grid control cooperation – coordination of secondary control · coordination of secondary...

75
Prof. Dr. techn. G. Scheffknecht Institute of Combustion and Power Plant Technology Exchange of balancing services Market design and modelling, Amsterdam October 28, 2010 Dipl.-Ing. Pavel Zolotarev University of Stuttgart Grid Control Cooperation – Coordination of Secondary Control

Upload: others

Post on 25-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Prof. Dr. techn. G. Scheffknecht

Institute of Combustion and Power Plant Technology

Exchange of balancing services ‐ Market design and modelling, AmsterdamOctober 28, 2010

Dipl.-Ing. Pavel ZolotarevUniversity of Stuttgart

Grid Control Cooperation –

Coordination of Secondary Control

Page 2: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

2

Introduction

Continental Europe power system - synchronously interconnected control areas

Load and power generation from renewable sources cannot be predicted accurately.

In order to ensure the power system stability power generation must be continuously adjusted to power demand by load-frequency control.

Page 3: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

3

Introduction

Continental Europe power system - synchronously interconnected control areas

Load and power generation from renewable sources cannot be predicted accurately.

In order to ensure the power system stability power generation must be continuously adjusted to power demand by load-frequency control.

Secondary Control (SC):• Stationary restores the power balance of a control area • Control variable – actual power interchange of a control area• Horizontal structure:

− One controller implemented in each control area− No coordination of secondary control power (SCP) activation

Page 4: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

4

Secondary Control Loop

Power balance of a control area

Control deviation: Area Control Error (ACE)

Power Balance

ACE

Page 5: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

5

Secondary Control Loop

Power balance of a control area

Control deviation: Area Control Error (ACE)

Control area short – positive SCP demandControl area long – negative SCP demand

Secondary Controller

Power Balance

ACE

SCP-request

Page 6: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

6

Secondary Control Loop

Power balance of a control area

Control deviation: Area Control Error (ACE)

Control area short – positive SCP demandControl area long – negative SCP demand

Secondary Controller

SC Power Plant Units

Power Balance

SCP

ACE

SCP-request

Page 7: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

7

Secondary Control Loop

Power balance of a control area

Control deviation: Area Control Error (ACE)

Control area short – positive SCP demandControl area long – negative SCP demand

Dimensioning of necessary SCP reserves and their activation is conducted with respect to technical and economic criteria for one

control area!

Secondary Controller

SC Power Plant Units

Power Balance

SCP

ACE

SCP-request

Page 8: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

8

Interconnected Power System

Secondary Controller

SC Power Plant Units

Power Balance

SCP

ACE

SCP-request

Control Area A

Page 9: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

9

Interconnected Power System

Secondary Controller

SC Power Plant Units

Power Balance

SCP

ACE

SCP-request

Control Area A

Power Balance

SC Power Plant Units

Secondary Controller

SCP

ACE

SCP-request

Control Area C

Secondary Controller

SC Power Plant Units

Power Balance

SCP

ACE

SCP-request

Control Area B

other control areas

Technical and financial benefit through Grid Control Cooperation!

Page 10: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

10

Index

1. Grid Control Cooperation Modules

2. Technical Concept

3. Example from Operation

4. Implementation in Germany

5. Summary

Page 11: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

11

Index

1. Grid Control Cooperation Modules

2. Technical Concept

3. Example from Operation

4. Implementation in Germany

5. Summary

Page 12: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

12

Module 1

Module 1:

Inherent in the system: concurrently short and long control areas activate SCP with different signs.

Counteracting SCP avoidance

Less control energy needed (lower energy costs)

Grid Control Cooperation

Page 13: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

13

Module 2

Module 2:

Control areas must cover the risk of power imbalances with SCP reserves.

Risk distribution and joint dimensioning of SCP reserves

Lower SCP reserves needed (lower costs)

Grid Control Cooperation

Module 1:Counteracting SCP avoidance

Page 14: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

14

Module 3

Module 3:

SCP reserves must be procured.

Joint cross-border procurement

Overall cheapest SCP is bought

Higher supply but stable demand could lead to lower prices

Grid Control Cooperation

Module 1:Counteracting SCP avoidance

Module 2:Joint dimensioning of SCP reserves

Page 15: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

15

Module 4

Module 4:

SCP is activated under consideration of energy costs (e.g. with respect to a merit order list).

Cross-border cost optimal SCP activation

Possible market based effects on control energy price

Module 3:Joint SCP procurement

Grid Control Cooperation

Module 2:Joint dimensioning of SCP reserves

Module 1:Counteracting SCP avoidance

Page 16: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

16

Grid Control Cooperation Modules

Module 4:Cross-border cost-optimal SCP activation

Grid Control Cooperation

Module 3:Joint SCP procurement

Module 2:Joint dimensioning of SCP reserves

Module 1:Counteracting SCP avoidance

Page 17: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

17

Index

1. Grid Control Cooperation Modules

2. Technical Concept

3. Example from Operation

4. Implementation in Germany

5. Summary and Outlook

Page 18: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

18

Grid Control Cooperation Modules

Module 4:Cross-border cost-optimal SCP activation

Grid Control Cooperation

Module 3:Joint SCP procurement

Module 2:Joint dimensioning of SCP reserves

Module 1:Counteracting SCP avoidance

Page 19: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

19

Grid Control Cooperation Modules

Module 4:Cross-border cost-optimal SCP activation

Grid Control Cooperation

Module 3:Joint SCP procurementonly organizational

Module 2:Joint dimensioning of SCP reserves

Module 1:Counteracting SCP avoidance

Page 20: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

20

Interconnected Power System

Secondary Controller

SC Power Plant Units

Power Balance

SCP

ACE

SCP-request

Control Area A

Power Balance

SC Power Plant Units

Secondary Controller

SCP

ACE

SCP-request

Control Area C

Secondary Controller

SC Power Plant Units

Power Balance

SCP

ACE

SCP-request

Control Area B

other control areas

Technical and financial benefit through Grid Control Cooperation!

Page 21: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

21

Secondary Control Optimization

Secondary Controller

SC Power Plant Units

Power Balance

SCP

ACE

SCP-request

Control Area A

Power Balance

SC Power Plant Units

Secondary Controller

SCP

ACE

SCP-request

Control Area C

Secondary Controller

SC Power Plant Units

Power Balance

SCP

ACE

SCP-request

Control Area B

other control areas

SC-Optimization

correction

correction

correction

correction

SCP demand SCP demand

SCP demand SCP demand

Page 22: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

22

Integration into Secondary Control Structure

int,aP -

K f∆int,setP Secondary Controller Secondary ControlledPower Plant Units

sc,setP-ACEP

existing

sc,aP

distint,aP

-

Page 23: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

23

Integration into Secondary Control Structure

int,aP -

K f∆int,setP Secondary Controller Secondary ControlledPower Plant Units

sc,setP-ACEP

existing

sc,aP

Page 24: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

24

Integration into Secondary Control Structure

-

corr,2 corr,3 corr,, , , iP P P

SC-Optimization

corr,1P

int,aP

K f∆int,setP Secondary Controller Secondary ControlledPower Plant Units

sc,setPACEP

existing

newdemand,1P

demand,2 demand,3 demand,, , , iP P P

sc,aP-

Page 25: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

25

Integration into Secondary Control Structure

- -

corr,2 corr,3 corr,, , , iP P P

SC-Optimization

corr,1P

int,aP

K f∆int,setP Secondary Controller Secondary ControlledPower Plant Units

sc,setPACEP

existing

newdemand,1P

demand,2 demand,3 demand,, , , iP P P

sc,aP

Definition of SCP demand?

Page 26: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

26

Integration into Secondary Control Structure

- -

SC-Optimization

corr,2 corr,3 corr,, , , iP P P

corr,1P

int,aP

K f∆int,setP Secondary Controller Secondary ControlledPower Plant Units

sc,setPACEP

-ACE corr,1P P−

demand,2 demand,3 demand,, , , iP P P

existing

newdemand,1P

sc,aP

Demand = ACE without correction

Page 27: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

27

Integration into Secondary Control Structure

- -

SC-Optimization

corr,2 corr,3 corr,, , , iP P P

corr,1P

int,aP

K f∆int,setP Secondary Controller Secondary ControlledPower Plant Units

sc,setPACEP

-ACE corr,1P P− sc,aP

demand,2 demand,3 demand,, , , iP P P

existing

newdemand,1P

sc,aP

Demand = ACE without correction and without activated SCP

Page 28: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

28

Integration into Secondary Control Structure

- -

SC-Optimization

corr,2 corr,3 corr,, , , iP P P

corr,1P

int,aP

K f∆int,setP Secondary Controller Secondary ControlledPower Plant Units

sc,setPACEP

-ACE corr,1P P− sc,aP

demand,2 demand,3 demand,, , , iP P P

existing

newdemand,1P

sc,aP

distint,aP

-

Demand = ACE without correction and without activated SCP

Page 29: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

29

Integration into Secondary Control Structure

- -

SC-Optimization

corr,2 corr,3 corr,, , , iP P P

corr,1P

int,aP

K f∆int,setP Secondary Controller Secondary ControlledPower Plant Units

sc,setPACEP

-ACE corr,1P P− sc,aP

demand,2 demand,3 demand,, , , iP P P

existing

newdemand,1P

sc,aP

distint,aP

-

+

Demand = ACE without correction and without activated SCP

Demand contains no information fromclosed control loop –

Stability is guaranteed!

Page 30: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

30

Integration into Secondary Control Structure

- -

SC-Optimization

corr,2 corr,3 corr,, , , iP P P

corr,1P

int,aP

K f∆int,setP Secondary Controller Secondary ControlledPower Plant Units

sc,setPACEP

-ACE corr,1P P− sc,aP

demand,2 demand,3 demand,, , , iP P P

existing

newdemand,1P

sc,aP

import/export boundson/off switch

Page 31: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

31

Index

1. Grid Control Cooperation Modules

2. Technical Concept

3. Example from Operation

4. Implementation in Germany

5. Summary and Outlook

Page 32: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

32

Grid Control Cooperation in Germany

TNG

TPS

Four control areas• Amprion GmbH (AMP)• TenneT TSO GmbH (TTG)• 50Hertz Transmission GmbH (50Hz)• EnBW Transportnetze AG (TNG)

AMP

50HzTTG

TNG

Page 33: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

33

Grid Control Cooperation in Germany

Four control areas• Amprion GmbH (AMP)• TenneT TSO GmbH (TTG)• 50Hertz Transmission GmbH (50Hz)• EnBW Transportnetze AG (TNG)

December 2008: Grid Control Cooperation launched by TNG,

50Hz and TTG Control areas remain independent

University of Stuttgart

AMP

50Hz

TNG

TTG

Page 34: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

34

Example from Operation

0 5 10 15 20 25 30 35 40 45 50 55 60-400

-200

0

200

400

600

800

1000

1200

1400

SCP demands

MW

min.

TNG demand 50Hz demand TTG demand

Page 35: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

0 5 10 15 20 25 30 35 40 45 50 55 60-400

-200

0

200

400

600

800

1000

1200

1400

35

Counteracting SCP Demands

SCP demands counteracting counteractingcounteractingcounteracting

MW

min.

TNG demand 50Hz demand TTG demand

Page 36: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

36

Netted Demand

Netted SCP demand of all participants

0 5 10 15 20 25 30 35 40 45 50 55 60600

800

1000

1200

1400

1600

+ 1500 MW

+ 640 MW

MW

min.

GCC demand

Page 37: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

37

TNG Demand

SCP demands counteracting counteractingcounteractingcounteracting

0 5 10 15 20 25 30 35 40 45 50 55 60-200

-100

0

100

200

300

400

500

600

700

800MW

min.

TNG demand

Page 38: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

38

Counteracting SCP avoidance

SCP demands counteracting counteractingcounteractingcounteracting

0 5 10 15 20 25 30 35 40 45 50 55 60-200

-100

0

100

200

300

400

500

600

700

800MW

min.

TNG demand TNG Module 1

Page 39: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

39

Counteracting SCP avoidance

SCP demands counteracting counteractingcounteractingcounteracting

0 5 10 15 20 25 30 35 40 45 50 55 60-200

-100

0

100

200

300

400

500

600

700

800MW

min.

TNG demand TNG Module 1

Saved energy!

Page 40: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

40

Counteracting SCP avoidance

SCP demands counteracting counteractingcounteractingcounteracting

0 5 10 15 20 25 30 35 40 45 50 55 60-200

-100

0

100

200

300

400

500

600

700

800MW

min.

TNG demand TNG Module 1

Cross-border cost optimization?

Page 41: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

41

Goal: Cost Optimal Netted Demand Coverage

Netted SCP demand of all participants

0 5 10 15 20 25 30 35 40 45 50 55 60600

800

1000

1200

1400

1600

+ 1500 MW

+ 640 MW

MW

min.

GCC demand

Cost optimization only for positive SCP demand needed

Page 42: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

42

Positive Merit Order List

+ 640 MW

+ 1500 MW

Merit Order List Position

Available in TNG [MW]

Available in TTG [MW]

Available in 50Hz [MW]

Available in Total [MW]

1 20 0 0 20

2 0 55 0 75

3 40 0 0 115

4 0 160 0 275

5 160 0 0 435

6 0 35 0 470

7 320 0 0 790

8 0 0 433 1223

9 428 0 0 1651

(minimum demand)

(maximum demand)

Lowest energy price

Highest energy price

Page 43: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

43

Positive Merit Order List

Coverage of minimum SCP demand (always activated)

Coverage of maximum SCP demand

Merit Order List Position

Available in TNG [MW]

Available in TTG [MW]

Available in 50Hz [MW]

Available in Total [MW]

1 20 0 0 20

2 0 55 0 75

3 40 0 0 115

4 0 160 0 275

5 160 0 0 435

6 0 35 0 470

7 320 0 0 790

8 0 0 433 1223

9 428 0 0 1651

+ 640 MW

+ 1500 MW

(minimum demand)

(maximum demand)

Lowest energy price

Highest energy price

Page 44: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

44

TNG Demand and Module 1

SCP demands counteracting counteractingcounteractingcounteracting

0 5 10 15 20 25 30 35 40 45 50 55 60-200

-100

0

100

200

300

400

500

600

700

800MW

min.

TNG demand TNG Module 1

Page 45: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

45

TNG Module 1 and Module 4

0 5 10 15 20 25 30 35 40 45 50 55 60-200

-100

0

100

200

300

400

500

600

700

800

SCP demand, Module 1 and Module 4 correction signals

MW

min.

TNG demand TNG Module 1 TNG Module 4

Page 46: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

0 5 10 15 20 25 30 35 40 45 50 55 60-200

-100

0

100

200

300

400

500

600

700

800

46

TNG – Effect of Correction Signal

MW

min.

TNG demand

SCP demand, correction signals and demand after correction

TNG Module 1 TNG Module 4 TNG corrected demand

Page 47: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

47

50Hz – Effect of Correction Signal

MW

min.

50Hz demand 50Hz corrected demand

SCP demand and demand after correction

0 5 10 15 20 25 30 35 40 45 50 55 60-200

-100

0

100

200

300

400

500

Page 48: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

48

TTG – Effect of Correction Signal

SCP demand and demand after correction

MW

min.

TTG demand TTG corrected demand

0 5 10 15 20 25 30 35 40 45 50 55 600

200

400

600

800

1000

1200

1400

Page 49: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

49

Goal: Cost Optimal Netted Demand Coverage

Netted SCP demand of all participants

0 5 10 15 20 25 30 35 40 45 50 55 60600

800

1000

1200

1400

1600

+ 1500 MW

+ 640 MW

MW

min.

GCC demand

Page 50: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

50

Result of Grid Control Cooperation

Netted SCP demand of all participants and sum of secondary controller outputs

0 5 10 15 20 25 30 35 40 45 50 55 60600

800

1000

1200

1400

1600MW

min.

GCC demand Sum of secondary controller outputs

The sum of SCP activation = Netted GCC demand!

Page 51: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

51

Index

1. Grid Control Cooperation Modules

2. Technical Concept

3. Example from Operation

4. Implementation in Germany

5. Summary and Outlook

Page 52: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

52

Grid Control Cooperation in Germany

Four control areas• Amprion GmbH (AMP)• TenneT TSO GmbH (TTG)• 50Hertz Transmission GmbH (50Hz)• EnBW Transportnetze AG (TNG)

December 2008: Grid Control Cooperation launched by TNG,

50Hz and TTG Control areas remain independent

University of Stuttgart

AMP

TNG

50HzTTG

Page 53: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

53

Grid Control Cooperation in Germany

Four control areas• Amprion GmbH (AMP)• TenneT TSO GmbH (TTG)• 50Hertz Transmission GmbH (50Hz)• EnBW Transportnetze AG (TNG)

December 2008: Grid Control Cooperation launched by TNG,

50Hz and TTG Control areas remain independent

May 2010: AMP joins the Grid Control Cooperation

AMP

TNG

University of Stuttgart

50HzTTG

Page 54: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

54

Timeline of Implementation

Nov. Dec. Jan. Feb. Mar. Apr. May. Jun. Jul. Aug. Sep. Oct.

20092008

Module 1 Module 2 Module 3 Module 4

Module 1: Counteracting SCP avoidance (December 2008)

Common balancing energy price for participating control areas (May 2009)

Module 2: Joint dimensioning of SCP reserves (June 2009)

Module 3: Joint procurement (July 2009)

Module 4: Cross-border cost optimization (October 2009)

Common balancing energy price

Page 55: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

55

Estimated Cost Savings for Germany

Nov. Dec. Jan. Feb. Mar. Apr. May. Jun. Jul. Aug. Sep. Oct.

20092008

Module 1 Module 2 Module 3 Module 4

Module 1: Counteracting SCP avoidance (December 2008) – approx. 120 mil. € pa.

Common balancing energy price for participating control areas (May 2009)

Module 2: Joint dimensioning of SCP reserves (June 2009) – approx. 140 mil. € pa.

Module 3: Joint procurement (July 2009)

Module 4: Cross-border cost optimization (October 2009)

Common balancing energy price

double digit mil. € savings

Page 56: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

56

Index

1. Grid Control Cooperation Modules

2. Technical Concept

3. Modelling

4. Implementation in Germany

5. Summary

Page 57: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

57

Summary

Grid Control Cooperation:• Counteracting SCP avoidance (Module 1)• Joint dimensioning of SCP reserves (Module 2)• Joint SCP procurement (Module 3)• Cross-border cost-optimal SCP activation (Module 4)

Page 58: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

58

Summary

Grid Control Cooperation:• Counteracting SCP avoidance (Module 1)• Joint dimensioning of SCP reserves (Module 2)• Joint SCP procurement (Module 3)• Cross-border cost-optimal SCP activation (Module 4)

Coordination of secondary control while maintaining the independence of participating control areas and power system stability

Congestion management system allows restriction power interchange within the Grid Control Cooperation framework

Page 59: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

59

Summary

Grid Control Cooperation:• Counteracting SCP avoidance (Module 1)• Joint dimensioning of SCP reserves (Module 2)• Joint SCP procurement (Module 3)• Cross-border cost-optimal SCP activation (Module 4)

Coordination of secondary control while maintaining the independence of participating control areas and power system stability

Congestion management system allows restriction power interchange within the Grid Control Cooperation framework

Implementation in Germany:• Cost savings: approximately 300 mil. € pa.• Common balancing energy price• Harmonization of SCP market

Page 60: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

60

The End

Thank you!

# Simplicity# Stability# Back-up plan# Cost savings# Market impact# Extension

AMP

VE-TTPS

TNG

Stuttgart

Nov. Dec. Jan. Feb. Mar. Apr. May. Jun. Jul. Aug. Sep. Oct.

20092008

Module 1 Module 2 Module 3 Module 4Common balancing energy price

Module 4:Cost-optimal SCP activation

Grid Control Cooperation

Module 3:Joint SCP procurement

Module 2:Joint dimensioning of SCP reserves

Module 1:Counteracting SCP avoidance

SecondaryController

SC Power Plant Units

Power Balance

SCP

ACE

SCP-request

Control Area A

Power Balance

SC Power Plant Units

SecondaryController

SCP

ACE

SCP-request

Control Area C

SecondaryController

SC Power Plant Units

Power Balance

SCP

ACE

SCP-request

Control Area B

other control areas

SC-Optimization

correction

correction

correction

correction

demand demand

demand demand

Powergrid 08.06.2010

- -

SC-Optimization

corr,2 corr,3 corr,, , , iP P P

corr,1P

int,aP

K f∆int,setP Secondary Controller Secondary ControlledPower Plant Units

sc,setPACEP

-ACE corr,1P P− sc,aP

demand,2 demand,3 demand,, , , iP P P

existing

newdemand,1P

sc,aP

import/export boundson/off switch

scheduled power plant units

secondary controller

Σ

secondary controlled power plant units

schedule

- -

-

- primary controlled power plants and

self-regulating effect

Σ

Σ

ΣK f∆

int,setP

sc,setP

sc,aP

ACEP

demandPcorrP

2,schedP

1,schedP

f∆

−load genP P

3,schedP

loadP

genP

int,aP

-

genP

zP

Page 61: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

61

Modelling of Power Systems at IFK

12 oW

0o

12oE 24oE

36o E

30 oN

36 oN

42 oN

48 oN

54 oN Nonlinear, dynamic model of the ENTSO-E CE power system including: > 1000 power plant units > 3000 dynamic loads > 7000 transmission lines > 900 transformers Investigation of dynamic and stationary power

system behavior 400 kV 220 kV HDVC

Wide Area Monitoring: 8 frequency measuring units in Europe:

• Sevilla, Madrid, Aalborg, Gliwice, Zagreb, Timisoara, Athens and Stuttgart

2 frequency measuring units in Africa:• Algiers/Algeria + Sfax/Tunesia

19 frequency measuring units in Turkey

Page 62: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Summary Dynamic Load-Frequency Model

Control Area 1

Control Area n

Control Area 2

Control Area k

Rest

62

Summary dynamic load-frequency behavior of a synchronous network:

……

Page 63: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Summary Dynamic Load-Frequency Model

Control Area 1

Control Area n

Control Area 2

Control Area k

Rest

63

Summary dynamic load-frequency behavior of a synchronous network:

−load genP P

……

Page 64: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Summary Dynamic Load-Frequency Model

Control Area 1

Control Area n

Control Area 2

Control Area k

Rest

Summarized Network

Dynamics

64

Summary dynamic load-frequency behavior of a synchronous network:

f∆

−load genP P

……

Page 65: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Summary Dynamic Load-Frequency Model

Control Area 1

Control Area n

Control Area 2

Control Area k

Rest

SC-Optimization

Summarized Network

Dynamics

f∆

demand corr,P P

65

Summary dynamic load-frequency behavior of a synchronous network:

……

−load genP P

Page 66: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Control Area Model

schedule

66

Page 67: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Control Area Model

Σschedule

Σ

2,schedP

1,schedP

3,schedP

GenP

67

primary controlled power plants and

self-regulating effect

scheduled power plant units

secondary controlled power plant units

Σ

Σ

Page 68: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Control Area Model

Σschedule

68

primary controlled power plants and

self-regulating effect

scheduled power plant units

secondary controlled power plant units

Σ

Σ

2,schedP

1,schedP

−load genP P

3,schedP

loadP

genP

genP

Page 69: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Control Area Model

Σschedule

-

zP

69

primary controlled power plants and

self-regulating effect

scheduled power plant units

secondary controlled power plant units

Σ

Σ

2,schedP

1,schedP

−load genP P

3,schedP

loadP

genP

genP

Page 70: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Control Area Model

Σschedule

-

-Σf∆

zP

70

primary controlled power plants and

self-regulating effect

scheduled power plant units

secondary controlled power plant units

Σ

Σ

2,schedP

1,schedP

−load genP P

3,schedP

loadP

genP

genP

Page 71: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Control Area Model

secondary controller

Σschedule

- -

-Σf∆

71

-

primary controlled power plants and

self-regulating effect

scheduled power plant units

secondary controlled power plant units

Σ

Σ

sc,setPACEP

2,schedP

1,schedP

−load genP P

3,schedP

loadP

genP

int,aP

genP

zP

K f∆

int,setP

Page 72: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Control Area Model

scheduled power plant units

secondary controller

Σ

secondary controlled power plant units

schedule

- -

-

- primary controlled power plants and

self-regulating effect

Σ

Σ

Σ

sc,setP

sc,aP

ACEP

demandPcorrP

2,schedP

1,schedP

f∆

−load genP P

3,schedP

loadP

genP

72

int,aP

-

genP

zP

K f∆

int,setP

Page 73: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

Control Area Model

scheduled power plant units

secondary controller

Σ

secondary controlled power plant units

schedule

- -

-

- primary controlled power plants and

self-regulating effect

Σ

Σ

Σint,setP

sc,setP

sc,aP

ACEP

demandPcorrP

2,schedP

1,schedP

f∆

−load genP P

3,schedP

loadP

genP

73

int,aP

-

genP

zP

control area disturbance from measurements

K f∆

Page 74: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

74

Remarks

Control area model can be used to represent a balancing group

Dynamic power plant models:• linear approximations for input-output behavior (“TSO perspective”),• or detailed, nonlinear models for investigations of load-frequency control impact on

power plant units (“power plant perspective”)− different power plant types (coal-fired, hydraulic, nuclear etc.)− different operating modes (turbine in control, steam generator in control)

Simplifications with respect to the focus of investigations are possible

Page 75: Grid Control Cooperation – Coordination of Secondary Control · Coordination of Secondary Control. 2 Introduction Continental Europe power system - synchronously interconnected

75

Remarks

Control area model can be used to represent a balancing group

Dynamic power plant models:• linear approximations for input-output behavior (“TSO perspective”),• or detailed, nonlinear models for investigations of load-frequency control impact on

power plant units (“power plant perspective”)− different power plant types (coal-fired, hydraulic, nuclear etc.)− different operating modes (turbine in control, steam generator in control)

Simplifications with respect to the focus of investigations are possible

Model validation based on comparison of simulated and published secondary control energy and costs:

• Simulation tends to overestimate activated control energy (and thus costs)• Overestimation error is smaller than 10%