Sc Magnet test facility
Consolidation
Project presentation
M. Bajko for the TEMBon behalf of the MSC TF
section team31. Aug. 2009
Extracts from the report of the review committee Superconductors and Magnet Laboratories at CERN
May 18 and 19 2009 All LHC magnet types can be tested except a few. An
adaptation of an SM18 bench for this is recommended The OSQAR base program as presented is endorsed. The String test appears as a useful step in the construction
and system validation but it should not replace the individual components tests….
The Fresca 2 program is considered important and should be executed with priority as the facility is important for the CERN program and beyond.
The HTS leads testing is important, new requests for HTS leads for smaller projects may come up and a re-installation of the facility is recommended.
Block4>SM18. The motivation is solid. …. The closing of Block4 in due time and the re-establishing of its functions in SM18 is endorsed.
SM18 benches: the committee endorses to keep 10 benches alive.
The RF line in SM18 is to be replaced to reduce the cryogenic load and to secure the test program as foreseen.
programs
facilities
Goals of the project Unify the Sc magnet test stations ( A + B)
A. the station known as “Block 4” situated in Prevessin, equipped with 4 vertical cryostats ( to test magnet alone in vertical position)
B. the test station known as “SM18” situated in between point 1 and 8, equipped with 12 horizontal test benches (to test magnets with their own cryostat in horizontal position)
Optimizes the use of : services and man power Extend the vertical test station to allow testing
magnets and Sc of future projects ( NIT, HFM, FCM)
Modify the horizontal test benches such to allow testing present and new inner triplet magnets
Prepare a zone for the STRING 3of new inner triplet magnets + Sc link
Stages of the project Part 1: Move the vertical test station from
Prevessin site to SM18 site (Block 4 to SM18 hall) for end of 2010
Part 2.: Modify one horizontal test bench of SM18, such to allow testing the new inner triplet magnet for end of 2011
Part 3. : Modify one or two horizontal test benches of SM18 such to allow testing the present inner triplet magnets , produced and tested by two US laboratories ( BNL and FNAL) as soon as possible for eventual need…
Part 4. : Prepare the STRING3 for 2014
SM18 layout today
Part 1 :The zone where the vertical test station is proposed to be installed
Part 4 :The zone we keep for the STRING 3 of about 60 m long
Part 2 and 3 :Modification of horizontal benches
Main installations
Power supplyand switches
20 kA
Control room
He distribution box
Vertical Cryostats
Platform and electrical racksMagnet preparation
zone
FCM and Sc Link Powering
max. 15 kA
Cryogenics
Cryogenics for FCM, Sc
link and STRING 3
Part 1
What would allow the “part 1” and what are the
difficulties ? The new installation would allow us to test in
Sm18: present LHC corrector magnets, diodes of MBs and MQs, new inner triplet correctors and new inner triplet quadruple model, HFM proptotypes and FRESCA magnet with some modification of one cryostat we should be
able to test also the present LHC HTc current leads. Difficulties:
before installing the new station we have to de-install from Block 4 as we recuperate most of the elements!!!!!
before installation of the vertical cryostats all services has to be ready
for END 2010
Part 1
1st Price estimate The total price to move Block 4 to SM18 and upgrade the control system of the two stations(of 300 kCHF ) is 1622 kCHF distributed as following:
This price does NOT includes.1. FRESCA 2 magnet cryostat ; to be covered by HFM budget2. FCM cryostat ;to be covered by FCM project3. Sc link installation; to be covered by NIT and FP74. Modification of the horizontal test benches for NIT triplet; to be covered by this project5. Modification of the horizontal test benches for present inner triplet ;to be covered by the spare parts projects6. String 3; to be covered by NIT project
245
323
226144
402
105 4235
GS-SEMTE-CRGTE-MSCEN-ELEN-ICEEN-MMETE-EPCEN-CV
In aprox. 3.5 year with the operation and
investment cost of Block 4 we can pay the new vertical
station in SM18
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Fonctionnement bloc4 :Avec 20KA, switch, barres cuivreAvec boite à vannes (possibilité tests avec PS 2KA et 600A)Fonctionnement SM18
PasserelleFabrication Pose avec Rehaussement alimentation triphasée M
Génie Civil (3 puits ou tranchet) + 1 trou + caniveauFabrication chassis et pose M
Installation cryogénieDistribution pompageRetour ballon retour chaudRéchauffeur pour retour froid et chaudBoîte à vannes
Alimentation et câbles de puissanceAlimentation 20KA M
Switch thyristor + mécanique M
Switch inverseur sectionneur M
Alimentation 600A M
Fabri. et pose Barres de cuivre pour distribution 20KA M
Fabri. et pose câbles de puissance entre alim. et barres M
Eau déminéralisée de refroidissement M
TourellesDémontage M
Modification et installation M
Installation racksPlc général+cryo.+ alimentations+sécurité E
Système d'acquisition E
Supervision
Fonctionnement Station- LongueRack cryo ?Rack détection quenches (potentiels) E
Rack mesures magnétique E
Rack Plc automate E
Rack acquisition E
Câbles puissance 20KA + support M
Déplacement et installation cryostat M
Fonctionnement Station- DiodesRack cryoRack lecture (potentiels, températures) E
Rack Plc automate E
Câbles puissance 20KA + support M
Déplacement et installation cryostat Temps pour accomplir les travaux et essais M
Fonctionnement nouvelle Station (Fresca) Fonctionnel
Rack cryoRack détection quenches (potentiels) E
Rack mesures magnétique E
Rack Plc automate E
Rack acquisition E
Câbles puissance 20KA + support M
Cryostat: M
Etude et fabricationinstallation
Insert :Etude et fabrication
mois 1 mois 2 mois 3 mois 4 mois 5 mois 6 mois 7 mois 8 mois 9 mois 10 mois 11 mois 12 mois 13 mois 14 mois 15 mois 16semaine semaine semaine semaine semaine semaine
Infrastructure commune
Installation Station Longue
semaine semaine semaine semaine
Installation station diodes
Installation station Fresca
semaine semaine semaine semaine semaine semaine
Planning
Total of 9 months is needed counting from the civil engineering work starting date to test the NIT magnets
The block 4 will be not operational
for more than 2500 A test
after 4 mounts from the beginning
….and completely stopped after the
6th mounts.
Status todayPart 1:a. layout drawings in EUCLID and in CATIA sufficiently advanced for
colleagues (GS SEM, EN EL, TE CRG) to work for interfaces done by EN MME with TE MSC.
b. GS SEM is well advanced with the dossier for call for tender ( “carottage “ this week). We estimate the start of civil engineering for the second week of January 2010.
c. Control system defined with EN- ICE and TE-CRG
Part 2: a. modelisation of one bench in CATIA has been started
Part 3:b. Information has been recovered from USA labsc. Feasibility study is planned for end of year… depending on resources
in EN MME
Part 4: a. We keep the space available for it.
Difficulties @ short & long term
@ short term: Definition of the cryogenic consumption of the
FRESCA 2 magnet Adapt one cryostat to test : diodes and CL of
all type for LHC @ long term
Leave with the 25g/s capacity of the 6kW CB Lhe production having the RF cryoline consuming 10 g/s. the estimations made by L. Walckiers shows that in 2013 even with a new line, clearly priorities has to be established between the different activities and a good co-ordination of test will be necessary.
Compatibility with 6 kW (@ 25 g/s) CB LHe production
Average consumption needed (in g/s)
Considering 6 kW CB current capacity 25 g/s, the requirements cannot be fulfilled at a present condition.
Only if the CB is fully upgraded (~30g/s) and the cavity transfer line is changed the requirement can be fulfilled except for 2013.
Peak of consumption possible: boosting by LHe, GHe to atmosphere or adapting the priorities between the tests.
New cavity line and CB upgrade is not expected before 2011.
20092nd
20101st
20102nd
20111st
20112nd
20121st
20122nd
20131st
20132nd
20141st
20142nd
Cavities (with new cavity line 2 g/s)*
4 6 6 6 10 10 11 25 23 0 0
Magnets 12.5 13 15 15 17 11 10 11 9 12.5 9.5
Total 16.5 19 21 21 27 21 21 36 32 12.5 9.5
Total if existing SRF cavity line (+10 g/s)**
26.5 29 31 31 37 31 31 46 42 12.5 9.5
* Estimated consumption of the new line ~2g/s
** Consumption of the existing line ~12 g/s
Extract from presentatation of V. BendaNumbers worked out with L. Walkiers
Number of Tests in SM18 up to 2014
Project Test Type
Test duration [week]
2009 2nd 2010 1st 2010 2nd 2011 1st 2011 2nd 2012 1st 2012 2nd 2013 1st 2013 2nd 2014 1st 2014 2nd
RF LHC & soleil cavity Vertical 1 2 2RF LHC & soleil cavity Bunker 4 1 2 1 1RF Quadrupole resonator Vertical 4 2 2 2 2 2RF SPL cavity conditioning Vertical 1 1 2 2 2 8 5 6 20 20RF SPL cavity final tests Bunker 4 1 1 3 3RF HIE-Isolde (cryolab ? ) Vertical 1 9 10 10 10RF HIE-Isolde Bunker 4 2 2 2
MB SSS Spares Hor. benches 1 10 10 10 10 10Quench Protection studies Hor. benches 2 1 1 1 1 1Field Measurement Fidel Hor. benches 2 1 1 1 1 1
LIUP1 Model Quad ST-Long Vertical 2 1 1LIUP1 corrector ST-Long 1 2 2 4 4 4 4 4LIUP1 Proto cold mass Hor. Bench 3 1 1LIUP1 Series Hor. Bench 1 5 5 5 5LIUP1 String Test 10 1
HFM SMC ST-Long 1 1 1 1 1HFM Fresca II (NbSn) New Vertical 4 1 1HFM Fresca II + Insert HTS New Vertical 2 1HFM quad ST-Long 4 1
US Larp New Vertical 2 1 1 1 1 1FCM demonstrator Supercritical 2 1 1 1SPL CLIC models ST-Long 1 1 1 1 1 1 1 1 1 1 1 1
OSQAR 2 hor. benches 10 1 1 1 1 1 1 1 1 1 1 1
Number of tests
Extract from presentatation of V. BendaNumbers worked out with L. Walkiers