Steps to create new project. 1 Open blank Microsoft office project file. 2 Create new calendar according to the given data.:TOOLS-CHANGE WORKING 3 Specify the start date of the project and calendar.PROJECT MENU- PRO 4 Assign the calendar in GANTT area. 5 Add activities.(Copy activities from given excel sheet). 6 Assign the WBS.Your WBS code & given WBS code should match. 7 Link activities.

Upload: rpkodam

Post on 19-Oct-2015

9 views

Category:

Documents


0 download

DESCRIPTION

ddd

TRANSCRIPT

PRACTICE

STEPSSteps to create new project.1Open blank Microsoft office project file.2Create new calendar according to the given data.:TOOLS-CHANGE WORKING TIME3Specify the start date of the project and calendar.PROJECT MENU- PROJECT INFORMATION4Assign the calendar in GANTT area.5Add activities.(Copy activities from given excel sheet).6Assign the WBS.Your WBS code & given WBS code should match.7Link activities.

ACTIVITIES & INSTRUCTIONSASSIGNMENT NO.1Strictly follow the following steps1Set the new calendar for the current project as per following conditions.Projecti) Working days are from Monday to Saturday.startii) Working time from Monday to Saturday is 9:00 -01:00pm. 2:00-6:00pmdateiii)Lunch Break from Monday to Saturday is 1:00 to 2:00pm1st Nov.12iv) Sunday is non working day from start to end of the project.2 Project start date is 1st Feb. 2011.3 Copy all the given activities & it's durations in msp 2007.4Prepare the WBS as given below only.The WBS code should match with given WBS code. i.e.A37 to A1435Please do not edit the given data.

Outline CodeW.B.S. NAMELevel Of WBS1Project "ABC"11.1General works21.2Substructure21.2.1Foundations31.2.2Basement RCC31.3Superstructure21.3.1Ground Floor RCC31.3.2First Floor RCC31.3.3Second floor RCC31.3.4Brickworks, door frames 31.3.5Internal Plaster 31.3.6External Plaster 31.3.7Concealed Conduiting & Waterproofing 31.3.8Aluminum Windows & grills Fixing31.3.9Toilet Dado 31.3.10TILING Flooring & Kitchen Dado 31.3.11Fixing doors shutters 31.3.12Internal Painting 31.3.13External Painting 31.3.14Sanitory Wares & Electrical Fittings 31.3.15Building Services3

W.B.STASK NAMESDURATIONS (day)1PROJECT "ABC"1.1General works1.1.1Obtain building permits41.1.2Install temporary power231.1.3Install temporary water service231.1.4Set up site office231.1.5Prepare site - lay down yard and temporary fencing26SS1.1.6Clear the site37SS+1 day1.1.7Lineout28FS-1 day,4,5,6,71.2Substructure1.2.1Foundations1.2.1.1.Excavations of foundations791.2.1.2Excavations of elevator pit191.2.1.3P.C.C. for all footings2131.2.1.4Reinforcement works for footings and columns714SS+2 days1.2.1.5Formwork for footings315SS+6 days,12,141.2.1.6Prepare and pour concrete for basement floor 31.2.2Basement (RCC)16FS+1 day1.2.2.1Casting of Columns1218SS+2 days1.2.2.2Casting of Lift wall 518SS+2 days1.2.2.3Casting of Staircase 718SS+6 days1.2.2.4Shuttering work for slab721,18,19,201.2.2.5Slab casting11.3Superstructure1.3.1Ground Floor (RCC)221.3.1.1Casting of Columns1225SS+2 days1.3.1.2Casting of Lift wall 525SS+2 days1.3.1.3Casting of Staircase 727SS+2 days1.3.1.4Shuttering work for slab725,28,26,271.3.1.5Slab casting11.3.2First Floor (RCC)291.3.2.1Casting of Columns1231SS+2 days1.3.2.2Casting of Lift wall 531SS+2 days1.3.2.3Casting of Staircase 733SS+2 days1.3.2.4Shuttering work for slab731,34,32,331.3.2.5Slab casting11.3.3Second floor (RCC)351.3.3.1Casting of Columns1237SS+2 days1.3.3.2Casting of Lift wall 537SS+2 days1.3.3.3Casting of Staircase 739SS+2 days1.3.3.4Shuttering work for slab737,40,38,391.3.3.5Slab casting11.3.4Brickworks, fixing of door frames 22FS+15 days1.3.4.1Basement1029FS+15 days1.3.4.2Ground1035FS+15 days1.3.4.3First1041FS+15 days1.3.4.4Second101.3.5Internal Plastering431.3.5.1Basement944,481.3.5.2Ground945,491.3.5.3First9461.3.5.4Second91.3.6External Plastering43,44,45,461.3.6.1Backside surface10531.3.6.2Left side surface7541.3.6.3Front side surface10551.3.6.4Right side surface71.3.7External Painter531.3.7.1Backside surface954,581.3.7.2Left side surface755,591.3.7.3Front side surface956,601.3.7.4Right side surface71.3.8Concealed Conduiting (Plumbing) & Waterproofing for toilets and bathrooms43,611.3.8.1Basement744,631.3.8.2Ground745,641.3.8.3First7461.3.8.4Second71.3.9Aluminum Windows & grills Fixing48,881.3.9.1Basement1049,89,681.3.9.2Ground1050,90,691.3.9.3First1051,91,701.3.9.4Second101.3.10Toilet Dado 631.3.10.1Basement1064,731.3.10.2Ground1065,741.3.10.3First1066,751.3.10.4Second101.3.11TILING Flooring & Kitchen Dado 481.3.11.1 Basement 749,781.3.11.2Ground750,791.3.11.3First7511.3.11.4Second71.3.12FIXING DOOR SHUTTERS 481.3.12.1 Basement 849,831.3.12.2Ground850,841.3.12.3First851,851.3.12.4Second81.3.13Internal Painting 781.3.13.1 Basement 1579,881.3.13.2Ground1580,891.3.13.3First1581,901.3.13.4Second151.3.14Sanitory Wares & Electrical Fittings 481.3.14.1 Basement 749,931.3.14.2Ground750,941.3.14.3First751,951.3.14.4Second71.3.15Building Services161.3.15.1Procurement of lift6056FS+7 days1.3.15.2Lift Installation work1518SS+2 days,991.3.15.3Procurement of DG 1518SS+2 days1.3.15.4Procurement of Transformor15281.3.15.5Installation of DG 15281.3.15.6Installation of Transformor1561SS+4 days1.3.15.7HT & LT Cabling work1566SS+5 days1.3.15.8Fire fighting system151.3.15.9Building Finishing3

Tips.1) Select any activity and decide which activity will be predecessors and successors for the current activity.2) If possible, link activities in parallel3) Except first and last activity, remaining all activities should not be open ended4) Try to reduce the total project durations.5) All relationships between activities shouls be realisticQ.N.1Find the total durations of the above project.

1.Project "ABC"1.2 Substructure1.3 Superstructure1.1 General

RESOURCESStrictly follow the following steps to assign the resources1Change the existing currency and specify new indian currency INR, symbol is Rs.2Copy following resources in the resource sheetAssumption: To execute all works, it is alloted to sub contractor with materials.RESOURCE NAME Material labelRATES1R.C.C.CUM60003100 mm Thk. WallSqm5504150 mm Thk . Wall Sqm5505200 mm Thk wall Sqm5506FW door Qty Sqm26007Door frames Rm4508Internal Plaster Sqm2509celling Plaster Sqm10010Toilet s water Proofing Sqm65011Aluminium powder coated sliding windowsSqm240012Cermic- Glazed Tiles Sqm10013Virtified Tiles Flooring Sqm90014Virtified Tiles Skirting Rm9015Cermic Tiles FlooringSqm70016Cermic Tiles SkirtingRm7017Anti-Skid Ceramic Tiles Sqm70018Black Granite platform in kitchenRm500019D1Sqm250020D2Sqm135021D3Sqm135022D4Sqm135023Internal Painting Sqm5024Sanitary Wares & Electrical Fittings Sqm5025External plasteringsqm27526External paintingsqm7527Excavationcum10028P.C.C.cum150029Female coolie150/d30Male coolie200/dBefore assigning any resources please follow next steps1) Select all activities2) Right click, task information,select advanced,select task type as fixed durations

W.B.STASK NAMESDURATION (day)BUDGETED RESOURCES 1Project "ABC"All works will be executed by the sub-contractor only.1.1General worksObtain building permits415000Install temporary power225000Install temporary water service210000Set up site office225000Prepare site - lay down yard and temporary fencing215000Clear the site35000Lineout2350001.2Substructure1.2.1FoundationsExcavations of foundations7Excavation (125 cum)Excavations of elevator pit1Excavation (50 cum)P.C.C. for all footings3P.C.C.(15 cum)Reinforcement works for footings and columns uptp basement floor7Rcc (20 cum)Prepare and pour concrete for basement floor 7Rcc (35 cum)1.2.2Basement (RCC)Casting of Columns12Rcc (30cum)Casting of Lift wall 5Rcc (2cum)Casting of Staircase 7Rcc (1.5cum)Shuttering work for slab7Slab casting1Rcc (90 cum)1.3Superstructure1.3.1Ground Floor (RCC)Casting of Columns12Rcc (30cum)Casting of Lift wall 5Rcc (2cum)Casting of Staircase 7Rcc (1.5cum)Shuttering work for slab7Slab casting1Rcc (90 cum)1.3.2First Floor (RCC)Casting of Columns12Rcc (30cum)Casting of Lift wall 5Rcc (2cum)Casting of Staircase 7Rcc (1.5cum)Shuttering work for slab7Slab casting1Rcc (90 cum)1.3.3Second floor (RCC)Casting of Columns12Rcc (30cum)Casting of Lift wall 5Rcc (2cum)Casting of Staircase 7Rcc (1.5cum)Shuttering work for slab7Slab casting1Rcc (90 cum)1.3.4Brickworks, fixing of door frames Basement10100 mm Thk.wall(280 sqm),150mm thk.wall(480 sqm),200mm thk.wall(240 sqm),FW door Qty(50 sqm),Door frames(sal wood)(210 Rm)Ground10100 mm Thk.wall(280 sqm),150mm thk.wall(480 sqm),200mm thk.wall(240 sqm),FW door Qty(50 sqm),Door frames(sal wood)(210 Rm)First10100 mm Thk.wall(280 sqm),150mm thk.wall(480 sqm),200mm thk.wall(240 sqm),FW door Qty(50 sqm),Door frames(sal wood)(210 Rm)Second10100 mm Thk.wall(280 sqm),150mm thk.wall(480 sqm),200mm thk.wall(240 sqm),FW door Qty(50 sqm),Door frames(sal wood)(210 Rm)1.3.5Internal PlasteringBasement9Internal Plaster (2849 SQM),celling plaster (964 sqm)Ground9Internal Plaster (2849 SQM),celling plaster (964 sqm)First9Internal Plaster (2849 SQM),celling plaster (964 sqm)Second9Internal Plaster (2849 SQM),celling plaster (964 sqm)1.3.6External PlasteringExternal Plaster (500 SQM)Backside surface10External Plaster (500 SQM)Left side surface7External Plaster (500 SQM)Front side surface10External Plaster (500 SQM)Right side surface7External Plaster (500 SQM)1.3.7External PainterBackside surface9External Painting (500 SQM)Left side surface7External Painting (500 SQM)Front side surface9External Painting (500 SQM)Right side surface7External Painting (500 SQM)1.3.8Concealed Conduiting (Plumbing) & Waterproofing for toilets and bathroomsBasement7Toilet s water Proofing (77 sqm)Ground7Toilet s water Proofing (77 sqm)First7Toilet s water Proofing (77 sqm)Second7Toilet s water Proofing (77 sqm)1.3.9Aluminum Windows & grills FixingBasement10Aluminium powder coated sliding windows(80 sqm)Ground10Aluminium powder coated sliding windows(80 sqm)First10Aluminium powder coated sliding windows(80 sqm)Second10Aluminium powder coated sliding windows(80 sqm)1.3.10Toilet Dado Basement10Cermic- Glazed Tiles (340 sqm)Ground10Cermic- Glazed Tiles (340 sqm)First10Cermic- Glazed Tiles (340 sqm)Second10Cermic- Glazed Tiles (340 sqm)1.3.11TILING Flooring & Kitchen Dado Basement 7Virtified Tiles Flooring (495 sqm),Vetrified tiles skirting(566 Rm),Cermic flooring(143 sqm),Cermic tiles skirting(199 Rm),Anti-skid ceramic tiles (165 sqm),black granit platform in kitchen(21 RM)Ground7Virtified Tiles Flooring (495 sqm),Vetrified tiles skirting(566 Rm),Cermic flooring(143 sqm),Cermic tiles skirting(199 Rm),Anti-skid ceramic tiles (165 sqm),black granit platform in kitchen(21 RM)First7Virtified Tiles Flooring (495 sqm),Vetrified tiles skirting(566 Rm),Cermic flooring(143 sqm),Cermic tiles skirting(199 Rm),Anti-skid ceramic tiles (165 sqm),black granit platform in kitchen(21 RM)Second7Virtified Tiles Flooring (495 sqm),Vetrified tiles skirting(566 Rm),Cermic flooring(143 sqm),Cermic tiles skirting(199 Rm),Anti-skid ceramic tiles (165 sqm),black granit platform in kitchen(21 RM)1.3.12FIXING DOOR SHUTTERS Basement 8D1(15 SQM),D2(37 SQM),D3(11 SQM),D4(41 SQM)Ground8D1(15 SQM),D2(37 SQM),D3(11 SQM),D4(41 SQM)First8D1(15 SQM),D2(37 SQM),D3(11 SQM),D4(41 SQM)Second8D1(15 SQM),D2(37 SQM),D3(11 SQM),D4(41 SQM)1.3.13Internal Painting Basement 15Internal Painting (2850 sqm)Ground15Internal Painting (2850 sqm)First15Internal Painting (2850 sqm)Second15Internal Painting (2850 sqm)1.3.14Sanitory Wares & Electrical Fittings Basement 7Sanitary Wares & Electrical Fittings (10156 sqm)Ground7Sanitary Wares & Electrical Fittings (10156 sqm)First7Sanitary Wares & Electrical Fittings (10156 sqm)Second7Sanitary Wares & Electrical Fittings (10156 sqm)1.3.15Building ServicesProcurement of lift15Fixed cost Rs.400000Lift Installation work15Fixed cost Rs.25000Procurement of DG 15Fixed cost Rs.300000Procurement of Transformor15Fixed cost Rs.100000Installation of DG 15Fixed cost Rs.15000Installation of Transformor15Fixed cost Rs.300000HT & LT Cabling work15Fixed cost Rs.50000Fire fighting system15Fixed cost Rs.15000Building Finishing3Total male coolie -15,Total female coolie -15Find the total cost of the project.