co2 emission comparison wp3 final english
TRANSCRIPT
-
8/4/2019 Co2 Emission Comparison WP3 Final English
1/30
Carbon Dioxide Capture from Coal-FiredPower Plants in China
Summary Report for NZEC Work Package 3September, 2009
Preparedby:
DoosanBabcockEnergyLimited JacquelineGIBSONandDiemoSCHALLEHN
TsinghuaUniversity,
DepartmentofChemicalEngineeringZHENGQueandCHENJian
TsinghuaUniversity,
DepartmentofThermalEngineering, Key
LaboratoryforThermalScienceandPower
EngineeringofMinistryofEducation
WANGShujuan
GreengenCo.Ltd,Beijing CAOJiang
ImperialCollegeLondon,
MechanicalEngineeringDepartment,
EnergyTechnologyforSustainable
DevelopmentGroup
JonGIBBINSandMathieuLUCQUIAUD
NorthChinaElectricPowerUniversity,KeyLabofConditionMonitoringandControl
forPowerPlantEquipmentofMinistryof
Education
YANGYongping,XUGangandDUANLiqiang
TsinghuaUniversity,BPCleanEnergy
Research&EducationCentreXUZhaofeng
WuhanUniversity HUJicaiandLIJi
ZhejiangUniversity,StateKeyLaboratoryof
CleanEnergyUtilization
FANGMengxiang,YANShuipingandLUO
Zhongyang
-
8/4/2019 Co2 Emission Comparison WP3 Final English
2/30
ii
050
100150200250
300350400
Advanced
supercrit
800MW
Oxyfiring Postcom
MEA
Postcom
aqueous
ammonia
Precom
IGCC
Precom
polygen
Existing
600MW
supercrit
Postcom
MEA
Postcom
aqueous
ammonia
Existing
300MW
subcrit
Postcom
MEA
Postcom
aqueous
ammonia
0
200
400
600
800
1000
Advanced
supercrit
800MW
Oxyfiring Postcom
MEA
Postcom
aqueous
ammonia
Precom
IGCC
Precom
polygen
Existing
600MW
supercrit
Postcom
MEA
Postcom
aqueous
ammonia
Existing
300MW
subcrit
Postcom
MEA
Postcom
aqueous
ammonia
0
5000
10000
15000
20000
Advanced
supercrit
800MW
Oxyfiring Postcom
MEA
Postcom
aqueous
ammonia
Precom
IGCC
Precom
polygen
Existing
600MW
supercrit
Postcom
MEA
Postcom
aqueous
ammonia
Existing
300MW
subcrit
Postcom
MEA
Postcom
aqueous
ammonia
0
10
20
30
40
50
Advanced
supercrit
800MW
Oxyfiring Postcom
MEA
Postcom
aqueous
ammonia
Precom
IGCC
Precom
polygen
Existing
600MW
supercrit
Postcom
MEA
Postcom
aqueous
ammonia
Existing
300MW
subcrit
Postcom
MEA
Postcom
aqueous
ammonia
NetEfficiency
(%L
HV)
CostofElectricity
(RMB/MWh)
Power plant net efficiencies with and without CO2 capture
Cost of electricity with and without CO2 capture, 85% load factor, 10% discount rate, tax not includedCoal costs: 16 RMB/GJ / 32 RMB/GJ
Capital expenditure
CAPEX = Total Installed Cost + 10% contingency + 7% owners costs, financing costs and taxes not included
Relativetonewbuildadvancedsupercritical
pulverisedcoalplant
Relativeto
existing600MW
supercritical coal
plant
Relativeto
existing300MW
subcritical coal
plant
CAPEX(RMB/kW)
CostofAbat
ement
(RMB/tCO2)
Cost of abatement
ExecutiveSummary
ThisreportdrawsonthecaptureplantcasestudiesbyNZECWorkPackage3partnerstopresent,in
aunifiedandconsistent form,the technicalandeconomicperformanceofpowergenerationwith
CO2 capture in China. Complementary work on performance calculations by Chinese and UK
partnershasbeencombinedwhereappropriatetogiveestimatedfinaloverallplantefficienciesand
CO2emission levels. Estimatedcapitalcostshavebeenusedtoderive levelisedcostsofelectricity
andemissionabatementcostsonaconsistentbasis.
Advancednewbuildcapturetechnologiesthathavestilltobedemonstrated,oxyfiring,post
combustionwithaqueousammoniaandprecombustioncaptureonIGCC,arepredictedtoachieve
similarpowerplantefficienciesof35.6,35.7and36.8%respectively. CAPEXvaluesfortheseplants
areapproximately9000to10000RMB/kWnet,withanestimated+/ 30%uncertainty. Levelised
costsofelectricityfortheseoptionsareestimatedtohavearangeofapproximately370410
RMB/MWhforacoalcostof16RMB/GJandapproximately40%higherforacoalcostof32RMB/GJ.
Costsofabatementarecalculatedrelativetothestandardalternativeplantthatwouldbebuilt,an
advancedsupercriticalplant. Sincethecostofabatementisbasedonthedifferencesbetweenrelativelylargernumbersthereismorevarianceintheresults,fromanestimated140RMB/tCO2for
oxyfiringto200RMB/tCO2forIGCC+CCS. Thesevaluesare,however,verysensitivetoestimatesfor
captureplantcosts,particularlytheadditionalcapitalcosts,andshouldberegardedaspreliminary.
PostcombustioncapturewithanMEAbased solvent,anolder technology, ispredicted tohavea
generally less favourableperformance.Polygenerationofelectricityandmethanolalsoappears to
havealowefficiencyandhighcapitalcosts,butthemethanolproductionisnottakenintoaccount.
-
8/4/2019 Co2 Emission Comparison WP3 Final English
3/30
iii
Table of contents1.Backgroundandsupportingcasestudyreports 1
1.1Backgroundandscope 1
1.2Contributingreports 1
2. PowergenerationfromnewbuildpulverisedcoalplantswithCCS(DB,DCE,DTE,IMP,NCEPU,ZJU) 2
2.1Advancedsupercriticalbaseplantfornewbuildcasestudieswithandwithoutcapture 2
2.2CO2captureusingoxyfiring(DB,ZJU) 5
2.3 Post-combustion CO2 capture (DCE, DTE, IMP, NCEPU, ZJU) 6
2.3.1 MEApostcombustioncapturesystem(DCE) 6
2.3.2Aqueousammoniapostcombustioncapturesystem(DTE) 7
2.3.3Thermalintegrationbetweenthepowerplantsteamcycleandpostcombustioncaptureunitsandcalculationofoverallplantefficiencyandcostwithcapture(DCE,DTE,IMP,NCEPU,ZJU) 8
3. PostcombustioncapturefromexistingChinesepowerplants(NCEPU) 11
3.1Chinese600MWsupercriticalunit 11
3.2Chinese300MWsubcriticalunit 11
3.3PerformancewithoutandwithCO2capture 11
4. ElectricpowergenerationwithprecombustionCO2capture(GG,THCEC) 12
4.1Background 12
4.2GS1 2400MWIGCCusingTPRIgasifierwithCCS(GG) 14
4.3GS2 1400MWpolygenerationsystemwithCCS(THCEC) 15
5. SummaryofCO2captureperformancefordifferentplanttypes 17
AppendixACasestudybasis 21
AppendixBTabulatedsummaryoftechnicalandeconomicperformance 23ofcoalfiredpowerplantswithCO2captureunderChineseconditions
AppendixC CO2captureusingmembranegasabsorptiontechnology 24
AppendixD LevelisedcostoftransportingCO2asafunctionofmassflowrate 26
-
8/4/2019 Co2 Emission Comparison WP3 Final English
4/30
1
1.Backgroundandsupportingcasestudyreports
1.1 Background and scope
ThisreportdrawsonthefollowingcaptureplantcasestudiesbyNZECWorkPackage3partners.
Salientfeaturesofthesestudiesarepresentedinthissummaryreportbutfordetailedinformation
readersshouldrefertotheoriginalsource(s). Theseareindicatedinthetextbytheappropriate
partnerabbreviationsshowninbracketsaftersectionheadings.
Theprincipalpurposeofthisreportistopresentinaunifiedandconsistentformthetechnicaland
economicperformanceofthemaincapturecasestudies. Complementaryworkonperformance
calculationsbyChineseandUKpartnershasbeencombinedwhereappropriatetogivefinaloverall
plantefficienciesandCO2emissionlevels. Estimatedcapitalcostshavebeenusedtoderivelevelised
costsofelectricityandemissionabatementcostsonaconsistentbasis. Thesearepresentedin
graphicalandtabulatedforms.
1.2 Contributing NZEC Work Package 3 Reports
Partner
Abbreviation
FullName ReportTitle
DB DoosanBabcockEnergyLimited JRGibsonandDSchallehn, ChinaUKNear
ZeroEmissionsCoal(NZEC)Oxyfiring
Options
DCE TsinghuaUniversity, Departmentof
ChemicalEngineering
QueZhengandJianChen,Costestimationfor
CO2CapturewithaMEAabsorptionprocess
DTE TsinghuaUniversity,Departmentof
ThermalEngineering, KeyLaboratory
forThermalScienceandPower
EngineeringofMinistryofEducation
WangShujuan,CarbonDioxideCaptureUsing
MDEAandAmmoniaSolutions
GG GreengenCo.,Ltd,Beijing CaseStudyforIGCCPowerPlantInChina
(withCCS)
IMP ImperialCollegeLondon,Mechanical
EngineeringDepartment,Energy
TechnologyforSustainable
DevelopmentGroup
MathieuLucquiaud, Steamcyclecalculations
forcapturereadysteamcycleandretrofits
withMEA,ammoniaandMDEAsolvents
NCEPU NorthChinaElectricPowerUniversity,
KeyLabofConditionMonitoringand
ControlforPowerPlantEquipmentof
MinistryofEducation
YongpingYang,GangXuandLiqiangDuan,
CarbonDioxideCapturefromExistingCoal
FiredPowerPlantinChina
THCEC TsinghuaUniversity,BPCleanEnergy
Research&EducationCentre
XUZhaofeng, Polygenerationusingtwo
stageslurrygasifierwithCCS
WHU WuhanUniversity HuJicaiandLiJi,CO2Transport
ZJU ZhejiangUniversity,StateKey
LaboratoryofCleanEnergyUtilization
MengxiangFang,ShuipingYanand
ZhongyangLuo,CarbonDioxideCapturefrom
aNewbuiltUltraSupercriticalPCPowerPlant
-
8/4/2019 Co2 Emission Comparison WP3 Final English
5/30
2
UsingHollowFibreMembraneContactors
2. PowergenerationfromnewbuildpulverisedcoalplantswithCCS(DB,DCE,
DTE,IMP,NCEPU,ZJU)
2.1 Advanced supercritical base plant for new build case studies with and withoutcapture (DB)
Newbuild, pulverised coal (PC) capture studies are based on Advanced Supercritical (ASC) Boiler
Turbine (BT) technology. Advanced supercritical boilers are already operating in China, with an
estimated Total Installed Cost of 5000 RMB/kW based on Chinese partners experience. Present
stateoftheart advanced supercritical boiler/turbine technology is used, with steam turbine inlet
conditionsof280bar/ finalsuperheat temperatureof600C/ final reheat temperatureof610C,
givinganefficiencyforthesiteandcoalsspecifiedof43.9%LHVnet. Emissionscontrolsconsistof
DeNOx,particulateremovalandDeSOxplant. Aunitwithanoutputof824.3MWnetisusedasthe
base case fornew build pulverised coaloptions with capture. This size ofunit is typical fornew
advanced supercriticalboilers planned in Europe and alsogives PC capture options with net MW
outputsthatareclosetothelimitingsizeforIGCC+CCSoptions. LargerPCbaseunits(e.g.10001200
MW)arefeasibleandarelikelytobebuiltinChina,buttheoutputoftheIGCC+CCSunitislimitedby
thesizeofthelargestgasturbinesavailable.
AblockflowdiagramforthebasecaseASCPCplant isshown inFigure21. Abriefdescriptionof
eachoftheunitsidentifiedintheblockflowdiagramisgivenbelow,withasubsectionaddinghow,if
atall,itmightneedtobemodifiedforuseinaPCbasedcaptureplant. Thebasecaseunitburnscoal
inairandsoalsodothepostcombustioncapturecases;thebaseplantdesignremainsessentially
unmodified for theseapart from theTurbine Island. Foroxyfiringcapture, thecoal isburntusing
oxygen insteadofair,mixedwith recycledcombustionproductsat theburners tomoderate flame
temperatures. Foroxyfiringcapturecertainaspectsofsometheunits inthebaseplantdesignwill
havetobechangedwhileotherswouldbeusedunaltered,asindicated.
Boiler:Theadvancedsupercriticalboiler isbasedonthestateoftheartDoosanBabcockTwoPass
single reheat BENSON boiler with Posiflow Technology, Balanced Draught, and Gas Biasing for
reheatsteamtemperaturecontrol.
Coalandashhandling:Aconventional system isemployed,withthedesignofthefurnacebottom
ash and fly ash systems from the boiler and downstream particulate removal systems following
modern conventional air fired power generation plant practice which aims to minimise tramp air
ingress.
PulverisedFuelMillingPlant: Coalwillbemilledusingconventionalpulverisers. Inthiscase,tube
-
8/4/2019 Co2 Emission Comparison WP3 Final English
6/30
3
mills are selected to pulverise the coal to a suitable fineness (typically >80% passing through
75microns). Ifthecoalsareinclinedtowardssubbituminouscoalsthenrollerorballmillscouldbe
substituted.
Modifications
for
capture
cases: Inanypulverisedfuelcombustionplantwithadirectfiringsystem
the primary gas supplied to the mill is required to both dry the asfired coal and to convey the
pulverisedcoalfromthemilltotheburners. Inthecaseofairfiring,hotcombustionairissupplied
from theair/gasheater,and in the caseofoxyfiring, fluegas is recycled from theFGDoutletand
passesthroughagas/gasheater. Theabilityoftheprimarygastodrythefuelisdrivenbytwofactors,
theoveralltemperatureandheatcapacityofthegasenteringthemill,and itsmoisturecontent.In
bothoxyfiringandair firingthetemperatureoftheprimarygas issimilar,althoughthevolumetric
heat capacity of recycled flue gas is greater than that of air due to the higher density of CO2
comparedtonitrogen.Whenoperatinginairfiringmodethemoistureinthecombustionair(i.e.its
relativehumidity) is low,making thedryingprocesseasierastheairhasahighcapacity toabsorb
evaporatingmoisture. Foroxyfiringoperationtherawrecycledfluegastypicallyhasasubstantially
highermoisturecontentwhich limits thedrying capacity.This reduction indrying capacity canbe
mitigatedbybothincreasingthemilloutlettemperature(althoughtherearepracticallimitstothis)
andbyreducingthemoisturecontentoftherecycledfluegas.
TurbineIsland: Stateoftheartadvancedsupercriticalturbinetechnologywillbeutilized.
Modificationsforcapturecases: Thiswillbeusedwithoutmodificationfromtheairfiringdesignfor
oxyfiring, but with provision for steamextractionafter the intermediatepressure (IP) cylinder for
postcombustioncapture (see section2.3.3below). Rejectedheat from the captureequipment is
usedtominimisethesteamextractionforfeedwaterheatingforallcaptureoptions.
DeNOx: New build plant is required to meetNOx emissions regulations (450mg/Nm3 @ 6%O2).
TechnologiesbasedonprimaryNOxreductionmeasures,(lowNOxburnersandoverfireair (OFA)),
andsecondarymeasures,(SelectiveCatalyticReduction(SCR)),canbeused.
Modificationsforcapturecases: DeNOxplantisnotarequirementwithintheoxyfiringboilerisland
astheNOxiscapturedinthedownstreamcompressionplant. However,DeNOxplantwillneedtobe
installedforpostcombustioncapturecaseswithairfiring.
ESP:Particulateremovalplantisessentialtobothmeetdustemissionlevellimits,asdefinedbythe
applicable environmental legislation, and to protect downstream flue gas fans and blowers from
excessiveerosion.ElectrostaticPrecipitators(ESP)areusedintheNZECbasecase.
Modifications forcapturecases: Whenoperating inoxyfiringmode theparticulateremovalplant
ensuresthattheFGRstreamsarerelativelydustfree.Theproposedoxyfiringandpostcombustion
-
8/4/2019 Co2 Emission Comparison WP3 Final English
7/30
4
plants both also utilise an ESP. Previous studies have shown that, as a direct result of the
performanceoftheairheater/gasgasheatermodule,theoperatingtemperatureoftheelectrostatic
precipitator (ESP) is increased during oxyfiring operation to typically between 160C and 200C.
Normally higher temperatures lead to less gas residence time in the ESP with a resulting loss in
particulatecollectionefficiency. However,oxyfiring fluegashasahigherdensitythanairfired flue
gasandthismitigatesthelossinefficiencyarisingfromtheincreasedtemperature.
DeSOx: ForairfiringanFGDisrequiredtomeetemissionslegislation.
Modificationsforcapturecases: Particularattentionwillbegiventoachievingaveryhighlevelof
removal(
-
8/4/2019 Co2 Emission Comparison WP3 Final English
8/30
5
2.2 CO2 capture using oxyfiring (DB, ZJU)
Overall,thekeyfeaturesofoxyfiring vsairfiringare:
IncorporationofanairseparationunitforremovalofN2tosupplyanearlypureO2stream
intotherecycledfluegasforthecombustionprocess.
Recirculationoffluegasbacktotheboiler(viaanFGDfortheNZECcoals)providinga
transportmediumforthepfandtomaintaintheradiativeandconvectiveheattransfer
characteristicsofthefurnaceandboiler.
Incorporationofgasgasheatersinsteadofconventionalairpreheatingarrangements.
Incorporationofafluegascoolerandcondensertorecoverheatintothesteamcycle
condensateandfeedwaterpreheatingsystems.
CO2compressionandinertsseparationplant,incorporatingadditionalsulphurremoval
Thisisconsideredalowriskapproachforanoperatorneedingtobeabletomaintainelectrical
outputbecausetheplantdesignsretainfullairfiringcapability,minimisingcommercialandtechnical
riskshouldtheoxyfiringcomponentsbeunavailable,byallowingcontinuedgenerationifthe
oxyfiringplantisoutofservice. Itisenvisagedthatanairfiringcapabilitywillonlybeappliedtothe
initialdemonstrationplants,however,astherearesignificantcostsassociatedwithretainingthison
anoxyfiringplant.
-
8/4/2019 Co2 Emission Comparison WP3 Final English
9/30
6
Thisconfigurationthusoffersanevolutionaryapproachfromwellknownandunderstoodplant:
Theplantisdesignedwithoperationalandpracticalexperienceofairfiring.
Similaritiesindesignandoperationtoconventionalairfired,pulverisedcoalpowerplants
foreachofthemajorplantsystemsandcomponents.
Newplantsystems(ASU,compressors)andcomponentsarewellprovendesignsand
commerciallyavailableattherequiredcapacities.
TheoxyfiringcasestudybyDoosanBabcockhasshownthatforanadvancedsupercriticalpower
plantdesignedtocaptureCO2thepenaltyintermsofcycleefficiencyis8.3percentagepoints
comparedwithanairfiredcasewithnoCO2capture,givingafinalefficiencyof35.6%LHVnet.This
penaltyhasbeenmitigatedbyrecoveringheatwithinthesystemtooffsettheadditionalpower
consumptionoftheCO2compressionplantandairseparationunit. Anapproximateestimateisthat
capitalcostsforsuchanoxyfiringplantwillbe48%higheronaRMB/kWbasisthanfora
conventionalairfiredplant(butbasedonUKexperience,ratherthandirectChinesemarketcosting),
givingaTotalInstalledCostof7390RMB/kWforanassumedbaseplantTIC(basedonestimates
fromChinesepartners)of5000RMB/kW. UnlikepostcombustionCO2capturesystems,oxyfiring
plantsdonotneedtomakeupanyCO2capturesolventlosses,sothisfairlysignificantcontribution
torunningcostsisavoided.
2.3 Postcombustion CO2 capture (DCE, DTE, IMP, NCEPU, ZJU)
PostcombustionCO2capturebasedontheuseofmonethanolamine(MEA)solutionswasstudiedin
conventional packedabsorbercolumns(DCE)andinmembranecontactors(ZJUalsoseeAppendix
C). Whilethelatterofferpotentialadvantagesforgasandsolidshandling,theselectedmembrane
materialswerelimitedtomorediluteMEAsolutions(20%w/w)thanthepackedcolumns(30%w/w).
Thismeantthattheperformanceofthemembranesystemwasworseandthereforenoresultsare
reportedinthedetailedcostcomparison;additionalworkisneededonthisnovelapproachifitisto
havethepotentialofbecomingcompetitivewithotheroptions. Similarly,theuseof
methyldiethanolamine(MDEA)inaconventionalpackedcolumn,examinedbyDTE,isalsonot
reportedinthissummarysinceitdidnotappeartoofferanysignificantadvantageoverMEA.
-
8/4/2019 Co2 Emission Comparison WP3 Final English
10/30
7
TheuseofaqueousammoniaasaCO2solventwasalsostudiedbyDTE. Whilestillrequiringfurther
developmentworkthisapproachappearstohavethepotentialtooffersignificantadvantagesin
termsofreducedenergypenaltyandcapitalcosts. Ithasthereforebeenincludedinthecomparative
analysisasapossibleexampleofthebenefitsthatimprovedpostcombustioncapture,usingthisor
othersecondgenerationsolvents,maybeabletodeliver,comparedwithplantsusingdesignsbased
ontheindustrystandardMEAsolvent.
2.3.1 MEApostcombustioncapturesystem(DCE)
AschematicflowdiagramfortheMEAcaptureprocessisshowninFigure22.
Figure22 ProcessflowdiagramforMEAcapture
TheconventionalMEAprocessisatemperatureswingabsorptionprocess.TheremovalofCO2from
fluegasisachievedbycontactingthefeedfluegasinanamineabsorberwithanaqueoussolutionof
analkanolamineatalowtemperature,wherethecarriersolution,anaqueousaminesolution
absorbsCO2toformcarbamateorbicarbamateionsandbecomeaCO2richsolution.Meanwhile,
CO2isremovedfromthefluegas.Inasolventregenerator,theCO2richsolutionthenliberatesthe
dissolvedCO2atanelevatedtemperaturetoreversetheabsorptionreactionandbecomesalean
solution.AhighpurityCO2streamisreleasedfromthesolventregeneratorandisthencompressed
to110atmospheres.TheregeneratedCO2leanaminesolutionisthencooledandrecycledtothe
amineabsorberfromthesolventregeneratorforfurtherCO2removal. Boththermalenergyand
electricalenergy,thelatterprincipallyforsolventpumping,fluegasblowersandCO2compression,
arerequiredtoruntheMEAcaptureprocess. Inthisstudyastandardvalueof150kWhpertonneof
CO2capturedisestimatedtoberequiredfortheelectricalenergyinput.
-
8/4/2019 Co2 Emission Comparison WP3 Final English
11/30
8
2.3.2Aqueousammoniapostcombustioncapturesystem(DTE)
AsshowninFigure23asimilarflowdiagramisusedforpostcombustioncaptureusingaqueous
ammoniasolutionsbut,becauseofthevolatilityoftheammonia,acondensermustbeprovided
insidethestripper.Theleansolutionfromthestripperiscooledbytherichsolutionandfurtherin
anexternallycooledheatexchangerinordertoreachthedefinedabsorberinlettemperature.In
addition,becauseofthevolatilityofammonia,theN2leavingtheabsorptioncolumnandtheCO2
leavingthedesorptioncolumnwillcontainsomeNH3. Additionalwaterwashingcolumnsareused
toabsorbthisNH3.
The CO2 absorber for ammonia capture is similar to SO2 absorbers (i.e. flue gas desulphurisation
plants FGD)and isdesignedtooperatewithaslurryfeed.Thefluegasflowsupwards incounter
current to the slurry containing a mix of dissolved and suspended ammonium carbonate and
ammoniumbicarbonate;90%oftheCO2fromthefluegasiscapturedintheabsorber.TheCO2rich
slurry from the absorber contains mainly ammonium bicarbonate as the dispersed solids, which
dissolves as the temperature increases in the heat exchanger to about 80C before it enters the
stripper.
Figure23Processflowdiagramforaqueousammoniacapture
-
8/4/2019 Co2 Emission Comparison WP3 Final English
12/30
9
2.3.3Thermalintegrationbetweenthepowerplantsteamcycleandpostcombustioncaptureunits
andcalculationofoverallplantefficiencyandcostwithcapture(DCE, DTE, IMP, NCEPU,
ZJU)
Effectiveintegrationbetweenthebasepowerplantandthepostcombustioncaptureequipmentis
essentialtokeeptheefficiencypenaltytoaminimum. AsshowninFigure24,lowpressuresteam
forsolventregenerationisextractedfromthecrossoverpipebetweentheintermediatepressure(IP)
andlowpressure(LP)turbinecylindersandheatrecoveredfromthecaptureplant(principallyfrom
initialCO2cooling)andfromtheCO2compressorintercoolersisrecoveredandusedforcondensate
heat(avoidingtheneedtoextractsteamfromtheLPturbine).
Thesteamturbineshavebeendesignedwithanintermediatepressure(IP)turbinecapableof
operatingwithafloatingoutletpressure,adesignthat(withslightlydifferentmodifications) is
suitableforbothcapturereadysteamplantsandnewbuildpowerplantsthatarecapableofflexible
operation. AfloatingIPturbinehastheadvantageofavoidingthethrottlinglossesofacontrolled
extractionsystemwithavalveattheLPturbinewhentheplantisoperatingwithcapturewhilenot
affectingtheplantefficiencywithoutcapture.TheIPturbineoutletpressureishigherthanthe
operatingpressureofthesolventreboilerwhentheplantdoesnotcaptureCO2.WhenCO2is
capturedsteamisextractedandsenttothesolventreboilertheIPoutletpressuredropstothe
pressurerequiredtofeedthesolventreboiler.
LPsteamextractionforfeedwaterheatingisreducedto10%ofthenoncapturevaluebyheating
boilercondensateusingheatrecoveredfromcoolingtheCO2afterthestripperandcompressor
stages. CalculatedpowerplantperformancewithoutandwithCO2captureisshowninTable21
below.
Tocalculatetheperformanceofthenewbuildpostcombustioncapturecasesthebasecase
advancedsupercriticalplantwasassumedtobemodifiedslightlytooperatewiththesteamcycle
showninFigure24. WhenthesteamrequiredforoperatingtheCO2captureplants,determinedby
modellingthecapturesystemsdescribedin2.3.1and2.3.2(andinmoredetailinDCEandDTEcase
studyreports)isextractedfromthesteamcycle,andalsotakingintoaccounttheheatrecoveryfrom
thecaptureandcompressionprocessesforcondensateheating,thepoweroutput(calculatedusing
gPROMSmodelsasdescribedintheImperialreport),fallstothevaluesshowninTable21below.
AdditionalelectricalpowertorunthecaptureplantsfansandpumpsandtheCO2compressors,
calculatedfromthespecificvaluespertonneofCO2captured foundinthecasestudies,hasalsoto
-
8/4/2019 Co2 Emission Comparison WP3 Final English
13/30
10
besubtractedtogivethereducedcaptureplantnetoutputsandnetefficienciesshowninTable21
below.
Table21Performanceofnewbuildadvancedsupercriticalpowerplant
without/withpostcombustionCO2capture
andprincipalenergyrequirementassumptions
Solvent MEA NH3
WITHOUTCAPTURE
Netplantpoweroutput(MWe) 824.3 824.3
Efficiency(%LHVnet) 43.9 43.9
IPturbineoutletpressure(bara) 9.34 25.53
WITHCAPTURE
IPturbineoutletpressure(bara) 4.17 12.57
Solventreboilersteampressure(bara) 3.67 12.06
Heatforsolventregeneration(MJ/kgCO2) 3.54 3.23
Turbineoutputpowerloss(MWe) 116.0 129.1
Captureandcompressionelectricity
requirements(kWh/tCO2)
150 43.4
Capture/compressionplantpowerconsumption
(MWe)
86.1 25.0
Netplantpoweroutput(MWe) 621.5 670.3
Efficiency(%LHVnet) 33.1 35.7
-
8/4/2019 Co2 Emission Comparison WP3 Final English
14/30
11
1
1
2
2 0
0
HPIP
condenser
LP LP
Heatrecoveryfrom
captureprocess
Solventreboiler
Desuperheater
Floatingpressure
Relocatedeaerator
steamextraction
3
3
4
4
Figure24 Steamturbine/captureplantintegrationwithafloatingintermediatepressureturbine
Themainadditionalassumptionsandestimatingproceduresforpostcombustioncaptureplant
capitalcostsareshowninthesummaryoftechnicalandeconomicperformanceinAppendixB. The
assumedadditionalchargesforthecaptureandcompressionequipmentandthe,relativelyminor,
modificationstothebaseplantarebasedontheNCEPUcasestudyresults. Aconservative
assumptionhasbeenmadethatthesecaptureandcompressionequipmentcosts(expressedas
RMB/kWthermal)willbethesameirrespectiveofthebaseplantsize(acrosstherangecoveredin
WP3),becauseofuncertaintiesregardingtheactualsizeoftheindividualabsorbersandstrippers
thatcouldbeused(currentlyconsideredtobelimitedto300400MWelectricaloutputequivalent).
Iflargercaptureequipmentunitsizesprovetobefeasibleinthefuturethensomeconsequent
economiesofscalewouldbeexpected,althoughtheeffectonoverallplantcostswouldbelimited
sincethecaptureequipmentitselfisestimatedtobeonly2025%ofthetotalpowerplantcapital
costwithCO2capture.
-
8/4/2019 Co2 Emission Comparison WP3 Final English
15/30
12
3. Post combustioncapturefromexistingChinesepowerplants(NCEPU)
InordertoevaluatetheimpactofCO2captureonexistingpulverisedcoalfiredChinesepower
stations,thecostandperformanceof600MWesupercriticaland300MWesubcriticalPCpower
plantswith90%CO2captureandcompressionusingMEAandaqueousammoniawerealso
estimated2.
3.1 Chinese 600MW supercritical unit
Theexampleplantusedasareference600MWsupercriticalunitforthiscasestudywasNo.1unitof
GuiGangpowerplant,locatedatGuangxi,PRChina. Thesteamgeneratorintheseplantsisa
tangentiallycoalfired,supercriticalpressure,controlledcirculation,andradiantreheatwallunit,
designedtogenerateabout1677.5t/hofsteamatnominalconditionsof24.2MPaand566Cwith
reheatsteamheatedto566C.Theunitisconfiguredinaconventionaltypedesignandis
representativeinmanywaysofalargenumberofcoalfiredunitsinusethroughoutbothChinaand
worldwidetoday.
3.2 Chinese 300MW subcritical unit
No.2unitofDaqipowerplantwasusedasareference300MWsubcriticalunit.TheDaqipulverised
coalpowerplantislocatedinNeimengguprovince,PRChina. Theunitisdesignedtogenerateabout
935t/hofsteamatnominalconditionsof16.7MPaand537Cwithreheatsteamheatedto537C.
3.3 Performance without and with CO2 capture
MEAandaqueousammoniatechnologyidenticaltothatusedfornewbuildcapturecaseswas
assumedtoberetrofittedtotheexistingplants. CalculatedperformancewithoutandwithCO2
captureisshowninTable31. Thecaptureefficiencypenaltyforthe600MWsupercriticalplantis
estimatedtobeslightlyhigherthanthatforthe300MWsubcriticalpowerplantwithasimilarCO2
captureprocess.Comparedto300MWsubcriticalunitsthe600MWsupercriticalunitshavehigher
steamtemperaturesandpressuresandhenceasmallersteamflowrateperMWgenerated.When
theCO2captureprocessisretrofittedthedecreaseinsteamflowwillthereforeberelativelylarger
forthesupercriticalplant,resultinginworseoperatingconditionsinthelowpressurecylinderofthe
steamturbine.
2
Amorespecialisedcase,inwhichanexistingsubcriticalpowerplantisrebuilttouseadvancedsupercriticalsteamconditionsandalsoconvertedtooxyfiringcaptureatthesametime,isdescribedintheDoosanBabcock
oxyfiringcasestudyreport.
-
8/4/2019 Co2 Emission Comparison WP3 Final English
16/30
13
Table31EstimatedperformanceforexistingPCplantswith90%CO2capture
600MW
no
capture
600MW
MEA
capture
600MW
ammonia
capture
300MW
no
capture
300MW
MEA
capture
300MW
ammonia
capture
Netoutput,MWe 574.09 398.01 435.61 295.13 202.42 225.23
NetPlantLHV
Efficiency(%)40.28 27.93 30.56 38.15 26.17 29.12
Efficiencypenalty
(%points) 12.35 9.72 11.98 9.03
4. Electricpowergenerationwithpre combustionCO2capture(GG,THCEC)
4.1 Background
Precombustioncapturetechnologyisbasedoncoalgasificationandmaybeimplementedasan
IntegratedGasifierCombinedCycle(IGCC)plantforelectricityproductiononlyorasapoly
generationsystem(forexample,hydrogenelectricitycoproduction,methanolelectricity
coproduction). Inallsuchsystems,thecoalwillfirstreactwithoxygentogeneratesyngaswhich
mainlyconsistsofCOandH2,andthentheCOinthesyngaswillbeconvertedintoCO2andH2ina
shiftreactor.ThemixtureofCO2andH2isrelativelyeasytoseparatebecauseitisathighpressure.
Precombustioncapturetechnologyhasthemeritofimposingalowerenergypenaltyandcapital
costincreasethanpostcombustioncapturewhencaptureisimplemented,butdoesrequirea
gasifierbasedpowerplant,whichcurrently,forpurepowergeneration,ismoreexpensivethana
pulverisedcoalpowerplantinChina.
InrecentyearsChinahasbuiltmanycoalgasificationprojects,mainlyforcoaltooil,coaltochemical
andpolygenerationconversionplants.AccordingtoarecentTHCECstudy,thereareapproaching
100largescalegasiferscurrentlyinoperationinChina. MostofthesearelicensedShellorGE
gasifiers,but4unitsaredomesticallydesignedslurryfeedgasifiers.In2005,Chinabuiltamethanol
electricitypolygenerationsysteminShandongprovince.Thepolygenerationprojectproduces
240,000tonnes/yrmethanoland60MWelectricityandhasbeensupportedbyaMOST863
programfordemonstratingdomesticslurrygasifiers.IGCCandprecombustionCO2capture
technology(basedonIGCC)arenowunderdevelopmentinChina.In2004,ChinaHuanengGroup
(CHNG)announcedtheGreenGenprojectandfoundedtheGreenGenCompanywithsevenother
ofthelargestenergycompaniesinChina.GreenGensgoalistodevelopanddemonstratean
-
8/4/2019 Co2 Emission Comparison WP3 Final English
17/30
14
IGCC+CCSprojectinChinaasoneofthekeytechnologyoptionsforChinaselectricityindustrytouse
totackleclimatechange. Nowtherearemorethan10IGCCpowerplantsproposedinChina,
includingTianjinIGCCdemonstrationpowerplant,whichisownedbytheGreenGenCompanyand
receivedapprovalfromNDRCinMay,2009.AsChinasfirstIGCCplant,itwillstartoperationin2011
andwillbethebasisforafutureIGCC+CCSdemonstrationprojectinChina.
InWorkPackage3twoprecombustionCO2capturecaseshavebeenstudiedindetail,anIGCCwith
CCSsystemusingadryfeedChinesegasifierdesignandachemicalelectricitypolygenerationplant
withCCSusingaslurryfeedChinesegasifierdesign. ParallelfeasibilitystudiesconfirmedthatShell
gasifiertechnologycouldalsobeappliedsatisfactorilytothecoalsbeingused.
Table
2
1
Pre
combustion
Capture
Case
Studies
Case GS1 GS2
Configurations 2400MW
IGCC+CCS
400MW
IGCC+0.3Mt/yr
methanol
Gasification 2TPRI 3Multinozzle
Gasturbine 29FA 19FA
ASU Lowpressure Lowpressure
Chemical
product
Methanol
Shift Twostage OptimisedforMeOH
CO2Separation Selexol Rectisol
CO2Removal
efficiency
90%(overallfor
powerplant)
86.4%(ofCO2at
separationpoint)
4.2 GS1 2400 MW IGCC using TPRI gasifier with CCS (GG)
TheflowdiagramoftheIGCC+CCSplantisshowninFigure41.TheIGCC+CCSsystemconsistsofa
coaldryingandmillingsubsystem,gasificationsubsystem,cleanupsubsystem,watergasshift(WGS),
CO2capturesystem,airseparationunit(ASU), gasturbine(GT), heatrecoverysteamgenerator
(HRSG)andsteamturbine(ST).
-
8/4/2019 Co2 Emission Comparison WP3 Final English
18/30
15
ThedrycoalpowderistransportedintothegasifierbynitrogenfromtheASU. OxygenfromtheASU
andsteamfromtheHRSGwillalsobeinjectedintothegasifierwheretheywillreactwiththecoal
powder. Slagproducedinthegasifierfallsdownintotheslagremovalsystemandcanbeusedas
constructionmaterial.Rawsyngasisquenchedwithdustfreecoldsyngasandentersthesyngas
cooler(SGC). IntheSGC,thesyngasiscooleddownthroughtwoheatexchangerswhichcan
producesaturatedsteamattwopressurelevels(highpressureandmediumpressure).Thesaturated
steamgeneratedintheSGCwillbesenttothesteamcyclesystemofthepowerisland.Thecooled
syngasisthendedustedinthedrysolidremovalsystem(DSR)andsplitintotwosubstreams.One
partisrecycledforthesyngasquench,theotherissenttothewetscrubbingsystemwhichremoves
hydrochloricandhydrofluoricacids.ThereactiontoconvertCOtoCO2happensinthewatergas
shift(WGS)unit.TheoutletstreamcomponentsoftheWGSreactoraremainlyCO2andH2.Thenthe
gasentersthesulphurremovalunitandCO2captureunit.SeparatedCO2iscompressedanddried.
TheremainingH2richgas,dilutedwithN2fromtheASU,entersthegasturbineswithcompressedair
fromtheGTcompressortogenerateelectricpower.
TheO2fromtheindependentASUisfedtothegasifier.SomeN2fromtheASUisusedforcoal
feeding,butthebulkoftheN2isinjectedintotheGTcombustortocontrolNOxemissions.Hotflue
gasfromthegasturbinepassesthroughtheheatrecoverysteamgenerator(HRSG).TheHRSGhas
sectionstoraisesteamatthreepressures(HP/IP/LP)andforreheating.Producedsteamissentto
thesteamturbine.Boththesteamturbineandthegasturbinegenerateelectricpower.
-
8/4/2019 Co2 Emission Comparison WP3 Final English
19/30
16
TPRI GASIFIER
ASU
Wet
Scrubber
SulfurRecovery
(claus-scottunit)
Gas
Turbine
SYNGAS
COOLER
WGS
HT LT
Acid Gas
Removal
CO2
RemovalHRSG
Dry Solid
RemovalCoal
O2
N2
QUENCHGAS
Air
N2 N2
Steam cycle(steam tubien)
Steam Steam
Steam
Water
Sulfur
O2
H2S
Drying and
compression
CO2
CO2
Poweroutput
Stack
Flue gas
WN
Air
Figure41 DiagramofCaseGS1IGCC+CCSSystem
The2400MWIGCCplusCCSplanthasagrossoutputof866.6MW,lowerthantheIGCCbasecase
withoutCO2capture(946.2MW)becausealargequantityofthesteamisusedintheshiftreaction
insteadofgeneratingelectricityinthesteamturbine.Aftersubtractingpowerusewithintheplantto
runtheASU,CO2compressorandotherequipment661.7MWisavailabletosupply,withanet
efficiencyof36.8%. TheTotalInstalledCostfortheIGCC+CCSplantis8589RMB/kW.
4.3 GS2 1400 MW polygeneration system with CCS (THCEC)
Thepolygenerationsystemisaseriessystem,i.e.chemicalandpoweraregeneratedsequentially.
TheflowsheetforcaseGS2isshowninFigure42.Firstwaterandcoalwillbemixedtoproducea
coalwaterslurry.Thecoalwaterslurryisthenpumpedintothegasifier,whereitreactswithoxygen
fromtheASUandinjectedsteam.Theamountofoxygeninjectedintothegasifierwillbecontrolled
carefully,inordertoavoidgeneratingmoltenslaginthefirststageofthegasifierandtoform
moltenslaginthesecondstage.Slagproducedinthegasifierfallsintotheslagremovalsystemand
canbeusedasagoodqualityconstructionmaterial.Rawsyngasproducedinthegasifieris
quenchedwithsteam.Thequenchedsyngasisthendedustedandcleaneduptoremove
hydrochloricandhydrofluoricacidsinthescrubber.Onepartofthecleanedsyngasissenttothe
watergasshift,wherealmostallCOinthesyngaswillreactwithsteamandchangeintoCO2,then
mixedwiththeotherpartofsyngas.Theratioofshiftedsyngaswillbeusedtocontroltheratio
-
8/4/2019 Co2 Emission Comparison WP3 Final English
20/30
17
betweenCOandH2inthemixedsyngastothedesiredvalueformethanolproduction.Before
enteringtheRectisolunit(whichusesmethanolproducedintheplant),thesyngaswillbecooled
downtoabout40Cbyexchangingheatwithwater,becausetheRectisolunitworksatlow
temperatures.IntheRectisolunit,H2SandCO2willbeselectivelyabsorbedbythemethanolsolvent,
andsubsequentlyreleasedbyheatingthesolvent.H2Swillbesenttoasulphurrecoveryunitto
produceelementalsulphur,andCO2willbecompressedfortransportandsequestration(110bar
assumed).ThesyngasleavingtheRectisolunitentersthemethanolreactorcontainingasynthesis
catalyst.Thetailgasisburntwithairinagasturbinetogeneratepower.Thehotfluegasleavingthe
gasturbinethenpassesthroughtheHeatRecoverySteamGenerator(HRSG).TheHRSGiscomposed
ofseveralheatexchangerswhichcanproducesteaminatwopressurereheatsteamcycle(HP/LP).
Thesteamissenttothesteamturbine.Electricityproducedbythesteamturbineandgasturbine
willbesenttothegridnetworkandsuppliedtoelectricityconsumers.Thelowtemperaturefluegas
isreleasedthroughthestack.
TheGS2polygenerationcasehasagrossoutputof525.8MWe+0.32Mt/yearmethanol,andthenet
outputis397.2MWe+0.3Mt/yearmethanol.Theconsumedelectricityisusedforrunningtheplant
facilities,suchastheASU,CO2compressor,pump,fan,etc. andsomeofthemethanolisconsumed
astheRectisolCO2absorptionsolvent.Theoutputofsulphur,abyproductofpolygeneration,is
about13855t/year.TheCO2emissionofthispolygenerationconfigurationis196kg/MWhof
electricity,assumingthatnoneoftheCO2emissionsareassignedtothemethanolproduction. A
consistenttreatmentofthebenefitsofproducingthiscoalderivedmethanolalsowithlower
productionCO2emissionswouldrequireawiderunderstandingofhowthemethanolwasused,
however,andisbeyondthescopeofthisstudy.
-
8/4/2019 Co2 Emission Comparison WP3 Final English
21/30
18
Figure42 BlockflowdiagramofGS2polygenerationplant
5. SummaryofCO2captureperformancefordifferentplanttypes
Figure51summarisesthecalculatedtechnicalandeconomicperformanceofarangeofcoalfired
powerplanttypeswithCO2captureunderChineseconditions. Acoalcostof16RMB/GJanda
discountrateof10%overaplantlifeof25yearsareassumed. Theloadfactoristakenas85%
(67.5%infirst,commissioning,year). Costsdonotincludefinancingcostsandtaxes. Othercase
studyparametersaretabulatedinAppendixAandnumericalvaluesforthecaptureperformanceare
presentedinAppendixB. ThecostsofCO2transporttothestoragesiteandstorageandmonitoring
arenotincluded,butcalculatedcostsforpipelinetransport,fromWHU,arepresentedinAppendixD.
Advancednewbuildcapturetechnologiesthathavestilltobedemonstrated,oxyfiring,post
combustionwithaqueousammoniaandprecombustioncaptureonIGCC,arepredictedtoachieve
similarefficienciesof35.6,35.7and36.8%respectively. CAPEXvaluesfortheseplantsare
approximately9000to10000RMB/kWnet,withanestimated+/ 30%uncertainty. Levelisedcosts
-
8/4/2019 Co2 Emission Comparison WP3 Final English
22/30
19
ofelectricityfortheseoptionsareestimatedtohavearangeofapproximately370410RMB/MWh.
Costsofabatementarecalculatedrelativetothestandardalternativeplantthatwouldbebuilt,an
advancedsupercriticalplant. Sincethecostofabatementisbasedonthedifferencesbetween
relativelylargernumbersthereismorevarianceintheresults,fromanestimated140RMB/tCO2for
oxyfiringto200RMB/tCO2forIGCC+CCS. Thesevaluesare,however,verysensitivetoestimatesfor
captureplantcosts,particularlytheadditionalcapitalcosts,andshouldberegardedaspreliminary.
Aqueousammoniapostcombustioncaptureispredictedalsotoworkwellretrofittedtoexisting
plant. Absoluteefficienciesarelower,duetoacombinationofthelowerefficiencyofthebaseplant
andhigherpenaltiesduetolesseffectiveintegration,butcalculatedcostsofabatement,ataround
200RMB/tCO2,wouldstillbecompetitivewithothercaptureoptionsstudied.
PostcombustioncapturewithanMEAbasedsolvent,alongestablishedtechnologywhichhasbeen
demonstratedatreasonablescaleforindustrialCO2separationapplicationsalthoughnotyetforfull
scalecaptureonpowerplants,ispredictedtohaveagenerallylessfavourableperformance,with
slightlyloweroverallcaptureplantefficiencyandhighercapital,electricityandabatementcosts.
Thisisinlinewithgeneralexperienceandexplainswhythedevelopmentofalternativepost
combustioncapturesolvents,suchasaqueousammoniabutalsoincludingadvancedaminesanda
rangeofothersystems,iscurrentlyreceivingwidespreadattention.
Polygenerationofelectricityandmethanolappearstohavealowefficiencyandhighcapitalcosts
butthisisbecausethemethanolproductionisnottakenintoaccount. Similarly,thecalculatedcost
ofabatementishighforthispolygenerationoptionbutthisdoesnottakeintoaccountthe
advantagesofproducingcoalderivedmethanolalsowithlowerproductionCO2emissions. A
consistenttreatmentofthesebenefitswouldrequireawiderunderstandingofhowthemethanol
wasused,however,andisbeyondthescopeofthisstudy.
Thesensitivityoflevelisedelectricitycoststovariationsfromthebasecaseparametersisshownin
Fig.5.2. Predictedelectricitycostsdecreasebyabout15%iftheassumeddiscountrateisreduced
from10%to5%,andincreasebyslightlymoreifitisincreasedfrom10%to15%,exceptfor
polygenerationwhichchangesbyabout25%becauseofitshighercapitalcosts. Adecreaseor
increaseof30%inassumedCAPEXgivesacorrespondingchangeinelectricitycostofapproximately
12%,exceptforpolygenerationat17%. Adoublingofcoalprice,fromanassumed16RMB/GJto32
RMB/GJincreasespowerplantgenerationcostsbyaround50%withoutcaptureandby40%with
-
8/4/2019 Co2 Emission Comparison WP3 Final English
23/30
20
050
100150200250300350400
Advanced
supercrit
800MW
Oxyfiring Postcom
MEA
Postcom
aqueous
ammonia
Precom
IGCC
Precom
polygen
Existing
600MW
supercrit
Postcom
MEA
Postcom
aqueous
ammonia
Existing
300MW
subcrit
Postcom
MEA
Postcom
aqueous
ammonia
0
200
400
600
800
1000
Advanced
supercrit
800MW
Oxyfiring Postcom
MEA
Postcom
aqueous
ammonia
Precom
IGCC
Precom
polygen
Existing
600MW
supercrit
Postcom
MEA
Postcom
aqueous
ammonia
Existing
300MW
subcrit
Postcom
MEA
Postcom
aqueous
ammonia
0
5000
10000
15000
20000
Advanced
supercrit
800MW
Oxyfiring Postcom
MEA
Postcom
aqueous
ammonia
Precom
IGCC
Precom
polygen
Existing
600MW
supercrit
Postcom
MEA
Postcom
aqueous
ammonia
Existing
300MW
subcrit
Postcom
MEA
Postcom
aqueous
ammonia
0
10
20
30
40
50
Advanced
supercrit
800MW
Oxyfiring Postcom
MEA
Postcom
aqueous
ammonia
Precom
IGCC
Precom
polygen
Existing
600MW
supercrit
Postcom
MEA
Postcom
aqueous
ammonia
Existing
300MW
subcrit
Postcom
MEA
Postcom
aqueous
ammonia
NetEfficiency
(%LHV)
CostofElectricity
(RMB/MWh)
Power plant net efficiencies with and without CO2 capture
Cost of electricity with and without CO2 capture, 85% load factor, 10% discount rate, tax not includedCoal costs: 16 RMB/GJ / 32 RMB/GJ
Capital expenditure
CAPEX = Total Installed Cost + 10% contingency + 7% owners costs, financing costs and taxes not included
Relativetonewbuildadvancedsupercritical pulverisedcoalplant
Relativetoexisting600MW
supercriticalcoalplant
Relativetoexisting300MW
subcriticalcoalplant
CAPEX(RMB/kW)
CostofAbatemen
t
(RMB/tCO2)
Cost of abatement
capture,whilepolygenerationelectricitycostsincreaseby60%. Anincreaseintheassumedselling
priceofmethanolfrom2000RMB/tonneto2500RMB/tonnewouldreducepolygeneration
electricitycostswithcapturebyapproximately10%andbringtheminlinewiththoseforother
captureoptionsforthebasecasevalues(at16RMB/GJcoalcosts).
Figure51SummaryoftechnicalandeconomicperformanceofcoalfiredpowerplantswithCO2
captureunderChineseconditions
-
8/4/2019 Co2 Emission Comparison WP3 Final English
24/30
0
100
200
300
400
500
600
700
800
900
Advanced
supercrit
800MW
Oxyfiring Postcom
MEA
Postcom
aqueous
ammonia
Precom
IGCC
Precom
polygen
Existing
600MW
supercrit
Postcom
MEA
Postcom
aqueous
ammonia
E
3
s
Basevalues 5%discountrate 15%discountrate 30%C AP EX +30%CAPEX Coal32RMB/GJ
Levelisedcostof
electricity(RMB/MWh)
Base values: 10% discount rate, Coal 16 RMB/GJ coal, 85% load factor, Financing costs and taxes not
included, CAPEX = Total Installed Cost + 10% contingency + 7% owners costs, Methanol 2000RMB/t
Figure52 Sensitivityoflevelisedelectricitycoststovariationsfrombasecasepara
-
8/4/2019 Co2 Emission Comparison WP3 Final English
25/30
22
AppendixACasestudybasis
ThecasestudieswerecarriedoutusingNZECstandardassessmentcriteria,whichwereconsultedon
byWP3groups.Themaincriteriaare:
Plantlocation:Tianjin,PRChina
Shenhuabituminouscoalasdesigncoal,Datongcoalascheckcoal
Coalprice16RMB/GJ,LHV(lowheatvalue)basis
63.75%loadfactorforthefirstoperatingyear,and85%loadfactorforotheroperatingyears
10%nominaldiscountrate(withoutconsideringinflation)
25operatingyears
Notconsideringotherthanlocaltaxes.
90%CO2captureandcompressionto110bar
Theambientconditions,sitecharacteristicsandcoaldataarepresentedinthefollowingtables.
TableA1 SiteCharacteristics
Location Tianjin,PRChina
Topography Level
Coaldelivery Unittrain
Ash/SlagDisposal Offsite
WaterSupply Riverwater
Access Trainandroad
TableA2 SiteAmbientConditions
Elevation(m) 5
BarometricPressure(bar) 1.013
Averageambienttemperature() 15
Maximumambienttemperature() 35
Minimumambienttemperature() 0
AmbientRelativelyHumidity(%) 60
-
8/4/2019 Co2 Emission Comparison WP3 Final English
26/30
23
TableA3 CharacteristicsofDesignCoals
Coalspecification UnitDesigncoal
(Shenhuacoal)
Checkcoal
(Datongcoal)
LHV MJ/kg,ar 22.76 26.71
HHV MJ/kg,ar 23.92
Ashcontent
Moisturecontent
Aar(%)
Mar
11
14
9.98
8.84
Ultimateanalysis
Cdaf
Hdaf
Odaf
Ndaf
Sdaf
80.44
4.83
13.25
0.93
0.55
84.43
4.89
8.44
0.91
1.33
Ashcharacteristics
DTC
STC
FTC
1130
1160
1210
-
8/4/2019 Co2 Emission Comparison WP3 Final English
27/30
-
8/4/2019 Co2 Emission Comparison WP3 Final English
28/30
25
AppendixC CO2captureusingmembranegasabsorptiontechnology(ZJU)
Unlikeconventionalchemicalabsorptiontechnology,themembranegasabsorptiontechnology
studiedbyZJUforNZECusesaminesolvents(MEAinthiscase)insidehydrophobichollowfibre
membranecontactorstoabsorbCO2 i.e.itisbasedonacombinationofmembranegasseparation
andchemicalabsorptiontechnology.Thebasicprincipleofmembranegasabsorptiontechnologyis
shownschematicallyinFig.C1.Unlikegasmembraneseparationprocesses(i.e.,withoutusing
solvents)whichdependsonthemembraneselectivity,thehollowfibresadoptedinthemembrane
contactor,whichhavemanymicroporesintheirwalls(asshowninFig.C2Fig.C2)aregenerallynot
selective.TheselectivitytoCO2isimplementedbythealkalinesolutioninsidethetubes,which
meansthatthedrivingforceforCO2absorptionisbasedontheCO2concentrationgradientbetween
thelumensideandshellsideofmembrane.
Fig.C1.Principleofmembranegasabsorption. Fig.C2.Microporesinthemembranewall.
AtypicalmembranecontactorisshowninFig.C3. Inthehollowfibremembranecontactor,
hydrophobicmicroporousmembranesareusedtoformapermeablebarrierbetweentheliquid
phaseandgasphase,whichpermitsmasstransferbetweenthetwophaseswithoutdispersingone
phaseintoanother.Ingeneral,thegasandliquidphasesalwaysflowinparallel(either
countercurrentlyorconcurrently)toeachotherontheoppositesideofthefibres,andthegas
preferentiallyfillsthehydrophobicmembraneporesandmeetstheliquidattheoppositesideof
membrane. Inthisstudy,polypropylene(PP)membranecontactorswereselectedtoactasthe
absorberinthemembranegasabsorptiontechnologybecauseoftheirlowerpriceandcommercial
availability.Theinnerdiameter(I.D.)ofthePPfibreisabout30 m,theouterdiameter(O.D.)of
fibreisabout40 mandtheporosityofthefibreisabout50%.
InordertopreventmembranewettingproblemsitispreferabletodecreasetheMEAconcentration.
ButlowerMEAconcentrationswillleadtoanincreaseintheflowrateofthesolventand
-
8/4/2019 Co2 Emission Comparison WP3 Final English
29/30
26
consequentlyanincreaseinregenerationenergyconsumption.So20%w/wMEAsolutionwas
selectedinthiscase,asacompromisebetweenrelativelyhighersurfacetensionandrelativelylower
solventflowrate. Thecalculatedthermalenergyconsumptionforsolventregenerationunderthese
conditionswas3.98GJ/tCO2. Thiswassignificantlyhigherthanforthe30%w/wMEAsolutionused
inaconventionalabsorber,whichwasestimatedtorequire3.54GJ/tCO2(DCE),andestimated
captureplantcapitalcostswerenotsignificantlydifferent. Soamembranegasabsorptionoption
wasnotincludedindetailedtechnoeconomiccomparisons.
Iffurtherdevelopmentworkwasabletoleadtoincreasedsolventloadingand/orsignificantly
reducedcapitalcoststhentheoperationaladvantagesofmembranecontactorscouldmakethemof
interest. Sincethegasandliquidphasesflowontheoppositesides(i.e.,shellandlumensides)of
thehollowfibrestheycanbecontrolledindependently.Thisisespeciallyeffectiveinavoiding
problemssuchasflooding,foaming,channellingandentrainment,whichcanbeencounteredin
packedortraytowers.
Fig.33 Typicalstructureofhollowfibermembranecontactor
-
8/4/2019 Co2 Emission Comparison WP3 Final English
30/30
27
AppendixD LevelisedcostoftransportingCO2asafunctionofmassflowrate
ThefollowingcostsfordensephasesupercriticalCO2transportbypipelineinChinaaretakenfrom
thereportfromWuhanUniversity(WHU). Theyarebasedoncontinuousutilisationofthepipeline
(i.e.365days/year). Forlowerutilisationratesthecostscanbeadjustedreasonablyaccuratelybydividingbytheutilisationfactor.
Cost(CNY/tCO2)vsTransportDistanceL (km)CO2Mass
Flowrate
(tonnes/day) L=50 L=100 L=200 L=300 L=500
2000 16.1535.34 77.35 128.14 225.02
4000 10.2922.52 49.29 81.19 143.42
6000 7.91 17.30 37.87 62.28 110.40
8000 6.5614.35 31.41 51.63 91.78
10000 5.6712.42 27.17 44.67 79.58
12000 5.0411.03 24.14 39.70 70.85
14000 4.569.98 21.83 35.93 64.25
16000 4.189.15 20.02 32.97 59.04
18000 3.87 8.47 18.54 30.57 54.82
20000 3.627.91 17.32 28.57 51.30