IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.1 Summary of the current month’s progressPhysical Progressof the project highway during current month is 4.89% and overall physical progress is 84.71% and financial progress is 84.71%.Total expenditure is Rs.1678.26 Crore till 25.02.2017.Concessionaire has completed DBM work for286.290 Kms. (2-lane) and BC work has been done for 247.550Kms. (2-lane).Further, DBM for four laning has been completed for approximately 143Kms.
Current Issue and recommended action by IE:
Issues related to the progress made by concessionaire: As per the opinion of IE, Concessionaire has achieved the milestone -III on 04.07.2016 within the stipulated grace period subject to:-
o The reasons stated by the Concessionaire for non-commencement of one major bridge, one minor bridge and project facilities as per stated reasons is acceptable to the Authority.
o It is also highlighted that the EOT proposal as recommended by IE, wherein milestones have been revised. The approval of EOT by the Competent Authority is yet to be sanctioned.
However scheduled completion of 4-laning might be further delayed because of the following reasons:-o Construction of Major Bridge at Km 35+803 and one EUP at Km 102+000 has been commenced in the end of Nov 2016. o Additional land required for project facilities like toll plaza, way side amenities, truck lay bye, bus bay and missing bits at various places,
to the tune of 14.767 Ha. Issues with pending land acquisition, clearances & utility shifting, encumbrances etc.:
o Almost complete stretch is encumbrance free and available for construction except a few missing bits comprising of a total length of approx. 0.36 Km. (4-lane) It is highlighted that four laning work is not affected because Concessionaire has not exhausted available working fronts.
Status of change of scope proposals: o The change of scope proposal has been submitted to NHAI vide IE letter No. SAI/IC/02/499/2016 Date: 10 thJun 2016 for 16 structures
(Slip / Service roads at 09 locations, 05 locations for underpasses, 01 box culvert and 01 double cell VUP). o There is a reduction in scope of work in terms of quantities – Approaches of structures. The complete proposal of saving amount yet to
be submitted by the concessionaire.o Concessionaire has constructed a PUP at Km 45+450, whereas a VUP is provisioned at this particular location as per Schedule ‘B’ of
CA, accordingly IE has issued a NCR to this effect.Summary of Progress:
The total length of the project is 166.173 Km. from 0+000 to 166+173 (Design length), the total project cost is Rs. 1410 Crore, with VGF of Rs. 548.49 Crore.The concessionaire for the project is M/s. Sai MaaTariniTollways Limited (SMTL). Letter of award was issued on 11 Aug 2011 and date of signing the agreement was 28 Sep 2011. Appointed date for the project is 02 May 2013, construction period is 910 days and concession period is 24 years including construction period. Scheduled completion date was 29 Oct 2015.
Project Milestone – I have been achieved on 26 Jan 2014, Project Milestone – II has been achieved on 30 Sep 2014 and project mile stone-III has been achieved on 04 July 2016 subjected to reasons stated above.
Scheduled completion of 4-laning might be further delayed because of the following reasons:-
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
o Construction of Major Bridge at Km 35+803 and one EUP at Km 102+000 has been commenced in the end of Nov 2016. o There is a total of 27.276 ha. Additional land required by concessionaire, for which land acquisition process is still in progress.
It is highlighted that the vigilance division, HO, NHAI, had carried out CTE type inspection from 07.11.2016 to 11.11.2016 and has intimated their detailed report vide NHAI letter no-13029/4/2014-Vig.dated -22.12.2016. Necessary action is being taken.
1.2 Critical Issue & Action Log1.2.1 Pending Issue & Action Log
Sl. No
Issue Description Type
Ongoing/New
Issue/Resolved
Concerned Authority
Chainage(s)
affected due
to the issue
Lengthaffecte
d(km)
Action(s) taken till now
Action(s)
suggested
by the IE
Reported
date/Actual Date for
resolving
issue
1Diversion of 151.94 ha of forest Land
Clearance Ongoing MoEF Nil Nil
State Govt. has recommended for Stage-II approval to MoEF, New Delhi.Tree cutting permission has been accorded by Office of the Divisional forest Officer, Keonjhar Division vide their letter no. 252/Mining dated 08 Sep 2015.
- -
2
4.36 Crcompensationdisbursement
pending in Jajpur Dist. (0+000 to 24+000)
Land Acquisition Resolved
Tahasildar cum CA,
Jajpur[Chainage] 0 km
Monthly Review meetings with State Chief Secretary are being conducted for early completion of disbursement by CALAs.
- -
3
pending 8.28 Crcompensationdisbursement
and pending 3D of missing bits/additional plots of 21.896 Ha in Keonjhar
Dist. (24+000 to 166+173)
Land Acquisition Resolved
Tahasildar cum CA, Keonjhar
[Chainage] 0.4kms
- Monthly Review meetings with State Chief Secretary are being conducted for early completion of disbursement by CALAs.
- -
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.2.2 Obligation as per ContractCritical Obligations and constraints of Concessionaire as per contract:-
1. Memorandum containing an inventory of the site including the vacant and unencumbered land, buildings, structures, road works, trees and any other immovable property on or attached to the site, which was communicated vide PIU letter No. 5111 dated 26 Jun 2013, was required to be signed by concessionaire, has not been signed as yet.
2. As per CA clause 10.3.6, concessionaire was required to provide the details of the additional land required for Toll Plazas, Traffic Aid Posts, Medical Aid Posts, Underpasses and Overpasses, and any additional land for construction of works specified in change of scope order issued under Article 16, within 60 days from the appointed date and has actually given this requirement in Jun 2014 i.e. almost after 1 year from appointed date.
3. Concessionaire has not submitted the revised work programme.4. Safety precautions taken by concessionaire are inadequate.5. Concessionaire has not exhausted completely, the working fronts available.6. It is pointed out that concessionaire has not ensured that the design & drawings / plan & profile of the specific structure / road work are
concurred by IE before commencement of the work. Further, it is also emphasized that more than three (3) years have been lapsed, but still there are certain compliance on the submitted design & drawings / plan & profile of the various structures / road works, which are yet to be complied by the concessionaire.
7. There are a total of 57 NCRs which has been raised till date, out of which only 27 are closed balance are 30 are still open. The detail of NCR is attached in Annexure-II.
Critical Obligations of Authority as per contract:-1. Delay in diversion of the forest land of 151.94 ha involving a total length of 23.6 Kms. out of a total stretch of 166.173 Kms. (14.20%).2. Delay in giving full possession of non-forest land, removal of govt. and private buildings from PROW and acquisition of additional land for
project facilities.3. Belbahali Issue: Concessionaire was not able to commence the construction of new Belbahali Bridge at Ch. 35+431, span 15 X 23.312 mtrs.
AsperCA.Villagers have represented the case in the Hon’ble High Court, Cuttack, Odisha. Recently in August 2016, the case has been dismissed by the Hon’ble Court and the decision has been given that the bridge to be constructed as per the provision of CA and recommendations given by IIT, Kharagpur. Now concessionaire has commenced the construction of this bridge.
4. Almost complete stretch is encumbrance free and available for construction except a few missing bits comprising of a total length of approx. 0.36 kms.((4-lane) (copy enclosed at Annexure-III)) It is highlighted that four laning work progress is not hampered because numbers of working fronts are still available.
Critical pending obligations of IE as per contract:-
NIL
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.3 Project Overview1.3.1 Salient Features of Project
Project Name Four laning of Panikoili – Rimuli section of NH-215NH No.(New/ Old) NH-215Scheme/Phase NHDP-Phase- IIIMode of the Execution (BOT Toll/ BOT Annuity/EPC/HAM item Rate/ Others)
DBFOT (Design, Built, Finance, Operate & Transfer (Toll))
No of Lanes/Configuration 4-LaneLength of the Project (in Km) 166.173 KmsTotal Project Cost (in Cr) 1410.00 Cr.No. of Bypass (Name of Town, Length) 05 nos. (Total Length-32.800 Kms)
Sl. No.
Km From
Km To Total Length
Location
1 6.700 13.150 6.450 Jajpur Road2 39.900 43.400 3.500 Anandpur3 74.800 79.000 4.200 Ghatgaon4 113.300 128.950 15.650 Keonjhar5 146.300 149.300 3.000 Jhumpura
No. of Major Bridge (Number and Location) 06 nos.
Sl. No
Bridge No. Chainage
01 36/2 35.37502 59/1 56.82003 85/1 83.63504 110/1 108.14705 137/1 139.56506 148/1 151.185
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
No. of Toll Plazas (Number of Location) 03 nos.
Sl. No. Chainage
1 33.002 92.003 134.38
No. of Fly Over (Number of Location) 01 no.(Ch. 125.345)
DPR Consultant Name AARVEE ConsultantLead & Consortium Members of Banks IDBI Bank, MumbaiConcessioner Name (SPV & Parent Company)
SAI MAA TARINI TOLWAYS LTD (GAYATRI PROJECT LTD)
Date of Award (LOA Date) 11.08.2011Appointed Date 02.05.2013Concession period 24 Years
Constriction Period (in Days) 910 days
O & M period (in Days) 7850 days
Scheduled Date of Completion 28-10-2015
Independent Engineer SAI CONSULTING ENGINEERS PVT. LTD (SYSTRA GROUP)
IE Agreement Date 25.06.2013
IE Mobilization Date 08.07.2013
1.3.2 Project Milestones
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
Project Milestone
Description
(Day from Appointed
Date
Planned Actual Delay (No. of month
Current Status
PhysicalProgres
s (%)
Scheduled Date
Physical
Progress (%)
revised Date
Milestone I
Project Milestone-I shall occur on the date
falling on the 180thday from the Appointed
Date.
4.28 28.10.2013 2.74 26.01.2014 Achieved
Milestone II
Project Milestone-II shall occur on the date
falling on the 400th day from the Appointed
Date
14.78 05.06.2014 12.75 30.09.2014 Achieved
Milestone III
Project Milestone-III
shall occur on the date falling on the 650th day
from the Appointed Date
10.02.2015 10.06.2016
Achieved subjecte
d to reasons stated above
ScheduledCompletio
n
The Scheduled Four-Laning date shall occur on the
910th day from the Appointed
date
28.10.2015 18.08.2017
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.3.3 Location Map
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.3.4 Key Plan
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.4 Physical Progress
Component % Weightage Physical Progress(During Current Month)
Physical Progress(Cumulative, Upto Current
Month)
Road Works 75.15 1.50 67.31
Major Bridge works and ROB / RUB 2.41 0.00 2.36(Please readthe“note” below)
Structures (Retaining Wall only) 5.35 0.03 5.29
Other Works 17.09 3.36 6.36
Total 100.00 3.67 84.710
Note: 1. The percentage weightage taken by concessionaire in column 2 above, which are incorrect, as per IE’s assessment the percentage weightage given to major bridge and ROB which is shown as 2.41, is much lesser because major bridge at Km 35+341 (Belbahali) which has been started recently by concessionaire, itself costs more than Rs. 50 Crore (2.5% of the EPC cost).
2. Looking to the above, the balance work on ground is Rs. 400Crores (approximately).
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.4.1 Detailed Scope of Work & Physical Progress by Component
ComponentCost
Weightage in Project (%)
Item Description Cost Weightage in Component
Planned in Scope (As per Scope of
Work
Progress till date
% Physical Progress
Value of Physical Progress
(7X4)1 2 3 4 5 6 7 8
1. Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB / RUB / Major Bridges / Structures (but excluding service roads)
75.15% 1. C & G 0.80% 324.63 315.700 97.25 0.77% 2. Embankment 9.18% 324.63 303.900 93.61 8.59% 3. Sub Grade 3.36% 324.63 300.180 92.47 3.10% 4. GSB 7.37% 324.63 296.510 91.34 6.74% 5. WMM 10.04% 324.63 290.500 89.49 8.98% 6. DBM 16.74% 324.63 286.290 88.19 14.76% 7. BC 10.05% 332.35 247.880 74.58 7.50% Minor Bridges 3.37% 60 Nos. 58.46 Nos 97.43 3.28% Flyovers 0.16% 2 Nos. 2 Nos. 100.00 0.16% Under Passes (VUP,PUP,AUP,EUP) 4.53% 30 Nos. 36.25 Nos. 92.60 4.19% Box & Slab Culverts 9.56% 295 Nos. 282 Nos. 96.50 9.23%
2. Major Bridge works and ROB / RUB2.41% 1. Major Bridges
1.72% 11 Nos. 9.00 Nos.
100.00 1.64% (5Nos X 2 Lane + 2 Lane = 11Nos.) 4. ROB (2 Nos. X 2 Lane = 4 Nos.) 0.70% 4 Nos. 4 Nos. 97.21 0.03%
3. Structures (elevated sections, reinforced earth)
5.35%
1. Foundation - - - - 0.00%2. Sub-structure - - - - 0.00%3. Super-structure - - - - 0.00%4. Reinforced Earth Wall 5.35% - - - 5.32%
4. Other Works
17.09%
Service Roads LHS 2.53% - - - 1.15%Service Roads RHS 2.53% - - - 1.25%Drainage & Protective Works 8.99% 166 - 46.75% 5.84%Highway Lighting 0.19% - - - 0.00%Road Appaurantances 1.21% 166 - 14.25% 0.40%Toll Plaza 1.65% 3 Nos. - 49.28% 1.07%
GRAND TOTAL 100.00% 100.00% 84.71%
1.5. Strip Chart
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.5.1 Strip Chart Plan (Details)Details of Strip Chart are furnish in Annexure - I
1.5.2 Strip Plan (Summary)
1.Work front Unavailability & Reason for Unavailability
2. 3.Length Completed by Layer (MCW) 4.Length Completed by Layer (Service Road)
Length (Km)% TotalPending Length
Length (Km)
% Total Length
Length (Km) % Total Length
Total Length 332.346 - BC 247.880 74.58 BC 4.120 8.20Total Work front Unavailability 0.570 0.170 DBM 286.290 88.19 DBM 10.500 20.90
Pending Land Acq. - - WMM 290.500 89.49 WMM 14.550 28.98
Pending Clearances 0.570 0.170 GSB 296.510 91.34 GSB 21.040 41.890
Encumbrances - - Sub-Grade 300.180 92.47 Sub-Grade 22.850 45.49C&G 315.700 97.25 C&G 32.230 64.17
1.6 Land Acquisition and Clearances:1.6.1 LA Summary
Description Total Required (ha) Total in possession at start (ha)
Total to be acquired (ha)
Existing ROW 314.78 314.78 0Pvt. Land To be Acquired 385.19 260.27 124.92Public Land To be Transferred 137.599 132.16 5.439Grant Total 989.506 707.21 282.296
1.6.2 LA Details by CALA
CALA
Total Land left
to be Acquired
(Ha)
3H Pending
(ha)
3H Done (Ha)
3G Pending
(Ha)
3G Done (Ha)
3D Pending
(Ha)
3D Done (Ha)
3A Pending
(Ha)
3A Done (Ha)
Amount Awarded
(Crore Rs.)
Amount Deposited
(CroreRs.)
Amount Disbursed by CALA (Crore
Rs.)
Pending Amount (Crore
Rs.)
[CALA-Keonjhar]
27.276 21.837 280.45 21.837 280.45 27.276 671.49 0.0 638.766 214.44 177.72 170.95 6.77
[CALA-Jajpur] 0.0 0 82.9 0.0 82.9 0.0 138.80 0.0 138.80 47.438 38.52 34.52 4.00
Grand Total 27.276 21.837 365.19 21.837 365.19 27.276 810.39 0.0 837.566 261.878 216.24 204.54 10.77
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.6.3 Clearance Summary
Environment
Proposal Description StatusLength
ImpactedCurrent Stage Issues / Comments
Approval of construction in coastal zone NA Nil NA
Forest Land
Proposal Description Status Length Impacted Current Stage Issues / CommentsDiversion of 11.89 Ha (0.00 to 24.00 Km):- Jajpur District, Forest Stretch-2.6Km
Stage-I Obtained
0Forest tree felling
completed
Stage II clearance pending, Tree cutting permission has been accorded by Office of the Divisional forest Officer, Keonjhar Division vide their letter no. 252/Mining dated 08 Sep 2015.
Diversion of 140.05 Ha ([24.00 to 166.173 Km]):- Keonjhar District, Forest Stretch-21.0Km Stage-I
Obtained3
Forest tree felling Ongoing
Stage II clearance pending,Tree cutting permission has been accorded by Office of the Divisional forest Officer, Keonjhar Division vide their letter no. 252/Mining dated 08 Sep 2015.
Wildlife
Proposal DescriptionStatus
Length Impacted
Current Stage Issues / Comments
N/A N/A N/A N/A N/A
Tree Cutting
Proposal Description StatusLength
ImpactedCurrent Stage Issues / Comments
Felling of 1054 nos. of trees from Ch. 0+000 to 24+000
Approved 24 Completed -
Felling of 1197 nos. of trees from Ch. 24 +000 to 58+000
Approved 34 Completed -
Felling of 4848 nos. of trees from Ch. 58 Approved 49 Completed -
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
+000 to 107+000 Felling of 1027 nos. of trees from Ch. 104+600 to 113+100
Approved8.50 Completed -
Felling of 4419 nos. of trees from Ch. 113+300 to Ch. 143+000
29.90Completed
-
Felling of 2415 nos. of trees from Ch. 143+000 to Ch. 163+000
Approved 20Completed
-
Felling of forest trees 29292 nos. from Ch. 58+000 to Ch. 113+000
Approved 65 On going -
Felling of forest trees 1210 nos. from Ch. 113+000 to Ch. 163+000
Approved 50 On going -
Railway ROBs/RUBsGAD Numbers Status Locations / Chainage Current Stage Issues / Comments
Approved CE drawing no. 1715/13 of ECoRdt. 20.05.13
ApprovedCh.9.18 KM (Railway Ch.334.682 of Korai -
JJKR)
Uploaded on portal on
[DD/MM/YYYY]- NIL
Approved CE drawing no.2244/15 of ECoRdt. 20.05.13
ApprovedCh.115.639 KM (Railway
Ch.65.318 of Tamka - Keonjhar - Bansapani)
Uploaded on portal on
[DD/MM/YYYY]- NIL
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.6.4 Status of Utility Shifting
Utility Catego
ryName Status Length
affectedDepartment
Date of request by Authority
for estimate
Date when Estimate
was received
from concerned
dept.
Date of approved
by authority RO/HQ
Date of deposit of
super-vision charge
Progress of
Physical Shifting
Date of
Certification from
Agency for
completion
Estimate Amount
(Rs)
Issue / Comments
Water
Shifting of TW
& Water
line
Estimate Approved 166.173 RWSS,
Keonjhar 06/11/2009 30/10.2015 30/10/2015 02/7/2012
Work Complet
edTBD 21468483/-
Shifting of TW
& Water lines
NHAI/BOT/11012/68/2005/Uti.Est/00-206/RWSS/229 dt.
06.11.2009Revised Est.NHAI/BOT/
11013/68/2005/1483 dt.
20.11.2015NHAI/11012/3/
RO/OD/4924/2015
dt.30.10.2015
RWSS, Keonjhar & RWSS,
Jajpur
21468483/- For Ch. Km.0-23-163
Shifting of TW
& Water lines
NHAI/BOT/11012/68/2005/
Uti.Est/Ph.Div/226 dt. 06.11.2009
Revised Est.NHAI/11012/3/
RO/OD/4924/2015
dt.30.10.2015
PH Division Rourkela
3121979
For Ch. Km.38.8-
40.65 & at Keonjhar Bypass.
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
Electricity
Shifting of
Electrical lines
NHAI/BOT/11012/68/2005/277 dt. 05.02.2010
142.173 NESCO, Balasore - - 05/02/2010 22/02/2012
Work Complet
edTBD 53518776/
-
For Ch. Km.23-163,
1st and 2nd RA Bill released
Shifting of
Electrical lines
NHAI/11012/2/01/RO-OD/976/2013 dt.
03.05.2013
24.000EE,
NESCO, Jajpur Road
- - 03/05/2013 17/06/2013
Work Complet
edTBD 21144456/
-
Rs.562008 deposited to
NESCO as supervision charges for Ch.km. 0-23
Shifting of
220KV &
132KV crossing near Panikoi
li
NHAI/BOT/11012/68/2005/
Tech/Utility/55 dt. 17.02.2011
And RO-Bhubaneswar
ltr no.11012/2/01/RO-OD/4309/2015
dt.27.07.2015
-OPTCL,
Bhubaneswar
- - 27/07/2015 03/03/2011
Work Complet
edTBD 14158963/
-
Rs.298801 deposited to GM, OPTCL, Bhubaneswar as balance supervision charges vide
T/O ltr no.8240
dt.30.11.2015 for shifting of 220KV &
132KV crossing
near Panikoili.
Shifting of UG cables
RO-Bhubaneswar ltr
no.11012/2/01/RO-OD/5219/2015
dt.18.12.2015
- NESCO, Keonjhar
- - 18/12/2015 01/01/2016 - - 5277685/- Rs.268864 deposited to
NESCO as supervision charges for undergroun
d XLPE cabling in
11KV/33KV lines
Ch.115.635 &Ch.128.83
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
4 Km, 1st and 2nd RA
released
Shifting of
Electrical lines
for Anand
pur division
RO-Bhubaneswar ltr no.
11012/2/01/RO-OD/2951/2016,
date- 25.07.2016
- NESCO, Balasore - 01.12.2016 - - - - 58298396/-
For Ch. Km.23-112
(For Anandapur Electrical Division)
PIU's letter no.8725
dt.08.03.2016, Estimate of NESCO
changed to Rs.5.82 Cr, 3rd RA Bill released.
Diversion of
132KV railway transmi
ssion line
RO-Bhubaneswar ltr
no.11012/2/01/RO-OD/1687/2016
dt.25.07.2016
Estimate approved
ECoR, Sr.DivisionalElectri
cal Engineer
(TRD), Khurda Road
25.07.2016 6525640/-
Diversion of 132KV railway
transmission line
between tower no.37
& 38 between
Naranpur&Basantpur railway station,
40,39691/- has been
released in the 1st and
final bill
Irrigation
NHAI/11011/17/PKR(COS)/2013/
Chief engineer, Kanpur
15.10.20153,81,65,262/
- 11 number of irrigation
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
culverts PIU/KJR/8093. irrigation culverts.
Govt. and
religious
structure
Nhai/11013/2015/PIU-
KJR/Panikoili-Rimuli sec./STS-
77/72799
08.10.201521,86,90,9
77/
143 number of Govt. and
religious structure.
1.7 Change of Scope
o The change of scope proposal has been submitted to NHAI vide IE letter No. SAI/IC/02/499/2016 Date: 10 thJun 2016 for 16 structures (Slip / Service roads at 09 locations, 05 locations for underpasses, 01 box culvert and 01 double cell VUP.
o There is a reduction in scope of work in terms of quantities – Approaches of structures. The complete proposal of saving amount yet to be submitted by the concessionaire.
1.8 Mobilization of Resources
Sl. No. Equipment Name Make Model/
CapacityAge of
Equipment
Planned / Required Quantity
Actual Quantity
Additional Deployed
During Month
Reason(s) for Under / Over Mobilization
Expected Delay due to
Under – Mobilization
(Months)PLANT
CRUSHER Metso (2 nos) &Puzzolana (4 nos)
240 TPH (4 nos) &200
TPH (2 nos)3 Years 5/5 5 - - -
Batching Plant SchwingStetter (6nos)
30 CPH (4 nos) & 60 CPH (2
nos)3 Years 4/4 4 - - -
WMM plantApollo (3 nos) ,
Maxmech (1 no) &Condequip (1 no)
250 TPH (1 no) & 200 TPH (3
nos) & 160 TPH (1 no)
3 Years 5/5 5 - - -
HM PlantApol l(3),SPECO(2)
200 TPH (2 nos) & 160 TPH (3 nos)
3 Years 5/5 5 - - -
Machinery
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
Excavator/Proclain TATA/L&T 1 m3 - - 88 - - -Loader Hindustan 1.7 m3 - - 27 - - -Soil compactors Escort/Dynapac/JCB 8-10 Ton - - 48 - - -Grader 120k CAT/SANY 200 Cum/Hr - - 19 - - -Sensor- Paver Vogele Cum/Hr/40/30 - - 7 - - -Crane hydra Ashok Leyland 5-20 Ton - - 2 - - -Dumper Ashok Leyland 20 MT - - 220 - - -BT Sprayer Ashok Leyland 2.4 – 6 Mtr - - 6 - - -Boom Placer Appolo - - 3 - - -Diesel tanker Ashok Leyland 12 KL - - 5 - - -Dozer Hindustan - - 18 - - -Concrete Pump (mcp/12) Greaves Cotton Ltd. 60Cum/Hr
(Max) - - 9 - - -
Dewatering Pump Kirolsker 0.75 – 2.5 HP - - 2 - - -DG Sets (5 Kva – 500 Kva) Kirlosker 5kva – 500
Kva - - 41 - - -
Kerb Laying Machine Appolo - - - 3 - - -Water Tanker Ashok Leyland 12 KL - - 16 - - -Transit Mixer Ashok Leyland 6 m3 - - 31 - - -Trailers Ashok Leyland - - - 7 - - -PTR Dynapac - - - 5 - - -Kerb Cutting Machine Appolo - - - 3 - - -
1.9 Financial Progress Details1.9.1 Pen Picture – Escrow
TPC (Cr)
Cumulative inflow to Escrow till previous
month (Cr)
Cumulative outflow to Escrow till previous
month (Cr)
Inflow to Escrow during the month
(Cr)
Outflow to Escrow
during the month (Cr)
2306.16 1998.72 1984.28 55.36 64.92
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.9.2 Escrow details
TPC (Cr)Cumulative
exp. Till date (Cr)
Escrow Plan till date- Debt
(BOT)(Cr)
Escrow Plan till date-
Equity (BOT) (Cr)
Escrow Plan till date-
VGF (BOT) (Cr)
Escrow Actual till date- Debt(BOT)
(Cr)
Escrow Actual till
date- Equity(BOT)
(Cr)
Escrow Actual till date- VGF(BOT)
(Cr)
2306.16 2049.20 1286.84 360.32 519.68 1230.73 360.32 460.89
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
1.10 Monitoring of operations & Maintenance Obligations1.10.1 Maintenance Status during Construction Phase
Expected Contents & Structure Status of traffic worthiness and safety of project highway:-
o Concessionaire has been maintaining the road regularly to keep the traffic worthiness of the road. However, there are certain pot holes on the project highway, which are yet to be tackled on priority.
o The diversions are not constructed with proper specification and lacking safety precautions.o Safety consultant (M/s NIT Rourkela) has been engaged on 21st Nov 2016 to carry out safety audit.
1.11 Pen Picture on safety features
Location of Black Spots
Suggested Remedial Measures within provisions of Concession
Agreement
Additional Remedial Measures
(if any)
Financial implications of additional Remedial Measures
for Authority (Cr.)
Ragadi (20+050)
VUP has been provided with Junction developments which will
take care of this black spot.Not required It is within the scope of CA.
Annexure- II
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
DETAILED OF NCPN AS ON 28 th Feb 2017 Sr. No. Description of NCR Letter No Date Status Remarks
01 Embankment Material (Ch 16+380 to 16+550) LHS (NCW) SAI/IC/03/100/2013 07.12.2013 Closed
02 MJBR at 56+800 SAI/IC/03/178/2014 08.02.2014 Open03 FO at 125+284 SAI/IC/03/179/2014 10.02.2014 Closed04 Batching Plant @ 146+000 SAI/IC/03/188/2014 14.02.2014 Closed05 MJBR @ 56+820 SAI/IC/03/196/2014 17.02.2014 Open06 BC @141+764 (L) SAI/IC/03/200/2014 24.02.2014 Closed07 VUP @ 131+412 SAI/IC/03/201/2014 24.02.2014 Closed08 Batching Plant @ 151+200 SAI/IC/03/203/2014 25.02.2014 Closed09 Unsuitable Embankment Material SAI/IC/03/219/2014 06.03.2014 Closed10 Unsuitable Material for Sub Grade SAI/IC/03/220/2014 06.03.2014 Closed11 MJBR at 56+800 SAI/IC/03/223/2014 08.03.2014 Open12 Unsuitable Embankment Material SAI/IC/03/225/2014 08.03.2014 Closed13 Unsuitable Embankment Material SAI/IC/03/271/2014 21.04.2014 Closed14 Safety during Construction SAI/IC/03/283/2014 01.05.2014 Open15 Unsuitable Embankment Material SAI/IC/03/299/2014 13.05.2014 Closed
16Without Confirmatory Boring structure work Completed up to Sub-Structure @ 56+800 MJB
SAI/IC/03/374/2014 08.08.2014 Open
17 No Proper storage platform at base camp Ch: 94+000 & 107+000 SAI/IC/03/376/2014 08.08.2014 Closed
18 GSB thickness are not uniform under MCW, Shoulders & Median SAI/IC/03/377/2014 08.08.2014 Open
19 WMM work at Km 133+000 to 133+300 SAI/IC/03/420/2014 12.11.2014 Closed
20 DBM work with 90mm thickness has been carried at some location without approval. SAI/IC/03/431/2014 25.11.2014 Closed
21 GSB materials found substandard quality. SAI/IC-03/433/2014 28.11.2014 Closed
22 GSB materials have been dumped over subgrade top layer without getting approval. SAI/IC-03/434/2014 03.12.2014 Closed
23 Work started without submit GFC drawings of major bridge at Ch. 151+200. SAI/IC-03/438/2014 03.12.2014 Closed
24The DBM layer has been laid whereas pavement design and mix design is yet to be finalized.
SAI/IC-03/445/2014 15.12.2014 Closed
25The work is under progress without submission of retaining wall design & drawings.
SAI/IC-03/456/2015 12.01.2015 Open
26The work is under progress without submission of retaining wall design & drawings (VUP).
SAI/IC-03/492/2015 13.03.2015 Open
27
The BBD report along with pavement design an ECW (Existing Carriage Way) in pursuant to IRC 81, have not been submitted. But it is seen at site all road works operations are being carried out without approval of plan & profile and overlay design details, over existing road carriage way.
SAI/IC-03/493/2015 13.03.2015 Closed
28
The compliance report has sought by IE pavement design engineer for final acceptance of pavement crust composition for New Carriage Way and use of VG-40 grade Bitumen in the project highway have not been furnished to IE, It is evident at site more than 35K DBM has already been constructed
SAI/IC-03/494/2015 13.03.2015 Closed
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
without concurrence from IE.
29
Drawings & design details of retaining walls at above maintained VUP locations have not yet been submitted to IE for review, but it is seen at site the aforesaid work is under progress, without having any GFC certification from IE.
SAI/IC-03/495/2015 14.03.2015 Open
30DBM work is in progress, FRL are checked and found not matching with concurred drawings.
SAI-IC-03-543-2015 28.05.2015 Open
31
During RO visit on 27th May 15, it was observed that DBM work carried out between out between Ch. 115+000 to 116+000 and Ch 159+000 to 160+000 were of very poor quality. Mix design used was not proper. Riding surface has lot of undulations.
SAI-IC-03-552-2015 30.05.2015 Closed
32
Refer WIR no. 33 10.06.2015, because of clay content of GSB layer exceeding the limiting value. WIR No. 33 was issued on 10.06.2015. Without compliance on WIR work has been continued.
SAI-IC-03-555-2015 12.06.2015 Closed
33 Wide alligator cracks and rutting observations from Ch. 131+600 to 131+900 on LHS. SAI-IC-03-560-2015 29.06.2015 Open
34 Settlement observed at the interface of culvert at Ch. 141+650 SAI-IC-03-561-2015 29.06.2015 Open
35
The DBM work has been constructed without execution of CD works at Km 0+720 (Box Culvert), and at Km 15+680 (HP Culvert), which are needs to be provided as per CA.
SAI-IC-03-569-2015 07.07.2015 Open
36
Specifications concessionaire has started execution of PUP in lieu of VUP as per CA at Km.45+450 without obtaining principle approval from NHAI/lE.
SAI-IC-03-591-2015 11.08.2015 Open
37
Horizontal and vertical unevenness and honey combs have been noticed on newly laid median drain walls at Km 15+300 to 15.470 by PD & Manager (Tech.).
SAI-IC-03-612-2015 18.09.2015 Closed
38WMM Top level & Camber details are not matching with concurred FRL’s and design super elevation at above mentioned location.
SAI/IC/03/622/2015 14.10.2015 Closed
39
Steel has been exposed BRACKET & SLAB since long time, no rectification measures have been taken up, despite repeated instructions.
SAI/IC/03/623/2015 14.10.2015 Closed
40
Refer WIR No. 56: Concreting of pier cap for P1 has been done without giving compliance report to WIR No. 56 which is issued on date 15.10.2015.
SAI/IC/03/625/2015 16.10.2015 Closed
41Km 115 Base Camp: Reinforcement lying in haphazard manner on ground inviting deterioration and carrion.
SAI/IC/03/652/2015 19.11.2015 Closed
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
42
151+200 Major Bridge (PSC Girder No. 14 &18): It is observed that Anchor cones of PSC Girder No 14 & 18 are failed and moved inside the end block while pre/stressing. And also observed some cracks on the end block of same girders. This may be because of poor workmanship at the time of concreting. IE recommended to give the compliance and conduct required NDT on above mentioned girders before launching.
SAI/IC/03/653/2015 24.11.2015 Closed
43 With reference to this office letter no. SAI/IC/03/602/2015 (Copy enclosed), it was requested to conduct the SBC test at various locations. Concessionaire has failed to submit the SBC test results till date.
SAI/IC/03/661/2015 30.11.2015 Closed
44
The required width of Embankment layers from Km 19+900 to Km 20+450 LHS only is not available due to lesser height of remaining wall at VUP 20+054.
SAI/IC/03/668/2015 12.12.2015 Open
45
In the above mentioned chainages, the retaining wall / Toe wall have been constructed of lower height; with the result side slope and gradient do not adhere to the MORT & H specifications.
SAI/IC/03/683/2016 18.01.2016 Open
46Additional PUP at Km 82+104 has been executed without obtaining principal approvals from competent authority (NHAI/IE).
SAI/IC/03/689/2016 29.01.2016 Closed
47
The founding level of abutment A-2 (LHS) for said minor bridge do not match with the funding level as per the concurred drawing by IE.
SAI/IC/03/691/2016 01.02.2016 Open
48
In spite of clear instructions from NHAI as well as IE, it has been that construction of a VUP at Ch. 9+457 has been stated. The same is not within the provisions of schedule ‘B’ of CA. Also no permission has been granted under change of scope for the construction of VUP at these locations. You are hereby instructed to stop the construction of this VUP at Ch. 9+457.
SAI/IC/03/726/2016 31.03.2016 Open
4991+900 (Toll Plaza): Work of Administrative building started without submitting design & drawings.
SAI/IC/03/739/2016 11.04.2016 Open
50Large size boulders are used in embankment construction from Ch. 110+600 to Km 110+680 (RHS).
SAI/IC/03/768/2016 18.07.2016 Open
51
It has been observed at site that the BC layer has been settled at Kerb side of right carriageway from Km 5+720 to Km 5+760, and DBM layer has been settled at shoulder side of left carriageway from km 10+640 to 10+670.
SAI/IC/03/779/2016 27.07.2016 Open
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
52Settlement observed in spite of approach slab at VUP Ch. Km 122+926 (A2) side LHS & RHS & VUP at Km 128+846 A1 side (LHS)
SAI/IC/03/780/2016 29.07.2016 Open
53
Stone used in slope protection work is not as per specification and filter media for the same is of substandard quality at location Km 83+310 (RHS) to Km 83+510(RHS), Km 92+400 (LHS) to Km 92+560 (LHS) & Km 95+100 to Km 95+220 (LHS).
SAI/IC/03/781/2016 03.08.2016 Open
54Horizontal and longitudinal cracks along with settlement observed in the stated locations at location Km 125+200 to Km 125+250 (LHS).
SAI/IC/03/789/2016 11.08.2016 Open
55Horizontal and longitudinal cracks along with settlement observed in the stated locations at location Km 107+900 to Km 108+020 (RHS).
SAI/IC/03/791/2016 22.08.2016
Open
56
Disobeying to the WIR No.-52, still repetition of same work is been carried out over size boulders are laid at location Km 106+260 to 106+450 (LHS).
SAI/IC/03/792/2016 23.08.2016 Open
57Settlement observed in spite of approach slabs at Km 131+412 VUP both sides of A1 & A2.
SAI/IC/03/796/2016 24.08.2016 Open
Total 57 27 30Closed
Closed : 30Open : 27Total : 57
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
Chainage wise Land Stretches Available as on Feb 2017: Annexure – III
Procurement of the site in terms of Length of Project Highway (From Km 0+000 to Km 166+173)Sl. No Villager Name Chainage As per submitted
MPRAs per IE
Observations on site RemarksFrom To Length
(In Km)Land
StatusLength ( In Km)
Land Status
1 Alatiri
00+000 00+120 0.120 Available 0.120 Available BC Completed on B/S
00+120 00+140 0.020
Structure under
Arbitration case
0.020 Available BC Completed on B/S
2
Alatiri, Patharapada, M.D Jamalpur, Ouapada, Dhanpur, Aliya,
00+140 03+350 3.210 Available 3.210 Available BC Completed on B/S
3 Aliya03+350 03+360 0.010 Available 0.010 Available BC Completed on B/S03+360 04+200 0.840 Available 0.840 Available BC Completed on B/S04+200 04+230 0.030 Available 0.030 Available BC Completed on B/S
4 Aliya, Ghikoili, Benapur 04+230 05+470 1.240 Available 1.240 Available BC Completed on B/S
5 Benapur05+470 05+500 0.030 Available 0.030 Available BC Completed on B/S05+500 05+670 0.170 Available 0.170 Available BC Completed on B/S
6 Benapur, Talugaon 05+670 06+700 1.030 Available 1.030 Available BC Completed on B/S7 Benapur, Talugaon 06+700 06+880 0.180 Available 0.180 Available BC Completed on B/S
8 Sanapatuli, Badapatuli, Tentulikhunta
06+880 07+000 0.120 Available 0.120 Available DBM Completed on B/S07+000 07+800 0.800 Available 0.800 Available DBM Completed on B/S07+800 09+460 1.660 Available 1.660 Available Work in Progress
09+460 09+500 0.040
Available, Local
problem due to
construction of PUP
0.040 Available Embankment Top Completed
9 Dandakiri, Baladia09+500 09+640 0.140 Available 0.140 Available Working Progress09+640 10+400 0.760 Available 0.760 Available DBM Completed on B/S
10 Baladia, Chandama, Santarapur 10+400 13+150 2.750 Available 2.750 Available DBM completed on B/S
11
Kuanarda, Nayagarh, Naguan,Itapur, Talagarh, Uparagarh,Mangarajpur, Manjuri, Ragadi,
13+150 19+200 6.050 Available 6.050 Available DBM Completed on B/S
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
12 Ragadi 19+200 20+800 1.600Ragadi
Reserve Forest
1.600 Available DBM Completed on B/S
13 Ragadi, Korabandi, Kadama, Andhari
20+800 22+920 2.120Available
2.120 Available DBM Completed on B/S22+920 22+950 0.030 0.030 Available DBM Completed on B/S22+950 24+380 1.430 1.430 Available Work in Progress
14 Andhari, Jarda 24+380 25+000 0.620 Available 0.620 Available LHS-DBM Completed
15 Ramachandrapur25+000 25+040 0.040
BSNL building (LHS), Private building
(RHS)
0.040 Available DBM Completed
25+040 25+070 0.030 Available 0.030 Available DBM Completed25+070 26+630 1.560 Available 1.560 Available DBM Completed on B/S
16
Ramachandrapur, Badapadana,Padanpur, Suanpada, Gointhagodi,Khalana, Agarda, Sainkula
26+630 28+200 1.570 Available 1.570 Available DBM Completed on B/S
17 Nuagaon28+200 28+215 0.015 Available 0.015 Available WMM Top Completed28+215 28+400 0.185 Available 0.185 Available WMM Top Completed
18 Khalana,Agarda, Sainkula
28+400 28+415 0.015 Available 0.015 Available DBM Completed on B/S28+415 29+900 1.485 Available 1.485 Available Work in Progress29+900 30+800 0.900 Available 0.900 Available Work in Progress
19 Sainkula30+800 31+270 0.470 Available 0.470 Available DBM Completed on B/S31+270 31+400 0.130 Available 0.130 Available Work in Progress
20Sainkula,Machala,Rudranarayanapur,Bamphidi, Hasanpur
31+400 33+100 1.700 Available 1.700 Available Work in Progress
33+100 33+480 0.380 Available 0.380 Available DBM Completed on B/S
21
Hasanpur
33+480 33+660 0.180 Available 0.180 Available DBM Completed on B/S
33+660 33+700 0.040 Available 0.040 Available Work in Progress
33+700 34+050 0.350 Available 0.350 Available DBM Completed on B/S
22
Hasanpur, Salapada, Belabahali, Barigaon
34+050 34+700 0.650Realignment & Major
Bridge0.650 Available Clearing and Grubbing
Completed
34+700 36+000 1.300 1.300 Available Clearing and Grubbing Completed
23Barigaon, Salapada, Sudusudia,Janra
36+000 38+400 2.400 Available 2.400 Available Work in Progress 38+400 38+680 0.280 The private
structure 3 nos Building pending for court case.
0.280 Available Work in Progress 38+680 38+720 0.040 0.040 Available Work in Progress
38+720 38+800 0.080 0.080 Available Work in Progress
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
24 Salapada 38+800 39+800 1.000 Available 1.000 Available Work in Progress
25 Salapada, Sudusudia, Janra 39+800 39+900 0.100 Available 0.100 Available Work in Progress
26Janra, Khaparakhai, Kainpura,Sailong
39+900 40+000 0.100 Available 0.100 Available DBM Completed on B/S
27 Janra, Khaparakhai 40+000 42+000 2.000 Available 2.000 Available DBM Completed on B/S
1Janra, Khaparakhai, Kainpura,Sailong 42+000 43+360 1.360 Available 1.360 Availabl
e DBM Completed on B/S
2 Sailong 43+360 43+400 0.040 Available 0.040 Available
BC Completed on B/S
3 Sailong, Morabali, Indupura, Gohira 43+400 45+150 1.750 Available 1.750 Availabl
e BC Completed on B/S
4 Gohira
45+150 45+390 0.240 Available 0.240 Available Work in Progress
45+390 45+430 0.040 Available 0.040 Available Work in Progress
45+430 45+460 0.030 Available 0.030 Available Work in Progress
45+460 45+470 0.010 Available 0.010 Available
SCHOOL From:45+460 to 45+470 RHS Lies within ROW but work not effected
45+470 45+800 0.330 Available 0.330 Available Work in Progress
5 Gohira, Talagaon, Biragobindapur 45+800 48+100 2.300 Available 2.300 Availabl
e BC Completed on B/S
6 Talagaon, Biragobindpur
48+100 48+580 0.480
Available
0.480 Available
BC Completed on B/S
48+580 48+590 0.010 0.010 Available
BC Completed on B/S
48+590 48+980 0.390 0.390 Available BC Completed on B/S
7 Biragobindapur, Bhalukuma 48+980 52+470 3.490 Available 3.490 Availabl
e BC Completed on B/S
8 Bhalukuma52+470 52+520 0.050 BSNL
office 0.050 Available DBM Completed
52+520 53+110 0.590 Available 0.590 Available DBM Completed
9 Dhakota 53+110 53+120 0.010 Private Temple
(RHS) on Govt. Land
3A Additional
Land, Missing
Bits,
0.010 Available
Subgrade work in progress.
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
Building (Vup
Location)
53+120 53+135 0.015 0.015 Available
Work In Progress
53+135 53+150 0.015 0.015 Available Subgrade work in progress.
53+150 53+410 0.260 0.260 Available Subgrade work in progress.
53+410 53+780 0.370 0.370 Available
Work In Progress
53+780 54+200 0.420 Available 0.420 Available
DBM Completed
10 Amaranga 54+200 54+220 0.020 Available 0.020 Available
BC Completed on B/S
11 Dhakota, Amaranga
54+220 54+830 0.610 Available 0.610 Available
BC Completed on B/S
54+830 54+870 0.040 Available 0.040 Work in Progress BC Completed on B/S
54+870 55+000 0.130 Available 0.130 Available
BC Completed on B/S
12Dhakota, Amaranga, Bandha,Nahaguna, Kanto
55+000 55+200 0.200 Available 0.200 Available
BC Completed on B/S
13 Kanto
55+200 56+100 0.900 Available 0.900 Available
DBM Completed
56+100 56+120 0.020 Available 0.020 Available
DBM Completed
56+120 56+140 0.020 Available 0.020 Available
DBM Completed
56+140 56+900 0.760 Available 0.760 Available Work in Progress
56+900 57+400 0.500 Available 0.500 Available Work in Progress
57+400 57+860 0.460 Available 0.460 Available Work in Progress
57+860 57+920 0.060 Available 0.060 Available
DBM Completed
57+920 58+870 0.950 Available 0.950 Available Work in Progress
58+870 60+250 1.380 Available 1.380 Available Work in Progress
14 Darkhola
60+250 61+780 1.530 Available 1.530 Available Work in Progress
61+780 62+300 0.520 Available 0.520 Available Work in Progress
62+300 66+800 4.500 Available 4.500 Available Work in Progress
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
15 Melana 66+800 69+150 2.350 Available 2.350 Available Work in Progress
16 Balijodi69+150 72+660 3.510 Available 3.510 Availabl
e BC Completed on B/S
72+660 74+400 1.740 Available 1.740 Available Work In Progress
17 Uperdiha
74+400 76+850 2.450 Available 2.450 Available Work In Progress
76+850 76+930 0.080
Temple & trees
considered as divine were not
allowed to be felled by public
0.080 Available Work In Progress
76+930 78+050 1.120 Available 1.120 Available Work In Progress
78+050 78+200 0.150 Available 0.150 Available Work In Progress
18 Kusunpur
78+200 78+630 0.430 Available 0.430 Available Work In Progress
78+630 78+660 0.030
Pvt. Building, Missing
bits
0.030 Available Work In Progress
78+660 78+690 0.030
Pvt. Building, Missing
bits
0.020 Available Work In Progress
78+690 78+780 0.090 Available 0.100 Available Work In Progress
78+780 78+810 0.030 Available 0.030 Available Work In Progress
78+810 79+160 0.320 Available 0.320
79+160 79+320 0.180
Land Problem (Missing
Bits)
0.180 RHSNotAvailable
LHS available. Work in Progress
79+320 79+330 0.010 0.010 Available Work In Progress
79+330 82+290 2.960 Available 2.960 Available Work In Progress
19 Bataharichandanpur 82+290 82+310 0.020 Available 0.020 Available Work In Progress
82+310 82+370 0.060 Available 0.060 Available
Work In Progress
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
82+370 82+400 0.030 Available 0.030 Available Work In Progress.
82+400 83+000 0.600 Available 0.600 Available Work In Progress
20
83+000 83+600 0.60 Available
Sanamasinabila83+600 83+900 0.30 Available 83+900 84+700 0.80 Available 84+700 86+400 1.70 Available
Sanabarabeda 86+400 88+380 1.98 Available Tikira 88+380 89+500 1.12 Available
Nangalkanti 89+500 90+100 0.60 Available
21 Dhenkikote 90+100 90+420 0.32 Available
90+420 90+430 0.01
Compensation not
received by demanding
excess payment
managed Work in progress
90+430 90+450 0.02 Available
90+450 90+470 0.02 Missing Plot 3A Work in progress
90+470 90+750 0.28 Available
90+750 90+810 0.06
Court Case, Bhagirathi Prusty. Khata No-163/44. Plot No-488/1881 &Khata No. 163/224. Plot No-488/1515. Str& Land not paid.
0.015 Only service road affected
90+810 91+165 0.36 Available
91+165 91+300 0.14
SatyaBhama Das. Khata
No-163/149. Plot No-10/1468, 10/1600, Payment
dispute and court case
0.01 Only service road affected only 20m
91+300 91+350 0.05 Available 91+350 91+390 0.04 Court case.
Plot and Khata no are not
found ROR
DBM completed BS but LHS completed
within width available
Work in progress
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
91+390 97+900 6.51 Available 22
Chinkinia, Pipila97+900 100+400 2.50 Available
100+400 100+580 0.18 Available 100+580 102+100 1.52 Available
Pipilia, Bankaputuli 102+100 102+850 0.75 Available Bankaputuli, Gopalapur 102+850 103+200 0.35 Available
Bankaputuli
103+200 103+600 0.40 Available
103+600 103+750 0.15
Rama Chandra
Naik. Khat No-20. Plot
No-1055,1056,1057 & 602,
Land not payment
Work in progress
103+750 106+200 2.45 Available
106+200 106+400 0.20 Tree cutting in progress
Work in progress
23
Gopalapur, Badaposi
106+400 107+920 1.52 Available
107+920 107+970 0.05
Upper Primary School,
Gopalpur
Work in progress
107+970 109+000 1.03 Available 109+000 110+100 1.10 Available
24Badaposi
110+100 113+776 3.68 Available 113+776 114+080 0.304 Available 114+080 114+194 0.114 Available
Jamunalia114+194 114+440 0.246 Available 114+440 115+250 0.810 Available
Tolankbahal 115+250 115+615 0.365 Available
Tulashichaura, Sirispal 115+615 115+650 0.035 Available 115+650 115+750 0.100 Available
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
115+750 117+100 1.350 Available 117+100 117+400 0.300 Available
25
Sirispal
117+400 117+710 0.310 Available 117+710 120+960 3.250 Available 120+960 121+150 0.190 Available 121+150 121+380 0.230 Available
121+380 121+400 0.020 Available
121+400 121+750 0.350 Available
121+750 121+821 0.071 Available
Sidhmath
121+821 123+500 1.679 Available
123+500 124+080 0.580 Available
124+080 124+180 0.100 Missing Plot
LHS Cannot be
completed till
compensation is made
0.025 Obstruction in LHS only 50m
124+180 125+075 0.895 Available
26Nizgarh 125+075 125+100 0.025 Available
Maligaon
125+100 127+050 1.950 Available
Work in progress
127+050 127+100 0.050 Available
127+100 127+300 0.200 Available
27Gopinathpur, Nuagaon
127+300 128+840 1.540 Available 128+840 128+860 0.020 Available
Nuagaon128+860 129+000 0.140 Available 129+000 129+020 0.020 Available
28
Dhurpada
129+020 129+340 0.320 Available 129+340 129+460 0.120 Available 129+460 129+650 0.190 Available 129+650 129+670 0.020 Available 129+670 129+900 0.230 Available
Dhurpada 129+900 130+340 0.440 Available
Raisuan
130+340 130+370 0.030 Available 130+370 130+600 0.230 Available 130+600 130+650 0.050 Available 130+650 131+090 0.440 Available
131+090 131+140 0.050Govt.
veterinary dispensary
Service road affected 0.012 (0.050/4=0.012) 10M
ONLY IN LHS
29 Raisuan&Gopinathpur 131+140 131+400 0.260 Available 131+400 131+430 0.030 Available 131+430 131+680 0.250 Available
131+680 131+780 0.100Court Case
MCW affected
Service road affected 0.025
(0.100/4=0.025m )ONLY RHS
131+780 132+000 0.220 Available 132+000 132+200 0.200 Available 132+200 132+260 0.060 Available
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
132+260 132+277 0.017 Available 132+277 132+300 0.023 Available 132+300 132+400 0.100 Available 132+400 132+515 0.115 Available 132+515 132+565 0.050 Available
132+565 132+600 0.035 Available
30 Silisuan
132+600 133+420 0.820 Available
133+420 133+450 0.030 Available
133+450 133+505 0.055 Available
133+505 133+580 0.075 Available
31
Banajodi133+580 134+010 0.430 Available
134+010 134+180 0.170 Available
Banajodi134+180 134+475 0.295 Available
134+475 134+575 0.100 Available
32 Banajodi, Padmapur
134+575 134+675 0.100 Available
134+675 134+890 0.215 Available
134+890 134+910 0.020 Available 134+910 134+970 0.060 Available 134+970 134+980 0.010 Available 134+980 135+249 0.269 Available 135+249 135+450 0.201 Available
135+450 136+010 0.560 Available
136+010 136+200 0.190 Available
136+200 136+530 0.330 Available
33
Padmapur, Putulia
136+530 136+580 0.050 Missing Plot Service road affected Available Service road affected
136+580 136+650 0.070W.P in
Honb'le High Court
Service road affected 0.020 Service road affected
136+650 136+700 0.050 Available
136+700 136+760 0.060 Not Available
Submitted to LAO for
further process
136+760 136+820 0.140 Not Available
High Court Case
136+900 136+929 0.029 Available 136+929 137+300 0.371 Available 137+300 137+343 0.043 Available 137+343 137+360 0.017 Available
Putulia 137+360 137+400 0.040 Available
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
137+400 137+600 0.200 Available
Keshpank 137+600 137+920 0.320 Available
137+920 138+420 0.500 Available
34 Jadichatra
138+420 138+480 0.060 Available 138+480 138+500 0.020 Available 138+500 138+523 0.023 Available 138+523 138+943 0.420 Available
35 Bankamarani
138+943 138+963 0.020 Available
138+963 139+000 0.037 Available
139+000 139+037 0.037 Available
139+037 139+200 0.163 Available
139+200 139+300 0.100 Available
139+300 139+469 0.169 Available
139+469 139+632 0.163 Available
36
Bankamarani, Hundla
139+632 140+200 0.568 Available
140+200 141+310 1.110 Available
141+310 141+800 0.490 Available
Jamudiha, Palasponga
141+800 142+060 0.260 Available
142+060 142+195 0.135 Available
142+195 142+205 0.010 Available
37
Palasponga
142+205 142+540 0.335 Available
142+540 143+400 0.860 Available
Palasponga, Murusuan 143+400 143+465 0.065 Available
38 Tangarani
143+465 144+615 1.150 Available
144+615 145+200 0.585 Available
145+200 145+210 0.010 Available
145+210 145+250 0.040 Available
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
145+250 145+270 0.020 Available
Jamuposhi ,Spongepatna
145+270 145+295 0.025 Available
145+295 147+600 2.305 Available
Jhumpura
147+600 147+800 0.200 Available
147+800 148+650 0.850 Available
148+650 149+050 0.400
Compensation is in process .Bhaluka villagers objecting for change of alignment
0.200 100M Local dispute
149+050 149+300 0.250 Available
Jhumpura, Bhaluka&Arsala 149+300 150+000 0.700 Available Structure
Dismentled Available
The mosque dismantled on 30th Jan and the entire stretch is encroachment
free
39Arsala
150+000 150+286 0.286 Available 150+286 150+430 0.144 Available 150+430 150+460 0.030 Available 150+460 150+600 0.140 Available 150+600 150+800 0.200 Available 150+800 152+260 1.460 Available
Sundhimursuan,Balabhadrapur
152+260 152+350 0.090 Available 152+350 152+380 0.030 Available
40 Balabhadrapur
152+380 152+430 0.050 Available 152+430 152+510 0.080 Available
152+510 153+040 0.530 Available
153+040 153+530 0.490 Available
153+530 153+600 0.070 Available
41 Balaibandh,Mursuan158+415 159+400 0.985 Available
159+400 159+415 0.015 Available
IE services for 4 laning of Panikoili-Remuli Section of NH-215 from Km 0.000 Monthly Progress Reportto Km 163.000 in the State of Odisha on DBFOT Basis under NHDP-Phase-III Feb-2017
42
Mursuan
159+415 159+590 0.175 Available
159+590 159+618 0.028 Available
159+618 159+690 0.072 Available
159+690 159+890 0.200 Available
159+890 160+110 0.220 Available
Mursuan,Parsala, Sijukala
160+110 160+380 0.270 Available
160+380 160+445 0.065 Available
160+445 160+573 0.128 Available
160+573 160+675 0.102 Available
160+675 160+728 0.053 Available
160+728 161+085 0.357 Available161+085 161+099 0.014 Available161+099 161+850 0.751 Available161+850 161+950 0.100 Available161+950 162+270 0.320 Available
162+270 162+350 0.080 Available
43
Mursuan,Parsala, Sijukala
162+350 162+450 0.100 Available 162+450 164+500 2.050 Available 164+500 164+540 0.040 Available 164+540 164+650 0.110 Available
Parsala, Sijukala
164+650 164+715 0.065 Available 164+715 165+010 0.295 Available 165+010 166+000 0.990 Available
Rimuli 166+000 166+173 0.173
Deadlock created by public of Taduabahal village from execution of 4-lanning
Total-787mtrs