sc magnet test facility consolidation project presentation m. bajko for the temb on behalf of the...

14
Sc Magnet test facility Consolidation Project presentation M. Bajko for the TEMB on behalf of the MSC TF section team 31. Aug. 2009

Upload: heaven-pettus

Post on 14-Dec-2015

216 views

Category:

Documents


3 download

TRANSCRIPT

Sc Magnet test facility

Consolidation

Project presentation

M. Bajko for the TEMBon behalf of the MSC TF

section team31. Aug. 2009

Extracts from the report of the review committee Superconductors and Magnet Laboratories at CERN

May 18 and 19 2009 All LHC magnet types can be tested except a few. An

adaptation of an SM18 bench for this is recommended The OSQAR base program as presented is endorsed. The String test appears as a useful step in the construction

and system validation but it should not replace the individual components tests….

The Fresca 2 program is considered important and should be executed with priority as the facility is important for the CERN program and beyond.

The HTS leads testing is important, new requests for HTS leads for smaller projects may come up and a re-installation of the facility is recommended.

Block4>SM18. The motivation is solid. …. The closing of Block4 in due time and the re-establishing of its functions in SM18 is endorsed.

SM18 benches: the committee endorses to keep 10 benches alive.

The RF line in SM18 is to be replaced to reduce the cryogenic load and to secure the test program as foreseen.

programs

facilities

Goals of the project Unify the Sc magnet test stations ( A + B)

A. the station known as “Block 4” situated in Prevessin, equipped with 4 vertical cryostats ( to test magnet alone in vertical position)

B. the test station known as “SM18” situated in between point 1 and 8, equipped with 12 horizontal test benches (to test magnets with their own cryostat in horizontal position)

Optimizes the use of : services and man power Extend the vertical test station to allow testing

magnets and Sc of future projects ( NIT, HFM, FCM)

Modify the horizontal test benches such to allow testing present and new inner triplet magnets

Prepare a zone for the STRING 3of new inner triplet magnets + Sc link

Stages of the project Part 1: Move the vertical test station from

Prevessin site to SM18 site (Block 4 to SM18 hall) for end of 2010

Part 2.: Modify one horizontal test bench of SM18, such to allow testing the new inner triplet magnet for end of 2011

Part 3. : Modify one or two horizontal test benches of SM18 such to allow testing the present inner triplet magnets , produced and tested by two US laboratories ( BNL and FNAL) as soon as possible for eventual need…

Part 4. : Prepare the STRING3 for 2014

SM18 layout today

Part 1 :The zone where the vertical test station is proposed to be installed

Part 4 :The zone we keep for the STRING 3 of about 60 m long

Part 2 and 3 :Modification of horizontal benches

The vertical test station zone

As today

As proposed

Part 1

The vertical

cryostats

Main installations

Power supplyand switches

20 kA

Control room

He distribution box

Vertical Cryostats

Platform and electrical racksMagnet preparation

zone

FCM and Sc Link Powering

max. 15 kA

Cryogenics

Cryogenics for FCM, Sc

link and STRING 3

Part 1

What would allow the “part 1” and what are the

difficulties ? The new installation would allow us to test in

Sm18: present LHC corrector magnets, diodes of MBs and MQs, new inner triplet correctors and new inner triplet quadruple model, HFM proptotypes and FRESCA magnet with some modification of one cryostat we should be

able to test also the present LHC HTc current leads. Difficulties:

before installing the new station we have to de-install from Block 4 as we recuperate most of the elements!!!!!

before installation of the vertical cryostats all services has to be ready

for END 2010

Part 1

1st Price estimate The total price to move Block 4 to SM18 and upgrade the control system of the two stations(of 300 kCHF ) is 1622 kCHF distributed as following:

This price does NOT includes.1. FRESCA 2 magnet cryostat ; to be covered by HFM budget2. FCM cryostat ;to be covered by FCM project3. Sc link installation; to be covered by NIT and FP74. Modification of the horizontal test benches for NIT triplet; to be covered by this project5. Modification of the horizontal test benches for present inner triplet ;to be covered by the spare parts projects6. String 3; to be covered by NIT project

245

323

226144

402

105 4235

GS-SEMTE-CRGTE-MSCEN-ELEN-ICEEN-MMETE-EPCEN-CV

In aprox. 3.5 year with the operation and

investment cost of Block 4 we can pay the new vertical

station in SM18

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Fonctionnement bloc4 :Avec 20KA, switch, barres cuivreAvec boite à vannes (possibilité tests avec PS 2KA et 600A)Fonctionnement SM18

PasserelleFabrication Pose avec Rehaussement alimentation triphasée M

Génie Civil (3 puits ou tranchet) + 1 trou + caniveauFabrication chassis et pose M

Installation cryogénieDistribution pompageRetour ballon retour chaudRéchauffeur pour retour froid et chaudBoîte à vannes

Alimentation et câbles de puissanceAlimentation 20KA M

Switch thyristor + mécanique M

Switch inverseur sectionneur M

Alimentation 600A M

Fabri. et pose Barres de cuivre pour distribution 20KA M

Fabri. et pose câbles de puissance entre alim. et barres M

Eau déminéralisée de refroidissement M

TourellesDémontage M

Modification et installation M

Installation racksPlc général+cryo.+ alimentations+sécurité E

Système d'acquisition E

Supervision

Fonctionnement Station- LongueRack cryo ?Rack détection quenches (potentiels) E

Rack mesures magnétique E

Rack Plc automate E

Rack acquisition E

Câbles puissance 20KA + support M

Déplacement et installation cryostat M

Fonctionnement Station- DiodesRack cryoRack lecture (potentiels, températures) E

Rack Plc automate E

Câbles puissance 20KA + support M

Déplacement et installation cryostat Temps pour accomplir les travaux et essais M

Fonctionnement nouvelle Station (Fresca) Fonctionnel

Rack cryoRack détection quenches (potentiels) E

Rack mesures magnétique E

Rack Plc automate E

Rack acquisition E

Câbles puissance 20KA + support M

Cryostat: M

Etude et fabricationinstallation

Insert :Etude et fabrication

mois 1 mois 2 mois 3 mois 4 mois 5 mois 6 mois 7 mois 8 mois 9 mois 10 mois 11 mois 12 mois 13 mois 14 mois 15 mois 16semaine semaine semaine semaine semaine semaine

Infrastructure commune

Installation Station Longue

semaine semaine semaine semaine

Installation station diodes

Installation station Fresca

semaine semaine semaine semaine semaine semaine

Planning

Total of 9 months is needed counting from the civil engineering work starting date to test the NIT magnets

The block 4 will be not operational

for more than 2500 A test

after 4 mounts from the beginning

….and completely stopped after the

6th mounts.

Status todayPart 1:a. layout drawings in EUCLID and in CATIA sufficiently advanced for

colleagues (GS SEM, EN EL, TE CRG) to work for interfaces done by EN MME with TE MSC.

b. GS SEM is well advanced with the dossier for call for tender ( “carottage “ this week). We estimate the start of civil engineering for the second week of January 2010.

c. Control system defined with EN- ICE and TE-CRG

Part 2: a. modelisation of one bench in CATIA has been started

Part 3:b. Information has been recovered from USA labsc. Feasibility study is planned for end of year… depending on resources

in EN MME

Part 4: a. We keep the space available for it.

Difficulties @ short & long term

@ short term: Definition of the cryogenic consumption of the

FRESCA 2 magnet Adapt one cryostat to test : diodes and CL of

all type for LHC @ long term

Leave with the 25g/s capacity of the 6kW CB Lhe production having the RF cryoline consuming 10 g/s. the estimations made by L. Walckiers shows that in 2013 even with a new line, clearly priorities has to be established between the different activities and a good co-ordination of test will be necessary.

Compatibility with 6 kW (@ 25 g/s) CB LHe production

Average consumption needed (in g/s)

Considering 6 kW CB current capacity 25 g/s, the requirements cannot be fulfilled at a present condition.

Only if the CB is fully upgraded (~30g/s) and the cavity transfer line is changed the requirement can be fulfilled except for 2013.

Peak of consumption possible: boosting by LHe, GHe to atmosphere or adapting the priorities between the tests.

New cavity line and CB upgrade is not expected before 2011.

20092nd

20101st

20102nd

20111st

20112nd

20121st

20122nd

20131st

20132nd

20141st

20142nd

Cavities (with new cavity line 2 g/s)*

4 6 6 6 10 10 11 25 23 0 0

Magnets 12.5 13 15 15 17 11 10 11 9 12.5 9.5

Total 16.5 19 21 21 27 21 21 36 32 12.5 9.5

Total if existing SRF cavity line (+10 g/s)**

26.5 29 31 31 37 31 31 46 42 12.5 9.5

* Estimated consumption of the new line ~2g/s

** Consumption of the existing line ~12 g/s

Extract from presentatation of V. BendaNumbers worked out with L. Walkiers

Number of Tests in SM18 up to 2014

Project Test Type

Test duration [week]

2009 2nd 2010 1st 2010 2nd 2011 1st 2011 2nd 2012 1st 2012 2nd 2013 1st 2013 2nd 2014 1st 2014 2nd

RF LHC & soleil cavity Vertical 1 2 2RF LHC & soleil cavity Bunker 4 1 2 1 1RF Quadrupole resonator Vertical 4 2 2 2 2 2RF SPL cavity conditioning Vertical 1 1 2 2 2 8 5 6 20 20RF SPL cavity final tests Bunker 4 1 1 3 3RF HIE-Isolde (cryolab ? ) Vertical 1 9 10 10 10RF HIE-Isolde Bunker 4 2 2 2

MB SSS Spares Hor. benches 1 10 10 10 10 10Quench Protection studies Hor. benches 2 1 1 1 1 1Field Measurement Fidel Hor. benches 2 1 1 1 1 1

LIUP1 Model Quad ST-Long Vertical 2 1 1LIUP1 corrector ST-Long 1 2 2 4 4 4 4 4LIUP1 Proto cold mass Hor. Bench 3 1 1LIUP1 Series Hor. Bench 1 5 5 5 5LIUP1 String Test 10 1

HFM SMC ST-Long 1 1 1 1 1HFM Fresca II (NbSn) New Vertical 4 1 1HFM Fresca II + Insert HTS New Vertical 2 1HFM quad ST-Long 4 1

US Larp New Vertical 2 1 1 1 1 1FCM demonstrator Supercritical 2 1 1 1SPL CLIC models ST-Long 1 1 1 1 1 1 1 1 1 1 1 1

OSQAR 2 hor. benches 10 1 1 1 1 1 1 1 1 1 1 1

Number of tests

Extract from presentatation of V. BendaNumbers worked out with L. Walkiers