emergency load management with demand...
TRANSCRIPT
1
Emergency Load management with Demand Response(DR)
Scheduling and Load Management
DR is additional emergency tool.
Long term contracts
Short term
Exchange
DR
Normal power requirement
Short term through trader
Daily deficits are met through exchange.
DR is voluntary load curtailments by large I & C consumers during peak hours when requested by Utility in order to create a curtail able capacity
during high demand months.
Utility is prevented from sourcing high cost short term power which consequently impacts customers through higher tariffs
NOC for ADR
ALERTCREATES DR
EVENTSE
ND
S D
R
EVEN
T TO
C
ON
TRO
LLER
NON CRITICAL LOAD SHED
INDUSTRY/ COMMERCIAL ESTABLISHEMENT
NORMAL
SCENARIOGRID
STRESS
Demand Response Server
Ev
en
t
No
tific
atio
n
NON CRITICAL LOAD SHED
Utility
Operator
ADR - EVENT
Salient Features of the Project
4
Project Components include : Automated Demand Response
infrastructure including DR server and sitecontrollers
Smart Meters RF Mesh based Communication MDMS and its integration with other OT &
IT systems like OMS, SAP, ADR
Collaborative partnership withselected vendors
First Utility initiated AMI based ADR program in the country
Project approved by Regulator
Project Objectives: To manage peak demand To manage Grid Stress situations
Project being undertaken to demonstrate: Technological capability Understand customer behavior Case study for regulator to work on
differential tariffs and financial incentives. Processes required for scaling up
5 5Author:
Salient Features
• RF Mesh network spread over an area of approx. 250 Sq km.
• 4 hour Advance intimation to the consumers in case of a scheduled DR event with opt out option through return SMS/Email.
• Near Real time 15 min granular data transmission of 15 min load interval data to TPDDL data acquisition system
• Real time intimation to consumers in case of violation of set thresholds with regards to Low PF and Load
• Advanced customer portal for providing granular 15 min interval data to customers for monitoring consumption pattern on daily/hourly basis
• Integration of Meter Data Management System(MDMS) and DRAS(Demand Response Automation Server), enabling elimination of role of aggregator and use of shadow meters for the purpose of calculation of baselines and actual shed calculation.
• Integration of MDMS system with the existing SAP system for creation of automatic service order and billing system.
Customer Coverage
6
Audit conducted for 550 Nos. of consumers & subsequently 162consumers have been enrolled for the project
Only Industrial & Commercial consumers have been targeted underthe project ; Potential Identified :12 MW
Consumers’ area of coverage: more than 250 Sq km
Industrial Category includes: Flour Mills, Plastic & Footwear, Printing ,Food & Cold Storage industries etc.
Commercial Establishments include: Commercial complexes, hospitals,Cinema halls, Offices etc.
Automated Demand Response
Step 1• Identification of Critical/ Non critical load through Site audit
Step 2• Installation of Controller and Control Wiring
Step 3
• DR Event notification to the consumer in case of grid stress
Step 4• Consumer Concurrence for Participation in DR
Step 5• Shedding of Identified Non Critical Loads during the DR slot
7
SHED POTENTIAL ANALYSIS
8 8Author:
Industry Cold Storage Flour & Dal MillFootwear & Plastic Printing steel Hospital Others
No of Consumers 8 39 39 7 10 3 61
Shed Potential (KW) 1364 3292 1718 423 629 375 3300
Sanctioned Load (KW) 10248 16891 6660 1528 2221 1970 24000
Percentage 13% 19% 26% 28% 28% 19% 14%
Industry Wise DR Shed Details
9
DateIndustrial
(kVAh)Commercial
(kVAh)Total
(kVAh) Industrial % Commercial %
8th July’2015 3235.92 534.73 3770.65 85 15
11th July’20153304.74 266.59 3571.33 92 8
17th July’2015 2366.54 588.74 2955.28 80 20
22nd Aug’2015 3369.82 826.8 4196.62 80 20
26th Aug’2015 6264.55 771.27 7035.82 90 10
29th Aug’20155198.72 1292.76 6491.48 80 20
Total Savings(FY 2015-16)- 0.063 MUs
Event Results– DR Event 26th August 2015
Total Non Critical Load Connected: 11.5 MW,
17 ADR Events conducted from May –
Oct 2015
Max Shed potential
achieved: 7.2 MVA during peak period
in August’2015
11
S. No Description Unit Amount
1 Per Unit cost of power through spot gas Rs 9
2 Shed Achieved during DR event MVA 7 .2
3 Units Saved due to DR Event KVAh 7159
Event Start
Event End
System Load Relief
7.2 MVA
AMI based ADR Project: Challenges
Design of ADR architecture with Smart meter
• Integration with existing IT-OT systems
• IT security
Technology selection
• Willingness of potential technology partners to invest in this complex project in order
• To keep the project cost within approved budget
Consumer enrollment
• Consumer engagement after conducting multiple interactions at different hierarchical
• level for convincing consumer to participate in DR program
• No direct incentive for participating consumers
• Technical feasibility for enrollment … manual starters / MCB operated loads,
• Continuous automated process
Way Forward
13
Delhi Electricity Regulatory Commission (DERC) vide its letter dated 9th February, 2016 has granted in-principle approval for the implementation of the ADR Scheme for two years under following conditions :
Project includes direct load control of equipment classified as non-critical
The incentive would be in the form of rebate of: 20% of the normal tariff against units saved during the Demand Response event (DR
event), if the notification of event was intimated 2 hrs. or more in advance. 40% of the normal tariff against units saved during the DR event, if the notification of
DR event was intimated between 30 mins. to 2 hrs.
The amount of incentive would be calculated based on the above said units and the basic unit rate for the category in which the consumer is billed
Project would be scaled up to 250 nos in this year from 162 at present
14
Thank you