sil & partial stroke testing solutionstation
TRANSCRIPT
![Page 1: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/1.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 1/42
SIL & Partial StrokeTesting Solutions
Permission granted for ISA Houston Section Website
![Page 2: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/2.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 2/42
© Metso2
OSHA 29 CFR 1910.119
“Process Safety Management (PSM) of Highly HazardousChemicals”
EPA 40 CFR 68“Chemical Accident Prevention Provisions”
• Hazards must be identified and appropriate measures takento protect employees, the community and the environment.
• Compliance requires use of “generally accepted goodengineering practice.”
Permission granted for ISA Houston Section Website
![Page 3: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/3.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 3/42
© Metso
Safety valve as part of the Safety InstrumentedSystem (SIS)
3
FT
Distributed Control
System (DCS)Inputs Outputs
Reactor
PT1A
PT1B
Safety System
Inputs Outputs
Permission granted for ISA Houston Section Website
![Page 4: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/4.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 4/42
© Metso4
Process Control System
(BPCS)
Safety Instrumented System
(SIS)
• Controls the process• Dynamic
• Failures “revealed”.
• Reduces risk• Passive
• Failures “hidden”
• To reduce risks associatedwith abnormal operation,availabil i ty must be high(probability of failure ondemand, PFD , must be low)
• Availability confirmed bytesting.
Permission granted for ISA Houston Section Website
![Page 5: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/5.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 5/42
© Metso
Safety instrumented system (SIS) for processindustries
• SIS monitors the process and ensuressafety by taking process to safe state
when unconventional condition occur• Safety engineers have been challenged to
comply string safety requirements
• Intelligent ESD valve solutions help to
reach the most demanding safety solutiontargets for final elements with minimuminvestment.
Permission granted for ISA Houston Section Website
![Page 6: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/6.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 6/42
© MetsoUNCLASSIFIED
Safety Standards To Comply With...
Safety
System
• IEC 61508: Functional Safety of Electrical /Electronic / Programmable Electronic Safety-Related Systems
• IEC 61511: Functional Safety InstrumentedSystems for the Process Industry Sector
• More redundant systems or more testing neededthan before
• This leads to very high CAPEX (capital expense)and OPEX (operating expense) unless the latesttechnology is utilized
Permission granted for ISA Houston Section Website
![Page 7: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/7.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 7/42
© Metso7
One study has shown
that valves can
represent as much
as 50% o f all SIS
failures.
One study has shown
that valves can
represent as much
as 50% o f all SIS
failures.
50%o f al l SIS fai lures
as much as
OREDA:Analysis of Safety Loop Failures
Permission granted for ISA Houston Section Website
![Page 8: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/8.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 8/42
© Metso8
0
0
1
1
2
3
3
0
0
1
1
2
3
3
4
0
1
1
2
3
3
4
4
0
P3 P2 P1
D1
D2
D3
D4
E1
E2
E1
E2
A1
A2
A1
A2
D - Extent of Damage
• D1: slight injury
• D2: severe injuries or one death
• D3: death of several persons
• D4: multiple deaths
E - Exposure Time
• E1: seldom to relatively frequent
• E2: frequent to continuous
A - Hazard Avoidance
• A1: possible under certain conditions
• A2: hardly possible
P - Probability to occur
• P1: very low
• P2: low
• P3: relatively high
Consequence only method: D
Risk matrix method: D + P Permission granted for
ISA Houston Section Website
![Page 9: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/9.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 9/42
© MetsoUNCLASSIFIED
“Off-line diagnostics”
(= periodic maintenance)
Validation - PFD for Component
Where:
λ d = dangerous failure rate = 1/MTBFd
MTBFd = mean time between dangerous failures
MTTR = mean time to repair
DC = diagnostic coverage factor
TIa = test interval for automatic testing
TIm = test interval for manual testing (= maintenance period)
“On-line diagnostics”
(= testing)
Permission granted for ISA Houston Section Website
![Page 10: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/10.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 10/42
UNCLASSIFIED
![Page 11: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/11.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 11/42
© Metso
UNCLASSIFIED
SIL vs. Probability of Failure on Demand
Difference between SILs is
an order of magnitude!
PFD = Probability to Fail on DemandWhat is the chance that the system fails
Permission granted for ISA Houston Section Website
![Page 12: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/12.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 12/42
© Metso12
I10-5 to 10-4
Probability of failure to
perform its design
function on demand
10-4 to 10-3
10-3 to 10-2
10-2 to 10-1
4
3
2
1
Low demand Mode: Frequency of demand no greater than once per year andno greater than twice the proof check frequency
Safety Availability
(1-PFD) X 100%
99.99% to 99.999%
99.90% to 99.99%
99.00% to 99.90%
90.00% to 99.00%
(IEC /ISA)
(IEC/ISA)
(IEC/ISA)
(IEC/ISA)
Safety Integrity Level
(SIL)(How reliable the SIS needs to be to reduce
a particular r isk to an acceptable level)
Permission granted for ISA Houston Section Website
![Page 13: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/13.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 13/42
© Metso
Validation - Calculating PFD
MTBFd = 50 years
SIL 3
SIL 2
SIL 1
Where, λ d = dangerous failure rate
TI = testing interval (shutdown interval)
Permission granted for ISA Houston Section Website
![Page 14: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/14.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 14/42
© Metso
Validation - PFD with diagnostic coverage
MTBFd = 50 years, DCF = 75%
SIL 3
SIL 2
SIL 1
Permission granted for ISA Houston Section Website
![Page 15: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/15.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 15/42
© Metso
Motivation to use partial valve stroke testing
• Safety valve proof testing is mandatory activity in accordance of
IEC 61511 standard
- Interval is defined according to the safety requirement of the plant
- BUT interval can be influenced with• Product selection (hardware fault tolerance reduction)
• PST implementation (online testing of critical components)
15
Maximizedproduction with
PST
…and at the same timesafety is improvedwith intelligent PST
valve stickinghigher needed torque
Permission granted for ISA Houston Section Website
![Page 16: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/16.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 16/42
© Metso
What is a safety valve?
• ESD (emergency shut down)valves or ESV (emergencyventing) valves operating in
demanding environment
• Part of Safety InstrumentedSystem (SIS)
• Defense against processupsets
• Operating only in trip situation
16Permission granted for ISA Houston Section Website
![Page 17: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/17.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 17/42
17Permission granted for ISA Houston Section Website
![Page 18: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/18.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 18/42
![Page 19: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/19.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 19/42
© Metso19
A solution to the dilemma:
“Run longer, test more often.”
?
Bypass
Partial strokeShutdown
Demand for
Uptime
Demand
for testing
Permission granted for ISA Houston Section Website
![Page 20: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/20.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 20/42
© Metso
Partial Stroke Testing Options
• Mechanical Jammer
• Instrumentation Based Custom Panel
• Redundant Solenoids
• Digital Positioner + solenoid
• Control System Based Solution
• PST with an Intelligent Safety Valve Controller
20Permission granted for ISA Houston Section Website
![Page 21: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/21.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 21/42
© Metso
Partial Stroke Testing Options
21
Jammer Based Solution
• Safety loop disabled during PST
• No real diagnostics information from the PST
• Testing requires manual work -> higher testing
costs• Human interaction always required for PST ->
safety risk
• The safety solenoid is tested only during PST
• Full stroke test needs to be done manually
Permission granted for ISA Houston Section Website
![Page 22: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/22.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 22/42
© Metso
Partial Stroke Testing Options
Instrumentation Based Solution
•Complicated system with multiple potential failurecauses
•Safety loop usually disabled during PST
•No real diagnostics information from the PST•Testing requires manual work -> high testing costs
•Human interaction always required for PST ->safety risk
•In most cases the safety solenoid is not tested
•Full stroke test needs to be done manually
Permission granted for ISA Houston Section Website
![Page 23: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/23.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 23/42
© Metso
Partial Stroke Testing Options
23
Redundant Solenoids
• PST not available or it requires difficult, manualconfiguration
• No diagnostics
• The solenoids can not be tested automatically• Full stroke test needs to be done manually
Permission granted for ISA Houston Section Website
![Page 24: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/24.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 24/42
© Metso
Partial Stroke Testing Options
Positioner + Solenoid
•Higher nuisance trip rate
•Solenoid can not be testedautomatically
•Manual testing and interpretation of
test results
Permission granted for ISA Houston Section Website
![Page 25: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/25.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 25/42
© Metso
Partial Stroke Testing Options
Control System Based Solution
•Use DCS to initiate and Monitor PST
•Solenoid and Limit Switch configuration
•Diagnostics Limited to timing of PST
•Limited Safety Features
Permission granted for ISA Houston Section Website
![Page 26: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/26.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 26/42
© Metso
Partial Stroke Testing Options
Intelligent PST Solution
• Safety loop enabled during PST
• Diagnostics information from PST Possibility to optimize ESD valvemaintenance
• Automated PST -> no testing costs
• Seamless Communication with DTMor EDDL
• HART Based
26Permission granted for ISA Houston Section Website
P i l S k T i O i
![Page 27: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/27.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 27/42
© Metso
Partial Stroke Testing Options
Intelligent PST Solution - continued
• Human interaction not required for
PST more effective use ofmaintenance resources
• Emergency trip captured
• Self documentation
• Improves safety while making lifeeasier with safety valves
• 3rd part certification (i.e. TÜV, Exida)
27Permission granted for ISA Houston Section Website
![Page 28: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/28.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 28/42
© Metso
Potential Issues with Conventional PST
• Human interaction is typicallyrequired
• The safety system must bedisabled during testing
• Testing creates high costs due tohuman factors
28Permission granted for ISA Houston Section Website
P t ti l I ith C ti l PST
![Page 29: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/29.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 29/42
© Metso
Potential Issues with Conventional PST
• Testing intervals are long
• Little or no diagnosticsinformation is received when thetests are being performed
• Safety solenoid valve might notbe tested at all
• Complex instrumentation is oftenrequired for conducting the tests
29Permission granted for ISA Houston Section Website
R t I t t i t lli t PST
![Page 30: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/30.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 30/42
© Metso
Recent Improvements to intelligent PST
• High Pneumatics Capacity- Improve SIL level by limiting need for
pneumatic accessories with lower PFD values
• Internal pneumatics test
- Improve PFD of valve controller with internaltesting that doesn’t move the valve
• PST stroke randomizer- Prevent buildup on the safety valve by
randomizing the stroke size
• Integrated Limit Switches
• Emergency trip test
- Report safety test figures• Full interoperability with all major safety
systems and asset management systems
30Permission granted for ISA Houston Section Website
E l f Di ti ith I t lli t PST f
![Page 31: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/31.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 31/42
© Metso
Example of Diagnostics with Intelligent PST forpredictive maintenance• Load factor and breakaway pressure
- Trends collected from partial stroke tests
- Results shown test based not time based
• Enables predictive maintenance- Potential valve failures can be detected in advance
31Permission granted for ISA Houston Section Website
The valve is in original condition
![Page 32: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/32.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 32/42
© Metso
0 % 10 % 20 % 30 % 40 % 50 % 60 % 70 % 80 % 90 % 100 %
Actuator outputtorque
Needed valve torque
The valve is in original condition
0 %
10 %
20 %
30 %
40 %50 %
60 %
70 %
80 %
90 %
100 %
Load factor trend for 10 latest PST's
FULLY OPENFULLY CLOSED
T O R Q U E
WARNING LIMIT
Permission granted for ISA Houston Section Website
When the needed valve torque exceeds the
![Page 33: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/33.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 33/42
© Metso
0 %
10 %
20 %
30 %
40 %50 %
60 %
70 %
80 %
90 %
100 %
Load factor trend for 10 latest PST's
0 % 10 % 20 % 30 % 40 % 50 % 60 % 70 % 80 % 90 % 100 %
Actuator outputtorque
Needed valve torque
qavailable actuator output torque, the valve is stuck
FULLY OPENFULLY CLOSED
T O R Q U E
WARNING LIMIT
Permission granted for ISA Houston Section Website
With less instrumentation, It can be easier, safer and more reliable
![Page 34: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/34.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 34/42
© Metso
, ,
34
ESD ball valve with:
• PST Device
• Inductive proximity
switches or positiontransmitter
• Filter regulator
• Volume booster ¾”
• ASCO solenoid valve
• Mounting panel
• Tandem mounting
• Tubing and fittings
Not Needed:Cv of SMARTPST Device
Not needed,
internal SOV
Not needed
Not needed
Less tubing andfittings, since SOVand booster can be
omitted
Permission granted for ISA Houston Section Website
General Feature Summary of Intelligent PST
![Page 35: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/35.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 35/42
© Metso
• Pneumatic capacity [Cv]
• PST• 100% Safety action test• Pneumatics test• Solenoid needed for trip
• Local user interface• Single and double acting• Energized to trip configuration• Full diagnostics included
• Plug-in needed• Diagnostics storage• PST speed control• Time stamping
• LCP Option• Continuous Power Option
35
• Max 6.4 Cv
• Manual, auto & variable stroke• Yes
• Yes
• No
• Yes• Yes
• Yes, with SOV
• Yes
• No, DTM free of charge• In the device
• Limiting execution time
• Based on AM system
• Yes
• Yes
General Feature Summary of Intelligent PST
Permission granted for ISA Houston Section Website
![Page 36: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/36.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 36/42
© Metso36
Seamless Integration into Control Systems
YokogawaCentum/PRM
ABB800xA
FoxboroIA
HoneywellExperion
Rockwell
MetsoDNA
EmersonDELTA V/AMS
Emerson375 Field Communicator
EDDL
DD
Permission granted for ISA Houston Section Website
![Page 37: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/37.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 37/42
© Metso37
Configuration and Testing Using Software Tools
• Automated Intervals
•Pushbuttons
•DTM
•EDD- Emerson AMS
•HART DD- 375 HART handheld
Permission granted for ISA Houston Section Website
Future of Partial Stroke Testing
![Page 38: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/38.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 38/42
© Metso
Future of Partial Stroke TestingFieldbus based PST
• FOUNDATION for SIF (Safety Instrumented Functions) has just beenintroduced to industry, only demo devices and systems exist
• Current Configuration of some devices allows for ESD activity tocome from Current Safety Systems while communication is FF toDCS or Asset Management System
38Permission granted for ISA Houston Section Website
TRAINING
![Page 39: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/39.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 39/42
24 VDC DO from Safety System
39Permission granted for ISA Houston Section Website
![Page 40: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/40.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 40/42
mA
Permission granted for ISA Houston Section Website
![Page 41: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/41.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 41/42
24 VDC
mA
RCI
Permission granted for ISA Houston Section Website
Thank You
![Page 42: SIL & Partial Stroke Testing Solutionstation](https://reader031.vdocument.in/reader031/viewer/2022021316/577cd12c1a28ab9e7893c65a/html5/thumbnails/42.jpg)
8/13/2019 SIL & Partial Stroke Testing Solutionstation
http://slidepdf.com/reader/full/sil-partial-stroke-testing-solutionstation 42/42
© Metso
Thank You
Questions????
Permission granted for ISA Houston Section Website