utility ceo forum on dsmdsm-india.org/wp-content/uploads/2016/06/theme-presentation.pdf · design...
TRANSCRIPT
Utility CEO Forum on DSM
Electric utility load research andDSM program design
25 September 2013
1 Need for best practices in load research and DSM program design 1
2 Introduction to load research 3
PageSection
Table of Contents
3 Case study: Load research in Himachal Pradesh 9
4 Introduction to the DSM programme designs 20
Section 1Need for best practices in load researchand DSM program design
25 September 20131
Utility CEO Forum on DSM •
Need for best practices in load research and design of DSM programs
Section 1 – Need for best practices in load research and DSM program design
Critical milestones in DSM planning process by distribution licensees
Load research
Resource potentialassessment
Cost effectivenessassessment
Design of DSMprograms
Current status of DSM planning by Indianutilities
Need of the hour
25 September 20132
Utility CEO Forum on DSM •
• In spite of the existence of DSM regulationsin many states, a majority of the distributionlicensees are yet to complete the DSMplanning process
• Many State-owned licensees are unaware ofthe commonly adopted methods for loadresearch and successful programme designs
• Case studies for illustration of load research• Examples of successful program designs in
India and other parts of the world
• Some states that have successfullycompleted load research studies – TamilNadu, Gujarat and Himachal Pradesh
Section 2Introduction to load research
25 September 20133
Utility CEO Forum on DSM •
Load research objectives and outcomes
Section 2 – Introduction to load research
Objectives
• To identify strategic demand side management (DSM) measures
Direct Outcomes Derived Outcomes
Load profile/curve/shape
of individual consumer
facilities in different
consumer categories
Stock of the installed
Overall load profile of different consumer categories and their
contribution to the systemic load curve
Strategic load management interventions to flatten the load curve
Market size of electrical appliances/equipment in different consumer
categories
• To identify strategic demand side management (DSM) measures
• To quantify the resource potential for those measures
25 September 2013
Stock of the installed
electrical equipment, their
capacity, make, technology
and time of usage
categories
Penetration of energy efficient technologies among electrical
appliances/equipment in different consumer categories
Load reduction measures targeting specific end use applications for energy
efficiency enhancements
Technical potential of energy and demand savings resulting from the
acquisition of identified demand side resources
4Utility CEO Forum on DSM •
Load research activities
Section 2 – Introduction to load research
Load research
Hourly loadrecording of
individual facilities
AMR datarecording
Load profile/shapeof individual
consumer facilitiesPhysicalmonitoring ofhourly energyconsumption
Questionnairebased interviews Stock of the
installed electrical
Lo
ad
ma
na
gem
ent
stra
teg
ies
red
uct
ion
stra
teg
ies
an
dre
sou
rce
po
ten
tia
les
tim
ate
s
25 September 2013
Load and marketsurveys
installed electricalequipment, theircapacity, make,technology andtime of usage
Questionnairebased e-surveys
5Utility CEO Forum on DSM •
Lo
ad
red
uct
ion
stra
teg
ies
an
dre
sou
rce
po
ten
tia
les
tim
ate
s
Section 3Case study: Load research in HimachalPradesh
25 September 20139
Utility CEO Forum on DSM •
Evolution of DSM in Himachal Pradesh
2009September 2011
HPERC published the DSM
Section 3 – Case study: Load research in Himachal Pradesh
2009
HPERC appointed PwC forpreparation of EE & DSM plan
Summer (May 2010 toJune2010) and the winter
(December 2010 toFebruary2011)
PwC conducted load researchacross Himachal Pradesh
HPERC published the DSMplan and also notified DSM
regulations
25 September 2013
Scope of Load research activities in Himachal Pradesh
• Load surveys (or walk through audit),
• Hourly recording of electricity meters and
• AMR data analysis
10Utility CEO Forum on DSM •
First level of stratification
Sampling process for load research activitiesStratification framework and sample distribution
Section 3 – Case study: Load research in Himachal Pradesh
Domestic stratification and sampledistribution framework
• Domestic,
• Commercial,
• Non-domestic non-commercial (NDNC),
• Water and irrigation powersupply (WIPS),
• Low tension (LT) industrial,High tension (HT) industry,Agriculture,
Domesticconsumerpopulation
<50 kWh permonth
Zonal distribution
50-150 kWh permonth
Zonal distribution
>150 kWh permonth
Zonal distribution
distribution framework
25 September 2013
Agriculture,
• Street lighting, and
• Bulk supply
11Utility CEO Forum on DSM •
Circle-wisedistribution
Sub-division leveldistribution
Circle-wisedistribution
Sub-division leveldistribution
Circle-wisedistribution
Sub-division leveldistribution
Stratification framework and sample distributionCommercial Consumers
Section 3 – Case study: Load research in Himachal Pradesh
Commercialconsumer populationconsumer population
Hotels andrestaurants
0-20kW
20-100kW
Shops
0-20kW
20-100kW
Privatehospitals
0-20kW
20-100kW
Banks
0-20kW
20-100kW
Coachinginstitutes
0-20kW
20-100kW
Private offices
0-20kW
20-100kW
Railways
0-20kW
20-100kW
25 September 201312
Utility CEO Forum on DSM •
100-500kW
>500kW
100-500kW
>500kW
100-500kW
>500kW
100-500kW
>500kW
100-500kW
>500kW
100-500kW
>500kW
100-500kW
>500kW
Findings of the load research study in Himachal Pradesh
Domestic load curve/shape/profile and Contribution of specific end-use applications
Section 3 – Case study: Load research in Himachal Pradesh
25 September 2013
0000-0500 0500-0900 0900-1800 1800-0000
Summer Winter Summer Winter Summer Winter Summer Winter
Conditioning 45.82 58.45 13.81 17.04 49.99 54.06 41.17 40.51
Cooking 0.00 0.00 5.92 4.34 11.99 10.97 7.98 5.55
Illumination 8.58 2.45 6.58 5.82 4.71 5.05 30.65 25.34
Water heating 4.68 2.32 26.30 38.23 0.00 2.32 2.16 18.25
Laundry 2.22 1.55 20.55 12.45 16.08 16.85 0.54 0.25
Refrigerator 38.70 35.23 26.84 22.12 17.22 10.75 17.50 10.12
15Utility CEO Forum on DSM •
Water and Irrigation Power SupplyLoad curve/shape/profile
Section 3 – Case study: Load research in Himachal Pradesh
25 September 201316
Utility CEO Forum on DSM •
HT Industry
Load curve/shape/profile
Section 3 – Case study: Load research in Himachal Pradesh
25 September 201317
Utility CEO Forum on DSM •
Consolidated load curve
Section 3 – Case study: Load research in Himachal Pradesh
800
900
1000
0
100
200
300
400
500
600
700
800
1:0
0A
M
2:0
0A
M
3:0
0A
M
4:0
0A
M
5:0
0A
M
6:0
0A
M
7:0
0A
M
8:0
0A
M
9:0
0A
M
10:0
0A
M
11:0
0A
M
12:0
0P
M
1:0
0P
M
2:0
0P
M
3:0
0P
M
4:0
0P
M
5:0
0P
M
6:0
0P
M
7:0
0P
M
8:0
0P
M
9:0
0P
M
10:0
0P
M
11:0
0P
M
12:0
0A
M
25 September 201313
Utility CEO Forum on DSM •
1:0
0A
M
2:0
0A
M
3:0
0A
M
4:0
0A
M
5:0
0A
M
6:0
0A
M
7:0
0A
M
8:0
0A
M
9:0
0A
M
10:0
0A
M
11:0
0A
M
12:0
0P
M
1:0
0P
M
2:0
0P
M
3:0
0P
M
4:0
0P
M
5:0
0P
M
6:0
0P
M
7:0
0P
M
8:0
0P
M
9:0
0P
M
10:0
0P
M
11:0
0P
M
12:0
0A
M
System Overall Domestic Commercial
Irrigation NDNC Street Lighting SME
HT Bulk Temporary
Since the overall load curve is relatively flat, strategic conservation and partial load shifting (from day to night) arethe main load management strategies proposed to achieve the DSM objectives
Load curves of individual consumer categories
Section 3 – Case study: Load research in Himachal Pradesh
25 September 201314
Utility CEO Forum on DSM •
7:00 AM 12:00 PM 9:00 PM
Peak contribution of different consumer categories
Section 3 – Case study: Load research in Himachal Pradesh
Summer Winter Summer Winter Summer Winter
Domestic 24.45% 28.08% 21.72% 19.37% 40.78% 43.33%
Commercial 2.75% 0.74% 9.61% 7.07% 9.40% 5.87%
WIPS 10.83% 6.73% 14.18% 8.85% 7.49% 2.23%
NDNC 0.38% 0.70% 4.27% 2.56% 0.69% 0.80%
Street lighting 0.01% 0.46% 0.00% 0.00% 1.04% 0.73%
SME 0.84% 1.34% 7.66% 6.39% 0.56% 0.75%
HT 57.27% 58.05% 55.38% 53.31% 40.37% 43.67%
25 September 2013
HT 57.27% 58.05% 55.38% 53.31% 40.37% 43.67%
Bulk 6.21% 3.34% 5.18% 1.99% 6.08% 2.62%
Temporary 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Agriculture 1.54% 0.56% 1.13% 0.47% 0.00% 0.00%
18Utility CEO Forum on DSM •
Load management interventions proposed
• Power factor improvement from 0.9 to 0.95Technical potential of load reduction measures
DSM strategies and interventions identified from a load research study
Section 3 – Case study: Load research in Himachal Pradesh
• Power factor improvement from 0.9 to 0.95
• Partial shifting of WIPS load from day time to nighttime
The annual energy savings potential estimated frompower factor improvement was 12 Million units whichcould translate to INR 3.8 crores of annual benefit tothe HPSEBL
Oldtechnology
Proposedtechnology
Sector Technicalpotential (MU)
Standardefficiency
motor
EnergyEfficient Motor
Industry HT 111.45
Standardefficiency
pumps
EnergyEfficientPumpingsystem
Industry HT 7.35
Reciprocatingcompressor
ScrewCompressor
Industry HT 6.69
SS blades incooling tower
FRP forcooling tower
Industry HT 2.09
Standard Energy Industry HT 108.29Impact of shifting 10 MW of peak WIPSload
25 September 2013
Standardefficiency
fans/blowers
EnergyEfficient
fans/blower
Industry HT 108.29
Incandescentbulb
CFL Industry HT 0.16
Incandescentbulb
CFL Domestic 1.11
Standardefficiency
pumps
EnergyEfficientPumpingsystem
Irrigation 72.27
19Utility CEO Forum on DSM •
load
• Annual Energy savings - 2161031.57 kWh
• Monetary benefits accrued by the HPSEBL - INR 75lakhs
Section 4Introduction to the DSM programmedesigns
25 September 201320
Utility CEO Forum on DSM •
Objectives
DSM Program Design – Objectives and key design components
Section 4 – Introduction to the DSM programme designs
Marketing Monitoring
• Replicate the impact of individualDSM measures on a larger(megawatt) scale
• Facilitate customer participationthrough incentives andinformation campaigns DSM Program
Designcomponents
MarketingandInformationcampaigns
Monitoringandverificationprotocols
Targetmarket andproductspecification
Incentives(both fiscal andnon-fiscal)
25 September 201321
Utility CEO Forum on DSM •
specification
Program goalsEnergy and demandsavings
Rebate programs
Section 4 – Introduction to the DSM programme designs
Retailer / Wholesaler Utility
Proof-of-sale
Sale of energyefficientappliance atdiscounted price
Proof-of-sale
Reimbursementof rebate
RebateModel 1
Wholesalers and distribution
25 September 2013
Rebate programmes offercapital rebates to offset thedifferential cost involved inpurchase of high efficiencyelectric appliances.
22Utility CEO Forum on DSM •
Customer
centres, can be reimbursed,typically requiring a proof-of-sale to a retail customer. In thiscase the customer can claimthe rebate at the time ofpurchase.
Model 2
Rebate programs (cont...)
Section 4 – Introduction to the DSM programme designs
Retailer / WholesalerMarketing platforms Model 2
Rebate programs can alsochannel rebate directly to thepurchaser, who submits aproof-of-purchase receipt. Inthis case, the customer mayself install the unit, providedthat they supply the paid salesinvoice along with the rebateapplication form.
Sale of energyefficientappliance
Marketing platforms
Utility can make customersaware of the product through
• Bill inserts,
• Direct mail pieces,
• Utility website,
• Appliance contractors,builders, and retailers
25 September 201323
Utility CEO Forum on DSM •
CustomerUtility
Proof-of-purchase
Reimbursementof rebate
Standard product program features
International case study: Eskom’s Standard Product Program in SouthAfrica
Section 4 – Introduction to the DSM programme designs
Total value of• Qualification criteria - demand reduction greater than 1kW and the
energy savings greater than 2MWh/annum
• Rebate cap - maximum of R500 000 per project site
• Approved Products /technologies - heat pumps, solar geyser, energysaving shower heads, CFL, and LED lighting systems
• Who is eligible to participate? - Customer (himself), Energy servicescompanies, or other project developers
Total value ofDSM projects
funded throughEskom initiatives
-R 5.6 billion
25 September 2013
companies, or other project developers
• Degree of incentive - Customers can receive up to 85% of capital costs asrebate under this program
24Utility CEO Forum on DSM •
ContractedDemand
2375 MWDemand reduction
verified1814 MW
Step 1: The customersubmits a project proposal
Eskom’s Standard product programme cycle
Section 4 – Introduction to the DSM programme designs
Customer / ESCO Utilitysubmits a project proposalwith all the requireddocumentation to the Eskomfor approval. On receipt of thesubmission, the Eskomcommunicates (in writing),the details of themeasurement and verification(M&V) process that will applyas well as the projectobligations (e.g. de-commissioning, disposalrequirements for existing
Customer / ESCO Utility
Proposal
Writtencommunication ofM&V, and other
obligations
Sign off on Scope,sustainability
commitment and
25 September 2013
requirements for existingtechnologies, sustainabilitycommitment, pledge, etc).
25Utility CEO Forum on DSM •
Step 2: The customer signs a predefined scope and sustainability commitment. This includes an indemnityclause, to prevent the customer from double claiming energy savings through other initiatives and encouragessustainability of the solution (e.g. necessary maintenance and continued, optimal operation) for a period of threeyears.
commitment andindemnity clause
Step 3: The customer selffinances the proposed
Eskom’s Standard product programme cycle (cont...)
Section 4 – Introduction to the DSM programme designs
Customer / ESCO UtilityNotification ofcompletion of
finances the proposedintervention. Less energyefficient technologies isreplaced with energy efficientstandard product solutions.
Step 4: The customerdecommissions andresponsibly disposes the lessenergy efficient equipmentWhere appropriate, thecustomer submits proof of thedisposal to the Eskom.
Customer / ESCO Utilitycompletion of
installation
Verifies and IssuesCompletioncertificate
Claims rebate withthe support of
completioncertificate
25 September 201326
Utility CEO Forum on DSM •
Step 5: The customer notifies the Eskom about the completion of installation. Eskom, at its own expense,performs a technical and disposal audit which may take the form of a phone call, a site visit or full measurementand verification (depending on the agreed project specifics in step 1). Eskom confirms and signs off on theimplementation based on which a project completion certificate is issued.
Step 6: The customer submits all the actual cost invoices reflecting final rebate (as agreed between Eskom andCustomer) to process the rebate payments by the Eskom.
• Direct install programmesuse utility or contractors to
International case study on the direct-install programme - SanDiego Gas and Electric Company’s (SDG&E) Direct Install program
Direct Install Program
Section 4 – Introduction to the DSM programme designs
use utility or contractors todirectly install low-cost, quickpay-back energy efficiencymeasures (reliable and highlycost-effective energy savings) incustomer facilities
• These programmes will deployteams of technicians in factoriesand facilities to identify andinstall low-cost, low riskmeasures
Diego Gas and Electric Company’s (SDG&E) Direct Install program
Key features
• Provides a number of free energy- and money-saving services forqualifying small- and medium-sized businesses.
• Qualifying businesses - commercial rate customers who do not havemonthly electrical demand over 100kW for three consecutive months
After the initial screening process, one of the approved contractors
25 September 2013
• This type programme is not yettested in India and is mostlyprevalent in developed countries
• After the initial screening process, one of the approved contractorsevaluates the customer's facility, identifies energy-saving opportunitiesand subsequently installs energy-efficient upgrades and retrofits at nocost to the customer.
• Free upgrades include fluorescent lighting, occupancy sensors andvending misers.
27Utility CEO Forum on DSM •
Bid programmes solicit energy services companies tosubmit proposals and improve energy efficiency levels
International case study on the direct-installprogramme
Bid Program
Section 4 – Introduction to the DSM programme designs
submit proposals and improve energy efficiency levelswithin a targeted group of customers. These set broadgoals such as location and measure and facility types,relying on bidders to propose projects. Such proposalsinclude a thorough cost benefit analysis.
programme
• Eskom has registered Energy Services Companies(ESCO) who identify energy efficiency opportunities,scope and execute projects in specific target markets
• ESCOs utilise their in house knowledge of efficienttechnologies and specialise in determining the bestand most suitable way of obtaining electricity savingsat a business.
Examples of projects similar to Bid programs inIndia
25 September 2013
• Qualifying criteria - electricity savings more than200kW which Eskom reviews on its technical andfinancial merits
• Four-way partnership via legal contracts betweenEskom, the customer, the ESCO, and anindependent, measurement and verification expert
28Utility CEO Forum on DSM •
• Agriculture Demand Side Management pilot projectin Solapur, Maharashtra
• Agriculture Demand Side Management project inHubli Electricity Supply Company in Karnataka
Standard Offer Program
Feed-in-tariffs for energy efficient technologies
Section 4 – Introduction to the DSM programme designs
• Standard offer programme is a mechanism to acquire demand-side resources (energy and demandsavings) based on a predetermined rate (e.g. Rs/kWh). Standard offer rates can be determined by the long runmarginal cost of supply necessary to attract commercial bids.
• ESCOs, equipment suppliers or other organisations that can deliver energy and demand savings at the agreedrate are eligible to submit projects.
• They are paid once the projects have been implemented and savings certified by an authorised monitoring andverification organisation.
25 September 2013
• Standard offer rates can vary by measure type, region, size of the project, or any other parameter that helpsimprove the programme’s potential to succeed
• The standard offer design is adopted by utilities worldwide but is yet to be tested in India
29Utility CEO Forum on DSM •
Eskom approved technologies and solutions
International case study: Eskom’s Standard Offer Program in South Africa
Section 4 – Introduction to the DSM programme designs
• Small-scale renewable energy, off-grid solutions suchas photo voltaic, biomass waste, wind energy,geothermal, solar, thermal gradient and groundsource heat; municipal solid waste
• Energy efficient lighting systems (CFL, T8, and T5)
• Building management systems (HVAC controlsystems, heat pumps, variable speed drives, sensors,and thermostats)
• Hot water systems (heat pumps and solar waterheaters)
Target technologies c/kWh
Energy efficient lighting
systems42
LED lighting technologies 55
Building management systems 42
Hot water systems 42
Process optimisation 42
Industrial and commercial solar
25 September 2013
• Process optimisation (efficient motors, fans, variablefrequency drives and others)
• LED down lighters
Industrial and commercial solar
water systems70
Renewable energy 120
30Utility CEO Forum on DSM •
Step 1: The customer submits thestandard offer application bycompletely filling the project and
Eskom’s Standard offer programme cycle
Section 4 – Introduction to the DSM programme designs
Customer UtilityApplicationsubmissioncompletely filling the project and
technical information templates,published by Eskom. The customeralso proposes a preliminary M&Vplan along with the standard offerapplication.
Where a customer opts to partnerwith an ESCO and requires theESCO to act on his behalf, thecustomer signs a letter of intent toconfirm this agreement for theentire contract period, includingthe three year sustainabilityportion. The standard offer project
Customer Utilitysubmission
Letter of Intent Applicationsubmission
25 September 2013
portion. The standard offer projectcontract is thus placed betweenEskom and the ESCO in suchcases.
31Utility CEO Forum on DSM •
ESCO
submission
Step 2: Evaluation of the standard offerapplication by the Eskom. If the evaluationcommittee approves the application, Eskom
Eskom’s Standard offer programme cycle (cont...)
Section 4 – Introduction to the DSM programme designs
Customer UtilityLetter of approvalfrom evaluation
committee approves the application, Eskomprovides the ESCO/ customer with aapproval letter.
Step 3: The M&V process begins. TheEskom appointed independent M&V teamprovides the ESCO/customer with thedetailed metering specifications to purchaseand install the metering equipment for thedevelopment of the project’s baseline.
Step 4: Upon receipt of meteringspecifications, the ESCO/customer purchasesand installs the necessary M&V equipment.Purchasing, installation and maintenance ofthe M&V equipment is managed by the
committee
Request to set upbaseline
Joint sign off onbaseline
25 September 2013
the M&V equipment is managed by theproject ESCO/ customer.
Step 5: The ESCO/customer and the M&Vteam jointly sign off the baseline establishedusing the M&V meters installed as per thespecifications.
32Utility CEO Forum on DSM •
M&V equipmentspecifications
M&V team
Step 6: The ESCO/customer andthe Eskom sign the final standard
Eskom’s Standard offer programme cycle (cont...)
Section 4 – Introduction to the DSM programme designs
Signing standardthe Eskom sign the final standardoffer contract after negotiating onsome key terms and conditions.
Step 7: Eskom gives theESCO/customer permission to startthe installation process. This marksthe beginning of projectimplementation.
Step 8: The previously installed,inefficient technologies are disposedof safely. Where appropriate acrushing or disposal certificate issubmitted to Eskom in order to
Customer / ESCO Utility
Signing standardoffer contract
Permission to startinstallation
Completesinstallation and
Submits proof ofdisposal
25 September 2013
submitted to Eskom in order tocomplete the implementationprocess.
Step 9: Eskom confirms and signsoff on the implementation based onwhich a project completioncertificate is issued.
33Utility CEO Forum on DSM •
disposal
Issues projectcompletioncertificate
Step 10: the project impactassessment is done by the appointed
Eskom’s Standard offer programme cycle (cont...)
Section 4 – Introduction to the DSM programme designs
Customer First progresspaymentassessment is done by the appointed
M&V team to confirm the electricitysavings that resulted from theefficiency upgrade. On conclusionthe M&V team's assessment ofsavings are communicated andagreed by the parties.
Step 11: The ESCO/customersubmits the application for the firstprogress installment (verifiedsavings at the published rate).
Over the next three years, annualpayment requests are submitted
Project impactassessment
Submits verifiedsavings report
25 September 2013
payment requests are submittedtogether with M&V reports.
34Utility CEO Forum on DSM •
assessment
M&V team
Section 5Annexure
25 September 201335
Utility CEO Forum on DSM •
Sample Load managementinterventions:
Load reduction measures
Load management strategies and Load reduction measures (Illustrative)
Section 5 – Annexure
Load ManagementStrategies
Peak clipping
Valley Filling
Load Shifting
interventions:
• Time of day (TOD) tariffs,
• Load factor/power factorimprovement incentives and
• Demand response initiatives
• Utility sponsored incentives toadopt energy-efficienttechnologies, equipment,appliances across various classesof end-users in the economy
• Utility sponsored incentives toinstall rooftop solar PV and solarthermal solutions that can offsetthe electricity demand on thepower grid
Strategies
25 September 2013
Load Shifting
Strategic
Conservation
power grid
35Utility CEO Forum on DSM •
• Demand side resources constitute energy and demand savings resulting from the load reductionmeasures available with the utilities
Resource potential from load reduction opportunities
Section 5 – Annexure
measures available with the utilities
• Technical potential is a theoretical construct of the technical upper bound of the energy anddemand savings resulting with complete market penetration of energy-efficient appliances,deemed technically feasible from an engineering perspective.
• Technical potential does not consider cost or acceptability factors of the customer.
25 September 201335
Utility CEO Forum on DSM •
Sampling methodology for load research activities
Stratified random sampling theory
The primary underlying assumption is that the targetpopulation is homogenous, without significant
The final sample size for conducting load surveysdepends on the number of stratified homogenous
Section 5 – Annexure
population is homogenous, without significantvariations. Therefore, the target population needs tobe stratified and filtered in order to identify reasonablyhomogeneous groups of population.
depends on the number of stratified homogenousgroups within the target population.
First level of stratification
Domestic (residential) Commercial (services) Low tension Industry
(manufacturing)
High tension Industry
(manufacturing)
Agriculture pumping
Further levels of stratification
Based on urban, rural
and connected load
Based on connected
load and function of
buildings
Based on connected
load and function of
facilities
Based on connected
load and function of
facilities
Based on connected
load and technology of
pump sets
< 2 kW < 10 kW < 10 kW 500-1000 kW <5 HP
2-5 kW 10-100 kW 10-100 kW >1000 kW 5-10 HP
25 September 2013
2-5 kW 10-100 kW 10-100 kW >1000 kW 5-10 HP
>5 kW >100 kW 100-500 kW Steel, cement, chemical,
textile, pharmaceutical,
plastic, paper, glass,
>10 HP
Hotels and restaurants,
shops, private hospitals,
banks, coaching
institutes, private
offices etc.
Food processing,
spinning mills, electrical
goods, brewery, rubber
engineering, polymer,
stone crushers, liquor,
poultry farms, and IT
parks
Monobloc pump sets,
submersible pump sets
35Utility CEO Forum on DSM •
NDNC category LT Industry (<100 kW) and
HT (>100kW) Industry
WIPS category
Stratification framework and sample distribution (cont…)
Section 5 – Annexure
• Government offices,
• Government hospitals,
• Educational institutes, and
• Religious places (havingconnected load > 5 kW),
• Village community centres,
• Charity hospitals,
• Municipal committees,
• Panchayats, and
HT (>100kW) Industry
• Iron and steel,
• Textile,
• Pharmaceuticals,
• Chemicals,
• Food processing,
• Paper,
• Glass ,
• Rubber,
• Connected load less than 100 kW,
• Between 100 - 500 kW and
• More than 500 kW
Street lighting and agriculture
• No sampling was done since thenature of the load was constant,and there were dedicated feedersserving these consumers.
25 September 2013
• Panchayats, and
• Other major consumers.• Rubber,
• Engineering,
• Plastic and Polymer,
• Stone crushers,
• Liquor, and
• IT parks
serving these consumers.
35Utility CEO Forum on DSM •
Consumer category Load research technique Output
Summary of load research activities in Himachal Pradesh
Section 5 – Annexure
Domestic, commercial, non-
domestic non-commercial,
water and irrigation power
supply and LT industrial
Questionnaire- based load and
market survey and
hourly recording of electricity meter
readings
Hourly load curve,
time of use of specific end -use
applications
HT Industry AMR data analysis,
Load and market surveys
Hourly load curve
time of use of specific end- use
applications
25 September 2013
Agriculture and street lighting Feeder-level energy data analysis Hourly load curve
35Utility CEO Forum on DSM •
Thank You
Section 5 – Annexure
25 September 201336
Utility CEO Forum on DSM •
© 2013 PricewaterhouseCoopers Private Limited. All rights reserved. In this document, “PwC” refers toPricewaterhouseCoopers Private Limited (a limited liability company in India), which is a member firm ofPricewaterhouseCoopers International Limited, each member firm of which is a separate legal entity.