2019 HFL PHASE 2.5 CAPITAL IMPROVEMENT PROJECT

Progress Report

January 2021

Presented by

Page 2: 2019 HFL PHASE 2

January 21st, 2021

Mr. Gene Mancuso, Superintendent of Schools

Honeoye Falls-Lima Central School District

20 Church Street

Honeoye Falls, NY 14472

Re: Honeoye Falls-Lima Central School District HFL 2019 Capital Improvement

Project - Phase 2.5 Monthly Report

Dear Mr. Mancuso:

Enclosed is our January 2021 Monthly Report for the 2019 Phase 2.5 Project. This progress

report is for your review and records.

Within this report, you will find detailed information related to Progress, Budget, and Schedule.

If there are any questions or comments regarding this information, please do not hesitate to

contact me to discuss. This progress report will be distributed monthly and provide periodic

updates of the past months progress and financial information.

Very truly yours,

Brian Bellaire

Sr. Project Manager

Campus Construction Management Group Inc.

CC: Dr. Bruce Capron, Honeoye Falls-Lima Central School District

Bob Fussa, Honeoye Falls-Lima Central School District

George Spinaris, Campus Construction Management Group

Sarah Bald, SEI Design Group

Page 3: 2019 HFL PHASE 2

HONEOYE FALLS LIMA CENTRAL SCHOOL DISTRICTPhase 2.5 Capital Improvement Project

MONTHLY PROGRESS REPORT

TABLE OF CONTENTS

EXECUTIVE SUMMARY SECTION 1

CONTRACTOR STATUS SECTION 2

BUDGET SUMMARY SECTION 3

CHANGE ORDERS, ALLOWANCES, SECTION 4

CHANGES & REQUESTS

PROJECT PHASING SCHEDULE SECTION 5

PROJECT PHOTOS SECTION 6

Page 4: 2019 HFL PHASE 2

Section 1

Executive Summary

Page 5: 2019 HFL PHASE 2

2019 HFL Phase 2.5 Capital Improvement Project

Executive SummaryJanuary 2021

Overview:

We are pleased to submit this month’s report for the HFL Phase 2.5 Project. This report captures work completed in late December 2020 and January 2021.

To date, Campus CMG has been attending regular meetings with Honeoye Falls Lima district staff and administration to provide updates and coordination for upcoming work.

Middle School:

Work at the Middle School began in late December 2020 with demo of existing classrooms, bathrooms, and computer lab. Throughout January contractors have removed old bathroom flooring, concrete slabs and CMU demising walls to create the new spaces.

High School:

In late December, contractors began working in the High School boiler room. They have since completed demo of the old Co-generation units and the old cooling system piping. Contractors have started rough installation of the utilities for new equipment and abatement of the cooling tower will be completed before the end of the month.

Budget Summary:

The budget summary details the project cost to date. The approved referendum authorization for the project is $ 9,786,661

Included in the summary are the contract values $5,663,689, project contingency $533,541, incidental budget $1,631,110, and a projected Lima budget of $1,273,159 for a total of $9,101,499. We are currently tracking potential changes of $0.00 and projecting a remaining contingency balance of $533,541.

Page 6: 2019 HFL PHASE 2

Section 2

Contractor Status

Page 7: 2019 HFL PHASE 2

2019 HFL Phase 2.5

Contractor StatusJanuary 2021

High School:

General Trades Contractor (Contract 101) UDNScope of work:

Staging area created outside the boiler room for dumpster and safety barrier for faculty/students

from work area.

Removal of old cooling tower including abatement.

Plumbing Contractor (Contract 102) Landry PlumbingScope of work:

Removal of old gas line and minor associated piping with old equipment.

HVAC Contractor (Contract 103) Nairy Mechanical Scope of work:

Removal of all Co-Gen equipment, duct work, and associated piping.

Removal of equipment pads for the Co-Gen equipment.

Removal and disconnect of all Day controls and associated writing.

Electric Contractor (Contract 104) Blackmon Farrell ElectricScope of work:

Make safe for other trades equipment removal.

Demolition of all electrical panels, control panels, and associated conduit/wiring.

Middle School:

General Trades Contractor (Contract 101) UDNScope of work:

Drywall temporary partitions installed to create a safety barrier for faculty/students from the work

area.

Removal of all casework, flooring, lockers, and ceilings.

Removal of entire slab in both the old bathrooms and room 302.

Removal of CMU demising walls to create future 8 single toilet rooms and Discovery lab spaces.

Page 8: 2019 HFL PHASE 2

Plumbing Contractor (Contract 102) Landry PlumbingScope of work:

Demolition of the old toilet fixtures and associated piping.

Demolition of equipment condensate lines.

HVAC Contractor (Contract 103) Nairy Mechanical Scope of work:

Demolition of the UV’s and associated ductwork/piping.

Removal of all HVAC controls.

Electric Contractor (Contract 104) Blackmon Farrell ElectricScope of work:

Make safe for other trades equipment removal and temporary lighting.

Demolition of all devices, conduit, and wiring.

Page 9: 2019 HFL PHASE 2

Section 3

Budget Summary

Page 10: 2019 HFL PHASE 2

Referendum Authorization 9,786,661$

Incidental Budget 1,631,110$

HF Construction ContractsContract Amount

Contract #101 - UDN, Inc. 2,461,097$ Contract #102 - Landry Mechanical 282,800$ Contract #103 - Nairy Mechanical 1,696,700$

Contract #104 - Blackmon Farrell 507,200$

State Contract Day Access Control - Security 52,986$

State Contract Day Controls 114,859$

State Contract Musco Sports Lighting 548,048$

Lima Construction Budget 1,273,159$

Contract Construction Amount 5,663,689$

Balance 1,218,703$

Construction Contingency $533,541

Change Order Amount Current Contract AmountContract #101 - UDN -$ 2,461,097$ Contract #102 - Landry -$ 282,800$ Contract #103 - Nairy -$ 1,696,700$ Contract #104 - Blackmon Farrell -$ 507,200$ Contract PT-68783 - Day (Security) -$ 52,986$ Contract PT-68783 - Day (Controls) -$ 114,859$ Contract KPN-201901-01 Musco -$ 548,048$

-$

Current Contract Construction Amount (with Change Orders) 5,663,689$

Total Change Orders Executed $0

Total Actual Construction Contingency Remaining $533,541

Pending Estimate Amount $0

Total Projected Construction Contingency Remaining $533,541

Unallocated Construction Funds (excludes construction contigiency) 685,162$

Allowances Allowances Used Allowances Available

Contract #101 - UDN 20,000$

Contract #102 - Landry 10,000$

Contract #103 - Nairy 30,000$

Contract #103 - Nairy 40,000$

Contract #104 - Blackmon Farrell 10,000$

Contract #104 - Blackmon Farrell 15,000$

Total Allowances Available 125,000$

1. Incidentals are budgeted costs for: Architect, Construction Manager, FFE and Misc.

2. Change orders executed includes cost of all change orders currently written

3. Total Pending Construction Contingency Remaining includes approved change orders and estimated open issues

Total

Project Budget SummaryPhase 2.5 Capital Improvement Project

January 22, 2021

Honeoye Falls-Lima Central School District

Print1/22/2021 2021.01.22 HFL Phase 2.5 Budget Summary Rev1.xlsx

Page 11: 2019 HFL PHASE 2

Section 4

Change Orders, Allowances, Changes & Requests

Page 12: 2019 HFL PHASE 2

Projected Remaining

Contingency Amount

Actual Contingency

Amount

Remaining Allowance

Amount

$533,541.00 $533,541.00 $125,000

$0 $0 $0

Date Issue# FO# Description Contractor BuildingTotal Estimate

AmountChange Order

AmountAllowance Drawdown

Error OmissionField

ConditionOwner

Request RFI # Justification Notes:

TOTAL $0 $0 $0 $0 $0 $0 $0

Phase 2.5 Capital Improvement Project

Status: (Estimate/

Proposal/ CO#/ Closed)

Page 13: 2019 HFL PHASE 2

January 21, 2021

DATE C.O. # Issue # FO # BUILDING DESCRIPTION AmountGeneral Status SED Status Month Billed

101 - General Trades - UDN

Total $0

102 - Plumbing - Landry

Total $0

103 - Mechanical - Nairy

Total $0

104 - Electical - Blackmon Farrell

HFL CSD Renewal ProjectCHANGE ORDER LOG

Page 14: 2019 HFL PHASE 2

January 21, 2021

DATE C.O. # Issue # FO # BUILDING DESCRIPTION AmountGeneral Status SED Status Month Billed

HFL CSD Renewal ProjectCHANGE ORDER LOG

Total $0

Day - Security

Total $0

Day - Controls

Total $0

Musco - Lighting

Total $0

Total Executed Change Orders $0

Page 15: 2019 HFL PHASE 2

Section 5

Project Phasing Schedule

Page 16: 2019 HFL PHASE 2

2019 HFL Phase 2.5

Schedule SummaryJanuary 2021

Overview:

We are pleased to submit this month’s report for the 2019 HFL Phase 2.5 Capital Improvement Project.

This report captures work scheduled from January through February 2021.

January 2021:

o High School:

Demo completed on cooling system including abatement of existing

cooling tower and ice storage tanks.

Coordination drawings complete and new heating system pipe rough to

begin.

o Middle School:

Rough Installation of underground piping for future 8 toilet rooms.

Slab preparation and installation

February 2021:

o High School:

Continued demo of exterior mechanical equipment and associated

underground utilities.

New heat system rough pipe installation continues.

Installation of concrete equipment pads

Wall a ceiling prep for painting of 1/3 of boiler room.

o Middle School:

Installation of CMU Walls

Begin mechanical, electrical, and plumbing rough installations for the

future Discovery Lab and 8 toilet room spaces.

Page 17: 2019 HFL PHASE 2

Section 6

Project Photos

Page 18: 2019 HFL PHASE 2

High School Boiler Room Before

High School Boiler Room Demo

Page 19: 2019 HFL PHASE 2

Middle School Corridor Before

Middle School Temporary Wall Partition

Page 20: 2019 HFL PHASE 2

Middle School Classroom Before

Middle School Concrete Floor Demo

Page 21: 2019 HFL PHASE 2

Middle School Concrete Floor Demo

Page 22: 2019 HFL PHASE 2