzhuang) and Taohuayu, altogether 16.

7. INCOME RECOVERY

7.1 Selection of Sample Households

Sample households for the purpose of this M&E are selected on the following principles:

(1) Selecting 20% households in different types (Option A, Option B, Option C) and with more land loss;

(2) Discussing with groups regarding the use of compensations and the remedy measures for income recovery;

(3) Interviewing with different types of sample households, e.g., those with land loss over 30%, including one of the vulnerable groups in each village, especially women-headed families;

(4) Conducting survey and qualitative analysis of remedy measures.

Dike, risky spot and river training subprojects

(1) Completion report: Sample households having lost more land and chosen Options and B are selected for the purpose of follow-up monitoring, not less than 20% of the affected households in each type.

(2) Follow-up monitoring report: Sample households having lost more land and chosen Options and B are selected for the purpose of follow-up monitoring, not less than 50% of the affected households in each type.

Village platform subprojects

Follow-up monitoring report: Sample households having lost more land and chosen Options and B are selected for the purpose of follow-up monitoring, not less than 20% of the affected households in each type (2005 and 2006).

Based on these principles, 292 sample households and 1,418 people have been selected from 15 subprojects. The original per capita farmland area is reduced from 1.351 mu to 1.102 mu, i.e. a per capita loss of 0.249 mu or 18.4%. This total number includes 119 households and 569 people in Option B, with a per capita farmland reduction of 0.331 mu or 24%, and 173 households and 849 people in Option A, with a per capita loss of 0.194 mu or 14%. Refer to Table 18 for details

Page 33: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

29

Further analysis indicates that:

(1) 59 households and 285 people in completed subprojects, including 38 and 166 in Option B, with a per capita loss of 0.258 mu or 22%, 21 and 119 in Option A, with a per capita loss of 0.35 mu or 26%;

(2) 138 households and 635 people in dike subprojects, including 29 and 134 in Option B, with a per capita loss of 0.37 mu or 23%, 109 and 501 in Option A, with a per capita loss of 0.17 mu or 13%;

(3) 70 households and 354 people in village platform subprojects, including 27 and 125 in Option B, with a per capita loss of 0.386 mu or 30%, 43 and 229 in Option A, with a per capita loss of 0.165 mu or 11%l

(4) 25 households and 144 people in river training subprojects, all in Option B, with a per capita loss of 0.329 mu or 24%.

Detailed information is given in Table 18.

Table 18 Profile of Sample Households

Subproject Sample Household People Original

Farmland

Current

Farmland

Per Capita

Loss Loss Rate

No. Category

Subtotal Option B Option A Subtotal Option B Option A Option B Option A Option B Option A Option B Option A Option B Option A

Unit home home home person person person mu mu mu mu mu mu % %

Column � � � � � � � � � � � � � �

Total 292 119 173 1418 569 849 775 1141 587.2 976 0.331 0.194 24 14

1 Kaifeng 17 10 7 77 46 31 52.8 37.3 40.7 35 0.263 0.074 23 6

2 Lankao (152) 4 4 19 19 19.3 15.3 0.211 21

3 Lankao (135) 5 5 30 30 22.5 15.8 0.223 30

4 Dongming 33 19 14 159 71 88 102.4 120.3 82.4 81 0.282 0.447 20 33

Completed

Subtotal 59 38 21 285 166 119 197 157.6 154.2 116 0.258 0.350 22 26

1 Yuanyang 50 21 29 247 95 152 123.6 224.9 82.27 204.5 0.435 0.134 33 9

2 Puyang 41 41 186 186 217 185 0.172 15

3 Mudan 19 8 11 81 39 42 94.6 55.8 86.34 46 0.212 0.233 9 18

4 Juancheng 28 28 121 121 152.6 129.7 0.189 15

Dike

Subtotal 138 29 109 635 134 501 218.2 650.3 168.6 565.2 0.370 0.170 23 13

1 Miaozhai 9 4 5 55 19 36 28.3 42 19.7 37.64 0.453 0.121 30 10

2 Wuqiu 17 17 87 87 116.6 98.65 0.206 15

3 Fanxian 14 14 69 69 55.3 32.9 0.325 41

4 Dongming 18 5 13 96 21 75 66 137.6 52.5 124.7 0.643 0.172 20 9

5 Pingyin 12 4 8 47 16 31 13 36.5 9.2 34 0.238 0.081 29 7

Village

platform

Subtotal 70 27 43 354 125 229 162.6 332.7 114.3 295 0.386 0.165 30 11

1 Wuzhuang 5 5 36 36 67.2 46.9 0.564 30

2 Shunhejie 20 20 108 108 130.3 103.2 0.251 21

River training

Subtotal 25 25 144 144 197.5 150.1 0.329 24

Notes: (1) The number of people is the census results of 2006; (2) households in Option B and Option A are followed in dike and river training, and those in Option A and Option B in village platform subprojects.

Page 34: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

30

7.2 Income Recovery

Income recovery by types of subprojects, i.e. completed, follow-up dike/river training and follow-up village platform subprojects, is analyzed by vertical comparison method. To put in another way, the income of sample households in the follow-up years is compared vertically with that in the base year.

7.2.1 Completed Subprojects

The year of 2003 is used as the base year of all the completed Kaifeng, Lankao (152), Lankao (135) and Dongming, with baseline data established for 2,440 sample households, including 1,629 choosing Option A and 811 preferring Option B.

Excluding the effect of escalation (minor escalation), follow-up monitoring of the recovery of family incomes in 3 straight years concludes that:

(1) as the recovery time extends, the percentage of income recovery is higher and higher, e.g., 60%, 70% and 90% sample households reached or exceeded their original income levels in the period of 2004 to 2006;

(2) as seen from group data, there is no major difference in the degree of income recovery of either Option A or B, indicating that both options meet the local conditions, represent the farmers’ willingness to achieve economic rehabilitation and does not play a decisive role in recovering family incomes;

(3) as shown by continuous follow-up monitoring results in 2006, only 78 of the 285 people choosing Options A and B had an increasing per capita income in the past 3 years, taking up 27% only, which means that, though 90% households have reached or exceeded their original income levels, joint efforts from all parties are needed to maintain the steady and continuous income growth of all affected people.

Refer to Table 19 for further information.

7.2.2 Dike and River Training Subprojects

On the one hand, the recovery time of 6 follow-up monitoring subprojects in this category is relatively short (Table 22 shows 2005 as the base year of 4 and 2004 of 2 subprojects); on the other hand, resettlement for all the subprojects is not completed yet. Thus the M&E team has analyzed the income recovery of sample households in 2006 only.

In 2006, the original income level was recovered or exceeded by 66% households, including 78% in Option B and 60% in Option A. As analyzed by subprojects, the percentage in Yuanyang, Mudan and Shunhejie was higher than 75%, whilst that in Puyang, Juancheng and Wuzhuang was lower than 50% partly because of the limited recovery time (base year 2005). See Table 20 for details.

Page 35: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

31

Table 19 Income Recovery of Completed Subprojects Follow-up Monitoring Recovered Income Level

People Per Capita Income Overall Option B Option A Increased Income

No. Subproject Year Subtotal Option B

Option A

AverageOption

B Option

A People % People % People % People %

Unit person person person RMB RMB RMB person % person % person % person % Base year 2440 811 1629 930 1058 875 Follow-up year (2004) 1878 691 1187 1233 1314 1200 1120 60 412 60 708 60 Follow-up year (255) 1247 583 664 1626 1583 1665 870 70 405 69 465 70

Total

Follow-up year (2006) 285 166 119 1815 1667 2021 256 90 151 91 105 88

78 27

Base year 608 433 175 1516 1228 2237 Follow-up year (2004) 551 395 156 1959 1656 2727 345 63 233 59 112 72 Follow-up year (255) 463 321 142 1769 1671 1992 266 57 187 58 79 56

1 Kaifeng

Follow-up year (2006) 77 46 31 2116 1781 2613 77 100 46 100 31 100

16 21

Base year 123 123 1090 1090 0 0 Follow-up year (2004) 97 97 1026 1026 67 69 67 69 Follow-up year (255) 75 75 1945 1945 70 93 70 93

2 Lankao (152)

Follow-up year (2006) 19 19 1581 1581 19 100 19 100

19 100

Base year 182 182 783 783 0 0 Follow-up year (2004) 151 151 836 836 99 66 99 66 Follow-up year (255) 114 114 1218 1218 87 76 87 76

3 Lankao (135)

Follow-up year (2006) 30 30 1901 1901 30 100 30 100

10 33

Base year 1527 73 1454 701 678 711 Follow-up year (2004) 1079 48 1031 937 588 969 609 56 13 27 596 58 Follow-up year (255) 595 73 522 1553 1395 1576 447 75 61 84 386 74

4 Dongming

Follow-up year (2006) 159 71 88 1681 1517 1813 130 82 56 79 74 84

33 21

Table 20 Income Recovery by Subprojects Follow-up Monitoring Recovered Income Level

People Per Capita Income Overall Option B Option ANo. Subproject Year Subtotal Option B Option A Average Option B Option A People % People % People %

Unit person person person RMB RMB RMB person % person % person %Base year 787 278 509 1668 1642 1682 Total 2006 779 278 501 2203 2345 2124 518 66 216 78 302 60Base year 247 95 152 1920 1773 2012 1 Yuanyang 2006 247 95 152 2442 2253 2562 206 83 89 94 117 77Base year 186 186 1230 1230 2 Puyang 2006 186 186 1505 1505 93 50 93 50Base year 85 39 46 1339 1423 1268 3 Mudan 2006 81 39 42 2785 2975 2608 64 79 31 79 33 79Base year 125 125 2107 2107 4 Juancheng 2006 121 121 2359 2359 59 49 59 49Base year 36 36 2042 2042 5 Wuzhuang 2006 36 36 1900 1900 13 36 13 36 Base year 108 108 1471 1471 6 Shunhejie 2006 108 108 2346 2346 83 77 83 77

7.2.3 Village Platform Subprojects

The year of 2003 is based as the bear use for village platform subprojects save for Pingyin. Follow-up monitoring results of income recovery in 3 consecutive years (2 years for Pingyin), in comparison with that of completed dike subprojects, reveal the following characteristics:

(1) As the recovery time extends, the percentage of recovery is higher and higher, but the rate is rather slow, e.g. 56%, 65% and 66% sample households reached or exceeded their original income levels in the period from 2004 to 2006, partly because the farmers inside the floodplains have richer farmland and depended on land more than those outside the dikes, and partly because the affected farmers are not entitled of land compensations

Page 36: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

32

(other than the compensation for the land use of village platforms, i.e. compensation for young crops).

(2) The mode of economic rehabilitation is not decisive for recovering family incomes and the percentage of households with increasing incomes is almost consistent with that in the completed subprojects.

(3) Income recovery is rather instable. In Miaozhai, for example, 79% households in Option B reached or exceeded their original income levels in 2005, but only 58% in 2006, versus 62% and 30% in Pingyin. This is because, in addition to drought/flood and other natural disasters, land adjustment in Pingyin disabled the timely farming of part of farmland, preparation for physical relocation and housing reduced the work time of farmer workers, and the quality of adjusted land varied from one place to another.

Analysis results are provided in Table 21 below.

Table 21 Analysis of Income Recovery in Village Platform Subprojects Follow-up Monitoring Recovered Income Level Increasing Income

People Per Capita Income Overall Option A Option B Option A Option B No. Subproject Year Subtotal Option A Option B Subtotal Option A Option B People % People % People % People % People %

Unit person person person RMB RMB RMB person % person % person % person % person %Base year 351 224 127 1263 1475 889 2004 290 179 111 1120 1086 1175 163 56 91 51 72 65 2005 355 230 125 1535 1576 1460 232 65 136 59 96 77

Total

2006 354 229 125 1665 1707 1590 233 66 141 62 92 74

52 23 36 29

Base year 55 36 19 1015 987 1068 2004 55 36 19 668 588 819 23 42 12 33 11 58 2005 55 36 19 1156 1106 1250 46 84 31 86 15 79

1 Miaozhai

2006 55 36 19 1144 1128 1175 47 85 36 100 11 58

7 19 11 58

Base year 87 87 1942 1942 2004 72 72 1164 1164 29 40 29 40 2005 87 87 1940 1940 35 40 35 40

2 Wuqiu

2006 87 87 2094 2094 48 55 48 55

18 21

Base year 70 70 802 802 2004 70 70 1260 1260 42 60 42 60 2005 69 69 1214 1214 52 75 52 75

3 Fanxian

2006 69 69 1290 1290 56 81 56 81

6 9

Base year 91 69 22 1056 1116 868 2004 93 71 22 1249 1260 1212 69 74 50 70 19 86 2005 97 76 21 1694 1408 2731 70 72 49 64 21 100

4 Dongming

2006 96 75 21 1941 1567 3277 68 71 47 63 21 100

11 15 15 71

Base year 48 32 16 1382 1528 1088 2004 2005 47 31 16 1371 1509 1106 29 62 21 68 8 50

5 Pingyin

2006 47 31 16 1471 1632 1160 14 30 10 32 4 25

16 52 4 25

7.3 Remedy Measures

To be abreast of the affected people have done to recover their family incomes under the condition of reduced farmland, 317 sample households (201) in dike, 81 in village platform and 35 in river training subprojects) have been selected for the purpose of a questionnaire containing 18 questions in the aspect of (1) how was your family income affected as a result of farmland reduction? (2) how did you use you land compensations? (3) what did you do to recovery you family income? All surveys are conducted face to face, with questionnaires completed by interviewers. The findings are discussed in the following paragraphs. Since the survey in these 3 aspects pays more attention to a trend, all of the 18 questions are weighted equally. The next M&E will quantify some indexes, e.g., the use of compensations, to analyze

Page 37: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

33

the trend of production and livelihood in the respect of structure.

(1) Income impacts by farmland reduction: The total number of 317 households includes (1) 89 with less income from farming activities but more from other sources, without any impact on the total income, taking up 28.1%; (2) 111 subject to minor impacts due to less land loss, 35%; (3) 53 subject to minor impacts due to interior quality of lost land, 16.7%; (4) 63 exposed to major impacts, 19.9%; and 1 in the category of others, 0.3%.

(2) Use of land compensations: Land compensation is used for (1) direct income recovery by 38.2% people, including farming by 31.9% and small business by 6.3%; and (2) indirect income recovery or other purposes by 61.8%, including medical fees, children’s tuitions and daily expenses by 47.6%, housing by 6.8%, debit and other purposes by 5.4%.

(3) Income recovery: The affected people have implemented various measures to recovery family incomes after farmland reduction, including 59.6% by working as farmer workers, 10.5% by doing small business, 6.9% by extensive farming, intercropping, reclamation, cropping, animal raising and plastic tunnel, and 5.7% by other measures. The rest 17.4% have not acted due to the lack of funds or inadequacy of deliberation. Refer to Table 22.

Table 22 Analysis of Income Recovery Total Dike Village River No. Item Home % Home % Home % Home %

1 Number of sample households 317 201 81 35 2 Questions 2.1 Income impacts by farmland 317 100 201 100 81 100 35 100 2.1.1 Less income from farming, but more 89 28.1 59 29.4 23 28.4 7 20.0 2.1.2 Minor impact due to less land loss 111 35.0 75 37.3 20 24.7 16 45.7 2.1.3 Minor impact due to poor land 53 16.7 32 15.9 18 22.2 3 8.6 2.1.4 Major impact 63 19.9 35 17.4 19 23.5 9 25.7 2.1.5 Others 1 0.3 1 1.2 2.2 Use of land compensations 351 100 252 100 45 100 54 100 2.2.1 Farming 112 31.9 89 35.3 10 22.2 13 24.1 2.2.2 Business 22 6.3 16 6.3 6 13.3 2.2.3 Housing 31 8.8 31 12.3 2.2.4 Medical fees, tuitions and other 167 47.6 97 38.5 29 64.4 41 75.9 2.2.5 Debit repayment 6 1.7 6 2.4 2.2.6 Others 13 3.7 13 5.2 2.3 Remedy measures 334 100 216 100 81 100 37 100 2.3.1 Farmer worker 199 59.6 123 56.9 45 55.6 31 83.8 2.3.2 Business 35 10.5 19 8.8 12 14.8 4 10.8 2.3.3 Cropping, animal raising or plastic 3 0.9 3 1.4 2.3.4 Extensive farming and intercropping 12 3.6 12 5.6 2.3.5 Reclamation or cultivating others’ 8 2.4 8 3.7 2.3.6 Trust to luck 58 17.4 43 19.9 13 16.0 2 5.4 2.3.7 Others 19 5.7 8 3.7 11 13.6

As mentioned above, approximately 80% of the sample households do not think their family incomes are affected significantly, over 80% have taken various actions for income recovery, about 40% have used the land compensations for recovering incomes directly. Refer to Table 5 for detailed information.

To follow how the seriously affected households, vulnerable groups and women-headed

Page 38: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

34

families are doing in income recovery, the M&E team has interviewed 16 households (2 in vulnerable groups and 1 women-headed family).

Profile of households: There are 74 people in these 16 families, i.e. an average family size of 4.63 people. Subsequent to land acquisition, the per capita farmland is reduced by 0.32 mu, which is more than 0.12 mu of all affected people or 0.249 mu of the follow-up households. A total amount of 148,893 RMB is paid to them as land compensations, i.e. 2,013 RMB per capita, with a maximum of 3,332 RMB in the scenario of Option B in dike subprojects and a minimum of 118 RMB in the scenario of Option A in village platform subprojects. Refer to Table 26 for detailed information.

Outcome of income recovery: Among these households, 14 have reached or exceeded their original income levels, taking up 87.5%. For instance, Gao Xinxiang, a resettler and also a land loser in Puyang, earns some 20,000 RMB a year by operating an electric motorcar shop with a loan in addition to the land compensation; Ding Xiaoru, a family of minimum income guarantee in Shunnan affected by Shunhejie River Training Subproject, depends on relatives for farming, 50 RMB/person allowance provided by the civil administration each month, plus flour and oil on the occasion of festivals, and cooperative medical care offered by the village. Also, as being close to a brick kiln nearby, he works for the kiln as arranged by the village, with more than 20 RMB earned a day to help out family expenses. Refer to Table 23.

Table 23 Income Recovery of Interviewed Households

Household Family Size Land Loss Compensation Use of Compensation Remedy Measure Outcome (Reach or

Exceed Original Income Level) No. Category

Mode of Economic

Rehabilitation Total Vulnerable

Group Women- headed Family

Total Average Area Per Capita Amount Per

Capita Farming Daily Expenses Others Farmer

Worker Business None Yes No

Unit home home home person person mu mu RMB RMB home home home hoome home home home home Total 16 2 1 74 4.63 23.9 0.32 148973 2013 7 7 2 12 3 1 14 2

Option B 5 1 22 4.4 7.3 0.33 73310 3332 3 2 5 51 Dike

Option A 5 1 26 5.2 7.7 0.3 70240 2702 2 3 4 1 52 River training Option B 1 1 2 2 2.2 1.1 1518 759 1 1 1

Option A 2 7 3.5 1.5 0.21 825 118 1 1 1 1 1 13 Village platform

Option B 3 17 5.67 5.2 0.31 3080 181 1 1 1 2 1 2 1

7.4 Analysis of Income Levels

Without escalation excluded, the increased income reduces the percentage of absolutely poor people by 15.1% and non-poor people by 19.2%. With regard to the completed and follow-up subprojects, due to the longer recovery time for the completed subprojects, absolutely poor people are reduced by 40.8% to the maximum, while non-poor people are increased by 48.6%, versus 3.6% and 9.3% in the follow-up monitoring dike subprojects.

Refer to Table 24 for further information.

As judged from the follow-up monitoring results of the sample households subject to major impacts, surveys of remedy measures taken by sample households and thorough interviews with typical households, more than 80% affected people do not think their family incomes are affected significantly, and about 40% use the land compensations for production directly. As

Page 39: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

35

the recovery time extends continuously, more and more households have reached or exceeded their original income levels, and the number of non-poor people is larger and larger.

Table 24 Follow-up Monitoring of Income Levels Unit: %

Base Year Follow-up Year (2006) Change No. Category Subproject Absolutely

Poor Low-

income Non-poor Absolutely Poor

Low- income Non-poor Absolutely

Poor Low-

income Non-poor

Total 24.2 12.1 63.7 9.1 8.0 82.9 -15.1 -4.1 19.2 1 Kaifeng 22.8 13.9 63.3 100 -22.8 -13.9 36.7 2 Lankao (152) 63.1 36.9 100 -63.1 -36.9 100 3 Lankao (135) 66.7 13.3 20 23.3 76.7 -66.7 10 56.7 4 Dongming 61.1 11.1 27.8 18.9 6.3 74.8 -42.2 -4.8 47

Completed

Average 51.4 13.8 34.8 10.5 6.0 83.5 -40.8 -7.8 48.6 1 Yuanyang 4.9 10.5 84.6 4.4 5.7 89.9 -0.5 -4.8 5.3 2 Puyang 27.4 11.8 60.8 26.3 15.6 58.1 -1.1 3.8 -2.7 3 Mudan 22.4 17.6 60 4.9 2.5 92.6 -17.5 -15.1 32.6 4 Juancheng 4.8 9.6 85.6 4.1 1.7 94.2 -0.7 -7.9 8.6

Follow-up dike

Average 11.9 11.7 76.4 8.3 6.0 85.7 -3.6 -5.7 9.3 1 Miaozhai 41.8 7.3 50.9 29.1 12.7 58.2 -12.7 5.4 7.3 2 Wuqiu 24.2 10.3 65.5 17.2 82.8 -7 -10.3 17.3 3 Fanxian 28.6 71.4 10.2 15.9 73.9 -18.4 15.9 2.5 4 Dongming 27.5 24.2 48.3 4.2 20.8 75 -23.3 -3.4 26.7 5 Pingyin 25 75 6.4 21.3 72.3 6.4 -3.7 -2.7

Follow-up village platform

Average 25.6 12.3 62.1 12.5 13.7 73.7 -13.1 1.4 11.6 1 Wuzhuang 100 13.9 86.1 13.9 -13.9 2 Shunhejie 19.4 13 67.6 1.9 98.1 -19.4 -11.1 30.5

Follow-up river training

Average 14.6 9.8 75.6 4.9 95.1 -14.6 -4.9 19.5

8. PROTECTION OF RIGHTS AND INTERESTS

Follow-up monitoring of rights/interests protection is continued in line with the progress of subprojects. This aspect covers resettlement training, complaints and vulnerable groups.

8.1 Training

Training includes resettlement staff and affected people.

During the implementation of resettlement, YRCC’s Project Office held 3 training courses for resettlement staff in July 2005, October 2006 and September 2007, mainly in the field of China and ADB’s resettlement policies, project RPs and action plans, resettlement M&E and post-evaluation. These have significantly contributed to improving the professional qualifies of resettlement staff. Apart from these, the Implementing Agencies have provided ad hoc arrangements and training courses for the relevant township/village leaders in resettlement implementation and management by means of mobilization and meeting, i.e. the so-called method of “meeting in lieu of training”.

With regard to training for the affected people, 44 subprojects are in the need of training for production skills (technical training is not included in the RP of Heigangkou and Dongbatou only). Training programs for cropping, animal raising and other production skills have been prepared for 12 subprojects, including Yuanyang, Kaifeng, Lankao (152), Lankao (135), Dongming, Mudan, Juancheng, Huangzhai, Huozhai, Baocheng, Gaocun and Liuzhuang, and

Page 40: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

36

implemented for Kaifeng, Lankao (152), Lankao (135), Mudan and Liuzhuang. This part of work is generally implemented by township governments as authorized by the Employer. As seen from the outcome of implementation, the trainees have mastered some practical skills. Everyone is quite satisfied.

In addition, this M&E includes an investigation of the demand of training. As shown by the results, 80% wish to be trained in scientific farming, animal raising, non-farm employment and other aspects. Generally speaking, training in production skills is needed for the land losers, so it is recommended that training programs be implemented as early as possible.

8.2 Complaints Management

Complaints are not received during the monitoring except for a few from Juancheng, Mudan and Puyang.

As found in the investigation, the channels of complaints management are smooth and the problems of affected people are basically responded or solved. By interviewing the township governments, village committees and affected people, it is found that farmers in Juancheng and Mudan principally complain about the poor drainage of seepage and rainwater and its subsequent adverse impacts on crops nearby, hoping that the responsible parties pay attention to preventing and treating problem. Some farmers in Puyang complain that land restoration has not been implemented as agreed, hoping that the relevant departments implement land restoration as soon as possible.

It is understood that there are mainly 4 channels available to the affected people: resettlement management system, local government system, judicial system, and resettlement M&E system. As seen from the complaints raised during land acquisition and resettlement, the channels are constantly improved and most complaints are treated.

8.3 Vulnerable Groups

Monitoring of the affected vulnerable groups is continued as a key point.

Altogether 49 households and 73 people are affected by Juancheng, Mudan and river training subprojects, including 3 households of 4 elderly living along (five-guarantee family) involved in physical relocation. These people are properly resettled with 3 major sources of income: income from the farmland cropped by their relatives/friends, food and cash relief provided by the county civil administration on festivals, and old folk’s home operated by the townships. Also, cooperative medical services are arranged and medical service fees exempted/reduced as appropriate by the counties, townships or villages in river training subprojects.

The vulnerable groups in Puyang, Yuanyang and risky spot subproject areas enjoy the equal rights as others in the respect of land compensation and adjustment, and the “five-guarantee families” receive subsidies from the local financial revenues each month, though the amount is different from one place to another. Those in good health live independently, with support

Page 41: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

37

provided by village committees or their relatives in the respect of both production and living, while others unable to take care of themselves in daily life can choose to stay in the old folks’ home. Cash relief is provided for the disabled who have certificates of disability issued by the government. With the help of subsidies provided by the villages and the county river bureau, the vulnerable groups in Puyang have been resettled properly.

Preferential policies oriented to vulnerable groups are not provided for the 5 village platform subprojects. These people enjoy the equal rights as others in the respect of land compensation and adjustment, and the local governments involved in 5 village platform subprojects promise to cover the relocation of poor families with local counterpart funds, mainly including subsidy or assistance for the housing of poor families.

The affected people in the completed Dongming, Lankao (152), Lankao (135), Kaifeng and Dongpinghu (55) Dike Subprojects include 142 households and 295 people in the category of vulnerable groups. They enjoy the equal rights as others in land compensation and adjustment. Although case-specific preferential policies are not provided by the Implementing Agency, these affected vulnerable groups enjoy the same preferential policies provided by the local government as others not affected. They are properly resettled in the following ways: (1) income from the farmland cropped by their relatives/friends, (2) food and cash relief provided by the county civil administration on festivals, and (3) old folk’s home operated by the townships. Also, Tax exemption and relief are provided for the disabled and women-headed families. In a word, the living conditions of vulnerable groups are not worsened due to construction, but bettered to the contrary.

8.4 Willingness to Move

As shown by follow-up monitoring of 82 people involved in 5 village platform subprojects in the respect of their willingness to move, 95% say yes, 10% higher than the figure shown in the last report, mainly because the percentage in Dongming is increased from 12% to 94%. This considerable increase in Dongming is largely attributable to the following reasons: (1) the villagers were previously concerned about the potential risk that the slope protection works would not be able to resist the scour of heavy rain, but the settlement of ground and the growth of turf over the past year have improved the sense of security; (2) the new homestead is 0.25 mu, relatively small, but very attractive to many families eager to have new houses (wedding); and (3) a lot of farmland is occupied by new village platforms and left idle for long, so the farmers hope for the earliest replacement. Some people in village platform subprojects are reluctant to move because: (1) the demand for flood control is already included in the their new houses completed recently, (2) without subsidies, they are unable to afford new houses by themselves; and (3) there has been recently a small flow in the Yellow River, without flood risks in the flood season.

As for the ability to complete housing within 2 years after the completion of village platforms, the percentage “yes” is 18%, which is 5% higher than that reported last time. This percentage in Miaozhai, Fanxian and Dongming is higher than that shown in the last report, but it

Page 42: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

38

remains the same in Wuqiu and declines by 8% in Pingyin. Failure to complete housing is mainly caused by the following reasons: (1) they are not able to afford or have built new houses recently; (2) they are hopeful of government subsidies for housing if saying “no”; (3) they wait to see. Refer to Table 25 for detailed figures.

Page 43: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

39

Table 25 Questionnaire for Willingness to Move Unit: person, %

Willing to Move? Able to Complete Housing within 2 Years after Completion of Platform?

Yes No Yes No No. Subproject M&E Subtotal People % People % Subtotal People % People %

Baseline survey 910 828 91 82 9 268 87 32 181 68 1st M&E 76 76 100 76 6 8 70 92 2nd M&E 99 88 89 11 11 99 9 9 90 91 3rd M&E 307 236 77 71 23 307 31 10 276 90 4th M&E 160 137 86 23 14 160 24 15 136 85 5th M&E 308 274 89 34 11 308 36 12 272 88 6th M&E 150 132 88 18 12 150 19 13 131 87 7th M&E 82 80 98 2 2 82 15 18 67 82

Total

Grand total 2092 1851 88 241 12 1450 227 16 1223 84 Baseline survey 90 86 96 4 4 1st M&E 38 38 100 38 4 11 34 89 2nd M&E 40 40 100 40 5 13 35 87 3rd M&E 37 34 92 3 8 37 37 100 4th M&E 18 18 100 18 1 6 17 94 5th M&E 50 50 100 50 50 100 6th M&E 37 37 100 37 37 100

1 Miaozhai

7th M&E 20 20 100 20 2 10 18 90 Baseline survey 117 101 86 16 14 1st M&E 38 38 100 38 2 5 36 95 2nd M&E 59 48 81 11 19 59 4 7 55 93 3rd M&E 55 45 82 10 18 55 55 100 4th M&E 38 31 82 7 18 38 1 3 37 97 5th M&E 31 31 100 31 31 100 6th M&E 30 30 100 30 30 100

2 Wuqiu

7th M&E 17 16 94 1 6 17 17 100 Baseline survey 217 215 99 2 1 1st M&E 2nd M&E 3rd M&E 59 52 88 7 12 59 15 25 44 75 4th M&E 22 19 86 3 14 22 9 41 13 59 5th M&E 30 30 100 30 3 10 27 90 6th M&E 9 8 89 1 11 9 9 100

3 Fanxian

7th M&E 15 15 100 15 1 7 14 93 Baseline survey 218 205 94 13 6 1st M&E 2nd M&E 3rd M&E 4th M&E 19 18 95 1 5 19 4 21 15 79 5th M&E 6th M&E 16 2 12 14 88 16 16 100

4 Dongming

7th M&E 18 17 94 1 6 18 9 50 9 50 Baseline survey 268 221 82 47 18 268 87 32 181 68 1st M&E 2nd M&E 3rd M&E 156 105 67 51 33 156 16 10 140 90 4th M&E 63 51 81 12 19 63 9 14 54 86 5th M&E 197 163 83 34 17 197 33 17 164 83 6th M&E 58 55 95 3 5 58 19 33 39 67

5 Pingyin

7th M&E 12 12 100 12 3 25 9 75

9. EVALUATION AND RECOMMENDATION

9.1 Experience and Inspiration

Having performed 7 M&E campaigns, the External Monitor has obtained experience and inspiration from discussions and interviews with the Employer, Implementing Agency and affected villages/households time and again, including analysis and comparison of findings.

Page 44: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

40

(1) Outcome of implementation. Implementation of the ADB-loaned Yellow River Flood Management Sector Project greatly improves the dike safety, especially the resistance to extreme floods. Despite the adverse impacts on the production and livelihood of some farmers, thanks to the dissemination of relevant resettlement agencies and Implementing Agencies and the implementation of appropriate compensation policies, the local farmers have fully understood and accepted the project. In addition, along with the accelerated pace of urbanization in China, farmers have changed greatly their concepts, considering farmer workers and business activities as their major sources of income, rather than taking the land as the sole source. Therefore, the implementation is generally successful, particularly the dike, risky spot and river training subprojects. Efficacy and efficiency are obvious and accepted by all parties, including the majority of affected people.

(2) The mode of ADB-loaned project management has changed the previous concept of project implementation management and improved the resettlement management at all levels. Such mode differs from previous Yellow River land acquisition and resettlement management in the follow aspects:

a. Operation System: Special planning and design of resettlement are developed and then assigned, in the form of agreement (contract) to local governments and special agencies or groups for implementation. The local governments and the Yellow River bureaus are involved in management and resettlement M&E mechanism introduced as a pioneering practice, causing resettlement work to look towards standardization.

b. Process and mode of management: A series of adequate procedures are provided for disbursement and settlement from upper to lower levels. Proper statistic statements and strict procedures are formulated for signing payment, to enable examination and check.

c. Open and transparent information, fairly satisfied with payment: (a) Compensation rates are open, and published in some subprojects by the county government in the form of public notices; (b) notices of entitlements are provided; (c) policies are published promptly and disseminated adequately; (d) compensations are paid at the published or agreed rates.

d. Forceful efforts for supervision: (a) The State Audit Administration conducts overall auditing of the project each year; (b) the executive authorities and Employers carry out irregular inspections each year; (c) the local governments make more efforts in management, together with irregular inspection and special auditing.

e. Attention to vulnerable groups, to reflect the people-oriented concept: Some subprojects necessitate the resettlement of many households, most of which are able to do by themselves, but a few have difficulties in affording new houses. They are provided with relief and properly resettled, e.g. in Mudan, Dongming and Juancheng. This has received much public praise.

Page 45: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

41

In a word, joint management of the local governments and the Yellow River bureaus is helpful for improving coordination, keeping aware of the actual conditions in townships and villages, especially villages, and treating problems more smoothly. Management on the basis of agreement (contract) is more legal and effective, meeting the “Regulations for Land Compensation and Resettlement in Major Water and Hydropower Projects” (Decree No. 471 of the State Council), which stipulates that “the Employer shall sign a resettlement agreement, according to the approved resettlement plan, with the provincial, autonomous region, municipal or city/county government of the resettlement area or host area”. The preparation and implementation of resettlement plans and action plans help cost and schedule control and safeguard the legal interests of affected people.

(3) Next steps for further improvement

a. Adequate attention should be paid to the efficiency of coordination between different departments or organizations during resettlement management and implementation.

b. Agreements (contracts) signed separately by projects, specialties and regions will be more beneficial for management. Standard agreements (contracts) will be provided.

c. Resettlement plans and action plans will be detailed further to be more operable, with differences in regions and projects taken into account. For example, the plans and designs of physical relocation should consider the flow direction of the Yellow River, which generally cuts through Henan Province from east to west and passes through Shandong from south to north locally, where most rural houses face south. Therefore, the plans of subprojects in Shandong and Henan should consider different conditions, to fully reflect the people-oriented concept.

d. Integrated guidelines for resettlement management will be provided.

9.2 Conclusions

(1) Compensation rates

A. Dike and river training subprojects

a. In the course of implementation, compensation rates are based on government notices and agreements in addition to the RP and IS.

b. Permanent land acquisition happens in 32 subprojects, 69% of which uses the rates fixed in the RP or IS, 25% applies those published in county government notices, and only 6% adopts agreed rates. Refer to Table 26.

c. Temporary land occupation happens in 45 subprojects, 65% of which uses the rates fixed in the RP or IS, 20% applies those published in county government notices, and 15% adopts agreed rates. Refer to Table 26.

Page 46: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

42

d. A total number of 7 subprojects involves physical relocation, including 43% uses the rates set forth in the RP or IS, while the rest 57% applies those published in county government notices. Refer to Table 26.

e. Price adjustment is made to the permanent land use for Kaifeng in Kaifeng Outskirts, temporary land use for treading in Juancheng and brick-concrete housing in Mudan only during implementation.

f. The current rates for permanent land use, either the published, or agreed or adjusted rates, are basically below the RP or IS, while those for temporary land use are over those fixed in the IS. The rates for physical relocation are all lower than as fixed in the RP or government notices.

Table 26 Basis of Current Compensation Rates Permanent Land Use

Temporary Land Use

Physical Relocation No. Basis

Number % Number % Number % 1 RP or IS 22 69 26 65 3 43 2 Government notice 8 25 8 20 4 57 3 Agreement 2 6 6 15

Number of subprojects 32 40 7 Total % of implemented subprojects (46) 70 87 15

B. Village platform subprojects

The compensation rates for the 5 village platform subprojects are based on the RP, IS and government notices, and different from one place to another during implementation. The standards and forms compensation are determined by the local government.

(2) Payment

a. By the time of this M&E, 315.83 million RMB has been paid as direct costs for dike, risky spot and river training subprojects, taking up 88% of the total, 56.70.77 million RMB more than the amount reported last time.

b. With an additional amount of 6.2563 million RMB paid according to the duration of occupation and progress of land adjustment or physical relocation, the cumulative payment for village platform subprojects amounts to 23.9901 million RMB.

(3) Permanent land acquisition and economic rehabilitation

a. The completed area for the permanent use of 37 subprojects by the time of this M&E is 21,946.36 mu, taking up 87.2% and 90.3% of the RP and IS respectively, 1,686.97 mu or 8.3% more than the figure reflected in the last report, or 8.3%.

b. Permanent land use for 32 dike, risky spot and river training subprojects involves a lot, including 249 villages, 588 groups, 19,789 households and 85,734 people, with a per capita loss of 0.12 mu, which takes up 8.2% of the original area of 1.457 mu. The mode of economic rehabilitation is basically determined, with Options A chosen by

Page 47: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

43

58.2 Groups, Option B by 34.2% and Option C by 7.3% respectively. The mode for the rest groups is still under discussion.

c. As for economic rehabilitation for the 5 village platform subprojects, land adjustment between villages/groups and within groups in village platform subprojects is arranged according to a balance between project benefits and disbenefits, with land adjusted between 53% villages and between/within 60% groups, 3% and 2% higher than the percentage reported last time.

(4) Temporary land occupation and restoration

a. Temporary land use for the 45 implemented subprojects involves 319 villages, with a completed area of 49,151.59 mu, taking up 84.5% and 83.7% of the RP and IS respectively, 8,182.97 mu or 20% more than the figure reported last time.

b. The land for the temporary use of dike, risky spot and river training subprojects has been restored by 76.8%, versus 68% for village platform subprojects. The remaining land, mostly fresh floodland for pumping purposes, will be restored when flooded.

(5) Income recovery

a. More than 80% of the affected people do not think their family incomes are greatly affected as result of land acquisition, and 40% have used their land compensations for the purpose of farming development.

b. About 90% households in the completed subprojects have reached or exceeded their original income levels, versus 66% in the follow-up monitoring subprojects. As the recovery time extends, more and more households will achieve income recovery and join non-poor people. Also, the speed of income recovery in 2/3 subprojects is higher than the growth rate in the project area.

c. Even the sample households having lost much land are subject to minor impacts, to say nothing of those having lost less land.

(6) Physical relocation and housing restoration

a. Land use for dike and 11 village platform subprojects necessitates physical relocation of 927 households, 97.5% of which have been relocated. Homesteads are identified for all the 824 households in need, including 80% having built new houses. The total number of resettlement families includes 69.7% resettled permanently by building or buying houses and 9.7% living in other houses elsewhere, and 20.6% temporarily by renting, borrowing and constructing temporary dwellings.

b. Main works for village platforms are completed, but infrastructures are still under construction or are to be started. Housing is started in Pingyin.

c. The baseline census and 1st-7th M&E results of 2,092 people in 5 village platform subprojects indicate that more than 88% people are willing to move because of flood

Page 48: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

44

risks, but only 16% are able to complete housing within 2 years the completion of village platforms, while the rest 84% are unable to make it due to economic and other reasons.

(7) Reconstruction of schools

a. Altogether 4 primary schools are involved.

b. Liuzhuang in Kaifeng and Xuji and Yantan in Dongming are completed, where the schooling conditions are bettered and orders are resumed.

c. An obvious progress has been made in reconstructing Donglou School, with 4.5 mu acquired as new site and 13 rooms (310 m2) completed. Pupils in higher grades are studying at the central primary school, and Grades 1 and 2 previously staying in rent rooms are moved to the new school, where the conditions and circumstances are improved.

(8) Protection of rights and interests

a. Training for resettlement staff is fine and technical training for the affected people is implemented by some subprojects, with good results achieved. The affected people are willing to be trained.

b. Help for moving poor families is promised by the local government, rehabilitation of vulnerable groups in dike subprojects is helped by townships and villages;

c. Vulnerable groups enjoy the equal rights as other villagers in land compensation and resettlement, the local government has clearly promised to help move the poor families in village platform subprojects, but case-specific preferential policies are not provided by other subprojects.

9.3 Problems and Recommendations

The problems identified in the last report are solved as follows:

(1) Lower compensation rates for some subprojects: Dongming and Mudan Implementing Agencies have prepared detailed action plans and submitted to the Employer, with the balance used for the purpose of bridges, roads, canals, streets and other public services. The previous balance in Dongming has been paid by 56%, with the remaining being under implementation.

(2) Payment: Compensations for the permanent land use of Huangzhai, Huozhai, Baocheng and Gaocun are paid in full to townships and villages by the county land bureau, while those for the permanent land use of break forests are paid to households. Payment of direct costs for Kaifeng and Lankao is finished except for an additional budget for young crops due to permanent land use (775,400 RMB for Kaifeng and 437,800 for Lankao).

(3) Training for skills: Technical training for the affected people begins to draw attention.

Page 49: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

45

Training programs for cropping, animal raising and other skills have been prepared for 12 out of 44 subprojects in the need of such training, and implemented by 5 (refer to Sub-section 8.1 above).

(4) Land restoration: A progress has been made in land restoration. An additional area of 1,000 mu has been restored in Dongming, where the remaining land includes 788 mu for pumping (53 mu farmland), 1,904 mu for excavation (563 mu farmland) and 29 mu for treading (for canals). The restored area in Lankao (152) is enlarged by 334.47 mu, but it is difficult to restore the remaining land operated to a depth of 8-10. Both Implementing Agencies and affected people have promised to restore the land step by step in combination with other new projects.

(5) Reconstruction of schools: A progress has been achieved in reconstructing Donglou School, with new rooms built and operation into service. Land leveling for Liuzhuang School is finished and an access road is built.

(6) Drainage in construction: As construction comes to an end, this is no longer a problem in Mudan. In Juancheng where construction was just finished, drainage impacts by pumping works will be eliminated step by step. Compensations have been paid for the houses and crops previously inundated in a few villages, e.g. 600 RMB/mu in Juancheng.

Outstanding problems together with recommendations are summarized in Table 27.

Table 27 Summary of Outstanding Problems and Recommendations No. Problem Description Recommendation

(1) Inadequate work is done in technical training for affected people.

Prepare and implement training programs as soon as possible.

1 Economic rehabilitation (2) Land restoration in Puyang and Dongpinghu (77) is

partly unfinished, or the standard is inadequate, rather difficult for farmers to restore alone in the near future.

The relevant departments pay attention to this and help the villagers achieve land restoration as soon as possible.

2 Impact on livelihood

(3) Poor drainage in Juancheng remains a problem somewhere.

The Implementing Agency cause proper treatment.

10. RESPONSE TO RELEVANT QUESTIONS IN ADB’S AIDE MEMOIRE

Table 28 below responds to the “ADB’s Discussion Notes on Monitoring and Evaluation (M&E) Report No. 6”, which is copied and included in the table as “ADB’s Comments”.

Table 28 Response to ADB’s Comments ADB’s Comments Response of External Monitor

1. ADB comments (from RSES) were provided to YRCC Resettlement Office, the external monitor, and discussed during the Review Mission.

The External monitor has received and fully understood the ADB Comments.

2. The M&E Reports should compare progress and achievements against the RPs. The Implementation Scheme is an updated set of impacts and revised budget, but the standards should be no lower than the approved RPs. One explanation in the summary section would be sufficient to clarify this. 3. The report should clearly explain the reason for the lower

Both Reports 6 and 7 delineate the reasons of lower standards in Sections 2.1.1-2.1.3 “Compensation Rates”, and describe the measures for treating the resultant balance of resettlement costs.

Page 50: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

46

compensation rates. ADB recognizes that the reasons were given in earlier M&E Reports but since this is now a major remaining issue, the current M&E Reports should briefly summarize the reasons why lower rates were paid and what measures have been taken to mitigate this issue. 4. The Provincial Audit Bureaus and YRCC Supervision collect spot checks on resettlement fund disbursement, the Mission was pleased to learn that the external monitor has collected accurate information on disbursements made by YRCC and the subsequent disbursements by local government to affected persons. In this manner, it is possible to determine where the un-disbursed amounts are and follow-up actions can be expedited. The external monitor also clarified that since the funds were approved by NDRC/MWR, they must be spent on rehabilitation measures for the affected persons according to national regulations. ADB requested the external monitor to (i) participate in the preparation of the Action Plan, (ii) ensure there is adequate consultation and disclosure to affected villages and (iii) monitor expenditures to ensure the affected persons will benefit.

This is responded to in Report No. 7, “2.1.4 Payment”.

5. Now that the Project is approaching completion, the M&E Reports should provide a balanced evaluation of both the positive and negative achievements and the lessons learned.

Refer to Report 7, “9.1 Experience and Inspiration”.

6. There was significant discussion regarding the evaluation sections on income restoration. Section 7 is the main section (in both the summary report and the separate appendixes) but section 7.4 (and Table 2) is out of place since it deals only with the impact of the land loss; it should come earlier so the reader can understand the change in incomes before and after impacts and compare the actual results. The conclusion (Section 7.5) says incomes are higher, but the key numbers are not presented here. How did compensation and rehabilitation measures help APs restore their incomes? Also, the concluding sections of the appendixes for the completion reports again summarize the income loss caused by land loss, rather than the actual income changes. The evaluation should focus on the latter and highlight those villages or households where incomes have not been restored. 7. The income analysis should have a representative baseline. The year 2003 was selected but in Kaifeng and Lankao Counties, incomes were affected by floods, so the base year incomes need to be adjusted to reflect a more normal year. Also, the target income should consider average rural income increases to ensure the APs have kept up with the other villagers in the Project area. 8. The income analysis should be more thorough in order to assess (i) the income effects for seriously affected households and (ii) the difference between villages that selected land adjustment, cash compensation or replacement land. The data is available so only further analysis is required; results can then be summarized in the M&E Reports. 9. The approach to survey sample households is the key method for evaluating income restoration, but such results can be supported by (i) conducting focus group discussions with village groups (e.g., to see how funds were spent and which rehabilitation measures worked best) and (ii) assessing changes in

This Report No. 7 discusses in detail the income recovery of affected people through analysis (quantitative and qualitative) of sample households in different types, trend of income growth in the subproject areas, and interview with typical households (with more land loss). Refer to “7 Income Recovery”.

Page 51: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

47

village statistics (e.g., average income growth, farm output, share of income from farming, and average expenditures). This information will help to isolate and explain the changes related to resettlement impacts and the compensation and rehabilitation measures. 10. The evaluation reports should provide gender disaggregated data and include gender assessment of impacts, living conditions, livelihood changes and income generation.

Such data are collected, but China’s livelihood is based on family units, where all members, male or female, are equal, so it is hard to distinguish the impacts, living conditions, livelihood changes and income generation by sex.

11. The external monitor should participate in the formulation of the Training Plans, since they have good insight on income effects and income restoration. Training should be based on villager’s needs and the most effective training courses and methods. The people to be trained should target (i) those most seriously affected, (ii) those who are vulnerable or facing difficulties due to resettlement impacts, and (iii) at least 50% should be women (i.e., since they tend to be less mobile, this should focus on home-based income generation activities). Although some vulnerable people may be too old for training, training/education can be provided for their children or a close relative. Livelihood development training should also be provided to village leaders to ensure the household and village strategies are implemented well and sustainable. The Training Plan will utilize project funds but should be integrated with the local government training programs to have greater impact.

Refer to Report 7, “8.1 Training”.

12. The external monitor agreed that the draft Action Plan addresses the main resettlement problems. They will place special focus on monitoring the Action Plan progress in the next M&E Report. Other investigations and problem identification will be continued so that less significant problems are still resolved in a timely manner (e.g., drainage problems, land adjustment and house construction).

Action Plans are arranged for the balance of some subprojects, e.g., Dongming, Mudan, Juancheng dike, , Huangzhai, Huozhai, Baocheng and Gaocun. These plans are mostly oriented to public services such as bridges, roads, canals and streets. Now they are under implementation.

13. Finally, continued attention should be placed on vulnerable groups and the measures taken and results should be documented in the M&E Reports. Since some subprojects have remaining funds to disburse, this is a good opportunity to target vulnerable affected households, including those having difficulties in restoring their livelihood.

Refer to Report 7, “8.3 Vulnerable Groups”.

Page 52: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

48

ANNEX 0-1 BASELINE CENSUS AND FOLLOW-UP FOLLOWING RESULTS

Annex 0-1 Baseline Census and Follow-up Monitoring Results Baseline Census 7th M&E Cumulative

Sample Household No. Subproject Village Group

Village Group Home People Village Group Home People Village Group Home People

Total 46 286 760 134 405 1846 8479 117 176 317 1473 619 988 4264 196091 Dike 191 448 90 223 833 3993 64 86 197 925 420 518 2397 10466

1.1 Yuanyang 36 139 13 26 112 559 12 29 50 247 40 72 221 1112 1.2 Kaifeng 15 46 9 25 121 608 2 3 17 77 46 122 507 2068 1.3 Lankao (152) 7 16 3 12 26 123 1 1 4 19 10 30 81 232 1.4 Lankao (135) 4 15 4 12 35 182 1 2 5 30 9 23 70 326 1.5 Puyang 12 48 9 23 120 522 8 20 41 186 29 66 249 1101 1.6 Dongming 44 103 28 78 322 1555 23 11 33 159 207 93 926 4212 1.7 Mudan 12 43 7 20 41 185 14 9 19 86 54 65 132 561 1.8 Juancheng 4 13 4 13 28 125 3 11 28 121 11 24 157 646 1.9 Dongpinghu (55) 38 15 4 4 10 44 4 12 26 108 1.10 Dongpinghu (77) 9 10 9 10 18 90 10 11 28 100 1.11 Dongpinghu (10) 10

2 Village platform 40 172 40 172 967 4280 12 27 70 354 93 278 1689 8712 2.1 Miaozhai 4 10 4 10 110 550 3 5 9 55 7 19 224 488 2.2 Wuqiu 3 23 3 23 118 559 3 9 17 87 6 27 238 564 2.3 Fanxian 9 46 9 46 253 1053 1 5 14 69 1 69 407 3412 2.4 Dongming 11 42 11 42 218 1063 2 4 18 96 38 46 334 3520 2.5 Pingyin 13 51 13 51 268 1055 3 4 12 47 41 117 486 728 3 Risky spot 28 57 5 1 2 8 48 78 92 119

3.1 Huayuankou 2 2 3 3 3.2 Madu 2 2 2 2 3.3 Zhaokou 3.4 Yangqiao 3.5 Jiubao 3.6 Heigangkou 1 1 1 1 3.7 Dongbatou 1 1 1 1 5 5 3.8 Huangzhai 6 18 9 18 5 26 3.9 Huozhai 3 4 5 10 27 27 3.1 Baocheng 2 11 2 11 3.11 Gaocun 4 12 10 22 42 42 3.12 Weishan 3 6 3 6 6 6 3.13 Fanpo 3 4 3 4 3.14 Likou 3.15 Liuzhuang 5 5 1 2 8 10 1 2 8

4 River training 27 83 4 10 46 206 36 62 48 186 58 114 86 312 4.1 Zhangwangzhuang 3 9 4 1 7 1 5 17 4.2 Dong’an 4 16 5 2 9 18 6 20 4.3 Laotian’an 1 1 2 4.4 Wuzhuang 2 9 1 1 5 20 1 1 5 36 3 4 5 36 4.5 Mao’an 4 14 6 12 5 31 10 26 5 31 4.6 Gucheng 1 1 1 4.7 Caogang 1 1 2 5 5 1 2 5 5 4.8 Shunhejie 2 8 2 8 32 138 2 8 20 54 4 16 40 119 4.9 Taohuayu 1 5 1 1 2 2 3 4 4.10 Baohezhai 1 1 4.11 Zhaokou 1 1 4.12 Weitan 2 20 5 4 6 11 4.13 Heigangkou 2 2 6 3 6 4.14 Fujunsi 1 1 1 3 12 1 1 3 12 4.15 Laozhaizhuang 1 2 1 1 9 48 6 25 9 48 7 27 14 68

Page 53: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

49

ANNEX 0-2 APPROVAL & IMPLEMENTATION OF RESETTLEMENT BUDGETS

Annex 0-2-1 Approval & Implementation of Resettlement Budgets Unit: 104 RMB

Approved Additional Total No. Subproject Index Land

AcquisitionDirect Cost

Land Acquisition

Direct Cost

Land Acquisition

Direct Cost

Agreed Completed

1. Permanent land use 14262.45 13732.74 2. Temporary land use 7345.37 6543.08 3. Housing 2565.39 2291.94 4. School 149.73 128.27 5. Special facility 5654.69 5234.68 6. Appurtenance & others 4962.53 3652.28

Subtotal

35870 32953 9515.4 2926.38 45385.37 35879.38

34940.15 31583.0 % of approved 106.0 95.8 % of IS 97.4 88.0

Total

% of agreed 90.4 1. Permanent land use 13511.16 13089.70 2. Temporary land use 6306.45 5738.57 3. Housing 2506.27 2234.52 4. School 149.73 128.27 5. Special facility 5047.07 4640.06 6. Appurtenance & others 4182.60 2971.67

Subtotal

32009 29413 9481.25 2890.51 41490.25 32303.51

31703.29 28802.79 % of approved 107.8 97.9 % of IS 98.1 89.2

1 Dike

% of agreed 90.9 1. Permanent land use 1471.97 1471.972. Temporary land use 2382.31 2382.315. Special facility 2643.09 2643.096. Appurtenance & others 705.99 705.99

Subtotal

7817 7187 1155.2 271.01 8972.2 7458.01

7203.36 7203.36 % of approved 100.2 100.2 % of IS 96.6 96.6

1.1 Yuanyang

% of agreed 100.0 1. Permanent land use 1731.57 1731.572. Temporary land use 864.74 864.744. School 76.2 76.25. Special facility 54.44 54.446. Appurtenance & others 100.01 100.01

Subtotal

2767 2563 1042.81 341.5 3809.81 2904.5

2826.96 2826.96 % of approved 110.3 110.3 % of IS 97.3 97.3

1.2 Kaifeng

% of agreed 100.0 1. Permanent land use 419.15 419.152. Temporary land use 60.24 60.243. Housing 340.32 340.325. Special facility 38.93 38.936. Appurtenance & others 52.96 52.96

Subtotal

886 814 318 119.35 1204 933.35

911.60 911.60 % of approved 112.0 112.0 % of IS 97.7 97.7

1.3 Lankao (135)

% of agreed 100.0 1. Permanent land use 373.37 373.372. Temporary land use 346.36 346.363. Housing 162.92 162.925. Special facility 123.94 123.946. Appurtenance & others 185.04 185.04

Subtotal

1248 1145 270.59 68.68 1518.59 1213.68

1191.63 1191.63 % of approved 104.1 104.1 % of IS 98.2 98.2

1.4 Lankao (152)

% of agreed 100.0 1. Permanent land use 1339.11 1339.112. Temporary land use 354.95 354.953. Housing 787.24 787.244. School 27.02 27.025. Special facility 148.75 148.756. Appurtenance & others 437.33 437.33

Subtotal

3021 2772 1024.1 499.81 4045.1 3271.81

3094.40 3094.40 % of approved 111.6 111.6 % of IS 94.6 94.6

1.5 Puyang

% of agreed 100.0

Page 54: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

50

Annex 0-2-2 Approval & Implementation of Resettlement Budgets Unit: 104 RMB

Approved Additional Total No. Subproject Index Land

AcquisitionDirect Cost

Land Acquisition

Direct Cost

Land Acquisition

Direct Cost

Agreed Completed

1. Permanent land use 6166.06 5874.66 2. Temporary land use 1236.08 951.00 3. Housing 748.36 642.654. School 46.51 25.05 5. Special facility 1280.32 1086.06 6. Appurtenance & others 1703.88 879.72

Subtotal

11141 10223 3823.68 958.22 14964.68 11181.22

11181.22 9459.14 % of approved 109.4 92.5 % of IS 100.0 84.6

1.6 Kaifeng

% of agreed 84.6 1. Permanent land use 1337.21 1306.482. Temporary land use 481.79 2803. Housing 74.31 58.715. Special facility 384.33 217.36. Appurtenance & others 392.58 196.65

Subtotal

2731 2506 926.52 164.89 3657.52 2670.89

2670.22 2059.14 % of approved 106.6 82.2 % of IS 100.0 77.1

1.7 Mudan

% of agreed 77.1 1. Permanent land use 373.78 284.982. Temporary land use 168.01 53.153. Housing 253.87 120.055. Special facility 36.51 3.936. Appurtenance & others 342.56 145.28

Subtotal

1140 1047 407.32 149.68 1547.32 1196.68

1174.73 607.39 % of approved 112.2 58.0 % of IS 98.2 50.8

1.8 Juancheng

% of agreed 51.7 1. Permanent land use 174.15 174.152. Temporary land use 85.03 85.033. Housing 1.9 1.95. Special facility 38.53 38.536. Appurtenance & others 36.88 36.88

Subtotal

107 99 331.84 252.03 438.84 351.03

336.49 336.49 % of approved 339.9 339.9 % of IS 95.9 95.9

1.9 Dongpinghu (15)

% of agreed 100.0 1. Permanent land use 124.79 114.262. Temporary land use 301.18 335.033. Housing 137.35 120.735. Special facility 147.23 134.096. Appurtenance & others 195.13 201.57

Subtotal

935 858 173.19 57.34 1108.19 915.34

905.68 905.68 % of approved 105.6 105.6 % of IS 98.9 98.9

1.10 Dongpinghu (77)

% of agreed 100.0 1. Permanent land use 2. Temporary land use 25.76 25.765. Special facility 151 1516. Appurtenance & others 30.24 30.24

Subtotal

216 199 8 8 224 207

207 207% of approved 104.0 104.0 % of IS 100.0 100.0

1.11 Dongpinghu (10)

% of agreed 100.0 1. Permanent land use 508.13 399.89 2. Temporary land use 702.22 476.92 3. Housing 59.12 57.42 5. Special facility 387.42 374.42 6. Appurtenance & others 450.01 361.58

Subtotal

2302 2113 -1.18 0.57 2300.82 2113.57

2106.90 1670.23 % of approved 99.7 79.0 % of IS 99.7 79.0

2 Risky spot

% of agreed 79.3

Page 55: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

51

Annex 0-2-3 Approval & Implementation of Resettlement Budgets Unit: 104 RMB

Approved Additional Total No. Subproject Index Land

AcquisitionDirect Cost

Land Acquisition

Direct Cost

Land Acquisition

Direct Cost

Agreed Completed

1. Permanent land use 2. Temporary land use 32.92 32.923. Housing 5.14 5.145. Special facility 70.57 70.576. Appurtenance & others 36.98 36.98

2.1 Huayuankou

Subtotal 145.61 145.611. Permanent land use 2. Temporary land use 12.2 12.25. Special facility 36.79 36.796. Appurtenance & others 13.87 13.87

2.2 Madu

Subtotal

222 204 4.41 4.41 226.41 208.41

62.86 62.86 % of approved 102.2 102.2 % of IS 100.0 100.0 2.1-2.2 % of agreed 100.0 1. Permanent land use 2. Temporary land use 27.32 27.323. Housing 6.62 6.625. Special facility 109.68 109.686. Appurtenance & others 24.03 24.03

2.3 Zhaokou

Subtotal 167.65 167.651. Permanent land use 2. Temporary land use 6.32 6.325. Special facility 39 396. Appurtenance & others 6.82 6.82

2.4 Yangqiao

Subtotal 52.14 52.141. Permanent land use 2. Temporary land use 1.57 1.575. Special facility 1.87 1.876. Appurtenance & others 5.54 5.54

2.5 Jiubao

Subtotal

249 229 -0.24 -0.24 248.76 228.76

8.98 8.98% of approved 99.9 99.9% of IS 100 1002.3-2.5 % of agreed 1001. Permanent land use 13.22 13.222. Temporary land use 5. Special facility 2.88 2.886. Appurtenance & others 7.25 7.25

Subtotal

31 28 -4.66 -4.66 26.34 23.34

23.35 23.35% of approved 83.4 83.4 % of IS 100.0 100.0

2.6 Heigangkou

% of agreed 100.0 1. Permanent land use 2. Temporary land use 6.26 6.263. Housing 9.84 9.845. Special facility 2.18 2.186. Appurtenance & others 11.56 11.56

Subtotal

33 30 -0.12 -0.12 32.88 29.88

29.84 29.84% of approved 99.5 99.5% of IS 99.9 99.9

2.7 Dongbatou

% of agreed 1001. Permanent land use 174.38 135.672. Temporary land use 186.97 100.62 3. Housing 1.98 1.98 6. Appurtenance & others 79.25 73.89

2.8 Huangzhai

Subtotal 442.58 312.16 1. Permanent land use 68.03 49.24 2. Temporary land use 68.68 35.86 6. Appurtenance & others 40.12 36.48

2.9 Huozhai Subtotal 176.83 121.58

1. Permanent land use 104.72 78.60 2. Temporary land use 102.89 52.26 3. Housing 23.86 23.86 5. Special facility 20.76 20.76 6. Appurtenance & others 66.21 60.05

2.10 Baocheng

Subtotal 318.44 235.52 1. Permanent land use 56.25 40.062. Temporary land use 78.15 58.62 3. Housing 3.73 2.03 5. Special facility 32.7 31.70 6. Appurtenance & others 35.28 44.17

2.11 Gaocun

Subtotal

1240 1138 1240 1138

206.11 176.58 % of approved 100.5 74.3 % of IS 100.5 74.3 2.8-2.11 % of agreed 74.3

Page 56: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

52

Annex 0-2-4 Approval & Implementation of Resettlement Budgets Unit: 104 RMB

Approved Additional Total No. Subproject Index Land

AcquisitionDirect Cost

Land Acquisition

Direct Cost

Land Acquisition

Direct Cost

Agreed Completed

1. Permanent land use 41.95 41.952. Temporary land use 44.67 44.673. Housing 1.05 1.055. Special facility 12.15 12.156. Appurtenance & others 10.76 10.76

2.12 Weishan

Subtotal 110.58 110.581. Permanent land use 20.78 20.782. Temporary land use 19.8 19.86. Appurtenance & others 17.84 17.84

2.13 Fanpo Subtotal

222 204 4.41 4.41 226.41 208.41

58.42 58.42% of approved 92.3 92.3% of IS 92.3 92.32.12-2.13 % of agreed 1001. Permanent land use 2. Temporary land use 38.67 38.675. Special facility 46.84 46.846. Appurtenance & others 5.6 5.6

Subtotal

98 89 -0.38 0.77 97.62 89.77

91.11 91.11% of approved 102.4 102.4% of IS 101.5 101.5

2.14 Likou

% of agreed 1001. Permanent land use 28.8 20.37 2. Temporary land use 75.8 39.83 3. Housing 6.9 6.95. Special facility 126. Appurtenance & others 88.9 6.74

Subtotal

229 212 0.34 0.34 229.34 212.34

212.4 73.84 % of approved 100.2 34.8 % of IS 100.0 34.8

2.15 Liuzhuang

% of agreed 34.81. Permanent land use 243.15 243.15 2. Temporary land use 336.70 327.59 5. Special facility 220.20 220.20 6. Appurtenance & others 329.92 319.04

Subtotal

1559 1427 35.3 35.3 1594.3 1462.3

1129.97 1109.98 % of approved 79.2 77.8 % of IS 77.3 75.9

3 River training

% of agreed 98.2 1. Permanent land use 39.05 39.052. Temporary land use 31.12 31.125. Special facility 6. Appurtenance & others 37.51 37.51

3.1 Zhangwangzhuang

Subtotal 107.68 107.681. Permanent land use 23.31 23.312. Temporary land use 11.27 11.275. Special facility 6. Appurtenance & others 17.22 17.22

3.2 Dong’an

Subtotal 51.8 51.81. Permanent land use 0.96 0.96 2. Temporary land use 24.43 24.43 5. Special facility 6. Appurtenance & others 7.99 7.99

3.3 Laotian’an

Subtotal

158 145 70.27 70.27 228.27 215.27

33.38 33.38 Total 192.86 192.86 % of approved 133.0 133.0 % of IS 89.6 89.6

3.1-3.3 % of agreed 100.0

Page 57: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

53

Annex 0-2-5 Approval & Implementation of Resettlement Budgets Unit: 104 RMB

Approved Additional Total No. Subproject Index Land

AcquisitionDirect Cost

Land Acquisition

Direct Cost

Land Acquisition

Direct Cost

Agreed Completed

1. Permanent land 11.05 11.05 2. Temporary land 18.16 18.16 5. Special facility 6. Appurtenance & 12.46 12.46

3.4 Wuzhuang

Subtotal 41.66 41.66 1. Permanent land 21.49 21.49 2. Temporary land 34.91 25.85. Special facility 6. Appurtenance & 26.15 15.27

3.5 Mao’an

Subtotal 82.55 62.561. Permanent land 15.67 15.672. Temporary land 15.10 15.10 5. Special facility 6. Appurtenance & 56.59 56.59

3.6 Shunhejie

Subtotal 87.36 87.361. Permanent land 13.04 13.042. Temporary land 43.77 43.775. Special facility 6. Appurtenance & 23.74 23.74

3.7 Gucheng

Subtotal 80.55 80.551. Permanent land 8.04 8.042. Temporary land 44.92 44.925. Special facility 6. Appurtenance & 15.96 15.96

3.8 Caogang

Subtotal

589 539 -107 -107 482 432

68.92 68.92Total 361.04 341.05 % of approved 67.0 63.3 % of total 83.6 78.9

3.4-3.8

% of agreed 94.5 1. Permanent land 14.27 14.27 2. Temporary land 2.13 2.13 5. Special facility 216.00 216.00 6. Appurtenance & 19.38 19.38

3.9 Taohuayu

Subtotal 251.78 251.78 1. Permanent land 17.71 17.71 2. Temporary land 2.62 2.62 5. Special facility 6. Appurtenance & 17.41 17.41

3.10 Baohezhai

Subtotal 37.73 37.73 1. Permanent land 2.24 2.24 2. Temporary land 19.02 19.02 5. Special facility 6. Appurtenance & 2.8 2.8

3.11 Zhaokou

Subtotal 24.06 24.061. Permanent land 29.74 29.74 2. Temporary land 5.15 5.15 5. Special facility 6. Appurtenance & 14.41 14.41

3.12 Weitan

Subtotal

372 343 26.11 26.11 398.11 369.11

49.30 49.30 Total 362.87 362.87 % of approved 105.8 105.8 % of total 98.3 98.3

3.9-3.12

% of agreed 100.0 1. Permanent land 1.76 1.762. Temporary land 7.24 7.245. Special facility 6. Appurtenance & 1.63 1.63

3.13 Heigangkou

Subtotal 10.63 10.631. Permanent land 2. Temporary land 28.58 28.585. Special facility 6. Appurtenance & 22.04 22.04

3.14 Fujunsi

Subtotal

64 59 2 2 66 61

50.62 50.62Total 61.25 61.25% of approved 103.8 103.8 % of total 100.4 100.4

3.13-3.14

% of agreed 1001. Permanent land 44.83 44.83 2. Temporary land 48.29 48.29 5. Special facility 4.2 4.26. Appurtenance & 54.63 54.63

Subtotal

376 341 43.92 43.92 419.92 384.92

151.95 151.95 % of approved 44.6 44.6

3.15 Laozhaizhuang

% of total 39.5 39.5

Page 58: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

54

% of agreed 100

Page 59: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

55

ANNEX 0-3 LAND ACQUISITION FOR IMPLEMENTED SUBPROJECTS

Annex 0-3-1 Land Acquisition for Implemented Subprojects Unit: mu, %

Permanent Land Use No. Subproject Item Total Subtotal Farmland Temporary Land Use Remarks

RP 83369.58 25169.01 19376.32 58200.57 IS 83043.13 24310.34 19157.78 58732.79 Agreed 76019.07 22229.23 18564.97 53789.84 Completed 71097.95 21946.36 18130.48 49151.59 % of RP 85.3 87.2 93.6 84.5 % of IS 85.6 90.3 94.6 83.7

Grand Total

% of agreed 93.5 98.7 97.7 91.4 RP 55014.95 15538.28 10051.24 39476.67 IS 55989.67 15465.15 10416.01 40524.52 Agreed 54101.98 14207.39 10659.00 39894.59 Completed 49809.27 14038.85 10377.11 35770.42 % of RP 90.5 90.4 103.2 90.6 % of IS 89.0 90.8 99.6 88.3

1 Dike

% of agreed 92.1 98.8 97.4 89.7

A total length of 133,990 m

RP 15294.63 3672.39 1616.01 11622.24 IS 15907.43 3392.01 1927.22 12515.42 Agreed 14733.02 2501.22 1890.58 12231.8 Completed 14733.02 2501.22 1890.58 12231.8 % of RP 96.3 68.1 117.0 105.2 % of IS 92.6 73.7 98.1 97.7

1.1 Yuanyang

% of agreed 100.0 100.0 100.0 100.0

A total length of 29,850 m

RP 6449.09 1410.4 951.51 5038.69 IS 6471.79 1410.4 897.23 5061.39 Agreed 6256.74 1341.03 1341.03 4915.71 Completed 6256.74 1341.03 1341.03 4915.71 % of RP 97.0 95.1 140.9 97.6 % of IS 96.7 95.1 149.5 97.1

1.2 Kaifeng

% of agreed 100.0 100.0 100.0 100.0

A total length of 8,432 m

RP 2113.06 414 311.9 1699.06 IS 2539.06 414 331.86 2125.06 Agreed 2579.92 360.17 360.17 2219.75 Completed 2579.92 360.17 360.17 2219.75 % of RP 122.1 87.0 115.5 130.6 % of IS 101.6 87.0 108.5 104.5

1.3 Lankao (152)

% of agreed 100.0 100.0 100.0 100.0

A total length of 3,450 m

RP 1155.42 358.92 243.05 796.5 IS 1200.83 404.33 302.4 796.5 Agreed 763.26 404.33 404.33 358.93 Completed 763.26 404.33 354.53 358.93 % of RP 66.1 112.7 145.9 45.1 % of IS 63.6 100.0 117.2 45.1

1.4 Lankao (135)

% of agreed 100.0 100.0 87.7 100.0

A total length of 2,662 m

RP 3664.41 1363.43 1363.43 2300.98 IS 3876.2 1516.68 1516.68 2359.52 Agreed 3380.88 1256.2 1256.2 2124.68 Completed 3380.88 1256.2 1256.2 2124.68 % of RP 92.3 92.1 92.1 92.3 % of IS 87.2 82.8 82.8 90.0

1.5 Puyang

% of agreed 100.0 100.0 100.0 100.0

A total length of 9,270 m

RP 19396.76 6370.06 4235.04 13026.7 IS 18948.74 6343.04 3849.95 12605.7 Agreed 19847.88 6419.76 3874.13 13428.12 Completed 17052.6731 6258.67 3594.5 10794 % of RP 87.9 98.3 84.9 82.9 % of IS 90.0 98.7 93.4 85.6

1.6 Dongming

% of agreed 85.9 97.5 92.8 80.4

A total length of 34,893 m

RP 3609.01 1402.55 940.43 2206.46 IS 3480.72 1274.26 1026.42 2206.46 Agreed 3480.72 1274.26 1026.42 2206.46 Completed 2388.38 1228.99 1093.5 1159.39 % of RP 66.2 87.6 116.3 52.5 % of IS 68.6 96.4 106.5 52.5

1.7 Mudan

% of agreed 68.6 96.4 106.5 52.5

A total length of 9,733 m

RP 1185.66 392.22 235.56 793.44 IS 1185.69 392.22 313.29 793.47 Agreed 1185.69 392.22 313.29 793.47 Completed 746.25 395.76 293.75 350.49 % of RP 62.9 100.9 124.7 44.2 % of IS 62.9 100.9 93.8 44.2

1.8 Juancheng

% of agreed 62.9 100.9 93.8 44.2

A total length of 2,300 m

Page 60: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

56

Annex 0-3-2 Land Acquisition for Implemented Subprojects Unit: mu, %

Permanent Land Use No. Subproject Item Total Subtotal Farmland Temporary Land Use Remarks

RP 330.8 2.71 2.71 328.09IS 480.84 166.61 99.36 314.23Agreed 499.97 158.5 93.15 341.47Completed 499.97 158.5 93.15 341.47% of RP 151.1 5848.7 3437.3 104.1 % of IS 104.0 95.1 93.8 108.7

1.9 Dongpinghu (55)

% of agreed 100.0 100.0 100.0 100.0

A total length of 22,300 m

RP 1675.98 151.6 151.6 1524.38IS 1675.08 151.6 151.6 1523.48Agreed 1148.715 99.7 99.7 1049.015Completed 1182.995 133.98 99.7 1049.015% of RP 70.6 88.4 65.8 68.8 % of IS 70.6 88.4 65.8 68.9

1.10 Dongpinghu (77)

% of agreed 103.0 134.4 100.0 100.0

A total length of 11,100 m

RP 140.13 140.13IS 223.29 223.29Agreed 225.181 225.181Completed 225.181 225.181% of RP 160.7 160.7 % of IS 100.8 100.8

1.11 Dongpinghu (10)

% of agreed 100.0 100.0

RP 13750.24 4679.51 4646.26 9070.73IS 13750.24 4679.51 4646.26 9070.73Agreed 10770 4652.95 4652.95 6117.05Completed 10128.5 4652.95 4652.95 5475.55% of RP 73.7 99.4 100.1 60.4 % of IS 73.7 99.4 100.1 60.4

2 Village platform

% of agreed 94.0 100.0 100.0 89.5

RP 2056.66 634.36 634.36 1422.3IS 2056.66 634.36 634.36 1422.3Agreed 1148.56 570.23 570.23 578.33Completed 1148.56 570.23 570.23 578.33% of RP 55.8 89.9 89.9 40.7 % of IS 55.8 89.9 89.9 40.7

2.1 Miaozhai

% of agreed 100.0 100.0 100.0 100.0

Permanent land acquisition completed

RP 1356.38 597.38 597.38 759IS 1356.38 597.38 597.38 759Agreed 1285.75 591.81 591.81 693.94Completed 1285.75 591.81 591.81 693.94% of RP 94.8 99.1 99.1 91.4 % of IS 94.8 99.1 99.1 91.4

2.2 Wuqiu

% of agreed 100.0 100.0 100.0 100.0

Permanent land acquisition completed

RP 3869.33 1001.76 1001.76 2867.57IS 3869.33 1001.76 1001.76 2867.57Agreed 1892.37 1069.45 1069.45 822.92Completed 1892.37 1069.45 1069.45 822.92% of RP 48.9 106.8 106.8 28.7 % of IS 48.9 106.8 106.8 28.7

2.3 Fanxian

% of agreed 100.0 100.0 100.0 100.0

Permanent land acquisition completed, excluding service roads

RP 3170.05 1080.35 1047.1 2089.7IS 3170.05 1080.35 1047.1 2089.7Agreed 3145.5 1055.8 1055.8 2089.7Completed 2504 1055.8 1055.8 1448.2% of RP 79.0 97.7 100.8 69.3 % of IS 79.0 97.7 100.8 69.3

2.4 Dongming

% of agreed 79.6 100.0 100.0 69.3

Permanent land acquisition completed

RP 3297.82 1365.66 1365.66 1932.16IS 3297.82 1365.66 1365.66 1932.16Agreed 3297.82 1365.66 1365.66 1932.16Completed 3297.82 1365.66 1365.66 1932.16% of RP 100.0 100.0 100.0 100.0 % of IS 100.0 100.0 100.0 100.0

2.5 Pingyin

% of agreed 100.0 100.0 100.0 100.0

Permanent land acquisition completed

RP 5481.04 498.29 225.89 4982.75 IS 5548.07 528.50 458.33 5019.57 Agreed 4537.7 449.58 333.71 4088.12 Completed 4653.536 451.80 297.66 4201.74

3 Risky spot

% of RP 84.9 90.7 131.8 84.3

Page 61: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

57

% of IS 83.9 85.5 64.9 83.7 % of agreed 102.6 100.5 89.2 102.8

Annex 0-3-3 Land Acquisition for Implemented Subprojects Unit: mu, %

Permanent Land Use No. Subproject Item Total Subtotal Farmland Temporary Land Use Remarks

RP 412.09 32.83 379.26IS 412.07 32.83 379.24Agreed 369.73 369.73Completed 369.73 369.73% of RP 89.7 97.5% of IS 89.7 97.5

3.1 Huayuankou

% of agreed 100.0 100

RP 216.21 22.5 193.71IS 216.2 22.5 193.7Agreed 125.37 125.37Completed 125.37 125.37% of RP 58.0 64.7% of IS 58.0 64.7

3.2 Madu

% of agreed 100.0 100

RP 364.43 364.43IS 364.43 364.43Agreed 275.14 275.14Completed 275.14 275.14% of RP 75.5 75.5% of IS 75.5 75.5

3.3 Zhaokou

% of agreed 100.0 100

RP 96.5 0.8 95.7IS 96.5 0.8 95.7Agreed 85.72 85.72Completed 85.72 85.72% of RP 88.8 89.6% of IS 88.8 89.6

3.4 Yangqiao

% of agreed 100.0 100

RP 41.2 41.2IS 41.2 41.2Agreed 27 27Completed 27 27% of RP 65.5 65.5% of IS 65.5 65.5

3.5 Jiubao

% of agreed 100.0 100

RP 75.51 13.69 13.69 61.82IS 75.51 13.69 13.69 61.82Agreed 13.62 13.62Completed 13.62 13.62% of RP 18.0 99.5% of IS 18.0 99.5

3.6 Heigangkou

% of agreed 100.0 100

RP 55.5 55.5IS 55.5 55.5Agreed 62.77 62.77Completed 62.77 62.77% of RP 113.1 113.1% of IS 113.1 113.1

3.7 Dongbatou

% of agreed 100.0 100

RP 1275.17 146.53 35.52 1128.64IS 1271.69 146.53 131.59 1125.16Agreed 1271.69 146.53 131.59 1125.16Completed 1167.86 145.95 102.43 1021.91% of RP 91.6 99.6 288.4 90.5% of IS 91.8 99.6 77.8 90.8

3.8 Huangzhai

% of agreed 91.8 99.6 77.8 90.8

RP 472.74 60.04 24.2 412.7IS 472.62 60.04 60.04 412.58Agreed 472.62 60.04 60.04 412.58Completed 424.154 54.404 39.1 369.75% of RP 89.7 90.6 161.6 89.6% of IS 89.7 90.6 65.1 89.6

3.9 Huozhai

% of agreed 89.7 90.6 65.1 89.6

RP 688.93 85.74 48.64 603.19IS 718.18 92.43 92.43 625.75Agreed 718.18 92.43 92.43 625.75Completed 606.802 86.852 31.45 519.95

3.10 Baocheng

% of RP 88.1 101.3 64.7 86.2

Page 62: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

58

% of IS 84.5 94 34 83.1% of agreed 84.5 94 34 83.1

Annex 0-3-4 Land Acquisition for Implemented Subprojects Unit: mu, %

Permanent Land Use No. Subproject Item Total Subtotal Farmland Temporary Land Use Remarks

RP 543.71 49.65 21.74 494.06IS 530.9 49.65 49.65 481.25Agreed 530.9 49.65 49.65 481.25Completed 627.56 44.26 44.26 583.3% of RP 115.4 89.1 203.6 118.1% of IS 118.2 89.1 89.1 121.2

3.11 Gaocun

% of agreed 118.2 89.1 89.1 121.2

RP 262.72 36.66 36.66 226.06IS 260.11 42.5 42.5 217.61Agreed 260.49 44.09 216.4Completed 260.49 44.09 39.4 216.4% of RP 99.2 120.3 107.5 95.7% of IS 100.1 103.7 92.7 99.4

3.12 Weishan

% of agreed 100.0 100 100

RP 151.89 20.54 20.54 131.35IS 170.41 43.22 43.22 127.19Agreed 155.33 43.22 112.11Completed 155.33 43.22 21.62 112.11% of RP 102.3 210.4 105.3 85.4% of IS 91.2 100 50 88.1

3.13 Fanpo

% of agreed 100.0 100 100

RP 174.83 174.83IS 169.14 169.14Agreed 169.14 169.14Completed 164.19 164.19% of RP 93.9 93.9% of IS 97.1 97.1

3.14 Likou

% of agreed 97.1 97.1

RP 649.61 29.31 24.9 620.3IS 693.61 24.31 25.21 669.3Agreed Completed 287.8 19.4 19.4 268.4% of RP 44.3 66.2 33.4% of IS 41.5 66.2 31

3.15 Liuzhuang

% of agreed

RP 9123.35 4452.93 4452.93 4670.42IS 7755.15 3637.18 3637.18 4117.97Agreed 6609.40 2919.31 2919.31 3690.09 Completed 6506.65 2802.76 2802.76 3703.89 % of RP 71.3 62.9 62.9 79.3 % of IS 83.9 77.1 77.1 89.9

4 River training

% of agreed 98.4 96.0 96.0 100.4

RP 639 566 566 73IS 639 566 566 73Agreed 650.3 566 566 84.3Completed 650.3 566 566 84.3% of RP 101.8 100.0 100.0 115.5 % of IS 101.8 100.0 100.0 115.5

4.1 Zhangwangzhuang

% of agreed 100.0 100.0 100.0 100.0

RP 385.8 337.8 337.8 48IS 385.8 337.8 337.8 48Agreed 385.8 337.8 337.8 48Completed 385.8 337.8 337.8 48% of RP 100.0 100.0 100.0 100.0 % of IS 100.0 100.0 100.0 100.0

4.2 Dong’an

% of agreed 200.0 100.0 100.0 100.0

RP 483.16 159.93 159.93 323.23IS 440.13 116.9 116.9 323.23Agreed 336.385 13.9 13.9 322.485Completed 336.385 13.9 13.9 322.485% of RP 69.6 8.7 8.7 99.8 % of IS 76.4 11.9 11.9 99.8

4.3 Laotian’an

% of agreed 200.0 100.0 100.0 100.0

RP 687.17 352.47 352.47 334.7IS 687.17 352.47 352.47 334.7Agreed 494.78 160.08 160.08 334.7Completed 494.78 160.08 160.08 334.7% of RP 72.0 45.4 45.4 100.0 % of IS 72.0 45.4 45.4 100.0

4.4 Wuzhuang

% of agreed 100.0 100.0 100.0 100.0

RP 939.17 477.67 477.67 461.5IS 939.17 477.67 477.67 461.5Agreed 772.9 311.4 311.4 461.5Completed 772.9 311.4 311.4 461.5

4.5 Mao’an

% of RP 82.3 65.2 65.2 100.0

Page 63: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

59

% of IS 82.3 65.2 65.2 100.0 % of agreed 100.0 100.0 100.0 100.0

Annex 0-3-5 Land Acquisition for Implemented Subprojects Unit: mu, %

Permanent Land Use No. Subproject Item Total Subtotal Farmland Temporary Land Use Remarks

RP 579.09 379.09 379.09 200.0 IS 542.65 342.65 342.65 200.0 Agreed 426.72 227.04 227.04 199.68Completed 426.72 227.04 227.04 199.68% of RP 73.7 59.9 59.9 99.8 % of IS 78.6 66.3 66.3 99.8

4.6 Shunhejie

% of agreed 100.0 100.0 100.0 100.0

RP 1171.84 435.70 435.70 736.14IS 962.17 226.03 226.03 736.14Agreed 766.34 189 189 577.34Completed 766.34 189 189 577.34% of RP 65.4 43.4 43.4 78.4 % of IS 79.6 83.6 83.6 78.4

4.7 Gucheng

% of agreed 100.0 100.0 100.0 100.0

RP 1047.72 463.72 463.72 584.00 IS 932.72 348.72 348.72 584.00 Agreed 828.19 244.26 244.26 583.93Completed 711.64 127.71 127.71 583.93% of RP 67.9 27.5 27.5 100.0 % of IS 76.3 36.6 36.6 100.0

4.8 Caogang

% of agreed 85.9 52.3 52.3 100.0

RP 783.97 209.77 209.77 574.2IS 96.97 80.77 80.77 16.2Agreed 73.2 57 57 16.2Completed 87 57 57 30% of RP 11.1 27.2 27.2 5.2 % of IS 89.7 70.6 70.6 185.2

4.9 Taohuayu

% of agreed 118.9 100.0 100.0 185.2

RP 241.37 206.37 206.37 35IS 241.37 206.37 206.37 35Agreed 241.37 206.37 206.37 35Completed 241.37 206.37 206.37 35% of RP 100.0 100.0 100.0 100.0 % of IS 100.0 100.0 100.0 100.0

4.10 Baohezhai

% of agreed 100.0 100.0 100.0 100.0

RP 369.6 117.0 117.0 252.6IS 288.6 36.0 36.0 252.6Agreed 283.15 32.46 32.46 250.69Completed 283.15 32.46 32.46 250.69% of RP 76.6 27.7 27.7 99.2 % of IS 98.1 90.2 90.2 99.2

4.11 Zhaokou

% of agreed 100 100 100 100

RP 501 431 431 70 IS 501 431 431 70 Agreed 517.54 447.54 447.54 70 Completed 517.54 447.54 447.54 70 % of RP 103.3 103.8 103.8 100.0 % of IS 103.3 103.8 103.8 100.0

4.12 Weitan

% of agreed 100.0 100.0 100.0 100.0

RP 143.57 46.98 46.98 96.59IS 123.98 25.48 25.48 98.50 Agreed 137.62 25.48 25.48 112.14Completed 137.62 25.48 25.48 112.14% of RP 95.9 54.2 54.2 116.1 % of IS 111.0 100.0 100.0 113.8

4.13 Heigangkou

% of agreed 100.0 100.0 100.0 100.0

RP 570.1 197.4 197.4 372.7IS 378.3 378.26 Agreed 378.3 378.3 Completed 378.3 378.3 % of RP 66.4 101.5 % of IS 100.0 100.0 100.0 100.0

4.14 Fujunsi

% of agreed 100.0 100.0 100.0 100.0

RP 580.79 72.03 72.03 508.76IS 596.16 89.32 89.32 506.84Agreed 316.8 100.98 100.98 215.82Completed 316.8 100.98 100.98 215.82% of RP 54.5 140.2 140.2 42.4 % of IS 53.1 113.1 113.1 42.6

4.15 Laozhaizhuang

% of agreed 100.0 100.0 100.0 100.0

Note: Farmland for the permanent use of river training subprojects is totally floodland.

Page 64: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Resettlement M&E Main Report (Report No. 6)

60

Page 65: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

56

ADB-loaned Yellow River Flood Management Sector Project

Yuanyang (Left Bank 100+800~124+700, 142+400~148+350)

Dike Consolidation

RESETTLEMENT M&E REPORT (Report No. 6)

Henan Huanghe Resettlement Economic Development Company

December 2007

Appendix 1

Page 66: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 6)

57

Approved: Yang Jianshe

Reviewed: Zhang Hao, Zuo Ping

Task Manager: Zuo Ping

Team Leader: Yun Lu

Chief Editor: Yun Lu

Proofreader: Jiao Lili, Zhao Huan’e, Wang Jianzhong, Yang Tao

Contributors: Cao Shurong, Chen Aiqin, Feng Jianmin, Guan Guosheng, Liu Xin,

Li Yuan, Shen Yanlong, Sun Jupei, Wang Jianzhong, Yang Jianshe,

Yang Tao, Yun Lu, Zhang Hao, Zuo Ping Duan Wei

Page 67: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 6)

58

Table of Contents

1. GENERAL ___________________________________________________________59

1.1 Project Brief ____________________________________________________59

1.2 Monitoring and Evaluation ________________________________________ 59

2. DISBURSEMENT AND PAYMENT ______________________________________60

2.1 Compensation Rates ______________________________________________60

2.2 Disbursement and Payment ________________________________________61

3. PERMANENT LAND USE AND ECONOMIC REHABILITATION ___________ 61

4. TEMPORARY LAND OCCUPATION AND RESTORATION ________________63

5. INCOME RECOVERY_________________________________________________66

5.1 Constituents and Changes of Incomes _______________________________66

5.2 Income Constituents and Changes in Option A and Option B ____________68

5.2.1 Option A____________________________________________________________68

5.2.2 Option B____________________________________________________________71

6. PROTECTION OF RIGHTS AND INTERESTS____________________________73

6.1 Training for Skills ________________________________________________ 73

6.2 Vulnerable Groups _______________________________________________ 73

7. EVALUATION AND RECOMMENDATION ______________________________73

7.1 Settlement of Earlier Problems _____________________________________ 73

7.2 Evaluation and Recommendations __________________________________ 73

Annex 1 Schedule of Incomes of Sample Households in 2004 ____________________75

Annex 2 Schedule of Incomes of Sample Households in 2005 ____________________76

Annex 3 Schedule of Incomes of Sample Households in 2006 ____________________77

Page 68: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

59

1. GENERAL

1.1 Project Brief

Yuanyang dike consolidation (100+800~124+700 and 142+400~148+350 sections on the left bank) is a subproject (referred to as the “Yuanyang Subproject” hereinafter) of the ADB-loaned Yellow River Flood Management Sector Project, with a total length of 29.85 km. This part of dike consolidation is implemented by warping with a design width of 80 m.

Xinxiang Yellow River Service acts as the Employer, with Yellow River Engineering Co., Ltd. appointed as the Designer. Yuanyang County has set up a Leading Group to function as the Implementing Agency in charge of land acquisition and resettlement.

The total budget approved by the State for this subproject is 394.96 million RMB, including 78.17 million RMB for land acquisition and resettlement (including 71.87 million RMB direct resettlement costs). By the time of this M&E, an additional amount of 11.552 million has been approved, including 2.7101 million RMB direct cost, which is 1.6362 million RMB more than the figure included in the approved budget. According to letter Nos.[2006]119 and [2007]90 of YRCC, an additional amount of 949,700 RMB is provided as compensation for young crops and 124,200 RMB for temporary land use. The completed amount of direct costs is 72.0336 million RMB, taking up 96.6% of the total. Refer to Table 1-1 for details.

Table 1-1 Approval and Application of Resettlement Funds Unit: 104 RMB

No. Item Approved Additional Total Completed 1 Rural resettlement 3812 514.94 4326.94 4196.522 Special facility 2473 263.26 2736.26 2643.093 Land restoration 902 -507.19 394.81 363.75

Subtotal Direct resettlement cost 7187 271.01 7458.01 7203.364 Miscellaneous & resettlement supervision 630 884.19 1514.19 623.49

Total 7817 1155.2 8972.2 7826.85

In the Resettlement Plan (referred to as “RP” hereinafter), it was planned to acquire 3,672.38 mu (including 1,168.72 mu non-productive land) for permanent and 11,622.24 mu (including 877.76 mu non-productive land) for temporary use, versus 3,392.01mu and 12,515.42 mu in the Implementation Scheme (referred to as the “Scheme hereinafter”). As of the this M&E, permanent land acquisition has been finished, with a total area of 2,501.22 mu (excluding non-productive land). The completed area for temporary use is 12,231.83 mu.

1.2 Monitoring and Evaluation

With preparation and field work conducted in September 2007, this M&E report is prepared on the basis of data interpretation and statistical analysis.

M&E activities mainly include: (1) treatment of the difference between current and approved compensation rates for permanent land use; (2) progress of permanent land use, payment and economic rehabilitation since the last M&E; (3) additional temporary land use, affected area,

Page 69: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

60

impact, payment, and restoration; (4) replacement of special facilities; (5) disbursement and payment; (6) training in production skills and protection of vulnerable groups; and (7) recovery of incomes of sample households since 2006.

A total area of 2,501.22 mu has been completed, 32.09 mu more than the figure reflected in the last report. The completed area for temporary use is 12,231.83 mu, including 7,832.09 mu restored already. There is no major change in special facility replacement, public participation, complaints management, resettlement training and vulnerable groups.

This report is focused on addressing the economic rehabilitation for permanent land use, the status of additional temporary land use, together with its affected area, impact, payment and restoration, and the income recovery of sample households in 2006. For this purpose, the M&E team has investigated a total number of 4 townships, 12 villages, 20 groups and 50 sample households as shown in Table 1-2.

Table 1-2 Statistical Results of Household Surveys

Township/Village Group Affected Group Investigated Group Sample Household 1 Jiangzhuang 15 15 2 7 1.1 Hucunpu 4 1-4 3 4 1.2 Didong 11 1-11 6 3 2 Guanchang 27 21 7 16 2.1 Huangsi 8 1-8 6 3 2.2 Fengzhuang 3 1 1 2 2.3 Liuyuan 7 1, 2, 5 1, 2 5 2.2 Lougudui 9 1-9 3, 4, 6 6 3 Jintang 25 14 5 13 3.1 Jiatan 10 1-9 6, 8 6 3.2 Shizhuang 9 2, 3, 5, 9 5, 9 5 3.3 Nainaimiao 6 2 2 2 4 Doumen 22 19 6 14 4.1 Dawuzhuang 7 1-7 2, 4 5 4.2 Dianchige 7 1, 2, 4, 7 2, 7 5 4.3 Taoyuan 8 1-8 3, 4 4

Total 89 69 20 50

2. DISBURSEMENT AND PAYMENT

2.1 Compensation Rates

The approved rate for irrigated land for permanent use is 12,930 RMB/mu. Before this M&E, compensation rate were used as published in the Government Notice of Yuanyang County Government. In the Government Notice, the rate for irrigated fields for permanent land is set at 9,050 RMB/mu as per the “Circular Letter on Publishing Compensation Rates for Appurtenances on the Land Acquired for State Construction in Xinxiang” issued by Xinxiang City Government in letter No. [1993]229. During this M&E, the previous rate of 9,050 RMB/mu was increased to 9,630 RMB/mu in practice, with price adjustment of 580 RMB/mu. At present, agreements on the payment of price adjustment are being executed.

Other rates are applied as fixed in the IS. The last report has discussed the rates in detail.

Page 70: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

61

2.2 Disbursement and Payment

The Employer has disbursed a total amount of 72.0336 million RMB up to this report, which is 10.7736 million RMB more than the amount reported last time, including 14.7197 million RMB for permanent land use, 1.0673 million RMB more than reported last time, mainly for additional permanent land use (land compensations have been paid to villages, but villager committees have not finally decided how to use them, 23.8231 million RMB for permanent land use, 26.4309 million RMB for special facilities, 3.4224 million RMB for appurtenances and others, and 3.6375 million RMB for land restoration. Detailed are given in Table 2-1.

Table 2-1 Payment of Resettlement Funds Unit: 104 RMB

6th M&E 5th M&E Increase No. Item Approved Total

Agreed Paid Agreed Paid Agreed Paid 1 Permanent land use 1471.97 1471.97 1365.24 1365.24 106.73 106.73 2 Temporary land use 2382.31 2382.31 1939.33 1939.33 442.98 442.98 3 Special facility & canal 2643.09 2643.09 2424.04 2424.04 219.05 219.05 Special facility 166.86 166.86 87.3 87.3 79.56 79.56 Canal 2476.23 2476.23 2336.74 2336.74 139.49 139.49

4 Appurtenance and others 342.24 342.24 271.16 271.16 71.08 71.08 Appurtenance 166.73 166.73 96.64 96.64 70.09 70.09 Fishpond 17.05 17.05 16.06 16.06 0.99 0.99 Appurtenance in old warping area 158.46 158.46 158.46 158.46 0 0

5 Land restoration

7187 7458.01

363.75 363.75 126.23 126.23 237.52 237.52 Total 7187 7458.01 7203.36 7203.36 6126 6126 1077.36 1077.36

3. PERMANENT LAND USE AND ECONOMIC REHABILITATION

There is an additional area of 32.09 mu for the permanent use of canals, totally farmland of Yuanyang Water Resources Bureau. The completed total area for permanent land use by the time of this M&E is 2,501.22 mu (excluding non-productive land), including 1,459.64 mu for main works and 1,041.58 mu for canals, accounting for 62 of 2,343.1 mu and 99% of 1,048.91 mu proposed in the Scheme.

The mode and progress of economic rehabilitation have not changed in any way since the last report, so they are not to be discussed herein. Refer to Table 3-1 for detailed information.

This M&E includes a survey of 50 households, in the form of multiple choice questionnaires, regarding the impacts of land acquisition, the use of compensations and the remedy measures for income recovery. This total number of 50 households includes 40% with less income from farming activities but more from other sources, without any impact on the total income, 52% subject to minor impacts due to less land loss, 2% subject to minor impacts due to the interior quality of lost land, and 6% exposed to major impacts.

Subsequent to farmland reduction, most farmers recover their family incomes by working as farmer workers, taking up 64% of the total number of people interviewed, while the others achieve income recovery by other means, including 14% by business, 16% by reclaiming waste land or contracting land, and 2% by developing farming, animal raising and plastic tunnel activities due to various restraints. The rest 16% have not taken any action.

Page 71: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

62

Table 3-1 Permanent Land Acquisition and Economic Rehabilitation

Original Affected Economic Rehabilitation

Group Home People Farmland Per

Capita Group Home People Area Farmland

Per

Capita

Loss

Group

with Land

Loss>10%

Land

Adjustment

Cash

Payment Others Township/Village

group home person mu mu group home person mu mu mu

Remarks

Zhulou 6 290 1300 1500 1.154 1 1 6 4.34 4.34 0.723 1

Hutangzhuang 6 290 1300 1500 1.154 1 1 6 4.34 4.34 0.723 1

Handongzhuang 40 1499 6401 7728 1.207 31 641 2808 307.11 130.65 0.035 5 26 31.84mu collective land

Dadongzhuang 9 379 1736 2189 1.261 9 379 1736 97.5 52.47 0.030 9

Chezhuang 7 208 830 1040 1.253 7 208 830 55.8 35.84 0.035 5 2 7.07mu collective land

Huangzhuang 8 223 1035 1029 0.994 8 73.7 15.35 8 15.35mu collective land

Laomengzhuang 5 400 1600 1600 1.000 2 47 208 33.7 10.35 0.050 2

Wanghe 4 64 300 420 1.400 4 7 34 7.61 7.22 0.212 4

Kongzhuang 4 90 400 720 1.800 36.3 9.12 .

Liwu 3 135 500 730 1.460 1 2.5 0.3 1 9.42mu collective land

Jiangzhuang 44 1477 6636 7865 1.185 34 516 2372 292.7 292.65 0.096 2 12 22 64.91mu collective land

Zhanglanzhuang 5 200 900 1200 1.333 1 40 230 14.4 14.37 0.062 1

Hucunpu 4 132 648 778 1.201 4 132 648 63.3 63.33 0.098 1 4

Qiansong 5 140 650 840 1.292 5 122 488 40.5 40.46 0.083 1 4

Shageda 6 197 951 1200 1.262 1 33 142 13 13 0.092 1 .

Didong 11 370 1500 1100 0.733 11 45 220 73 73.01 0.113 1 1 10 48.11mu collective land

Mazhuang 7 240 1100 1400 1.273 6 48 180 41.8 41.82 0.139 1 5 16.8mu collective land

Zhanggu 6 198 887 1347 1.519 6 96 464 46.7 46.66 0.101 3 3

Guanchang 51 2297 9749 10973 1.126 30 856 3909 607.72 353.37 0.070 7 19 11 78.31mu collective land

Liugu 8 327 1473 800 0.543 1 7 28 9.03 0.46 0.016 1

Lougudui 9 196 962 973 1.011 9 191 902 105 104.82 0.116 4 3 6

Liuyuan 7 630 2000 2400 1.200 3 213 853 79.8 66.91 0.057 1 3 17.95mu collective land

Huangshi 8 320 1560 1872 1.200 8 320 1560 262 81.18 0.052 1 8

Lizhuang 4 301 1175 1320 1.123 4 25 100 14.1 6.01 0.060 4

Quandiliu 4 130 670 920 1.373 33.8 33.84

Xiaoliugu 1 110 560 1300 2.321 29.6 26.11

Banzhang 3 80 400 420 1.050 1.49 0.41

60.36mu collective land

Fengzhuang 3 82 355 400 1.127 1 34 140 12.5 12.54 0.090 1 1

Hezhuang 4 121 594 568 0.956 4 66 326 15.9 15.93 0.049 4

Army 44.5 5.16

Jintang 34 1367 6050 8733 1.443 19 628 3049 583.6 528.88 0.156 7 14 3 2 53.35mu collective land

Jiatan 10 498 2173 3123 1.437 10 377 1683 320 320.12 0.190 3 8 2

Shizhuang 9 319 1520 2110 1.388 4 99 470 138 128.71 0.199 2 1 3 35mu collective land

Zhuangzhai 9 280 1250 1400 1.120 4 117 723 67.9 22.35 0.014 1 4 12.35mu collective land

Nainaimiao 6 270 1107 2100 1.897 1 35 173 57.7 57.7 0.299 1 1 6mu collective land

Guozhuang 8 525 2223 1916 0.862 2 27 130 33.71 33.73 0.201 1 1 7.61mu collective land

Zhaozhuang 4 200 846 916 1.083 7.61 7.61 7.61mu collective land

Huiwan 4 325 1377 1000 0.726 2 27 130 26.1 26.12 0.201 1 1

Doumen 32 1491 6129 6653 1.085 22 779 3366 410 284.87 0.074 7 7 15 36.54mu collective land

Dianchige 7 370 1500 1656 1.104 4 178 754 129 73.77 0.092 3 4 4.7mu collective land

Dawuzhuang 7 349 1570 1600 1.019 7 349 1570 174 156.82 0.091 3 7 13.72mu collective land

Taoyuan 8 252 1042 1156 1.109 8 252 1042 91 46.43 0.035 1 4 4 10.27mu collective land

Zhangsu 3 170 697 741 1.063 3 13.9 5.75 3

Zhuzhuang 7 350 1320 1500 1.136 2.1 2.1 7.85mu collective land

County Water

Resources Bureau 262.09 262.09

Total 215 8946 38488 45368 1.179 139 3448 15640 2501.22 1890.58 0.086 23 58 79 2 272.56mu collective land

Page 72: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

63

Land compensations, when received, are used to for farming activities, children’s tuitions and daily expenses by 64% farmers, housing by 10%, business by 10%, and debit repayment by 6%. Details are given in Table 3-2.

Table 3-2 Questionnaire of Impacts, Remedy Measures and Compensation Uses

No. Item Household % I Impact by farmland reduction 50 100

1 Less income from farming, but more from other sources, without any impact on total income 20 40

2 Minor impact due to less land loss 26 52 3 Minor impact due to poor land quality 1 2 4 Major impact 3 6 5 Others 0 0 II Use of land compensations 1 Farming 32 64 2 Business 5 10 3 Housing 5 10 4 Medical fees, tuitions and other living expenses 32 64 5 Debit repayment 3 6 6 Others 13 26

III Remedy measures 1 Farmer worker 32 64 2 Business 7 14 3 Cropping, animal raising or plastic tunnel 1 2 4 Extensive farming and intercropping 0 0 5 Reclamation or cultivating others’ land 8 16 6 Trust to luck 8 16 7 Others 8 16

4. TEMPORARY LAND OCCUPATION AND RESTORATION

Temporary land occupation: The main works are completed. The completed total area for temporary use is 12,231.83 mu, which is 2,511.74 mu more than the figure reflected in the last report, taking up 98 of 12,515.42 mu in the Scheme. Refer to Table 4-1.

Compensation for temporary land occupation: Compensations are paid to villages according to the construction schedules and agreed quantities at the rates fixed in the approved Scheme, 2,408 RMB/mu for farmland and 690 RMB/mu for floodland. As found in this M&E, the farmers considered the approved rates too low to be acceptable, and allowances were offered by contractors sometimes, mainly for the land used for warping and excavation works, at the rates depending the depth of excavation: 2,600-3,00 RMB/mu for excavation with a depth of 2-3 m and 2,600-10,000 RMB/mu for pumping with a depth of 3-10 m.

Land restoration: It is shown by the survey results that 7,832.09 mu for temporary use has been restored, 64% of the total area for temporary use, 15% more than reported last time. Some lands were restored, but the signing of agreements was delayed sometimes. Agreements

Page 73: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

64

and payments have been completed for 7,813.33 mu, which takes up 99.8% of restored land.

Table 4-1 Temporary Land Occupation and Restoration Cumulative Land Restoration

Restored Remaining Township/Village 6th M&E Subtotal Excavation Pumping Treading Increase DepthArea % Area %

Unit mu mu mu mu mu mu m mu % mu % Zhulou 80.56 80.56 80.56 80.56 100

Hutangzhuang 80.56 80.56 80.56 2 80.56 100Handongzhuang 1473.27 1825.07 1055.15 495.6 274.34 351.8 907.99 50 917.08 50 Dadongzhuang 189.28 306.08 152.68 153.4 116.8 2 140 46 166.08 54 Huangzhuang 316.99 316.99 316.99 2 316.99 100 Laomengzhuang 178.44 178.44 178.44 2 178.44 100 Mengzhuang 72.21 72.21 72.21 72.21 100 Liwu 155.49 155.49 17.49 138 3 48 31 107.49 69 Huyao 149.64 149.64 142.13 7.51 2 149.64 100

Yuanyang Tree Farm 8.22 8.22 8.22 8.22 100 Wanghe 163.6 348.6 342.2 6.4 185 2 163.6 47 185 53 Caopo 42 42 42 42 100

Zhaomeiwu 197.4 197.4 197.4 197.4 100 Renzhuang 50 50 50 50 100

Jiangzhuang 891.2 1903.87 1261.81 512.5 129.56 1012.67 1131.41 59 772.46 41 Didong 53 334.4 334.4 281.4 2-3 334 100 0.4 Hucunpu 51.74 147.74 96 51.74 96 50 34 97.74 66 Mazhuang 568.05 652.05 631.15 20.9 84 2 547.15 84 104.9 16 Qiansong 1.55 1.55 1.55 0 1.55 100 Yangchang 201.26 201.26 200.26 1 2 200.26 100 1 Luchang 1.07 1.07 1.07 1.07 100 Hetou 1.83 1.83 1.83 1.83 100 Zhanglan 9.25 9.25 9.25 9.25 100 Yinlizhuang 3.45 3.45 3.45 3.45 100 Jinwu 512.5 512.5 512.5 2-3 512.5 100 Duwu 8.32 8.32 8.32 8.32 100

Niuliurao 8.32 8.32 8.32 8.32 100 Xiwangwu 16.63 16.63 16.63 16.63 100 Housongzhuang 5.5 5.5 5.5 5.5 100 Guanchang 3656.27 4172.39 90.2 3747.21 334.98 516.12 3755.15 90 417.24 10 Huangsi 500 550 470 80 50 3-4 550 100 Lizhuang 293.61 293.61 252.93 40.68 6 250 85 43.61 15 Liuyuan 464.6 551.81 471.81 80 87.21 3-7 551.81 100 Lougudui 125 125 125 2 125 100 Quandiliu 340.2 340.2 90.2 250 3 300 88 40.2 12 Xiaoliugu 1018.7 1202.96 1109.66 93.3 184.26 3 1019.16 85 183.8 15 Huihuiying 468.58 468.58 468.58 4-7 468.58 100 Xinchang 129.98 129.98 129.98 3 0 129.98 100 Panguan 224.6 239.6 239.6 15 224.6 94 15 6 Liyuechang 91 270.65 229.65 41 179.65 266 98 4.65 2 Guozhuang 1217.25 1217.25 1166.91 50.34 877.9 72 339.35 28 Heishi 1217.3 1217.25 1166.91 50.34 5-6 877.9 72 339.35 28 Jintang 842.9 1136.83 108.75 994.66 33.42 293.89 293.84 26 842.99 74 Xiayan 16.62 16.62 16.62 16.62 100

Zhangxinzhai 60 60 60 3 60 100 Zhuangzhai 16.8 252.32 235.52 16.8 235.52 252.32 100 Baobei 557.4 557.4 557.4 7 92.1 17 465.3 83 Zhuzhuang 99.99 99.99 99.99 10 99.99 100 Baoxi 108.75 108.75 108.75 3 108.75 100 Nainaimiao 41.75 41.75 41.75 41.75 100

Doumen 1183.45 1520.71 0 1432.12 88.59 337.26 865.8 57 654.91 43 Taoyuan 1.76 1.76 1.76 1.76 100 Doudong 4.73 4.73 4.73 4.73 100 Xuzhuang 1176.3 1231.26 1170.62 60.64 54.96 6-7 733 60 498.26 40 Dianchige 0.66 112.66 112.66 0.66 112 112 99 0.66 1 Luzhuang 20.8 20.8 20.8 20.8 100 Nanwangzhuang 149.5 149.5 149.5 149.5 100 Qiaobei 74.7 74.7 74.7 74.7 100 Sizhuang 74.7 74.7 74.7 3 74.7 100

Page 74: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

65

Ecology Development Co. 300.45 300.45 300.45 300.45 100 Total 9720.09 12231.83 2671.15 8649.45 911.23 2511.74 7832.09 64 4399.74 36

How temporary land occupation affected the farmers’ production and livelihood has attracted the high attention of previous M&E activities. As found in our field survey of the affected villages and households, the production of one crop was generally affected, but farmers were compensated for this. Moreover, better irrigation and soil improvement increased output of the previously uneven and highly desertified farmland.

This M&E includes interviews with typical households in Xiaoliugu, where much land was used for temporary use. Refer to the box below.

Interview 1 Temporary Land Use for Excavation Background: The land area for temporary use in Xiaoliugu was 1,202.96 mu, including 1,109.66 mu for pumping to a depth of 2-3 m. According to the schedule, borrow area operation affected the output of autumn crops in 2005 or spring ones in 2006. Compensations have been paid. Profile of Interviewee: Name: Lou Shengli, Sex: Male, Age: 45, Education: Junior middle school, Position: Party secretary, Family size: 6 people Brief of interview: Lou had 12 mu farmland, which was totally used for pumping works to a depth of 3 m, affecting the autumn crops 2006. A total amount of 38,400 RMB was paid at the rate of 3,200 RMB/mu. Land restoration was finished at the time of this interview. The original farmland was uneven and highly desertified. After borrow area operation, sand soils were removed and soil properties changed, with clay left in the field and crop output improved (see Photograph 1). Removal of pest-containing soils enabled less use of pesticide. The compensations were used to establish a dairy, which cost 60,000 RMB, including a bank loan. With workshops completed, he is about to purchase dairy cattle (see Photograph 2).

Page 75: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

66

Photograph 1: Autumn Rice Doing Well in Restored Field Photograph 2: Built Dairy Workshop

5. INCOME RECOVERY

As required in the TOR, sample households opting for land adjustment and cash payment (referred to “Option A” and “Option B”) are selected for follow-up monitoring, with a percentage not less than 50% of the affected sample households. Altogether 50 households are selected, including 29 opting Option B and 21 for Option A.

5.1 Constituents and Changes of Incomes

As indicated by our follow-up monitoring results of 50 samples households in 12 villages, there was a per capita income of 1,920 RMB before land acquisition in 2004, versus 2,072 RMB in 2005 and 2,442 RMB in 2006 after land acquisition, meaning a tendency of increase from year to year. Major sources of income included farming, sideline, fruit, animal raising and others. Farming produced 1,025 RMB in 2004, 903 RMB in 2005 and 1,063 RMB in 2006, taking up 53%, 44% and 44% of the per capita income. This source of income declined in the first year of land acquisition, 122 RMB less than in the base year of 2004, but increased by in 2006, 38 RMB more, indicating that the income from farming activities was restored to a certain extent. Subsequent land acquisition, the income from sideline activities went up year by year, from 748 RMB in 2004 to 1,156 RMB in 2006, and contributed more and more to the total family income, from 39% to 47%. Refer to Table 5-1 and Chart 1.

The per capita income of sample households was not reduced as a subsequence of farmland reduction, mainly because (1) the structure of incomes changed – more income was produced by sidelines, especially farmer workers, which offset the loss due to farmland reduction; and (2) some farmers rent land after farmland reduction, mainly in Dawuzhuang and Dianchige, where farmland was rent from the army to offset the lost income of farming.

Page 76: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

67

Chart 1 Per Capita Incomes& Constituents of Sample Households in 2004-2006

0 500

1000 1500

2000 2500

3000

Total Farming Sideline Fruit Animal Raising Others

Income (R

MB

)

200420052006

Page 77: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

68

Table 5-1 Per Capita Income of Sample Households (2004-2006) Farming Fruit Animal Raising Sideline Others

Income Percent Income Percent Income Percent Income Percent Farmer Worker Income PercentNo. Township Village Year PeoplePer Capita Farmland

(mu)

Farmland (mu)

Per Capita Income (RMB) RMB % RMB % RMB % RMB % Income Percent RMB %

2004 18 1.38 24.9 1999 954 48 39 2 1000 50 533 53 6 0

2005 18 0.54 9.7 2054 262 13 22 1 1763 86 896 51 7 0 1 Dawuzhuang

2006 18 0.54 9.7 2098 432 21 1651 79 785 48 15 1

2004 22 1.23 27 1358 821 60 41 3 441 32 91 21 55 4

2005 22 0.80 17.6 1482 738 50 9 1 602 40 466 77 133 9 2 Dianchige

2006 22 0.80 17.6 2274 1253 55 45 2 864 38 318 37 112 5

2004 17 1.07 18.2 1793 695 39 1082 60 1082 100 16 1

2005 17 0.95 16.1 2494 728 29 1756 71 1756 100 10 0 3

Doumen

Taoyuan

2006 17 0.95 16.1 2525 759 30 1735 69 1735 100 31 1

2004 11 1.57 17.25 2067 908 44 1136 55 1136 100 23 1

2005 11 1.53 16.8 2404 1109 46 1273 53 1273 100 22 1 4 Fengzhuang

2006 11 1.51 16.6 2390 1170 49 1182 49 1182 100 38 2

2004 17 1.42 24.2 1771 1296 73 15 1 353 20 353 100 107 6

2005 17 1.46 24.8 1871 1236 66 15 1 471 25 471 100 149 8 5 Huangsi

2006 17 1.46 24.8 2155 1366 63 647 30 647 100 142 7

2004 33 1.72 56.6 2317 1309 57 218 9 770 33 442 57 20 1

2005 33 1.33 43.75 2477 1352 55 30 1 1076 43 773 72 19 1 6 Liuyuan

2006 33 1.40 46.15 2917 1502 51 170 6 1212 42 909 75 33 1

2004 42 1.04 43.6 2594 655 25 345 13 1581 61 952 60 13 1

2005 42 0.90 37.6 2483 498 20 375 15 1224 49 1164 95 386 16 7

Guanchang

Lougudui

2006 42 0.90 37.6 2634 494 19 376 14 1369 52 1369 100 395 15

2004 12 1.80 21.6 1589 1465 92 124 8

2005 12 1.73 20.8 1617 1368 85 125 8 125 100 124 8 8 Didong

2006 12 1.73 20.8 3906 1557 40 2208 56 125 6 141 4

2004 17 1.38 23.5 1627 973 60 635 39 282 44 19 1

2005 17 1.32 22.4 1746 1004 58 724 41 371 51 18 1 9

Jiangzhuang

Hucunpu

2006 17 1.32 22.4 2200 1555 71 612 28 259 42 33 1

2004 28 1.43 40 1190 906 76 264 22 107 41 20 2

2005 28 1.24 34.6 1421 811 57 593 42 307 52 17 1 10 Jiatan

2006 28 1.24 34.6 1790 928 52 -36 804 45 625 78 94 5

2004 6 2.18 13.1 2632 1642 62 833 32 125 5 125 100 32 1

2005 6 2.05 12.3 2559 1612 63 667 26 250 10 250 100 30 1 11 Nainaimiao

2006 6 2.05 12.3 2672 1704 64 667 25 250 9 250 100 51 2

2004 24 1.60 38.5 1831 1420 78 392 21 392 100 19 1

2005 24 1.17 28.07 2143 1043 49 1083 51 1083 100 17 1 12

Jintang

Jiangzhuang

2006 24 1.17 28.07 2180 1110 51 1042 48 1042 100 28 1

2004 247 1.41 348.45 1920 1025 1920 21 1 94 5 748 39 490 66 32 2

2005 247 1.15 284.52 2072 903 2072 17 1 70 3 978 47 796 81 104 5 Total

2006 247 1.16 286.72 2442 1063 2442 12 0 91 4 1156 47 858 74 120 5

5.2 Income Constituents and Changes in Option A and Option B

During this M&E, 29 sample households choosing Option A and 21 preferring Option B were selected for follow-up monitoring of their income changes subsequent to land acquisition.

5.2.1 Option A

The monitoring covers 29 sample households from 8 villages, namely, Fengzhuang, Huangsi, Liuyuan, Lougudui, Didong, Hucunpu, Jiatan and Nainaimiao. The monitoring results show a total farmland area of 224.85 mu and per capita area of 1.48 mu before land acquisition, versus 204.45 mu and 1.34 mu thereafter, or a loss of 0.14 mu per capita.

These families had a per capita income of 2,012 RMB in 2004 (without land acquisition), 2,086 RMB in 2005 and 2,562 RMB in 2006, including 1,069 RMB, 1,031 RMB and 1,187 RMB from farming. The income inclined in the first year after land acquisition, but increased from the second year.

Page 78: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

69

To look into the reason that farming incomes were not reduced, it is known that the sharing of the loss of farmland mitigated the impacts of land acquisition and that the recent escalation of food prices implied slightly higher incomes despite the increase of production costs, with an increase of 118 RMB in the per capita farming income in 2006 than in 2004, a percentage of 11%. Refer to Table 5-2 and Chart 2.

The per capita income from sideline activities was 824 RMB in 2004, 781 RMB in 2005 and 1,145 RMB in 2006, accounting for 41%, 42% and 45% to the total income. Both amounts and percentages increased from year to year. Typically, 3 sample households in Didong were absolutely dependent upon farming in 2004, but earned 2,208 RMB per capita from sideline in 2006, constituting 56% of the total income and representing a major change to the structure of income. Refer to the interview with a typical household. In 2006, there was a decline of 39 RMB in Lougudui in comparison with the income level of 2004, largely attributable to less income from farming and sideline.

As analyzed above, land acquisition has not posed major impacts on the income of sample households.

Table 5-2 Incomes of Sample Households Preferring Option A Farming Fruit Animal Raising Sideline Others

Farmer WorkerIncome Percent Income Percent Income Percent Income Percent

Income PercentIncome PercentNo. Township Village Year People

Per Capita

Farmland

(mu)

Farmland

(mu)

Per

Capita

Income

(RMB) RMB % RMB % RMB % RMB % Income Percent RMB %

2004 11 1.57 17.25 2067 908 44 1136 55 1136 100 23 1

2005 11 1.53 16.8 2404 1109 46 1273 53 1273 100 22 1 1 Fengzhuang

2006 11 1.51 16.6 2390 1170 49 1182 49 1182 100 38 2

2004 17 1.42 24.2 1771 1296 73 15 1 353 20 353 100 107 6

2005 17 1.46 24.8 1871 1236 66 15 1 471 25 471 100 149 8 2 Huangsi

2006 17 1.46 24.8 2155 1366 63 647 30 647 100 142 7

2004 33 1.72 56.6 2317 1309 57 218 9 770 33 442 57 20 1

2005 33 1.33 43.75 2477 1352 55 30 1 1076 43 773 72 19 1 3 Liuyuan

2006 33 1.40 46.15 2917 1502 51 170 6 1212 42 909 75 33 1

2004 28 1.02 28.6 2884 641 22 0 0 2229 77 1286 58 14 1

2005 28 0.96 26.8 2604 467 18 27 1 1536 59 1446 94 574 22 4

Guanchang

Lougudui

2006 28 0.96 26.8 2845 479 17 29 1 1754 62 1754 100 583 20

2004 12 1.80 21.6 1589 1465 92 124 8

2005 12 1.73 20.8 1617 1368 85 125 8 125 100 124 7 5 Didong

2006 12 1.73 20.8 3906 1557 40 2208 57 125 6 141 3

2004 17 1.38 23.5 1627 973 60 635 39 282 44 19 1

2005 17 1.32 22.4 1746 1004 58 724 41 371 51 18 1 6

Jiangzhuang

Hucunpu

2006 17 1.32 22.4 2200 1555 71 612 28 259 42 33 2

2004 28 1.43 40 1190 906 76 264 22 107 41 20 2

2005 28 1.24 34.6 1421 811 57 593 42 307 52 17 1 7 Jiatan

2006 28 1.24 34.6 1790 928 52 -36 -2 804 45 625 78 94 5

2004 6 2.18 13.1 2632 1642 62 833 32 125 5 125 100 32 1

2005 6 2.05 12.3 2559 1612 63 667 26 250 10 250 100 30 1 8

Jintang

Nainaimiao

2006 6 2.05 12.3 2672 1704 64 667 25 250 9 250 100 51 2

2004 152 1.48 224.85 2012 1069 53 35 2 47 2 824 41 511 62 37 2

2005 152 1.33 202.25 2086 1031 49 28 1 12 1 871 42 697 80 144 7 Total

2006 152 1.34 204.45 2562 1187 46 20 1 42 2 1145 45 842 74 168 6

Page 79: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

70

Interview regarding Income Recovery (Option A)

Time: 2007-09-13 Place: Didong Villager Committee, Jiangzhuang Township Interviewee Code: YYDFJZHDD1 Position: Vice Village Leader Sex: Male Age: 42 Education: Junior middle school Background: The village comprised of 11 villager groups, all involved in the acquisition of 73.01 mu, totally collective farmland except for 49.9 contracted land of Group 6. Money was distributed and land adjustment completed by Group 6 in the same year of land acquisition. The resultant per capita farmland reduction was 0.07 mu only, without any major impact on the affected households. The farmers’ incomes were not reduced as a consequence. Brief of interview: Interviewer: Hello, sorry to bother you again. This time we came to follow your change of income on the basis of previous findings and know how you have been affected as a result of land acquisition. Interviewee: OK, thank you for your interest. Interviewer: You are from Group 6, where land adjustment has happened. How much farmland have you lost after land adjustment? Interviewee: 0.2 mu, with 7.8 mu now. Interviewer: How much money have you received as land compensation? How many times has it been paid? What are the constituents? How have you used the money? Interviewee: 8,000 RMB as a lump sum at the rate of 1,600 RMB/person. Since the money was shared and land adjusted, payment was made to all. I have put the majority in farming activities. Interviewer: As the farmland is reduced, what have you done to offset your income loss? Interviewee: At present my income mainly comes from small business. For instance, I provided signboards on both sides of the expressway in 2006, and let it out for 10,000 RMB a year. Ordinarily, I make some money from doing some small. My farmland is principally the source of food for personal consumption, not the source of income. Interviewer: Do you think your family income is greatly affected by farmland reduction? Interviewee: With land adjustment, no major impact. Interviewer: Are you satisfied with the existing production/living conditions? What’s your plan for the future? Interviewee: Basically satisfied, hoping to make more money by doing business. Interviewer: Thank you and wish you a better life.

Chart 2 Per Capita Incomes and Constituents of Sample Households in 2004-2006 (Option A)

0 500

1000 1500 2000 2500 3000

Total Farming Sideline Fruit Animal l Raising

Others

RM

B 2004 2005 2006

Page 80: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

71

5.2.2 Option B

The follow-up monitoring covers 21 sample households in 5 villages, namely, Dawuzhuang, Dianchige, Taoyuan, Lougudui and Shizhuang. The monitoring results show a total farmland area of 123.6 mu and per capita area of 1.3 mu before land acquisition, versus 82.27 mu and 0.87 mu thereafter, or a loss of 0.43 mu per capita.

These families had a per capita income of 1,773 RMB in 2004, 2,051 RMB in 2005 and 2,253 RMB in 2006, with a tendency of increase in both per capita and farming incomes.

The per capita income from sideline activities was 955 RMB in 2004, 697 RMB in 2005 and 866 RMB in 2006. It was considerably decreased in the very year of land acquisition (2005) and recovered the next year, but still less than that of 2004. The proportion declined from 54% to 38%. The loss of farmland and escalation of production costs were both the cause of less income from farming (especially in Dawuzhuang, Lougudui and Shizhuang). Some farmers in Dawuzhuang and Shizhuang rent the farmland of army nearby, to offset the loss due to farmland reduction. Refer to the interview with typical households.

Interview regarding Income Recovery (Option B) Time: 2007-09-13 Place: Dawuzhuang Villager Committee, Doumen Township Interviewee Code: YYDFDMDWZH20 Position: Farmer Sex: Male Age: 46 Education: Junior middle school Background: The village comprised of 7 villager groups, all involved in land acquisition. A total area of 174 mu was acquired for permanent use, including 156.82 mu farmland (143.1 mu contracted land). Option B was adopted as the mode of economic rehabilitation, with land compensations paid to land losers at the rate of 9,050 RMB/mu. Being close to an army’s farm, some farmers rent land from the farm. Brief of interview: Interviewer: Hello, sorry to bother you. This time we came to follow your change of income on the basis of previous findings and know how you have been affected as a result of land acquisition. Interviewee: OK, thank you for your kindness. Interviewer: According to the follow-up monitoring data, 2.2 mu of our family was acquired for permanent use and compensated for a lump sum of 19,910 RMB at the rate of 9,050 RMB/mu (excluding the unpaid price adjustment), without land adjustment. Interviewee: You are right. I have been compensated for the use of farmland. Interviewer: How have you used the money? Interviewee: Mainly used as input in farming, including chemical fertilizer and pesticide, and partly for my child’s wedding. Interviewer: There are 5 people in your family, but only 2.3 mu farmland, is it enough? As farmland is reduced, what have you done to offset your income loss? Interviewee: The farmland can solve the issue of grain rations. Less farmland means surplus of labor forces, so I rent 4 mu from the army to gain more from farming. In addition, My child and I make some money by working outside as farmer workers. Interviewer: Do you think your family income is greatly affected by farmland reduction? Interviewee: It is affected somewhat, but the loss is partly offset by rending farmland and working as farmer works. Interviewer: The reality is there, no chance to change. Anyway, I hope for good weather for the crops, good harvests and more job opportunities.

Page 81: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

72

Interviewer: Thank you and wish you a better life.

The income from sideline was 626 RMB in 2004, 1,150 RMB in 2005 and 1,175 RMB in 2006, taking up 35%, 56% and 52% of the total income, with an increase in both amounts and percentages. The percentage in 2006 was 17% higher than in 2004.

As analyzed above, less was generated by farming. Adjusted structure of cropping activities mitigated the income loss, better awareness of farmer workers and business improved the income from sideline activities, and employment of farmer workers and renting of farmland offset the impacts by farmland reduction. Therefore, the per capita income was not lowered. Refer to Table 5-3 and Chart 3.

Table 5-3 Incomes of Sample Households Preferring Option B Farming Fruit Animal Raising Sideline Others

Farmer WorkerIncome Percent Income Percent Income Percent Income Percent

Income PercentIncome PercentNo. Township Village Year People

Per Capita

Farmland

(mu)

Farmland

(mu)

Per

Capita

Income

(RMB) RMB % RMB % RMB % RMB % Income Percent RMB %

2004 18 1.38 24.9 1999 954 48 39 2 1000 50 533 53 6 0

2005 18 0.54 9.7 2054 262 13 22 1 1763 86 896 51 7 0 1 Dawuzhuang

2006 18 0.54 9.7 2098 432 21 0 0 1651 79 785 48 15 1

2004 22 1.23 27 1358 821 60 41 3 441 32 91 21 55 4

2005 22 0.80 17.6 1482 738 50 9 1 602 41 466 77 133 9 2 Dianchige

2006 22 0.80 17.6 2274 1253 55 45 2 864 38 318 37 112 5

2004 17 1.07 18.2 1793 695 39 0 0 1082 60 1082 100 16 1

2005 17 0.95 16.1 2494 728 29 0 0 1756 70 1756 100 10 0 3

Doumen

Taoyuan

2006 17 0.95 16.1 2525 759 30 0 0 1735 69 1735 100 31 1

2004 14 1.07 15 2016 684 34 1036 51 286 14 286 100 10 0

2005 14 0.77 10.8 2240 559 25 1071 48 600 27 600 100 10 0 3 Guanchang Lougudui

2006 14 0.77 10.8 2218 526 24 1071 48 600 27 600 100 21 1

2004 24 1.60 38.5 1831 1420 78 0 0 392 21 392 100 19 1

2005 24 1.17 28.07 2143 1043 49 0 0 1083 51 1083 100 17 1 5 Jintang Shizhuang

2006 24 1.17 28.07 2180 1110 51 0 0 1042 48 1042 100 28 1

2004 95 1.30 123.6 1773 955 54 169 10 626 35 457 73 23 1

2005 95 0.876 82.27 2051 697 34 164 8 1150 56 954 83 40 2 Total

2006 95 0.876 82.27 2253 866 38 168 7 1175 52 884 75 44 2

0

500

1000

1500

2000

2500

Total Farming Sideline Fruit Animal Raising

Others

RM

B

2004

2005

2006

Chart 3 Per Capita Incomes and Constituents of Sample Households in 2004-2006 (Option B)

Page 82: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

73

6. PROTECTION OF RIGHTS AND INTERESTS

6.1 Training for Skills

The investigation shows that the affected people have never been trained in farming skills, resettlement policies, regulations and other aspects, but they wish to be trained in mastering farming skills, adjusting planting structures, and developing animal raising activities. To meet the demands of farmers, training programs for plastic tunnel, animal raising and cropping skills were developed in the Implementing Agencies in 2007, though these programs have not been implemented yet.

6.2 Vulnerable Groups

This M&E includes high attention to the impact on the production and living of vulnerable groups due to dike construction. As shown by survey results, the affected vulnerable groups enjoy the equal rights as others and compensations have been paid to them.

Among the families enjoy “five-guarantees”, those unable to take care of themselves in daily life can choose to go to the old folks home, while others capable of taking care of themselves are paid 60 RMB living allowances from the government each month and supported by villages in both farming and living. Also, relief such as flour and bed quilt is offered by the county and township civil administrations on holidays and festivals.

Women headed families are mostly dependent upon themselves, whereas the disabled with certificates of disability are entitled of cash relief each year.

The vulnerable groups enjoy the equal rights as others in the respect of land compensation, without case-specific preferential policies.

7. EVALUATION AND RECOMMENDATION

7.1 Settlement of Earlier Problems

Agreements on price adjustment were signed with affected villages at the time of this M&E, with the compensation rate adjusted from 9,050 RMB/mu to 9,630 RMB. Payment has been made to villages.

Agreements on land restoration were signed and implemented.

7.2 Evaluation and Recommendations

Main works are to be taken over very soon. Land acquisition and resettlement are basically finished, with 2,501.22 mu acquired for permanent and 12,231.83 mu for temporary use, 7,832.09 mu restored, and 72.0336 million RMB disbursed.

(1) Compensation rates

The rate of 9,050 RMB/mu is used for permanent land use, mainly on the basis of “Circular Letter on Publishing Compensation Rates for Appurtenances on the Land Acquired for State Construction in Xinxiang” issued by Xinxiang City Government in letter No. [1993]229, but 9,630 RMB/mu is approved in the Scheme. At Present, agreements on price adjustment are

Page 83: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

74

being signed and implemented, and other rates applied as approved in the Scheme.

(2) Permanent land acquisition and economic rehabilitation

The completed land area for permanent use is 2,501.22 mu (excluding non-productive land), taking up 68% of the RP and 74% of the Scheme, involving 7 townships, 36 villages and 139 groups. The mode of economic rehabilitation is up to the farmers, with Option B chosen by 58 groups and Option B by 79. The rest 2 groups have not made a decision. With farmland reduced, the farmers take various measures to increase their family incomes, such as working as farmer workers, doing business and renting farmland.

(3) Temporary land occupation and restoration

Most of the land for temporary use is highly desertified hilly land and uneven farmland hard to irrigate. With compensations, farmers are willing to provide their land. The completed area for temporary use is 12,231.83 mu, including 7,832.09 mu.

(4) Income recovery

As known from income analysis of 50 sample households in 2004, 2005 and 2006, 78% of them have a per capita income not less than that without land acquisition. Option B causes more impacts on farming incomes, but the farmers have recovered by renting farmland or working as farmer workers, so their income is not reduced as a result of farmland reduction. Option A enables the sharing of loss and avoids any major impacts on farming incomes, thus the total income is not less as compared with the level without land acquisition (except for a decline of 39 RMB in Lougudui). Income recovery is achieved by working as farmer workers, doing business and other means.

It is recommended that training programs be implemented as early as possible.

Restoration of the remaining land and payment of the balance will be emphasized in future M&E.

Page 84: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

75

Annex 1 Schedule of Incomes of Sample Households in 2004 Sideline

No. Township Village Sample Code PeopleFarmland (mu)

in 2004 Per Capita

Income (RMB)Farming Fruit

Animal Raising Subtotal

Farmer Worker

Others

1 YYDFDMDWZH07 2 4.5 1446 1424 222 YYDFDMDWZH20 5 4.5 2533 600 1920 1920 133 YYDFDMDWZH26 3 3.3 256 256 4 YYDFDMDWZH28 4 5.6 3046 946 2100 5 YYDFDMDWZH29 4 7 1867 1692 175

Dawuzhuang

Subtotal 18 24.9 1999 954 39 1000 533 66 YYDFDMDCHG05 3 2.3 1080 413 667 667 7 YYDFDMDCHG10 4 5.6 1666 991 50 625 8 YYDFDMDCHG15 4 5.1 2420 1720 100 300 3009 YYDFDMDCHG17 7 9.2 791 362 429 10 YYDFDMDCHG21 4 4.8 1187 862 75 250

Dianchige

Subtotal 22 27 1358 821 41 441 91 5511 YYDFDMTY04 5 4.5 1598 303 1280 1280 1512 YYDFDMTY23 4 4.7 802 784 1813 YYDFDMTY25 4 4.3 3801 785 3000 3000 1614 YYDFDMTY29 4 4.7 1022 1007 15

Doumen

Taoyuan

Subtotal 17 18.2 1793 695 1082 1082 1615 YYDFGCHFZH1 6 9.75 2184 827 1333 1333 2416 YYDFGCHFZH5 5 7.5 1929 1007 900 900 22

Fengzhuang

Subtotal 11 17.25 2067 908 1136 1136 2317 YYDFGCHHS2 5 6 2331 1105 8 1200 1200 1818 YYDFGCHHS3 7 12.5 1596 1338 26 23219 YYDFGCHHS5 5 5.7 1454 1428 6 20

Huangsi

Subtotal 17 24.2 1771 1296 15 353 353 10720 YYDFGCHLY01 7 9.6 2020 1142 429 429 429 2021 YYDFGCHLY03 7 8 3389 1229 600 1543 1722 YYDFGCHLY08 7 15 1961 1483 457 457 2123 YYDFGCHLY09 7 13 2069 1148 900 900 2124 YYDFGCHLY10 5 11 2077 1637 420 420 20

Liuyuan

Subtotal 33 56.6 2317 1309 218 770 442 2025 YYDFGCHLGD11 4 3.7 599 586 1426 YYDFGCHLGD24 6 7 3135 826 2083 217 217 1027 YYDFGCHLGD25 8 8 1175 577 250 338 338 1028 YYDFGCHLGD28 12 12 4866 654 4200 3000 1229 YYDFGCHLGD29 7 9.4 2394 660 1714 2030 YYDFGCHLGD30 5 3.5 637 627 10

Guanchang

Lougudui

Subtotal 42 43.6 2594 655 345 1581 952 1331 YYDFJZHDD1 5 8 1837 1579 25832 YYDFJZHDD3 4 8.3 1353 1322 3133 YYDFJZHDD4 3 5.3 1492 1466 26

Didong

Subtotal 12 21.6 1589 1465 12434 YYDFJZHHCP1 4 6.3 2032 1259 750 2335 YYDFJZHHCP2 5 6 1559 945 600 1436 YYDFJZHHCP4 4 5.6 1659 888 750 750 2137 YYDFJZHHCP5 4 5.6 1277 806 450 450 21

Jiangzhuang

Hucunpu

Subtotal 17 23.5 1627 973 635 282 1938 YYDFJTJT08 4 5.6 844 829 1539 YYDFJTJT09 4 5.6 840 825 1540 YYDFJTJT10 5 7.5 1663 1040 600 600 2341 YYDFJTJT12 3 4.9 811 787 2442 YYDFJTJT14 6 8.4 1583 962 600 2143 YYDFJTJT15 6 8 1054 901 133 20

Jiatan

Subtotal 28 40 1190 906 264 107 2044 YYDFJTNNM3 4 7 2211 1497 500 188 188 2645 YYDFJTNNM4 2 6.1 3477 1932 1500 45

Nainaimiao

Subtotal 6 13.1 2632 1642 833 125 125 3246 YYDFJTSHZH05 4 7.2 852 837 1547 YYDFJTSHZH06 6 10.8 2043 1361 667 667 1548 YYDFJTSHZH10 4 7 25221 2496 2649 YYDFJTSHZH11 4 4.5 1123 1106 1750 YYDFJTSHZH13 6 9 2283 1361 900 900 22

Jintang

Shizhuang

Subtotal 24 38.5 1831 1420 392 392 19 Total 247 348.45 1920 1025 21 94 748 490 32

Page 85: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

76

Annex 2 Schedule of Incomes of Sample Households in 2005 Sideline

No. Township Village Sample Code PeopleFarmland (mu)

in 2005 Per Capita

Income (RMB)Farming Fruit

Animal Raising Subtotal

Farmer Worker

Others

1 YYDFDMDWZH07 2 2.3 784 769 15 2 YYDFDMDWZH20 5 2.3 3132 126 3000 3000 6 3 YYDFDMDWZH26 3 1 249 244 5 4 YYDFDMDWZH28 4 2.1 4239 331 3900 8 5 YYDFDMDWZH29 4 2 513 125 100 281 281 7

Dawuzhuang

Subtotal 18 9.7 2054 262 22 1763 896 7 6 YYDFDMDCHG05 3 1.4 1100 333 750 750 17 7 YYDFDMDCHG10 4 3.4 1044 673 200 200 171 8 YYDFDMDCHG15 4 2.4 3029 1270 1250 750 509 9 YYDFDMDCHG17 7 7 1307 692 600 600 15 10 YYDFDMDCHG21 4 3.4 967 654 50 250 0 13

Dianchige

Subtotal 22 17.6 1482 738 9 602 466 133 11 YYDFDMTY04 5 4 2036 424 1600 1600 12 12 YYDFDMTY23 4 3.9 3214 837 2363 2363 14 13 YYDFDMTY25 4 4 3733 719 3000 3000 14 14 YYDFDMTY29 4 4.2 1107 1007 100 100 0

Doumen

Taoyuan

Subtotal 17 16.1 2494 728 1756 1756 10 15 YYDFGCHFZH1 6 9.6 2898 1208 1667 1667 23 16 YYDFGCHFZH5 5 7.2 1812 990 800 800 22

Fengzhuang

Subtotal 11 16.8 2404 1109 1273 1273 22 17 YYDFGCHHS2 5 5.7 2513 888 8 1600 1600 17 18 YYDFGCHHS3 7 12 1684 1324 26 334 19 YYDFGCHHS5 5 7.1 1488 1461 6 21

Huangsi

Subtotal 17 24.8 1871 1236 15 471 471 149 20 YYDFGCHLY01 7 2.8 1781 275 1500 1500 6 21 YYDFGCHLY03 7 7.2 2422 835 143 1429 0 15 22 YYDFGCHLY08 7 13 2710 1827 857 857 26 23 YYDFGCHLY09 7 11 3036 2157 857 857 22 24 YYDFGCHLY10 5 9.75 2420 1793 600 600 27

Liuyuan

Subtotal 33 43.75 2477 1352 30 1076 773 19 25 YYDFGCHLGD11 4 3.4 1234 599 625 0 10 26 YYDFGCHLGD24 6 5.8 4217 708 2500 1000 1000 9 27 YYDFGCHLGD25 8 5 758 448 300 300 11 28 YYDFGCHLGD28 12 11.5 4019 200 2500 2500 1319 29 YYDFGCHLGD29 7 8.9 2094 930 1143 1143 22 30 YYDFGCHLGD30 5 3 1012 354 150 500 500 8

Guanchang

Lougudui

Subtotal 42 37.6 2482 498 375 1224 1164 386 31 YYDFJZHDD1 5 7.8 1565 1302 263 32 YYDFJZHDD3 4 8 1341 1315 26 33 YYDFJZHDD4 3 5 2071 1550 500 500 21

Didong

Subtotal 12 20.8 1617 1368 125 125 124 34 YYDFJZHHCP1 4 5.8 2036 1264 750 0 22 35 YYDFJZHHCP2 5 6 1810 1197 600 0 13 36 YYDFJZHHCP4 4 5.3 1826 681 1125 1125 20 37 YYDFJZHHCP5 4 5.3 1296 826 450 450 20

Jiangzhuang

Hucunpu

Subtotal 17 22.4 1746 1004 724 371 18 38 YYDFJTJT08 4 4.9 872 854 0 0 18 39 YYDFJTJT09 4 4.1 1930 665 1250 1250 15 40 YYDFJTJT10 5 6.8 1416 917 480 480 19 41 YYDFJTJT12 3 4.2 944 925 20 42 YYDFJTJT14 6 7.9 1542 823 700 200 19 43 YYDFJTJT15 6 6.7 1569 721 833 15

Jiatan

Subtotal 28 34.6 1421 811 593 307 17 44 YYDFJTNNM3 4 6.5 2160 1261 500 375 375 24 45 YYDFJTNNM4 2 5.8 3359 2316 1000 43

Nainaimiao

Subtotal 6 12.3 2559 1612 667 250 250 30 46 YYDFJTSHZH05 4 5.8 3063 1043 2000 2000 20 47 YYDFJTSHZH06 6 9.4 3255 1235 2000 2000 20 48 YYDFJTSHZH10 4 4.5 780 764 16 49 YYDFJTSHZH11 4 2.4 504 495 950 YYDFJTSHZH13 6 5.97 2419 1402 1000 1000 17

Jintang

Shizhuang

Subtotal 24 28.07 2143 1043 1083 1083 17 Total 247 284.52 2072 903 17 70 978 796 104

Page 86: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

77

Annex 3 Schedule of Incomes of Sample Households in 2006 Sideline

No. Township Village Sample Code PeopleFarmland (mu)

in 2006 Per Capita

Income (RMB)Farming Fruit

Animal Raising Subtotal

Farmer Worker

Others

1 YYDFDMDWZH07 2 2.3 807 778 29 2 YYDFDMDWZH20 5 2.3 3204 592 2600 2600 12 3 YYDFDMDWZH26 3 1 264 245 19 4 YYDFDMDWZH28 4 2.1 4265 352 3900 13 5 YYDFDMDWZH29 4 2 572 278 281 281 13

Dawuzhuang

Subtotal 18 9.7 2098 432 1651 785 15 6 YYDFDMDCHG05 3 1.4 1383 699 667 667 17 7 YYDFDMDCHG10 4 3.4 1795 1014 750 750 31 8 YYDFDMDCHG15 4 2.4 3205 1983 250 500 0 472 9 YYDFDMDCHG17 7 7 2922 1456 1429 0 37 10 YYDFDMDCHG21 4 3.4 1355 823 500 500 32

Dianchige

Subtotal 22 17.6 2274 1253 45 864 318 112 11 YYDFDMTY04 5 4 2131 705 1400 1400 26 12 YYDFDMTY23 4 3.9 3231 824 2375 2375 32 13 YYDFDMTY25 4 4 3734 701 3000 3000 33 14 YYDFDMTY29 4 4.2 1102 819 250 250 33

Doumen

Taoyuan

Subtotal 17 16.1 2525 759 1735 1735 31 15 YYDFGCHFZH1 6 9.6 2855 1315 1500 1500 40 16 YYDFGCHFZH5 5 7 1832 996 800 800 36

Fengzhuang

Subtotal 11 16.6 2390 1170 1182 1182 38 17 YYDFGCHHS2 5 5.7 2699 1070 1600 1600 29 18 YYDFGCHHS3 7 12 1926 1626 0 0 300 19 YYDFGCHHS5 5 7.1 1933 1297 600 600 36

Huangsi

Subtotal 17 24.8 2155 1366 647 647 142 20 YYDFGCHLY01 7 5.2 2095 704 86 1286 1286 19 21 YYDFGCHLY03 7 7.2 3246 934 2286 857 26 22 YYDFGCHLY08 7 13 2635 1589 1000 1000 46 23 YYDFGCHLY09 7 11 3797 2622 714 429 429 32 24 YYDFGCHLY10 5 9.75 2775 1726 1000 1000 49

Liuyuan

Subtotal 33 46.15 2917 1502 170 1212 909 33 25 YYDFGCHLGD11 4 3.4 1392 469 900 900 23 26 YYDFGCHLGD24 6 5.8 4082 556 2500 1000 1000 26 27 YYDFGCHLGD25 8 5 821 504 300 300 17 28 YYDFGCHLGD28 12 11.5 4443 200 2917 2917 1326 29 YYDFGCHLGD29 7 8.9 2219 1043 1143 1143 33 30 YYDFGCHLGD30 5 3 1041 365 160 500 500 16

Guanchang

Lougudui

Subtotal 42 37.6 2635 494 376 1369 1369 395 31 YYDFJZHDD1 5 7.8 5931 1652 4000 0 279 32 YYDFJZHDD3 4 8 3067 1767 1250 0 50 33 YYDFJZHDD4 3 5 1650 1117 500 500 33

Didong

Subtotal 12 20.8 3906 1557 2208 125 141 34 YYDFJZHHCP1 4 5.8 2643 1857 750 0 36 35 YYDFJZHHCP2 5 6 1874 1244 600 0 30 36 YYDFJZHHCP4 4 5.3 1831 1198 600 600 33 37 YYDFJZHHCP5 4 5.3 2534 2001 500 500 33

Jiangzhuang

Hucunpu

Subtotal 17 22.4 2200 1555 612 259 33 38 YYDFJTJT08 4 4.9 1514 1108 375 375 31 39 YYDFJTJT09 4 4.1 2124 848 1250 1250 26 40 YYDFJTJT10 5 6.8 2069 1239 800 800 30 41 YYDFJTJT12 3 4.2 2047 1012 1000 1000 35 42 YYDFJTJT14 6 7.9 1598 898 667 667 33 43 YYDFJTJT15 6 6.7 1585 591 -167 833 0 328

Jiatan

Subtotal 28 34.6 1790 928 -36 804 625 94 44 YYDFJTNNM3 4 6.5 2181 1265 500 375 375 41 45 YYDFJTNNM4 2 5.8 3656 2583 1000 73

Nainaimiao

Subtotal 6 12.3 2672 1704 667 250 250 51 46 YYDFJTSHZH05 4 5.8 3072 1036 2000 2000 36 47 YYDFJTSHZH06 6 9.4 3285 1414 1833 1833 38 48 YYDFJTSHZH10 4 4.5 808 781 27 49 YYDFJTSHZH11 4 2.4 456 442 14 50 YYDFJTSHZH13 6 5.97 2544 1520 1000 1000 24

Jintang

Shizhuang

Subtotal 24 28.07 2180 1110 1042 1042 28 Total 247 286.72 2443 1063 12 91 1156 858 120

Page 87: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Yuanyang Dike Subproject Resettlement M&E Report (Report No. 5)

78

Page 88: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

77

ADB-loaned Yellow River Flood Management Sector Project

Puyang Dike Consolidation

RESETTLEMENT M&E REPORT (Report No. 4)

Henan Huanghe Resettlement Economic Development Company

December 2007

Appendix 2

Page 89: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

78

Approved: Yang Jianshe

Reviewed: Zhang Hao, Zuoping

Task Manager: Zuo Ping

Team Leader: Liu Fengjing

Chief Editor: Liu Fengjing, Duan Yongfeng

Proofreader: Jiao Lili, Zhao Hua’e, Wang Jianzhong, Yang Tao

Contributors (alphabetical): Dong Kunjie, Duan Yongfeng, Guan Guosheng, Lu

Shouchao, Li Li, Liu Fengjing, Song Bo, Wang Jianzhong,

Yun Lu, Yang Jianshe, Yang Tao, Zhang Hao, Duan Wei,

Zhao Huan’e, Zuo Ping

Page 90: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

79

Table of Contents

1. GENERAL ___________________________________________________________80

1.1 Subproject Brief _________________________________________________80

1.2 Implementation __________________________________________________80

2. MONITORING AND EVALUATION _____________________________________82

3. LAND ACQUISITION AND RESETTLEMENT____________________________82

3.1 Disbursement____________________________________________________82

3.2 Permanent Land Acquisition and Economic Rehabilitation _____________ 82

3.3 Temporary Land Occupation and Restoration ________________________ 84

3.4 Physical Relocation and Resettlement _______________________________85

3.5 Reconstruction of School __________________________________________86

3.6 Replacement of Special Facilities ___________________________________ 88

4. INCOME RECOVERY_________________________________________________88

4.1 Selection of Sample Households and Composition of Incomes____________88

4.2 Income Recovery of Sample Households _____________________________89

4.3 Implication of Income Changes _____________________________________ 90

5. PROTECTION OF RIGHTS AND INTERESTS____________________________91

5.1 Complaints Management __________________________________________91

5.2 Vulnerable Groups _______________________________________________ 91

6. SETTLEMENT OF EARLIER PROBLEMS_______________________________92

7. OUTSTANDING PROBLEMS AND RECOMMENDATIONS ________________92

Page 91: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

80

1. GENERAL

1.1 Subproject Brief

ADB-loaned Puyang Dike Consolidation Subproject is located on the left bank of the lower Yellow River, including two dikes 80+500-86+700 and 98+530-101+600, with a length of 9.27 km. Both are consolidated by warping, with a crest width of 100m, slope 1:3, a volume of 7.1838 million m3 earth works for embankments and 626,400 m3 for covering works and service roads.

The original project cost estimate approved by the State amounts to 140.38 million RMB (referred to as the “Original Estimate” hereinafter), including 30.21 million RMB for land acquisition (direct resettlement cost 27.72 million RMB). An “Implementation Scheme for Land Acquisition and Resettlement of Puyang Dike Consolidation” (referred to as the “Scheme” hereinafter) was prepared by Yellow River Engineering Co., Ltd. in July 2005 and approved by YRCC in letter No. (2005)143. However, many problems were found during implementation and YRCC decided to update and re-approve the Scheme, with an additional amount of 4.4376 million RMB direct costs in the updated Scheme approved by YRCC in letter No.[2006111. Later on, another additional amount of 5.8029 million RMB (including 560,500 RMB for young crops and 5.2429 million RMB for land restoration, overhead and registration) was approved by YRCC in letter No.[2006]119. As of this M&E, the approved total resettlement budget is 40.451 million RMB, including 32.7181 million RMB direct costs, and the completed amount is 30.944 million RMB. Refer to Table 1.

Table 1 Summary of Resettlement Costs Unit: 104 RMB

No. Item Original Additional Total Completed Remarks 1 Rural resettlement 2555.00 359.07 2914.07 2945.65 2 Special facility 217.00 140.74 357.74 148.75

Subtotal (direct resettlement cost) 2772.00 499.81 3271.81 3094.40

3 Miscellaneous & Resettlement Supervision

249.00 524.29 773.29

Total 3021.00 1024.1 4045.10

1. The amount of 32.7181 million RMB direct costs includes 32.1576 and 0.5605 million RMB approved in letters [2006]111 and [2006]119. 2. The amount of 7.7329 million RMB for resettlement supervision includes 2.49 and 5.2429 million RMB approved in letter Nos. [2006] 111 and [2006]119.

1.2 Implementation

Puyang Yellow River Engineering Bureau acts as the Project Employer who is responsible for project construction and resettlement management. Yellow River Engineering Co., Ltd. is appointed as the Designer in charge of planning and design and Henan Huanghe Resettlement Economic Development Company as the External Monitor.

Puyang County Government acts as the Implementing Agency is in charge of organizing and implementing physical relocation and resettlement. It has set up a Leading Group headed by the county governor and composed of members from relevant authorities and townships, to instruct, coordinate and inspect resettlement activities. Liyuan and Wangchenggu Township Governments are in charge of organizing and implementing land acquisition and resettlement activities according to the target-oriented management responsibilities agreed with the county government.

Page 92: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

81

Main works are finished and associated works are under construction.

In the Resettlement Plan (referred to as the “RP” hereinafter), it is planed to acquire 1,363.43 mu for the permanent use of works, new villages and special facilities, versus 1,516.68 mu in the Scheme, including 1,256.2 mu agreed and completed. The total area for temporary use is 2,300.98 mu in the RP versus 2,359.52 mu in the Scheme, including 2,124.68 mu agreed and completed. Physical relocation involves 6 villages and 205 households in the RP, versus 317 (with 59 idle houses included in house foundation compensation, infrastructure planning and transportation only, but excluded from land acquisition for new sites. The progress of housing in new sites is surveyed as part of this M&E) and 6 in the Scheme, including 227 completed in accordance with the progress of construction. Table 2 is a summary of the main physical indexes.

Table 2 Comparison of Main Physical Indexes

Item Unit RP Scheme 3rd M&E 4th M&R Increase Remarks

Affected village mu 12 12 13

Total area mu 1363.43 1516.68 1256.20 1256.20

Land for works mu 1176.74 1208.27

Farmland mu 595.45 743.21

Forestry mu 6.47

Pond mu 268.77 213.58

Non-farmland mu 306.05 251.48

New site mu 186.69 308.41

Residence mu 117.70 142.56

School mu 5 5

Road mu 4.36 19.52

1. Land

Irrigation canal mu 59.63 141.33

1256.20 1256.20

Affected village 6 6 6 6

Household 205 317 215 227 12 Incl. 59 idle houses in 317

People 819 1459 924 970 46

Housing area m2 24685.5 33714.01 26873.23 33241.54 6368.31

Brick-concrete m2 3498.3 4459.24 4180.03

2. Population & Housing

Brick-timber m2 18027.5 22993.36 23393.71

Fence m2 7765 10065.52 7833.06 9876.01 2042.95

Pressure well 163 323 234 295 61

Sparse tree 10240 26489 20984 25844 4860 3. Appurtenance

Tomb 150 1118 658 1090 432

School 1 1 1 1

Canal m/Qty 2250/2 4500/2

Road m/Qty 2260/14 2860/13

Power line m/Qty 3131/14 7750/14

Telecom line m/Qty 1340/5 12000/5

Permanent Land Use

4. Special facility

Bridge 3 9 5 5

Ongoing

1. Scope Affected village 15 22 7

Area mu 2300.98 2359.52 937.04 2124.68 1187.64

Irrigated land mu 2061.63 2359.52 937.04 2124.68 1187.64 2. Land

Floodland mu 239.35

Temporary Land Use

3. Appurtenance Sparse tree 6185 23579 3824 14211 10387

Page 93: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

82

2. MONITORING AND EVALUATION

It is the 4th M&E of Puyang Subproject. TOR was prepared and questionnaires formulated in September 2007, which was followed by field work. This report is prepared on the basis of subsequent field work, data processing and statistical analysis.

The focus of this M&E includes: (1) any change in permanent land acquisition and payment since the 3rd M&E, including economic rehabilitation; (2) the progress of temporary land use, payment, land restoration; (3) the status of physical relocation and rehabilitation of housing conditions; (4) the replacement of schools and special facilities, including disbursement and outstanding problems; and (5) the income recovery of sample households in 2006.

As understood in field surveys, a total area of 2,124.68 mu has been completed for temporary use, 1,187.64 mu more than the figure reflected in the last report. A progress has been made in school replacement, which is finished already, but without any change in permanent land acquisition, public participation, complaints management and vulnerable groups protection.

This report is focused on: additional temporary land use, affected area, extent of impact, land restoration, restoration of housing conditions, reconstruction of schools, and income recovery of sample households in 2006.

3. LAND ACQUISITION AND RESETTLEMENT

3.1 Disbursement

The compensation rates have not been changed since the last M&E. Disbursement is nearly finished. By the time of this M&E, Puyang Yellow River Bureau has agreed and disbursed a sum of 30.944 million RMB, taking up 94.58% of the total direct cost budget of 32.7181 million RMB, including 13.3911 million for permanent land use, 3.5495 million RMB for temporary land use, 7.8724 million RMB for housing, 270,200 RMB for school replacement, 1.4875 million RMB for special facilities, and 4.3733 million RMB for attachments and others. Refer to Table 3 for details.

The disbursement since the last M&E is 6.1393 million RMB, mainly for temporary land use and attachments and others, accounting for 37% and 40% respectively.

Table 3 Progress of Disbursement Unit: 104 RMB

Direct Cost Agreed & Completed No. Item Original Total 4th M&E 3rd M&E Increase 1 Permanent land use 1339.11 1339.11 0.00 2 Temporary land use 354.95 127.92 227.03 3 Housing 787.24 735.50 51.74 4 School 27.02 27.02 0.00 5 Special facility 148.75 61.23 87.52 6 Attachment & others

2772.00 3271.81

437.33 189.69 247.64 Subtotal 2772.00 3271.81 3094.40 2480.47 613.93

% of total 94.58 75.81 18.76

3.2 Permanent Land Acquisition and Economic Rehabilitation

The completed permanent land acquisition up to date is 1,256.2 mu, without any change since the last M&E, including 1,243.794 mu for the use of works and involving a total number of 12 villages, 2,084 households and 9,120 people, with a per capita land loss of 0.19 mu.

Page 94: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

83

Compensations are paid to villages and shared equally by all within the group, with land adjustment, or paid directly to households, without land adjustment (referred to as “Option A” or “Option B”). Land adjustment has been nearly finished by the time of this M&E.

As understood in interviews with the village leaders, the affected people have taken various measures to mitigate/offset the income impacts by farmland reduction, including farmer worker, business and extensive farming in account of their own capability and affordability.

To further understand what the affected people have done to recover their family incomes, 45 sample households have been selected and interviewed in the following aspects: (1) how was your family income affected as a result of farmland reduction? (2) how did you use you land compensations? what did you do to recovery you family income? As shown by the findings:

(1) Income impacts by farmland reduction: The total number of 45 households includes 22 households with less income from farming activities but more from other sources, without any impact on the total income, 10 subject to minor impacts due to less land loss, 8 subject to minor impacts due to interior quality of lost land, and 5 exposed to major impacts, taking up 48.9%, 22.2%, 17.8% and 11.1% respectively,

(2) Use of land compensations: Land compensations are used for farming by 14 (31.1%) of these 45 sample households, medical fees, children’s tuitions and daily expenses by 24 (53.3%), housing by 10 (22.2%), and business and debit repayment by others.

(3) Income recovery: The affected people have implemented various measures to recovery family incomes after farmland reduction, including 29 households working as farmer workers (64.5%), 2 doing business (4.4%), and 14 trusting to luck (31.1%).

Refer to Table 4 for a summary of impacts, remedy measures, and compensation uses.

Table 4 Questionnaire of Impacts, Remedy Measures and Compensation Uses No. Item Household % Remarks

I Impact by farmland reduction 45

1 Less income from farming, but more from other sources, without any impact on total income 22 48.9

2 Minor impact due to less land loss 10 22.2 3 Minor impact due to poor land quality 8 17.8 4 Major impact 5 11.1 5 Others II Use of land compensations 1 Farming 14 31.1 2 Business 2 4.4 3 Housing 10 22.2 4 Medical fees, tuitions and other living expenses 24 53.3 5 Debit repayment 1 2.2

Some farmers give more than one answer, showing more than one use.

6 Others III Remedy measures 1 Farmer worker 29 64.4 2 Business 2 4.4 3 Cropping, animal raising or plastic tunnel 4 Extensive farming and intercropping 5 Reclamation or cultivating others’ land 6 Trust to luck 14 31.1 7 Others

Page 95: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

84

3.3 Temporary Land Occupation and Restoration

Temporary Land Occupation: As main works are almost completed, temporary land occupation is finished, involving 4 townships and 22 villages. A total area of 2,124.68 mu has been agreed and completed, 1,187.64 mu larger than the figure reported last time, taking up 92% of 2,300.98 mu proposed in the RP and 90% of 2,359.52 mu in the Scheme.

(1) Occupation: a total of 369.82 mu in 17 villages of 4 townships;

(2) Excavation: a total of 1,754.85 mu in 10 villages of 2 townships. To minimize the use of land, many lands are used for both pumping and excavation works during construction. It is hard to take them apart, so they are all considered as land for excavation. Excavation mostly happens in Donglou, Tunzhuang, Houliyuan and Mahai of Liyuan Township, Wuxiangtun and Suliangzhuang of Wangchenggu.

The lands for temporary use in Donglou, Tunzhuang, Houliyuan and Mahai of Liyuan Township are all located in low-lying areas on the waterside, with low and instable outputs. In Wuxiangtun and Suliangzhuang, the lands for such purposes are all fresh floodland near the river course, to be restored naturally when flooded, normally one crop in the year.

Land Restoration

(1) Occupation: The land for temporary use can be restored naturally upon completion of the project. Up to date, 275.42 mu has been restored, accounting for 74% of 369.83 mu occupied. The remaining land is not restored yet because some pipes are not removed and will be used for warping purposes of land restoration.

(2) Excavation: A total area of 1,754.85 mu has been used for excavation, including 574.41 mu restored already, taking up 33%. The remaining lands are distributed in Wuxiangtun and Suliangzhuang, all fresh floodland close to the Yellow River, to be restored naturally by gravity warping. This will not be a big problem. The lands for excavation in Donglou and Houliyuan, all located on the waterside and at the dike foot, are used as agreed in the “Agreement on Soil Improvement” between villages and contractors, who have promised to restore the lands about 0.5 m above the ground in the surroundings by May 2007. Also, it is stated in the agreement that compensation will be paid continuously if there is any delay in restoration. Land restoration is partly unfinished and compensations are not paid to households as agreed. This will continue to draw the attention of the M&E team.

Refer to Photographs 1 and 2 for the progress of temporary land occupation and restoration, and also Table 5 for detailed information.

Photograph 1: Restored Land in Donglou Photograph 2: Land Being Restored in Wuxiangtun

Page 96: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

85

Table 5 Progress of Temporary Land Occupation and Restoration Completed Restored %

Subtotal Occupation Excavation No. Township & Village

4th M&E 3rd M&E 4th M&E 3rd M&E 4th M&E 3rd M&E Subtotal Occupation Excavation Subtotal Occupation Excavation

Unit mu mu mu mu mu mu mu mu mu % % % 1 Xixinzhuang 3.18 3.18 3.18 3.18 3.18 3.18 100 100 2 Wangdaozhuang 15.05 15.05 15.05 15.05 15.05 15.05 100 100 3 Tunzhuang 241.97 40.63 40.63 40.63 201.34 70 20 50 29 49 25 4 Meizhai 0.9 0.9 0.9 0.9 0.9 0.9 100 100 5 Liuzhai 20.75 20.75 20.75 20.75 20.75 20.75 100 100 6 Donghanzhai 20.89 20.89 20.89 20.89 20.89 20.89 100 100 7 Renzhai 95.13 80.14 5.69 5.69 89.44 74.45 45.69 5.69 40 48 100 45 8 Xihanzhai 10.87 10.87 4.46 4.46 6.41 6.41 10.87 4.46 6.41 100 100 100 9 Gaozhai 0.95 0.95 0.95 0.95 0.95 0.95 100 100 10 Zhangshuikeng 33.48 17.52 33.48 17.52 17.52 17.52 52 52 11 Dongxizhuang 20.97 4.92 20.97 4.92 4.92 4.92 23 23 12 Qianliyuan 30.96 8.03 8.03 8.03 22.93 8 8 26 35 13 Donglou 178.89 178.89 178.89 178.89 20 20 11 11 14 Houliyuan 89.52 89.52 89.52 89.52 15 Mahai 450.24 450.24 150 33 33 16 Tunzhuang 26.04 26.04 26.04 100 100 17 Others 14.45 14.45 14.45 14.45 14.45 14.45 100 100

Liyuan 1254.24 506.69 215.47 157.42 1038.8 349.27 429.21 154.8 274.41 34 72 26 1 Chaozhuang 4.66 9.51* 4.66 9.51 4.66 4.66 100 100

Xuji 4.66 9.51 4.66 9.51 4.66 4.66 100 100 Baigang 71.42 37.68 71.42 37.68 37.68 37.68 53 53

1 Wuxiangtun 514.19 326.49 11.85 502.34 311.85 11.85 300 61 100 60 2 Suliangzhuang 205.29 16.56 16.56 205.29 3 Yugu 8.45 17.49 17.49 8.45 4 Mazhang 4.69 10.71 4.69 10.71 4.69 4.69 100 100 5 Fantun 5.07 11.91 5.07 11.91 5.07 5.07 100 100 6 Others 56.67 56.67 56.67 56.67 56.67 100 100

Wangchenggu 794..36 383..16 78.28 56.67 716.0.8 326.49 378..28 78.28 300 48 100 42 Total 2124..68 937..04 369..83 261.28 175.4.88 675.76 849..83 275.42 574.41 40 74 33

Notes: 1. Figures are from the External Monitor; 2. Report No. 3 includes errors in Chaozhuang.

3.4 Physical Relocation and Resettlement

In the RP, physical relocation involves 6 villages, 205 households and 819 persons, versus 6, 258 and 1,188 in the Scheme (excluding 59 idle houses of 271 people). According to resurvey results, it is necessary to relocate 227 households. This part of work is finished, involving 6 villages and 970 people, including 48 households and 208 people in Qianliyuan, 48 and 270 in Houliyuan, 37 and 180 in Donglou, 3 and 14 persons in Qianchen, 79 and 226 in Houchen, 12 and 72 in Zhaozhuang. The removed total housing area is 33,241.54 m2, including 1,586.42 m2 multistory, 4,180.03 m2 brick-concrete, 23,393.71 m2 brick-timer, 667.85 m2 earth-timer, 3,413.53 m2 simple and other structures.

By the time of report, 227 households have been completed, 78 more than the figure reported last time, taking up 88% of the total number of 258 households.

Homesteads are needed for all of these 227 households. Now, this part of work is finished, 25 households more than reported last time, or a percentage of 6%.

Altogether 177 households have moved to new houses, an increase of 62 in comparison with the progress made by the last M&E, or 24.5%, while 28 live in borrowed houses, 10 in rent ones and 12 in other dwelling places. The progress of physical relocation meets the schedule of construction. Resettlement families are resettled properly. New houses are improved in

Page 97: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

86

respect of floor area, lighting and structure. Water/power supply is nearly completed. Living circumstances are somewhat bettered. Refer to Photographs 3 and 4.

As known from interviews with the Implementing Agency and the affected households, some people are not eager to build new houses partly because they are busy as farmer works or businessmen all the year round, without thinking about housing, and partly because they live with their children, without any plan to build new houses at present. Tables 6 and 7 show the progress of physical relocation and resettlement.

Photograph 3: New House in Donglou Photograph 4: New House In Zhaozhuang

Table 6 Progress of Physical Relocation and Resettlement Homestead Housing Resettlement Item Village Household Subtotal Completed Subtotal Built Subtotal New House

Unit home home home home home home Qty 6 215 215 202 202 117 215 115 3rd

M&E % 94 57.9 53.5 Qty 6 227 227 227 227 177 227 177 4th

M&E % 100 78 78 Qty 6 12 12 25 25 60 12 62 Increase % 6 20.1 24.5

3.5 Reconstruction of School

Donglou Primary School in Liyuan Township needs to be removed and reconstructed. On the principle of restoring the “original scale, original standard, original function”, a new school is to be built in the original village. The budget is 264,400 RMB (excluding land acquisition for the new site) in the RP and 270,200 RMB in the Scheme, including house compensation, ground leveling, access road, power/power supply and other infrastructures. Now, this amount of 270,200 RMB has been disbursed to Donglou in full as agreed. The new site is wide open and immediately close to the main street in the village, convenient for pupils to go to school.

A significant progress has been made since the last M&E, including the acquisition of 4.5 mu land and completion of 13 rooms (310m2), which are being installed with doors/windows and painted. When this report is completed, Grades 1-3 will have been moved to new classrooms at the end of November 2007. As illustrated in Photographs 5 and 5, the new school and its surroundings are much better.

Page 98: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

87

Table 7 Progress of Physical Relocation and Housing Restoration Date: 21st September, 2007

Removed Homestead Identification Housing Resettlement Needed Needed No. Village Stage

Home PeopleSub-total Sub-

totalDone Not

Not Needed

AreaSub-total Sub-

total Built

BeingBuilt

OthersNot

neededTotal New Borrow Rent Temporary Others

Unit home person home home home home home mu home home home home home home home home home home home Column 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

RP 205 819 0.25 Scheme 258 1188 0.40 Total 6 Completed 227 970 227 227 227 0.40 227 227 177 39 11 227 177 28 10 12 PR 29 130 0.25 Scheme 49 225 0.40 1 Qianliyuan Completed 48 208 48 48 48 0.40 48 48 48 48 48 PR 49 216 0.25 Scheme 47 257 0.40 2 Houliyuan Completed 48 270 48 48 48 0.40 48 48 9 39 48 9 20 7 12 PR 49 131 0.25 Scheme 57 205 0.40 3 Donglou Completed 37 180 37 37 37 0.40 37 37 37 37 37 PR 3 13 0.25 Scheme 3 14 0.40 4 Qianchen Completed 3 14 3 3 3 0.40 3 3 3 3 3 PR 61 288 0.25 Scheme 81 394 0.40 5 Houchen Completed 79 226 79 79 79 0.40 79 79 79 79 79 PR 14 41 0.25 Scheme 21 93 0.40 6 Zhaozhuang Completed 12 72 12 12 12 0.40 12 12 1 11 12 1 8 3

Notes: 1. The number of 258 households in the Scheme excludes 59 idle houses. 2. “RP” and “Scheme” figures are from the Special Report prepared by Yellow River Engineering Co., Ltd., while the “Completed” ones are from field surveys.

3. Column 1=column 3=column 9=column 15.

Page 99: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

88

Photograph 5: Donglou School under Construction Photograph 6: Gate of Donglou School

3.6 Replacement of Special Facilities

The affected special facilities include roads, power lines, telecommunications and irrigation facilities. Those having lost functions are excluded from the RP and are not to be replaced.

Qingjiangou, previously an irrigation and drainage canal, is already restored and put into operation.

The access bridge across the ditch is restored with additional compensations.

Yanglougou, which used to be a drainage ditch not related to farming significantly, has not been implemented since the new site is not determined yet. To implement as planned will necessitate the resettlement of many people and represent a high degree of difficulty.

The restoration of service roads is underway.

Replacement is not necessary for some power and telecommunications facilities, which are compensated only, but necessary for others. This part of work is finished.

4. INCOME RECOVERY

4.1 Selection of Sample Households and Composition of Incomes

A baseline survey was conducted in 2004 and follow-up monitoring in 2005. Altogether land acquisition was started in October 2005, but not implemented on a large scale until the spring 2006, without affecting the farming incomes of sample households in 2005, so this report compares with the situation in 2005. This follow-up monitoring covers 41 households and 186 people selected from the 88 sample households, all resettled in the mode of Option A, which is adopted by all the affected villages except in Zhaozhuang, where few groups prefer Option B. The farmland area of these 41 sample households is reduced from the original 217 mu to 184.7 mu, i.e. 34.3 mu less, with a per capita loss of 0.17 mu of 14.9%.

In 2006, these sample households had a per capita net income of 1,505 RMB, including 481 RMB from farming, 995 RMB from sideline and 29 from other sources, taking up 32%, 66.1% and 1.9% respectively. As judged from the structure of incomes, sidelines play the leading role in family incomes, especially farmer workers, who contributed 884 RMB or 88.8% to the income from sidelines.

Page 100: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

89

The per capita income in 2006 was 275 RMB more than in 2005, with 357 RMB more from sideline and other sources, but 84 RMB less from farming and animal raising.

Refer to Table 8 for the per capita net income, Chart 1 for income composition, and Attached 1 for breakdown income of sample households with versus without project.

Table 8 Farmland Reduction and Per Capita Income of Sample Households

Sideline (RMB) Year

Farmland (mu)

Total Income (RMB)

Farming Income (RMB)

Subtotal Farmer Worker

Others

Animal Raising (RMB)

Others (RMB)

2005(without project) 217 1230 560 649 567 82 5 16 2006(with project) 184.7 1505 481 995 884 111 29 Change 32.3 275 -79 346 317 28 -5 13 % 14.9 22.4 -14.1 53.3 55.9 33.7 -100 81.3

Chart 1 Income Composition of Sample Households

图 1 濮阳堤防加固工程前后样本户人均收入

4.2 Income Recovery of Sample Households

As seen from follow-up monitoring results, the family income of sample households is not reduced as a result of farmland reduction, mainly because the major income source of most families is sideline. In 2005, sideline and farming activities contributed 52.8% and 45.5% to the total family incomes, versus 66.1% and 32% in 2006. Farming takes up a small proportion and largely depends on the year’s harvest. After land acquisition, more is generated by sideline activities, mainly farmer workers, with an increase from 567 RMB to 884 RMB, or a per capita increase of 317 RMB, which offsets the loss due to farmland reduction.

The following box contains a typical interview with affected farmers, giving a picture of the impacts on production/livelihood.

Interview regarding Income Recovery (Option A)

Time: 19th September 2007 Place: Gaozhai in Liyuan Township

Name: Gao Xiangxian Position: farmer

Sex: male Age: 60 Education: junior middle school

Interviewer: Hello, how many people are there in your family? How much land did you have? How much was used for the project? When?

0200400600800

1000120014001600

Tot al Far mi ng Si del i ne Ani malRai si ng

Ot her s

2005(without project)

2006(with project)

Page 101: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

90

Interviewee: 5 people, 5 mu land, including 1.5 mu acquired in June 2005.

Interviewer: Was land adjustment arranged subsequently? If yes, when?

Interviewee: Yes, in September 2005.

Interviewer: How much have you received as land compensation? How many times has it been paid? What are the constituents? How have you used the money?

Interviewee: I received 10,000 RMB at 3 different times, including 2 portions, one paid for young crops and the other for land compensations which were shared equally with all others. I used it cover medical fees and daily expenses.

Interviewer: As farmland is reduced, what have you done to offset your income loss?

Interviewee: Mainly farmer workers, to effectively maintain the income level.

Interviewer: Do you think your family income is greatly affected?

Interviewee: It is affected to a certain extent, but I’m working as a farmer worker now, and family income is ever higher than that before.

Interviewer: Are you satisfied with the existing production/living conditions? What’s your plan for the future?

Interviewee: I’m basically satisfied. I will continue to be a farmer worker, as the major source of family income.

Interviewer: Thank you and wish you a better life, we will be back in the near future.

Farmland reduction does reduce farming incomes. As judged from interviews, however, the affected farmers have built new houses with land compensations, some have bought tricars, tractors and other farming machines and tools, and some have developed animal raising activities. More farming machines represent better production conditions. Also, some farmers invest their compensations in business, and more people go out as farmer workers, to increase their family incomes by various means.

As presented by the leaders of Qianliyuan, their land compensations are shared equally according to the number of people, with land adjusted accordingly. The money, when received, is mostly used to buy farming machines and means of transportation, while a few households do business and 5 develop animal raising activities, including one with additional number of 20 sheep. Additionally, some people increase their family income as farmer workers.

Gao Xinxiang, a resettler and also a land loser, operates an electric motorcar shop with a loan in addition to land compensation. Now, he earns about 20,000 RMB a year. See Photograph 7 for his shop.

4.3 Implication of Income Changes

According to China’s communiqué of national economic and social development, the total number of sample 41 households and 186 people include 49 absolutely poor

Photograph 7: Gao Xinxiang’s Electric Motorcar Shop

Page 102: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

91

people (26%) with a per capita income less than 693 RMB, 2 or 1% less than the number before; 29 low-income people (16%) with 694-958 RMB, 7 or 4% more; and 108 non-poor people (58%) with more than 958 RMB, 5 or 3% less. Refer to Table 9 for detailed figures.

Table 9 Comparison of Poverty Populations Year Item Standard Household People % of People

Unit RMB/year·person home person % Absolutely <683 14 51 27 Low-income 684-944 5 22 12 Non-poor >944 22 113 61 2005

Subtotal 41 186 100 Absolutely <693 12 49 26 Low-income 694-958 6 29 16 Non-poor >958 23 108 58 2006

Subtotal 41 186 100 Absolutely <693 -2 -2 -1 Low-income 694-958 1 7 4 Change Non-poor >958 1 -5 -3

5. PROTECTION OF RIGHTS AND INTERESTS

5.1 Complaints Management

Regarding complaints management, the 45 households interviewed in 9 villages believe that the channels are smooth and complaints are basically responded to. As known in interviews, some farmers complain that the land for excavation has not been restored as agreed, hoping the relevant parties to cause early restoration.

5.2 Vulnerable Groups

Now vulnerable groups are properly resettled, with 3 major sources of income: income from farmland cropped by their relatives/friends, food and monetary relief provided by the county civil administration on festivals, and old folk’s home operated by township governments.

This M&M includes continued attention to Cao Yincheng, a poor family in Qianliyuan. At the time of the last M&E, he was temporarily resettled in 3 idle rooms at the central primary school. Now, having moved to a new house, he is satisfied with the production and living conditions. See Photographs 8 and 9 for his housing conditions.

Photograph 8: Cao’s Temporary Home (in 2006) Photograph 9: Cao’s Comfortable New House

Page 103: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

92

6. SETTLEMENT OF EARLIER PROBLEMS

(1) The problem of pending infrastructures in the new sites of Qianliyuan and Doulou has been reflected in the previous report. With an additional amount in place, the local government is arranging implementation in account of the actual conditions in 6 new villages. The infrastructures in Donglou new site have been completed, and compensations paid in full to the rest 5 villages, which are free to use them.

(2) As for the problem of pending reconstruction of Donglou Primary School, a new site has been identified, close to the main street and convenient for pupils to go to school. An obvious progress has been made since the last M&E, with 4.5 mu land acquired, 13 new rooms (310 m2) built and Grades 1-3 moved to new classrooms in November 2007. The school conditions will be thoroughly improved.

7. OUTSTANDING PROBLEMS AND RECOMMENDATIONS

The main existing problem is land restoration. Some land for excavation is not restored, and compensations are neither paid to households as agreed. The farmers complain about this. It is expected that responsible departments draw attention to this, to enable early payment and restoration. The M&E team will continue its attention to this issue.

Page 104: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

93

Attachment 1:

Breakdown Per Capita Income of Sample Households in 2005 Sideline Others

No. Township Village Sample Code PeopleOriginal Farmland

(mu)

Per Capita Income (RMB)

FarmingAnimal Raising Subtotal

Farmer Worker

Subtotal

1 PYDFLYDXZH03 2 3.6 369 346 23 2 PYDFLYDXZH04 3 5.3 952 929 23 3 PYDFLYDXZH06 6 5.6 1014 668 333 333 13 4 PYDFLYDXZH07 3 5.0 98 85 13 5 PYDFLYDXZH08 3 5.5 448 98 333 333 17 6 PYDFLYDXZH10 5 7.0 1574 1541 33 7 PYDFLYDXZH11 4 4.8 410 248 150 150 12 8 PYDFLYDXZH12 5 7.5 451 432 19 9 PYDFLYDXZH18 4 7.5 3676 652 3000 3000 24

10 PYDFLYDXZH20 4 5.5 1075 808 250 250 17

Dongxinzhuang

村合计 39 57.3 1079 634 426 426 19 11 PYDFLYDL01 12 15.0 1964 112 1833 1833 19 12 PYDFLYDL02 3 4.2 130 112 18 13 PYDFLYDL14 2 3.4 570 548 22 14 PYDFLYDL16 3 7.0 717 697 20 15 PYDFLYDL17 4 7.0 1347 1120 200 200 27

Donglou

Total 24 36.6 1359 389 950 950 20 16 PYTFYYXGZH04 5 5.0 243 230 13 17 PYTFYYXGZH05 5 6.5 978 961 17 18 PYTFYYXGZH11 5 4.5 1305 489 800 800 16 19 PYTFYYXGZH14 6 5.0 1039 528 500 500 11 20 PYTFYYXGZH15 3 3.3 573 559 14

Gaozhai

Total 24 24.3 858 552 292 292 14 21 PYDFLYHLY04 8 4.0 1575 318 1250 1250 7 22 PYDFLYHLY08 5 5.0 730 720 10 23 PYDFLYHLY10 4 4.0 728 715 13 24 PYDFLYHLY11 3 3.0 1166 320 833 833 13 25 PYDFLYHLY14 7 4.0 580 431 142 7 26 PYDFLYHLY15 7 5.7 2288 205 2071 2071 12

Houliyuan

Total 34 25.7 1257 424 29 794 794 10 27 PYDFLYQLY03 2 2.3 2667 653 2000 14 28 PYDFLYQLY05 4 3.6 1482 470 1000 12 29 PYDFLYQLY06 3 4.0 3546 1196 2333 17 30 PYDFLYQLY07 5 6.5 1999 982 1000 1000 17

Qianliyuan

Total 14 16.4 2279 835 1429 357 15 31 PYDFLYXXZH03 6 7.0 658 636 22 32 PYDFLYXXZH04 6 11.0 888 855 33

Liyuan

Xixinzhuang Total 12 18.0 772 745 27

33 PYDFWCGHC01 1 1.4 606 588 18 34 PYDFWCGHC02 4 4.0 241 228 13 35 PYDFWCGHC03 6 7.0 1775 921 833 833 21 36 PYDFWCGHC05 4 4.8 926 910 16 37 PYDFWCGHC10 5 3.5 1232 423 800 800 9 38 PYDFWCGHC13 6 6.5 1906 561 1333 1333 12

Houchen

Total 26 27.2 1289 621 654 654 14 39 PYTFWCGQC02 6 4.5 1313 469 833 833 11 40 PYTFWCGQC04 3 2.5 558 427 120 0 11 41 PYTFWCGQC10 4 4.5 1645 379 1250 1250 16

Wangchenggu

Qianchen

Total 13 11.5 1241 431 797 769 13 Grand Total 186 217 1230 560 5 649 567 16

Page 105: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Puyang Dike Subproject Resettlement M&E Report (Report No. 4)

94

Breakdown Per Capita Income of Sample Households in 2006 Sideline Others

No. Township Village Sample Code PeopleOriginal Farmland

(mu)

Per Capita Income (RMB)

FarmingSubtotal

Farmer Worker

Subtotal

1 PYDFLYDXZH03 2 3.0 92 50 0 0 42 2 PYDFLYDXZH04 3 4.5 835 793 0 0 42 3 PYDFLYDXZH06 6 5.0 1363 904 417 417 42 4 PYDFLYDXZH07 3 4.5 141 99 0 0 42 5 PYDFLYDXZH08 3 4.2 608 569 0 0 39 6 PYDFLYDXZH10 5 6.0 1015 960 0 0 55 7 PYDFLYDXZH11 4 4.8 704 421 250 250 33 8 PYDFLYDXZH12 5 6.2 1023 589 400 400 34 9 PYDFLYDXZH18 4 6.0 4250 458 3750 3750 42

10 PYDFLYDXZH19 4 5.0 263 221 0 0 42

Dongxinzhuang

Total 39 49.2 1132 565 526 526 41 11 PYDFLYDL01 12 13.1 1796 222 1542 833 32 12 PYDFLYDL02 3 2.7 9952 -73 10000 10000 25 13 PYDFLYDL14 2 3.2 532 487 0 0 45 14 PYDFLYDL16 6 6.5 1416 486 900 900 30 15 PYDFLYDL17 4 6.8 373 26 300 300 47

Donglou

Total 27 32.3 2313 238 2041 1726 34 16 PYTFYYXGZH04 5 4.0 731 499 200 200 32 17 PYTFYYXGZH05 5 5.0 752 624 100 100 28 18 PYTFYYXGZH11 5 3.0 4204 188 4000 4000 16 19 PYTFYYXGZH14 6 3.5 189 173 0 0 16 20 PYTFYYXGZH15 3 2.1 1447 228 1200 1200 19

Gaozhai

Total 24 17.6 1413 345 1046 1046 22 21 PYDFLYHLY04 8 3.5 1557 293 1250 1000 14 22 PYDFLYHLY08 5 3.5 276 265 0 0 11 23 PYDFLYHLY10 4 3.0 390 369 0 0 21 24 PYDFLYHLY11 3 2.3 1344 323 1000 1000 21 25 PYDFLYHLY14 7 3.8 346 331 0 0 15 26 PYDFLYHLY15 6 5.7 3383 688 2667 2667 28

Houliyuan

Total 33 21.8 1277 380 879 818 18 27 PYDFLYQLY03 2 2.0 2636 608 2000 2000 28 28 PYDFLYQLY05 4 3.0 1797 779 1000 0 18 29 PYDFLYQLY06 3 3.6 2490 790 1667 0 33 30 PYDFLYQLY07 4 5.0 2517 990 1500 1500 27

Qianliyuan

Total 13 13.6 2308 820 1462 769 26 31 PYDFLYXXZH03 6 6.5 808 772 0 0 36 32 PYDFLYXXZH04 6 9.0 840 648 150 150 42

Liyuan

Xixinzhuang Total 12 15.5 824 710 75 75 39

33 PYDFWCGHC01 1 1.4 1377 1322 0 0 55 34 PYDFWCGHC02 4 4.0 1438 886 525 525 27 35 PYDFWCGHC03 6 6.2 1638 410 1200 1200 28 36 PYDFWCGHC05 4 3.6 1324 424 875 875 25 37 PYDFWCGHC10 5 3.5 1993 971 1000 1000 22 38 PYDFWCGHC13 6 6.0 656 295 333 333 28

Houchen

Total 26 24.7 1391 602 762 762 27 39 PYTFWCGQC02 5 3.7 1491 351 1120 1120 20 40 PYTFWCGQC04 3 2.1 475 123 333 0 19 41 PYTFWCGQC10 4 4.2 3072 794 2250 2250 28

Wangchenggu

Qianchen

Total 12 10.0 1765 442 1300 1217 23 Grand Total 186 184.7 1505 481 995 884 29

Page 106: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

95

ADB-loaned Yellow River Flood Management Sector Project

Mudan Dike Consolidation

RESETTLEMENT M&E REPORT (Report No. 4)

Henan Huanghe Resettlement Economic Development Company

December 2007

Appendix 3

Page 107: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No.4)

96

Approved: Yang Jianshe

Reviewed: Zhang Hao, Zuo Ping

Task Manager: Zuo Ping

Team Leader: Chang Quanli

Chief Editor: Chang Quanli, Li Yang

Proofreader: Wang Jianzhong, Jiao Lili, Yang Tao

Contributors: Chen Aiqin, Chang Quanli, Duan Yongfeng, Jiao Lili, Li Yang, Shen Yanlong, Sun Fengzhi, Wang Jianzhong, Xue Changyu, Yang Jianshe, Yang Tao, Zhang Hao, Zhao Huan’e, Zuo Ping, Duan Wei

Page 108: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No.4)

97

Table of Contents

1. GENERAL ___________________________________________________________99

1.1 Subproject Brief__________________________________________________ 99

1.2 Land Acquisition and Resettlement_________________________________100

1.3 Monitoring and Evaluation _______________________________________ 103

1.3.1 Study Area and Focus _______________________________________103

1.3.2 Methodology ______________________________________________103

1.3.3 Schedule _________________________________________________103

2. DISBURSEMENT AND PAYMENT _____________________________________103

2.1 Disbursement ___________________________________________________103

2.1.1 Process of Disbursement_____________________________________103

2.1.2 Progress of Disbursement and Payment _________________________104

2.2 Comparison of Compensation Rates ________________________________105

2.3 Balance and Its Use ______________________________________________105

3. LAND ACQUISITION AND ECONOMIC REHABILITATION______________106

3.1 Permanent Land Acquisition and Economic Rehabilitation_____________ 106

3.2 Temporary Land Use and Restoration ______________________________107

4. RESTORATION OF HOUSIGN CONDITIONS ___________________________108

4.1 Physical Relocation ______________________________________________ 108

4.2 Resettlement____________________________________________________108

4.3 Development of Residential Sites ___________________________________ 110

5. REPLACEMENT OF SPECIAL FACILITIES ____________________________ 110

6. INCOME RECOVERY________________________________________________ 111

6.1 Selection and Follow-up Monitoring of Sample Households_____________ 111

6.2 Recovery of Incomes _____________________________________________ 113

6.2.1 Recovery of Farming Incomes ________________________________113

6.2.2 Sideline and Other Incomes __________________________________113

6.2.3 Analysis of Income Recovery _________________________________114

6.3 Implication of Income Changes ____________________________________ 115

7. PROTECTION OF RIGHTS AND INTERESTS___________________________ 115

7.1 Training _______________________________________________________ 115

7.2 Complaints Management _________________________________________ 116

7.3 Vulnerable Groups ______________________________________________ 116

Page 109: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No.4)

98

8. EVALUATION AND RECOMMENDATION _____________________________ 116

8.1 Evaluation _____________________________________________________ 116

8.2 Problems and Recommendations___________________________________ 117

8.2.1 Settlement of Earlier Problems ________________________________117

8.2.2 Outstanding Problems _______________________________________117

ANNEX 8-1 INTERVIEW REGARDING INCOME RECOVERY ______________ 118

Page 110: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

99

1. GENERAL

In September 2005, a baseline survey and the first monitoring of Mudan Dike Consolidation Subproject (“Mudan Subproject”) were carried out by Henan Huang Resettlement Economic Development Company (“HHREDC”), with baseline data established for 41 sample households from 7 villages. On this basis, a baseline survey report and 3 M&E reports have been prepared in Chinese and English. This document reports the 4th M&E.

1.1 Subproject Brief

The main works under this subproject comprise warping works with a total length of 9.733 km and width of 100+10 m, wave protection forests with a length of 887 m and width of 30 m, crest roads, and associated structures.

A budget of 27.31 million RMB for land acquisition and resettlement was approved by the State in 2004 (referred to as the “Approved Budget” hereinafter), including 25.06 million RMB for direct resettlement costs and miscellaneous.

Based on the “Special Report on Preliminary Design of Land Acquisition and Resettlement for Mudan Dike Consolidation” (referred to as the “Resettlement Plan” or “RP” for short) approved by the State, a “Special Report of Implementation Scheme for Land Acquisition and Resettlement of Mudan Dike Consolidation (right-bank 217+968~221+110, 224+100~227+ 500, 229+670~232+861, referred to as the “IS”) was completed by the Yellow River Engineering Consulting Co., Ltd. in May 2005 and subsequently approved by Shandong Yellow River Engineering Bureau in letter No. [2005]42, with a total budget of 28.14 million RMB (including 25.89 million RMB as direct resettlement costs).

In November 2005, the Project Office at Shandong Yellow River Engineering Bureau issued a letter under the title of “Approval of Compensations for A kiln in Mudan Dike Subproject (217+968~221+110)” (Ref [2005]21), with an additional amount of 182,700 RMB approved as compensation for the kiln and included in resettlement contingencies.

In December 2006, YRCC certified an additional budget of 8.2552 million RMB under the title “Approval of Resettlement Costs for Shandong ADB-loaned Project” (Ref[2006]133), including 638,900 RMB for young crops (included in direct costs), 7.1559 million RMB for land reclamation, 247,800 RMB for overhead, 202,600 land surveying and 10,000 RMB for land registration. This additional budget was paid out of the resettlement contingencies and the saved construction costs.

Up to date, a total budget of 36.5752 million RMB has been certified, including 26.7089 million RMB as direct resettlement costs. Refer to Table 1-1 for details.

Page 111: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

100

Table 1-1 Schedule of Resettlement Costs Unit: 104 RMB

No. Item Approved Additional Total Remarks

I Rural resettlement 2308 2285.89 Including land restoration and young crops covered by additional budget

II Relocation of industry 25 92 Including 182,700 RMB for a kiln due to design changes

III Replacement of special facility 173

164.89

293

The increase results from the additional costs for replacing irrigation and power facilities and roads, and the additional costs paid for such facilities at the rates of Shandong.

Subtotal 2506 164.89 2670.89

IV Miscellaneous 175 761.63 936.63 Including land restoration and others covered by the additional budget

V Resettlement supervision 50 50 VI Total 2731 926.53 3675.52

Source: Letter [2005]42 and [2005]21 of Shandong Yellow River Engineering Bureau and [2006]133 of YRCC.

1.2 Land Acquisition and Resettlement

Heze Yellow River Engineering Bureau acts as the Employer, which has established Mudan Project Office to be fully responsible for field management.

Mudan District Government has a Project Office also (referred to as the “District Project Office” hereinafter), which includes a general office to take the responsibility for steering and coordination during implementation.

Further to these institutional arrangements, the Employer has employed Heze Yellow River Industrial Co., Ltd. to be responsible for special facility replacing and land restoration and Engineering Department 2 of Heze Yellow River Engineering Bureau for site clearing and compensation.

The Yellow River Engineering Consulting Co., Ltd. is employed as the Designer and the HHREDC as the Internal Monitor.

According to the IS, permanent land use mainly involves 13 villages in Licun Township of Mudan District, Caiyuanji Township of Dongming County and Linpu Township of Juancheng County.

The main works have been completed. In comparison with the progress made by the last E&M, the land acquired for permanent use is increased by 1.08 mu. By the time of 4th E&M, 1,228.99 mu have been acquired in 12 villages (96.4% of the IS) and 3,370.52 m2 housings relocated (95.7% of the IS, 757.18 m2 more than M&E Report 3). Refer to Table 1-2.

With regard to special facilities, Heze Yellow River Industrial Co., Ltd. has built 4 bridges and hardened 2 access roads.

Compensation for the enterprise owned by Heze Yellow River Industrial Co., Ltd. has been

Page 112: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

101

completed. Refer to Table 1-2 for a comparison of resettlement work quantities.

Page 113: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

102

Table 1-2 Comparison of Main Indexes

Item Unit RP IS 3rd M&E 4th M&E Increase Remarks

Affected village No. 13 13 12 12

New land acquisition mu 1402.55 1274.26 1227.91 1228.99 1.08

Incl. Farmland mu 940.43 1026.42 1093.56 1094.64 1.08

Garden plot mu 80.95

Pond mu 42 110.32 101.82 101.82

Forestland mu 246.59 27.19 32.53 32.53

Non-productive mu 92.58 110.33

1. Land

Existing land acquisition mu 128.29

Affected village No. 6 6 6 6

Number of households No. 63 69 25 30 5

Number of people person 241 255 89 118 29

Housing m2 7816.39 3521.82 2613.34 3370.52 757.18

Incl. Brick-concrete m2 2314.39 747.18 605.9 646.5 40.6

2. Population &

Housing

Brick-timber m2 4542.3 2120.03 1179.92 1598.11 418.19

Fence m2 4202.3 850.3 1006.94(m) 1006.94(m)

Pressure well No. 46 32 33 1

Sparse tree No. 11060 126404 120628 121699 1071

Incl. Timber tree No. 10871 118745 112420 113072 652

Fruit tree No. 189 7394 8208 8627 419

Tomb No. 383 252 372 372

3. Ground

Attachment

Motor-pumped well No. 15 6 2 2

Road m/No. 2940/14 4150/18 462.15/2 462.15/2

Power line pole/No. 2030/7 87/11(Pole/line) 66(pole) 69(pole) 3(pole)

Telecom line pole/No. 3800/2 101/3(pole/line) 7(pole) 7(pole)

Canal m/No. 1950/4 2405/7

Bridge m/No. 731/6 1174.7/9 45/3 669/7 624/4

4. Special

Facility

GPS benchmark No. 1

Permanent Land U

se

5. Industry Enterprise No. 2 2 1 2 1

1. Range Affected village 11 11 14 14

Land occupation No. 2206.46 2206.46 987.4 1159.39 171.99

Incl. Irrigated land mu 881.46 2050.91 987.4 1159.39 171.99 Excavation &

occupation

Dryland mu 970.91 109.92

2. Land

Floodland mu 353.63 45.63

Temporary U

se

3. Appurtenance Sparse tree No. 6619 2645 2510 2613 103

Notes: The RP and IS figures are from the Special Report prepared by Yellow River Engineering Consulting

Co., Ltd., while the figures completed by the time of the 3rd and 4th M&E are from the External Monitor.

Page 114: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

103

1.3 Monitoring and Evaluation

1.3.1 Study Area and Focus

The study area mainly covers the Employer, Implementing Agency, and affected townships, villages and households. The M&E is focused on: recovery of family income, causes of and measures for compensation rates lower than those approved by the State, management of cost balance, training for production skills, and protection of vulnerable groups.

1.3.2 Methodology

Get familiar with the state, local and ADB’s resettlement laws/regulations and policies, the resettlement plan, the previous reports, and the TOR for this report; discuss with the local Yellow River Engineering Bureaus at all levels and the Implementing Agency, for them to have an understanding of the purpose, scope of work, and methodology of monitoring, and also the information and assistance expected of them; discuss with village/group leaders and villagers, explain to them the significance of M&E, complete forms, and collect necessary information; discuss with the responsible departments and persons of local governments and Yellow River Engineering Bureaus, feedback findings, and discuss relevant matters; process and analyze the findings from field work, and, on this basis, prepare the M&E report.

1.3.3 Schedule

The process of M&E started in September 2006, including field work, form completion, statistic analysis, report preparation, and data interpretation, etc.

2. DISBURSEMENT AND PAYMENT

2.1 Disbursement

2.1.1 Process of Disbursement

Land acquisition and resettlement funds are paid out of the financial revenues directly.

Process of application:

Mudan Project Office →Heze Yellow River Engineering Bureau → Shandong Yellow River Bureau →YRCC →Ministry of Water Resources → Ministry of Finance

Process of disbursement:

Ministry of Finance (special account of national treasure) →Heze Yellow River Engineering Bureau (zero-balance account) → Mudan Project Office

Permanent land use: Mudan Project Office →township→ village → group→ household, or Mudan Project Office →township→ village

Page 115: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

104

Temporary land use: Mudan Project Office→village →household

Housing and appurtenance: Mudan Project Office → township → village (household) → household

Special facility: Employer →contractor

2.1.2 Progress of Disbursement and Payment

Agreements for a sum of 26.7022 million RMB have been completed by and between the Employer and the Implementing Agencies, taking up 106.6% of the Approved Budget and 100% of the IS. This agreed amount is 638,900 RMB larger than that of the last report (26.0633 million RMB), mainly due to additional costs for young crops. The Employer has paid a total amount of 26.6998 million RMB to the Implementing Agencies.

As shown in Table 2-1, the Implementing Agencies have paid a sum of 20.5914 million RMB, including 13.0648 million RMB for permanent land use, 2.8 million RMB for temporary land use, 587,100 RMB for housing, 919,900 RMB for industries, 1.2531 million RMB for special facilities, and 1.9665 million RMB for appurtenances and others.

Refer to Table 2-1 for the progress of disbursement.

Following the last report, an amount of 2.8975 million RMB was disbursed during this 4th M&E period, 11.6% of the Approved Budget and 10.9% of the IS, including 118,500 RMB for permanent land use, 337,800 RMB for temporary land use, 5,900 RMB for housing, 494,000 RMB for industries, 1.1477 million RMB special facilities, and 793,600 RMB for appurtenances and others.

Table 2-1 Progress of Disbursement Unit: 104 RMB

No. Item Approved IS Agreed 3rd M&E 4th M&E Increase Remarks 1 Permanent land use 1337.21 1284.63 1306.48 11.85

2 Temporary land use 481.79 426.22 280.00 33.78 Agreed amount includes land restoration.

3 Housing 74.31 58.12 58.71 0.59

4 Industry 92.27 42.59 91.99 49.40 Incl. 182,700 RMB for a kiln due to design change.

5 Special facility 292.06 10.54 125.31 114.77

6 Appurtenance & others

2506 2670.89

392.58 117.29 196.65 79.36 Agreed amount includes 638,900 RMB additional costs for young crops.

Direct cost 2506 2670.89 2670.22 1769.39 2059.14 289.75 IS includes 8.2552 million RMB additional costs.

% of approved 106.6 70.6 82.2 Total

% of IS 100 66.2 77.1

Page 116: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

105

2.2 Comparison of Compensation Rates

In comparison with the last report, the compensation rates remain unchanged.

The current rate for permanent land use remains 2,000 RMB/mu, but 1,000 RMB/mu, 2,000 RMB/mu and 4,000 RMB/mu is separately added to the rates for nurseries, fishponds and lotus ponds.

As for temporary land use, the land for pumping is compensated according to the actual depth of excavation, 1,005 RMB/mu per meter, while that for occupation is compensated at the rate of 500 RMB/mu per season.

Different rates are used for housings and appurtenances according to their type of structure and duration of service life, with 180~260 RMB/m2 used for brick-concrete structures and 100~240 RMB/m2 for brick-timber ones. Generally, these rates are still lower than as fixed in the RP and IS. Brick and stone fences as part of appurtenances are compensated at 4 different rates, namely, 50 RMB/m, 60 RMB/m, 65 RMB/m and 70 RMB/m. Trees are compensated at the rates published by Mudan District Government, where the rates for initial-resulting, best-resulting and grape trees are lower than those set forth in the RP and IS.

2.3 Balance and Its Use

As of this report, a cumulative amount of 20.5814 million RMB has completed, taking up 77.1% of the total budget. The balance of 22.9% results from: (1) outstanding resettlement costs, (2) current compensation rates lower than approved ones, (3) resurveyed entitlements inconsistent with approved ones, and (4) failure to implement due to actual conditions. While making active efforts for payment, Mudan Project Office has prepared an action plan for the balance of 2.6925 million RMB, which is being submitted to higher levels.

The said action plan is mainly aimed at improving production/living conditions by dredging canals, warping low-lying lands, constructing village platforms and performing other public services. By the time of this M&E, these activities have been nearly completed by Mudan Project Office, which has enabled the farmers to cultivate a part of low-lying lands again. For example, 425 mu waterlogged land was warped in Liuzhuang during this M&E, which has restored the land that had been out of cultivation for years and satisfied the farmers. See Photographs 1 and 2.

Photograph 1: Warped Land in Liuzhuang (1) Photograph 2: Warped Land in Liuzhuang (2)

Page 117: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

106

3. LAND ACQUISITION AND ECONOMIC REHABILITATION

3.1 Permanent Land Acquisition and Economic Rehabilitation

Permanent land acquisition is increased by 1.08 mu in comparison with the progress achieved by the time of the last M&E, mainly due to the fact that the disputed area at the boundary of Chahetou was excluded from the last report. According to the IS, the subproject requires a total land area of 1,274.26 mu for permanent use. A total area of 1,228.99 mu (including 1,094.64 mu farmland) has been acquired from 12 villages in 3 townships as of this report, accounting for 96.4% of the IS. The additional area of 1.08 mu is owned by the village collective. Based on field surveys, the land loss per capita by villages is 0.07 mu, or 3.59%. Liuzhuang is the only village that has a loss rate over 10%, with a per capita loss of 0.25 mu, i.e. 22.44%. Details are provided in Table 3-1 below.

Table 3-1 Progress of Permanent Land Acquisition Original Permanent Land Use

Vulnerable Group Farmland Affected Vulnerable

Group Economic Rehabilitation

Mode No. Village Farmland Group Home People Home People

SubtotalArea Loss

Rate

Per Capita Loss

Group Home People Home People Option A

Option B Others

Unit Mu group group person home person mu mu % mu No. No. person home person group group group Column 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Total 30495 85 4100 1670

9 45 70 1228.991094.6

4 3.59 0.07 43 1985 8339 33 51 39 4 1 Huangzhuang 1400 9 305 1210 11.2 11.2 0.8 0.01 1 28 118 1 2 Chahetou 2600 6 310 1560 212.59 207.44 7.97 0.13 3 90 414 3

3 Liuzhuang 671 6 124 610 1 1 158.2 150.622.4

4 0.25 6 124 610 1 1 6 4 Youlou 1856 10 400 1620 28.8 25.3 1.36 0.02 4 141 555 4 5 Jiazhuang 6620 15 812 3036 7 8 201.4 171.3 2.59 0.06 15 812 3036 7 8 15 6 Lankoucun 1989 6 326 1580 145.2 91.2 4.59 0.06 2 115 530 2 7 Wulou 1800 8 360 1300 8 13 5.5 5.5 0.31 8 Xigaozhai 2492 4 245 958 9 18 159.7 151.9 6.1 0.16 4 245 958 9 18 4 9 Zhulou 2000 5 108 400 10.3 10.3 0.52 0.03 10 Wangshengtun 4200 4 320 1270 4 6 41.6 21.3 0.51 0.02 11 Donggaozhai 2167 4 290 1405 12 19 130.7 124.8 5.76 0.09 4 290 1405 12 19 4 12 Daliutun 2700 8 500 1760 4 5 123.8 123.8 4.59 0.07 4 140 713 4 5 4 Source: Townships, villages and groups; Column 9=column 8/column 1*100%; column 10=column 8/column 4.

Economic rehabilitation: The farmland in the project area is generally farmed and managed by groups, so adjustment and distribution by groups are carried out after land increase/ decrease, with a part reserved for public use in a few villages. As found in investigations, different modes of economic rehabilitation are selected by the groups in account of the actual circumstances. Among the 43 groups involved, with a total number of 1,985 households and 8,339 people, 39 with 1,867 households and 7,807 people have chosen Option A, while 4 with 118 households and 532 people choose Option B, taking up 93.6% and 6.4% of the affected population Either mode, the result of repeated deliberations and discussions, is preferred and backed by the majority.

Where Option A is chosen, the impacts are shared equally by all, which mitigates short-term

Page 118: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

107

impacts on land losers and allows more room for economic rehabilitation.

Where Option B is used, the compensations are directly paid to the households having lost their land, which enables them to have more money in hand and facilitates their development and adjustment of economic activities. In Chahetou with better economic conditions, all the 3 affected groups have adopted Option B. In 2006, for instance, the land losers adjusted their structure of cropping, increased the cropping area of water melon and other cash crops, and more people went out for business activities and farmer workers.

The acquired land in Zhulou and Wulou is less, all collective land, without impacts on the households. In Wangshengtun, the farmland of Group 1 is partly acquired, but land is given to the households directly by taking a part out of the reserved collective land. Some villages and groups have taken other measures.

3.2 Temporary Land Use and Restoration

According to the IS, the subproject necessitates the occupation of 2,206.46 mu for temporary use, including 1,845.11 mu for excavation and 361.35 mu treading, all irrigated field. The completed total area is 1,159.39 mu, 52.5% of the IS, involving 3 townships and 14 villages.

Temporary land occupation involves 2 forms of use: excavation and treading. The former is for edging and covering of warping works and the latter for pipes and construction roads.

(1) A total area of 569.89 mu is completed for pumping, taking up 30.9% of the IS. There are 2 types of borrow areas: fresh floodland, which is close to the river course and restored naturally when flooded, involving Houyoulou, Jiazhuang, Zhulou and Xigaozhai; and waste sand, which is on the landside and rather far from the dike, mostly collective idle non-farmland preferred to be used as borrow areas for pumping, involving only one natural village--Qianyoulou.

(2) The land for treading purposes is totally farmland, with a total area of 589.5 occupied by the time of this report, taking up 163% of the IS. Refer to Table 3-2 for details.

Table 3-2 Progress of Temporary Land Occupation Distance to Dike Restoration

To Be Restored Restored

Township Form of

Use Purpose Village Type of Land

Actual Area

Average Depth Waterside Landside

Not to Be

RestoredSubtotal

Area % Not

Restored

Remarks

Unit mu m m m mu mu mu % mu Total 1159.39 33.4 1125.99 862.21 77 263.78 Subtotal 569.89 33.4 536.49 272.71 51 263.78

Qianyoulou Waste sand 33.4 3.5 1500 33.4 Being warped

Houyoulou Fresh floodland 272.71 1 500 272.71 272.71 100

Jiazhuang Fresh floodland 121.3 6.2 2000 121.3 121.3 Zhulou Fresh floodland 140 6.5 3500 140 140

Pumping Edging & covering

Xigaozhai Fresh floodland 2.48 2.48 2.48

Yellow River water imported for warping

Subtotal Farmland 589.5 589.5 589.5

Access road Farmland 157.21 157.21 157.21 100 Work area & camp

Farmland 78.46 78.46 78.46 100

Waste canal Farmland 55.76 55.76 55.76 100

Licun

Treading

Pipe

14, including Zhulou, Lankou, Jiazhuang

Farmland 265.43 265.43 265.43 100

Naturally restored after construction

Page 119: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

108

Others Farmland 32.64 32.64 32.64 100

Source: Implementing Agencies (as of September 30, 2007).

Land restoration: It is necessary to restore 1,125.99 mu farmland in total, including 536.49 mu for pumping and 589.5 mu for treading as shown in Table 3-3.

The land for treading is generally used for 2-4 seasons. With main works completed, pipes and camps removed, land restoration is already finished.

The land for pumping is located on the waterside except in Qianyoulou, where such land is on the landside. Since the last M&E, land restoration has achieved to a varying extent. The land in Qianyoulou is waste sand, not needing restoration. However, restoration by warping is arranged by the village. Now, this work is coming to the end (see Photograph 3). In Zhulou, Jiazhuang and Xigaozhai, land restoration is in progress (see Photograph 4).

Photograph 3: Land Restoration in Qianyoulou Photograph 4: Land Restoration in Jiazhuang

4. RESTORATION OF HOUSIGN CONDITIONS

4.1 Physical Relocation

According to the IS, permanent land use necessitates the resettlement of 69 homes and 255 people in 6 villages and the relocation of 3,521.85 m2 housings. By the time of this report, the resurveyed housing area to be relocated is 3,756.49 m2, involving 33 households and 128 people in 6 villages, with an increase of 279.09 m2 (mostly temporary ones) as compared with the figure reflected in the last report.

Now 33 of the 33 households have been moved, with a total housing area of 33370.52 m2, i.e. 95.7% of the IS. The rest 3 households remain in the area for the use of service roads, not affecting the performance of construction. Refer to Table 4-1 for details.

4.2 Resettlement

Homestead identification: The total number of 33 households includes 8 whose properties are affected, not needing homesteads, and 25 having received homesteads, with an average

Page 120: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

109

surface area of 258 m2. Refer to Tables 4-2 and 4-3.

Housing: Among the 25 households having received homesteads, 13 have built new houses, 4 are building, and 8 are ready to act. The reasons for delayed housing include: (1) some house foundations are in water due to poor drainage, which frustrates house construction; and (2) some families live with their relatives, not needing new houses at this moment.

There are 4 more households having completed new houses and 3 less ready to act in comparison with the progress reflected in the last report. Refer to Table2 4-2 and 4-3.

Resettlement: Of the 30 households having been relocated, 13 live in new, 5 in borrowed and12 in other houses. Refer to Table 4-3.

Table 4-1 Progress of Physical Relocation and Resettlement 3rd M&E 4th M&E Item Household % Household %

To be relocated 33 33 Relocated 25 70 30 91 Relocation Remaining 8 24 3 9 New 8 32 13 43 Borrowed 7 28 5 17 Rent 1 4 Temporary 9 36 Others 12 40

Resettlement

Subtotal 25 30

Table 4-2 Progress of Homestead Identification and Housing 3rd M&E 4th M&E Item Household % Household %

Subtotal 25 76 25 76 Identified 25 76 25 76 Needed Remaining

Not needed 8 24 8 24

Homestead identification

Total 33 33 Ready to start 11 44 8 32 Under construction 5 20 4 16 Completed 9 36 13 52 Housing

Total 25 25

Table 4-3 Rehabilitation of Housing Conditions Household Homestead Identification Housing Resettlement

Needed No. Village To Be Relocated

Relocated Completed Remaining

Not Needed

Homestead Area Subtotal Built

Being Built

Not Started

Subtotal New Borrow Rent Others

Unit home home home home home mu home home home home home home home home homeColumn 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Total 33 30 25 8 258 25 13 4 8 30 13 5 12 1 Chahetou 5 5 1 4 233 1 1 5 1 4 2 Liuzhuang 2 2 1 1 267 1 1 2 1 1

Page 121: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

110

3 Lankou 16 16 16 265 16 9 4 3 16 9 3 4 4 Xigaozhai 6 6 3 3 249 3 2 1 6 2 1 3 5 Zhulou 3 1 3 220 3 3 1 1 6 Wangshengtun 1 1 300 1 1

Source: RP, IS and field surveys; Column 1=Column 3+Column 4+Column 5; Column3=Column 7; Column 2=Column 11

4.3 Development of Residential Sites

Infrastructures: Homesteads are identified by villages/groups for the 25 households to be resettled in 6 villages, and 13 households have moved to their new houses. Water supply is up to the resettlement families themselves. Now, each of those having completed new houses has a pressure well, which solves the problem of drinking water supply. Power lines are installed by users themselves. Refer to Table 4-4 for the progress of infrastructures at new sites.

Table 4-4 Development of Residential Sites Village Home People Progress Remarks Total 25 89

Chahetou 1 4 One family is to be resettled. The main house and a pressure well are completed, and power lines are installed.

Completed

Liuzhuang 1 6 One family is to be resettled. The main house and a pressure well are completed, and power lines are installed.

Completed

Lankou 16 52 Decentral resettlement within the village is planned. Nine houses are built, with a pressure well for each. Power lines are accessible to users. Housing is not yet started by some families due to poor drainage.

Underway

Xigaozhai 3 13 There are 3 resettlement families, including 2 having moved to new houses, with a pressure well for each. Power lines are installed. The rest one lives with the son, not needing a new house temporarily.

Underway

Zhulou 3 11 Decentral resettlement within the village. Land leveling is completed. Underway Wangshengtun 1 3 Decentral resettlement within the village. Land leveling is completed. Underway Note: Figures reflect the progress achieved by the time of this report.

5. REPLACEMENT OF SPECIAL FACILITIES

In the IS, land acquisition involves a total number of 11 power lines with 87 poles (10 kv), 3 communication lines with 101 poles, 3 transformers, and 9 bridges with 1,174.7 m2.

Since the last report, Heze Yellow River Industrial Co., Ltd. has completed 4 bridges and 2 roads, which greatly conveniences the affected villages (see Photographs 5 and 6). Table 5-1 details the progress of special facilities.

In addition, it is necessary to relocate 2 industrial enterprises, namely Chahetou Brick Factory and a business operated by Heze Yellow River Industrial Engineering Co., Ltd. The former is reconstructed, with production resumed, while the latter is compensated directly, with a new site selected for reconstructed by the enterprise.

Page 122: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

111

Photograph 5: New Access Road in Liuzhuang Photograph 6: New Access Bridge in Liuzhuang

Table 5-1 Progress of Special Facilities

6. INCOME RECOVERY

6.1 Selection and Follow-up Monitoring of Sample Households

As found in our follow-up monitoring of 19 households and 81 people in 2 of the 7 villages and 41 sample households for which baseline data have been established, Option A is chosen by 11 households and 42 people in Liuzhuang, whilst Option B is adopted by 8 households and 39 people in Chahetou.

According to the follow-up monitoring of the 19 sample households, they earned a per capita net income of 2,785 RMB in 2006, including 46%, 50% and 4% from agriculture, sideline and other sources respectively as shown in Tables 6-1 and 6-2.

Through further analysis, the overall per capita net income of Chahetou and Liuzhuang has already exceeded that of the base year. In Chahetou where Option B is chosen, the income is 1,552 RMB more than that of the base year, including 777 RMB from farming and 893 RMB from sideline activities. In Liuzhuang where Option A is adopted, the income is 1,340 RMB more, including 434 RMB and 799 RMB from farming and sideline activities respectively. Refer to Tables 6-3 and 6-4 for detailed information.

Power Communication Canal Bridge Asphalt Road Earth Road Village Stage

Line Length Pole Transformer Line Length Pole Qty Length Land Use Qty. Land

Use Qty Length Land Use Qty Length Land

Use Unit No. M pole No. No. m Pole No. m mu No. m2 No. m mu No. m mu

RP 7 2030 4 2 3800 4 1950 12 6 731 8 1730 26 6 1210 10.9

IS 11 87 3 3 101 7 2405 9 1174.

7 12 2940 26 6 1210 11.5Total

Completed 69 1 7 7 669 2 462.15

Chahetou Completed 14 1 214.8 Liuzhuang Completed 11 4 201 Youlou Completed Jiazhuang Completed 1 156

Lankou Completed 6 1 156 1 247.35

Xigaozhai Completed 23 1 Wangshengtun Completed 6 7 1 156 Donggaozhai Completed 9 Source: Implementing Agencies.

Page 123: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

112

Table 6-1 Per Capita Incomes of Sample Households Unit: RMB, %

Farming Sideline Animal Raising

Others*

SubtotalFarmer

Workers Village Year Home People Farmland(mu) Subtotal

Income %Income % Income %

Income % Income %

2004 (base year) 8 39 94.6 1423 974 69 262 18 72 27 5 182 13Chahetou

2006 (follow-up year) 8 39 86.3 2975 1751 59 1154 39 803 70 69 2 2004 (base year) 11 46 52.2 1268 423 33 827 65 801 97 18 1

Liuzhuang2006 (follow-up year) 11 42 46 2607 857 33 1626 62 1626 100 124 5 2004 (base year) 19 85 146.8 1339 676 51 568 42 466 82 2 93 7

Total 2006 (follow-up year) 19 81 132.3 2785 1288 46 1399 50 1230 88 98 4

Note:* Including fruit and others.

Table 6-2 Breakdown Incomes of Sample Households Sideline

No. Village Sample Code Year People Farmland(mu)

Total Net

Income (RMB)

Per Capita Income (RMB)

Farming Fruit Forestry

Animal Raising Total Farmer

WorkerOthers

2004 5 14 12656 2531 6074 1400 51821 MDQDFCHHT012006 5 13.94 20006 4001 6689 12960 4800 357 2004 6 13 5738 956 5569 169 2 MDQDFCHHT022006 6 12.5 18710 3118 10985 7200 7200 525 2004 3 7 4993 1664 3902 1000 1000 91 3 MDQDFCHHT032006 4 5.1 6238 1560 4952 1000 286 2004 5 13 5680 1136 5511 169 4 MDQDFCHHT042006 4 11.5 11387 2847 8892 2400 2400 95 2004 5 10 11902 2380 5798 6000 104 5 MDQDFCHHT052006 6 10 19377 3230 9797 9160 7000 420 2004 4 12.5 5650 1413 3687 1800 1800 163 6 MDQDFCHHT062006 4 9.6 15736 3934 7350 8100 8100 286 2004 5 9.4 4408 881 3325 1000 83 7 MDQDFCHHT072006 4 9.4 9934 2484 7840 1800 1800 294 2004 6 14.3 4467 744 4142 200 125 8

Chahetou

MDQDFCHHT082006 6 14.3 14619 2437 11791 2400 428 2004 39 94.6 55494 1423 38008 1000 200 10200 2800 6085 Subtotal 2006 39 86.34 116007 2975 68296 45020 31300 2691 2004 5 5 5257 1051 1992 3200 2000 65 9 MDQDFLZH02 2006 5 5 18201 3640 3944 13900 13900 357 2004 6 6 -37 -6 -115 78 10 MDQDFLZH03 2006 5 5.5 7414 1483 5088 2000 2000 326 2004 5 6 2109 421 2180 1 -150 -150 78 11 MDQDFLZH04 2006 5 6 11386 2277 3176 8000 8000 210 2004 6 7 3308 551 2217 1000 1000 91 12 MDQDFLZH05 2006 5 5 13108 2622 5551 7200 7200 357 2004 2 2 1185 592 859 326 13 MDQDFLZH06 2006 2 1.8 1434 717 650 784 2004 5 5.5 25938 5187 2366 -500 24000 24000 72 14 MDQDFLZH07 2006 5 5.4 24148 4830 5938 18000 18000 210 2004 2 2.2 3148 1574 1119 2000 2000 29 15 MDQDFLZH08 2006 2 2.2 293 147 167 126 2004 2 2.2 1589 794 1210 379 16

Liuzhuang

MDQDFLZH09 2006 2 2.2 1136 568 1049 87

Page 124: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

113

2004 5 5.5 6193 1238 3121 3000 3000 72 17 MDQDFLZH10 2006 5 5.5 8338 1668 3181 4800 4800 357 2004 2 3 1530 765 1491 39 18 MDQDFLZH11 2006 1 2.4 3355 3355 1299 2056 2004 6 7.8 8091 1348 2990 5000 5000 101 19 MDQDFLZH12 2006 5 5 20726 4145 5969 14400 14400 357 2004 46 52.2 58308 1268 19429 -500 38050 36850 1329 Subtotal 2006 42 46 109539 2608 36012 68300 68300 5226 2004 85 146.8 113802 1339 57437 501 200 48250 39650 7415 Total 2006 81 132.34 225546 2785 104308 113320 99600 7917

6.2 Recovery of Incomes

6.2.1 Recovery of Farming Incomes

The 19 sample households covered by this follow-up monitoring have a net farming income of 1,288 RMB per capita. Excluding the factor of escalation, the income in 2006 was 612 RMB more than that in the base year (2004), i.e. an increase of 91%. Table 6-3 indicates the fact that the farming incomes of affected people are recovered and even greatly increased after land acquisition. This is mainly attributable to the following reasons: (1) farmers begin to lay stress on the adjustment of cropping structures, with the cropping area of cash crops enlarged according to market demands and the structure of cropping activities adjusted on the basis of the market prices of produce, to gain more incomes; (in Chahetou and Liuzhuang, for instance, the enlarged cropping area of water melon in 2006 was an important cause of the considerably higher farming incomes); and (2) preferential policies provided by the State in the recent couple of years, especially the cancellation of agricultural taxes and the subsequent implementation of allowances for grain production, allow farmers to put more investment and enthusiasm in farming, with more stress placed on farming activities to cope with the changes subsequent to land loss.

Table 6-3 Income Recovery of Sample Households

Follow-up Year (2006) Base Year (2004) Difference Per Capita Net

Income Per Capita Net

Income Income Change

Sample Village With Land

Acquisition PeopleTotal Farming

Without Land

AcquisitionPeople

Total Farming Total FarmingUnit mu people RMB RMB RMB RMB RMB RMB RMB RMB

Chahetou 86.3 39 2975 1751 94.6 39 1423 974 1552 777 Liuzhuang 46 42 2608 858 52.2 46 1268 423 1340 435

Total 132.3 81 2785 1288 146.8 85 1339 676 1446 612

6.2.2 Sideline and Other Incomes

In 2006 the sample households had a per capita income up to 1,497 RMB from other sources than farming, 125.8% more than the figure of 834 RMB in the base year (2004), including 1,399 RMB from sidelines, mostly farmer workers who contributed 82.2% of the incomes from sideline and other sources. The ever-increasing income of farmer workers turns out to be the major source of incomes other than farming. Details are provided in Table 6-4.

Table 6-4 Changed Per Capita Incomes from Sideline and Other Sources Sample Follow-up Year (2006) Base Year (2004) Difference

Page 125: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

114

Sideline Sideline Sideline Animal Raising Subtotal Farmer

Worker Others Subtotal Animal

Raising Subtotal Farmer Worker

Others Subtotal Animal Raising Subtotal Farmer

Worker Others Subtotal

Chahetoou 1155 803 69 1224 5 262 72 182 449 -5 893 731 -113 775 Liuzhuang 1626 1626 124 1750 827 801 18 845 0 799 825 106 905

Total 1399 1230 98 1497 2 568 466 93 663 -2 831 764 5 834

6.2.3 Analysis of Income Recovery

Based on the quantitative analysis of income recovery, a survey was conducted as part of this M&E by interviewing with the sample households, to have a full picture of the income recovery subsequent to land loss. This can be described in the following aspects:

Impacts by farmland reduction: As indicated in Table 6-4, out of the total number of 19 households, 2 have less income from farming but more from other sources, without any impact on the total income, 12 are subject to minor impacts due to less land loss or poor land quality, and 5 are affected considerably, taking up 11%, 63% and 26% respectively.

Use of land compensations: As found in field surveys, 32% of the sample households use land compensations for direct income recovery, including 26% investing in farming and 6% going in for business, while the rest 68% use such for indirect income recovery measures including 42% paying medical fees and children’s tuitions among other daily living expenses, 21% choosing to build houses, and 5% repaying old debits. Refer to Table 6-5 for details.

Remedy measures: Out of the 19 sample households, 9 (47%) have recovered their incomes by farmer workers and business. Refer to Table 6-5.

Table 6-5 Analysis of Income Recovery

No. Item Household %

I Impact by farmland reduction 19

1 Less income from farming, but more from other sources, without any impact on total income 2 11

2 Minor impact due to less land loss 10 52 3 Minor impact due to poor land quality 2 11 4 Major impact 5 26 5 Others II Use of land compensations 19 1 Farming 5 26 2 Business 1 6 3 Housing 4 21 4 Medical fees, tuitions and other living expenses 8 42 5 Debit repayment 1 5 6 Others

III Remedy measures 19 1 Farmer worker 8 42 2 Business 1 5 3 Cropping, animal raising or plastic tunnel 4 Extensive farming and intercropping

Page 126: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

115

No. Item Household %

5 Reclamation or cultivating others’ land 6 Trust to luck 10 53 7 Others

6.3 Implication of Income Changes

According to China’s communiqué of national economic and social development in 2006, the absolute poverty line for rural areas was adjusted from 683 RMB in the previous year to 693 RMB, while the low-income level was changed from 944 to 958 RMB. Accordingly, rural residents with a per capita income less than 693 were classified as absolutely poor, those with 694-958 as low-income and those with more than 958 as non-poor people.

Among the 81 samples surveyed in 2006, 92.6% were above the line of non-poor people, 32.6% higher than the percentage in the base year, while the percentage of low-income and absolutely poor people was decreased by 2.5% and 4.9% accordingly. Refer to Table 6-6.

Table 6-6 Comparison of Poverty Populations Item 2004 2006 Increase/Decrease

People % People % People % Non-poor 51 60.0 75 92.6 24 32.6 Low-income 15 17.6 2 2.5 -13 -15.2 Absolutely poor 19 22.4 4 4.9 -15 -17.4

Total 85 100 81 100 4

7. PROTECTION OF RIGHTS AND INTERESTS

7.1 Training

As found in the investigation of training for production skills, agreements have been signed to this effect between the Employer and Licun Township Government, which is responsible for training the affected people in production skills. In August 2007, agricultural experts were invited to a workshop for some affected villages. According to our survey results, 7 of the 19 sample households participated in this workshop, taking up 36.8%. They were quite satisfied

Chart 1 Change of Poverty Populations

0

20

40

60

80

Non-poor People Absolute Poor People

2004 Base year

2006 Follow-up Year

Non-poor People

Page 127: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

116

with this workshop, considering it very helpful. Also, the rest 63.2% desired to receive such training. Refer to Table 7-1 for detailed information.

Table 7-1 Willingness to Be Trained

Subtotal Yes No No. Index

Yes No People % People %

I Have you been trained since 2004? 7 12 7 36.8 12 63.2

1 If yes, training in farming skills? 7 12 7

2 Training in policies and laws/regulations?

3 Any other training?

4 Do you wish to be trained? 12 12 5 If yes, scientific farming? 7 7 58 6 Animal raising? 2 2 15

7 Sideline? 3 3 25

8 Others?

7.2 Complaints Management

As known from investigations, channels are smooth and complaints are basically responded to. Most complaints arise out of the negative impacts on crops in the vicinity of dikes due to seepage and drainage in rainy days. It is expected that the relevant parties draw attention to the early prevention and management of this.

7.3 Vulnerable Groups

As investigated, vulnerable groups include 33 households with 51 people, taking up 0.6% of the affected total population. These people are properly resettled. As found in our interviews, Zhang Guanli and his wife, an old couple in Lankou, were provided preference in policies by Mudan Project Office in the course of resettlement. Now, they are satisfied with the living circumstances and housing conditions.

8. EVALUATION AND RECOMMENDATION

8.1 Evaluation

Permanent land acquisition is already finished, and resettlement is approaching to the end. Having chosen cash payment or land adjustment as the mode of economic rehabilitation, the affected farmers are taking active actions to adapt to and recover their production/livelihood by various means, including adjusting the structure of crops and increasing the work time of farmer workers.

As for temporary land use, the land for treading is restored as the main works are completed, whilst the land for pumping, as being mostly on the waterside, can be warped by diverting the

Page 128: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

117

Yellow River. At present, restoration of the remaining land is doing on, which will be focused in the next M&E. Generally, thanks to proper compensations, there is no major impact on the production of affected farmers.

The Implementing Agencies have built bridges and access roads, which greatly conveniences the production/livelihood of the local residents.

Land compensations in the later period of construction, mainly for temporary land use, are paid to the affected villages and households in time, without causing any major impacts on their production and livelihood.

Since the implementation, the affected farmers have taken various measures to recover their incomes, such as farmer workers and adjustment of cropping structures. These measures have enabled quick income recovery of the affected people.

8.2 Problems and Recommendations

8.2.1 Settlement of Earlier Problems

(1) Poor drainage during the performance of pumping works

Drainage is greatly reduced upon completion of the main works. Recently, Mudan Project Office has excavated canals in affected villages by using the balance of land compensations, which has solved the problem of drainage.

(2) Lower percentage of payment

At present, the percentage of payment is increased to a certain extent. In comparison with the progress made by the time of the last M&E, the payment is increased by 2.8975 million RMB, with a cumulative amount of 20.5914 million RMB, taking up 82.2% of the approved direct resettlement costs and 77.1% of the total direct resettlement costs.

8.2.2 Outstanding Problems

The Implementing Agency has not implemented the compensations for young crops approved by YRCC in Ref [2006]133. It is recommended that payment be made as early as possible.

Page 129: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Mudan Dike Subproject Resettlement M&E Report (Report No. 4)

118

ANNEX 8-1 INTERVIEW REGARDING INCOME RECOVERY

Time: September 15, 2007 Place: Group 1, Chahetou Village, Licun Township Interviewee: Li Hemin Position: None Sex: Male Age: 43 Education: High school

Interviewer: Hello, man, how many people are there in your family? How much land do you have? How much is used for the project? When?

Interviewee: There are 4 people and 9.6 mu land, on both sides of the dike. In April 2005, the land of our village was partly acquired for dike widening, including 0.8 mu of mine.

Interviewer: Was land adjustment arranged subsequently? If yes, when?

Interviewee: No. Our group specially met to discuss how to distribute land compensations. The majority requested to pay to land losers and cash payment was choose by the group, without land adjustment. Following this, the land to be acquired was surveyed by the village and group jointly with households.

Interviewer: How much have you received as land compensation? How many times has it been paid? What are the constituents? How have you used the money?

Interviewee: I received 8,400 RMB at two different times in May and June 2005 separately, and used it for building a new house.

Interviewer: As the farmland is reduced, what have you done to offset your income loss?

Interviewee: The output of crops is less due to farmland reduction, so we have to go out as farmer workers to offset the income loss. Now the children are grown up, they can go out to make money. I myself also go out to work in the slack season. Nowadays, farming alone is less profitable, so farmer workers are the major means of helping out the family expenses.

Interviewer: Do you think your family income is greatly affected by farmland reduction?

Interviewee: Since the land is of inferior quality, my family income is not affected greatly. Yet many trees have been inundated due to serious seepage through the widened dike and subsequent poor drainage.

Interviewer: Are you satisfied with the existing production/living conditions? What’s your plan for the future?

Interviewee: Yes, I’m satisfied. Now the access road is paved with cement, which conveniences our farming and harvesting. I’m thinking about making some money from animal raising activities.

Interviewer: Thank you and wish you a better life.

Page 130: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

118

Appendix 4

ADB-loaned Yellow River Flood Management Sector Project

Juancheng Dike Consolidation

RESETTLEMENT M&E REPORT (Report No. 3)

Henan Huanghe Resettlement Economic Development Company

December 2007

Page 131: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

119

Approved: Yang Jianshe

Reviewed: Zhang Hao, Zuo Ping

Task Manager: Zuo Ping

Team Leader: Chang Quanli

Chief Editor: Sun Fengzhi

Proofreader: Jiao Lili, Zhao Huan’e, Wang Jianzhong, Yang Tao

Contributors: Chang Quanli, Duan Yongfeng, Jiao Lili, Li Yang, Shen Yanlong,

Sun Fengzhi, Wang Jianzhong, Xue Changyu, Yang Jianshe, Yang

Tao, Zhao Hao, Duan Wei, Zuo Ping, Zhao Huan’e

Page 132: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

120

Table of Contents

1. INTRODUCTION ____________________________________________________________ 121

1.1 Subproject Brief ________________________________________________121

1.2 Land Acquisition and Resettlement ________________________________122

1.3 Monitoring and Evaluation _______________________________________123 1.3.1 Study Area and Focus ______________________________________123 1.3.2 Methodology______________________________________________123 1.3.3 Schedule _________________________________________________123

2. DISBURSEMENT AND PAYMENT _____________________________________________ 123

2.1 Process of Disbursement and Payment ______________________________123

2.2 Progress of Disbursement_________________________________________124

2.3 Compensation Rates and Payment _________________________________124

3. LAND OCCUPATION AND ECONOMIC REHABILITATION______________________ 126

3.1 Permanent Land Acquisition ______________________________________126

3.2 Temporary Land Occupation _____________________________________127

4. RESTORATION OF HOUSING CONDITIONS ___________________________________ 128

4.1 Physical Relocation and Resettlement ______________________________128

4.2 Development of Residential Sites___________________________________129

5. REPLCAEMENT OF SPEICAL FACILITIES ____________________________________ 130

6. INCOME RECOVERY________________________________________________________ 130

6.1 Follow-up Monitoring of Sample Households ________________________130

6.2 Recovery of Incomes_____________________________________________131 6.2.1 Farming Incomes__________________________________________131 6.2.2 Sideline and Other Incomes _________________________________132

6.3 Implication of Income Changes ____________________________________133

6.4 Evaluation _____________________________________________________133

7. PROTECTION OF RIGHTS AND INTERESTS___________________________________ 134

7.1 Training _______________________________________________________134

7.2 Complaints Management _________________________________________134

7.3 Vulnerable Groups ______________________________________________134

8. EVALUATION AND RECOMMENDATION _____________________________________ 135

8.1 Evaluation _____________________________________________________135

8.2 Problems and Recommendations __________________________________135

Page 133: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

121

1. INTRODUCTION

This subproject was formally implemented in September 2005. As the farming income of the resettlement families was not affected by land acquisition that year, the M&E team conducted a baseline census and the 1st M&E in June 2006, established baseline data for 4 sample villages and 28 sample households, and prepared a baseline census report and M&E report 1. Up to now, 3 M&E reports have been prepared in both Chinese and English, including this report which documents the 3rd M&E.

1.1 Subproject Brief

Juancheng Yellow River Dike in Shandong is on the right bank. The dike section 257+200~ 259+500 under the ADB-loaned Yellow River Flood Management Sector Project is designed to be consolidated by landside warping. The “Preliminary Design of Land Acquisition and Resettlement of Juancheng Dike Consolidation Subproject” (257+200~259+500) (referred to as “Resettlement Plan” or “RP” hereinafter) was prepared by the Yellow River Engineering Consulting Co. Ltd. in September 2003 and formally approved by the National Development & Reform Commission in October 2004, with a certified resettlement budget of 11.4 million RMB (referred to as the “Approved Budget” hereinafter), including 10.47 million RMB as direct costs. Subsequently an “Implementation Scheme of Land Acquisition and Resettlement under Juancheng Dike Consolidation Subproject” (referred to as the “Implementation Scheme” or “IS” hereinafter) was completed by the Yellow River Engineering Consulting Co. Ltd. as required by the ADB in May 2005, and reviewed and approved by Shandong Yellow River Engineering Bureau via letter [2005]42 on July 1st 2005, with a resettlement budget of 11.75 million RMB (350,000 RMB more than the Approved Budget, totally direct costs), including 10.82 million RMB direct costs. On December 13, 2006, an additional amount of 2.7901 million RMB was approved by the Yellow River Conservancy Commission in letter No.[2006]133 “Approval of Additional Land Compensation Costs for Shandong ADB-loaned Project”, including 213,700 RMB for direct costs (for young crops) and 2.5764 million RMB for land restoration and miscellaneous costs. In furtherance, a variation was approved in letter No. [2007]67 during implementation, with an additional amount of 933,100 RMB direct costs. Therefore, the total resettlement budget is 15.4732 million RMB, including 11.9668 million direct costs. Refer to Table 1 for details.

Table 1 Comparison of Approved Resettlement Costs Unit: 104 RMB

No. Item Approved Additional IS Remarks

1 Rural resettlement 1034 125.68 1159.68Incl. land restoration

2 Special facility replacement 13 24 37

Subtotal Direct cost 1047 149.68 1196.68

3 Miscellaneous 93 257.64 350.64

Total 1140 407.32 1547.32

Page 134: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

122

1.2 Land Acquisition and Resettlement

The resettlement organization framework includes: Heze Yellow River Engineering Bureau as the Employer, Yellow River Engineering Co., Ltd. as the Designer, Juancheng County Government as the Implementing Agency, and Henan Huanghe Resettlement Economic Development Company as the External Monitor.

As required, Heze Yellow River Engineering Bureau has established a Project Office to perform the responsibilities and obligations on behalf of the Employer. Juancheng County Government has set up a Leading Group, which includes a Resettlement Office in charge of land compensation, resettlement, infrastructure, and field coordination.

The quantities of work completed by the time of this M&E include: acquisition of 395.76 mu for permanent use (100.9% of the IS), involving 1 township and 4 villages; relocation of 93 households and 9,448.77 m2 housings (12 households and 197.96 m2 more than the figures of the last report, 78.8% of the IS); clearing 6,000 sparse trees (2,000 more, 67.9%), 176 tombs (56 more, 95.7%) and 4 motor wells (1 more, 100%); and acquisition of 350.49 mu for temporary use (including 58.62 mu for occupation and 291.87 mu for excavation, 44.2%). Now construction is totally completed.

Table 2 compares the main physical indexes.

Table 2 Comparison of Main Physical Indexes

Item Unit RP IS 2nd M&E 3rd M&E Increase Remarks

Village involved No. 5 5 4 4

Land acquired mu 392.22 392.22 395.76 395.76

Incl. Cropland mu 235.56 313.29 293.75 Data from village

Forestland mu 94.79 7

Pond mu 7.73 7.73

1. Land

Non-productive land mu 54.14 64.2

102.01 395.76

Affected village No. 4 4 4 4

Number of household No. 109 108 81 93 12

Number of people person 454 452 326 388 62

Housing m2 11689.9 11989.9 9250.81 9448.77 197.96 Relocated

Incl. brick-concrete m2 754.5 754.5 9250.81 539.2

Brick-timber m2 9277.7 9577.7 8909.57

2. Population &

housing

Fence m2 4989.4 1989.4 2033.8 3078.3 1044.5

Pressure well No. 96 110 49 94 45

Sparse tree No. 5667 8840 4000 6000 2000

Tomb 97 184 120 176 56 3. Appurtenance

Motor-pump well 4 4 3 4 1

Canal m/No. 150/1 150/1 150/1 150/1

Road m/No. 920/5 920/5 920/5 920/5

1..Permanent

land use

4. Special

facility Telecom line m/No. 2450∕1 2450∕1 2450∕1 2450/1

2.Temporary 1. Range Affected village No. 9 9 9 9

Page 135: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

123

Area mu 793.44 793.47 281 350.49 69.49 58.62 mu for occupation, 291.782 mu for excavation

Incl. Irrigated field mu 789.34 793.47 281 350.49 69.49 2. Land

Floodland mu 4.1

land use

3. Appurtenance Sparse tree No. 2380 2367

Note: The figures in “RP” and “IS” columns are from the “Resettlement Plan” and “Implementation Scheme” prepared by the Yellow River Engineering Consulting Co., Ltd. in September 2003 and May 2005 respectively, while those in “3rd M&E” are from field surveys during the 3rd M&E period.

1.3 Monitoring and Evaluation

1.3.1 Study Area and Focus

The study area of this M&S mainly covers the Employer, Implementing Agency, and relevant townships, villages and households, with focus placed on: disbursement, payment, townships, villages, groups and households involved in permanent/temporary land use, including the percentage of lost land, economic rehabilitation measures, temporary land occupation and restoration, housing restoration, residential site development, and income recovery, etc.

1.3.2 Methodology

Get familiar with the state, local and ADB’s resettlement laws/regulations and policies, the Resettlement Plan, the previous reports, and the TOR for this report; discuss with the local Yellow River Engineering Bureaus at all levels and the Implementing Agency, for them to have an understanding of the purpose, scope of work, and methodology of monitoring, and also the information and assistance expected of them; discuss with village/group leaders and villagers, explain the significance of M&E, complete forms, and collect information as necessary; feedback findings, and discuss relevant matters; process and analyze the findings from field work, and, on this basis, finally complete the M&E report.

1.3.3 Schedule

The schedule of M&E is as follows: conduct field work in September 2007 and complete report preparation and data interpretation by in October 2007, with the final draft submitted.

2. DISBURSEMENT AND PAYMENT

2.1 Process of Disbursement and Payment

Resettlement costs for the subproject are paid out of the state financial revenues directly.

The process of application for resettlement costs is as follows:

Resettlement Office →Heze Yellow River Engineering Bureau (Employer)→ Shandong Yellow River Engineering Bureau →Yellow River Conservancy Commission → Ministry of Water Resources →Ministry of Finance

Resettlement costs are disbursed in the following process:

Ministry of Finance (special account of state treasury) →Heze Yellow River Engineering Bureau (small account) → Resettlement Office, including

Page 136: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

124

(1) Permanent land use: Resettlement Office→ Land Bureau → village→ group→ household

(2) Temporary land use: Resettlement Office→ village→household (3) Housing and attachment: Resettlement Office→village (household)→ household

2.2 Progress of Disbursement

As of this report, the Resettlement Office has disbursed a total amount of 607.39 million RMB, accounting for 58% of the Approved Budget, 50.8% of the IS and 51.7% of the agreed amount, 762,500 RMB more than the sum reflected in the last report. In specific, this amount includes: 2.8498 million RMB settled for permanent land use, 531,500 RMB paid for temporary land use, 1.2005 million RMB settled for housing, 39,300 RMB paid for replacing special facilities, and 1.4528 million RMB paid for clearing sparse trees, tombs and other appurtenances, taking up 76.2%, 31.6%, 47.3%, 10.8% and 42.4% of the agreed amounts respectively. Table 3 shows a summary of resettlement costs.

There remains a balance of 5.6734 million RMB. As an action plan in under preparation, the next M&E will consider this as a key point.

The low percentage of payment is mainly related to low compensation rates. The cumulative amounts are included herein as completed actually.

Table 3 Summary of Resettlement Costs Unit: 104 RMB, %

No. Item Approved Total Agreed 1st M&E Increase

1 Permanent land use 373.78 308.69* 284.98 -23.71 2 Temporary land use 168.01 21.07 53.15 32.08 3 Housing 253.87 132.57* 120.05 -12.52 4 School 5 Special facility 36.51 3.93 3.93 6 Appurtenance & others

1047 1196.68

342.56 64.88 145.28 80.4 Amount 1047 1196.68 1174.73 531.14 607.39 76.25 % of RP 58.0 58 % of IS 50.8 50.8

Total

% of agreed 51.7 51.7

*1. There were mathematical errors in the cumulative figures of permanent land use and housing from the relevant parties last time; 2.The cumulative figures in the column of “3rd M&E” are completed actually.

2.3 Compensation Rates and Payment

Juancheng dike consolidation comprises 11 components and 13 lots, involving 20 villages in 5 townships, with large quantities of resettlement work. However, only 1 lot is included in the Yellow River Flood Management Sector Project, involving 4 villages in a single township. Considering the fact that the compensation rates previously applied to local-fund components are lower than those approved for the ADB-loaned subproject, the Resettlement Office has published the “Compensation Scheme”, which is current now.

Although some items and metric units do not correspond to each other, but the rates provided in the “Compensation Scheme” are obviously lower.

Page 137: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

125

In practice, the rate of 7,200 RMB/mu is applied to permanent land acquisition, plus 600 RMB/mu for young crops for a year (360 RMB/mu for summer and 240 RMB/mu for autumn crops), and 2,300 RMB to permanent land use (including restoration). Other rates are used as fixed in the “Compensation Scheme”. Refer to Table 4 below.

Now compensations for houses and appurtenances are paid, as advance payment, against the verified quantities and the rates shown in the “Compensation Scheme”.

Table 4 Comparison of Main Compensation Rates No. Item Unit Approved Compensation Scheme Implemented Remarks

I Permanent land use RMB/mu Irrigated field RMB/mu 11320 Standard fishpond RMB/mu 14500 Medium-yield fishpond RMB/mu 13300 Low-yield fishpond RMB/mu 12100 Lotus pond RMB/mu Nursery RMB/mu 11320

Cropland: 7200 RMB Forestland: 5850 RMB

Cropland: 7200 RMB, plus 600 RMB/a (360 RMB for summer + 240 RMB for autumn crops) as young crop compensation for 1 year; Forestland: 5850 RMB

II Temporary land use RMB/mu Young crops Irrigated 2264

1698 Summer crop: 360 RMB Autumn crop: 240 RMB

Dryland 1005 (I) Treading

Floodland 690 350 RMB/a

As fixed in Compensation Scheme

Irrigated 2264

1698 600 RMB/a, plus 2 RMB per cubic meter of soil

2300 RMB/mu (including land restoration)

Dryland 1005

(II)

Excavation

Floodland 690 350 RMB/a

III Housing RMB/m2 Brick-concrete RMB/m2 260 220 Brick-timber RMB/m2 220 160 Service RMB/m2 163 Brick-earth-timber RMB/m2 215 120 Earth-timber RMB/m2 201 80 Simple RMB/m2 50 50

IV Accessories Brick-stone fence RMB/m2 25 Brick-earth fence RMB/m2 15 Earth fence RMB/m2 9

30 RMB/m

Gate arch RMB/m2 145 Pressure well RMB/each 150 Small well RMB/each 300 80 Motor-pump well RMB/each 5000 150 RMB/m Plastic tunnel RMB/m2 50 Greenhouse RMB/m2

Plastic tunnel: 10 RMB/m2

V Sparse tree <5cm RMB/each 5 2 5-10cm RMB/each 20 20 10-20cm RMB/each 30 30 >20cm RMB/each 45 30

VI Tomb Single coffin RMB/each 204 Double coffin RMB/each 254

120 VII Special facility

Asphalt road RMB/m2 30 Power/communication line RMB/pole 1000 Arch bridge RMB/m2 700

As fixed in Compensation Scheme

Page 138: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

126

3. LAND OCCUPATION AND ECONOMIC REHABILITATION

3.1 Permanent Land Acquisition

As understood in field investigations, permanent land acquisition is finished, with 395.76 mu acquired (including 293.75 mu farmland), the same as reported last time, taking up 100.9% of the IS and involving 13 groups in 4 villages.

These 13 groups have lost 15.5% of their farmland on the average, or 0.2 mu per capita.

(1) Farmland reduction over 10%: involving 3 villages, 8 groups, 224 households and 932 people, i.e. 63% of the affected people, with a per capita loss of 0.27 mu or an average loss rate 25%;

(2) Farmland reduction of 5~10%: involving 1 village, 3 groups, 55 households and 240 people, taking up 16% of the affected people, with a per capita loss of 0.14 mu or an average loss rate of 7.5%;

(3) Farmland reduction below 5%: involving 1 village, 2 groups, 73 households and 304 people, taking up 21% of the affected people, with a per capita loss of 0.03 mu or an average loss rate of 2.4%. Refer to Tables 5 and 6 for details.

Table 5 Summary of Affected Villager Groups

Existing Affected Economic Rehabilitation

Vulnerable Groups

Vulnerable Groups Area Item

Farmland Group Home People Home People

Group Home PeopleHome People Subtotal Farmland Loss

Rate Per

Capita

Option A

Option B

Unit mu mu home person home person group home person home person mu mu % mu group mu Qty 989 8 224 932 6 8 8 224 932 6 8 286 247.4 25 0.27 8 Loss rate

>10% %% 52 62 63 63 50 53 62 64 63 50 53 75 84 66 Qty 483 3 57 253 3 55 240 76.77 36.4 7.5 0.14 2 1 Loss Rate

5~10% % 26 23 16 17 23 15 16 20 12 17 100 Qty 424 2 73 304 6 7 2 73 304 6 7 17.22 10 2.4 0.03 2 Loss rate

<5% % 22 15 21 20 50 47 15 21 21 50 47 5 4 17 Total 1896 13 354 1489 12 15 13 352 1476 12 15 380 293.8 15.5 0.2 12 1

Source: Townships, villages and groups in relevance.

Table 6 Statistical Data on Permanent Land Use Existing Permanent Land Use

Economic RehabilitationVillage Group

Farmland Home People Vulnerable

Groups Home People

Vulnerable Groups Subtotal Farmland

Loss Rate

Per Capita Loss

Option A

Option B

Others

Unit group mu home person home person home person home people mu mu % mu group group group

Dalizhuang 8 840 210 825 5 8 109 459 2 3 102.36 97.83 11.65 0.12 Group 4 330 109 459 2 3 109 459 2 3 102.36 97.83 29.65 0.21 4

Wanglou 5 697 87 379 85 366 158.95 91.66 13.15 0.25

Group 5 697 87 379 85 366 158.95 91.66 13.15 0.24 4 1 Wangqiao 4 869 158 651 10 12 158 651 10 12 118.7 104.26 12 0.16

Group 4 869 158 651 10 12 158 651 10 12 118.7 104.26 12 0.16 4

Dongzhuang 4 523 135 495 7 9 15.75 Collective non-productiveTotal group 13 1896 354 1489 12 15 352 1476 12 15 380.01 293.75 15.49 0.199 12 1 Total village 21 2929 590 2350 22 29 352 1476 12 15 395.76 293.75 10.02 0.125 12 1

Page 139: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

127

Economic rehabilitation for permanent land acquisition: The increased/decreased farmland is readjusted and redistributed by groups after land acquisition.

The mode of money-based economic rehabilitation is used for the project area. After having received land compensations, the affected villages or groups determine how to use the money in the light of their actual conditions and on the basis of adequate public consultation. To sum up, there are 2 different scenarios as follows:

(1) Land contracted to individuals: There are 2 modes of economic rehabilitation: share the money with all in the same group, with land adjustment, and pay to households directly, without land adjustment (referred to as “Option A” and “Operation B”). Among the 13 affected groups with 352 households and 1,476 people, only 65 people in 1 groups select Option B, accounting for 4.4%, while the rest 1,411 people adopt Option A, i.e. 95.6%. To put in another way, 600 RMB (young crop compensation for 1 year) of the land compensations (7,800 RMB/mu) received is paid to the households directly, with the remaining 7,200 RMB shared by all and land adjusted by the group.

(2) Land reserved for public use: A total area of 102.01 mu in this type is acquired for permanent use, including forestland, pond and non-productive land, and compensations are paid in full. Through public consultation, the compensations for non-productive land are to be retained by the village/group for common use, mainly for the construction of new residential sites, and those for forestlands and ponds are paid to households directly and equally according to the number of people, and used for economic activities.

Land loss implies more time for the affected people to work outside as farmer workers and go in for transportation, small business and other sideline activities, which partly offsets their loss of income.

3.2 Temporary Land Occupation

According to the IS, temporary land uses include borrow areas, access roads, temporary dwellings, warehouses and pipes, 793.47 mu in total, all irrigated fields, including 586.98 mu for excavation and 206.49 mu for treading. Now 350.492 mu is occupied. The land for pipe installation is 58.62 mu, involving 8 villages, and that for excavation is 291.872 mu, involving 3 villages.

Land restoration: Pipes are generally arranged in line with roads or fields, with less use of farmland. Further to this, such land can be cultivated as soon as warping works are completed, so major impacts on farming will not be caused. Excavation involves 69.356 mu in Wangqiao, 98.766 mu in Dalizhuang and 123.75 mu in Laozhaizhuang of Jiucheng Township, with an average excavation depth about 1 m.

By the time of this M&E, the land for pipe installation has been totally restored. This is also the case of 291.872 mu for excavation purposes. Refer to Table 7 and Photographs 1 and 2.

Page 140: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

128

Table 7 Progress of Temporary Land Occupation and Restoration Restoration

Restored Purpose Township Village Area Average Depth

Rate Amount Area %

Not Restored

Remarks

Unit mu m RMB mu % mu Total

350.49 531552.20 350.49 100

Subtotal 58.62 54657.00 58.62 100 Jiucheng Jiazhuang 6.660 600RMB/mu/crop 7992.00 6.660 100 2 crops (wheat & autumn crop 06)Jiucheng Anzhuang 18.675 600RMB/mu/season 22410.00 18.675 100 2 crops (wheat & autumn crop 06)Jiucheng Kuigu 4.800 600RMB/mu/season 5760.00 4.800 100 2 crops (wheat & autumn crop 06)Jiucheng Wanglou 1.860 600RMB/mu/season 2232.00 1.860 100 2 crops (wheat & autumn crop 06)Jiucheng Anzhuang 18.675 300RMB/mu/half season 6723.00 18.675 100 Half season (autumn crop 06) Jiucheng Luzhuang 1.068 600RMB/mu/season 1281.60 1.068 100 2 crops (wheat & autumn crop 06)Jiucheng Gezhuang 1.134 600RMB/mu/season 1360.80 1.134 100 2 crops (wheat & autumn crop 06)

Occupation

Jiucheng Kangzhuang 5.748 600RMB/mu/season 6897.60 5.748 100 2 crops (wheat & autumn crop 06)Subtotal 291.87 476895.20 291.87 100 Jiucheng Wangqiao 39.400 1.0 1600 RMB/mu 63040.00 39.400 100 Jiucheng Dalizhuang 98.766 1.0 1600 RMB/mu 158025.60 98.766 100 Jiucheng Wangqiao 29.956 1.0 1600 RMB/mu 47929.60 29.956 100

Excavation

Jiucheng Laozhaizhuang 123.750 1.0 1600 RMB/mu 207900.00 123.750 100

Photograph 1: Restored Borrow Area in Wangqiao Photograph 2: Restored Borrow Area in Dalizhuang

4. RESTORATION OF HOUSING CONDITIONS

4.1 Physical Relocation and Resettlement

According to the IS, it is necessary to resettle 108 households and 452 people from 4 villages, and relocate 11,989.9 m2 housings. As verified by the end of this report, it needs to resettle 101 households.

Physical relocation: By the time of this report, 93 households have been relocated, with a floor area of 9,448.775 m2, 12 households more than reported last time, accounting for 92% of the total number. The rest 8 have not been moved because their land for the use of service roads does not affect the performance of construction at this moment. These 91 families having received homesteads have started housing except for one, with 64 houses built (9 more than reported last time) and 26 being built. Refer to Tables 8 and 9.

Identification of homesteads: The 101 households include 91 in the need of homesteads. As shown in Tables 9 and 10, this part of work is finished. The total number of 93 relocated families includes 64 having moved to new houses, 9 more than reported last time, 26 dwelled by relatives or governments, and 3 having other dwellings. Refer to Tables 8 and 10.

Page 141: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

129

Table 8 Comparison of Physical Relocation and Resettlement

2nd M&E 3rd M&E Item

Household % Household % To be relocated 101 100 101 100 Completed 81 80.2 93 92 Relocation Remaining 20 19.8 8 8 New 52 64.2 64 68.82 Borrowed 17 21.0 26 27.95 Temporary 1 1.2 Others 11 13.6 3 3.23

Resettlement

Subtotal 81 100 93 100

Table 9 Progress of Homestead Identification and Housing

1st M&E 2nd M&E Item

Household % Household % Subtotal 92 91.1 91 100 Completed 65 64.4 91 90 Needed Remaining 27 26.7

Not needed 9 8.9 10 10

Homestead identification

Total 101 100 101 100 Not started 6 9.2 1 1.10 Being built 4 6.2 26 28.57 Built 55 84.6 64 70.33

Housing

Total 65 100 91 100

Table 10 Progress of Physical Relocation and Resettlement

Involved Homestead Identification Housing Resettlement Household Needed

To Be Relocated Completed People Area

Completed Remaining Not

NeededSubtotal Built

Being Built

Not Started

Subtotal New Borrow Others No Village

home home person m2/home home home home home home home home home home home home Total 101 93 400 279 91 10 91 64 26 1 93 64 26 3

1 Dalizhuang 6 5 27 240 6 6 5 1 5 5 2 Wanglou 61 56 231 286 53 8 53 53 56 53 3 (other dwellings) 3 Wangqiao 11 11 54 246 11 11 11 11 11 4 Dongzhuang 23 21 88 240 21 2 21 21 21 21

4.2 Development of Residential Sites

Construction of infrastructures: As of this report, all the 53 households in Wanglou where the mode of central resettlement is chosen have moved to a new site, with 3 main and 5 branch streets, a pressure well for each family, and power lines available to users. In Wangqiao where decentral resettlement is adopted, 11 houses are totally completed, with a pressure well and power lines for each family. In Dalizhuang and Dongzhuang, homestead identification is finished, and the development of residential sites is in progress. Table 11 shows the progress of infrastructures in new residential sites.

Page 142: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

130

Table 11 Progress of Residential Sites

Resettlement Village

Home People Residential Site Development Remarks

Total 91 380

Dalizhuang 6 27 New homesteads are provided. In progress

Wanglou 53 215

The mode of central resettlement is adopted, with some 33 mu

land acquired. All the 53 houses are completed, with a pressure

well for each. Power lines are available to all. There are 3

asphalt main streets and 5 macadam branch ones. Drainage

ditches are excavated.

All moved to new

houses

Wangqiao 11 54

Decentral resettlement is used, with some 8 mu acquired. All the

11 houses are completed, with a pressure well for each. Power

lines are available for all.

All moved to new

houses

Dongzhuang 21 83 New homesteads are provided. In progress

Note: Figures reflect the progress achieved by the time of this M&E.

5. REPLCAEMENT OF SPEICAL FACILITIES

The special facilities affected by the subproject include 5 roads with a length of 920 m (all earth roads), 1 telecommunication line with a length of 2,450 m, a canal with a length of 150 m, and an access bridge in Dongzhuang.

These have been completed except for the access bridge under construction in Dongzhuang.

6. INCOME RECOVERY

6.1 Follow-up Monitoring of Sample Households

According to the impacts by the subproject, all the 28 sample households in 3 sample villages are covered by the follow-up monitoring. As indicated by the findings, there was a per capita net income of 2,359 RMB in 2006, 252 RMB more than that in the previous year. Wanglou had the highest, 2,858 RMB per capita, while the other 2 villages had 2,299 and 1,830 RMB respectively. Follow-up monitoring results are provided in Tables 12 through 14.

Regarding the constituents, family incomes include 72% from sideline, the largest contributor, 25.6% from farming, the second contributor, and 2.4% from animal raising and other sources.

With regard to the change of incomes, there is an increase except in Wangqiao where there is a decrease (due to flooding in 2006). Particularly, the per capita income is increased by 766 RMB in Wangqiao.

Table 12 Per Capita Incomes of Sample Households (2006) Farming Animal Raising Sideline Others Village Home People Subtotal

Income % Income % Income % Income % Dalizhuang 11 51 2299 478 20.8 1804 78.5 17 0.7 Wanglou 9 39 2858 931 32.6 38 1.3 1782 62.4 107 3.7 Wangqiao 8 31 1830 402 22.0 1416 77.4 12 0.7 Total 28 121 2359 604 25.6 12 0.5 1698 72.0 45 1.9

Page 143: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

131

Table 13 Change of Per Capita Incomes Unit: RMB/person

Sample Village Per Capita Net Income in Follow-up Year

Per Capita Net Income in Bear Year Change

Dalizhuang 2299 2035 264 Wanglou 2858 2092 766 Wangqiao 1830 2235 -405 Total 2359 2107 252

Table 14 Breakdown Incomes of Sample Households (2006) Farmland (mu) Constituent

No. Village Sample Code People WithoutProject

With Project

Total Net Income (RMB)

Net Per Capita Income (RMB)

Farming Animal Raising Sideline Others

1 JCHDFJCHZHDLZH01 6 4 3.8 25576 4262 1464 24000 112 2 JCHDFJCHZHDLZH02 3 3 2.1 1103 367 1044 59 3 JCHDFJCHZHDLZH03 2 3.6 1.7 12906 6453 858 12000 48 4 JCHDFJCHZHDLZH04 5 5 5 7555 1511 2415 5000 140 5 JCHDFJCHZHDLZH05 4 3.6 2.8 10240 2560 1661 8500 78 6 JCHDFJCHZHDLZH06 9 9 7.2 23604 2622 5528 18000 76 7 JCHDFJCHZHDLZH07 6 6 5.2 9182 1530 3536 5500 146 8 JCHDFJCHZHDLZH08 5 6 4.2 8811 1762 2693 6000 118 9 JCHDFJCHZHDLZH09 3 2.4 2.1 3624 1208 1566 2000 59

10 JCHDFJCHZHDLZH10 5 4.8 4 11068 2213 2026 9000 42 11

Dalizhuang

JCHDFJCHZHDLZH11 3 2.7 2.1 3591 1197 1591 2000 0 Subtotal 51 50.1 40.2 117260 2299 24383 92000 876

12 JCHDFJCHZHWL01 4 5.1 4.8 8395 2098 2783 5500 112 13 JCHDFJCHZHWL02 3 5.1 4.8 4206 1402 2622 1500 84 14 JCHDFJCHZHWL03 4 6.8 6.4 9304 2326 5124 4000 179 15 JCHDFJCHZHWL04 5 9 8.2 11601 2320 4447 4000 3154 16 JCHDFJCHZHWL05 4 6 5.3 6430 1607 3318 3000 112 17 JCHDFJCHZHWL06 5 9 8.2 22328 4465 4188 18000 140 18 JCHDFJCHZHWL07 7 7.5 7 26236 3748 6040 20000 196 19 JCHDFJCHZHWL08 4 6 6.4 13510 3377 5331 8000 179 20

Wanglou

JCHDFJCHZHWL09 3 5 3 9450 3150 2450 7000 0 Subtotal 39 59.5 54.1 111459 2858 36303 1500 69500 4156

21 JCHDFJCHZHWQ01 3 6 5.4 9450 3150 1421 8000 29 22 JCHDFJCHZHWQ02 7 7.8 6.1 10147 1449 3578 6500 69 23 JCHDFJCHZHWQ03 5 5.8 4.5 8424 1684 2375 6000 49 24 JCHDFJCHZHWQ04 3 3.9 3 10260 3420 639 9600 21 25 JCHDFJCHZHWQ06 2 3 2.5 127 63 114 13 26 JCHDFJCHZHWQ07 2 4.5 3.9 1613 806 693 800 120 27 JCHDFJCHZHWQ08 4 4.5 3.9 6263 1565 1235 5000 28

28

Wangqiao

JCHDFJCHZHWQ09 5 7.5 6.1 10459 2091 2410 8000 49 Subtotal 31 43 35.4 56742 1830 12464 43900 378

Total 121 152.6 129.7 285461 2359 73150 1500 205400 5410

6.2 Recovery of Incomes

6.2.1 Farming Incomes

The sample households covered by this follow-up monitoring had a net farming income of 1,605 RMB per capita and 564 RMB per mu in 2006. Farmland reduction caused a decrease of 187 RMB in comparison with the income in the previous year 2005, or a loss rate of 23.6%. The highest loss was found in Wangqiao, 234 RMB, or 36.8%. Refer to Table 15 for detailed information.

Page 144: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

132

Table 15 Farming Income Impacts by Farmland Reduction Follow-up Year (2006) Base Year (2005) Reduction

With Project Per Capita Income

Without Project

Per Capita Income Farmland Income Village

Farmland People Total Farming Income per mu Farmland People Total Farming

Farming Income Per mu Area % Amount %

Unit mu person RMB RMB RMB mu person RMB RMB RMB mu % RMB % Dalizhuang 40.2 51 2299 478 603 50.1 51 2035 569 579 9.9 19.8 91 16.0Wanglou 54.1 39 2858 931 671 59.5 41 2092 1196 823 5.4 9.1 265 22.1Wangqiao 35.4 31 1830 402 352 43 33 2235 636 488 7.6 17.7 234 36.8

Total 129.7 121 2359 605 563 152.6 125 2107 792 630 22.9 15.0 187 23.6

As understood in further investigations, the decrease of farming incomes in 2006 was mainly attributable to excessive rainfall and subsequent drop in production.

6.2.2 Sideline and Other Incomes

In 2006 the sample households earned 440 RMB more from other activities than farming, including 472 RMB more from sidelines (an increase of 38%, mainly farmer workers, 33%) and 35 RMB less from other sources. There was an increase in Dalizhuang (1,031 RMB) and Wanglou, but a decrease in Wangqiao. This indicates less time for farming and more time for farmer workers, and subsequently more incomes from sideline and other sources. Refer to Table 16 for details.

Table 16 Changed Per Capita Incomes from Sideline and Other Sources Follow-up Year (2006) Base Year (2005) Difference

Sideline Sideline Sideline Sample Village Animal

Raising Subtotal Farmer Worker

Others Subtotal Animal Raising Subtotal Farmer

WorkerOthers Subtotal Animal

Raising Subtotal Farmer Worker

Others Subtotal

Dalizhuang 1804 1412 17 1821 1414 1276 53 1467 390 136 -36 354

Wanglou 38 1782 1782 107 1927 24 707 658 165 896 36 1075 1124 -58 1031

Wangqiao 1416 1416 12 1428 1582 1582 18 1600 0 -166 -166 -6 -172

Total 12 1698 1532 45 1755 8 1226 1154 80 1314 4 472 378 -35 441

In order to have a better understanding of the mitigating/offsetting measures, interviews with households have been conducted as part of this M&E. Refer to Table 17 for details.

Impacts by farmland reduction: Out of the total number of 28 households, 15 (54%) say their land loss is limited, with minor impacts on their incomes, if any; 6 (21%) feel the loss of poor quality land does not cause any major impacts on their family incomes; 5 (18%) believe their family incomes are affected considerably; and 2 earn less from farming but more from other sources, without impacts on their total incomes.

Use of land compensations: As found in field surveys, 9 of the sample households use land compensations for farming, 14 for medical fees and children’s tuitions among other daily expenses, 2 for business, and 3 for housing, taking up 32%, 50%, 7% and 11% respectively.

Remedy measures: Out of the 15 sample households, 9 have recovered their incomes by farmer workers and 10 by extensive farming and intercropping, constituting 54% and 36%.

To sum up, 18% households believe that their family incomes are affected considerably, but only 3% have not yet taken remedy measures to recovery incomes, whilst 97% have taken various measures, such as farmer worker, business, intensive farming and intercropping, to minimize the negative impacts by farmland reduction.

Page 145: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

133

Table 17 Questionnaire for Income Recovery

Yes No No. Item People % People % I Impact by farmland reduction 28 100

1 Less income from farming, but more from other sources, without any impact on total income 2 7

2 Minor impact due to less land loss 15 54 3 Minor impact due to poor land quality 6 21 4 Major impact 5 18 5 Others II Use of land compensations 28 100 1 Farming 9 32 2 Business 2 7 3 Housing 3 11 4 Medical fees, tuitions and other living expenses 14 50 5 Debit repayment 6 Others

III Remedy measures 28 100 1 Farmer worker 15 54 2 Business 2 7 3 Cropping, animal raising or plastic tunnel 4 Extensive farming and intercropping 10 36 5 Reclamation or cultivating others’ land 6 Trust to luck 1 3 7 Others

6.3 Implication of Income Changes

According to China’s communiqué of national economic and social development in 2006, rural residents with a per capita income less than 693, 694-958 and more than 958 RMB were classified as absolutely poor people, low-income and non-poor people respectively.

In comparison with the situation in the base year, the number of absolutely poor and low- income people was decreased by 1 and 10 respectively, 0.7% and 7.9%, whilst that of non- poor people was increased by 7, or 8.6%. This suggests improvement of poverty regardless farmland reduction. Refer to Table 18 for details.

Table 18 Comparison of Poverty Populations

Item 2005 2006 Change Unit People % People % People %

Non-poor 107 85.6 114 94.2 8.6 Low-income 12 9.6 2 1.7 -7.9 Absolutely poor 6 4.8 5 4.1 -0.7

Total 125 100.0 121 100.0

6.4 Evaluation

As understood in interviews with sample households, farmland reduction implies more time for farmer workers, without any major impacts on family incomes except in Wanglou, where the incomes are reduced due to the inundation of farmland (mostly in floodplains) this year.

Page 146: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

134

7. PROTECTION OF RIGHTS AND INTERESTS

7.1 Training

The M&E team has discussed with local responsible departments regarding training activities in production skills, including training programs and demands. It is known that the Employer has concluded a training program with Jiucheng Township. As found in interviews with 28 sample households, however, such program is not yet implemented. Also, it is understood that 96% of them wish to be trained, including 53% in farming, 29% in animal raising and 14% in sideline and other activities. Refer to Table 19.

Table 19 Willingness to Be Trained

Subtotal Yes No No. Index

People % People % People %

I Have you been trained since 2004? 28 100

1 If yes, training in farming skills? 2 Training in policies and laws/regulations? 3 Any other training? 4 Do you wish to be trained? 27 96 1 4

5 If yes, scientific farming? 15 55.6

6 Animal raising? 8 29.6

7 Sideline? 4 14.8 8 Others?

7.2 Complaints Management

As understood in interviews with the township governments, village committees and farmers, the affected people generally concern and complain about poor drainage during construction, hoping for early and thorough dredging.

As understood in discussions with responsible departments, the problem of poor drainage will be solved no sooner than the completion of construction.

7.3 Vulnerable Groups

This monitoring continues special attention to the vulnerable groups affected in the project area. As found in the investigation, 12 households and 15 people are affected, taking up for 1% of the total number of affected people, including 3 and 4 elderly persons of no family involved in physical relocation, accounting for % of the total resettlement population. Now these people live on 3 major sources: income from farmland cultivating by relatives/friends, food and monetary relief provided by the county civil administration on festivals, and old folk’s home operated by the township government. For example, Zhang Baoqi, an elderly person of no family and also a resettlement household in Wanglou, is provided with a new house with some 2,000 RMB from the county civil administration; Dong Chunqiang and Dong Zhanyun in Dongzhuang are provided with 8 RMB allowance each month and 25 kg flour on festivals by the county civil administration. With the help of the local governments, these vulnerable groups are properly resettled.

Page 147: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Juancheng Dike Subproject Resettlement M&E Report (Report No. 3)

135

8. EVALUATION AND RECOMMENDATION

8.1 Evaluation

The mode of money-based economic rehabilitation is used for permanent land acquisition. Through wide public consultation, the mode of cash payment or land adjustment is adopted. Permanent land acquisition involves 4 villages, 13 groups, 352 households and 1,476 people. Among these groups, only 1 adopts Option B, taking up 4% of the number of households and people, while the rest 12 choose Option A, i.e. 96%, which maximizes the impacts on production by land reduction.

As construction is finished, the land for the use of pipes has been totally restored by the time of this M&E. This is also the case of 291.87 mu for excavation purposes. Compensations for temporary land use have been paid in full as agreed.

In respect of income recovery, the per capita net income is 252 RMB more than that in the base year, without any major impacts on farming incomes as a result of farmland reduction. But Wangqiao is another story, where there is a decrease due to the inundation of farmland (mostly in floodplains).

Regarding the rehabilitation of housing conditions, all the resettlement families are properly resettled, new residential sites are developed now, and living circumstances are improved.

Compensation rates are published in the form of government notices, to be open and transparent, and payments are basically made in time according to the published rates.

Also, the local government authorities have provided proper measures for vulnerable groups.

8.2 Problems and Recommendations

Poor drainage during the performance of pumping works results in farmland and house inundation somewhere. Fortunately, the Implementing Agency has promised to cause the earliest treatment of this issue.

Having communicated and discussed with the responsible parties, the Implementing Agency has proposed a program for the application of outstanding amounts and promised to use them for economic/livelihood rehabilitation. This will be reviewed as a priority of the next M&E.

Page 148: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

136

ADB-loaned Yellow River Flood Management Sector Project

Dongpinghu Rehabilitation

RESETTLEMENT M&E REPORT (Report No. 5)

Henan Yellow River Resettlement Economic Development Company

December 2007

Appendix 5

Page 149: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

137

Approved: Yang Jianshe

Reviewed: Zhang Hao, Zuo Ping

Task Manager: Zuo Ping

Team Leader: Liu Fengjing

Chief Editor: Liu Fengjing, Dong Kunjie

Proofreader: Jiao Lili, Wang Jianzhong, Zhao Huan’e, Yang Tao

Contributors: Dong Kunjie, Guan Guosheng, Lu Shouchao, Jiao Lili, Li Li, Liu

Fengjing, Song Bo, Wang Jianzhong, Yang Jianshe, Duan Wei, Yang

Tao, Zhang Hao, Zhao Huan’e, Zuo Ping

Page 150: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

138

Table of Contents

1. OVERVIEW_________________________________________________________139

1.1 Subproject Brief_________________________________________________ 139

1.2 Land Acquisition and Resettlement_________________________________140

1.3 Monitoring & Evaluation _________________________________________ 141

2. DISBURSEMENT AND PAYMENT _____________________________________141

2.1 Process of Disbursement __________________________________________141

2.2 Compensation Rates _____________________________________________141

2.3 Payment _______________________________________________________143

3. IMPACTS AND ECONOMIC REHABILITATION ________________________144

3.1 Dongpinghu 77__________________________________________________144

3.2 Dongpinghu 10__________________________________________________148

4. PHYSICAL RELOCATION AND HOUSING RESTORATION ______________148

5. REPLACEMENT OF SPECIAL FACILITIES ____________________________150

6. PROTECTION OF RIGHTS AND INTERESTS___________________________150

7. EVALUATION AND RECOMMENDATION _____________________________150

8. OUTSTANDING PROBLEMS__________________________________________151

Page 151: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

139

1. OVERVIEW

This is the 5th M&E of Dongpinghu Rehabilitation Subproject. Dongpinghu rehabilitation programs were approved at 2 different times, with Dongpinghu 55+000~77+300 (referred to as “Dongpinghu 55 hereinafter) approved at the 1st time (Group 1 subprojects under the ADB-loaned Yellow River Flood Management Sector Project), Dongpinghu 77+300~88+ 400 and Dongpinghu 10+471~55+000 (referred to as “Dongpinghu 77” and “Dongpinghu 10” respectively) at the 2nd time (Group 4). Dongpinghu 55, a core subproject, has been completed, with a completion report prepared as part of the last M&E report. Thus, this Report No. 5 discusses Dongpinghu 77 and Dongpinghu 10 only.

1.1 Subproject Brief

(1) Dongpinghu 77

Dongpinghu 77 is located in Dongping County, Shandong Province, with a total length of 11.1 km. Main works are for dike raising/widening and cutoff wall, together with 10 m wide land acquired for protection works at station No. 77+300~88+400. The total budget approved by the State is 75.49 million RMB, including 9.35 million RMB for land acquisition (8.58 million RMB direct costs).

An “Implementation Scheme” (referred to as the “Scheme” hereinafter) was prepared by the Yellow River Engineering Consulting Co., Ltd. in May 2006 and subsequently approved by Shandong Yellow River Engineering Bureau in July 2006, as authorized by YRCC, via letter No. (2006)23, with an additional budget of 480,000 RMB approved as direct costs. In 2006, another amount of 1.2519 million RMB was approved by YRCC in letter No. [2006]133, including 93,400 RMB for young crops and 1.1585 million RMB for land restoration and other purposes. The total resettlement budget is 11.0819 million RMB, including 9.1534 million RMB direct costs.

Construction was commenced in April 2006 and nearly finished in November 2007.

(2) Dongpinghu 10

Dongpinghu 10 is located in Liangshan County, with a total length of 44.529 km. Main works are totally for cutoff walls. The approved resettlement budget is 88.67 million RMB, including 2.16 million RMB for land acquisition (1.99 RMB direct resettlement costs).

An “Implementation Scheme” was prepared by Shandong Yellow River Design Institute in May and approved by Shandong Yellow River Engineering Bureau in July 2006, with an additional amount of 80,000 RMB approved as direct resettlement costs. The total resettlement budget is 2.24 million RMB, including 2.07 million RMB direct costs.

Construction was commenced in August 2006 and basically completed by April 2007.

Table 1 below is a summary of the approved, additional and total resettlement budgets for Dongpinghu 77 and Dongpinghu 10.

Page 152: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

140

Table 1 Summary of Approved Resettlement Budgets

Unit: 104 RMB Dongpinghu 77 Dongpinghu 10

No. Item Approved Additional Total Approved Additional Total

1 Rural resettlement 722 46.34 768.34 56 56 2 Special facility 136 11 147 143 8 151

Subtotal Direct cost 858 57.34 915.34 199 8 207 3 Miscellaneous & resettlement monitoring 77 115.85 192.85 17 17

Total 935 173.19 1108.19 216 8 224 1.2 Land Acquisition and Resettlement

Dongping Lake Management Bureau acts as the Employer, which has set up a Project Office to be in charge of resettlement and field management. Liangshan and Dongping Counties function as the Implementing Agency, with a separate Project Office established to be responsible for the implementation of land acquisition and resettlement. The Yellow River Engineering Consulting Co., Ltd. is employed as the Designer and Henan Huanghe Resettlement Economic Development Company as the External Monitor.

Dongpinghu 77: Land acquisition and physical relocation were commenced in April 2006, with 133.98 mu (including 99.7 mu farmland and 34.28 mu non-productive land) agreed and acquired for permanent use by the time of the last M&E, taking up 88% of the figure of 151.61 mu shown in the resettlement plan (referred to as the “RP”). Permanent land acquisition meets the demand of construction, not needing any further land acquisition. The completed area for temporary use is 1,049.015 mu, including 751.855 mu for excavation and 297.16 mu for occupation, taking up 69% of 1,523.48 mu included in the Scheme. Altogether 89 households have been relocated, and those in the need of housing have moved to new houses. By the time of this M&E, construction was nearly finished, permanent land acquisition completed, land for temporary use restored by 97%, and special facilities replaced.

Dongpinghu 10: Construction was started in August 2006. Permanent land acquisition use and physical relocation are not necessary for this subproject. The clearing of attachments mainly involves shade trees at the crest and on the waterside. The completed land area for temporary use is 225.18 mu, totally for the purpose of camps and stockpile areas, taking up 100.6% of the figure of 223.29 mu proposed in the Scheme. Special facilities include power lines, optical cables and roads.

The progress of land acquisition is shown in Table 2.

Table 2 Progress of Implementation Unit: 104 RMB

Permanent Land Use Temporary Land Use No. Subproject County

RP Scheme 4th M&E 5th M&E % of RP RP Scheme 4th M&E 5th M&E % of RP

1 Dongpinghu 77 Dongping 151.61 151.61 133.98 133.98 88% 1524.38 1523.48 883.7 1049.015 69%

2 Dongpinghu 10 Liangshan 140.14 223.29 225.18 100.6

Page 153: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

141

1.3 Monitoring & Evaluation

This 5th M&E is an extension of the previous M&E of Dongpinghu Rehabilitation Subproject (including Dongpinghu 55).

Study area and focus: The study area covers the Employer, Implementing Agency, affected townships, villages and farmers, focusing on: (1) operation of resettlement organizations, (2) disbursement, rate, payment of compensations, (3) townships, villages, groups and farmers affected by permanent land use, together with land loss, economic rehabilitation and income recovery, (4) temporary land occupation and restoration, (5) restoration of housing conditions, and (6) development of residential sites.

Methodology: An TOR was prepared in August and field work performed in early September 2007. Information on the progress of land acquisition, payment and economic rehabilitation is collected by discussing discussion with Dongpinghu Lake Bureau and Dongping/Liangshan Project Office and interviewing with the affected townships, villages, groups and farmers. Sample households are interviewed in the respect of impacts by land acquisition, progress of physical relocation, and protection of their rights and interests. This report is prepared on the basis of data processing and statistical work.

2. DISBURSEMENT AND PAYMENT

2.1 Process of Disbursement

The process of disbursement for both subprojects is arranged as follows:

Permanent land acquisition: Dongpinghu Lake Bureau →County Project Office→township→ village

Temporary land occupation: Dongpinghu Lake Bureau→County Project Office→village or household

Housing and attachments: Dongpinghu Lake Bureau→County Project Office→village or household

Special facilities: Dongpinghu Lake Bureau→County Project Office→contractor

2.2 Compensation Rates

Compensations Dongpinghu 77 are paid at the rates fixed in the Scheme except for temporary land use, without price adjustment in the course of implementation.

Adjusted rates for the temporary land use of Dongpinghu 77:

In the Scheme, the land for the use of excavation is compensated per season on the basis of the output value of 1 year and 1.5 years, i.e. 1,146 RMB/mu and 1,719 RMB/mu, while that for the use of occupation is compensated per season on the basis of the output value of 0.5, 1 and 1.5 years, i.e. 573 RMB/mu, 1,146 RMB/mu and 1,719 RMB/mu respectively.

Page 154: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

142

Since Dongpinghu 77 is adjacent to the borrow areas for Jihe Expressway, which uses the rate of 3,500 RMB/mu, much higher than the highest rate of 1,719 RMB/mu approved in the Scheme, there is a high degree of difficulty in temporary land occupation. To enable smooth progress of implementation, the Project Office held a meeting to the effect of “resettlement issues in Dongpinghu Rehabilitation Subproject” in August 2006, which was attended by the Designer, Employer, External Monitor and Implementing Agency. On the principle of seeking truth from facts, it was agreed to increase the compensation rates to 3,000 RMB/mu, 3,200 RMB/mu, 3,500 RMB/mu and 3,900 RMB/mu respectively, with price adjustment paid out of the total budget.

Table 3 shows a summary of the RP, Scheme and actual rates for main entitlements.

Table 3 Comparison of Main Compensation Rates for Dongpinghu 77

No. Item Unit RP Scheme Actual I Permanent land use Farmland mu 11460 11460 11460

II Temporary land use 1 Excavation mu 1 year mu 1146 1146 1.5 year mu 1719 1719

3000 RMB/mu, 3200 RMB/mu, 3500 RMB/mu, 3900 RMB/mu

2 Occupation 0.5 year mu 573 573 573 1 year mu 1146 1146 1146 1.5 year mu 1719 1719 1719

III Housing & attachment 1 Main room Brick-concrete m2 260 260 260 Brick-timber m2 220 220 220 Earth-timber m2 201 180 180 Mixed m2 215 180 180

2 Auxiliary room Brick-concrete m2 163 163 163 RMB/m2, 160 RMB/ m2 Earth-timber m2 121 121 121 Simple m2 50 50 50

IV Sparse tree 1 Timber tree Small tree 20 4 4 Middle tree 30 30 30 Big tree 45 45 45

2 Sparse fruit Small 30 30 30 Middle 190 190 190 Big 300 300 300

For Dongpinghu 10 (without permanent land use and physical relocation), rates for temporary land use, attachments and special facilities are all applied as approved in the Scheme. Table 4 compares the RP, Scheme and actual rates.

Page 155: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

143

Table 4 Comparison of Main Compensation Rates for Dongpinghu 10 No. Item Unit RP Scheme Actual

I Temporary land use Camp (1 year) mu 1146 1146 1146 Warehouse (1 year) mu 1146 1146 1146 Temporary facility (2years) mu 2292 2292 2292

II Crest attachment Small tree 20 20 20 Middle tree 30 30 30 Big tree 45 45 45

III Special facility Power line km 18000 18000 18000 High-voltage line (10kv) Km 100000 100000 100000 High-voltage line (35kv) Km 150000 150000 150000 Telecom line Km 2000 2000 2000 Optical cable km 6500 6500 6500

2.3 Payment

A total amount of 9.0568 million RMB has been paid to the affected villages, households and organizations in Dongpinghu 77, i.e. 98.9% of the total budget of 9.1534 million RMB, including 1.1426 million RMB for permanent land use, 3.3503 million RMB for temporary land use (including land restoration), 1.8577 million RMB for housing, 1.3409 million RMB for special facilities, and 1.3653 million RMB for attachments and others. The additional payment since the last M&E is 3.3556 million RMB, with 65.3% paid for temporary land use. Payment for this subproject is nearly finished. The outstanding amount, an additional budget approved by YRCC in letter No.[2006]133, will be addressed in the next M&E.

Table 5 shows the payment of direct resettlement costs for Dongpinghu 77.

Table 5 Payment of Direct Resettlement Costs for Dongpinghu 77

No. Item Approved Total Agreed 4th M&E

5th M&E Increase

1 Permanent land use 124.79 114.26 114.26 2 Temporary land use 301.18 115.92 335.03 219.11 3 Housing 137.35 162.82 185.77 22.95 4 Special facility 147.23 129.54 134.09 4.55 5 Attachment & others

858 915.34

195.13 47.58 136.53 88.95 Amount 858 915.34 905.68 570.12 905.68 335.56 % of approved 105.6 66.4 105.6 % of total 98.9 62.3 98.9 Total % of agreed 100.0 62.9 100.0

Source: Implementing Agency.

The total amount of 2.07 million RMB for Dongpinghu 10 has been paid in full, including 257,600 RMB for temporary land use, 302,400 RMB for crest attachments and 1.51 million RMB for special facilities. In comparison with the progress achieved by the time of the last M&E, there is an additional payment of 1.77 million RMB, mostly for special facilities (83.5%). Refer to Table 6 for the progress of payment for Dongpinghu 10.

Table 7 shows a summary of the resettlement costs paid for Dongpinghu 77 and Dongpinghu 10 and reflected in previous M&E.

Page 156: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

144

Table 6 Payment of Direct Resettlement Costs for Dongpinghu 10

No. Item Approved Total Agreed 4th M&E

5th M&E Increase

1 Temporary land use 25.76 10 25.76 15.76 2 Special facility 151.00 151.00 151.00 3 Attachment & others

199 207 30.24 20 30.24 10.24

Amount 199 207 207.00 30 207.00 177.00 % of approved 104.0 15.1 104.0 % of total 100.0 14.5 100.0 Total % of agreed 100.0 14.5 100.0

Source: Implementing Agency.

Table 7 Summary of Previous Payments for Dongpinghu 77 and 10

Dongpinghu 77 Dongpinghu 10 M&E M&E No. Item

Approved Total 3rd M&E 4th M&E

5th M&E % of Total Approved Total

3rd M&E 4th M&E 5th M&E % of

Total 1 Resettlement 722 768.34 121.32 535.28 771.59 100.4 56 56 Not started 30 56 100 2 Special facility 136 147 0 34.84 134.09 91.1 143 151 0 0 151 100

Total Direct cost 858 915.34 121.32 570.12 905.68 98.9 199 207 0 30 207 100

Source: Letter Nos. [2006] and [2006]23 of Shandong Project Office, Dongping/Liangshan Project Office, and letter No. [2006]133 of YRCC.

3. IMPACTS AND ECONOMIC REHABILITATION

3.1 Dongpinghu 77

The completed land area for permanent use is 133.98 mu in Beimen, Zhanyuan, Wangyaowa, Duyaowa, Gezhenyuan, Xielou, Xizhengzhuang, Chenfang and Wujiawan, including 99.7 mu farmland (51.74 mu contracted to farmers and the rest owned by collective) and 34.28 mu non-productive land.

Detailed information is given in Table 8 below.

Table 8 Permanent Land Use for Dongpinghu 77

Original Farmland Permanent Land Use Farmland No. Affected Village

Group Home People Farmland Group Home People SubtotalPrivate Per Capita Loss

Unit home person mu home person mu mu mu Chuancheng Township 48 2010 7573 6224 13 430 1615 99.70 51.74 0.032 1 Beimen 6 198 875 660 2 50 202 3.27 3.27 0.016 2 Gezhenyuan 9 430 1612 1035 Collective 5.13 3 Zhanyuan 5 175 678 700 5 175 678 11.94 11.94 0.018 4 Wangyaowa 3 150 490 330 3 10 35 18 18 0.51 5 Duyaowa 3 195 700 332 3 195 700 18.53 18.53 0.026 6 Xielou 4 172 662 718 Collective 2.76 7 Xizhengzhuang 8 260 1008 1080 Collective 11.12 8 Chenfang 6 250 897 818 Collective 14.78 9 Wujiaman 4 180 651 551 Collective 14.17

(1) Permanent land use and economic rehabilitation

As the land is distributed vertically to the pot dam, the acquired private land is limited, but the range of impact is very large, involving 13 groups, 430 households and 1,615 people in Beimen, Zhanyuan, Wangyaowa and Duyaowa, with a per capita loss of 0.032 mu.

Page 157: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

145

Economic rehabilitation: Land compensations for the 9 villages are totally retained for public utilities such as roads, canals and wells as discussed and agreed by farmers. Among the 4 villages where private land is used, Beimen and Wangyaowa have finished land adjustment, Zhanyuan dons not need land adjustment because of little land is taken out of all homes, and Duyaowa pays 600 RMB/mu to farmers until proposed land adjustment in June 2008, when the contract will expires.

The farmers affected by permanent/temporary land use and physical relocation have been interviewed on a random basis, which reveals the impacts on their production and livelihood.

The following box records an interview with Zhao Qingju, who is involved in permanent land use in Wangyaowa:

Interviewer: Hello, how many people are there in your family? How much land did you have? How much was used for the project? When?

Zhao: 5 people, 3.35 mu land, including 3 mu field and 0.35 mu vegetable plot. In 2006, 0.2 mu was acquired for permanent use, vegetable plot.

Interviewer: Was land adjustment arranged subsequently? If yes, when?

Zhao: Yes, 0.2 mu collective land was provided by the village in June 2006.

Interviewer: How much have you received as land compensation? How many times has it been paid? What are the constituents? How have you used the money?

Zhao: No compensation was received, because land adjustment was practiced as the mode of economic rehabilitation, without cash payment. The compensation was retained by the village and used for road building.

Interviewer: What have you done to offset your income loss?

Zhao: The farming income was not reduced.

Interviewer: Do you think your family income is greatly affected?

Zhao: With land adjustment, there is no impact.

Interviewer: Are you satisfied with the existing production/living conditions? What’s your plan for the future?

Zhao: I’m satisfied. No objection to the use of land compensations. The village leaders act fairly and road building is convenient to all of use. My son and daughter will continue to work as farmer workers outside.

Interviewer: Thank you, we will be back in the near future. Wish you a better life.

Page 158: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

146

(2) Temporary land occupation and restoration

An additional area of 165.29 mu has been used since the last M&E, including 82.16 mu for occupation and 83.13 mu for excavation. The completed total area by the time of this M&E is 1,049.02 mu, 68.86% of the Scheme, including 751.86 mu (farmland) for borrow areas and 297.16 mu for occupation purposes. The affected facilities and organizations include: a warehouse of Chuncheng Township in Dongping, 8 villages (Shiliulin, Zhangliulin, Shanlou, Gezhenyuan, Dadongmen, Wenmiao, Chenfang and Weizihe), 6 households (An Jiahou, An Licheng, Han Wei, Peng Guangqin, Shi Cunqing, Zhan Baoru), and Jihe Expressway Project Management—Lot 10, Shandong Highway & Bridge Construction Group. Refer to Table 9.

Table 9 Progress of Temporary Land Use for Dongpinghu 77

4th M&E 5th M&E Increase Purpose Scheme

Area % of Scheme Area % of Scheme Area % Occupation 304.42 215 70.63 297.16 97.62 82.16 26.99 Excavation 1219.06 668.73 54.86 751.86 61.67 83.13 28.27

Total 1523.48 883.73 58.01 1049.02 68.86 165.29 10.85

By the time of this M&E, 1,019.15 mu has been restored though the restoration of 30 mu in Shiliulin fails to meet the requirements, a percentage of 97%. See Photographs 1 and 2 for the situation of land restoration. With payment and most land restoration achieved in time, the farmers are fairly satisfied.

Photograph 1: Land Being Restored in Shiliulin Photograph 2: Autumn Harvest in Restored Land in Shiliulin

During the temporary occupation of land, the farmers work outside to mitigate/offset income loss. Compensations are mostly used to buy farming machines and developing animal raising activities. Therefore, temporary land use has not caused major impacts on their production and livelihood.

Table 10 shows the progress of temporary land occupation and restoration.

Page 159: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

147

Table 10 Temporary Land Use for Dongpinghu 77 Land Restoration

Restored Village Private Area Depth Rate Amount Area % Cost

Not RestoredPurpose Township

Unit mu m RMB/mu RMB mu % RMB mu 90.43 1146 103633.00 90.43 100 6601 Township 114.24 1719 196378.56 114.24 100 8340

Chenfang 2.62 1146 3002.52 2.62 100 191 2.55 1719 4383.45 2.55 100 186 Dongpinghu

Bureau 15.75 1146 18049.5 15.75 100 1150 Gezhenyuan 7.53 1719 12944 7.53 100 550

2.1 573 1203 2.1 100 153 9.61 1146 11013.06 9.61 100 702 Shanlou 10.78 1146 12353.88 10.78 100 787

Dadongmen 7.445 573 4266 7.445 100 543 Wenmiao 3.515 573 2014 3.515 100 257

12.24 1146 14027.04 12.24 100 894

Chuancheng

Shiliulin 18.35 1146 21029.10 18.35 100 1340

Occupation

Subtotal 297.16 404297.11 297.16 100 21693 An Jiahou 29.715 1.3 3000 89145 29.72 100 14620 Gezhenyuan An Licheng 22.79 1.3 3000 68370 22.79 100 11213

Han Wei 33.46 1.3 3000 100380 33.46 100 16463 Peng Guangqin 21.18 1.3 3000 63540 21.18 100 10421

Zhanyuan Zhan Baoru 20 1.3 3000 60000 20 100 9841 63.5 1.3 3200 203200 63.5 100 31242 Daniu Shi Cunqing 5.95 1.3 3200 19040 5.95 100 2927

31.28 1.3 3500 109480 31.28 100 15390 Shanlou 18.57 1.3 3500 64995 18.57 100 9136 Shiliulin 358.76 1.3 3500 1255660 328.76 92 176510 30

Chuancheng

Zhangliulin 18.43 1.5 3900 71877 18.43 100 9068 Jihe Expressway Project Management –Lot 10 52 1.3 3500 182000 52 100 25585

Pengji Township 76.22 1.3 3500 266770 76.22 100 37500

Excavation

Subtotal 751.86 2554457 721.855 96 369915 Total 1049 2958754.11 1019.015 97 391606 30

Source: Project Office.

The box records an interview with Chen Qingyu, who is affected by temporary land use in Shanlou of Chuancheng Township, Dongping County:

Interviewer: Hello, how many people are there in your family? How much land did you have? How much was used for the project? When?

Yu: 6 people, 6 mu for grain rations and 2.85 mu contracted collective land. In October 2006, 1 mu contracted land was used as borrow area.

Interviewer: Was the land restored? If yes, when?

Yu: Yes, in June 2007.

Interviewer: How much have you received as land compensation? How many times has it been paid? What are the constituents? How have you used the money?

Yu: The land for temporary use was contracted collective land, rather than private land for producing food for personal consumption, so compensations were retained by the village for road/well building. But the village exempted me from 220 RMB rent for 2007, and, further to this, contracted 1 mu restored land to me after applying fertilizer and ploughing after the wheat harvest this year, allowing me to plant an autumn crop.

Interviewer: What have you done to offset your income loss?

Page 160: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

148

Yu: The farming income was not reduced.

Interviewer: Do you think your family income is greatly affected?

Yu: No, cropping was affected, but the village exempted me from 1-year rent and enabled me to crop an autumn crop.

Interviewer: Are you satisfied with the existing production/living conditions? What’s your plan for the future?

Yu: I’m satisfied and will continue farming.

Interviewer: Thank you, we will be back in the near future. Wish you a better life.

3.2 Dongpinghu 10

Permanent land use is not necessary for Dongpinghu 10. With 1.952 mu used since the last M&E, a total of 225.181 mu as been used, accounting for 100.8% of 223.29 mu included in the Scheme. This area is totally used for camps and warehouses, involving 9 villages, 11 households and 130 people in Liangshan County, namely, Huangheya, Yanlou, Weizhuang in Xiao’anshan Township, Houmatou, Chazhuang in Liangshan Township, Sigai, Dinglou, Beiwang and Qianyao in Hangang Township.

Land restoration has been finished and compensation paid to affected villages by the time of this M&E.

Detailed information is given in Table 11 below.

Table 11 Progress of Temporary Land Use for Dongpinghu 10

Land Restoration Restored Township Village Area Amount

Area % Purpose

Unit mu RMB mu % Huangheya 35.00 35.00 100 Yanlou 15.00 15.00 100 Xiao’anshan Weizhuang 19.81

80002.34 19.81 100

Sigai 27.221 31210.00 27.221 100 Dinglou 30.00 30.00 100 Beiwang 39.71 39.71 100 Hangang

Qianyao 35 119997.66

35.00 100 Houmatou 13.96 16000.00 13.96 100

Occupation

Liangshan Chazhuang 9.48 10400.00 9.48 100 Subtotal 225.181 257610.00 225.181 100

Source: Liangshan Project Office

4. PHYSICAL RELOCATION AND HOUSING RESTORATION

All the 85 resettlement families in 3 villages have been resettled, with 1.8577 million RMB paid by the Project Office, including 1.2073 million RMB for housings (6,242.44 m2, main and auxiliary rooms) and 650,400 RMB for associated structures and sparse trees. In the course of implementation, payments are made at the rates approved in the Scheme except for minor price adjustment for auxiliary rooms.

Due to land restrains, resettlement of these 85 families is done in 2 different modes: decentral resettlement in Gezhenyuan and Wujiaman, combination of decentral and central resettlement

Page 161: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

149

in Xizhengzhuang. Homesteads have been identified for all of the 83 households in need of new homesteads, including 72 having completed houses (including 14 bought) and the rest 11 not needing new houses at this moment (living with family members). Resettlement families are resettled, new houses are better in both area and structure. Water/power supply, road and other amenities are completed.

See Photographs 3 and 4 for new houses and new road.

Photograph 3: New Xizhengzhuang Photograph 4: New Road in Xizhengzhuang

Table 12 Physical Relocation and Housing in Dongpinghu 77

Planned Housing Resettlement Village Scheme

Subtotal Done Undone Homestead Identification Subtotal Built Bought Pending Homestead Subtotal New Buy

Join Family Member

Unit home home home home home home home home home mu home home home home Gezhenyuan 42 42 42 42 42 31 6 5 0.47 42 31 6 5 Xizhengzhuang 36 38 38 36 36 22 8 6 0.35 36 22 8 6 Wujiaman 11 5 5 5 5 5 0.4 5 5

Total 89 85 85 83 83 72 14 11 83 58 14 11 % 95.5 100 100 100 70 13 13 0.41 100 70 17 13

The M&E team has interviewed Zheng Dongxian, a resettlement family in Xizhengzhuang. The following box records this interview:

Interviewer: Hello, how many people are there in your family? Zheng: 3 people. Interview: Have you built a new house? If yes, How many rooms? Zheng: Yes, 4 main rooms, 4 auxiliary rooms, 1 gate and a staircase, with a floor area of some 126 m2. Interviewer: How much have you received as housing compensation? How have you used the money? Zheng: 15,700 RMB, not enough a construct a new house, which costs more than 50,000 RMB. But the new house is larger, running water rather than well water is available, and a road together with street lamps is in place. Interviewer: Do you think your livelihood is greatly affected? Zheng: It is affected in a sense, but living and housing conditions are improved. Interviewer: Are you satisfied with the existing production/living conditions? What’s your plan for the

Page 162: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

150

future? Zheng: Yes. I will go on farming, but also work outside in the slack season, to make more money. Interviewer: Thank you, we will be back in the near future. Wish you a better life.

5. REPLACEMENT OF SPECIAL FACILITIES

The special facilities affected by Dongpinghu 77 include: 300 m 35kv high voltage power line, 30 m 10kv power line, an optical cable and 300 m telephone line. Compensations for the replacement of such have been disbursed to responsible contractors by the Project Office.

The special facilities affected by Dongpinghu 10 include: 72 power lines and optical cables (4 35kv high-voltage lines, 13 10kv high-voltage lines, 55 other lines) and 4 access crossings. These have been completed by the time of this M&E.

6. PROTECTION OF RIGHTS AND INTERESTS

A sample inspection is made in Shanlou with more temporary land use and Xizhengzhuang with physical relocation in Dongpinghu 77, to keep aware of the progress of temporary land use, physical relocation, economic rehabilitation, housing restoration, and income recovery. Refer to the recorded interviews.

With the exception of a family “enjoying five guarantees” in Xizhengzhuang, which has been resettled properly, land acquisition has not affected in any vulnerable groups elsewhere.

7. EVALUATION AND RECOMMENDATION

(1) Compensations are paid as fixed in the Scheme except that the rate for temporary land use is adjusted to 3,000 RMB/mu, 3,200 RMB/mu, 3,500 RMB/mu and 3,900 RMB/mu, and that for auxiliary brick-timber housing to 163 RMB/m2 and 160 RMB/m2 in practice respectively.

(2) Land compensations for permanent land use are totally retained by villages and, through discussion of villagers, used for public utilities such as roads, canals and wells. Among the 4 affected villages, 2 have carried out land adjustment, while the other 2 do not need land adjustment due to little land loss of all families. This does not represent any major impacts on farming.

(3) Payment for temporary land use is made in full. As construction is totally completed, land restoration and economic rehabilitation are performed except that the restoration of 30 mu in Shiliulin fails to meet the requirement.

(4) Resettlement families are resettled properly, and housing is nearly finished. Homestead areas, housing structures, living circumstances and other amenities such water/power supply facilities and access roads are ameliorated. Farmers are fairly satisfied.

(5) Special facilities are replaced as required in the Scheme, and payment is finished.

(6) Case-specific preferential policies are not provided, but the affected vulnerable groups enjoy equal rights as other affected people regarding compensation and local government preference. They have been all resettled properly.

Page 163: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Dongpinghu Rehabilitation Subproject Resettlement M&E Report (Report No. 5)

151

8. OUTSTANDING PROBLEMS

(1) The restored 30 mu land in Shiliulin is not even, being prone to flooding and affecting the harvest. It is expected that the responsible departments help solve this issue.

(2) Additional compensations for young crops have not been paid.

Page 164: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

151

Appendix 6

ADB-financed Yellow River Flood Management Sector Project

Village Platform Subproject

RESETTLEMENT M&E REPORT

Henan Huanghe Resettlement Economic Development Company

December 2007

Page 165: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

152

Approved: Yang Jianshe

Reviewed: Zhang Hao, Zuo Ping

Task Manager: Zuo Ping

Chief Editor: Li Li

Checked: Jiao Lili, Wang Jianzhong, Yun Lu, Yang Tao

Contributors: Cao Shurong, Chang Quanli, Chen Aiqin, Dong Kunjie, Duan Wei, Duan Yongfeng, Guan Guosheng, Huang Jianqiang, Jiao Lili, Li Li, Li Yang, Liu Fengjing, Shen Yanlong, Shi Jianzhu, Sun Fengzhi, Sun Jupei, Wang Jianzhong, Xue Changyu, Yang Jianshe, Yang Tao, Yun Lu, Zhao Huan’e, Zhang Hao, Zuo Ping

Page 166: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

153

Table of Contents

1. GENERAL.....................................................................................................................154

1.1 Project Brief ........................................................................................................154

1.2 Monitoring and Evaluation ...............................................................................154

1.3 Land Acquisition and Resettlement..................................................................154

2. COMPENSATION........................................................................................................156

2.1 Enforcement of Government Commitments....................................................156

2.2 Compensation Rates and Payments..................................................................156

3. LAND ACQUISITION AND ECONOMIC REHABILITATION............................160

3.1 Permanent Land Acquisition.............................................................................160

3.2 Temporary Land Occupation and Restoration ...............................................161

3.3 Economic Rehabilitation....................................................................................162

4. INCOMES OF AFFECTED PEOPLE........................................................................164

4.1 Income Recovery ................................................................................................164

4.2 Implication of Income Changes.........................................................................165

4.3 Income Recovery of Affected People ................................................................166

5. PHYSICAL RELOCATION AND RESETTLEMENT ............................................167

5.1 Overall Planning of Village Resettlement ........................................................167

5.2 Physical Relocation.............................................................................................167

6. PROTECTION OF RIGHTS AND INTERESTS......................................................168

6.1 Vulnerable Groups .............................................................................................168

6.2 Willingness to Move ...........................................................................................168

7. EVALUATION AND RECOMMENDATION ...........................................................168

7.1 Evaluation ...........................................................................................................168

7.2 Problems and Recommendations......................................................................170

Page 167: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

154

1. GENERAL

1.1 Project Brief

The village platform subprojects of ADB-loaned Yellow River Management Sector Project are intended to protect the life and property of the people living in floodplain, improve production and habitation and settle people’s worry by village platforms and escape roads. This component includes 6 village platform subprojects in 5 counties of 5 cities, including Miaozhai and Wuqiu in Changyuan of Xinxiang (Henan), Lankao of Kaifeng (Henan), Fanxian of Puyang (Henan), Dongming of Heze (Shandong) and Pingyin of Jinan (Shandong). The approved cost estimate is 229.27 million RMB, including 145.36 million RMB national investments and 83.91 million RMB ADB loan proceeds.

Among the 6 approved village platform subprojects, Lankao has been abandoned, and the main works of the other 5 ones have been completed and accepted preliminarily. At present, the construction of associated works and infrastructures is going on in succession.

Table 1 Progress of Project Implementation No. Subproject Main Works Infrastructure Budget 1 Miaozhai Totally completed Not implemented 2736

2 Wuqiu Main works have been completed, edging and covering works have not been started. Not implemented 2543

3 Lankao Not implemented Not implemented 1989 4 Fanxian Totally completed Not implemented 6064 5 Dongming Totally completed Not implemented 4195 6 Pingyin Totally completed In progress 5400

Total 22927

1.2 Monitoring and Evaluation

Study Area and Scope of Work: Continue to monitor and evaluate the implementation of the 5 subprojects, including the following aspects: (1) progress of construction, (2) permanent land use, affected area, impact and economic rehabilitation; (3) temporary land occupation, affected area, and restoration, (4) disbursement and payment of funds promised by the local government, (5) integral programming of villages and construction of infrastructures, (6) income recovery and remedy measures, (7) vulnerable groups, and (8) willingness of move.

1.3 Land Acquisition and Resettlement

According to the Resettlement Plan (referred to as the “RP”), 15 village platforms will be built in Miaozhai, Wuqiu, Fanxian, Dongming and Pingyin to resettle 37065 people of 9028 households in 39 villages, with 4679.51 mu land for permanent use and 9070.73 mu for temporary use. During implementation, 3 village platforms in Miaozhai were consolidated into a large one, and resettlement population was kept constant, thus 13 village platforms are built in 5 subprojects, including Miaozhai of Changyuan, Tanjing and Sanyi in Wuqiu of Changyuan, Luji in Fanxian, south and north in Dongming, Dong’e, Wangxiaozhuang, Houzhai, Lingzhuang, Qianruaner, Xinboshi, Laoboshi and Liuquanhecun in Pingyin. With an additional village in Pingyin, the total number of affected villages is 40.

Page 168: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

155

By the time of this report, permanent land acquisition and main works have been completed for all subprojects. Except Tanjing and Sanyi village platforms in Wuqiu, the edging and covering works of the other 11 village platforms have been completed, but associated works are still going on.

A total area of 4652.95 mu for permanent land use is completed, accounting for 99% of 4679.51 mu in the RP and involving 37 villages, without any change since the last M&E. Land adjustment is necessary among 37 villages and between or within 43 groups, including 19 villages and 26 groups having finished this work. A total area of 5475.55 mu for temporary land use is completed, accounting for 60% of 9070.73 mu in the RP, and 3535.87 mu has been restored, accounting for 68% of 5231.55 mu to be restored, without any change since the last M&E.

Refer to Table 2 for details.

Table 2 Land Acquisition and Resettlement

Unit:mu,% Resettlement Land Acquisition

No. Subproject Stage Village Platfor

m Village Household People Total

Permanent Land Use

Temporary Land Use

RP 15 39 9028 37065 13750.24 4679.51 9070.73IS 13 40 9028 37065 13750.24 4679.51 9070.73Completed 13 10128.5 4652.95 5475.55

Total

% of RP 74 99 60 RP 3 4 890 3988 2056.66 634.36 1422.3IS 1 4 890 3988 2056.66 634.36 1422.3Completed 1 1148.56 570.23 578.33

1 Miaozhai

% of RP 56 90 41 RP 2 3 1181 4651 1356.38 597.38 759IS 2 3 1181 4651 1356.38 597.38 759Completed 2 1285.75 591.81 693.94

2 Wuqiu

% of RP 95 99 91 RP 1 9 2178 8704 3869.33 1001.76 2867.57IS 1 9 2178 8704 3869.33 1001.76 2867.57Completed 1 1892.37 1069.45 822.92

3 Fanxian

% of RP 49 107 29 RP 2 11 2297 9594 3170.05 1080.35 2089.7IS 2 11 2297 9594 3170.05 1080.35 2089.7Completed 2 2504 1055.8 1448.2

4 Dongming

% of RP 79 98 69 RP 7 12 2482 10128 3297.82 1365.66 1932.16IS 7 13 2482 10128 3297.82 1365.66 1932.16Completed 7 3297.82 1365.66 1932.16

5 Pingyin

% of RP 100 100 100

Page 169: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

156

2. COMPENSATION

2.1 Enforcement of Government Commitments

The Government investments are used for the main and associated works 5 village platform subprojects. The local government is responsible for physical relocation, appurtenance and young crop compensation, infrastructure construction, and also poor family relocation after the completion of village platforms, but housing in new village platforms is financed by resettlement families themselves.

The counterpart funds promised by the provinces, cities, counties involved are 49.8704 million RMB. By the time of this M&E, 36.50 million RMB has been disbursed, 5 million RMB more than the progress reported last time, including 3 million RMB disbursed by Jinan City of Shandong Province and 2 million RMB by Fanxian of Henan Province. A total amount of 23.99 million RMB has been paid as compensations for appurtenances, young crops and housings. The outstanding amount is partly disbursed/paid at present and partly retained for the purpose of infrastructure construction and physical relocation.

Counterpart funds promised by provinces:A total amount of 23.5 million RMB has been disbursed, including 3.5 million RMB of 5 million RMB promised by Henan and 20 million RMB by Shandong.

Counterpart funds promised by cities:A sum of 10.5 million RMB has been disbursed, 3 million RMB more than that disbursed by the last M&E, including 1.5 million RMB for Fanxian Subproject promised by Puyang and 9 million RMB out of 15 million RMB for Pingyin promised by Jinan. The amount of 7.8704 million RMB promised by Heze for Dongming has not been disbursed up to date.

Counterpart funds promised by counties:Fanxian disbursed 2 million RMB for Fanxian Subproject in addition to 0.5 million RMB, with 2.5 million RMB available at present.

2.2 Compensation Rates and Payments

Compensation for the 3 subprojects covers permanent land use, temporary land use, roads, land restoration, appurtenances, housings, and special facilities. Different rates and suitable forms are provided by the local government according to different local economic levels. By the time of this report, 23.99 million RMB counterpart funds have been paid to households in full according to the applicable rates, an additional amount of 6.2562 million RMB since the last M&E. Refer to Tables 3-1 and 3-2 for details.

The progress of payment can be summarized as follows:

Miaozhai: Since the last M&E, an additional amount of 10.7 million RMB has been paid for young crops in Mayezhuang and Gaozhuang at the rate of 300 RMB/mu for wheat and 200 RMB/mu for autumn crops. Land use for pipes is compensated at the rate of 500 RMB/mu/year according to the duration of use, and housings are compensated for according

Page 170: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

157

to the quality and quantity, with a total amount of 12.34 million RMB, the same as reflected in the last report.

Wuqiu: The progress of payment is the same as reported last time. Compensations are paid for appurtenances only, not for young crops. Temporary land use of pipes is compensated at the rate of 500 RMB/mu/year according to the duration of occupation, while that for pumping works is paid as agreed according to the depth, with a lump sum of 4,000 or 5,100 RMB/mu. A total amount of 1.2794 million has been paid.

Fanxian: There is no change except that an additional amount of 54,400 RMB has been paid for the land use of service roads at the same rate of permanent land use. Young crops affected by the land use of village platforms and treading activities are compensated at the rate of 350 RMB/mu until land adjustment or land restoration, and those by excavation works are paid at the rate of 600 RMB/mu until land restoration. In addition, 10 and 50 RMB/mu is paid to townships and villages for their cooperation and 200 RMB/mu to households as award for their clearing efforts and 300/room RMB for housing relocation. The total amount is 2.0063 million RMB, including appurtenances.

Dongming: Compensation rates include 600 RMB/mu for the permanent land use of village platforms and temporary land use of treading, and 10,000 RMB/mu for the permanent land use of the escape road for the north platform. Land use for village platforms is compensated on the basis of different impacts and benefits until the achievement of the achievement of land adjustment. Land use for treading is paid according to the duration of occupation. A lump sum of 1,005 RMB/mu is paid for the temporary land use of excavation works and 3,000-9,050 RMB/mu for pumping works as agreed according to the depth. The compensation rates for housings are used as published in the Government Notice, with 220 RMB/m2 for brick-concrete, 160 RMB/m2 for brick-timber, 120 RMB/m2 for brick-earth, 80 RMB/m2 for earth-timber, and 50 RMB/m2 for simple structures. An additional amount of 1.3526 million RMB has been paid for young crops and 15.19 million RMB for housings since the last M&E, with a sum of 2.8812 million RMB and 0.2993 million RMB respectively. Plus the payment for appurtenances, the cumulative amount of payment for Dongming is 11.2 million RMB.

Pingyin: Different rates are applied according to the season and output value, in the range of 400, 500 and 650 RMB/mu, with the term fixed in accordance with the degree of difficulty in land adjustment. Housings are compensated according to their different types, with 500-1,500 RMB/room for main rooms, 400-700 RMB/room for side rooms, 200-300 RMB/room for simple rooms, and 200-300 RMB/room for simple sheds. Since an additional amount of 3.4184 million RMB paid since the last M&E, the cumulative payment amounts to 9.2739 million RMB.

Page 171: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

158

Table 3-1 Compensation for Village Platform Subprojects Permanent Temporary Appurtenance House

Rate Rate No. Subproject Village Moved

Affected Village Rate Amount Treading Excavation Pumping Amount Tree Well Tomb Amount Rate Amount

Land Use for Roads

Special Facility Restoration Other1 Total

Unit RMB/ mu/season RMB RMB/mu

/year RMB/mu RMB/mu per year RMB RMB RMB RMB RMB RMB/m2 RMB RMB RMB RMB RMB RMB

Total 40 37 4015475 7221756 1251304 480902 95000 288900 190920 10445807 23990046 Mayezhuang Mayezhuang 300 56994 38000 78753 135747 Gaozhuang Gaozhuang 300,200 50000 500 20976 4470 10300 81276 Heluzhuang Heluzhuang 500 13352 13352

Miaozhai

Weizhai 1

Subtotal 4 3 106994 34328 89053 230375

Tanqiu Tanqiu 5005000,

500 200 57092.6

11000,12000,20000

23000 80092.6

Jingzhai Jingzhai 500 26400 5000 200 47289.6 4800,3600 28400 102089.6 Sanyi Sanyi 500 4500 200 111800 2000 9000 190920 316220 Shangzhai 300 4000 101000 101000

Wuqiu

Yuzhai 5100 680034 680034

2

Subtotal 3 5 811934 216182 60400 190920 1279436.2 Luji Luji 610、350 648509 150、200 47002 300 32100 727611 Caozhuang Caozhuang 610、350 171811 150、200 14800 186611 Baizhuang Baizhuang 610、350 21859 860、600 5738 150、200 8750 36346.5 Qianwanglou Qianwanglou 610、350 51503 150、200 1450 52953 Beiyang Wanggeng 0 Zhangdouhuan Houshi Malukou Sunlou 610、350 124267 150、200 13500 137767 Dingzhuang 610、350 1516 1516 Qianshi 860、600 133590 133590 Xiwuzhuang 860、600 29813 29813 Dingshiwang 860、600 51772 51772 Shidamiao 860、600 396551 396551

Fanxian

Others 7804 610 244000 251804

3

Subtotal 9 10 1027269 861464 85502 32100 0 2006335

Page 172: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

159

Table 3-2 Compensation for Village Platform Subprojects Permanent Temporary Appurtenance House

Rate Rate No. Subproject Village Moved Affected Village Rate AmountTreading Excavation Pumping

AmountTree Well Tomb

Amount Rate Amount

Land Use For Roads

Special Facility Restoration Others1 Total

Unit RMB/mu /season RMB RMB/mu

/year RMB/mu RMB/mu /year RMB RMB RMB RMB RMB RMB/m2 RMB RMB RMB RMB RMB RMB

Qianzhaizhuang Qianzhaizhuang 650 1153185 650 1005 183535 1171907 1336720 650 341830 650 178062 519892 Houzhaizhuang Houzhaizhuang

0 Xindianji 0 Yangzhuang 0 Guanzhai 0 Linkou

650

0 Maozhuang Maozhuang 650 441035 650 315370 756405 Dongzhulin Dongzhulin 650 199594 650 62080 261674 Xizhulin Xizhulin 650 413475 650 71650 485125 Xinliuxiang Xinliuxiang 650 332074.5 25960 358034.5 Laoliuxiang 0 Changxing tree farm 14102 14102 Changxing brick kiln 56000 56000 Others2 3000-9050 42861

299349 95000 288900

42861

Dongming

Others 5514030

Brick-concrete: 220 RMB/m2, Brick-timber: 160 RMB/m2, Brick-earth-timber: 120 RMB/m2, Earth-timber: 80 RMB/m2, Simple: 50 RMB/m2

299349 95000 288900 1171907 7369186

4

Subtotal 11 6 2881194 5514030 949620 299349 95000 288900 0 1171907 11200000 Liuzhuang Liuzhuang Xiaoliuhe Xiaoliuhe Tieyang Tieyang Suqiao Suqiao

400, 500, 650

Dahekou Wangxiaozhuang Wangxiaozhuang Dingkou Dingkou Houzhai Houzhai Lingzhuang Lingzhuang Qianzhai Qianruan’er Qianruan’er Xinboshi Xinboshi Laoboshi Laoboshi

Pingyin

Liuhequan Liuhequan

400, 500, 650

5855500 5855500 5

Subtotal 13 13

Main house: 500-1500 RMB/room, side house: 400-700 RMB/room, simple house and shed: 200-300 RMB/room

5855500 Notes: 1. Others1 and Others2 from some subprojects are not provided by items and villages.

Page 173: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

160

3. LAND ACQUISITION AND ECONOMIC REHABILITATION

3.1 Permanent Land Acquisition

According to RP, the 13 village platforms would resettle 37065 people of 9028 households in 40 villages (in base year). As of this report, 4652.95 mu land acquisition involving 37 villages has been implemented, the same as achieved by the time of the last M&E. Refer to Table 4.

Table 4 Permanent and Temporary Land Use Permanent Land Use Temporary Land Use

RP Completed Restored

No. Subproject Village Moved Affected Village Home People

PlannedSubtotal

Village Platform

Service/Escape Road

Planned Completed To Be

Restored Area %

Unit mu mu mu mu mu mu mu mu % Total 40 37 9028 37065 4679.51 4652.95 4580.12 72.829 9070.73 5475.55 5231.55 3535.87 68

Mayezhuang Mayezhuang 435 1954 269.01 206.18 189.98 488.9 257.66 257.66 0

Gaozhuang Gaozhuang 147 652 103.69 217.05 217.05 48.2 116.18 116.18 26.22 23 Heluzhuang Heluzhuang 198 910 156.96 147 147

16.2

49.3 150.49 150.49 16.69 11 Weizhai 110 472 102.3 0 791.9 54 54 0

Sujiucheng 0.19 1.2

Miaozhai

Others 2.21 42.8

1

Subtotal 4 3 890 3988 634.36 570.23 554.03 16.2 1422.3 578.33 578.33 42.91 7

Tanqiu Tanqiu 452 1983 254.07 206.07 206.07 46.1 398.6 398.6 33.6 8

Jingzhai Jingzhai 297 952 128.03 162.72 162.72 28.5 100 100 20 20

Others 417.6 Sanyi Sanyi 432 1716 215.28 223.02 223.02 240.1 9 9 9 100

Others 26.7 Shangzhai 53 53 30 0

Wuqiu

Yuzhai 133.34 133.34 0

2

Subtotal 3 5 1181 4651 597.38 591.81 591.81 759 693.94 693.94 92.6 13

Luji Luji 792 2646 290.7 677.875 675.53 2.345 28.28

Caozhuang Caozhuang 166 790 99.5 184.754 178.97 5.784 28.67

Baizhuang Baizhuang 356 1576 173.1 22.77 22.77 19.96 3.93 3.93 0

Qianwanglou Qianwanglou 100 465 69.9 53.65 20.15 33.5 7

Beiyangcun 115 554 60.8 0 6.85

Wanggengbai 177 594 65.3 0 0

Zhangdouhai 159 730 94.1 0 11.6

Houshi 154 729 80.1 0 19.98

Malukou 159 620 68.2 0 18.48

Sunlou 128.82 113.82 15

Dingzhuang 1.58 1.58

Qianshi 0 91.5 91.5 0

Xiwuzhuang 0 20.42 20.42 0

Dingshiwang 0 35.46 35.46 0

Shidamiao 0 271.61 271.61 0

Fanxian

Others 0 2726.75 400 400 400 100

3

Subtotal 9 10 2178 8704 1001.766 1069.45 1012.82 56.629 2867.57 822.92 822.92 400 49

Qianzhaizhuang Qianzhaizhuang 335 1576 170.99 408 408 98.5 154.9 154.9 154.9 100

Houzhaizhuang Houzhaizhuang 103 434 47.08 54.3 54.3 35.8 151.3 151.3 151.3 100

Xindianji 141 600 65.14 0 52.4 0 0

Yangzhuang 204 731 79.28 0 32.1 0 0

Guanzhai 92 427 46.33 0 18.7 0 0

Linkou 90 432 46.86 0 18.9 0 0

Others 5.91 0 395.8 Maozhuang Maozhuang 301 1117 123.31 216 216 69.8 290 290 290 100

Dongzhulin Dongzhulin 326 1370 153.02 68.7 68.7 59.1 222 222 179 81

4 Dongming

Xizhulin Xizhulin 225 968 109.17 214.5 214.5 60.8 158 158 158 100

Page 174: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

161

Xinliuxiang Xinliuxiang 313 1276 135.53 94.3 94.3 62.2 0 0

Laoliuxiang 167 663 70.42 0 31.3 0 0

Yaochang 0 241 93 0

Linchang 0 231 135 135 100

Others 27.3 0 1154.3 0 0

Subtotal 11 6 2297 9594 1080.35 1055.8 1055.8 0 2089.7 1448.2 1204.2 1068.2 89

Liuzhuang Liuzhuang 63 256 31.83 392.14 49.73 49.73 49.73 49.73 100

Xiaohekou Xiaohekou 179 780 97.06 151.49 151.49 151.49 151.49 100 Tieyang Tieyang 147 598 74.5 116.13 116.13 116.13 116.13 100 Suqiao Suqiao 267 1145 142.54 222.39 222.39 222.39 222.39 100 Dahekou 81 371 46.21

392.14

72.06 72.06 72.06 72.06 100 Wangxiaozhuang Wangxiaozhuang 247 992 153.64 331.24 180.8 180.8 180.8 180.8 100

Dingkou Dingkou 412 1676 177.6331.24

301.42 301.42 301.42 301.42 100 Houzhai Houzhai 229 906 145.11 145.11 145.11 235.24 235.24 235.24 235.24 100

Lingzhuang Lingzhuang 93 379 79.45 79.45 157.65 157.65 157.65 157.65 100

Qianzhai 79.45

Qianruan’er Qianruan’er 469 1833 229.22 229.22 229.22 180.88 180.88 180.88 180.88 100

Xinboshi Xinboshi 100

Laoboshi Laoboshi 202 815 117.11 117.11 117.11 83.69 83.69 83.69 83.69

Pingyin

Liuhequan Liuhequan 93 377 71.39 71.39 71.39 180.7 180.7 180.7 180.7 100

5

Subtotal 13 13 2482 10128 1365.666 1365.66 1365.66 0 1932.16 1932.16 1932.16 1932.16 100

Note: Permanent land use includes service and escape roads.

3.2 Temporary Land Occupation and Restoration

No change has taken place in the aspect of temporary land use and restoration since the last M&E. The completed area is 5475.55 mu, mainly including 3681.89 mu for excavation and 1793.66 for treading. The restored land is 3535.87 mu, taking up 68% of the total to be restored. The remaining area of 1695.68 mu includes 82.8% fresh floodland, which will be silted up and restored naturally by the Yellow River.

By the time of this report, the floodland with a pumping depth of 6—8 m in Miaozhai and Wuqiu has not been restored. In Fanxian, 400 mu for treading has been restored totally, and the fresh floodland for pumping has been silted up when flooded. In Dongming, 646.2 mu for treading and 422 mu for excavation have been restored, excluding the brick kiln, tree farm and hold village platform which are not necessary to be restored, and the land for pumping has not be restored yet. In Pingyin, the land for temporary use has been totally restored. Refer to Table 5.

Table 5 Progress of Land Restoration

Completed Temporary Land OccupationRestored Not Restored

No. Subproject Township

& Village Subtotal Excavation Pumping Treading

Depth Of

Excavation

To Be

RestoredArea % Subtotal

Fresh

Floodland

Unit mu mu mu mu m mu mu mu mu %

1 Miaozhai 3 578.33 535.42 42.91 6--8 578.33 42.91 7 535.42 535.42 100

2 Wuqiu 5 693.94 601.34 92.6 6--9 693.94 92.6 13 601.34 445 74

3 Fanxian 14 822.92 422.92 400 7--8 822.92 400 49 422.92 422.92 100

4 Dongming 7 1448.2 422 380 646.2 1--6 1204.2 1068.2 89 136

5 Pingyin 13 1932.16 1320.21 611.95 1--2 1932.16 1932.16 100

Total 42 5475.55 1742.21 1939.68 1793.66 5231.55 3535.87 68 1695.68 1403.34 83

Page 175: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

162

3.3 Economic Rehabilitation

Economic rehabilitation is mainly achieved by land adjustment. Details on land adjustment are as follows:

(1) Among the 40 villages moved, 12 not involved in land acquisition need to give farmland;

(2) Among the 37 villages involved in land acquisition (including 9 not to be resettled), 7 are almost balanced between the benefits and impacts of land acquisition, without needing land adjustment between villages, but needing adjustment between and within groups;

(3) The 6 villages involved only in temporary land acquisition do not need any form of land adjustment after having received compensations;

(4) There are 36 villages (36=12+37-7-6) needing land adjustment between villages, and 43 (43=12+37-6) needing land adjustment between and within groups;

(5) By the time of this report,

a. Of the 36 villages needing village-to-village land adjustment, 19 have done (53%), one more since the last M&E, but the others have not (47%), including 4 having reached an initial intention;

b. Among the 43 villages needing adjustment between and within groups, 26 have adjusted between groups (60%), the same progress as achieved by the time of the last M&E, and 26 villages adjusted within groups (60%), one more than the figure reported last time. Refer to Table 6 for details.

Land adjustment:

In Miaozhai, 3 villages including Mayezhuang, Gaozhuang and Heluzhuang are involved in permanent land acquisition, and land adjustment is needed between 4 villages. At present, village-to-village adjustment has been finished, and adjustment within groups of Mayezhuang, Gaozhuang and Heluzhuang has been finished also. With Miaozhai Township Government’s coordination and a compensation for young crops for 4 seasons, Gaozhuang has agreed to accept the 121 mu farmland which the village was previously unwilling to accept. But the land has not been accepted by the time of this M&E. Gaozhuang has provided farmers with flour as compensation paid for young crops.

In Wuqiu, land adjustment between and within groups has been finished in Tanqiu, Jingzhai and Sanyi.

In Fanxian, altogether 11 villages are in need of land adjustment, including Luji, Caozhuang, Baizhuang, Qianwangzhuang, Beiyangcun, Wanggengbai, Zhangdouhai, Houshi, Malukou, Sunlou and Dingzhuang. By the time of this report, because of villagers’ worry about the loss due to difficulties in replacing the old village platform by farmland, village-to-village and group-to-group land adjustment has not been implemented, though the county and township governments have coordinated.

Page 176: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

163

Table 6 Land Acquisition and Economic Rehabilitation

RP Village-Village Adjustment

Group-Group Adjustment

Adjustment Within Group No. Subproject Village moved Village involved

Household People

PermanentLand Use

Unit mu Done Undone Done Undone Done Undone

Total 40 37 9028 37065 4652.95 19 17 26 17 26 17 Mayezhuang Mayezhuang 435 1954 √ √ √ Gaozhuang Gaozhuang 147 652 √ √ √ Heluzhuang Heluzhuang 198 910

570.23√ √ √

Miaozhai

Weizhai 110 472 √ √ √ 1

Subtotal 4 3 890 3988 570.23 4 3 1 3 1 Tanqiu Tanqiu 452 1983 √ √ √ Jingzhai Jingzhai 297 952 368.79 √ √ √ Sanyi Sanyi 432 1716 223.02 √ √ √ Shangzhai

Wuqiu

Yuzhai

2

Subtotal 3 5 1181 4651 591.81 3 3 3 Luji Luji 792 2646 677.875 √ √ √ Caozhuang Caozhuang 166 790 184.754 √ √ √ Baizhuang Baizhuang 356 1576 22.77 √ √ √ Qianwanglou Qianwanglou 100 465 53.65 √ √ √ Beiyangcun 115 554 √ √ √ Wanggengbai 177 594 √ √ √ Zhangdouhai 159 730 √ √ √ Houshi 154 729 √ √ √ Malukou 159 620 √ √ √ Sunlou 128.82 √ √ √ Dingzhuang 1.58 √ √ √ Qianshi Xiwuzhuang Dingshiwang Shidamiao

Fanxian

Others

3

Subtotal 9 10 2178 8704 1069.45 11 11 11 Qianzhaizhuang Qianzhaizhuang 335 1576 √ √ √ Houzhaizhuang Houzhaizhuang 103 434 √ √ √ Xindianji 141 600

462.3√ √ √

Yangzhuang 204 731 √ √ √ Guanzhai 92 427 √ √ √ Linkou 90 432 √ √ √ Maozhuang Maozhuang 301 1117 √ √ √ Dongzhulin Dongzhulin 326 1370 √ √ √ Xizhulin Xizhulin 225 968 √ √ √ Xinliuxiang Xinliuxiang 313 1276

593.5

√ √ √ Laoliuxiang 167 663 √ √ √

4 Dongming

Others Subtotal 11 6 2297 9594 1055.8 6 5 7 4 7 4

Liuzhuang Liuzhuang 63 256 √ √ √ Xiaohekou Xiaohekou 179 780 √ √ √ Tieyang Tieyang 147 598 √ √ √ Suqiao Suqiao 267 1145

392.14

√ √ √ Dahekou 81 371 √ √ √ Wangxiaozhuang Wangxiaozhuang 247 992 √ √ Dingkou Dingkou 412 1676 331.24

√ √ Houzhai Houzhai 229 906 145.11 √ √ Lingzhuang Lingzhuang 93 379 √ √ √ Qianzhai

79.45 √ √ √ Qianruan’er Qianruan’er 469 1833 229.22 √ √ Xinboshi Xinboshi √ √ Laoboshi Laoboshi

202 815 117.11 √ √

Pingyin

Liuhequan Liuhequan 93 377 71.39 √ √

5

Subtotal 13 13 2482 10128 1365.66 6 1 13 1 13 1

Page 177: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

164

In Dongming, village-to-village and group-to-group land adjustment has been finished in and between Qianzhaizhuang, Houzhaizhuang, Xindianji, Yangzhuang, Guanzhai and Linkou villages involved in the south village platform. The quantity of village-to-village land adjustment between Maozhuang, Dongzhulin, Xizhulin, Xinliuxiang and Laoliuxiang villages involved in the north village platform has been fixed but not implemented yet, and except for Maozhuang, the other 4 haven’t finished adjustment within groups due to the farmers’ lack of confidence in replacing the old village platform by farmland.

In Pingyin, Lingzhuang and Dong’e village platforms are in the need of village-to-village land adjustment. By the time of this report, adjustment between and within villages for Lingzhuang village platform has been finished. Liuzhuang, Xiaohekou, Tieyang and Suqiao villages are in the need of village-to-village land adjustment for Dong’e village platform. Liuzhuang has accepted the farmland given by Tieyang and Suqiao and allocated it to households. As the land contract hasn’t expired, Xiaohekou has not given the farmland to Liuzhuang as planned. With the township government’s coordination, however, Xiaohekou has promised to compensate Liuzhuang for young crops until the transfer of land. Land adjustment between and within groups for the other village platforms has been finished.

4. INCOMES OF AFFECTED PEOPLE 4.1 Income Recovery

This M&E includes a survey of 70 households and 354 people regarding the recovery of incomes, impacts by land acquisition and remedy measures for income recovery, including 9 households in Miaozhai, 17 in Wuqiu, 14 in Fanxian, 18 in Dongming and 12 in Pingyin.

These sample households had an overall per capita income of 1,650 RMB in 2006, 390 RMB more than the figure of 1,260 in the base year, specifically including 1,144 RMB in Miaozhai, 2,094 RMB in Wuqiu, 1,290 RMB in Fanxian, 1,941 RMB in Dongming and 1,471 RMB in Pingyin, respectively 129 RMB, 152 RMB, 488 RMB, 885 RMB and 89 RMB more than in the base year. Generally, there was a tendency toward increase. The structure of incomes was not quite different, but the percentage of constituents was rather different (refer to Charts 1 and 2). In Fanxian and Dongming, there was a higher growth rate of the absolute value mainly because of more time for farmer workers due to farmland reduction and subsequently considerable increase in the income from sideline activities. In Fanxian, the income of farmer workers was 22% more regardless 18% reduction of farming incomes. With the percentage of farming income maintained consistent, the income of farmer workers was increased by 37% in Dongming, causing a considerable increase in the total per capita income. With a negative increase in this source of income in Miaozhai and minor increase in Wuqiu and Pingyin, 7% and 5% respectively, the growth of per capita income was relatively less. As judged from this, farmer workers made a great contribution to the growth of family incomes. Refer to Table 7.

Page 178: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

165

020406080

100

Miao

zhai

Wuqi

u

Fanx

i an

Dong

ming

Ping

yin

Far mi ngSi del i neOt her s

020406080

100

Miao

zhai

Wuqi

u

Fanx

i an

Dong

ming

Ping

yin

Far mi ngSi del i nOt her s

Chart 1 Incomes by Sectors in Base Year Chart 2 Incomes by Sectors in 2006

Table 7 Incomes of Sample Households Farming Sideline Others

Subtotal Farmer Worker Subproject Year Household People

Per Capita Income Income %

Income % Income % Income %

Unit home person RMB RMB % RMB % RMB % RMB % Base year 9 55 1015 368 36 636 63 491 48 11 12006 9 55 1144 502 44 605 53 451 39 37 3Miaozhai Change 0 0 129 134 8 -31 -10 -40 -9 26 2Base year 17 87 1942 494 25 1372 71 427 22 76 42006 17 87 2094 620 30 1374 66 609 29 100 5Wuqiu Change 0 0 152 126 5 2 -5 182 7 24 1Base year 14 70 802 223 28 579 72 236 29 2006 14 69 1290 131 10 1153 89 664 51 6Fanxian Change 0 -1 488 -92 -18 574 17 428 22 6Base year 18 91 1056 489 46 567 54 103 10 2006 18 96 1941 904 47 962 50 913 47 75 3Dongming Change 0 5 885 415 0 395 -4 810 37 75 3Base year 12 48 1382 610 44 703 51 703 51 69 52006 12 47 1471 461 31 837 57 816 55 173 12Pingyin Change 0 -1 89 -149 -13 134 6 113 4 104 7Base year 70 351 1260 436 35 795 63 348 28 29 22006 70 354 1650 560 34 1016 62 708 43 74 4Total Change 0 3 390 124 -1 221 -1 360 15 45 2

4.2 Implication of Income Changes

The M&E has traced the poverty situation of sample households according to the national standard, with 2004 used as the base year for Wuqiu (Sanyi Village) and Pingyin and 2003 for the other subprojects. Table 8 provides the statistics of absolute values according to different standards in different years, excluding price indexes. The findings indicate 13% reduction of poor people, 11% increase of non-poor people and general growth of income levels.

Table 7 Income Levels of Sample Households

Base Year (2003, 2004) Follow-up Year (2006) Change Subproject Absolutely

Poor Low-income Non-poor

Absolutely Poor

Low-income Non-poorAbsolutely

Poor Low-income Non-poor

Miaozhai 42 7 51 29 13 58 -13 6 7Wuqiu 24 10 66 17 83 -7 -10 17Fanxian 29 71 10 16 74 -19 16 3Dongming 28 24 48 4 21 75 -24 -3 27Pingyin 25 75 6 21 72 6 4 3Total 26 12 62 13 14 73 -13 2 11

Page 179: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

166

4.3 Income Recovery of Affected People

To have a better understanding of the impacts on production/livelihood, 81 households have been interviewed regarding: (1) impact of farmland reduction, (2) use of land compensation, and (3) remedy measures for income recovery.

As shown by the findings, with regard to the impact of farmland reduction, 29% people have other incomes to offset their loss of farming income, without any major impacts on their total incomes, while 25% and 22% have lost less land or interior land, with any major impacts on their total incomes either. Only 20% believe their family incomes are affected as a result of farmland reduction. Compensations are used to cover daily expenses, children’s tuitions and medical fees by 65% and develop farming and sideline activities by 35%. The findings do not indicate that the use of compensations has greatly promoted the sustainable growth of family incomes, so more will be done to initiate the effective use of compensations. Regarding the aspect of remedy measures for income recovery (no investigation data from Miaozhai where compensation for young crops is involved only, without land compensation), 55% people offset their income loss due to farmland reduction by working as farmer workers and 15% by doing small business, whilst 16% do not care at all. To put in another way, 60% are active in coping with farmland reduction.

Table 9 Questionnaire for Income Recovery

Total Miaozhai Wuqiu Fanxian Dongming PingyinNo. Item

Yes % Yes % Yes % Yes % Yes % Yes %I Impact by farmland reduction 81 100 17 100 19 100 15 100 18 100 12 100

1 Less income from farming, but more from other sources, without any impact on total income

23 29 6 35 12 63 4 27 1 8

2 Minor impact due to less land loss 20 25 5 29 4 21 1 7 8 44 2 17 3 Minor impact due to poor land quality 18 22 3 18 3 16 3 20 5 28 4 334 Major impact 19 23 3 18 7 46 4 22 5 42 5 Others 1 1 1 6 II Use of land compensations 45 100 15 100 18 100 12 1001 Farming 10 22 4 27 4 22 2 17 2 Business 6 13 6 40 0 0 3 Housing 0 0 0 0 0 4 Medical fees, tuitions and other living expenses 29 65 5 33 14 78 10 83 5 Debit repayment 6 Others

III Remedy measures 81 100 17 100 19 100 15 100 18 100 12 1001 Farmer worker 45 55 7 41 12 63 8 53 11 61 7 58 2 Business 12 15 2 12 2 11 7 47 0 1 8 3 Cropping, animal raising or plastic tunnel 0 0 0 0 0 0 0 4 Extensive farming and intercropping 0 0 0 0 0 0 0 5 Reclamation or cultivating others’ land 0 0 0 0 0 0 0 6 Trust to luck 13 16 2 12 0 0 7 39 4 347 Others 11 14 6 35 5 26 0 0 0

Page 180: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

167

5. PHYSICAL RELOCATION AND RESETTLEMENT

5.1 Overall Planning of Village Resettlement

Resettlement plans have been prepared for all the 5 subprojects. As entrusted by Changyuan County Government, Hebi Institute of Urban Planning & Design has prepared an overall planning of new Miaozhai and Wuqiu. Entrusted by Fanxian County Government, the Architectural Design Institute of China Global Company has designed the “Planning of Village and Township Construction in Luji Village Platform”. Dongming County Government has completed the “Implementation Scheme for the Planning of Dongming Subproject”. In Pingyin, a “Resettlement Plan of Village Platform” has been worked out for Dong’e village platform.

5.2 Physical Relocation

Miaozhai, Wuqiu, Dongming and Pingyin necessitate the relocation of 71 households in 2 villages. As of this report, these households have been all moved and resettled in different modes, including 48 renting houses, 7 borrowing houses, 15 building temporary houses and 1 living in an old house.

This total number of 71 households includes 58 in Pingyin, i.e. 82%, which is the focus of M&E. Among the 58 affected households, 12 live in the temporary dwellings in the farmland identified as temporary residential and stockpile areas east of the village and 46 rent houses in 10 adjacent villages. In order to enable resettlement as soon as possible, while providing economic compensations (refer to Report No.4 for details), Dong’e Township Government has also made a “Resettlement Plan” for 58 households, providing the scope and method of homestead identification, rate of housing allowance, and schedule of housing. To encourage the villagers to build new houses without delay, this plan provides a subsidy of 2,000 RMB for each household that will have completed housing by the end of June 2007. As of this M&E, 22 of these households have started housing in the new platform, including 16 having completed house foundations and received housing subsidies paid on the basis of schedule.

Table 10 Progress of Physical Relocation and Housing Restoration Relocation Homestead Identification Housing Resettlement

Home Planned No. Subproject M&E Village

Planned Moved Subtotal Done Undone

Not

needed

Sub-

totalBuilt

Being

Built

Ready

To Act

Sub-

totalNew Buy Borrow Rent Temporary Old

This Report 2 2 2 2 2 1 1 1 Miaozhai

Last Report 2 2 2 2 2 1 1 This Report 3 6 6 6 6 1 2 2 1

2 Wuqiu Last Report 3 6 4 6 6 1 2 2 1This Report 1 5 5 5 5 5 5

3 Dongming Last Report 1 5 5 5 5 5 5 This Report 1 58 58 34 34 24 34 12 22 58 46 12

4 Pingyin Last Report 1 58 58 12 12 46 12 12 58 46 12

Total of this report 7 71 71 39 34 5 32 34 12 22 71 7 48 15 1Total of last report 7 71 69 17 12 5 54 12 12 71 7 48 15 1Total

Change 2 22 22 0 22 22 22

Page 181: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

168

6. PROTECTION OF RIGHTS AND INTERESTS

6.1 Vulnerable Groups

The M&E includes high attention to the affected vulnerable. According to the investigation, no case-specific preferential policies are provided, but the vulnerable groups enjoy the same rights as the other villagers in compensation and land adjustment.

Local governments promise to solve the relocation of poverty-stricken families by using local counterpart funds, mainly including financial support for or assistance in housing.

6.2 Willingness to Move

As shown by our follow-up monitoring of 82 people involved in the 5 subprojects in respect of their willingness to move, 98% say yes, somewhat higher than 88% reported last time. Generally, there is a stable and better willingness to move (refer to Table 8). In Dongming, the percentage of yes is 50%, greatly higher than that reported land time, reflecting the eager to move and initiative in financing. As investigated, 82% households are unable to complete housing within 2 years after the completion of village platforms, largely because they are (1) unable to afford a new house, or unable to afford another house after having built one recently, (2) hoping for government subsidy for housing by saying “No”, and (3) waiting to see.

7. EVALUATION AND RECOMMENDATION

7.1 Evaluation

(1) Compensation rates and disbursement/payment

The local government has promised to pay various compensations out of the local counterpart funds. Although different compensation rates and forms are used for different subprojects, compensations are paid at established rates. As of this report, 36.50 million RMB has been disbursed, including 23.99 million RMB paid for appurtenances, young crops, housings and special facilities. The outstanding amounts are in the progress of payment and partly retained the purpose of infrastructure construction and physical relocation.

(2) Permanent land acquisition and economic rehabilitation.

A total land area of 4652.95 mu has been acquired for the permanent use of village platforms, without any change since the last M&E. According to the balance between relocation benefit and effect of land acquisition, 53% villages have finished village-to-village land adjustment, 60% implemented group-to-group land adjustment and 60% implemented adjustment within groups.

(3) Temporary land occupation and restoration.

The temporary land acquisition is 5475.55 mu, of which 3535.87 mu has been restored (68% of 5231.55 mu to be restored), mainly in Miaozhai and Wuqiu. The farmland for pipes in Fanxian, pipes and excavation works in Dongming and temporary purposes in Pingyin has been totally restored.

Page 182: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

169

Table 8 Questionnaire for Willingness to Move

Willing to move? Able to complete housing within 2 years after completion of village platform?

Yes No Yes No No. Subproject M&E Subtotal People % People % Subtotal People % People %

Baseline survey 90 86 96 4 4 1st M&E1 38 38 100 38 4 11 34 892nd M&E 40 40 100 40 5 13 35 873rd M&E 37 34 92 3 8 37 37 1004th M&E 18 18 100 18 1 6 17 945th M&E 50 50 100 50 50 1006th M&E 37 37 100 37 37 100

1 Miaozhai

7th M&E 20 20 100 20 2 10 18 90Baseline survey 117 101 86 16 14 1st M&E1 38 38 100 38 2 5 36 952nd M&E 59 48 81 11 19 59 4 7 55 933rd M&E 55 45 82 10 18 55 55 1004th M&E 38 31 82 7 18 38 1 3 37 975th M&E 31 31 100 31 31 1006th M&E 30 30 100 30 30 100

2 Wuqiu

7th M&E 17 16 94 1 6 17 17 100Baseline survey 217 215 99 2 1 1st M&E1 0 2nd M&E 0 3rd M&E 59 52 88 7 12 59 15 25 44 754th M&E 22 19 86 3 14 22 9 41 13 595th M&E 30 30 100 30 3 10 27 906th M&E 9 8 89 1 11 9 9 100

3 Fanxian

7th M&E 15 15 100 15 1 7 14 93Baseline survey 218 205 94 13 6 1st M&E1 0 2nd M&E 3rd M&E 4th M&E 19 18 95 1 5 19 4 21 15 795th M&E 6th M&E 16 2 12 14 88 16 16 100

4 Dongming

7th M&E 18 17 94 1 6 18 9 50 9 50Baseline survey 268 221 82 47 18 268 87 32 181 681st M&E1 2nd M&E 3rd M&E 156 105 67 51 33 156 16 10 140 904th M&E 63 51 81 12 19 63 9 14 54 865th M&E 197 163 83 34 17 197 33 17 164 836th M&E 58 55 95 3 5 58 19 33 39 67

5 Pingyin

7th M&E 12 12 100 12 3 25 9 75Baseline survey 910 828 91 82 9 268 87 32 181 68 1st M&E1 76 76 100 0 0 76 6 8 70 92 2nd M&E 99 88 89 11 11 99 9 9 90 91 3rd M&E 307 236 77 71 23 307 31 10 276 90 4th M&E 160 137 86 23 14 160 24 15 136 85 5th M&E 308 274 89 34 11 308 36 12 272 88 6th M&E 150 132 88 18 12 150 19 13 131 87 7th M&E 82 80 98 2 2 82 15 18 67 82

Total

Grand total 2092 1851 88 241 12 1450 227 16 1223 84

(4) Income recovery

According to survey results of 70 households and 354 people, there was a per capita income of 1,650 RMB in 2006, which was 390 RMB more than 1,260 in the base year, 13% decrease of poor population and 11% increase of non-poor people in comparison with the situation in the base year. There is a general growth of family incomes.

Page 183: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project Village Platform Subproject Resettlement M&E Report

170

(5) Physical relocation and housing restoration

All the 71 houses affected by permanent land use and construction drainage have been moved. Homesteads are needed for 39 households, including 34 having received homesteads, with 12 houses built and 22 being built. These 71 households have been resettled in different ways.

(5) Protection of rights and interests

Resettlement in new village platforms has not been started, but local governments promise to give help to poverty-stricken families during relocation period. Case-specific protection policies are not provided for vulnerable groups, such as families enjoying “five guarantees”, those with physical disabilities and women headed families, they enjoy the equal rights as others in the respect of compensation and resettlement.

Main works for village platforms are nearly completed, but infrastructures are not started. On the basis of the willingness to move, a high degree of difficulty is forecast in resettlement and housing.

7.2 Problems and Recommendations

(1) Economic rehabilitation. In Miaozhai, the dispute about land adjustment in Gaozhuang has been solved by the township government’s promising to compensate for young crops for 4 seasons and Gaozhuang’s agreeing to accept the farmland, but the land has not been accepted formally. In Fanxian and Dongming, land adjustment is still under discussion, mainly because of the villagers’ worry about great farmland loss caused by old village platforms’ uselessness after the transfer of farmland now on hand. However, they will be compensated for young crops prior to the achievement of land adjustment. In Pingyin, with township government’s coordination, the villages which ought to receive farmland will be compensated for young crops until the acceptance of farmland. Compensation for young crops has not been implemented. It is recommended that the county and township governments provide necessary measures for restoring old village platforms, to eliminate villagers’ worry.

(2) Construction drainage. The villagers of Tanqiu and Jingzhai have complained about farmland inundation and house cracking due to village platform scouring by rain. This problem is under discussion and treatment.

(3) Willingness to move. As shown by our follow-up monitoring in the respect of willingness to move, 97% say yes, but only 18% say yes in the respect of being able to build their houses in time. In the view of investigation indexes, the percentage is relatively low due to one reason or another, which is somewhat different from the project objectives. It is expected that facing a large scale of relocation, the local government put forward some feasible measures, especially preferential policies on funds, to encourage the completion of housing in time.

Page 184: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

171

-

ADB-loaned Yellow River Flood Management Sector Project

River Training

RESETTLEMENT M&E REPORT (Report No. 2)

Henan Huanghe Resettlement Economic Development Company

December 2007

Appendix 7

Page 185: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No.2)

172

Approved: Yang Jianshe

Reviewed: Zhang Hao, Zuo Ping

Task Manager: Zuo Ping

Team Leader: Jiao Lili

Chief Editor: Jiao Lili

Proofreader: Wang Jianzhong, Zhao Hua’e, Yang Tao

Contributors: Cao Jin, Li Yang, Jiao Lili, Shen Yanlong, Wang Jianzhong, Xue Changyu, Yang Jianshe, Yang Tao, Yu Lu, Zhang Hao, Duan Wei, Zuo Ping, Zhu Pengfei, Zhao Huan’e

Page 186: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No.2)

173

Table of Contents

1. GENERAL __________________________________________________________175

1.1 Subproject Brief_________________________________________________ 175

1.2 Land Acquisition and Resettlement_________________________________176

1.3 Monitoring and Evaluation _______________________________________ 177

1.3.1 Basis of M&E _____________________________________________177

1.3.2 Study Area and Focus _______________________________________178

1.3.3 Methodology ______________________________________________178

1.3.4 Selection of Samples________________________________________178

1.3.5 Time Schedule_____________________________________________178

2. DISBURSEMENT AND PAYMENT _____________________________________178

2.1 Process of Disbursement __________________________________________178

2.2 Compensation Rates _____________________________________________179

2.3 Disbursement and Payment _______________________________________179

3. LADN ACQUISITION AND RESETTLEMENT___________________________183

3.1 Permanent Land Acquisition and Economic Rehabilitation_____________ 184

3.1.1 Zhangwangzhuang _________________________________________184

3.1.2 Dong’an__________________________________________________184

3.1.3 Laotian’an ________________________________________________185

3.1.4 Wuzhuang ________________________________________________185

3.1.5 Mao’an __________________________________________________186

3.1.6 Shunhejie_________________________________________________187

3.1.7 Gucheng _________________________________________________187

3.1.8 Caogang__________________________________________________188

3.1.9 Taohuayu _________________________________________________188

3.1.10 Baohezhai ________________________________________________188

3.1.11 Zhaokou__________________________________________________188

3.1.12 Weitan ___________________________________________________189

3.1.13 Heigangkou _______________________________________________189

3.1.14 Fujunsi___________________________________________________190

3.1.15 Laozhaizhuang ____________________________________________190

3.2 Temporary Land Occupation and Restoration _______________________ 190

4. PHYSICAL RELOCATION AND ECONOMIC REHABILITATION _________192

Page 187: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No.2)

174

4.1 Compensation for Housings _______________________________________192

4.2 Restoration of Housing Conditions _________________________________192

5. REPLACEMENT OF SPECIAL FACILITIES ____________________________ 193

6. RECOVERY OF INCOMES ___________________________________________194

6.1 Land Acquisition and Impacts _____________________________________194

6.2 Impacts and Recovery of Incomes in Options A and C _________________ 195

6.3 Income Constituents and Changes of Sample Households in Option B____196

6.4 Implication of Income Changes in Option B__________________________ 198

7. PROTECTIN OF RIGHTS AND INTERESTS ____________________________200

7.1 Training _______________________________________________________200

7.2 Complaints Management _________________________________________200

7.3 Vulnerable Groups ______________________________________________ 201

8. EVALUATION AND RECOMMENDATIONS ____________________________201

Annex 1 Progress of Land Acquisition_________________________________203

Annex 2 Progress of Resettlement Compensation________________________ 205

Annex 3 Sample Inspection of Payments _______________________________ 207

Annex 4 Permanent Land Acquisition and Economic Rehabilitation _______ 209

Annex 5 Constituents and Changes of Incomes of Sample Households ______ 212

Page 188: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

175

1. GENERAL

1.1 Subproject Brief

River training includes 15 components, with 14 located in Henan Province and 1 in Shandong Province, involving 5 cities and 10 counties/districts: Wenxian and Wuzhi Counties of Jiaozuo City, Yuanyang and Fengqiu Counties of Xinxiang City, Huiji District, Zhongmou County and Xingyang of Zhengzhou City, Kaifeng Suburbs and Kaifeng County of Kaifeng City in Henan Province, and Juancheng County of Heze City in Shandong Province.

In July 2004, a “Resettlement Plan of Lower Yellow River Training Works” (referred to as the “Resettlement Plan” or “RP” for short hereinafter) was prepared by Henan Yellow River Reconnaissance and Design Institute. Subsequently, a “Special Report on Preliminary Design of Land Acquisition and Resettlement under Yellow River Training Works in Shandong” (referred to as “Special Report”) was prepared by Shandong Yellow River Reconnaissance and Design Institute in May 2005. A total budget of 465.31 million RMB has been approved by the State for river training works in both Henan and Shandong, and 15.59 million RMB by YRCC for land acquisition and resettlement, including 14.27 million RMB as direct costs.

As required by YRCC Project Office in letter No. [2006]01 “Request for Earliest Preparation of Resettlement Implementation Scheme”, the said design institutes have separately prepared “Special Report on Implementation Scheme of Land Acquisition and Resettlement in Jiaozuo River Training Works”, “Special Report on Implementation Scheme of Land Acquisition and Resettlement in Xinxiang River Training Works”, “Special Report on Implementation Scheme of Land Acquisition and Resettlement in Kaifeng River Training Works”, “Special Report on Implementation Scheme of Land Acquisition and Resettlement in Zhengzhou River Training Works” and “Implementation Scheme of Land Acquisition and Resettlement in Shandong Yellow River Training Works” (referred to as the “Implementation Scheme” or “IS” for short hereinafter). As entrusted by YRCC Project Office, Henan/Shandong Yellow River Bureau approved 15.2292 million RMB in the IS, including 13.9092 million RMB direct costs, respectively 360,800 and 360,800 RMB less than the original figures.

In the period of September to October 2007, an additional amount of 713,800 RMB was approved as direct costs by YRCC in letter Nos. [2007]70 “Approval of Additional Costs for Laotian’an River Training Works”, [2007]115 “Approval of Design Changes of Taohuayu River Training Works”, and [2007]124 “Approval of Design Changes of Dong’an and Zhangwangzhuang River Training Works”, including 197,800 RMB for Laotian’an, 100,500 RMB for Dong’an, 334,400 RMB for Zhangwangzhuang and 81,100 RMB for Taohuayu.

To sum up, a total budget of 15.943million RMB has been approved for land acquisition and resettlement, including 14.623 million RMB direct costs.

By the time of this M&E, main works for all these 15 components have been completed. Refer to Table 1-1 for a summary of these river training works.

Page 189: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

176

Table 1-1 Summary of River Training Works

Unit: 104 RMB Approved Resettlement Cost

Land Acquisition

Affected No. Component

Total Subtotal

Direct Cost

AdditionalDirect Cost

Land Acquisition

Direct Cost

Progress of Main Works

City, Province County

Total 46531 1559 1427 35.30 1594.3 1462.3 1 Zhangwangzhuang Completed Wenxian 2 Dong’an Completed3 Laotian’an

158 145 70.27 228.27 215.27Completed

Jiaozuo, Henan Wuzhi

4 Wuzhuang Completed5 Mao’an Completed

Yuanyang

6 Shunhejie Completed7 Gucheng Completed8 Caogang

589 539 -107 482 432

Completed

Xinxiang, Henan Fengqiu

9 Taohuayu Completed Xingyang, Henan Guangwu 10 Baohezhai Completed Huiji 11 Zhaokou Completed Zhongmou12 Weitan

372 343 26.11 398.11 369.11

CompletedZhengzhou, Henan

Zhongmou13 Heigangkou Completed Suburbs 14 Fujunsi

44560

64 59 2 66 61 Completed

Kaifeng, Henan Kaifeng

15 Laozhaizhuang 1971 376 341 43.92 419.92 384.92 Completed Heze, Shandong Juancheng

Note: The additional budget includes 2 part in the approved Scheme and design change respectively.

1.2 Land Acquisition and Resettlement

The city Yellow River engineering bureau acts as the Executive Agency of land acquisition and resettlement, to be responsible for resettlement management and coordination. In practice, the county/district Yellow River engineering bureaus are entrusted, in the form of notice of land acquisition on behalf, to contact with the local land management authorities and village committees, deal with land acquisition on behalf, compensation for temporary land use and other matters, and disburse resettlement funds as agreed. The Implementing Agency includes relevant county and township governments and village organizations, which are responsible for implementing resettlement. Henan/Shandong Yellow River Reconnaissance and Design Institute is employed as the Designer to be responsible for preparing resettlement plans, and Henan Huanghe Resettlement Economic Development Company as the Engineer to be in change of cost and schedule control during implementation. The resettlement management framework meets basically project management requirements and land resettlement demands.

The scope of work in resettlement mainly covers acquisition of land, relocation of housings, clearing of attachments and replacement of special facilities.

It is planned to acquire 9,123.35 mu for the 15 components, including 4,452.93 mu for permanent and 4,670.42 mu for temporary use, versus 7,755.15 mu, 3,637.18 mu and 4,117.97 mu in the IS. By the time of this report, a total land area of 2,802.76 mu has been acquired for permanent use, accounting for 63% of the RP, 77% of the IS and 96% of the agreement, involving 10 counties, 17 townships, 41 villages, 3 townships and a state-owned tree farm, and 3,703.85 mu for temporary use, taking up 79%, 90% and 100% respectively.

Page 190: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

177

Table 1-2 and Annex 1 show the progress of land acquisition.

Table 1-2 Progress of Land Acquisition Unit: mu

Permanent Land Acquisition State Total Subtotal Farmland Temporary Land

Occupation Remarks RP 9123.35 4452.93 396.94 4670.42 IS 7755.15 3637.18 352.1 4117.97 Agreed 6609.40 2919.31 3690.09 Completed 6506.65 2802.76 3703.89 % of RP 71 63 79 % of IS 84 77 90 % of agreed 98 96 100 Source: External Monitor.

Resettlement funds are disbursed by city Yellow River engineering bureaus to county/district bureaus for implementation, which is called “land acquisition on behalf”. The total amount of disbursement is 14.6271 million RMB.

Agreements for resettlement compensation have been signed for the 15 components, with a sum of 11.29968 million RMB, taking up 79% of the approved budget and 77% the total and “land acquisition on behalf”. The completed amount is 11.09978 million RMB (98% of the agreed amount), accounting for 78% and 76% respectively. Refer to Table 1-3.

Table 1-3 Progress of Resettlement Compensation

Unit: 104 RMB, %

No. Item Approved Total Acquisition on Behalf Agreed Completed Remarks

1 Permanent land use 265.47 243.153 243.153 2 Temporary land use 406.37 336.699 327.589 3 Land acquisition 135.40 73.8 73.8 4 Special facility 304.04 220.2 220.2 5 Attachment & others 351.43 256.116 245.236

Direct cost

1427 1462.23

1462.71 1129.968 1109.978 % of RP 79 78 % of IS 77 76 % of acquisition on behalf 77 76

Total

% of agreed 98 Source: External Monitor.

1.3 Monitoring and Evaluation

1.3.1 Basis of M&E

The basis of M&E mainly includes: (1) national and local law management laws/regulations and resettlement policies; (2) approved RP and IS; (3) ADB resettlement policies and M&E contracts between the External Monitor and YRCC Project Office.

Page 191: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

178

1.3.2 Study Area and Focus

This is the 2nd resettlement M&E of the 15 components. The study area M&S mainly covers the Employer, Implementing Agency, and relevant townships, villages and households, with the focus placed on: disbursement, payment, compensation rates, townships, villages, groups and households involved in permanent/temporary land use, including the percentage of lost land, economic rehabilitation measures, income recovery, temporary land occupation, land restoration, housing restoration, and training, etc.

1.3.3 Methodology

Get familiar with the state, local and ADB’s resettlement laws/regulations and policies, the resettlement plan and the TOR for M&E; discuss with the Yellow River engineering bureaus at all levels and the Implementing Agencies, for them to have an understanding of the purpose, scope of work and methodology of M&E, and the information and assistance expected of them; discuss with village/group leaders and villagers, explain to them M&E, inquire about resettlement, complete questionnaires, collect information as necessary; discuss with the responsible departments and persons of county/township governments and Yellow River engineering bureaus, feedback findings, and discuss relevant matters; process and analyze the findings from field work, and, on this basis, prepare M&E report.

1.3.4 Selection of Samples

The M&E has (i) completed an all-round census of affected 10 counties (city, 17 townships, 41 villages, 3 townships and 1 state-owned tree farm, (ii) interviewed with villages regarding income recovery in different modes of economic rehabilitation, and (iii) selected 25 sample households from 3 villages where there is a higher percentage of land loss and the mode of cash payment is adopted, including 1/3 from each of high, middle and low income levels, for the purpose of baseline census and follow-up monitoring.

1.3.5 Time Schedule

Field work was finished before September 30, with forms completed, data interpreted and M&E draft report prepared on this basis.

2. DISBURSEMENT AND PAYMENT

2.1 Process of Disbursement

Land acquisition: For collective land of villages and private land of households, agreements are signed between the county Yellow River bureau authorized as one party by the city bureau and the local township governments, villager committees or households as the other party, with compensations disbursed by the city bureau to villages and households directly on the basis of the approved budget, agreement and schedule. If industries are involved, agreements are signed between the county Yellow River bureau authorized by the city bureau as one party

Page 192: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

179

and enterprises as the other party, with compensations disbursed by the city bureau to the enterprises directly on the basis of the approved budget, agreement and schedule.

Attachments: Where private attachments are affected, agreements are signed between the city Yellow River bureau authorized by the city bureau as one party and township governments, villager committees or households as the other party, with compensations disbursed by the city bureau to households directly on the basis the approved budget, agreement and schedule. Where industries are affected, agreements are signed between the city Yellow River bureau authorized as one party by the city bureau and the enterprises as the other party, with compensations disbursed by the city bureau to enterprises directly according to the approved budget, agreement and schedule.

Special facilities: Agreements are signed between the city bureau and the owner or contractor of such facilities, and compensations disbursed by the city bureau to the owner or contractor directly according to the approved budget, agreement and schedule.

2.2 Compensation Rates

Permanent land use: According to the RP, floodland is acquired gratis for the use of spurs and protection works, while farmland, fishponds and nurseries are compensated at the rate of 690 RMB/mu (for young crops only), 2,800 RMB/mu and 1,500 RMB/mu respectively. In practice, compensation rates are used as fixed in the RP and IS except for Laozhaizhuang.

Temporary land use and restoration: Compensation rates are used as proposed in the RP and the IS. The rate for temporary land use is 759 RMB/mu for excavation and 690 RMB/mu for occupation respectively, and that for land restoration is 250 RMB/mu for excavation and 150 RMB/mu.

Housings and attachments: Housings and attachments, which are affected by Laozhaizhuang only, compensated at the rates published by the government.

Trees (except for weedtrees), butt wells and tombs: These are compensated at the rates fixed in the IS, and weedtrees and motor-pumped wells are compensated as priced in the RP and IS.

Special facilities: The rates for special facilities are as fixed in the IS except for low-pressure poles and gates, to which the rates set in the RP and IS are applied.

Table 2-1 contains a comparison of compensation rates.

2.3 Disbursement and Payment

By the time of this report, a cumulative amount of 11.29968 million RMB has been agreed and 11.09978 million RMB disbursed to affected counties, townships, villages, households and organizations, including 2.43153 million RMB for permanent land use, 3.27589 million RMB for temporary land use, 738,000 RMB for land restoration, 2.45236 million for attachments and others, and 2.202 million RMB for special facilities.

Page 193: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

180

In comparison the made progress by the time of the 1st M&E, there is an increase of 9.58723 million RMB in the agreed total amount and 9.89205 million RMB in the disbursed amount, with 1.736798 million RMB for permanent land use, 3.08159 million RMB for temporary land use, 738,000 RMB for land restoration, 2.13366 million RMB for attachments and others, and 2.202 million RMB for special facilities.

Refer to Table 2-2 for details.

Table 2-1 Comparison of Main Compensation Rates No. Item Unit RP IS Agreed Completed

I Permanent land use Spurs and protection works Floodland RMB/mu 690 690 Fishpond RMB/mu 2800 2800 Nursery RMB/mu 1500 1500

As fixed in RP and IS

II Temporary land use Excavation RMB/mu 759 759 Occupation RMB/mu 690 690 As fixed in RP and IS

III Housing Brick-concrete RMB/m2 260 260 Brick-timber RMB/m2 220 220 Temporary RMB/m2 65 65

As fixed in government notice

IV Attachment Brick fence RMB/m2 20 20 As fixed in RP and IS Butt well RMB/each 300 As fixed in IS Motor well RMB/each 3000 3000 As fixed in RP and IS Small motor well RMB/each 1000 1000

V Sparse tree Weedtree RMB/each 10 10 As fixed in RP and IS Sampling RMB/each 3 Small RMB/each 5 Medium RMB/each 15 Big RMB/each 30 Fruit RMB/each 100 25 Ligustrun lucidum Ait RMB/each 20 Flos Lonicerae RMB/each 30

VI Tomb 200 1000

As fixed in IS

VII Land restoration Excavation RMB/mu 250 250 Occupation RMB/mu 150 150 As fixed in RP and IS

VIII Others Low-voltage pole RMB/each 250 250 As fixed in RP and IS

High-voltage pole RMB/each 300/270 Telecom pole 220 Macadam road RMB/km 5000

As fixed in IS

Gate RMB/each 216.09 216.09 As fixed in RP and IS

Source: Resettlement Plan and Special Report.

Table 2-2 Progress of Disbursement/Payment Unit: 104 RMB

Item Acquisition on Behalf

1st M&E 2nd M&E Increase

Agreed Completed Agreed Completed Agreed Completed Permanent land use 265.47 92.434 69.473 243.153 243.153 150.719 173.68Temporary land use 406.37 46.941 19.43 336.699 327.589 289.758 308.159Land restoration 135.4 73.8 73.8 73.8 73.8Special facility 304.04 220.2 220.2 220.2 220.2

Page 194: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

181

Attachment & others 351.43 31.87 31.87 256.116 245.236 224.246 213.366Total 1462.71 171.245 120.773 1129. 968 1109.978 958.723 989.205

In specific, the progress of compensation can be summarized as follows:

(1) Heigangkou and Fujunsi: Direct costs are paid as included in the total budget;

(2) Zhangwangzhuang, Dong’an, Baohezhai, Zhaokou and Weitan: Direct costs have been paid as “land acquisition on behalf”;

(3) Laotian’an, Wuzhuang, Mao’an, Gucheng, Caogang, Taohuayu and Laozhaizhuang: The disbursement and payment of direct costs are in progress, to which the M&E team will continue its attention.

Table 2-3 shows the disbursement/payment of direct costs, while Annex 2 provides more detailed information.

Table 2-3 Progress of Disbursement/Payment Unit: 104 RMB

2M&E Increase No. Item Approved Total Acquisition on Behalf Agreed Completed Agreed Completed

1 Zhangwangzhuang 107.68 107.68 107.68 89.16 98.662 Dong’an 51.8 51.8 51.8 34.4 34.43 Laotian’an

145 215.2755.79 33.377 33.377 17.099 32.652

Subtotal 215.27 192.857 192.857 140.659 165.712 % of approved 133 133 97 114 % of total 90 90 65 81 1-3

% of agreed 100 100 100 100 4 Wuzhuang 71.59 41.661 41.661 41.661 41.6615 Mao’an 82.54 82.55 62.56 69.67 52.376 Shunhejie 89.68 87.36 87.36 68.55 68.557 Gucheng 104.27 80.55 80.55 80.55 80.558 Caogang

539 432

84.08 68.92 68.92 68.92 68.92Subtotal 432.16 361.041 341.051 329.351 312.051% of approved 67 63 67 63 % of total 84 79 84 79 4-8

% of agreed 94 94 9 Taohuayu 258.03 251.784 251.784 243.783 243.783

10 Baohezhai 37.731 37.731 37.731 37.731 37.73111 Zhaokou 24.055 24.06 24.06 6.8112 Weitan

343 369.11

49.297 49.297 49.297 15.919Subtotal 369.11 362.872 362.872 281.514 304.243% of approved 106 106 106 106 % of total 98 98 98 98 9-12

% of agreed 100 0 10013 Heigangkou 10.63 10.63 10.63 10.63 10.6314 Fujunsi 59 61 50.62 50.62 50.62 44.62 44.62

Subtotal 61.25 61.25 61.25 55.25 55.25% of approved 104 104 104 104 % of total 100 100 100 100 13-14

% of agreed 100 100 Laozhaizhuang 341 384.92 384.92 151.948 151.948 151.9484 151.9484% of approved 45 45 45 45% of total 39 39 39 3915

% of agreed 100

Page 195: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

182

Page 196: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

183

A random inspection of disbursement/payment is conducted as part of this M&E. As shown by the inspection results,

(1) all city Yellow River bureaus have disbursed to the relevant counties, townships, villages, households and industries directly according to the agreement and schedule;

(2) during the random inspection of 14 villages and 1 township involved in 8 components, all village leaders provide financial evidences of their receipt of compensations; and

(3) through a random inspection of 23 households and villager representatives affected by 7 components, the affected people say that they have received their due compensations for attachments and permanent land use among other entitlements.

3. LADN ACQUISITION AND RESETTLEMENT

Permanent land use includes spurs, protection works, access roads, and Laozhaizhuang new site, with a total area of 4,452.93 mu comprising floodland, waters and farmland. According to the IS, permanent land acquisition is necessitated by all the 15 components except for Fujunsi, with 3,637.18 mu, including floodland for the use of spurs and protection works. By the time of this M&E, a total area of 2,802.76 has been acquired for the permanent use of 14 components, i.e. 63% of the RP and 77%, involving 10 counties (district), 17 townships and 41 villages. Specifically, this total area includes 376.519 mu collective land of 3 townships and farms, 1,150.174 mu collective land of 19 villages and groups, and 1,142.3 mu contracted land of 2,323 households and 10,180 people in 22 villages and 83 groups.

Where collective land is used, compensations are reserved by villages/groups for the common use of infrastructures. Where contracted land is acquired, economic rehabilitation is arranged by villager groups in the following 3 modes as chosen by the majority on the basis of public consultation:

(1) Option A: pay to land losers in full or in part, with the remaining shared equally and land adjustment arranged;

(2) Option B: pay to land losers directly, without land adjustment;

(3) Option C: provide collective land for land losers, with compensations retained for public use, or partly paid to land losers as compensation for one crop and partly retained for public use.

As found in the investigation, Option A is chosen by 34 of the 83 affected groups, Option B by 41 and Option C by 8.

Refer to Table 2-4 for the progress of land acquisition and resettlement, and Annexes 1 and 4 for more detailed information.

Page 197: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

184

Table 2-4 Progress of Permanent Land Use Affected Economic Rehabilitation

Land No. Item Qty Group Home People

Subtotal ContractedOption A Option B Option C Others

Unit group home person mu mu group group group1 Collective land of township 3 170.149 2 Farm 1 206.37 3 Collective land of village/group 19 1150.174 4 Contracted land 22 83 2323 10180 1276.067 1142.297 34 41 8

The RP shows 4,670.42 mu for temporary use, versus 4,117.97 mu in the IS. By the time of this M&E, 3,690.085 mu has been agreed and 3,703.885 mu completed, taking up 79% and 90% of the RP and IS, involving 37 villages, 2 township governments and 1 farm.

According to the IS, land restoration is needed for Zhangwangzhuang, Dong’an, Laotian’an, Wuzhuang, Mao’an, Shunhejie, Gucheng, Caogang and Laozhaizhuang, with a total area of 3,267.41 mu. The total area restored by the time of this M&E is 2,815.255 mu, taking up 86% of the IS.

3.1 Permanent Land Acquisition and Economic Rehabilitation

3.1.1 Zhangwangzhuang

In the RP and IS, it is planned to acquire 566 mu for permanent use. By the time of this M&E, 566 mu has been agreed and completed, i.e. 100% of both RP and IS.

Permanent land use involves Zhangzhuang, Wangzhuang, Zhangwangzhuang of Wenquan Township in Wenxian County of Jiaozuo City, Qilipu of Heluo Township and Dayugou Township Government in Gongyui City, totally collective land of townships and villages or groups.

In Zhangzhuang where collective land of 8 groups is used, compensations are part paid to households at the rate of 150 RMB/mu and partly used for installing power lines and planting trees. The land in Zhangwangzhuang is owned by the collective, and land compensations are used for infrastructures such as wells and roads. In Wangzhuang where the collective land has been contracted to farmers, so compensations are paid to households directly. In Qilipu where the acquired floodland of Groups 5 and 6 on the opposite river bank is acquired, since the farmers are reluctant to go across the river for farming, these groups have separately contracted 252 mu and 280 mu to 30 and 36 local households. For the use of construction, 170.645 mu has been acquired here and compensations paid to the contractors directly, who have paid rent. The land acquired in Dayu Township is owned by the township government, which puts the compensations under its own control.

3.1.2 Dong’an

In the RP and IS, it is planned to acquire 337.08 mu for permanent. The area agreed and fully completed by the time of this M&E is 337.8 mu, i.e. 100% of the RP and IS.

Page 198: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

185

This aspect involves 16 groups, 448 families and 1,933 people in Dongcaoting, Xicaoting, Mahouzhuang, Lihouzhuang and Jiangou of Beiguo Township, Wuzhi County. Excluding the collective floodland in Xicaoting, 201.6 mu of the rest 208.87 mu contracted land involves 446 households and 1,926 people of 16 groups, with a per capita loss of 0.05-0.35 mu, or a an average percentage of 0.105 mu. On the basis of full discussion between group leaders and farmers, Option C is chosen by 6 groups in Dongcaoting, while Option B is preferred by 10 groups in Mahouzhuang, Lihouzhuang and Jiangou. Refer to Annex 4 for details.

3.1.3 Laotian’an

The RP shows 159.93 mu for permanent use, versus 116.9 mu in the IS. By the time of this report, 50.9 mu has been completed, i.e. 9% of the RP and IS. This involves the collective floodland of Yangyanjing in Zhandian Township, Wuzhi County. Compensations have been paid to the village as agreed and used for infrastructures.

Agreements and compensations for 37 mu are pending because the compensations rates are low and unacceptable in the opinion of farmers.

3.1.4 Wuzhuang

The proposed permanent land use in the RP is 352.47 mu, versus 352.4 mu in the IS. By the time of this report, 160.08 mu has been agreed and completed, taking up 45.4% of the RP and IS and 100% of the agreed area, involving Wuzhuang, Panguan, Yisanzhuang, Liyuechang and Huanglianji in Guanchang Township. Payment is not yet made to Huanglianji due to the undefined boundary of land. With 7.46 mu collective floodland acquired in Liyuechang and 120.22 mu contracted land in Wuzhuang, Panguan and Yisanzhuang, there is a per capita loss of 0.1-0.69 mu, or 0.15-7.19%.

In Wuzhuang, 4.11 mu fresh floodland is taken out of Group 8, and, on the basis of internal discussion within the group, Option B is chosen as the mode of economic rehabilitation. Land acquisition of 41.19 mu in Panguan involves 2 groups, 65 households and 346 people. Based on internal discussion, Option C is used for economic rehabilitation, with collective floodland provided for the land losers and compensations retained to offset the sufficient costs for excavating wells. At present, 30 wells are completed, which greatly benefits irrigation. The land in Yisanzhuang is distributed here and there, generally with several fields for each family, including good farmland which produces food for personal consumption and floodland which does not provide firm outputs. A total area of fresh floodland 83.94 mu is used for the project, involving 6 groups, 30 households and 144 people, with a per capita loss of 0.28-0.78 or a loss rate of 4.14-4.64%. Through internal discussion, Option B is adopted as the mode of economic rehabilitation.

Detailed information is provided in Table 3-1 below.

Page 199: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

186

Table 3-1 Permanent Land Acquisition for Wuzhuang

Original Land Acquisition Economic Rehabilitation

Floofland No. Village & Group Home People Total

Farmland Per

Capita Land

Home People Subtotal CollectivePer

Capita Loss

Loss Rate

Option B

Option C

Unit home person mu mu home person mu mu mu % group group

Remarks

1 Panguan 440 2200 2900 1.318 65 346 41.20 0.12 1.42 2 Excl. floodland Affected group 87 463 640 1.382 65 346 41.20 0.12 6.44 2 Group 5 42 202 270 1.337 20 85 14.6 0.17 5.41 1 Group 6 45 261 370 1.418 45 261 26.6 0.10 7.19 1 2 Wuzhuang 432 1800 2800 1.556 6 24 4.11 0.17 0.15 1 3 Yisanzhuang 199 900 1615 1.794 30 144 83.94 9.02 0.52 5.20 6 Affected group 204 884 1615 1.827 30 144 74.92 0.52 4.64 6 Group 1 30 110 300 2.727 3 18 12.42 0.69 4.14 1 Group 2 32 120 270 2.250 3 16 12.4 0.78 4.59 1 Group 3 35 158 265 1.677 5 26 12.1 0.47 4.57 1 Group 4 34 156 240 1.538 3 16 12.3 0.77 5.13 1 Group 5 37 180 260 1.444 10 46 12.7 0.28 4.88 1 Group 6 36 160 280 1.750 6 22 13 0.59 4.64 1 4 Liyuechang 7.46 7.46 5 Huanglianji 23.38

Total 1071 4900 7315 1.493 101 514 160.08 16.48 0.28 1.64 7 2

3.1.5 Mao’an

According to the RP and IS, it is planned to acquire 477.67 mu for permanent use. By the time of this report, 311.4 mu has been agreed and completed, accounting for 65% of the RP and IS and 100% of the agreed area.

Permanent land use involves 4 villages in Jintang Township of Yuanyang County, namely, Nanliuzhuang, Baobei, Baonan, Baoxi, Caozhuang and Zhu’an, with 311.4 mu, including 117 mu collective land of Baobei, Baonan and Baoxi, 17.58 mu collective land of Caozhuang and Zhu’an, and 176.82 mu contracted land which involves 12 groups, 93 households and 469 people in Nanliuzhuang, Caozhuang and Zhu’an, with a per capita loss of 0.37 mu or an average percentage of 1.36%.

In Nanliuzhuang, there used to be 9 groups, 550 households and 2,454 people, with a per capita farmland area of 3.11 mu. Land acquisition affects 5 groups, 25 households, 127 people and 69.62 mu fresh floodland, with a per capita loss of 0.48-1.09 mu, or 0.23-1.4%. Caozhuang had 8 groups, 305 households and 1,600 people, with a per capita farmland area of 1.7 mu. The acquisition of 6.43 mu fresh floodland affects 1 group, 30 households and 156 people, with a per capita loss of 0.04 mu or 0.79% on the average. With limited land loss, both villages have used Option B as the mode of economic rehabilitation. Zhu’an used to have 6 groups, 303 households and 1,336 people, with 2.993 mu farmland per capita. A total area of 100.77 mu is acquired for permanent use, involving 38 households and 186 people in all 6 groups directly, with a per capita loss of 0.41-1.15 mu or 1.62-3.86%. Due to the higher land loss, Option B is employed for economic rehabilitation as preferred by the majority, with young crop compensations paid to land losers directly and land adjustment arranged in the whole village. Subsequent to land adjustment, the per capita loss of affected groups ranges from 0.05 to 1.0 mu on the average, and that of the whole village is 0.08 mu only.

Refer to Table 3-2 for details.

Page 200: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

187

Table 3-2 Permanent Land Acquisition for Mao’an

Original Land Acquisition Economic Rehabilitation

Floofland Per Capita Loss No. Village & Group Home People Total

Farmland

Per Capita Land

Home PeopleSubtotal Collective

Loss Rate Before Land

Adjustment After Land Adjustment

Option B

Option A

Unit home person mu mu home person mu mu % group group1 Nanliuzhuang 550 2454 7639 3.113 25 127 69.62 0.91 0.55 5 Affected group 272 1376 5480.4 3.983 21 107 69.82 1.27 0.65 5 0 Group 1 58 256 1039.4 4.060 1 5 2.4 0.23 0.48 1 Group 2 68 430 1389 3.230 10 52 30 2.16 0.58 1 Group 3 58 265 1139.5 4.300 4 23 16.1 1.41 0.70 1 Group 4 52 250 1125 4.500 3 13 14.2 1.26 1.09 1 Group 5 36 175 787.5 4.500 3 14 7.12 0.90 0.51 1

2 Caozhuang 305 1600 2720 1.700 30 156 21.43 15 0.79 0.04 1 3 Zhu’an 303 1336 3998 2.993 38 186 103.35 2.58 2.59 0.54 0.08 6 Affected group 303 1336 4033 3.019 38 186 100.77 2.50 0.54 0.08 6 Group 1 43 198 536 2.707 4 18 20.68 3.86 1.15 0.10 1 Group 2 42 193 609 3.155 7 34 14.03 2.30 0.41 0.07 1 Group 3 44 203 598 2.946 9 44 20.48 3.42 0.47 0.10 1 Group 4 46 205 615 3.000 6 32 18.4 2.99 0.58 0.09 1 Group 5 66 288 924 3.208 12 58 27.18 1.62 0.47 0.05 1 Group 6 62 249 751 3.016 1

4 Baobei 460 1700 2981 1.754 39 39 5 Baonan 387 2000 2780 1.390 39 39 6 Baoxi 410 1720 2760 1.605 39 39

Total 2415 10810 22878 2.116 93 469 311.4 134.58 1.36 0.377 0.039 6 6

3.1.6 Shunhejie

In the RP, it is planned to acquire 379.09 mu for permanent, versus 342.65 mu in the IS. By the time of this report, 227.04 mu has been agreed and completed, i.e. 60% of the RP, 66% of the IS and 100% of the agreed area.

Land acquisition involves Shunzhong and Shunnan in Jinglonggong Township of Fengqiu County. Shunzhong used to have 2 groups, 237 households and 1,010 people, with a per capita farmland area of 1.552 mu. The use of 94.7 mu floodland affects 66 households and 315 people of both groups here, with a separate per capita land loss of 0.28 and 0.32 mu, or a percentage of 5.2% and 6%. Shunnan used to have 8 groups, 610 households and 2,056 people, with a per capita farmland area of 1.513 mu. The lost land is 132.34 mu, involving 6 groups, 93 households and 370 people, with a per capita loss of 0.31-0.5 mu, or 2.3-8.7%. Subsequent to land acquisition, Option B is chosen by the 8 affected groups in both villages.

Table 3-3 provides detailed figures.

3.1.7 Gucheng

The proposed permanent land use in the RP and IS is 435.7 mu and 226.03 mu respectively. By the time of this M&E, 189 mu has been agreed and completed, taking up 43% of the RP, 84% of the IS and 100% of the agreed area. Collective floodland is acquired in Chenqiao of Chenqiao Township, Fengqiu County.

Compensations for this 189 mu land have been paid to the village in full and partly used to compensate for land which is farmed by farmers voluntarily, at the rate of 300 RMB/mu, and part retained by the village for the construction of infrastructures such as roads and power facilities.

Page 201: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

188

Table 3-3 Permanent Land Acquisition for Shunhejie

Original Land Acquisition Economic Rehabilitation

Vulnerable Group Floodland No. Village &

Group Home People Total Farmland Per

Capita Land

Home PeopleHome People Subtotal Collective

Per Capita Loss

Loss Rate Option B

Remarks

Unit home person mu mu home person home person mu mu mu % group 1 Shunzhong 237 1010 1568 1.552 66 315 94.70 0.30 5.9 2 Affected group 237 1010 1568 1.552 66 315 94.70 0.30 6.0 2 Group 1 118 528 845 1.600 34 160 44.8 0.28 5.2 1 Group 2 119 482 723 1.500 32 155 49.9 0.32 6.9 1

2 Shunnan 510 2056 311000 1.513 93 370 132.34 0.36 5.1 Affected group 232 1127 1600 1.420 93 370 132.34 0.36 8.3 6 Group 3 39 201 315 1.567 4 16 1 4 8 0.50 2.5 1 Group 4 71 310 480 1.548 11 43 11 0.26 2.3 1 Group 5 60 278 400 1.439 17 65 1 2 26.8 0.41 6.7 1 Group 6 59 283 380 1.343 22 91 1 2 28.5 0.31 7.5 1 Group 7 55 269 420 1.561 26 106 36.54 0.34 8.7 1 Group 8 58 297 400 1.347 13 49 21.5 0.44 5.4 1

Total 469 2137 3168 1.482 159 685 3 8 227.04 0.33 7.2 8

3.1.8 Caogang

It is proposed to acquire 463.72 mu for permanent use in the RP and 348.72 mu in the IS. By the time of this M&E, 244.26 mu has been agreed and 127.71 mu completed, taking up 28% of the RP, 37% of the IS and 52% of the agreement.

This completed land area includes 116.55 mu of Shaozhai and 11.16 mu of Changmenkou in Caogang Township, Fengqiu County. Compensations have been paid to villages and used as allowance for road construction.

3.1.9 Taohuayu

The RP includes 209.77 mu for permanent use, versus 80.77 mu in the IS (with 5.77 mu for the use of access road excluded from the approved IS). The agreed and completed area by the time of this M&E is 57 mu, taking up 27% of the RP and 76% of the IS, involving collective land of Taohuayu and Bawangcheng in Guangwu Township, Yingyang City.

Compensations for 49 mu fishponds contracted to individuals are partly paid to contractors at the rate of 1,900 RMB/mu and partly shared by all villagers (900 RMB/mu), while those for 8 mu forestlands are paid to their contractors at the rate of trees.

3.1.10 Baohezhai

Both RP and IS include 206.37 mu for permanent, including 163.54 mu floodland and 42.83 mu nursery. The agreed and completed area is 206.37 mu, i.e. 100% of the RP and IS.

As found in the investigation, the land is totally owned by Zhengzhou Huanghe Farm, which owned 7,000 mu. The percentage of land loss is 2.9%. The acquired land has been contracted, not involving anybody of the Farm.

3.1.11 Zhaokou

The RP includes 117 mu for permanent, versus 36 mu in the IS. By the time of this M&E,

Page 202: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

189

32.46 mu bas been signed and completed, i.e. 27.7% of the RP and 99.2% of the IS.

Permanent land acquisition involves the collective land of Wantan Township, Zhongmou County. Compensations have been paid to and retained by the township government.

3.1.12 Weitan

In the RP and IS, it is planned to acquire 431 mu for permanent. By the time of this M&E, 447.54 mu has been agreed and completed, i.e. 4% larger than the area proposed in the RP and IS, involving Xinzhuang, Nanbeijie, Nanwei and Nanren in Langchenggang Township, Zhongmou County.

The land acquired in Nanbeijie and Nanwei is totally collective land. The land in Xinzhuang includes 40 contracted land, involving 1 group, 16 households and 62 people, with a per capita farmland reduction of 0.645 mu. Through internal discussion, Option B is used for economic rehabilitation. In Nanren, 286 mu is acquired, including 249.1 mu contracted land, affecting 7 groups, 80 households and 410 people, with a per capita farmland reduction of 0.59 mu. On the basis of internal discussion, Option B is adopted for economic rehabilitation, with 350 RMB/mu paid to land losers, collective land adjusted, and remaining money shared equally by all. After land adjustment, 7 groups, 817 households and 3,660 people are affected, with a per capita loss of 0.02 mu only.

Refer to Table 3-4 for details.

Table 3-4 Permanent Land Acquisition for Weitan

Original Land Acquisition Economic Rehabilitation

Floofland Per Capita Loss No. Village & Group Home People Total

Farmland

Per Capita Land

Home PeopleSubtotal Collective

Loss Rate Before Land

Adjustment After Land Adjustment

Option B

Option A

Unit home person mu mu home person mu mu % group group1 Xinzhuang 715 3576 11700 3.272 16 62 104.00 64.00 0.9 1.677 1 Affected group 120 550 2000.0 3.636 16 62 40.00 64.00 2.0 0.645 1 Group 1 120 550 2000.0 3.636 16 62 40.00 2.0 0.645 1 Group 2 Group 5 Group 8

46.00 64.00

2 Nanren 1156 5200 13000 2.50 80 410 274.90 36.90 2.1 0.698 0.02 7 Affected group 817 3660 9393.0 2.566 80 410 249.1 2.6 0.590 0.03 7 Group 1 113 476 1220.0 2.563 113 476 36.00 3.0 0.655 0.03 1 Group 2 117 466 1193.0 2.560 117 466 31.50 2.6 0.788 0.03 1 Group 3 127 551 1410.0 2.559 127 551 35.00 2.5 0.660 0.02 1 Group 4 119 573 1470.0 2.565 119 573 37.90 2.6 0.621 0.02 1 Group 5 128 591 1520.0 2.572 128 591 36.50 2.4 0.553 0.02 1 Group 6 130 588 1520.0 2.585 130 588 35.00 2.3 0.340 0.02 1 Group 7 83 415 1060.0 2.554 83 415 30.00 2.8 0.938 0.03 1 Collective 36.90 36.90

3 Nanbeijie 18.44 18.44 4 Nanwei 39.10 39.10

Total

3.1.13 Heigangkou

The RP includes 46.98 mu for permanent use, versus 25.48 mu in the IS. By the time of this M&E, 25.48 mu has been completed, i.e. 100% IS.

Page 203: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

190

Permanent land use involves Nanbeidi in Shuidao Township, Kaifeng County and Shunbei in Jinglonggong Township, Fengqiu County. Nanbeidi had 16 groups, 760 households, 3,700 people, and 3,900 mu land, including 11.85 acquired, involving 6 groups, 76 households and 326 people, with a per capita loss of 0.036 mu. Since this village is involved in the permanent land use for other projects, Option A is used as discussed between the groups. In Shunbei, 13.63 mu is acquired, totally collectively floodland. Compensations have been partly paid to households and partly retained for the purpose of infrastructures.

3.1.14 Fujunsi

The RP includes 197.4 mu for permanent use, but none in the IS and in practice.

3.1.15 Laozhaizhuang

The RP includes 72.03 mu for permanent use, versus 89.32 mu in the IS, including 79.13 mu for works and 10.19 mu for new sites. The completed area is 100.9796 mu, i.e. 40% and 13% more than the RP and IS, involving Laozhaizhuang, Gaozhuang, Wanglou, Kangtun, Maowa, Meizhuang and Jiucheng. Contracted land is acquired in Gaozhuang, Wanglou, Kangtun and Maowa, and collective land in Laozhaizhuang. Statistical data of Meizhuang and Jiucheng are not available now.

A total number of 24 groups are involved in Gaozhuang, Wanglou, Kangtun and Maowa, with a loss percentage of 0.5-2.3%. Gaozhuang had 1,100 mu, including 25.475 mu acquired in 5 groups, i.e. 2.3%. Wanglou lost 9.445 mu of the original 406 mu, i.e. 2.3%, with 2 groups affected. Maowa had 1,525 mu, including 18.8773 mu acquired in 4 groups, with a loss rate of 1.2%. Kangtun had 3,200 mu, including 15,4395 mu acquired in 13 groups, with a loss rate of 0.5%. As discussed by the groups and farmers, Option A is used by 15 and Option B by 9 groups as detailed in Table 3-5.

Table 3-5 Permanent Land Acquisition for Laozhaizhuang

Original Land Acquisition Economic

Rehabilitation Floofland

No. Village &

Group Group

Total Farmland

Per Capita Land

GroupSubtotal Collective

Loss Rate

Option B Option A

Unit group mu mu group mu mu % group Group

Remarks

1 Laozhaizhuang 6 550 1.10 4 8.693 8.693 Collective2 Gaozhuang 6 1100 1.403 5 25.475 2.3 5 3 Wanglou 4 406 1.108 2 9.445 2.3 2 4 Kangtun 13 3200 2.000 13 15.4395 0.5 9 4 5 Maowa 6 1525 2.098 4 18.8773 1.2 4 Unpaid 6 Meizhuang 18.4718 Unpaid

Total 35 6825 1.694 28 100.9796 8.693 1.5 9 15

3.2 Temporary Land Occupation and Restoration

By the time of this M&E, 3,690.085 mu has been signed and 3,703.885 mu completed for the temporary use of excavation and treading, accounting for 79% of 4,670.42 mu proposed in the RP and 90% of 4,117.97 in the IS, involving 37 villages, 2 township governments and 1 farm.

Page 204: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

191

Refer to Annex 1 for detailed information.

According to the IS, land restoration is needed for Zhangwangzhuang, Dong’an, Laotian’an, Wuzhuang, Mao’an, Shunhejie, Gucheng, Caogang and Laozhaizhuang, with a total area of 3,267.41 mu to be restored. By the time of this M&E, 2,815.255 mu has been restored, taking up 86% of the IS 3,276.41 mu and 100% of the actual area 2,815.22 mu. Refer to Table 3-6.

(1) Temporary land occupation: This part of work is completed as proposed in the RP and IS for Zhangwangzhuang, Dong’an, Laotian’an, Wuzhuang, Mao’an, Shunhejie, Caogang, Taohuayu, Baohezhai, Zhaokou, Weitan, Heigangkou and Fujunsi, and being performed for Gucheng and Laozhaizhuang.

(2) Land restoration: This work is finished for Zhangwangzhuang, Dong’an, Laotian’an, Wuzhuang, Mao’an, Shunhejie and Caogang as proposed in the IS, and for Gucheng and Laozhaizhuang as agreed.

Photographs 1 and 2 show the restored land in Mao’an and Shunhejie, whereas Photographs 3 and 4 illustrate the land being leveled in Laozhaizhuang and Gucheng.

Table 3-6 Progress of Temporary Land Occupation and Restoration Land Occupation Land Restoration

IS (mu) Completed (mu) Completed No. Component RP (mu)

Area PlannedAgreed (mu) Subtotal Excavation Occupation

Planned (mu) Area

(mu) %

1 Zhangwangzhuang 73 73 73 84.3 84.3 72.3 12 84.3 84.3 100 2 Dong’an 48 48 48 48 48 36 12 48 48 100 3 Laotian’an 323.23 323.23 323.23 322.485 322.485 315.285 7.2 309.95 309.95 100 4 Wuzhuang 334.7 334.7 334.7 334.7 334.7 325.1 9.6 334.7 334.7 100 5 Mao’an 461.5 461.5 461.5 461.5 461.5 444.7 16.8 461.5 461.5 100 6 Shunhejie 200 200 200 199.68 199.68 191.8 7.88 199.68 199.68 100 7 Gucheng 736.14 736.14 736.14 577.34 577.34 569.96 7.38 577.34 577.34 100 8 Caogang 584 584 584 583.93 583.93 567.43 16.5 583.93 583.93 100 9 Taohuayu 574.2 16.2 16.2 30 28.8 1.2

10 Baohezhai 35 35 35 35 29 6 11 Zhaokou 252.6 252.6 250.69 250.69 249 1.69 12 Weitan 70 70 70 70 46 24 13 Heigangkou 96.59 98.5 112.14 112.14 98.95 13.19 14 Fujunsi 372.7 378.3 378.3 378.3 359 19.3 15 Laozhaizhuang 508.76 506.84 506.84 215.82 215.82 193.188 22.632 215.82 215.82 100

Total 4670.42 4117.97 3267.41 3690.085 3703.885 3526.513 177.372 2815.22 2815.22 100

Page 205: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

192

Photograph 1: Restored Land in Mao’ an Photograph 2: Restored Land in Shunhejie

Photograph 3: Land Leveling in Laozhaizhuang Photograph 4: Leveled Land in Gucheng

Land restoration is not involved in Taohuayu, Baohezhai, Zhaokou, Weitan, Heigangkou and Fujunsi. In practice, however, the Implementing Agency has leveled the land for temporary use, wherever possible, to enable farming by the local farmers. For instance, this is done by the Implementing Agency for the barren hills for the temporary use of Taohuayu.

4. PHYSICAL RELOCATION AND ECONOMIC REHABILITATION

Laozhaizhuang is the only component that necessitates physical relocation and economic rehabilitation.

In the RP and IS, this aspect involves 18 households and 85 people in Meizhuang, including 9 affected and 9 not affected directly. In practice, due to the difficulty in identifying homesteads on the opposite side of the river and the unwillingness of some people to move to the opposite side, the 9 affected households are moved backwards only, with the original village maintained in its integrity.

By the time of this M&E, these 9 households have been all relocated, with a total floor area of 1,143.753 m2.

4.1 Compensation for Housings

Compensation rates: The RP and IS include 260 RMB/m2, 220 RMB/m2, 160 RMB/m2 and 65 RMB/m2 for brick-concrete, brick-timber, earth-timber and sample structures. In practice, the rates are applied as published in the government notice, i.e. 160 RMB/m2, 120 RMB/m2, 80 RMB/m2 and 50 RMB/m2 respectively.

Payment: Compensations for housings have been paid to the 9 households in full by the time of this M&E, with a sum of 164,450 RMB.

4.2 Restoration of Housing Conditions

Homestead identification and housing: Housing is needed for all the 9 resettlement families. By the time of this M&E, homesteads have been identified for all, with 6 houses built, 1 being built and 2 to be built. Two families have not acted because one does business in the town, not eager to have a new, and the other is ready to start after the busy season.

Page 206: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

193

Resettlement: The total number of 9 households includes 5 moved in new houses, 2 living in borrowed rooms and 2 elsewhere in the town/city.

Refer to Table 4-1 for the progress of resettlement and Photographs 5 and 6 for a comparison of housing conditions.

Evaluation: The progress of physical relocation practically meets the schedule of construction. Compensations for housings have been paid to households. Homesteads have been identified for all. Resettlement families have been resettled properly. New houses are somewhat better than old ones in respect of circumstances, areas and structures. Drinking water is available. Power supply for domestic use is in progress. The affected people are rather satisfied.

Table 4-1 Restoration of Housing Conditions Relocated Homestead Housing Resettlement

Planned No. Home Head Home People

Identified Remaining Not

NeededBuilt

Being Built

Not Started

New Bought Borrowed Others

Unit home person home home home home home home home home home home 1 Ren Guofeng 1 5 √ √ √ 2 Ren Baolin 1 5 √ √ √ 3 Ren Baoguo 1 5 √ √ √ 4 Ren Baocun 1 5 √ √ √ 5 Ren Guoqiang 1 6 √ √ √ 6 Ren Guofu 1 5 √ √ House in town 7 Ren Guoqin 1 5 √ √ √ 8 Ren Xuemin 1 6 √ √ House in city 9 Ren Guoxian 1 6 √ √ √

Total 9 48 9 6 1 2 5 2 2

Photograph 5: Old House in Meizhuang Photograph 6: New House in Meizhuang

5. REPLACEMENT OF SPECIAL FACILITIES

Replacement of special facilities is necessitated by Taohuayu and Laozhaizhuang only.

It is proposed to replace a gate affected by Taohuayu with an approved budget of 2.16 million RMB. An agreement was concluded with the Water Supply Division of Henan Yellow River Engineering Bureau in November 2006, with an agreed amount of 2.16 million RMB. Now, a new gate has been completed and put into operation.

Special facilities affected by Laozhaizhuang include a gate, a waste canal, 2 access bridges, a

Page 207: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

194

GPS benchmark, 650 m canals, and 1,300 m power lines. By the time of this M&E, 32 power poles have been replaced, but other facilities are still in progress.

6. RECOVERY OF INCOMES

The M&E team has looked into the impact on and recovery of incomes, interviewed with the villages, groups or households choosing Options A and C, and followed the family incomes of sample households in groups preferring Option B.

6.1 Land Acquisition and Impacts

The affected households have been interviewed in the form of multiple choice questionnaires regarding the income impact of land acquisition, use of compensations and remedy measures.

As shown by the investigation results from 35 households, 46 have less land loss, with minor impacts (if any) on their family incomes; 20% earn less from farming but more from other sources, without any impact on their total incomes; 8% have lost poor quality land, with minor impacts; and 26% are affected considerably. Regarding the use of land compensations, 74% households use them for medical fees and daily expenses, 43% for children’s tuitions, and 37% for farming activities. Subsequent to farmland reduction, farmer workers are the major means of income recovery, accounting for 89% of the households interviewed. The rest 11% increase their family incomes by business. Detailed figures are provided in Table 6-1.

Table 6-1 Questionnaire for Income Recovery

No. Item Household % I Impact by farmland reduction

1 Less income from farming, but more from other sources, without any impact on total income 7 20

2 Minor impact due to less land loss 16 46 3 Minor impact due to poor land quality 3 8 4 Major impact 9 26 5 Others II Use of land compensations 1 Farming 13 37 2 Business 3 Housing 4 Children’s tuitions 15 43 5 Medical fees and daily expenses 26 74 6 Debit repayment 7 Others

III Remedy measures 1 Farmer worker 31 89 2 Business 4 11 3 Cropping, animal raising or plastic tunnel 4 Extensive farming and intercropping 5 Reclamation or cultivating others’ land 6 Trust to luck 2 6 7 Others

Page 208: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

195

6.2 Impacts and Recovery of Incomes in Options A and C

This M&E includes a typical survey of the villages, groups or households preferring Options A and C regarding how their family incomes are affected by the acquisition of collective land. The following boxes record such interviews.

(1) Interview with Chenqiao involved in Gucheng

Interview 1

Background: 180 mu collective floodland is acquired in Chenqiao for the permanent use of Gucheng.

Interviewee: Liu Jizhong, Party branch secretary.

Brief of interview:

A total area of 189 mu collective land of the village is acquired for permanent use, all proposed wetland, partly cultivated by some farmers now. Payments are used to compensate for more than 50 mu at the rate of 200-300 RMB/mu, with the remaining maintained by the village and totally used for public purposes, including power facilities and roads.

Farmers are for the training works, which, when completed, will not affect our production and livelihood, but will protect the farmland and facilitate farming activities and ensure good harvests.

(2) Interview with Panguan and Nanren with a higher percentage of farmland loss due to permanent land acquisition for Wuzhuang and Weitan

Interview 2

Background: 41.19 mu floodland is acquired in Panguan for the permanent use of Gucheng.

There used to be 8 groups, 440 households and 2,200 people in the village, with 1.318 mu per capita. Land acquisition involves 2 groups, 65 households and 346 people, with a per capita land loss of 0.12 mu. Option C is used for economic rehabilitation.

Interviewee: Li Fuqun, Party branch secretary.

Brief of interview:

Our village is stable, with a per capita farmland area of 1.318 mu. 2 groups are involved in land acquisition, and land adjustment was performed as early as before the commencement of construction, probably in August-September last year, with collective land provided for the land losers. Compensations have been received before long, distributed to groups, and used for excavating wells as discussed by our representatives, with 30 wells completed for the convenience of irrigation. Land losers are affected in now way. Their land is cropped in time, without any impact.

Page 209: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

196

Interview 3

Background: 286 mu floodland is acquired in Nanren for the permanent use of Gucheng, including 36.9 mu collective land. There were previously 12 groups, 1,156 households and 5,200 people with a per capita farmland area of 2.5, including 7 groups, 80 households and 410 people with a per capita farmland area of 0.608 mu. Option A is adopted for economic rehabilitation.

Interviewee: Ma Qingchun, leader of Group 5.

Brief of interview:

There were previously 128 households and 591 people, with a per capita farmland area of 2.572 mu. 36.5 mu is acquired this time, involving 13 households and 66 people, i.e. a per capita loss of 0.553 mu. Meetings were held by the group. Since the land was compensated as floodland, all farmers complained of less compensation, willing to get land instead. It was agreed to provide the reserved collective land for the farmers who have lost land. Our collective land is much. How much you have lost, how much is provided for you, so nobody complain now.

Compensations were received by the villager committee long ago and handed over to groups. An amount of 300 RMB/mu was paid to households to compensate for young crops, and land was farmed in time, without any impact on households. The remaining money was retained by the group for the purpose of excavating wells and planting trees.

As shown by interviews, the acquired land is floodland, and the replaced land is floodland too, so the resultant farmland is neither less in quantity regardless Option A or C, nor different in quality. Additionally, farming in time is not delayed, so land acquisition has not caused any major impacts.

6.3 Income Constituents and Changes of Sample Households in Option B

As understood in our surveys of sample households, major impacts on family incomes largely exist where there is less farmland per capita and Option B is adopted. In this case, the M&E team has carried out a baseline census of the incomes 2005 and a follow-up investigation of the income recovery 2006 of 25 sample households in 3 villages which have lost a higher percentage of land and adopted Option B for economic rehabilitation.

The survey results indicate a per capita income of 1,614 RMB in 2005, including 942 RMB from farming, 649 RMB from sideline and 22 RMB from other sources, taking up 58.4%, 40.2% and 1.4% respectively; versus 2,234 RMB in 2006, including 789 RMB, 1,425 RMB and 20 RMB, or 35.3%, 63.8 and 0.9%. Farming, sideline and others were the major sources of family incomes.

With the income in the follow-up year compared with that in the base year, the per capita

Page 210: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

197

income in 2006 included 154 RMB less from farming and 776 RMB more from sideline, taking up 23.1% less and 23.6% more of family incomes. The structure of incomes changed in that sideline has become the largest contributor of family incomes step by step. Refer to Table 6-3 and Chart 1 for further information.

More information on the constitutions and changes of family incomes of sample households is provided in Annex 5.

Table 6-3 Constituents and Changes of Family Incomes Sideline (RMB) Farming

(RMB) Subtotal Farmer WorkerOthers (RMB) No. Village Year Home People

Per Capita Income (RMB) Income % Income % Income %

Fruit (RMB)

Animal Raising (RMB) Income %

2006 5 36 1900 1105 58.2 764 40.2 764 100.0 31 1.6 2005 5 36 2042 1527 74.7 486 23.8 486 100.0 30 1.5 1 Yisanzhuang Change -142 -421 -16.6 278 16.4 278 1 0.1 2006 6 34 2533 995 39.3 1518 59.9 1126 74.2 20 0.8 2005 6 34 1850 1036 56.0 794 42.9 603 75.9 20 1.1 2 Shunzhong Change 683 -41 -16.7 724 17.0 524 -1.7 -0.3 2006 14 74 2260 539 23.9 1705 75.4 1705 100.0 15 0.7 2005 14 74 1297 615 47.4 663 51.1 663 100.0 19 1.5 3 Shunnan Change 963 -75 -23.5 1042 24.4 1042 -4 -0.8 2006 25 144 2234 789 35.3 1425 63.8 1333 93.5 20 0.9 2005 25 144 1614 942 58.4 649 40.2 604 93.0 22 1.4 Total Change 620 -154 -23.1 776 23.6 729 0.5 -2 -0.5

Note: 2005 is used as base year and 2006 as follow-up year.

Further analysis reveals a decline of 421 RMB in the farming incomes and an increase of 278 RMB in sideline incomes in Yisanzhuang (separately 16.6% less and 16.4% more), slightly less family incomes, 41 RMB and 724 RMB in Shunzhong (16.7% and 17%), more family incomes, 75 RMB and 1,042 RMB in Shunnan (23.5% and 24.4%), obviously more family incomes.

As seen from comparison of the family incomes in the base and follow-up years, 1 household and 6 people out of the total number of 5 sample households and 36 people in Wuzhuang

Chart 1 Constitutions and Changes of Family Incomes

0.0

500.0

1000.0

1500.0

2000.0

2500.0

Per Capita Income Farming Sideline 2006 2005

Others

Page 211: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

198

earned more in the year of land acquisition, accounting for 17% of the total, versus 15 and 83 out of the total number of 20 sample households and 108 people in Shunhejie, taking up 77%. Details are given in Table 6-4 and Annex 5.

The reason is that farmland reduction has caused in a decline in farming incomes, but better awareness of farmer workers, who contribute more and more to the family incomes as one of the major sources of income. Particularly in Shunzhong and Shunnan, where brick kilns in the floodplain areas nearby represents easier opportunities and less costs for farmer workers than in urban areas, most farmers work for the kilns and earn more than in farming. This has greatly increased the total income of sample households.

Table 6-4 Income Recovery of Sample Households

Sample Household Equal or Higher Income Level Component Year Home People Home People %

Base year 5 36 Wuzhuang Follow-up year 5 36 1 6 17Base year 20 108 Shunhejie Follow-up year 20 108 15 83 77Base year 25 144 Total Follow-up year 25 144 16 89 62

The following is an interview with Shunnan villagers:

Interview 4

Background: A total area of 132.34 mu is taken from Shunnan for the use of Shunhejie River Training Works, involving 6 groups and causing a per capita loss of 0.358 mu. Option B is adopted as the mode of economic rehabilitation.

Interviewee: Ding Xiaoru, a family of minimum income guarantee in Group 6

Brief of interview:

There are 2 people in my family, with 2.5 mu, including 2.2 mu acquired this time, causing considerable impacts on my family. Compensations have been received long before.

As a family of minimum income guarantee, we depend on relatives who help our farming, 50 RMB/person allowance provided by the civil administration each month, plus flour and oil on the occasion of festivals, and cooperative medical care offered by the village. Now the land is less, we can manage to cultivate the remaining land by ourselves and get enough food to eat.

All families are working for a kiln in the adjacent village, quite close to here. I’m idle at home, so the village has found an errant for me at the kiln, with more than 20 RMB earned per day to help out family expenses.

6.4 Implication of Income Changes in Option B

According to China’s Communiqué of National Economic and Social Development in 2006, rural residents with a per capita income less than 693, in the range of 694-958 and more than

Page 212: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

199

958 RMB were respectively classified as absolutely poor people, low-income and non-poor people in 2006, versus less than 683, in the range of 684-945 and more than 945 RMB in the base year of 2005.

Wuzhuang: In the base year, all sample households had a per capita income over 945 RMB, 36 non-poor people in total. In the follow-up year, due to land acquisition and less time for farmer works, 5 people earned less than 958 RMB and joined the low-income population, causing a reduction of 5 people in the non-poor population as a consequence, i.e. 14%. The situation of poverty changed.

Shunhejie: In the base year, 21 people had a per capita income less than 683 RMB, while 14 earned 684-945 RMB and 73 more than 945 RMB, falling within the poor, low-income and non-poor populations respectively. In the follow-up year, more incomes generated by farmer workers and allowances provided by the State for grain production reduced the absolutely poor and low-income populations by 21 and 12 people respectively, i.e. 19% and 11%, and increased the non-poor population by 33, or 31%, implying obvious improvement of poverty.

Detailed information is given in Table 6-5 and Charts 2 and 3.

Table 6-5 Status and Changes of Poverty Populations Wuzhuang Shunhejie

2005 2006 Change 2005 2006 Change Population People % People % People % People % People % People %

Absolutely poor 21 19 -21 -19.4Low-income 5 14 5 14 14 13 2 2 -12 -11 Non-poor 36 100 31 86 -5 -14 73 68 106 98 33 31

Subtotal 36 100 36 100 108 100 108 100

0

10

20

30

40

Absolutely poor Low-income Non-poor

Chart 2 Comparison of Poverty Populations in Wuzhuang

Base year Follow-up year

Page 213: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

200

7. PROTECTIN OF RIGHTS AND INTERESTS

This M&E includes a survey of 7 villages and 35 households in the form of questionnaire regarding resettlement training and complaints management, including channel and output.

7.1 Training

As shown investigation results, 100% of the 35 households are willing to be trained, mainly in animal raising and sideline activities, accounting for 49% and 29% respectively as shown in Table 7-1.

Thus, it is expected that the responsible departments provide training programs and arrange multilevel and multidiscipline training activities, for the affected people to adjust their structure of farming activities and find more sources of income under the condition of farmland reduction, so as to recover and improve their original productivity and standard of living as early as possible.

Table 7-1 Willingness to Be Trained Subtotal Yes No No. Index People % People % People %

1 Have you received training since 2005? 35 100 3 9 32 91 2 If yes, training in farming skills? 3 Training in policies and laws/regulations? 3 3 4 Any other training? 5 Do you wish to be trained? 35 100 35 100 6 If yes, cropping? 1 3 7 Animal raising? 17 49 8 Sideline? 10 29 9 Others? 4 11

7.2 Complaints Management

In the course of construction and resettlement, the affected people have the right to appeal as per the constitution and other laws when their interests are encroached upon.

0 20 40 60 80

100 120

Absolutely poor Low-income Non-poor

Chart 3 Comparison of Poverty Populations in Shunhejie

Base year Follow-up year

Page 214: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

201

The M&E includes interviews with 35 affected people in 7 villages regarding their degree of satisfaction with the channel and output of complaints management. None of them had any complaint.

7.3 Vulnerable Groups

This M&E includes special attention to the affected vulnerable groups in the project area. As investigated, there are 4 households and 7 people affected by the 15 components, accounting for 20% of the total number of households investigated. These people are properly resettled: supported by relatives/friends who cultivate their farmland on behalf, or provided with food and cash relief by the county civil administration on festivals. Also, the county, township or village has arranged cooperative medical care for them, providing them with access to medical care and relieving them from medical service fees.

8. EVALUATION AND RECOMMENDATIONS

(1) Compensation rates: Compensation rates for both permanent and temporary land use are applied as approved in the RP and IS. In Laozhaizhuang, housings are compensated at the rates published by the government and attachments at the rates fixed in the IS.

(2) Payment: A total sum of 11.29968 million RMB direct resettlement costs has been agreed, accounting for 79% of the approved and 77% of the total budget, and 11.09978 million RMB has been paid, taking up 78% and 76% respectively.

(3) Permanent land use and economic rehabilitation: Permanent land acquisition is necessary for all the components except for Fujunsi, with a total area of 2,802.76 mu completed by the time of this M&E, taking up 63% of the RP and 77% of the IS, involving both collective and contracted land of 17 townships and 41 villages in 10 counties. Altogether 83 groups of 22 villages are involved in the use of contracted land, with Option A chosen by 34, Option B by 41 and Option C by 8 as the mode of economic rehabilitation.

(4) Temporary land occupation and restoration: A total area of 3,690.085 mu has been signed for temporary use, including 3,703.885 mu completed, accounting for 79% of the RP and 90% of the IS. The land to be restored amounts to 2,815.22 mu, which is all restored, accounting for 86% of the IS.

(5) Physical relocation and resettlement: Compensations for housings have been paid to 9 resettlement families in Laozhaizhuang, with homesteads identified and people resettled properly.

(6) Income recovery: Land acquisition has caused less income from farming, but more from sideline activities, especially farmer works, so the family income of sample households are generally maintained. The family income of 17% people in Wuzhuang and 77% in Shunhejie reached or exceeded the original level in the year of land acquisition.

Page 215: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

202

(7) Protection of rights/interests: The affected people have never received any training under the project, but they wish to be trained. Vulnerable groups, such as the families enjoying “five guarantees”, people with physical disability and women-headed families, enjoy the equal rights as others in the respect of compensation and resettlement.

Page 216: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

203

Annex 1 Progress of Land Acquisition Unit: mu

Permanent Land Use Temporary Land Use No. Village

RP IS Agreed Completed RP IS Agreed Completed1 Zhangwangzhuang 566 566 566 566 73 73 84.3 84.3

1.1 Zhangzhuang 97.6 123.8 123.8 84.3 84.3 1.2 Wangzhuang 112.6 78.807 78.807 1.3 Zhangwangzhuang 120.1 55.059 55.059 1.4 Wenquan

Township105.1 8.091 8.091

1.5 Heluo Township 170.645 170.645 1.6 Dayugou

Township130.6

566

129.598 129.598

73 73

2 Dong’an 337.8 337.8 337.8 337.8 48 48 48 48

2.1 Dongcaoting 75.1 82.78 82.78 24 24 2.2 Mahouzhuang 82.6 61.5 61.5 2.3 Lihouzhuang 3.32 3.32 2.4 Jiangou 60.1 60.27 60.27 24 24 2.5 Xicaoting 52.5 129.93 129.93 2.6 Xiefeng 67.5

337.8

48 48

3 Laotian’an 159.93 116.9 13.9 13.9 323.23 323.23 322.485 322.485

3.1 Yangyanjing 45 13.9 13.9 124.33 88.5 88.5 3.2 Guo’an 37.5 103.6 116.41 116.41 3.3 Dachabao 34.5 95.3 105.075 105.075 3.4 Others 42.93

116.9

323.23

12.5 12.5 4 Wuzhuang 352.47 352.4 160.08 160.08 334.7 334.7 334.7 334.7

4.1 Panguan 105.6 41.19 41.19 59.31 59.31 4.2 Wuzhuang 90.5 4.11 4.11 7.35 7.35 4.3 Xiaozhuang 87.5

283.53

4.4 Yisanzhuang 83.94 83.94 44.73 44.73 4.5 Liyuechang 7.46 7.46 136.03 136.03 4.6 Huanglianji 23.38 23.38 87.28 87.28 4.7 Others 68.87 68.87

334.7 334.7

5 Mao’an 477.67 477.67 311.4 311.4 461.5 461.5 461.5 461.5

5.1 Naliuzhuang 240.2 240.2 69.62 69.62 36.8 36.8 5.2 Baobei 39 39 45.9 45.9 5.3 Baonan 39 39 41.47 41.47 5.4 Baoxi 39 39 23.7 23.7 5.5 Caozhuang 180.1 180.1 21.43 21.43 162.44 162.44 5.6 Zhu’an 103.35 103.35 136.09 136.09 5.7 Haozhai 15.1 15.1 5.8 Others 57.37 57.37

461.5 461.5

6 Shunhejie 379.09 342.65 227.04 227.04 200 200 199.68 199.68

6.1 Shunzhong 94.7 94.7 40.26 40.26 6.2 Shunnan

180.1 132.34 132.34 46.15 46.15

6.3 Jingnan 162 58.07 58.07 6.4 Township

government 55.2 55.2

6.5 Others 36.99

342.65

200 200

Page 217: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

204

Progress of Land Acquisition – continued Unit: mu

Permanent Land Use Temporary Land Use No. Village

RP IS Agreed Completed RP IS Agreed Completed7 Gucheng 435.70 226.03 189.00 189.00 736.14 736.14 577.34 577.34

7.1 Chenqiao 90.30 189.00 189.00 736.14 736.14 577.34 577.34 7.2 Gucheng 75.20 7.3 Sanhe 60.20 7.4 Others 210.00

226.03

8 Caogang 463.72 348.72 244.26 127.71 584 584 583.93 583.93

8.1 Shaozhai 165.3 116.55 116.55 575.49 575.49 8.2 Changmenkou 183.4 127.71 11.16 8.44 8.44 8.3 Others 115.02

348.72

584 584

9 Taohuayu 209.77 80.77 57 57 574.2 16.2 16.2 30 9.1 Taohuayu 55 43 43 350.9 9.2 Bawangcheng 35

75 14 14 223.3 16.2 30

9.3 Others 119.77 5.77 16.2

10 Baohezhai 206.37 206.37 206.37 206.37 35 35 35 35

10.1 Yellow River Farm 206.37 206.37 35 35 11 Zhaokou 117.0 36.0 32.46 32.46 252.6 252.6 250.69 250.69

11.1 Xinzhai 18.5 129.5 129.5 11.2 Liubao 17.5 123.1 123.1

250.69 250.69

11.3 Others 81 36 32.46 32.46

12 Weitan 431 431 447.54 447.54 70 70 70 70

12.1 Nanren 120.1 120.1 286 286 19.5 19.5 12.2 Xinzhuang 135.2 135.2 104 104 22 22

70 70

12.3 Nanbeijie 78.1 78.1 18.44 18.44 12.6 12.6 12.5 Nanwei 39.1 39.1 12.6 Sunba 97.6 97.6 15.9 15.9 13 Heigangkou 46.98 25.48 25.48 25.48 96.59 98.5 112.14 112.14

13.1 Nanbeidi 11.85 11.85 81.86 81.86 13.2 Shunbei

46.98 25.48 13.63 13.63

96.59 98.5 30.28 30.28

14 Fujunsi 197.4 0 372.7 378.3 378.3 378.3 14.1 Yuanfang 326.3 326.3 14.2 Shaodong

372.7 378.3 52.0 52.0

15 Laozhaizhuang 72.03 89.32 100.9796 100.98 508.76 506.84 215.82 215.82 15.1 Laozhaizhuang 8.693 8.693 40.729 40.729 15.2 Gaozhuang 25.475 25.475 4.87 4.87 15.3 Wanglou 9.445 9.445 100.905 100.905 15.4 Kangtun 15.4395 15.4395 44.645 44.645 15.5 Maowa 18.8773 18.8773 24.67 24.67 15.6 Meizhuang 18.4718 18.4718 15.7 Jiucheng

72.03 89.32

4.578 4.578

508.76 506.84

Total 4452.93 3637.18 2919.31 2802.76 4670.42 4117.97 3690.09 3703.89

Page 218: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

205

Annex 2 Progress of Resettlement Compensation Unit: 104 RMB

1st M&E 2nd M&E Increase No. Component Item Approved Total Acquisition on Behalf

Agreed Completed Agreed Completed Agreed Completed

Permanent land use 265.47 92.434 69.473 243.1528 243.1528 150.719 173.68Temporary land use 406.37 46.942 19.431 336.699 327.589 289.758 308.159Land restoration 135.4 73.8 73.8 73.8 73.8 Special facility 304.04 220.2 220.2 220.2 220.2Attachment & others 351.43 31.87 31.87 256.116 245.236 224.246 213.366Total

1427 1462.3

1462.7 171.246 120.774 1129.968 1109.978 958.723 989.205% of approved 79 78 % of total 77 76

Grand total of Items 1 to 15

% of agreed 98 Permanent land use 39.05 16.84 7.34 39.05 39.05 22.21 31.71Temporary land use 31.12 31.12 31.12 31.12 31.12Land restoration 9.49 9.49 9.49 9.49 9.49Special facility Attachment & others 28.02 1.68 1.68 28.02 28.02 26.34 26.34

1 Zhangwangzhuang

Subtotal 107.68 18.52 9.02 107.68 107.68 89.16 98.66Permanent land use 23.31 14.34 14.34 23.31 23.31 8.97 8.97Temporary land use 11.27 11.27 11.27 11.27 11.27Land restoration 3.42 3.42 3.42 3.42 3.42Special facility Attachment & others 13.8 3.06 3.06 13.8 13.8 10.74 10.74

2 Dong’an

Subtotal 51.8 17.4 17.4 51.8 51.8 34.4 34.4Permanent land use 3.51 0.725 0.725 0.9596 0.9596 0.2346 0.2346Temporary land use 39.48 15.553 24.427 24.427 8.874 24.427Land restoration 12.8 7.99 7.99 7.99 7.99 Special facility Attachment & others

3 Laotian’an

Subtotal

145 215.27

55.79 16.278 0.725 33.377 33.377 17.099 32.652 Sum 215.27 52.198 27.145 192.857 192.857 140.659 165.712 % of approved 36 19 133 133 97 114 % of total 24 9 90 90 65 81

Total of Items 1 to 3

% of agreed 100 100 100 100 Permanent land use 11.15 11.046 11.046 11.046 11.046Temporary land use 25.34 18.155 18.155 18.155 18.155Land restoration 8.27 8.27 8.27 8.27 8.27Special facility Attachment & others 26.83 4.19 4.19 4.19 4.19

4 Wuzhuang

Subtotal 71.59 41.661 41.661 41.661 41.661Permanent land use 21.49 12.88 10.19 21.49 21.49 8.61 11.3Temporary land use 34.91 34.91 25.8 34.91 25.8Land restoration 11.27 11.37 11.37 11.37 11.37Special facility 0 0Attachment & others 14.87 14.78 3.9 14.78 3.9

5 Mao’an

Subtotal 82.54 12.88 10.19 82.55 62.56 69.67 52.37Permanent land use 16.3 15.67 15.67 15.67 15.67 0 0Temporary land use 15.12 15.1 15.1 15.1 15.1Land restoration 4.92 4.92 4.92 4.92 4.92Special facility 0 0Attachment & others 53.34 3.14 3.14 51.67 51.67 48.53 48.53

6 Shunhejie

Subtotal 89.68 18.81 18.81 87.36 87.36 68.55 68.55Permanent land use 14.99 13.04 13.04 13.04 13.04Temporary land use 55.8 43.77 43.77 43.77 43.77Land restoration 18.3 14.36 14.36 14.36 14.36Special facility 0 0Attachment & others 15.18 9.38 9.38 9.38 9.38

7 Gucheng

Subtotal 104.27 80.55 80.55 80.55 80.55Permanent land use 20.08 8.04 8.04 8.04 8.04Temporary land use 44.15 44.92 44.92 44.92 44.92Land restoration 14.35 13.98 13.98 13.98 13.98Special facility 0 0Attachment & others 5.5 1.98 1.98 1.98 1.98

8 Caogang

Subtotal

539 432

84.08 68.92 68.92 68.92 68.92

Page 219: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

206

Progress of Resettlement Compensation - continued Unit: 104 RMB

1st M&E 2nd M&E Increase No. Component Item Approved Total Acquisition

on Behalf Agreed Completed Agreed Completed Agreed Completed

Total 432.16 31.69 29 361.041 341.051 329.351 312.051 % of approved 67 63 67 63 % of total 84 79 84 79

Total of Items 4 to 8

% of agreed 94 94 Permanent l d

19.312 14.272 14.272 14.272 14.272 Temporary l d

2.131 1.221 1.221 2.131 2.131 0.91 0.91 Land

i

Special f ili

216 216 216 216 216 Attachment & h

20.584 6.78 6.78 19.381 19.381 12.601 12.601

9 Taohuayu

Subtotal 258.03 8 8 251.784 251.784 243.783 243.783 Permanent l d

17.709 17.709 17.709 17.709 17.709 Temporary l d

2.615 2.615 2.615 2.615 2.615 Land

i

Special f ili

Attachment & h

17.407 17.407 17.407 17.407 17.407

10 Baohezhai

Subtotal 37.731 0 0 37.731 37.731 37.731 37.731 Permanent l d

2.24 2.24 2.24 2.24 2.24 Temporary l d

19.016 19.02 12.21 19.02 19.02 6.81 Land

i

Special f ili

Attachment & h

2.799 2.8 2.8 2.8 2.8

11 Zhaokou

Subtotal 24.055 24.06 17.25 24.06 24.06 6.81 Permanent l d

29.739 29.739 18.968 29.739 29.739 10.771 Temporary l d

5.148 5.148 5.148 5.148 5.148 Land

i

Special f ili

Attachment & h

14.41 14.41 14.41 14.41 14.41

12 Weitan

Subtotal

343 369.11

49.297 49.297 33.378 49.297 49.297 15.919 Sum 369.11 81.358 58.629 362.872 362.872 281.514 304.243 % of approved 106 106 106 106 % of total 98 98 98 98

Total of Items 9 to 12

% of agreed 100 0 100 Permanent l d

1.76 1.76 1.76 1.76 1.76 Temporary l d

7.24 7.24 7.24 7.24 7.24 Land

i

Special f ili

Attachment & h

1.63 1.63 1.63 1.63 1.63

13 Heigangkou

Subtotal 10.63 0 0 10.63 10.63 10.63 10.63 Permanent l d

Temporary l d

28.58 6 6 28.58 28.58 22.58 22.58 Land

i

Special f ili

Attachment & h

22.04 22.04 22.04 22.04 22.04

14 Fujunsi

Subtotal

59 61

50.62 6 6 50.62 50.62 44.62 44.62 Sum 61.25 6 6 61.25 61.25 55.25 55.25 % of approved 104 104 104 104 % of total 100 100 100 100

Total of Items 13 & 14

% of agreed 100 100 Permanent l d

44.83 44.827 44.827 44.8272 44.8272 Temporary l d

84.45 48.293 48.293 48.2932 48.2932 Land

i52.58

Special f ili

88.04 4.2 4.2 4.2 4.2 Attachment & h

115.02 54.628 54.628 54.628 54.628 Subtotal

341 384.92

384.92 151.948 151.948 151.9484 151.9484 % of approved 45 45 45 45 % of total 39 39 39 39

15 Laozhaizhuang

% of agreed 100

Page 220: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

207

Annex 3 Sample Inspection of Payments Payment

Permanent Land Use Temporary Land Use Attachment & Others Component Village Home Comparison Total Area Rate Amount Area Rate Amount Subtotal Tree Well Tomb Restoration

Unit RMB mu RMB/mu RMB mu RMB/mu RMB RMB RMB RMB RMB RMB

Remarks

Payable 123413 178.859 690 123413 Wenquan Paid 123413 178.859 690 123413 Payable 47188 123.8 260 32188 15000 15000 Zhangzhuang Paid 47188 123.8 260 32188 15000 15000 Payable 4669 17.957 260 4669

Zhangwangzhuang

Dongcun Paid 4669 17.957 260 4669

Collective land is acquired for permanent use, so young crops are compensated only, with the remaining retained for public use.

Payable 146220 82.78 690 57118 78 759 59202 29900 11400 18500 Dong’an Dongcaoting Paid 146220 82.78 690 57118 78 759 59202 29900 11400 18500

Sample survey of villages

Payable 74417 10.5 690 7245 88.5 759 67172 Yangyanjing Paid 74417 10.5 690 7245 88.5 759 67172

Collective land

Payable 88348 116.4 759 88348 Laotian’an

Guo’an Paid 88348 116.4 759 88348

Collective land

Payable 26910 39 690 26910 Baonan Paid 26910 39 690 26910

Collective land

Payable 131141 103.35 690 71312 67.14 759 50959 8870 8870 Zhu’an Paid 131142 103.35 690 71312 67.14 759 50959 8871 8871

Sample survey of villages

Payable 64618 69.62 690 48038 16580 16580

Mao’an

Nanliuzhuang Paid 64618 69.62 690 48038 16580 16580

Sample survey of villages

Payable 517216 116.55 690 80420 575.49 759 436797 Caogang Shaozhuang Paid 517216 116.55 690 80420 575.49 759 436797

Sample survey of villages

Payable 70798 52 759 39468 31330 31330 Fujunsi Paid 70798 52 759 39468 31330 31330

Sample survey of villages

Payable 432372 326.3 759 247662 184710 184710 Fujunsi

Shaodong Paid 432372 326.3 759 247662 184710 184710

Sample survey of villages

Payable 45540 60 759 45540 Heigangkou Nanbeidi Paid 45540 60 759 45540 Payable 6524 9.455 690 6524 Wanglou Paid 6524 9.455 690 6524

Sample survey of villages

Payable 17578 25.475 690 17578 Laozhaizhuang

Gaozhuang Paid 17578 25.475 690 17578

Sample survey of villages

Page 221: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

208

Sample Inspection of Payments - continued Payment

Permanent Land Use Temporary Land Use Attachment & Others Component Village Home Comparison Total Area Rate Amount Area Rate Amount Subtotal Housing Well Tomb RestorationUnit RMB mu RMB/mu RMB mu RMB/mu/season RMB RMB RMB RMB RMB RMB

Remarks

Payable 30967 40.8 759 30967 Tanlu Wang Lianxiang Paid 30967 40.8 759 30967 Land contractor Payable 21859 28.8 759 21859 Zhangwangzhuang

Chengguan Wang Peihong Paid 21859 28.8 759 21859 Land contractor Payable 5313 7.7 690 5313 Wang Xiaohong Paid 5313 7.7 690 5313 Payable 9080 12 690 8280 800 800 Dong’an Dongcaoting

Zhang Weiguo Paid 9080 12 690 8280 800 800 Payable 2981 4.32 690 2981 Wang Maolin Paid 2981 4.32 690 2981 Payable 6831 9.9 690 6831 Zhu’an

Zhu Guangting Paid 6831 9.9 690 6831 Payable 1835 2.66 690 1835 Ma Hong’an Paid 1835 2.66 690 1835 Payable 711 1.03 690 711 Nanliuzhuang

Li Fangzheng Paid 711 1.03 690 711 Payable 1321 1.74 759 1321 Lou Yanjie Paid 1321 1.74 759 1321 Payable 1943 2.56 759 1943 Caozhuang

Wang Yongqian Paid 1943 2.56 759 1943 Payable 30967 40.8 759 30967 Tanlu Wang Lianxiang Paid 30967 40.8 759 30967 Land contractor Payable 21859 28.8 759 21859

Mao’an

Chengguan Wang Peihong Paid 21859 28.8 759 21859 Land contractor Payable 1380 2 690 1380 Ding Xiaohai Paid 1380 2 690 1380 Payable 2277 3.3 690 2277 Shunnan

Ding Weixiang Paid 2277 3.3 690 2277 Payable 1242 1.8 690 1242 Che Yukui Paid 1242 1.8 690 1242 Payable 421 0.61 690 421

Shunhejie

Shunzhong Wen Yongzhou Paid 421 0.61 690 421

Payable 2004 2.64 759 2004 Shao Xianxiu Paid 2004 2.64 759 2004 Payable 1822 2.4 759 1822 Fu Xinghai Paid 1822 2.4 759 1822 Payable 5844 7.7 759 5844

Caogang Shaozhuang

Shao Xian Paid 5844 7.7 759 5844 Payable 20700 30 690 20700 Li Xiaoyun Paid 20700 30 690 20700 Villager representative Payable 17436 25.27 690 17436 Weitan Nanren

Guo Guangquan Paid 17436 25.27 690 17436 Villager representative Payable 19901 19901 19901 Ren Guofeng Paid 19901 19901 19901

Laozhaizhuang Meizhuang

Ren Guobao Payable 38726 38726 38726

Resettlement family

Page 222: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

209

Paid 38726 38726 38726

Annex 4 Progress of Permanent Land Acquisition and Economic Rehabilitation Original Affected Economic Rehabilitation

Floodland No. Component County/City Township Village Group Home People Farmland

Per Capita Farmland

Group Home PeopleSubtotal Contracted

Per CapitaLand Loss

Option B Option A Option C

Unit group home person mu mu group home person mu mu mu group group group

Remarks

Zhangzhuang 8 560 2650 3700 1.4 123.80 Collective land

Wangzhuang 18 615 2720 7100 2.61 78.807 Contracted land

Zhangwangzhuang 6 55.059 Collective land Wenxian Wenquan

Township government 8.091 Contracted land

Heluo Qilipu 15 1100 4500 3150 0.70

170.645

Gongyi

Dayu Township government 129.59

8 Contracted land

1 Zhangwangzhuang

Subtotal 47 227

5 9870 13950 1.41 566

Dongcaoting 8 475 2000 5000 2.50 6 356 1521 82.78 82.78 0.050 6

Mahouzhuang 3 367 1728 2764.8 1.60 3 35 175 61.5 61.50 0.350 3

Lihouzhuang 6 210 1100 1320 1.20 5 5 20 3.32 3.32 0.170 5

Jiangou 6 350 1600 2880 1.80 2 50 210 60.27 54.00 0.260 2

Wuzhi Beiguo

Xicaoting 7 406 1720 4200 2.44 2 7 129.93 Contracted land

2 Dong’an

Subtotal 30 180

8 8148 16165 1.98 16 448 1933 337.8 201.60 0.104 10 6

Wuzhi Zhandian Yangyanjing 2 125 613 915 1.49 13.9 Collective land 3 Laotian’an

Subtotal 2 125 613 915 1.49 13.9 Panguan 8 440 2200 2900 1.318 2 65 346 41.19 41.19 0.119 2

Wuzhuang 9 432 1800 2800 1.556 1 6 24 4.11 4.11 0.171 1

Yisanzhuang 6 199 900 1615 1.794 6 30 144 83.94 74.92 0.52 6

Liyuechang 7.46 Collective land

Yuanyang Guanchang

Huanglianji 23.38 23.38 Unpaid

4 Wuzhuang

Subtotal 23 107

1 4900 7315 1.493 9 101 514 160.08 143.60 0.279 7 2

Nanliuzhuang 9 550 2454 7639 3.11 5 25 127 69.62 69.62 0.548 5 5 Mao’an Yuanyang Jintang

Baobei 8 460 1700 2981 1.703 39 Collective land

Page 223: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

210

Baonan 11 387 2000 2780 1.39 39 Contracted land

Baoxi 8 410 1720 2760 1.6 39 Collective land

Caozhuang 8 305 1600 2720 1.7 1 30 156 21.43 6.43 0.041 1

Zhu’an 6 303 1336 3998 2.993 6 303 1336 103.35 100.77 0.075 6

Subtotal 50 241

5 1081

0 22878 2.116 12 358 1619 311.4 176.82 0.109 6 6

Progress of Permanent Land Acquisition and Economic Rehabilitation – continued Original Affected Economic Rehabilitation

Floodland No. Component County/City Township Village Group Home People Farmland Per Capita Farmland Group Home People

Subtotal Contracted Per CapitaLand Loss Option B Option A Option C Others

Unit group home person mu mu group home person mu mu mu group group group groupRemarks

Shunzhong 2 237 1010 1568 1.552 2 66 315 94.7 94.7 0.301 2 Fengqiu Jinglonggong Shunnan 8 510 2056 3110 1.513 6 93 370 132.34 132.34 0.358 6 6 Shunhejie Subtotal 10 747 3066 4678 1.526 8 159 685 227.04 227.04 0.331 8

Fengqiu Chenqiao Chenqiao 189.00 Collective 7 Gucheng Subtotal 189.00 Shaozhai 116.55 Collective Fengqiu Caogang Changmenkou 11.16 Collective 8 Caogang

Subtotal 127.71 Taohuayu 5 210 890 731 0.821 43 Contracted Yingyang Guangwu Bawangcheng 14 Contracted 9 Taohuayu

Subtotal 5 210 890 731 0.821 57 Zhengzhou Huiji Farm 206.37 Farm 10 Baohezhai Subtotal 206.37 Zhongmou Wantan 32.46 Collective 11 Zhaokou Subtotal 32.46

Nanren 12 1156 5200 13000 2.5 7 80 410 286 249.1 0.608 7 Xinzhuang 8 715 3576 11700 3.27 1 16 62 104 40 0.645 1 Nanbeijie 18.44 Collective Zhongmou Langchenggang

Nanwei 39.10 Collective 12 Weitan

Subtotal 20 1871 8776 24700 2.814 8 96 472 447.54 158.44 0.613 289.1 7 Kaifeng Shuidao Nanbeidi 16 760 3700 3900 1.054 6 76 326 11.85 11.85 0.036 6 Fengqiu Jinglonggong Shunbei 6 438 1895 3025 1.596 13.63 Collective 13 Heigangkou

Subtotal 22 1198 5595 6925 1.238 6 76 326 25.48 13.63 0.036 11.85 6 Laozhaizhuang 6 112 513 550 1.10 8.693 Gaozhuang 6 180 784 1100 1.403 5 164 640 25.475 25.475 0.04 5 Wanglou 4 82 406 450 1.108 2 46 192 9.445 9.445 0.049 2

14 Laozhaizhuang Juancheng Jiucheng

Kangtun 13 380 1600 3200 2.00 13 15.4395 15.4395 9 4 Being paid

Page 224: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

211

Maowa 6 180 727 1525 2.098 4 138 549 18.8773 18.8773 0.034 4 Meizhuang 18.4718 18.4718 Unpaid Jiucheng 4.578 4.578 Unpaid

Subtotal 35 934 4030 6825 1.694 24 348 1381 100.9896 8.693 0.067 9 15 Total 10 17 41 244 12654 56698 105082 1.853 83 2323 10180 2802.76 1142.30 0.112 41 34 8

Page 225: RESETTLEMENT M&E MAIN REPORT (No. 7) · Jining, Tai’an, Jinan and Liaocheng Cities (Shandong). A total budget of 2,80432 million RMB was approved for 4 groups of subprojects by

ADB-loaned Yellow River Flood Management Sector Project River Training Subproject Resettlement M&E Report (Report No. 2)

212

Annex 5 Constituents and Changes of Incomes of Sample Households Per Capita Income by Sector (RMB)

Sideline Farming Subtotal Farmer Worker Others No. Village Sample Code Year People Per

Capita Farmland

(mu)

Per Capita Net

Income (RMB) Amount % Amount % Amount %

Fruit Animal Raising Amount %

2006 13 1.154 1893 935 49 923 49 923 100 0 0 35 2 2005 13 1.385 1402 1032 74 346 25 346 100 0 0 25 2 O

KDWZHGCHYSZH01

Change -0.23 491 -97 -24 577 24 577 0 0 0 10 0 2006 5 1.800 3150 1323 42 1800 57 1800 100 0 0 28 1 2005 5 2.400 3236 1621 50 1600 49 1600 100 0 0 16 0 2 KDWZHGCHYSZH02Change -0.60 -86 -298 -8 200 8 200 0 0 0 12 0 2006 6 0.900 1291 688 53 583 45 583 100 0 0 20 2 2005 6 1.667 1837 1141 62 667 36 667 100 0 0 30 2 3 KDWZHGCHYSZH03Change -0.767 -546 -453 -9 -83 9 -83 0 0 0 -10 2006 7 2.214 2234 2193 98 0 0 0 0 0 41 2 2005 7 2.857 3064 3013 98 0 0 0 0 0 51 2 4 KDWZHGCHYSZH04Change -0.643 -830 -820 0 0 0 0 0 0 -10 0 2006 5 0.400 928 309 33 600 65 600 100 0 0 20 2 2005 5 1.440 1325 1099 83 200 15 200 100 0 0 26 2 5

Yisanzhuang

KDWZHGCHYSZH05Change -1.040 -397 -790 -50 400 50 400 0 0 0 -6 0 2006 8 1.625 2332 1316 56 1000 43 1000 100 0 0 17 1 2005 8 1.625 1442 1425 99 0 0 0 0 0 18 1 6

KDFQJLGSHZH06

Change 0.000 890 -109 -42 1000 43 1000 100 0 0 -1 -1 2006 3 1.500 2850 825 29 2000 70 2000 100 0 0 25 1 2005 3 1.500 2261 506 22 1733 77 1733 100 0 0 22 1 7 KDFQJLGSHZH07Change 0.000 589 319 7 267 -6 267 0 0 0 3 0 2006 8 1.600 2572 1015 39 1538 60 1538 100 0 0 20 1 2005 8 1.600 2144 1521 71 600 28 600 100 0 0 24 1 8 KDFQJLGSHZH08Change 0.000 428 -506 -31 938 32 938 0 0 0 -4 0 2006 6 0.883 2538 713 28 1800 71 0 0 0 0 25 1 2005 6 1.050 1140 459 40 667 58 0 0 0 0 16 1 9

KDFQJLGSHZH09

Change -0.167 1398 255 -12 1133 12 0 0 0 0 9 0 2006 4 1.450 2755 1237 45 1500 54 1500 100 0 0 18 1 2005 4 1.600 2221 1073 48 1125 51 1125 100 0 0 24 1 10 KDFQJLGSHZH10Change -0.150 534 164 -3 375 4 375 0 0 0 -6 0 2006 5 0.720 2417 697 29 1700 70 1200 70.6 0 0 20 1 2005 5 1.160 2338 621 27 1700 73 1200 70.6 0 0 17 1 11

Shunzhong

KDFQJLGSHZH11

Change -0.440 79 76 2 0 -2 0 0 0 0 3 0 2006 2 0.600 5500 91 2 5400 98 5400 100 0 0 9 0 2005 2 1.100 1910 545 29 1350 71 1350 100 0 0 16 1 12

KDFQJLGSHN12

Change -0.500 3590 -453 -27 4050 28 4050 0 0 0 -7 -1 2006 4 1.100 1533 619 40 900 59 900 100 0 0 14 1 2005 4 1.100 1634 868 53 750 46 750 100 0 0 16 1 13

KDFQJLGSHN13

Change 0.000 -101 -249 -13 150 13 150 0 0 0 -2 0 2006 7 0.429 1749 590 34 1143 65 1143 100 0 0 16 1 2005 7 1.100 1909 750 39 1143 60 1143 100 0 0 16 1 14

KDFQJLGSHN14

Change -0.671 -160 -160 -6 0 5 0 0 0 0 0 0 2006 5 1.320 1086 479 44 600 55 600 100 0 0 7 1 2005 5 1.320 999 381 38 600 60 600 100 0 0 18 2 15

KDFQJLGSHN15

Change 0.000 87 98 6 0 -5 0 0 0 0 -11 -1 2006 6 1.417 2629 1110 42 1500 57 1500 100 0 0 19 1 2005 6 1.417 678 662 98 0 0 0 0 0 0 16 2 16

KDFQJLGSHN16

Change 0.000 1951 448 -55 1500 57 1500 100 0 0 3 -2 2006 7 1.214 2667 948 36 1714 64 1714 100 0 0 5 0 2005 7 1.214 861 845 98 0 0 0 0 0 0 17 2 17

KDFQJLGSHN17

Change 0.000 1806 104 -63 1714 64 1714 100 0 0 -12 -2 2006 5 0.660 2782 377 14 2400 86 2400 100 0 0 5 0 2005 5 0.660 1308 498 38 800 61 800 100 0 0 10 1 18

KDFQJLGSHN18

Change 0.000 1474 -121 -25 1600 25 1600 0 0 0 -5 -1 2006 6 0.250 3006 200 7 2800 93 2800 100 0 0 7 0 2005 6 1.100 646 443 69 188 29 188 100 0 0 16 3 19

KDFQJLGSHN19

Change -0.850 2360 -243 -62 2613 64 2613 0 0 0 -9 -2 2006 5 0.800 1868 886 47 960 51 960 100 0 0 22 1 2005 5 1.200 942 626 66 300 32 300 100 0 0 16 2 20

KDFQJLGSHN20

Change -0.400 926 260 -19 660 20 660 0 0 0 6 0 2006 2 0.150 769 0 0 625 81 625 100 0 0 144 19 2005 2 1.250 896 737 82 0 0 0 0 0 160 18 21

KDFQJLGSHN21

Change -1.100 -127 -737 -82 625 81 625 100 0 0 -16 1 2006 6 0.417 1345 283 21 1050 78 1050 100 0 0 12 1 2005 6 1.100 1704 638 37 1050 62 1050 100 0 0 16 1 22

KDFQJLGSHN22

Change -0.683 -359 -355 -16 0 16 0 0 0 0 -4 0 2006 6 0.400 2649 305 12 2333 88 2333 100 0 0 11 0 2005 6 1.100 2877 528 18 2333 81 2333 100 0 0 16 1 23

KDFQJLGSHN23

Change -0.700 -228 -223 -7 0 7 0 0 0 0 -5 0 2006 9 0.733 2523 383 15 2133 85 2133 100 0 0 7 0 2005 9 0.733 497 486 98 0 0 0 0 0 0 11 2 24

KDFQJLGSHN24

Change 0.000 2026 -104 -83 2133 85 2133 100 0 0 -4 -2 2006 4 1.350 2111 737 35 1350 64 1350 100 0 0 25 1 2005 4 1.350 2062 692 34 1350 65 1350 100 0 0 20 1 25

Shunnan

KDFQJLGSHN25

Change 0.000 49 44 1 0 -2 0 0 0 0 5 0 2006 144 1.042 2234.2 789 35 1425 64 1333 93.5 0 0 20 1 2005 144 1.372 1613.8 942 58 649 40 604 93 0 0 22 1 Total Change 0 -0.329 620 -154 -23 776 24 729 1 0 0 -2 0

Note: For the sample households whose change of per capita farmland is zero, their autumn crops were affected only in 2006.