saic-l-2074 rev 0

2
1. SAES-H- 200, Storage, Handling and Installation o f Externally Coated Pipe, 31 July, 2004 2. 01-SAMSS-024, Pipe Handling and Nesting, 29 October, 2003 3. SAES-L-350, Construction of Plant Piping , 30 September, 20 03 4. SAES-H-100, Coating Materials & Appli cation Requir ements for Indu strial Facili ties, 31 July, 2004 5. AWWA C205, Cement-Mortar Lining..., 11 June 2000 6. Saudi Aramco Form 175-012500, Concrete-Mortar Lining, March 1998 REMARKS: REFERENCE DOCUMENTS:  A9 Handling, Loading & Stacking, Plastic End Cap requirements as per Final Inspection & Testing Requirements, is observed. SA Form 175- 012500  A8 The maximum number of rows in a stack of pipe is limited by the maximum allowable static load stress in the wall of the most heavily loaded pipe in the bottom row of the stack. For stacks in the pipe yard: 0.6 times the SMYS of the pipe material. 01-SAMSS-024 Para. 7.1  A7 Plastic end caps are securely fastened to ends of completed pipe for protection of the cement-mortar lining. End caps are maintained in place until time of installation.  AWWA C205 Sec. 6.2  A6 Fittings are stored in shipping crates or on racks. SAES-L-350 Para. 7.3  A5 Filler material used at construction sites is covered with appropriate canvas, tarpaulins, or equivalent for a temporary storage period not to exceed 14 days. SAES-H-100 Para. 6.2  A4 Filler material is stored in well-ventilated buildings at storage temperatures as recommended in the Manufacturer's data sheet SAES-H-100 Para. 6.1  A3 Lined pipes and fittings are lifted with wide fabric or rubber-covered slings and padding is used to prevent damage to lining, in accordance with SAES-H-200. SAES-L-350 Para. 8.2  A2 Internally coated or lined pipes are handled from the outside diameter (OD) only. 01-SAMSS-024 Para. 5.1.6 RE-INSP DATE  A1 Internally coated or lined pipe is handled at all times in a manner that prevents damage. SAES-H-200 Para. 5.1.1 REFERENCE PASS FAIL N/A Y = YES N = NO F = FAILED *Person Responsible for Comple tion of Quality Work / Test QC Super visor Proponent and Other s Cont r act or / Thir d-Part y Saudi Ar amco Name, Sign and Date: Quality Record Approved: Work Verified Perf or med Inspectio n Work / Rework May Pr oceed Work is Complete and Ready for Inspection: Name, Initials and Date: Name, Initials and Date: QC Inspect or PID Repr esent at i ve QC Record Reviewed Construction Representative* PMT Representative Work Verified T&I Witnessed Name, Initials and Date: Name, Initials and Date: T&I Wit ne ssed QC Re co rd Re vi ewed Name, Organization, Initials and Date: T&I Witne ssed QC Re c or d R ev i ewed Work Verified SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004) SAUDI ARA MCO INSPE CTION CHE CKL IS SAIC NUMBER DATE APPROVED QR NUMBER PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR Storage, Handling and Preservation of Cement Lined Pipe/Fittings and Joint Filler Materials SAIC-L-2074 25-May-05 PIPE- PLANT NO. EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO. TRAVEL TIME SAUDI ARAMCO USE ONLY SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED? SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL ITEM No.  ACCEPTANCE CRITERIA Page 1 of 1

Upload: philipyap

Post on 02-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SAIC-L-2074 Rev 0

7/27/2019 SAIC-L-2074 Rev 0

http://slidepdf.com/reader/full/saic-l-2074-rev-0 1/1

1. SAES-H-200, Storage, Handling and Installation o f Externally Coated Pipe, 31 July, 2004

2. 01-SAMSS-024, Pipe Handling and Nesting, 29 October, 2003

3. SAES-L-350, Construction of Plant Piping , 30 September, 2003

4. SAES-H-100, Coating Materials & Appli cation Requirements for Industrial Facili ties, 31 July, 2004

5. AWWA C205, Cement-Mortar Lining..., 11 June 2000

6. Saudi Aramco Form 175-012500, Concrete-Mortar Lining, March 1998

REMARKS:

REFERENCE DOCUMENTS:

 A9Handling, Loading & Stacking, Plastic End Cap requirements as per 

Final Inspection & Testing Requirements, is observed.

SA Form 175-

012500

 A8

The maximum number of rows in a stack of pipe is limited by the

maximum allowable static load stress in the wall of the most heavily

loaded pipe in the bottom row of the stack. For stacks in the pipe yard:0.6 times the SMYS of the pipe material.

01-SAMSS-024

Para. 7.1

 A7

Plastic end caps are securely fastened to ends of completed pipe for 

protection of the cement-mortar lining. End caps are maintained in place

until time of installation.

 AWWA C205

Sec. 6.2

 A6 Fittings are stored in shipping crates or on racks.SAES-L-350

Para. 7.3

 A5

Filler material used at construction sites is covered with appropriate

canvas, tarpaulins, or equivalent for a temporary storage period not to

exceed 14 days.

SAES-H-100

Para. 6.2

 A4Filler material is stored in well-ventilated buildings at storage

temperatures as recommended in the Manufacturer's data sheet

SAES-H-100

Para. 6.1

 A3

Lined pipes and fittings are lifted with wide fabric or rubber-covered

slings and padding is used to prevent damage to lining, in accordance

with SAES-H-200.

SAES-L-350

Para. 8.2

 A2Internally coated or lined pipes are handled from the outside diameter 

(OD) only.

01-SAMSS-024

Para. 5.1.6

RE-INSP DA

 A1Internally coated or lined pipe is handled at all times in a manner that

prevents damage.

SAES-H-200

Para. 5.1.1

REFERENCE PASS FAIL N/A

Y = YES N = NO F = FA*Person Responsible for Completion of Quality Work / Test

QC Supervisor Proponent and Others

Contractor / Third-Party Saudi Aramco

Name, Sign and Date:

Quality Record Approved: Work Verified

Performed Inspection Work / Rework May Proceed

Work is Complete and Ready for Inspection:

Name, Initials and Date:

Name, Initials and Date:

QC Inspector PID Representative

QC Record Reviewed

Construction Representative* PMT RepresentativeWork VerifiedT&I Witnessed

Name, Initials and Date:

Name, Initials and Date:

T&I Wi tnessed QC Record Reviewed

Name, Organization,

Initials and Date:

T&I Wi tnessed QC Record Reviewed

Work Verified

SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

SAUDI ARAMCO INSPECTION CHECKLISSAIC NUMBER DATE APPROVED QR NUMBER

PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Storage, Handling and Preservation of Cement Lined Pipe/Fittings and

Joint Filler MaterialsSAIC-L-2074 25-May-05 PIPE-

PLANT NO.EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

TRAVEL TIMSAUDI ARAMCO USE ONLY

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT

SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUI

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM

No. ACCEPTANCE CRITERIA

Page 1 of 1